Professional Documents
Culture Documents
A. Arko-Adjei
Department of Geomatic Engineering
KNUST, Kumasi, Ghana
arkoadjei@hotmail.com
March 2014
Mass haul diagrams
Borrowed material
• Is the volume of material brought into a section
owing to a deficiency of suitable material or
economic considerations or unsuitability of the
material.
Definitions and terminology
Waste
• The earth excavated to form cuttings may be
deposited in tips at regular intervals along the
project to form spoil heaps for later use in
embankments formation or may be wasted.
• A waste is the volume of material taken from
the section due to excess or unsuitability of the
material
Definitions and terminology
Shrinking and bulking
• Constructions materials often occupy different
volumes after excavation and compaction as
compared to when it was in its natural condition.
• The volume material occupies after compaction
depends on its shrinking or bulking factors
Definitions and terminology
Shrinking and bulking
• Different materials have different shrinking or bulking
factors
• Rocks undergo a bulking and has a bulking factor of
say 1.1
• Clay materials undergo shrinking and have shrinking
factor of say 0.8. (A 100 cubic metres of clay
material may occupy only 80 cubic metres after
compaction - a shrinkage factor of 80/100).
Definitions and terminology
Shrinking and bulking
• Two methods are used to calculate and estimate
volumes
• Amend the calculated volume, knowing the bulking
and shrinkage factors
• Amend the calculated volume of cut by multiplying
them by the factor used
Definitions and terminology
Haul distance
• Is the distance from the point of excavation of the
material to the tipping point.
Definitions and terminology
Average haul distance
• The distance from the centre of gravity of the
cutting or excavation to the centre of gravity of the
tip or filling.
• Note that since neither the excavation nor the tip
has a uniform shape it is better to use the centre of
gravity which will give a better approximation than
any point within the cut of fill.
Definitions and terminology
Free haul distance
• It is that distance, usually given and specified in the
contract over which a charge is levied on only for
volume of earth excavated and not its movement.
• If a tract moves within the free haul distance for an
excavated material during the construction, the cost
involved is not paid. However the cost of excavation
within the free haul distance is paid for.
Definitions and terminology
E M
N
D L
C
O
Vertical distance
B Formation level
K
A F
P
G J
I
H
A
chainage
f
e
d g
Aggregated volume
+ c
b
h
a k’
f’ q p
o chainage
i
n
j
- m
k
l
Mass-haul diagram
Construction of mass-haul diagram
Procedure
4. Plot the longitudinal section along the proposed
center line is plotted, the proposed formation level
being included.
5. The axes of the mass haul diagram are drawn
underneath the longitudinal profile such that
chainage zero of the profile coincides with
chainage zero on the diagram.
6. The points are joined by curves or straight lines to
obtain the finished mass haul diagram.
Construction of mass-haul diagram
E M
Vertical distance N
D L
C
O
B Formation level
K
A F
P
G J
I
H
A
chainage
f
Aggregated volume e
d g
+ c
b
h
a k’
f’ q p
chainage
o
i
n
j
- m
k
l
Characteristics of mass-haul diagram
Refer to the figure above
• Rising curve indicates cutting as the aggregate
volume is increasing. e.g. a to f.
• Maximum point on the curve agrees with the end
of the cut (f, F) and the minimum indicates the end
of fill.
• Falling curve indicates filling as the aggregate
volume is decreasing - f to k agrees with F to K on
the profile.
Characteristics of mass-haul diagram
Refer to the figure above
• Vertical difference between a maximum point and
the next forward minimum point represents the
volume of embankment in that section. i.e. (ff’ +
k’k) represents the volume of embankment on that
surface.
• The vertical difference between any two points
having no maximum or minimum represent the
volume between the chainage.
Characteristics of mass-haul diagram
• If any horizontal line is drawn cutting the mass haul
curve at any two or more points, such as a, q, p,
with the volume of cut and the volume of fill being
the same, it is known as balancing line.
• When the horizontal balancing line intercepts the
curve, the area above the curve indicates that earth
works must be moved forward to fill (a to q).
• If the curve lies below the horizontal line then the
earth work must be moved backwards to fill (p to
q).
Characteristics of mass-haul diagram
• The length of the balancing line between
intercepting points is the maximum haul distance
in that section. eg. aq and qp represents the
maximum haul distance aq=chainage q- chainage a
and
qp=chainage p - chainage q.
Characteristics of mass-haul diagram
• Q is the maximum haulage point for both forward
and back movement.
• The area contained between the curve and the
balancing line represents the haul in that section
(eg. afqf ’a)
Characteristics of mass-haul diagram
Note:
• Instead of calculating the centers so gravity of
excavations and tips, which can be a difficult task,
the average haul distance in each section can be
easily found by dividing the haul in that section by
the volume in that section
eg: average haul distance = area afgf ’a m3
ff ’ m3
Economics of mass-haul diagram
Cost of free haul
• Any earth moved over a distance not greater than
the free haul distance is cost only on the
excavation of its volume.
Economics of mass-haul diagram
Cost of overhaul
• Any earth moved over distances greater than the
free haul distance is charged both for its volume
and for the distance in excess of the free haul
distance over which it is moved. This charge can
be specified either for units of haul (i.e.
staionmetrer (m3 m) or for units of volume.
Economics of mass-haul diagram
Cost of waste
• Any surplus or unsuitable material which must be
removed from the site and deposited in a tip is
usually charged on units of its volume. This charge
may vary from one section of the site to another
depending on the nearness of tips.
Economics of mass-haul diagram
Cost of borrow
• Any extra material which must be brought on the
site to make up a deficiency is also usually charged
on units of volume. This charge may also vary from
one section of the site to another, depending on
the nearness of borrow pit or spoil heaps.
Economics of mass-haul diagram
Construction
• It helps in selecting the suitable plant and
machinery before construction starts.
Uses of mass-haul diagram
In planning ahead
• Mass haul diagrams can be used to indicate the
effect that other engineering works within the
overall project area will have on earth moving.