Planned Project: HCPI Facility renovation Project

Implemented Area/s: Area A & D


Not Implemented Date: Arpil 01 to 07

Item Activity Start Finish Duration 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr

1 Devanning Mon Tue Wed Thu Fri Sat Sun Mon

Breaking of concrete Apr-01 Apr-02 2 1 1 0 0 0 0 0 0


Clearing and hauling Apr-03 Apr-03 1 0 0 1 0 0 0 0 0
Subgrade preparation and compaction Apr-04 Apr-05 2 0 0 0 1 1 0 0 0
FDT Apr-06 Apr-06 1 0 0 0 0 0 1 0 0
Base coarse and compaction Apr-07 Apr-08 2 0 0 0 0 0 0 1 1
FDT Apr-09 Apr-09 1 0 0 0 0 0 0 0 0
RSB and Formworks Apr-10 Apr-11 2 0 0 0 0 0 0 0 0
Concreting Apr-12 Apr-12 1 0 0 0 0 0 0 0 0

Plastering Apr-01 Apr-03 3 1 1 1 0 0 0 0 0


Retaining wall rectification Apr-04 Apr-06 3 0 0 0 1 1 1 0 0
0 0 0 0 0 0 0 0
Open truss Apr-08 Apr-15 8 0 0 0 0 0 0 0 1
Full weld (Girder) Apr-16 Apr-17 2 0 0 0 0 0 0 0 0
Additional beam Apr-18 Apr-20 3 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Steel Fence Apr-02 Apr-03 2 0 1 1 0 0 0 0 0
Sliding gate Apr-04 Apr-07 4 0 0 0 1 1 1 1 0

Dock Leveler
Roll up Door

2 RTC Mon Tue Wed Thu Fri Sat Sun Mon

Breaking of slab Apr-01 Apr-01 1 1 0 0 0 0 0 0 0


Hauling Apr-02 Apr-02 1 0 1 0 0 0 0 0 0
Concreting Apr-03 Apr-03 1 0 0 1 0 0 0 0 0
0 0 0 0 0 0 0 0
Item Activity Start Finish Duration 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr

Steel Fence Apr-08 Apr-09 2 0 0 0 0 0 0 0 1


Sliding gate Apr-10 Apr-12 3 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Open Truss Apr-13 Apr-17 5 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Roll up Door

3 HLI Office Mon Tue Wed Thu Fri Sat Sun Mon

Installation of door Apr-02 Apr-02 1 0 1 0 0 0 0 0 0


Concreting Apr-03 Apr-03 1 0 0 1 0 0 0 0 0

4 Lubes Mon Tue Wed Thu Fri Sat Sun Mon

Formworks Apr-01 Apr-02 2 1 1 0 0 0 0 0 0


Concreting Apr-03 Apr-03 1 0 0 1 0 0 0 0 0
Cleaning and painting of trench Apr-04 Apr-06 3 0 0 0 1 1 1 0 0
0 0 0 0 0 0 0 0
Open Truss Apr-05 Apr-07 3 0 0 0 0 1 1 1 0
Louver Cover Apr-08 Apr-09 2 0 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0
Roller guide rectification 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
5 Advance Release Mon Tue Wed Thu Fri Sat Sun Mon

Open Truss Apr-08 Apr-10 3 0 0 0 0 0 0 0 1


Louver Cover Apr-11 Apr-12 2 0 0 0 0 0 0 0 0

Roller guide rectification 0 0 0 0 0 0 0 0


0 0 0 0 0 0 0 0
6 Shipping Area Mon Tue Wed Thu Fri Sat Sun Mon

Rail Elbow Apr-02 Apr-02 1 0 1 0 0 0 0 0 0


0 0 0 0 0 0 0 0
Open Truss Apr-11 Apr-13 3 0 0 0 0 0 0 0 0
Item Activity Start Finish Duration 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr

Louver Cover Apr-14 Apr-15 2 0 0 0 0 0 0 0 0

Roll up Door
0 0 0 0 0 0 0 0
7 Bolted Fence Line 7 Mon Tue Wed Thu Fri Sat Sun Mon

Fabrication and Erection Apr-01 Apr-15 15 1 1 1 1 1 1 1 1

8 Metal Siding Partition Mon Tue Wed Thu Fri Sat Sun Mon

Breaking of Slab and Hauling Apr-08 Apr-09 2 0 0 0 0 0 0 0 1


Fabrication and installation of railguide Apr-10 Apr-11 2 0 0 0 0 0 0 0 0
Fabrication of sliding gate with door Apr-12 Apr-14 3 0 0 0 0 0 0 0 0
Erection Apr-15 Apr-16 2 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Breaking and hauling of slab Apr-01 Apr-02 2 1 1 0 0 0 0 0 0
RSB installation (dowel) Apr-03 Apr-04 2 0 0 1 1 0 0 0 0
CHB laying Apr-05 Apr-07 3 0 0 0 0 1 1 1 0
Concreting Apr-08 Apr-09 2 0 0 0 0 0 0 0 1
0 0 0 0 0 0 0 0
Fabrication and Erection Apr-11 Apr-25 15 0 0 0 0 0 0 0 0

9 Toilet 1-A Mon Tue Wed Thu Fri Sat Sun Mon

Plumbing Apr-08 Apr-09 2 0 0 0 0 0 0 0 1


Backfill and compaction Apr-10 Apr-10 1 0 0 0 0 0 0 0 0
Slab Apr-11 Apr-12 2 0 0 0 0 0 0 0 0
Floor and wall tiles Apr-13 Apr-17 5 0 0 0 0 0 0 0 0
Ceiling Apr-20 Apr-24 5 0 0 0 0 0 0 0 0
Doors and cubicles Apr-25 Apr-26 2 0 0 0 0 0 0 0 0

10 Toilet 2 and 3 Mon Tue Wed Thu Fri Sat Sun Mon

CHB Apr-01 Apr-02 2 1 1 0 0 0 0 0 0


Plumbing Apr-03 Apr-04 2 0 0 1 1 0 0 0 0
Item Activity Start Finish Duration 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr

Backfill and compaction Apr-05 Apr-06 2 0 0 0 0 1 1 0 0


Slab Apr-07 Apr-08 2 0 0 0 0 0 0 1 1
CHB Apr-09 Apr-12 4 0 0 0 0 0 0 0 0
Column Apr-13 Apr-15 3 0 0 0 0 0 0 0 0
Plastering Apr-16 Apr-18 3 0 0 0 0 0 0 0 0
Floor and wall tiles Apr-19 Apr-23 5 0 0 0 0 0 0 0 0
Ceiling Apr-26 Apr-30 5 0 0 0 0 0 0 0 0
Doors and cubicles May-01 May-02 2 0 0 0 0 0 0 0 0

11 Roofing Mon Tue Wed Thu Fri Sat Sun Mon

Gutter Replacement (Devanning) 0 0 0 0 0 0 0 0


Lower Molding (Devanning) 0 0 0 0 0 0 0 0

Gutter Replacement (RTC) 0 0 0 0 0 0 0 0


Lower Molding (RTC) 0 0 0 0 0 0 0 0

Lower Molding (Lubes to Shipping) 0 0 0 0 0 0 0 0

Gutter Replacement (Mid Roof) 0 0 0 0 0 0 0 0


Lower Molding (Mid Roof) 0 0 0 0 0 0 0 0

Removal of cut exhaust 0 0 0 0 0 0 0 0


Repair of cut exhaust 0 0 0 0 0 0 0 0

Repair of ductings 0 0 0 0 0 0 0 0

Prepared by: Noted by: Approved by: