You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/245533897

Sustainable bridge construction through innovative advances

Article in Bridge Engineering · January 2008


DOI: 10.1680/bren.2008.161.4.183

CITATIONS READS

18 5,233

5 authors, including:

P.A. Muhammed Basheer Jeannette Kirkpatrick


University of Leeds University of Leicester
238 PUBLICATIONS 5,766 CITATIONS 11 PUBLICATIONS 153 CITATIONS

SEE PROFILE SEE PROFILE

Barry Rankin Adrian E. Long


Queen's University Belfast Queen's University Belfast
36 PUBLICATIONS 536 CITATIONS 103 PUBLICATIONS 2,727 CITATIONS

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Barry Rankin on 28 March 2017.

The user has requested enhancement of the downloaded file.


Proceedings of the Institution of
Civil Engineers
Bridge Engineering 161 Adrian E. Long P. A. Muhammed Basheer Susan E. Taylor
Month 2008 Issue BE4 Professor Emeritus, Professor, Senior lecturer,
Pages 183–188 Queen’s University, Queen’s University, Queen’s University,
doi: 10.1680/bren.2008.161.4.183 Belfast, UK Belfast, UK Belfast, UK
Paper 800006
Received 21/01/2008
Accepted 08/08/2008
Keywords: Barry G. I. Rankin Jim Kirkpatrick
bridges/concrete technology & Head of Technical Advisory, Research Associate, Queen’s
manufacture/sustainability Queen’s University, Belfast, UK University, Belfast, UK

Sustainable bridge construction through innovative advances


A. E. Long, P. A. M. Basheer, S. E. Taylor, B. G. I. Rankin and J. Kirkpatrick

Sustainability is now recognised as a key issue that must be has high embodied energy and low operational requirements
addressed in the design, construction and lifelong whereas a hospital, with its demanding service conditions, has a
maintenance of civil engineering structures. This paper high proportion of operational energy. However, for bridges the
briefly discusses the generic aspects of sustainability, but relative proportion of these energies depends on the extent of
the main focus is its application to bridges. Motorway maintenance/repair during their lifetime. If minimal
bridges built in the 1960s and 1970s had design lives of maintenance/repairs are required, the operational energy may be
120 years; many, however, were showing signs of only marginal. However, if extensive repairs are necessary and
deterioration after only 20–40 years. This led to much considerable disruption/congestion results, the energy consumed
(ongoing) debate on the issue of initial versus full life-cycle can increase dramatically. The challenge for designers is thus
costing. In order to address the highly complex issue of to achieve minimum total energy used over a 120-year design
the sustainability of bridges, this paper considers the life and to persuade clients that a sustainable approach is
following specific areas that impinge on this important preferable to a minimum initial cost design.
subject: the impact on sustainability of different forms of
bridge construction and maintenance/repair/replacement In order to contribute to better understanding of the highly
strategies; the utilisation of innovative in situ testing complex issue of the sustainability of bridges, the following
equipment for assessing the long-term durability of specific factors will be discussed
concrete; the development of innovative structural
designs for bridges that inherently have greatly extended (a) the relative merits of different forms of construction from
lives at minimal, if any, additional cost. the sustainability viewpoint
(b) the utilisation of innovative in situ testing equipment that
allows the durability of concrete bridges to be assessed
1. INTRODUCTION (c) technological innovations that could lead to much more
durable and sustainable forms of construction for concrete
The built environment has to coexist with the natural
bridges based on
environment with which it is inseparably linked. Energy,
(i) the enhanced strength of deck slabs arising from
materials, water and land are all consumed in the construction
arching action
and operation of buildings and infrastructure to such an extent
(ii) a novel flexible concrete arch system.
that sustainable development can be said to depend on the built
environment. The world’s cities have a major impact on
In terms of technological advances, the approach adopted
greenhouse gas emissions and global warming: they take up
in research at Queen’s University Belfast, carried out in
around 2% of the Earth’s surface but account for nearly 80% of
collaboration with industry, will be placed in context.
the carbon emissions from human activities. The urban
environment influences our living conditions, social wellbeing
2. SUSTAINABILITY ISSUES AFFECTING BRIDGES
and health. Thus the performance characteristics and quality of
our infrastructure are of fundamental importance to urban 2.1. The environmental impact of new bridges
sustainability and the wellbeing of our environment. The The embodied energy from the use of construction materials is a
significance of this should not be underestimated, especially source of concern to engineers when planning, designing and
bearing in mind that our infrastructure accounts for at least 50% constructing a bridge. However, relatively little advice or
of our national wealth. guidance is given in the literature as to the relative merits of
different forms of construction. A recent paper by Collings1
The burden placed on natural resources by construction activities presents the results of a comparative study derived from an
can be estimated from embodied energy—that is, the total actual project. A bridge in the UK over a river 120 m wide with
primary energy that has to be extracted from the Earth to produce 66 m of approach spans on each side was considered. The total
a specific product—usually measured per square metre of plan deck area was over 4000 m2 and the bridge allowed
area. In addition, the operational energy used during a structure’s consideration of shorter spans on the approaches as well as the
lifetime has to be taken into account. The relative proportion of main river span. Three basic forms of construction were
the two depends on the form of construction. In general, a bridge considered for the river span—a profiled girder, a tied arch and

Bridge Engineering 161 Issue BE4 Sustainable bridge construction through innovative advances Long et al. 183
Delivered by ICEVirtualLibrary.com to:
IP: 143.117.49.17
On: Thu, 23 Jun 2011 11:29:32
experienced designers need to be encouraged so that the most
Embodied energy during
construction: GJ/m2 appropriate forms of construction, from the sustainability
viewpoint, are selected.
Energy Type Steel Concrete Composite
2.2. Repair, maintenance and congestion
Minimum Viaduct 17$8 15$7–16$6 16$6
Girder 30$9 23$6 29$1 All bridges will require some form of intervention during their
Arch 49$8 34$3 48$8 lifetime; ideally, this, as well as all other aspects, should be
Cable- 40$3 21$1–22$1 37$7 taken into account in the design process. Even the most basic
stayed maintenance will cause congestion but the impact of
Average Viaduct 23$5 21$1–22$1 22$1
replacement can be much greater, as exemplified by
Girder 39$3 30$6 37$0
Arch 61$9 49$1 60$8 the Tinsley viaduct.2
Cable- 50$6 43$9 47$7
stayed The Tinsley viaduct is a twin-deck steel–concrete composite
Maximum Viaduct 30$8 28$1–28$6 29$2 girder bridge that carries the M1 motorway and the A631
Girder 49$3 39$1 46$6
trunk road across the Don Valley near Sheffield, UK. The
Arch 75$6 60$9 74$4
Cable- 62$6 54$8 59$3 1 km long structure has 20 spans and crosses two railway
stayed lines, the River Don and a canal. As a strategic part of the
motorway network, the viaduct carries approximately 115 000
Table 1. Embodied energy during construction (GJ/m2) for vehicles per day. However, in the late 1990s it failed to
various structural forms and materials1
satisfy requirements for the introduction of 40 t lorries and
decisions had to be taken on whether to strengthen or replace
a cable-stayed bridge. Constant-depth girders were used for all
the structure.
the approach spans. Temporary works were included, as was
an estimate of the likely repair and maintenance during the
A replacement bridge was estimated to cost £200 million;
lifetime of the three basic forms of construction (steel, concrete
however, the associated cost of congestion over the two to
and composite).
three year period of construction was considered to be around
£1400 million. This enormous additional cost, not to mention
Useful comparative tables and graphs are given in Collings’
the associated environmental impact of congestion, was clearly
paper;1 only results summarising the impact of the span and the
unacceptable. The decision was made to carry out an
form of construction on the embodied energy are included here. innovative high-technology strengthening process2 while
Table 1 shows estimates of embodied energy during construction keeping the viaduct open to traffic except for a short period
(per square metre of bridge deck). Values vary from each night. Tinsley viaduct was repaired at a cost of £80
approximately 16 to 75 GJ/m2 of deck, with the short-span million with minimal congestion—a net saving of some
concrete structural form giving the lowest values and the all-steel £1500 million.
or composite, longer-span structure the highest. The embodied
energy is also presented graphically in Figure 1, which clearly From the viewpoint of the impact of congestion, this extreme
shows that longer spans consume greater embodied energy/m2 example demonstrates the benefits of bridges that can be repaired
(not unexpected as cost/m2 also follows this trend). Figure 1 also while effectively remaining in service. In this regard, steel is more
implies that a well-engineered longer-span bridge using local amenable to strengthening; however, the availability of carbon
materials, recycled steel and sustainable cement can be almost fibre composites allows comparable action to be taken for
as environmentally friendly as a shorter-span structure where concrete bridges. It should also be noted that the
sustainability issues are not considered. Table 1 and Figure 1 cost/environmental impact of congestion is an ever-increasing
also indicate that for the spans under consideration, the more problem as many urban bridges built in the 1960s and 1970s are
architectural solutions (arches, cable stayed) have a higher now in need of remedial action. This should be considered, even
environmental burden for all materials (as well as a cost if only approximately, in the total life-cycle design of future
premium). Further comparative studies of this nature by bridges. Although possibly increasing the design cost, long-term
savings could be enormous.
80
Steel The relative importance of congestion also requires designers to
70
Composite think carefully about the selection of durable materials and the
60
Concrete most appropriate form of construction. As a consequence, in the
Energy: GJ/t

50
future it will be even more important to build bridges that require
40 minimal maintenance and to ensure that premature replacement
30 is avoided.
20
10 2.3. Total life-cycle ‘cost’ of bridges
0
0 20 40 60 80 100 120 140 While initial ‘costs’ are useful, a more significant factor is
Span: m ‘cost’/‘energy use’ over the bridge lifetime. In this context, the
importance of adopting integral bridges3 for relatively short
Figure 1. Variations in embodied energy with span and material spans is highlighted. Basically, by designing a bridge without
type (from Collings1)
movement joints and one that is integral from one abutment to

184 Bridge Engineering 161 Issue BE4 Sustainable bridge construction through innovative advances Long et al.
Delivered by ICEVirtualLibrary.com to:
IP: 143.117.49.17
On: Thu, 23 Jun 2011 11:29:32
the various deterioration
Concrete manufacture mechanisms involved. In
essence, permeability
influences the primary method
Permeability/transport properties
of transport of moisture and
aggressive ions into concrete
Alkali Water Sulphate Chloride Oxygen
Carbonation diffusion
Water Salt solution and subsequent increases in
ingress saturation absorption ingress saturation ingress
transport properties are
Modification of pores
responsible for the increased
Alkali ASR gel Sulphate Corrosion of Frost Salt rate of damage. Thereafter,
attack expansion attack reinforcement attack attack
crack growth (which depends
on the fracture strength)
Strength properties accelerates the penetration of
aggressive substances into
concrete and the spiral of
Cracking
deterioration continues
downwards. The
Figure 2. Causes of concrete deterioration—physical properties interaction model4
interdependence of all these
factors and the importance
the other, maximum resistance to chloride penetration is of transport properties and strength are clearly illustrated
4
obtained. As a further step, timely and appropriate application of in Figure 2.
protective coatings while the bridge is in service can delay the
need for repairs. Using these methods and some of the innovative 3.2. Measurement of durability-related properties
approaches detailed later in this paper, the life of specific types of Recognising the importance of these parameters, researchers at
bridges can be greatly enhanced and total life-cycle cost/energy Queen’s University Belfast responded by developing
use reduced. the following in situ test methods and associated novel
test equipment
3. DEVELOPMENT OF NOVEL IN SITU TEST
METHODS (a) the ‘pull-off’ test6 for estimating the tensile strength of
concrete using the ‘limpet’
3.1. Background (b) permeability testing7 utilising the ‘autoclam’
The single most important factor that leads to premature bridge (c) assessing the diffusion characteristics of concrete using the
deterioration is ingress of moisture into concrete.4,5 The ‘permit ion migration test’.8
permeability of concrete to the macro-environment during its
service life can thus be used as a measure of durability. In the All three in situ tests have been used on site to assess corrosion-
development of a holistic model for concrete deterioration, induced damage to the Dickson Bridge in Montreal.9 The tests
Mehta5 considered the influence of environmental factors on indicated that tensile strength did not correlate well with level of
deterioration, but permeability
and diffusivity provided much
Autoclam air
Autoclam air permeability useful information.
permeability index (×10–2):
index (×10–2): Ln (mbar)/min
Ln (mbar)/min 3.3. Conclusions on in situ
35
35 test methods
30 In the assessment of durability,
30
25
the following potential uses for
25 strength, permeability and
Ln (mbar)/min

20 diffusion testing have been


20
identified.
15
15 (a) Estimating the life of new
10
structures. The equipment
10
5 was used to develop a
5 ‘mix design for
0 durability’10 and
0
important trends have
been identified (Figure 3)
3
0·7 4 that could be extremely
5
0·6 ent relevant to new
Wa 6 em
e/c
ter/ce 0·5 7 re gat construction.
me
nt 0·4 8 Agg
(b) Assessing the remaining
life of existing structures.
Figure 3. Influence of mix proportion on Autoclam air permeability index10
The good correlation

Bridge Engineering 161 Issue BE4 Sustainable bridge construction through innovative advances Long et al. 185
Delivered by ICEVirtualLibrary.com to:
IP: 143.117.49.17
On: Thu, 23 Jun 2011 11:29:32
Reinforcement
yielding
Arching
enhancement

Applied load
Bending Higher restraint
Medium restraint
First cracking Zero restraint

Mid-span deflection

Figure 5. Interaction between flexural and arching action


Figure 4. Permit, limpet and autoclam (from left to right)

(a) reduction in reinforcement (from 1$7% to 0$5% or less)


between permeability indices and durability characteristics
(b) same slab depth for greater spacing of beams
can allow remedial action to be taken before irreparable
(c) lower overall cost of bridge superstructure (one larger beam
damage has occurred.
at 2 m centres is less expensive than two smaller beams at
1 m centres). Generally, the modest increase in beam depth
However, if significant progress is to be made it will be essential
for practising engineers to work closely with those involved in will not be a problem unless the minimum possible
relevant research. In this context the limpet, autoclam and permit structural depth has to be achieved.
ion migration test (Figure 4) could provide invaluable tools for
generating useful data. One is already a standard test within Thus, substantial reductions in costs can be achieved while at
Europe and efforts are being made to have the other two accepted the same time retaining comparable strength and durability
in Europe and other international markets (for further (see unbroken lines in Figure 6). Research12,13 has also shown
information, see www.amphorandt.com). that significant enhancement in durability/sustainability can be
achieved by utilising

4. TECHNOLOGICAL INNOVATIONS FOR


(a) concrete containing fibres to control cracking or by taking
ENHANCED SUSTAINABILITY
advantage of the fact that for a given degree of restraint, the
4.1. Background strength of slabs developing arching action significantly
Bridges with spans of up to 30 m constitute the vast majority of increases with concrete strength
road infrastructure bridges in service across the world. Within (b) conventional steel reinforcement located in a single layer at
this category of bridges, concrete deck slabs are widely used in the centre of the slab (greatly increased cover) to reduce
combination with precast prestressed concrete beams or steel corrosion and the likelihood of spalling; field testing13,14 has
girders. In addition, arch bridges have been widely used in the demonstrated that due to arching action, cracking under
past for shorter spans. However, even though their durability and service loads is well within limits and crack control has not
aesthetics are unquestioned, the labour-intensive method of been found to be a problem
construction has made them unpopular for many decades. (c) glass/carbon-fibre-reinforced plastic reinforcing bars.
Technological advances to overcome some of these problems will
now be briefly described. Hence, by using high-strength concrete (with or without fibres) in
conjunction with corrosion-free reinforcement, bridge decks that
4.2. Design of bridge deck slabs based on arching action
Tests carried out by Ockleston11 on the interior panels of the Old
Dental Hospital in Johannesburg revealed collapse loads of three
to four times those predicted by the yield line method. This Standard deck Repair
(normal durability) cost
enhanced capacity was attributed to the development of an
internal arching mechanism arising from the lateral restraint Repair cost
Unit cost

provided by the surrounding panels. Figure 5 shows a typical


load—deflection curve with the contributions of arching and
Arching action deck
flexural action separately identified. Arching action deck (enhanced durability)
(normal durability)

Extensive laboratory and field testing programmes have been


carried out in Canada12 and Northern Ireland13 to allow strength
and serviceability benefits to be quantified. Guidance that allows Years in service
the advantages of arching action to be taken into account in the
design process is now available14,15 and the following benefits Figure 6. Comparison of total unit cost of standard deck and
arching action decks over full service life
can be achieved

186 Bridge Engineering 161 Issue BE4 Sustainable bridge construction through innovative advances Long et al.
Delivered by ICEVirtualLibrary.com to:
IP: 143.117.49.17
On: Thu, 23 Jun 2011 11:29:32
In situ screed/concrete Polymeric
reinforcement

Individual voussoirs (precast)

Figure 7. Construction of arch unit using precast individual


voussoir concrete blocks

should be virtually maintenance-free could be produced (see


dashed line in Figure 6).
(a)

5. DEVELOPMENT OF A NOVEL Arch SYSTEM


Brick or stone masonry arch bridges have been utilised for
thousands of years and have proven durability. However, it is no
longer economically viable to construct a masonry arch in the
traditional way due to the costs of accurate centring and
preparation of masonry blocks. In order to provide a viable
alternative, researchers at Queen’s University Belfast, in
collaboration with Macrete Ireland Ltd, developed the flexiarch
system made of unreinforced precast concrete voussoirs. The arch
system is constructed and transported to site as a ‘flat-pack’ and
polymer grid reinforcement is used to carry the self-weight
during lifting as it takes up the form of an arch. The voussoirs are
precast individually, laid contiguously in a horizontal line with a
(b)
layer of polymer grid reinforcement placed on top. Subsequently,
an in situ concrete screed is placed on top and allowed to harden
to interconnect the voussoirs. The preferred method of
construction of the arch unit is shown in Figure 7. It should be
noted that the alternative method of casting the whole system
in situ has been investigated and rejected because

(a) the manufacture of precision wedges is difficult and fixing


them during casting is problematic
(b) removal of the arch from the formwork is difficult and could
result in damage to the system.

The arch unit can be cast in convenient widths to suit design


requirements, site restrictions and available lifting capacity.
When lifted, the wedge-shaped gaps close, concrete hinges form (c)
in the concrete screed and the unit is supported by tension in the
polymer grid. The arch-shaped units are then placed on precast
footings and all self-weight is then transferred from tension in
the polymer to compression in the ‘voussoir’ elements of the
arch (Figure 8).

The novel arch system has been demonstrated16,17 to be a viable


alternative to long-established methods of construction for spans
up to 10–12 m. Furthermore

(a) as the arch system is cast horizontally, it can conveniently


be transported to site in ‘flat-pack’ form
(b) centring is not required during installation so the process is
greatly simplified and speed of construction enhanced
(d)
(c) long-term durability is assured as there is no corrodible
reinforcement Figure 8. ‘Flat pack’ arch ready for lifting (a) arch unit during
(d) the system is cost-competitive with less aesthetic reinforced lifting (b) arch located on tapered seating units (c) full
arch (d)
coucrete box culverts.

Bridge Engineering 161 Issue BE4 Sustainable bridge construction through innovative advances Long et al. 187
Delivered by ICEVirtualLibrary.com to:
IP: 143.117.49.17
On: Thu, 23 Jun 2011 11:29:32
Tests have shown that when the FlexiArch is used in conjunction 4. BASHEER P. A. M., CHIDIAC S. and LONG A. E. Predictive models
with lean-mix concrete, it is exceptionally strong and for deterioration of concrete structures. Construction and
serviceability requirements are easily met.18 A number of arch Building Materials, 1996, 10, No. 1, 27–36.
units have been supplied and installed by Macrete; clients 5. MEHTA P. K. Concrete technology at the crossroads—problems
have been impressed with the speed of construction and the and opportunities; concrete technology—past, present and
limited site preparation when compared with that required future. Proceedings of Malhotra Symposium, 1994, ACI SP
for box culverts. 144, pp. 1–30.
6. MURRAY A. M. and LONG A. E. A study of the in situ variability
6. CONCLUDING REMARKS of concrete using the pull-off method. Proceedings of the
The sustainability of infrastructure is now accepted as a key issue Institution of Civil Engineers, 1987, 83, No. 2, 731–746.
in many parts of the world. It is essential that the construction 7. BASHEER P. A. M. A brief review of methods for measuring the
industry recognises the important role it has to play and responds permeation properties of concrete in situ. Proceedings of the
positively to the associated challenges. Within our national Institution of Civil Engineers, Structures and Buildings, 1993,
transportation networks, crucial for continued economic growth, 99, No. 1, 74–83.
bridges form a critical part. Deficiencies in the 8. BASHEER P. A. M., ANDREWS R. J., ROBINSON D. J. and LONG A. E.
durability/strength of bridges that necessitate repair/replacement ‘PERMIT’ ion migration test for measuring the chloride ion
can lead to considerable disruption/congestion within the transport of concrete on site. NDT&E International, 2005, 38,
network and have a very negative impact on sustainability. Thus, No. 3, 219–229.
bridge engineers will have to integrate aspects of sustainability— 9. FAZIO R., MIRZA M. S., MCCAFFERTY E., ANDREWS R. J., BASHEER
such as the relative merits of different forms of construction, P. A. M. and LONG A. E. In situ assessment of corrosion-
maintainability and associated congestion—into the total life- induced damage of the Dickson Bridge deck. Proceedings
cycle cost design process. of 8dbmc, Vancouver, 1999, 1, 269–279.
10. HENDERSON G. D. Development of Design Procedures for
Innovative research carried out over the past 30 years at Queen’s
Durable, Strong and Workable Concrete Mixes. PhD thesis,
University Belfast has been aimed at increasing the durability of
Queen’s University, Belfast, 1998.
concrete structures and bridges in particular and has led to the
11. OCKLESTON A. J. Load tests on a three storey reinforced
following conclusions.
concrete building in Johannesburg. The Structural Engineer,
1955, 33, No. 10, 304–322.
(a) The availability of improved in situ test methods paves the
12. MUFTI A. A., JAEGER L. G., BAHKT B. and WEGNER L. D.
way for greatly enhanced durability by design for new and
Experimental investigation of fibre reinforced concrete deck
existing concrete structures.
slabs without internal steel reinforcement. Canadian
(b) Advances in structural design based on research on arching
Journal of Civil Engineering, 1993, 20, No. 3, 398–406.
action in bridge deck slabs can lead to virtually
maintenance-free systems. 13. KIRKPATRICK J., RANKIN G. I. B. and LONG A. E. The influence of
(c) The flexible concrete arch system, which can be transported compressive membrane action on the serviceability of beam
to site in ‘flat-pack’ form and avoids the need for centring, and slab bridge decks. The Structural Engineer, 1986, 64B,
has great potential. No. 1, 6–12.
14. TAYLOR S. E., RANKIN G. I. B. and CLELAND D. J. Serviceability of
ACKNOWLEDGEMENTS bridge deck slabs with arching action. ACI Structural
Journal, 2007, 104, No. 1, 39–48.
The input of research students and colleagues at Queen’s
15. HIGHWAYS AGENCY. BD81/02, Use of compressive membrane
University Belfast and support from EPSRC, DRD (Road Service)
action in bridge decks. In Design Manual for Roads and
NI, ICE, Research and Innovation Fund, Invest NI and KTP are
gratefully acknowledged. Bridges. HA, London, 2002, vol. 3, section 4, part 20.
16. GUPTA A., TAYLOR S. E., KIRKPATRICK J., LONG A. E. and HOGG I. A
REFERENCES flexible concrete arch system for durable bridges.
Proceedings IABSE Conference, Budapest, 2006,
1. COLLINGS D. An environmental comparison of bridge forms.
pp. 372–373.
Proceedings of the Institution of Civil Engineers, Bridge
17. TAYLOR S. E., GUPTA A., KIRKPATRICK J., LONG A. E., RANKIN G. B.
Engineering, 2006, 159, No. 4, 163–168.
and HOGG I. Development of a novel flexible concrete arch
2. MILNER A. L. Tinsley viaduct strengthening, UK. Proceedings
system. Proceedings of an International Conference on
of the 4th International Conference on Current and Future
Structural Faults and Repairs, Edinburgh, 2006.
Trends in Bridge Design, Construction and Maintenance,
Kuala Lumpur, 2005, 1, 225–236. 18. TAYLOR S. E., ROBINSON D., LONG A. E., GUPTA A. and KIRKPATRICK J.
3. HIGHWAYS AGENCY. Design of Integral Bridges. HA, London, Testing a novel flexible concrete arch system. Proceedings
1996, BA 42/96. New York Bridge Conference, New York, 2007.

What do you think?


To comment on this paper, please email up to 500 words to the editor at journals@ice.org.uk
Proceedings journals rely entirely on contributions sent in by civil engineers and related professionals, academics and students. Papers
should be 2000–5000 words long, with adequate illustrations and references. Please visit www.thomastelford.com/journals for author
guidelines and further details.

188 Bridge Engineering 161 Issue BE4 Sustainable bridge construction through innovative advances Long et al.
Delivered by ICEVirtualLibrary.com to:
IP: 143.117.49.17
On: Thu, 23 Jun 2011 11:29:32
View publication stats

You might also like