CLIENT : M/s.

ONGC
Contractor : M/s. LTHE
PROJECT : Balance work for Pipeline Replacement Project - 4

CA : M/S. ABSIV PRODUCTION DATE: 07.03.2018


TPI : M/S. DNV-GL REPORTING DATE : 10.03.2018
Location : Mumbai Port
Barge: Ocean303
Sr. no Description SCOPE Today's Progress Cumulative Remarks
Items/ Qty / Unit Fit - up Welding NDT Progress
No.

Distribution and Contact List

ABSIV sekumaran@eagle.org, pramanathan@absconsulting.com, dbhujbal@absconsulting.com


ONGC pandey_ak5@ongc.co.in, khanra_Rajat@ongc.co.in, Thakur_Ashish@ongc.co.in
DNV-GL birju.jaiswal@dnvgl.com, mani.choudhary@dnvgl.com, merlyn.menezes@dnvgl.com

Activities performed

1 LTHE, ABSIV & DNV Persons boarded on Barge Ocean 303 at Anchorage Point, Mumbai Port

Planned activities(Next Day) :-

1 Barge Ocean 303 is planning to transit from Mumbai Port to Neelam field

Bhabesh Porel Vipin James EL.Krishnan

DNV -Mech. ( ONGC-TPI) DNV-E&I (ONGC-TPI) ABSIV-Mech. (ONGC-CA) ABSIV-E & I (ONGC-CA) (ONGC REP.)