This procedure covers the installation of UPVC Pipe work and ancillaries for soil,
waste, vent and storm water.
This will ensure proper workmanship and acceptable as per specification and contract
document.
2.0 REFERENCES
2.1 Particular Specification Section-1.
2.2 General Specification Section-P.
2.3 Approved Thermo Shop Drawings for Drainage System Layout.
2.4 Thermo Project Quality Plan.
2.5 Thermo Safety Manual and Arabtec’s Safety Manual.
2.6 BS 4514 & BS 5255.
Work will be carried out only when main contractor clearance given for access to
work. This will also ensure the requirement of scaffolding, ladders, etc.
Health and Safety procedure by Main Contractor and Thermo will be implemented
for this job. A routine safety check will be done by the Safety Officer in charge as
per Thermo Safety Procedure.
a. Safety Lighting.
Safety Lights will be used in case there is a failure of normal lights and will
ensure that adequately provided.
b. Task Lighting
Adequate lighting will be provided in the work areas in order to execute the task
by all the workmen in the area.
c. Emergency Arrangements.
General : Site general safety procedures will be followed and in case of
any emergency, safety officer will be administered the emergency
arrangements as per the system, stop the work and reporting to Assembly
Point, etc.
Safety Officer Name: Mr. Ahsan Echty. Contact No. 050-6512317.
Fire Precautions : General fire precautions will be maintained in the
site as per the approved safety procedure.
Cont : THERMO
METHOD STATEMENT Doc.No : MS-PL-001
Rev : 0
INSTALLATION OF UPVC PIPES & Page : Page 5 of 14
JBR – 3
FITTINGS (DRAINAGE) Date : 13/07/04
5.0 DEFINITIONS
6.4 QA/QC Department will be looking after all the quality requirements for
the Project in co-ordination with the Project Engineer as per approved
Project Quality documents.
6.5 Safety Officer will be responsible for Health and Safety aspects in the site
in line with Main Contractor/ Client and Thermo Standard Safety
requirements.
7.1.1 Prior to start of activity area and access will be inspected to ensure
the area is suitable for installation of UPVC Pipes & Fittings for
the Drainage System.
7.1.2 Prior to start of activity pre-inspection will be carried out for all
materials and ensure that they are complied with relevant
specification and are in sound condition.
7.1.3 Make sure that all openings are in correct location and adequate
size.
8.0 TRAINING
8.1 Thermo employed all well experienced peoples for the execution of the
projects. In case any training requirements identified will be carried out in
accordance with Thermo Quality System / Safety procedure requirements.
All new employees are covered as Thermo standard Training system.
8.2 Tool box meeting will be carried out in every area where activities will start
and also every time when new labours start the activities.
All work place where Thermo people are working shall be kept clean and tidy. A
regular cleaning system shall be maintained in order to keep Healthy and good
working environment. This will ensure to maintain access and egress in the event of
an emergency situation.
Job supervision shall be carried out in accordance with organization chart attached
in the Project Quality Plan.
Materials shall be used as per the approved drawing and technical submittals.
Single phase / 3 phase normal power supply for using the light tools for
installation purpose.
Cont : THERMO
METHOD STATEMENT Doc.No : MS-PL-001
Rev : 0
INSTALLATION OF UPVC PIPES & Page : Page 9 of 14
JBR – 3
FITTINGS (DRAINAGE) Date : 13/07/04
e. Working Platforms
NOTE: Copies of the ITP and Inspection Check List attached in Section 19.0.
16.0 DISTRIBUTION
16.1 Main Contractor.
16.2 Site Engineer / Supervisor.
16.3 Or as required.
18.1 Site Safety Engineer / Officer carried out the Safety Inspection as per the
approved HSE procedure
18.2 All electrical tools will be certified by Safety Officer.
18.3 All ladders and scaffoldings will be certified by Safety Officer.
Cont : THERMO
METHOD STATEMENT Doc.No : MS-PL-001
Rev : 0
INSTALLATION OF UPVC PIPES & Page : Page 10 of 14
JBR – 3
FITTINGS (DRAINAGE) Date : 13/07/04
19.0 ATTACHMENTS
19.1 Inspection & Test Plan for Installation of above ground Drainage Piping
System – C4400-ITP-P-02.
19.2 Installation Check list for above ground Drainage Piping System –
C4400-QC-P-02.
19.3 Safety Inspection Checklists – Mobile Tower Scaffolding, Fire Prevention
and Ladder.
19.4 Risk Assessment.
(NOTE: The above attachments for ITPs & Checklists are to be used final
approved one for the actual inspection.
Safety inspections shall be carried out as per the scope of job applicable in the
contract.)
Cont : THERMO
METHOD STATEMENT Doc.No : MS-PL-001
Rev : 0
INSTALLATION OF UPVC PIPES & Page : Page 11 of 14
JBR – 3
FITTINGS (DRAINAGE) Date : 13/07/04
ATTACHMENT 19.1
ATTACHMENT 19.2
ATTACHMENT 19.3
ATTACHMENT 19.4
Risk Assessment