Professional Documents
Culture Documents
net/publication/319483454
CITATIONS READS
13 256
3 authors:
Georgios C Christoforidis
University of Western Macedonia
164 PUBLICATIONS 1,683 CITATIONS
SEE PROFILE
All content following this page was uploaded by Georgios C Christoforidis on 05 September 2017.
Abstract― Photovoltaic (PV) penetration in Low-Voltage NZEB is meant to be a building of very low energy demand, a
(LV) networks is expected to increase in the following years, requirement that should be achieved mostly by energy
posing a series of problems in the operation pf low-voltage
networks. Among the most important challenges imposed, is the produced from on-site renewables. For South Europe at least,
reverse power flow caused by high injected energy from this refers mostly to PVs. Under the requirements of this
distributed PVs during peak irradiation hours. This is the reason directive, all new buildings should be NZEB from 2019, thus a
of voltage rises above the permissible limits. Amongst other considerable number of PVs is expected to be installed in LV
solutions, such as active power curtailment and reactive power distribution networks.
absorption, the installation of distributed Energy Storage Systems
(ESS) seems to be an attractive solution since it can absorb Distributed generation poses unprecedented technical
surplus power locally, avoiding curtailment methods, power flow challenges for the smooth and reliable LV network operation
losses on the feeder and grid reinforcements. As the cost of storage grids, such as: voltage regulation issues, overloading of
is decreasing, ESS are expected to be increasingly adopted by network equipment and dynamic stability problems [4]. ESSs
prosumers. This work evaluates the influence of such systems on can tackle the problems occurring during high generation of
the voltage profile of LV feeders and on the self-consumed energy
of prosumers. Intensive simulations on a benchmark feeder assess PVs, by absorbing locally the energy that is not consumed at
the conflicted benefits of power system operators and ESS that time, thus alleviating high reverse power. In that way,
owners. voltage rises created by the reverse power flow can be
Index Terms-- Energy storage, Low-Voltage distribution prevented and the Distribution System Operator (DSO) may
grids, overvoltage, photovoltaic, self-consumption rate, self- postpone necessary grid reinforcements. At the same time, the
sufficiency rate. self-consumed energy of the prosumer owning a PV-storage
I. INTRODUCTION system can be increased.
A thorough investigation of the impact of decentralized ESS
Energy policies of European Union are promoting the installations on the grid operation and prosumers’ self-
increase of Renewable Energy Sources (RES) share in the consumption is needed. In [5] the possibilities of ESS to
production of electrical energy. The Paris Agreement that is mitigate the challenges of high PV integration on LV grids are
effective globally after 4 November 2016 is becoming a evaluated under storage control strategies that satisfy the
decisive element for the utilization of electricity from RES [1]. German DSO guidelines. Different charging and discharging
PV technology is one of the key choices for moving towards rates were tested in [6] for the operation of certain capacity
this direction. However, the existing electrical power systems ESSs installed on a practical distribution feeder, showing that
are not always ready to support a high penetration of PVs. For selecting proper charging and discharging rates can alleviate
example, on June 2014, there was about 23 GW of solar power voltage rises. In [7], the analysis of several control strategies
on the German grid, covering more than 50% of the total of ESS estimated that using battery management based on
electricity demand at noon [2]. Under this situation a huge forecasts may provide a higher potential to the grid relief than
amount of PV produced energy had to be curtailed to maintain selecting a charge scenario which aims on maximizing self-
the stability of the power system. A solution that can avert the consumption. However, the results were not evaluated by
curtailment PV generated power is the installation and simulations on a distribution grid. The study in [8] proposes
operation of distributed Energy Storage Systems (ESS). Such the calculation of a power threshold above which PV energy
a solution can provide flexibility to the system by storing the should be stored in the ESS, thus preventing voltage rises. This
surplus energy and shifting its consumption to periods with low threshold is highly dependent on the PV penetration level of
production and high demand. the examined feeder.
Simultaneously, the concept of the Nearly Zero Energy Our study carries out an analysis of LV grid operation in the
Buildings (NZEB) was introduced in Europe in 2010 with the presence of PVs and ESSs, aiming to explore the extent to
Recast of the Energy Performance Building Directive [3]. which battery capacity and control strategy of ESSs affect the
voltage level along a distribution network. At the same time
the study evaluates the ESSs influence on the prosumers’ self-
consumed energy. A common benchmark LV feeder is used
for time-series simulations of different examined cases. The
study provides conclusions about the benefits of ESSs for
prosumers and network operators.
The paper is organized as follows. Firstly, section II
describes the theoretical background of the metrics used to
evaluate the impact of ESS on grid operational limits and on
customers’ energy management. Section III presents the
system that is used for the simulations and describes the
different scenarios tested. In Section IV results of the multiple
scenarios are demonstrated and discussed, while section V
concludes the paper. Fig. 1. Sample PV production and consumption profiles of a certain
installation throughout a day. Letters are indicating energy amounts used in
II. THEORETICAL BACKGROUND equations 1, 2.
A. ESS technology 𝐶𝐶 + 𝐸𝐸
Among the most commonly used battery technologies is SSR = (2)
𝐴𝐴 + 𝐶𝐶 + 𝐸𝐸
Lithium-ion (Li-ion) [9]. Li-ion technology characteristics
such as lifetime, self-discharge rate and charge-discharge
efficiency are superior compared to other battery technologies, III. SYSTEM UNDER STUDY
thus making it an attractive solution for investments on ESS by
residential prosumers. Therefore, we assume that this A. Network Description
technology is used in the simulations carried out in this work. A CIGRE LV distribution network benchmark [10] is used
The usable capacity of Li-ion batteries is limited to a State of in this work to evaluate the impact of distributed storage
Charge (SOC) between 20% and 90%, to ensure a longer systems on the voltage profile. The residential feeder of the LV
lifetime [8]. An inverter efficiency of 95% is assumed for the benchmark network is used, with a base frequency of 50Hz, as
ESS. depicted in Fig. 2. It has a radial structure and is connected to
the medium-voltage (MV) network through a 500 kVA, 20/0.4
B. Self-consumption Rate and Self-sufficiency Rate kV transformer. This feeder supplies 35 customers, which for
Self-consumption Rate (SCR) and Self-sufficiency Rate our case are assumed to have three-phase connections.
(SSR) are two indicators showing at what extent the prosumer Alongside, three-phase PVs are installed at every load bus. The
takes advantage of the energy generated by his own PV following paragraphs describe how the load and generation
installation. These two indicators that characterize each profiles are used.
prosumer in our test are defined below.
Self-consumption is the fraction of electrical energy B. PV and Load profiles
generated by the PV system that is directly consumed on-site The consumers connected to the feeder include single family
residences and commercial loads. Demand data are derived
or stored for later use, over the total PV generated energy. This
is better demonstrated through (1) and Fig. 1: from [11], a dataset developed by the U.S. National Renewable
Energy Laboratory (NREL). This dataset consists of averaged
𝐶𝐶 + 𝐸𝐸 load data, randomized to emulate real load profiles. Consumers
SCR = (1) were randomly placed on the test network. As an example, Fig.
𝐵𝐵 + 𝐶𝐶 + 𝐷𝐷
3 depicts indicative load profiles of five residential loads
located at nodes 10, 11, 14, 15 and 17, for one day of July. The
Self-sufficiency is defined as the ratio of the renewable reactive load is calculated by using a power factor of 0.95 on
energy generated by the PV system, which is used to supply the active load profiles.
the prosumer’s own needs, over the total consumed energy, as Generation profiles used for the simulations have been
shown in (2) and Fig. 1: constructed using solar irradiation data from the Photovoltaic
Geographical Information System (PVGIS) online platform of
the EU Joint Research Centre [12]. The PV output power in
kW/kWp depends on global horizontal solar irradiation, air
temperature, orientation and performance characteristics of the
PV-inverter system. In this test, an inclination angle of 220
(inclined roof) is assumed.
MV the option of installing an ESS of a certain capacity at each
customer is supposed.
20/0.4 kV
Different cases of battery size and operation control are
LV
1
examined in order to evaluate on the one hand the effect of ESS
on the feeder operating limits and on the other hand ESS
11 2 contribution on increasing prosumers’ self-consumed energy.
3 The last is quantified using the indicators SCR and SSR.
5x
12 13 14
Battery nominal capacities examined in our test are in the
4 range of 5 kWh to 40 kWh with a step of 5 kWh. For every
simulation the ESS size is equal at every prosumer. Three
16 5 15
5x charging-discharging schedules are adopted [8], as mentioned
5x 6 below:
a) charge of the battery starts as soon as PV generated power
7
is greater than demand power (Scenario I),
8 b) charge of the battery occurs during peak generation, i.e.
17
5x while PV power exceeds the 70% of its peak production
9 (Scenario II),
18
5x 10
Node c) charge of the battery occurs during peak generation, i.e.
Prosumer while PV power exceeds the 80% of its peak production
(Scenario III).
Fig. 2. Single-line diagram of the residential feeder of CIGRE Low Voltage It should be noted that in all scenarios, the battery is charged
benchmark network.
only if the PV output power exceeds load demand. The
maximum charge and discharge rate that is adopted on our tests
8
Node 10
is 1C, i.e. a 5 kWh battery can be charged in one hour with a
7
Node 11 charge rate of 5 kW.
Node 14
Node 15
Network power flow is simulated with a 15-min resolution
6 Node 17 for the month with the highest PV produced energy, i.e. July,
5
in order to obtain the voltage profile for all nodes.
D. Simulation Tool
Power (kW)
4
A simulation tool developed in [14] has been used for the
3 time-series power flow analysis in the test network. This tool
2
offers a graphical user interface for the design of electrical
circuits and uses Open Distribution System Simulator
1
0 4 8 12 16 20 24
(OpenDSS) [15] and Matlab [16] for the analysis of electrical
Time distribution systems.
Fig. 3. Load profiles during the 1st of July for residential loads located at IV. RESULTS AND DISCUSSION
nodes 10, 11, 14, 15 and 17.
Various scenarios were simulated to investigate how the
The same solar irradiation data apply for all PVs, because of battery size and energy management influence the voltage
the short length of the examined network. A profile of the levels across the LV feeder and the SCR and SSR of
production for a typical day of each month in 15-min. time prosumers. Longer voltage violations are observed at node 15
steps is then constructed using the appropriate kWp installed of the network in the case where no ESS are installed on the
capacity of each PV and assuming 10% system losses. prosumers’ sites. Results of different cases are presented and
discussed below.
C. Investigated Scenarios A. Scenario I
It is assumed that every one of the 35 customers has a PV In this scenario, the ESS at each installation is charged as
system installed, acting as a prosumer. The size of each PV soon as the generated power exceeds load demand. The daily
system has been calculated so that an average SCR of 30% is mean duration of overvoltages at node 15 can be seen in Fig.
obtained at the month of maximum PV generation. Due to the 4a. It is shown that even with an ESS capacity of 40 kWh, the
overvoltages occurring on the network during peak generation voltage limit is surpassed for more than three hours a day. This
hours, PV power curtailment is taking place in order to is because the SOC of each battery reaches 90% before
maintain the voltage under the accepted operating limits, maximum generation. At the time of peak production, a huge
defined by the Standard EN 50160, i.e. 0.9 - 1.1 p.u. [13]. In amount of generated power is injected to the network by all
order to avoid the loss of RES energy injected to the grid and prosumers causing overvoltages, as all batteries are already
the loss of prosumers’ revenues occurring by the curtailment, fully charged.
Regarding the self-consumption of prosumers, their SCR
and SSR are increasing as battery capacity is growing. Fig. 5 55
nodes 10, 11, 15, 16, 17, 18. Starting from the case where no
45
ESS is installed, the SCR is 30% as assumed for the tests. It
SCR (%)
40
can be seen that with a battery size of 40 kWh prosumers
achieve an SCR of 47%. The SSR depends on the battery size 35
SSR (%)
70
Among the different battery capacities that are tested, it is
shown that overvoltage occurrences are reduced as battery size 60
a) b)
4 4 45
40
2 2
SCR (%)
35
0 0
Duration (h)
Duration (h)
0 5 10 15 20 25 30 35 40 0 5 10 15 20 25 30 35 40
c) d) 30
4 4 40
30 35
10 20 25
11 15 16 17 5 10 15
18 0
2 2 Node number Battery size (kWh)
Fig. 7. SCR of 6 indicative prosumers connected on nodes 10, 11, 15, 16,
0 0 17, 18 for several battery sizes, using charging scenario II.
0 5 10 15 20 25 30 35 40 0 5 10 15 20 25 30 35 40
Battery size (kWh) Battery size (kWh)
80
Fig. 4. Daily mean duration of voltage limit violation at node 15 for different
70
sizes of battery installed at each prosumer, under 4 different ESS control
strategies: (a) Charge as soon as PV power exceeds load power, (b) Charge
SSR (%)
after PV power reaches (b) 50% of the peak power, (c) 70% of the peak power, 60
40 35 40
25 30
10 15 20
11 15 10
16 17 5
18 0
Node number Battery size (kWh)
Fig. 8. SSR of 6 indicative prosumers connected on nodes 10, 11, 15, 16,
17, 18 for several battery sizes, using charging scenario II.
C. Scenario III
This scenario examines the schedule in which the battery is
50
set to charge when PV output power is greater than the 80% of
its peak output power. In this case, the overvoltage occurrence 45
SCR (%)
kWh, above which voltage limit is not violated. A size of 20 35
no ESS are installed at the prosumers’ sites and the case where Charge strategy
ESS with 20 kWh batteries are installed. As expected, in the
Fig. 10. Comparison of SCR of load on node 10, for several battery sizes,
second case voltage is below the limit of 1.1 p.u. at any node. between the three charging strategies described in scenarios A, B, C.
SSR (%)
60
In Fig. 4, the daily mean duration of voltage limit violation at
node 15 for different sizes of battery installed at each prosumer 50
35
40
30
is illustrated, under 4 different ESS charge strategies: (a), (c), 40
15
20
25
10
(d) correspond to Scenarios I-III and (b) refers to the case ar io A B 0
5
Battery size (kWh)
Scen rio rio C
cena a
where battery is charged while PV output is beyond 50% of the S Scen
peak power. It can be realized that for a specific network, load Charge strategy
characteristics and PV installed capacity, there is a minimal
Fig. 11. Comparison of SSR of load on node 10, for several battery sizes,
ESS capacity that should be installed at all prosumers, above
between the three charging strategies described in scenarios A, B, C.
which overvoltages can be prevented. This minimal capacity
highly depends on the ESS charging schedule. In our test As explained already, the SCR and SSR rise when the ESS size
network, overvoltages are prevented when charge scenarios II increases. However, it should be noticed that for Scenario III,
and III are employed and for capacities above 30 kWh and 20 there is a certain ESS capacity above which SCR and SSR are
kWh respectively, whereas in scenario I the voltage limit is not increasing, i.e. 20 kWh for the prosumer shown in Fig. 10
surpassed. and Fig. 11. When operating the ESS following Scenario III
In addition, the self-consumption and self-sufficiency of and for ESS sizes beyond 20 kWh the battery is never fully
each prosumer greatly depend on the selected charge strategy charged, since the energy produced when PV output exceeds
and ESS capacity. Fig. 10 and Fig. 11 depict the SCR and SSR 80% of peak production is not sufficient to make full use of the
of an indicative prosumer connected at node 10. battery capacity.
1.12 V. CONCLUSIONS
1.1 High PV penetration in LV distribution networks is one of
1.08
the causes of inverse power flow and violation of voltage
operational limits. DSOs already use various methods to
1.06 prevent such phenomena, frequently including PV power
Voltage (p.u.)