You are on page 1of 16

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/305417550

Analytical Approach to Estimate Feeder Accommodation Limits Based on


Protection Criteria

Article  in  IEEE Access · January 2016


DOI: 10.1109/ACCESS.2016.2589545

CITATIONS READS
17 4,189

4 authors:

Harsha Vardhana Padullaparti Pisitpol Chirapongsananurak


National Renewable Energy Laboratory Chulalongkorn University
37 PUBLICATIONS   254 CITATIONS    21 PUBLICATIONS   77 CITATIONS   

SEE PROFILE SEE PROFILE

Miguel Hernandez Surya Santoso


Electric Power Research Institute University of Texas at Austin
34 PUBLICATIONS   251 CITATIONS    293 PUBLICATIONS   6,682 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

PV smart inverter control tuning View project

Photovoltaic Hosting Capacity View project

All content following this page was uploaded by Surya Santoso on 31 January 2017.

The user has requested enhancement of the downloaded file.


This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

Analytical Approach to Estimate Feeder


Accommodation Limits based on Protection Criteria
Harsha V. Padullaparti, Student Member, IEEE, Pisitpol Chirapongsananurak, Student Member, IEEE,
Miguel Hernandez, Student Member, IEEE, and Surya Santoso, Fellow, IEEE

Abstract—Widespread deployment of large-scale photovoltaics DG (RBDG) such as synchronous machine-based DG and


(PV) and energy storage systems (ESS) in distribution net- induction machine-based DG on feeder overcurrent protection
works necessitates the development of methods to assess their schemes is reported in [7], [8]. As opposed to the RBDG,
possible system impacts. One of the primary concerns related
to the integration of these systems is short-circuit overcurrent inverter-interfaced distributed generation (IIDG) such as PV
protection problems. Present techniques use simulations of full systems do not make much fault current contribution. While
and detailed distribution circuit models with large number of the fault current contribution of PV systems can vary from
scenarios to estimate the PV and ESS sizes a distribution feeder 1.1 to 2.5 times the inverter rated current depending on the
can accommodate without causing adverse impacts. As this type of inverter, the rule of thumb in the industry for system
process requires considerable time and effort, this paper develops
a practical and simplified analytical approach to conservatively studies is 2 times the inverter rated current [9], [10]. Such
estimate a utility distribution feeder’s accommodation limits low PV fault currents may not interfere with the overcurrent
without causing protection problems. Sympathetic tripping and protection schemes in case of small-scale PV systems with
relay insensitivity problems are considered in this work under low penetration level. However, large-scale PV installations
both symmetrical and unsymmetrical fault conditions. Using can inject high fault currents into the system and can lead
the analysis presented, the factors influencing these protection
problems are determined to provide insights into relay settings. to protection problems [11], [12]. Some of the operational
The feeder accommodation limits obtained using the proposed issues associated with PV can be mitigated by installing and
analytical approach are compared with those obtained using operating ESS along with PV [13].
simulations of an actual detailed distribution circuit model. Energy storage systems (ESS) have many applications in
The findings show that the proposed approach is accurate in both transmission and distribution systems. In a distribution
estimating the feeder’s accommodation limits for integrating
large-scale PV and ESS. system, the benefits of ESS include peak shaving, load level-
ing, time-shifting of renewable energy, and voltage stabiliza-
Index Terms—Photovoltaic systems, energy storage, power
tion [14]. Although the ESS have various benefits, their wide-
distribution faults, short circuit currents
spread deployment is being limited by few barriers. The key
barrier among them as on date is the cost. Nevertheless, there
I. I NTRODUCTION are numerous large-scale ESS projects in commercial opera-

T HE installed capacity of photovoltaic (PV) systems has


grown rapidly in the past decade in the U.S. This growth
can be attributed primarily to the decline in the PV prices
tion now world-wide [15]. Further, the deployment of ESS is
expected to grow dramatically in near future [16]. Similar to
PV systems, the fault current contributions from ESS can also
and the incentives from the government [1]. Being highly have adverse impacts on the distribution feeder overcurrent
scalable, the PV installations can be found in various sizes protection schemes [17]. Considering the widespread existence
ranging from few kilowatts to several hundreds of megawatts. and expected growth of large-scale ESS, there is a need to
The PV systems of smaller ratings such as those found on study the influence of ESS on feeder overcurrent protection
residential and commercial rooftops can be considered as schemes.
small-scale PV systems. According to Energy Information The amount of PV a distribution feeder can accommodate
Administration (EIA), the PV systems of ratings above 1 MW without violating the nominal system operating conditions
can be considered as utility-scale or large-scale PV systems is the feeder’s PV hosting capacity or feeder’s PV accom-
[2]. Besides the small-scale residential PV systems, large-scale modation limit [18]. In case of ESS, it can be referred to
PV installations are also in commercial operation now in the as ESS accommodation limit of the circuit. Approaches for
distribution feeders [3]. Integration of distributed generation determination of a feeder’s accommodation limits with relay
(DG) such as PV, in general, brings numerous technical insensitivity and sympathetic tripping as impact criteria using
benefits such as reduced line losses, improved voltage profiles, circuit simulations are reported in [19], [20]. Keeping in view
and enhanced system reliability [4]. However, it also poses of the new grid regulations and worst case system conditions,
challenges to existing system protection schemes and utility these studies are performed considering ‘low voltage ride
voltage regulation practices [5]. through’ (LVRT) requirement of the PV systems. With the
Before integrating DG, system studies need to be performed growing concerns to integrate higher amounts of PV into distri-
to assess associated impacts on the existing overcurrent protec- bution systems along with possible adverse impact mitigating
tion schemes [6]. The impact is highly dependent on the type measures such as installing ESS, suitable methods are required
of DG being integrated. Influence of rotating machine-based for estimating the sizes of large-scale PV and ESS a feeder

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

can accommodate without creating protection problems. In to accept PV interconnection requests. For PV integration, the
this work, an analytical approach is presented to determine penetration level is limited to 15% of the maximum feeder
a distribution feeder’s accommodation limits of integrating load on a line section to avoid any adverse impacts [19].
large-scale PV and ESS based on relay insensitivity and Alternatively, system studies need to be performed with all
sympathetic tripping as impact criteria considering LVRT. The possible combinations of fault types, fault locations, PV size
analysis presented in this work is validated against simulation and locations which is time consuming posing scalability
studies on a distribution circuit model in OpenDSS developed challenges and resulting in circuit specific outcomes. In this
using actual circuit data from a utility. The results match context, the main contribution of this work is development of
within 7% of theoretical predictions, thus validate the analysis. a scalable analysis-based method to conservatively estimate
This paper is organized into six sections. The problem large-scale PV and ESS accommodation limits of a distribution
statement and the motivation of this work are detailed in feeder without causing relay insensitivity and sympathetic
Section II. An overview of distribution feeder overcurrent tripping problems. The objective is to simplify the estimation
protection is provided in Section III. The relay insensitivity process with reasonable approximations under conservative
and sympathetic tripping problems are also described in this settings. The other contribution is providing insights into
section. In Section IV, the analysis of relay insensitivity and overcurrent relay settings when large-scale PV and ESS are
sympathetic tripping protection problems in the presence of present. The analysis for assessing the impact of ESS installed
large-scale PV and ESS is presented and key parameters in- either individually or in conjunction with PV on the protection
fluencing these problems are discussed. Section V presents the relay response and its application to assess accommodation
simulation results using a detailed distribution circuit model limits of a utility distribution feeder is not reported in litera-
that validate the analysis. The conclusions and discussion are ture.
provided in Section VI. In recent years, there are several changes to the regulations
for grid interconnection of DG. While previous regulations
mandated disconnection of DG during abnormal system con-
II. P ROBLEM S TATMENT AND M OTIVATION
ditions, many new regulations require the DG to remain
Protection studies, similar to other impact studies, for connected during the faults, referred to as ‘low voltage ride
deployment of PV systems require development of detailed through’ (LVRT) or ‘fault ride through’ (FRT). Similar to DG,
distribution system models using distribution system sim- as part of grid support functions, the ESS also offers LVRT
ulation tools [21]. Then the developed model is validated functionality [24]. Since protection studies are performed con-
using suitable methods such as comparing power flow results sidering the worst case situation, it is reasonable to consider
with actual field measurements. Once the validated model that the large-scale PV and ESS remain connected in the
is available, simulation studies are performed to assess the system during the fault conditions and assess the impact of
impact of PV integration on protection schemes with large their steady state current injection into the distribution network
number of scenarios. However, this process requires consider- [20]. Thus, in this work, analysis is provided considering
able time and effort [22]. Furthermore, in this particular case LVRT requirements of PV and ESS.
of determining feeder accommodation limits of integrating PV
using circuit simulations, the approach presented in [19] is III. OVERVIEW OF D ISTRIBUTION F EEDER OVERCURRENT
useful to study only small test systems with few nodes. Such a P ROTECTION AND I MPACTS OF PV AND ESS
simulation based approach when applied to actual distribution
Majority of the conventional distribution systems are radial
feeders having thousands of buses poses several complications
in nature as the radial systems are least expensive, simpler in
of scalability. Some of the reported scalability challenges are
planning, design and operation compared to other alternatives
power flow solution convergence problems, complexity of
[25]. In radial systems, the primary substation is the only
analysis and visualization of results considering large number
source feeding the distribution load and there exists only
of fuses, huge time requirement to study all possible combina-
a single path between each customer and the substation.
tions of PV sizes, and fault locations [20]. These complexities
Typically, overcurrent protection is the main feeder protec-
can be handled to some extent by using network reduction
tion in radial systems. Overcurrent relays, circuit breakers,
technique [23] and some reasonable approximations such as
reclosers, sectionalizers and fuses are the main protection
modeling only few main protection devices such as reclosers,
devices in overcurrent protection schemes. The role of these
simulating only few representative scenarios of selected PV
protection devices and the overcurrent protection coordination
locations [20]. However, the accommodation limits obtained
are briefly explained in this section. Then relay insensitivity
as outcome pertains only to that particular circuit and is valid
and sympathetic tripping problems that may arise due to the
only for a particular set of protection device settings. As such,
presence of large-scale PV and ESS are described.
the conclusions may not necessarily be applicable to other
circuits or even to the same circuit with different protection
device settings as the results are highly dependent on the A. Overcurrent Protection Devices
circuit characteristics. 1) Circuit Breakers: Circuit breakers are used to protect the
In the absence of insights into the relationship among distribution networks by interrupting the fault currents during
various system parameters, the utility planners are usually faulty circuit conditions. Overcurrent relays control the circuit
forced to apply conservative rules of thumb penetration levels breaker operations. While isolating the faulted line section,

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

due to the interruption of inductive current, electric arc forms total clearing curve is a plot of the longest melting time versus
between the circuit breaker contacts. To quench the electric the current required to melt the fuse link. When a fuse melts,
arc, circuit breakers use different types of arc-extinguishing the fault current and its associated time would lie between the
media such as air, oil, vacuum or SF6 gas. two curves.
2) Overcurrent relays: Overcurrent relays are the fault
sensing devices that detect faults in the distribution system 1000
and open the circuit breaker. They can function as phase
overcurrent or ground overcurrent relays depending on the 100
current being monitored. Phase overcurrent relays detect the
fault currents flowing in the lines. When the line currents are 10

Time [seconds]
above the phase overcurrent relay pickup setting, the relay
Total Clearing
trips the circuit breaker. The trip time depends upon the time-
dial setting of the relay. For detecting the unbalanced faults, 1

ground overcurrent relays are used. These relays provide more


sensitive protection for phase to ground faults. The ground 0.1
overcurrent relays respond to the residual or unbalance current Minimum Melting
which is the sum of the currents in all the three phases in 0.01
a three-phase distribution system. When the residual current 10 100 1000 10000 100000
seen by the ground overcurrent relay exceeds the relay pickup Current [Amperes]
setting, it opens the circuit breaker.
3) Reclosers: A recloser trips the circuit whenever a fault is Fig. 1. Typical TCC curve of a fuse.
detected and automatically recloses after a predetermined time
in the anticipation of the fault getting cleared. This reclosing
action is performed a preset number of times after which the
B. Overcurrent Protection Coordination
recloser will stay open and isolates the fault if the fault still
persists in the circuit. As majority of the faults in the overhead The process of selecting the appropriate settings for the
distribution systems are temporary in nature and last for only overcurrent relays such that whenever there is a fault, the
a few cycles, the reclosers avoid unnecessary service outage overcurrent relay operations ensure that the fault is isolated
for temporary faults. Reclosers can detect both phase and as fast as possible while causing minimum service outage
ground overcurrent conditions and therefore have the ability to the customers is known as protection coordination. The
to protect the distribution network in case of both balanced coordination arrangement is done such that whenever there
and unbalanced permanent faults. is a fault, all the protective devices sense the fault but the
4) Sectionalizers: Sectionalizers are used to isolate the device that is closest to the fault (main protective device)
faulted sections of a distribution circuit after an upstream operates first. If the main protective device fails to operate,
protection device has interrupted the fault current. Since the next protective device upstream (backup protective device)
sectionalizers do not have fault current interrupting capability, would operate after some time delay to isolate the fault. Thus,
they must be used in conjunction with backup protection upstream protective devices provide backup protection for the
devices such as circuit breaker or recloser and are installed downstream protective devices.
downstream from the backup protection device. Under fault Following distribution system data is required for choosing
conditions, the sectionalizer counts the number of upstream proper overcurrent relay settings [26]:
recloser operations. In case of temporary faults, the fault i) One-line diagram of the distribution system with locations
gets cleared before the recloser finishes the preset number of of protective devices and their time current characteristics
reclose operations. Then the circuit recloses successfully and ii) Maximum expected load current through the protective
the sectionalizer counter resets to its normal position. Thus, devices
the service to the customers is continued with few momentary iii) Maximum and minimum fault currents or short-circuit
interruptions during recloser operations. In case of permanent levels at each protective device
faults, the recloser remains open after the preset number of The details of expected load currents and fault currents
recloser operations, isolating the faulty section of line. through the protective devices are obtained from load flow
5) Fuses: Fuses consist of a fusible metallic conductor link study and fault studies respectively. All the protective devices
that passes current under normal circuit conditions. During need to be well coordinated with each other. In what follows,
faults, the fuse link melts due to overheat produced by the the typical protective device coordinations that need to be
fault current and opens the fuse contacts, thus interrupts the taken care of are briefed.
fault current. The time of operation of a fuse depends upon 1) Fuse-Fuse Coordination: The coordination among the
the fault current and the time current characteristic (TCC) of fuses connected in series can be achieved by appropriate
the fuse. The TCC has two curves: (i) the minimum melt selection of TCC curves of the fuses. When fuses are in series,
curve and (ii) the total clearing curve as shown in Fig. 1. the fuse that is nearest to the fault can be referred to as main
The minimum melting curve is a plot of the minimum time fuse or protecting fuse. The next fuse upstream towards the
required against the current required to melt the fuse link. The source of supply is backup fuse or protected fuse. For proper

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

Recloser slow curve multiplied by accomplish the recloser-recloser coordination by selecting dif-
safety factor
C’ ferent types of reclosers. If same type of reclosers are chosen,
C
Fuse TCC curves
the coordination can be done by selection of different current
ratings or different operating sequences of the reclosers.
4) Relay Coordination with Reclosers and Sectionalizers:
A Fig. 3 shows the typical arrangement of circuit breakers,
Time, S

reclosers, and sectionalizers in a distribution typical distribu-


tion system. The feeder breakers are usually equipped with
overcurrent protection relays. The operations of the relays
controlling the circuit breaker need to be time delayed to allow
the fault clearance by the downstream reclosers. In case of
Isc max at recloser
Current, A permanent faults downstream of the recloser, the sectionalizers
(a) isolate the faulted section at a current zero after preset number
of recloser operations. This operation of the sectionalizer
Recloser fast curve
multiplied by safety factor allows the service to resume to healthy feeder section after
A’ recloser closes the circuit.
A

CB – Circuit Breaker
R – Recloser
A S – Sectionalizer
Time, S

Fuse TCC curves CB F – Fuse


Substation

CB

S F
Isc max at recloser CB R
Current, A

(b) S F
F
Fig. 2. Fuse-recloser coordination (a) when fuse is at the source side (b)
when fuse is at the load side.
Fig. 3. Typical arrangement of protective devices in a distribution system.

coordination, the total clearing time of the main fuse should


not exceed 75% of the minimum melting time of the backup
fuse for a given current level [26]. This ensures that the main C. Impacts of PV and ESS on Distribution System Protection
fuse melts and isolates faulty line section before the backup Distribution system overcurrent protection schemes assume
fuse is damaged. The 25% margin accounts for the variables single source of supply in the system and unidirectional current
such as load current, ambient temperature and partial melting flow from the source to the customer loads. The presence of
of the fuse due to fault currents of short duration. PV systems, ESS and their corresponding current injections
2) Recloser-Fuse Coordination: The coordination between effectively creates multiple sources and bi-directional current
recloser and fuse depends upon their relative locations and flows in the system. This interferes with the protection relaying
which device is intended to act as the backup device to the and causes protection issues [6]. Following impacts of PV
other. When the fuse is at the source side and upstream from and ESS on the distribution system overcurrent protection are
the recloser, the fuse is the backup device to the recloser. reported in literature:
Then to prevent melting of the fuse, all the recloser operations 1) Reduction of Reach: In distribution systems, overcurrent
should be faster than the fuse. To account for cumulative relays control the utility breaker and reclosers. The overcurrent
heating effect on the fuse due to multiple recloser operations, relays are set to detect faults within a certain distance along
the recloser slow curve is multiplied by a factor to make it the feeder, referred to as ‘reach’ of the relay. Reach of an
slower as shown in Fig. 2(a). Still, this slower curve also overcurrent relay is determined by its pickup current setting.
should lie below the minimum melting curve of the fuse Usually, the pickup current setting is chosen above the maxi-
making the recloser operations faster before the fuse gets mum load current and below the minimum fault current in the
affected. When the fuse is at the load side and downstream feeder so that the relay does not respond to the load currents
from the recloser, the fuse acts as the main protective device. In and be able to detect and respond to the fault currents [27]. The
this case, both the minimum melting and total clearing curves fault current contributions from DG reduce the fault current
of the fuse should lie in between the recloser fast and slow seen by the upstream protection devices. As a result, reach of
curves as shown in Fig. 2(b). the upstream protection devices is reduced. For a sufficiently
3) Recloser-Recloser Coordination: When there are more high level of fault current injections by DG, as happens in the
than one recloser present in a distribution system, coordination case of large-scale PV, upstream protection devices may fail to
is required among them. In such situations, utilities prefer to detect the fault. This phenomenon is called relay insensitivity.

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

Reduction of relay reach is illustrated in Fig. 4 where a large- actual utility distribution circuit model and protection device
scale PV system is planned to be connected to a bus in the settings reported in [20] indicates that sympathetic tripping
middle of the feeder. The fault current contribution by the PV is one of the major issues utility planners face due to the
for a fault downstream of the PV reduces the reach of the integration of IIDG. Solutions for preventing the protection
relay upstream. problems under study are reported in [37]–[39]. However,
implementing these over many distribution networks can be
a costly decision [20]. Therefore, there is a strong motivation
Vsg
Fault to perform comprehensive analysis into relay insensitivity and
R sympathetic tripping problems.
3) Protection Coordination Issues: The bi-directional cur-
IR
rent flows due to fault current injections from PV and ESS in-
PV terfere with the coordination of overcurrent protective devices
and could lead to misoperations. The exact impact typically
depends upon the size of the PV, relative locations of PV, ESS
Fig. 4. Illustration of reduction of relay reach.
and protective devices, protection settings and the distribution
Fault analysis to calculate reduction of relay reach consider- system feeder impedance.
ing RBDG is presented in [19], [28]. Unlike the RBDG, which 4) Reverse Power Flow: At higher PV penetration levels
acts as a voltage behind a reactance during the faults, IIDG and minimum loading condition in the feeder, the power flow
acts as a current source due to the current controllers present direction reverses at the substation when the PV generation
in the IIDG controlling their power output [12]. Therefore, the is more than the power consumption in the feeder. The
fault analysis of RBDG is not applicable to IIDG. Considering reverse power flow could possibly operate the reverse power
this fact, analysis for the impact of IIDG on relay reach with relays installed at the head of the feeder causing outage of
IIDG acting as a current source is reported in [29]–[31]. A the feeder significantly affecting the system reliability [40].
real-world example of a potential relay insensitivity problem in The power reversal could also cause incorrect operation of
a distribution feeder due to the integration of a large-scale PV voltage regulators and capacitor controls as these controls
system is reported in [3], indicating the necessity of studying are not designed for reverse power flow. This increases the
relay insensitivity problem. number of operations and related equipment wear in addition
to power quality problems to the customers. The operational
2) Sympathetic Tripping: Sympathetic tripping occurs
problems due to reverse power flow include over voltages on
when the fault current from the PV causes relays on the healthy
the distribution feeder and increased short-circuit levels.
feeder to pick up for faults on the adjacent feeders and results
5) Fuse Saving and Fuse Tripping: Majority of the faults
in unnecessary outage of the healthy feeder [5], [6]. This is
in the distribution systems are temporary in nature. They
illustrated in Fig. 5 where a large-scale PV system is connected
occur momentarily for various reasons and are cleared by
in Feeder 1 and a fault occurs on adjacent Feeder 2. During
themselves. Isolation of such faults by blowing the fuses cre-
the fault, if the PV system remains in the circuit as per LVRT
ates unnecessary long duration service outages. To minimize
requirements, it feeds the fault back through the relay ‘R’ at
the service outages for temporary faults, utilities use ‘fuse
the substation. When the large-scale PV is of considerable size,
saving practice for coordination of breaker or recloser with
the fault current from the PV can go above the pickup setting
the downstream fuses. In this practice, the breaker or recloser
of the overcurrent relay at the substation causing unwanted
operates on fast curve before the fuse gets affected as was
tripping of the Feeder 1 [32]–[34].
shown in Fig. 2(b). This saves the fuse in case of temporary
faults. For permanent faults, the fuse blows when the breaker
or recloser operates on slow curve after preset number of fast
PV operations. The faster curve of breaker or recloser can also
Vsg Feeder 1 be replaced with instantaneous overcurrent elements. In that
IfPV case, the instantaneous overcurrent element trips the breaker
R
or recloser before the fuse melts and is blocked temporarily.
If the fault is permanent, the fuse blows as the breaker or
Ifgrid
recloser operation is delayed based on their slow curve. The
Fault
fuse saving practice leads to increased number of momentary
service interruptions as the breaker or recloser trips the entire
Feeder 2 line downstream for all faults. As such, the utilities follow fuse
tripping practice wherein the fuse is allowed to blow for all
Fig. 5. Illustration of sympathetic tripping. faults. The fuse blowing practice produces fewer momentary
interruptions but more sustained interruptions.
While sympathetic tripping may not be likely a problem The DG installations could affect the timing coordination
in case of small-scale PV with low penetration levels, it is between breaker/recloser and the fuse due to the additional
a potential problem with high penetration of PV or large- fault current contribution from the DG. As a result, the fuse
scale PV [35], [36]. The IIDG impact study results using an could blow first or both the fuse and breaker/recloser could

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

operate at the same time [41].


ZLine1 ZLine2
IV. A NALYSIS OF R ELAY R EACH AND S YMPATHETIC
T RIPPING WITH PV AND ESS
IR,no PV
In this section, the impact of large-scale PV and ESS on the Zeq
overcurrent relay reach and sympathetic tripping is analyzed. Rf
Battery energy storage system is assumed for ESS.
Vsg

A. Reduction of Relay Reach


Consider the distribution circuit shown in Fig. 6 where
a large-scale PV system is planned to be connected to a (a)
bus in the middle of the feeder. The upstream transmission
system of the substation including the substation transformer ZLine1 ZLine2
is represented by a Thevenin equivalent circuit with impedance
Zeq . Phase overcurrent relay ‘R’ is installed at the substation.
Since the faults farther from the substation cause minimum IR,PV
fault currents which are more challenging to detect, a remote Zeq
end fault with resistance Rf is assumed for conservative IfPV Rf
study. The impedances of the feeder sections upstream and
downstream of the PV location are represented by ZLine1 and Vsg
ZLine2 , respectively.

(b)
Vsg
Zeq Fault
Fig. 7. Equivalent circuit of the distribution system a) without PV and b)
R ZLine1 ZLine2
with PV.
IR,no PV Rf
PV substation. The location of PV alters the fault current distri-
bution. During faults, the PV systems behave like constant
power sources and the PV inverters try to push the same
Fig. 6. Distribution system with fault.
power even at the low terminal voltages by injecting higher
1) Analysis for symmetrical faults: Consider the fault in currents [31]. As such, a PV system located close to the fault
Fig. 6 is a three-phase fault. Fig. 7(a) shows the equivalent can inject a higher current due to its lower terminal voltage
circuit of the system when the PV is not connected. Using compared to the PV system located far away from the fault
Kirchoff’s voltage law (KVL), the fault current seen by the which has higher terminal voltage during the same fault for
relay is given by: a given PV power output. Conservatively, this current can be
considered as 2 times the inverter rated current [31]. When
Vsg the PV fault current contribution is fixed at this value, the
IR,noP V = (1)
(Zeq + ZLine1 + ZLine2 + Rf ) PV can be placed close to the substation with the fault at
where Vsg and IR,noP V are the line-to-ground pre-fault volt- the end of the feeder as per (2) so that ZLine2 is maximum
age at the substation bus and fault current through the relay causing more reduction in the fault current seen by the relay
without PV, repectively. at the substation. In such a scenario, when the three-phase
When the large-scale PV system is connected injecting a fault resistance is sufficiently high, the fault current seen
fault current IPf V during the three-phase fault, the equivalent by the relay goes below its phase overcurrent pickup value,
circuit of the distribution system is shown in Fig. 7(b). making the relay insensitive to the fault. Under this situation,
Then the fault current through the relay with the large-scale any additional fault current contribution from the PV would
PV connected can be obtained by applying superposition in further reduce the fault current seen by the relay and make it
Fig. 7(b) as insensitive to the faults with lesser fault resistance. In other
words, the large-scale PV reduces the reach of the overcurrent
(ZLine2 + Rf )
IR,P V = IR,noP V − If relay.
(Zeq + ZLine1 + ZLine2 + Rf ) P V Considering the bus voltage phasor where the large-scale
(2)
PV/ESS is connected as reference and the steady-state fault
Equation (2) shows that the fault current through the relay current contribution from the large-scale PV is twice the PV
is reduced due to the fault current contribution from the PV rated current in phase with the bus voltage [9], [10], [20], the
during a three-phase fault. This current seen by the relay is fault current through the phase overcurrent relay from (2) can
also influenced by the available short-circuit capacity at the be expressed in terms of the PV size as (3). Taking the PV/ESS

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

bus voltage as reference significantly reduces the complexity ZLine1 ZLine2


of analysis without introducing much error in the estimate. R
Although the analysis is done in this paper by assuming PV Zeq I R0 ,noPV
fault current contribution is 2 times its rated current (rule of
thumb for system studies), the analysis can be extended along Vsg
the same lines for other levels of PV fault current contributions
depending upon PV inverter technology.
ZLine1 ZLine2
 
2 × PV rating R
IR,P V = IR,noP V − Z  √ (3)
3 × PV bus voltage I R0 ,noPV 3Rf
Zeq
(ZLine2 + Rf )
where Z  =
(Zeq + ZLine1 + ZLine2 + Rf )
When the ESS is also present in the system, we need to Z0Line1 Z0Line2
R
consider its fault current contribution also [42] for assessing
the reduction in the upstream relay current. Since the ESS I R0 ,noPV
Z0eq
also uses power electronic interface similar to PV, its fault
current contribution may also be approximated as 2 times its
rated current for conservative analysis. Furthermore, the ESS
acts as an active load when it is in charging mode and as (a)
a generator when it is in discharging mode. For conservative
protection studies, the ESS need to be acting as a generator
ZLine1 ZLine2
to contribute fault current. Therefore, it is considered as R
operating in discharge mode with 100% discharge rate to
ensure maximum fault current contribution. This additional Zeq I R1, PV
fault current contribution from ESS results in further reduction f
I PV 1
in the relay reach. Then (2) can be modified as: Vsg

IR,P V +ESS = IR,noP V − Z (IPf V + f
IESS )
f
where IESS is the fault current contribution from the ESS. ZLine1 ZLine2

It is observed from Z  that the maximum reach reduction R


occurs when ZLine2 is maximum i.e., when the PV or ESS is I R 2, PV 3Rf
installed close to the substation and the fault is located at the Zeq f
I PV 2
remote end. Under this condition, if the grid impedance Zeq
is neglected as it is typically much smaller than the feeder
impedance, then Z  = 1. This implies that the reduction in Z0Line1 Z0Line2
phase overcurrent relay current is exactly equal to the fault R
current injection from the PV or ESS.
I R 0, PV
2) Analysis for unsymmetrical faults: When the fault at the Z0eq I PVf 0
remote end of the feeder is single-line to ground (SLG), the
analysis can be done using sequence networks. The sequence
network diagrams of the distribution system without PV and (b)
with PV during the fault are shown in Fig. 8(a) and Fig.
8(b), respectively. The relay ‘R’ at the substation is considered Fig. 8. Distribution system with SLG fault a) without PV and b) with PV.
as ground overcurrent relay for unsymmetrical fault analysis.
Noting that the positive and negative sequence impedances
of distribution lines are equal, corresponding impedances of 0
where ZT S = 2(ZLine1 + ZLine2 ) + (ZLine1 0
+ ZLine2 )+
feeder sections upstream and downstream of the PV location 0
(2Zeq + Zeq ) + 3Rf
are denoted as ZLine1 and ZLine2 respectively in the figure.
Zero sequence impedances of the feeder sections are denoted The fault current through the relay at the substation is three
0
by ZLine1 0
and ZLine2 . times the zero sequence current
When the large-scale PV is not connected, from Fig. 8(a), 3Vsg
IRN,noP V = (4)
the positive, negative and zero sequence currents through the ZT S
relay are all equal and are given by: where ‘N ’ denotes the neutral.
0 Vsg When the PV is connected, the sequence components of the
IR,noP V =
ZT S PV current injections during the SLG fault condition can be

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

3Vsg IP V 0
IRN,P V = − [2ZLine2 + ZLine2 + 3Rf
ZT S ZT S
f
I PVc I PVc − 3(ZLine1 + Zeq )]

IRN,P V = IRN,noP V − Z  × IP V (8)


I PVa I f
2 I PVa 1
PVa
where Z  = 0
[2ZLine2 +ZLine2 +3Rf −3(ZLine1 +Zeq )].
ZT S
f
I PVb I PVb

In terms of PV rating, (8) may be expressed as


 
PV rating
Fig. 9. Fault current injections by PV systems for maximum unbalance during IRN,P V = IRN,noP V − Z  √ (9)
the SLG fault. 3 × PV bus voltage

Considering maximum PV unbalance, the maximum reduc-


computed as: tion in ground fault current seen by the relay due to the
[IPf V ]012 = [A]−1 [IPf V ]abc presence of PV is given by (8). It indicates that the ground fault
⎡ ⎤ current reduction depends on PV rated current (PV size), fault
1 1 1 resistance, PV location and available short-circuit capacity at
where [A] = ⎣1 a2 a ⎦ and a = 1∠120◦ . the substation. For the worst case scenario, PV is installed
1 a a2 close to the substation and SLG fault occurs at feeder’s remote
For SLG faults, it is expected that the ground overcurrent end resulting in maximum ground fault current reduction.
relay senses the ground fault current which is three times the
zero sequence current and trips. The zero sequence current From the parameters of Z  , it is observed that the maximum
through the relay can be computed by applying superposition reach reduction occurs when ZLine2 is maximum i.e., when
in Fig. 8(b) for each source Vsg , IPf V 1 , IPf V 2 , IPf V 0 and then the PV is installed close to the substation and the fault is at
adding the zero sequence currents resulting by each of these remote end. Under this condition, if Zeq is neglected, then
sources. The zero sequence current through the relay is: Z  = 1. This implies that the reduction in ground overcurrent
0 1  relay current is exactly equal to the rated PV current which is
IR,P V = Vsg + (Zeq + ZLine1 ) IPf V 1 less than PV fault current contribution. As such, the reduction
ZT S
in ground fault current seen by feeder head-end relay is less
+ (Zeq + ZLine1 ) IPf V 2 − (2ZLine1 + 2ZLine2 (5)

than the phase overcurrent relay current reduction in case of
0
+ZLine2 + 2Zeq + 3Rf IPf V 0 three-phase faults.

For the worst case scenario, the maximum unbalance is When the ESS is also present, analysis can be done along
considered in the large-scale PV fault current injections i.e., it the same lines and the ground fault current seen by the
is assumed that the PV is injecting 2 times the rated current upstream relay can be obtained from (8) as
(IP V ) in the faulted phase and rated currents in the healthy
phases as shown in Fig. 9. IRN,P V +ESS = IRN,noP V − Z  (IP V + IESS ) (10)
The sequence components of fault currents injected by the
PV for maximum unbalance is given by: For conservative estimation, (10) considers that both ESS
⎡ ⎤ ⎡ ⎤ and PV fault currents are in phase with each other. Then, the
2IP V a IP V ∠0◦
1
[IPf V ]012 = [A]−1 ⎣ IP V b ⎦ = ⎣4IP V ∠0◦ ⎦ (6) PV rating in (9) includes both PV and ESS ratings.
3
IP V c IP V ∠0◦
Sometimes the phase overcurrent relays alone are used for
From (5) and (6), the zero sequence current through the protection against all types of faults [43]. As such, we are
relay for maximum unbalance is given by: also interested in determining the reduction of fault current
Vsg IP V 0
seen by the phase overcurrent relay installed at the substation
IR0,P V = − [2ZLine2 + ZLine2 + 3Rf due to the ground fault current injections by the PV and ESS
ZT S 3ZT S (7)
− 3(ZLine1 + Zeq )] during remote end SLG fault. The fault current seen by phase
overcurrent relay in the presence of large-scale PV can be
The ground fault current seen by the relay is three times computed by applying superposition in Fig. 8(b) for each
the zero sequence current: source Vsg , IPf V 1 , IPf V 2 , IPf V 0 and by adding the resulting
currents to determine the current flowing through the relay
IRN,P V = 3IR0,P V in each sequence network IR1,P V , IR2,P V , IR0,P V . Then the

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

fault current through the relay is


IR,P V = IR1,P V + IR2,P V + IR0,P V PV
PV

1 0 0
= IR,noP V − (−ZLine1 + 2ZLine2 + ZLine1 + ZLine2 Vsg Feeder 1
IfPV
ZT S Zeq
0 R
−Zeq + Zeq + 3Rf )(IPf V 1 + IPf V 2 ) + (2ZLine1 + 2ZLine2

Ifgrid
0 0 0
−2ZLine1 + ZLine2 + 2Zeq − 2Zeq + 3Rf )IPf V 0 Fault

(11)
Feeder 2
Rf
When the maximum unbalance is considered, from (6) and
(11) we can determine the maximum reduction in this fault
current as:
(a)
IR,P V = IR,noP V − Z  × IP V (12)
Zeq
1
where Z  = 0
[4ZLine2 ++ZLine1 0
2ZLine2 0
+Zeq +6Rf − R
ZT S
(ZLine1 + Zeq )]
Ifau lt,3φ IR=-IfPV
Ifgrid
The above equation indicates that the ground fault current
contribution of the large-scale PV during the SLG fault Rf IfPV
downstream causes reduction in the fault current seen by the Vsg
upstream phase overcurrent relay also. The above analysis can
be extended to include the impact of ESS also as
IR,P V +ESS = IR,noP V − Z  (IP V + IESS ) (13) (b)
In (13), fault current injection of ESS is considered as Fig. 10. Distribution system with three-phase fault a) without PV and b) with
in phase with the PV fault current injection for maximum PV.
reduction. In terms of the PV and ESS ratings, (13) can be
expressed as
study. Considering the PV and ESS fault current contributions
(PV + ESS) rating are in phase for conservative estimation, the fault current seen

|IR,P V +ESS | = IR,noP V − Z × √
3 × PV bus voltage by relay becomes |IR | = |IPf V + IESS
f
| and the PV rating in
(14) (15) includes ESS rating also.
B. Sympathetic Tripping 2) Analysis for unsymmetrical faults: In case of SLG faults,
the ground overcurrent relay of the feeder shall detect the
To analyze the sympathetic tripping, consider the system
ground fault current and trip. The ground fault current or
shown in Fig. 10(a) where a large-scale PV system is installed
residual current through the relay is the sum of the fault
in Feeder 1 and a three-phase fault is assumed on adjacent
currents being injected by the PV system in all the three phases
Feeder 2. Its equivalent circuit is shown in Fig. 10(b). During
and can be expressed as:
the fault, the PV system feeds the fault back through the relay
‘R’ at the substation. IRN,P V = −(IPf V a + IPf V b + IPf V c ) = −3IPf V 0 (16)
1) Analysis for symmetrical faults: From Fig. 10(b), the From (6) and (16), the current seen by the ground overcur-
fault current through the relay in Feeder 1 is rent relay under maximum unbalance condition is |IRN,P V | =
IR = −IPf V |IP V |. In terms of PV rating, this can be expressed as

PV rating
It indicates that the current through the relay solely depends |IRN,P V | = |IP V | = √ (17)
on the fault current from the large-scale PV system and flows 3 × PV bus voltage
in the reverse direction. Therefore, as the PV size increases, When the ESS is also present, the total ground fault current
its fault current contribution also increases and eventually trips through the relay would be vectorial sum of both the ground
the relay when the fault current contribution from the PV goes fault currents from the PV and the ESS which is given by
above the phase overcurrent relay pickup current setting.
IRN,P V +ESS = − (IPf V a + IPf V b + IPf V c )
Considering that IPf V is twice the IP V for the conservative
f f f
study, the magnitude of fault current flowing through the relay − (IESSa + IESSb + IESSc ) (18)
can be expressed in terms of the PV rating as: =− 3(IPf V 0 + f
IESS0 )

2 × PV rating
|IR | = |IPf V | = √ where IPf V 0 and IESS0
f
(15) are the zero sequence current injec-
3 × PV bus voltage tions from PV and ESS respectively.
If the ESS is also present in the system, we need to consider For conservative estimation, the ESS fault current injection
its fault current contribution also for the sympathetic tripping would be in phase with PV fault current. Then the PV rating

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

10

TABLE I
S EQUENCE IMPEDANCES OF DIFFERENT S ECTIONS OF THE UTILITY Vsg Bus 1 Bus 2 Bus 3
DISTRIBUTION FEEDER Zeq, Z0eq ZLine 1, Z0Line 1 ZLine 2, Z0Line 2
Fault
R
Feeder Section Sequence Impedance (Ω) IR,PV+ESS Rf
IfPV IfESS
Zeq = 0.1016∠72.4◦
Substation
0 = 0.312∠74.1◦
Zeq PV
PV ESS
PV
ZLine1 = 1.389∠55.4◦
Upstream of PV & ESS
0
ZLine1 = 2.193∠55.56◦
Fig. 11. Single-line diagram of utility distribution feeder with fault.
ZLine2 = 0.538∠59.45◦
Downstream of PV & ESS
0
ZLine2 = 1.678∠60.97◦
3 times the maximum steady-state load current is used [46].
In this study, pickup current of 1500 A is used for the phase
overcurrent relay which is 2.05 p.u. of maximum steady-state
in (17) gives combined PV and ESS rating.
load current in the circuit (730 A). For ground overcurrent
relays, pickup current need to be above the maximum expected
V. VALIDATION OF R ELAY R EACH AND S YMPATHETIC
unbalance current in the circuit. For most feeders, the ground
T RIPPING USING U TILITY D ISTRIBUTION F EEDER M ODEL
relays are set with a pickup range from 25% to 50% of the
The analysis presented in the previous section is validated phase relay pickup [46]. In this study, 750 A is chosen as
through the simulation studies on a utility distribution feeder pickup current setting for the ground overcurrent relay which
model in OpenDSS. The generator and storage objects avail- is 0.5 p.u. of the phase relay pickup setting.
able in the OpenDSS model library are used for simulating PV b) The PV and ESS are connected to a bus approximately 0.83
and ESS respectively. A common approach to model inverters mi away from the substation (Bus 2) and the fault is simulated
for a fault study is to assume inverters behave like synchronous at the remote bus (Bus 3) as shown in Fig. 11.
generators during faults. The transient reactance Xd then c) Although loading condition does not have much impact
can be adjusted to obtain desired fault current output like a on short-circuit studies, more current from PV fault current
PV inverter [44]. The generator model (model 7) available injection is available when the load is minimum. Therefore,
in OpenDSS is useful for this purpose to approximate the minimum loading condition is considered for conservative
nominal behavior of the inverter based DG systems [45]. study.
For simulating PV fault current behavior two times its rated
current, the ‘xdp’ parameter of the generator model (model 7) B. Reduction of Relay Reach
is adjusted to 0.5.
The utility distribution feeder model is simulated initially
with a bolted three-phase fault at bus 3 without the large-scale
A. System Description PV and ESS in the system. The fault resistance is increased
For simulation studies, a detailed distribution circuit model and the phase-A current through the relay at the substation
has been developed in OpenDSS using the data obtained is monitored. Next, a large-scale PV system is connected to
from a utility. The data comprises of transformer, line data, bus 2 and the study is repeated. The fault current profiles seen
load profiles, capacitors, regulator data etc. The system has by the phase overcurrent relay for varied fault resistance as
a 24 MVA transformer at the substation. The three-phase the PV size is increased from 1 MW to 8 MW are shown in
and single-phase short-circuit MVA of transmission system Fig. 12. It is observed that when the PV is not connected, the
upstream of the substation transformer are 562 MVA and 93 relay at the substation is insensitive to the three-phase faults
MVA respectively. A 1.6 mi long 12.47 kV level primary with Rf > 3.8 Ω. In other words, the phase overcurrent relay
distribution feeder is supplied by this transformer. Maximum cannot detect the three-phase remote end faults having fault
loading in the feeder is 15.77 MW and the corresponding load resistance higher than 3.8 Ω. The relay is blind to the fact that
current is 730 A. Minimum loading is 6 MW. This detailed a fault is present in the system. As the PV size is increased, the
distribution model is used for simulations. corresponding PV fault current contribution IPf V is increased
Fig. 11 shows the single-line diagram of the distribu- resulting in relay insensitivity at lower fault resistances. For
tion system used for theoretical calculations. The sequence the large-scale PV size of 8 MW, the phase overcurrent relay is
impedances of the system are obtained from the short-circuit insensitive to the remote end three-phase fault with resistance
study which are given in the Table I. above 2.5 Ω. This means, if the relay at the substation is set
Following are the circuit conditions considered for this to detect a 3.8 Ω fault resistance considering no PV in the
study: system, the relay fails to perform its intended operation due
a) The breaker installed at the feeder head is controlled by to the presence of PV.
both phase and ground overcurrent relays. The pickup current The simulation results can be compared with theoretical
setting for the phase overcurrent relay should be above the relay currents predicted using (2) to validate the analysis.
maximum cold load pickup current in the feeder and below The pre-fault voltage of bus 3 is obtained from the load
the minimum fault current. Typically, a pickup value of 1.5 to flow program as Vsg = 7279∠ − 33.7◦ V. Using the system

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

11

Phase-A fault current seen by relay (A)


4000

3000
No PV
No PV
PV = 1 MW PV = 1 MW &
PV = 1 MW
2000 ESS = 3 MW
Ip = 1500 A
Ip = 1500 A
1000 IfPV = 63 A
Rf = 2.5 Ω Rf = 3.8 Ω Rf = 3.1 Ω Rf = 3.6 Ω IfESS = 179.6 A
PV = 8 MW
0
0 2 4 6 8 10
Fault resistance Rf (Ω)

Fig. 12. Fault current seen by phase overcurrent relay with large-scale PV
and varied remote end three-phase fault resistance using circuit simulations.
Fig. 14. Fault current seen by phase overcurrent relay installed at the
substation for various PV ratings and three-phase fault resistance.

in the previous case. When the 1 MW PV is connected, the


relay is insensitive to the three-phase faults with Rf > 3.6 Ω
No PV
due to the fault current injection of IPf V = 63 A by the
PV = 1 MW PV. And when the 3 MW ESS is also connected, the relay
insensitivity occurs at further lower value of Rf > 3.1 Ω due
f
Ip = 1500 A to the additional fault current contribution of IESS = 179.6 A
by the ESS. The results show that the effect of ESS is similar
Rf = 2.5 Ω Rf = 3.5 Ω
to that of the large-scale PV for protection studies. As such,
PV = 8 MW
the ESS of higher ratings can reduce the overcurrent seen by
the upstream phase overcurrent relays and can interfere with
the feeder overcurrent protection.
Fig. 13. Predicted current seen by relay for various PV ratings and Rf using The impact of ground fault current contribution from the
(19). large-scale PV on the fault current seen by the ground overcur-
rent relay can be predicted using (9) for the system parameters
in Table I. The predicted ground overcurrent results when the
parameters given in Table I, (2) can be written in terms of the large-scale PV ratings are 1 MW and 8 MW are shown in
PV rating as Fig. 15. For ease of comparison, the ground overcurrent results
7279∠ − 33.7◦ obtained from the SLG fault simulation using the detailed
IR,P V = distribution system model are also shown on the same figure.
(2.024∠57.32◦ + Rf )
  (19) From both theoretical predictions and simulation results, it is
(0.538∠59.45◦ + Rf ) 2 × PV rating
− √ observed that the reduction in the ground fault current seen
(2.024∠57.32◦ + Rf ) 3 × 12.47 kV by the upstream relay increases as the large-scale PV size
Fig. 13 shows the predicted fault currents seen by phase increases. Note that (9) gives most conservative predictions
overcurrent relay at the substation using (19) for various by considering maximum unbalance in the PV fault current
PV ratings and Rf . The theoretical predictions shown in injection. It is observed that the error between the predicted
Fig. 13 closely match with the results obtained using circuit and simulated fault current results in the region of interest
simulations shown in the Fig. 12, confirming the validity of the where the relay insenstivity of ground overcurrent relay occurs
analysis. In particular, the PV size to cause relay insensitivity that is at Rf = 7 Ω is very less which validates the analysis.
for a remote end three-phase fault resistance of Rf = 2.5 Ω When the ESS is also connected, its fault current contribu-
is 8 MW in both the figures. tion causes more reduction in the fault currents seen by the
The impact of ESS on the fault current seen by the upstream phase and ground overcurrent relays. Fig. 16 shows the fault
phase overcurrent relay is studied by connecting a three-phase current seen by phase overcurrent relay at the substation when
ESS of rating 3 MW to bus 2 along with the large-scale PV there is no PV, when 1 MW PV connected to bus 2 (three
of rating 1 MW. The variation of fault currents seen by the single-phase PV rated 333 kW, unity power factor each), and
phase overcurrent relay when there is no PV, when the PV is when both 1 MW PV and 3 MW ESS (three single-phase ESS
connected to bus 2, and when both PV and ESS are connected rated 1 MW each). These results are obtained from distribution
to bus 2 is shown in Fig. 14. It is observed that when the circuit simulations. The results confirm that both large-scale
large-scale PV is not connected, the phase overcurrent relay PV and ESS cause reduction in the fault currents seen by
is insensitive to the three-phase faults with Rf > 3.8 Ω as phase overcurrent relays located upstream for the SLG fault

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

12

Ground fault current seen by relay (A) 3000


Predicted
No PV
2500 Simulated
8 MW PV Error
2000
1500
1000 Ipn = 750 A Ip = 1500 A

500 Rf = 7 Ω
0 0 1 2 3 4 5 6 7 8 9 10
Fault resistance Rf (Ω)

Fig. 15. Comparison of predicted ground fault current seen by relay using
(8) and simulated values without PV and with 8 MW PV for varied Rf .
Fig. 17. Locational impact of large-scale PV systems.
Phase-A fault current seen by relay (A)

PV
3000
Vsg
Zeq IfPV
2500 No PV R
IfESS
2000 1 MW PV, No ESS
ESS
PV
1500 I = 1500 A
p

1000
1 MW PV, 3 MW ESS
500 Fault
0
0 1 2 3 4 5 6 7 8 9 10 Adjacent feeder
Fault resistance Rf (Ω)

Fig. 18. Utility distribution system with adjacent feeder.


Fig. 16. Simulation results of impact of PV and ESS on the fault current
seen by the phase overcurrent relay.
from 1 to 24, that is total size of large-scale PV systems
is varied from 500 kW to 12000 kW. Twenty scenarios are
downstream of the PV and ESS. Reduction in the ground
considered for each 500 kW step increment of PV size, with
fault current is observed in case of SLG fault. However, the
the locations of the PVs varied stochastically among the four
reduction in the ground fault current due to the presence of
chosen PV locations [18] in each scenario. A three-phase
PV and ESS is less as compared to the reduction in the phase
fault with resistance Rf = 2.5 Ω is simulated at the end of
overcurrent due to the reasons discussed in Section II.
the feeder at bus 3 and the fault current at the substation is
The analysis provided in Section IV considers a single large-
recorded for each scenario. The results are shown in Fig. 17 as
scale PV connected at middle of the feeder. The large-scale PV
a scatter plot wherein each point correspond to one scenario.
systems behave like current sources, particularly during fault
It is observed that for a three-phase fault with resistance
conditions. They inject fault currents of magnitude determined
Rf = 2.5 Ω, the feeder can host about 8 MW of large-scale PV
by their inverters into the system. As such, the locations
with relay insensitivity as impact criteria. As can be seen in the
of the large-scale PV systems generally do not have much
figure, the impact of different locations for a given step size is
influence on the relay insensitivity. Therefore, a set of few
less, therefore analysis for the conservative PV location (that
large-scale PV systems can be approximated as a single large-
is close to substation) would provide an approximate estimate
scale PV system of size totaling their individual ratings located
of the feeder accommodation limit.
anywhere on the primary feeder. As mentioned earlier, for
conservative protection study, the single equivalent large-scale
PV can be placed close to the substation and fault can be C. Sympathetic Tripping with PV and ESS
considered at the end of the feeder. Fig. 18 shows the single-line diagram of the utility distri-
To demonstrate the influence of PV locations, four locations bution feeder including an adjacent feeder. In the OpenDSS,
along the feeder are chosen for PV deployment. The locations the adjacent feeder is modeled as an aggregated load equal to
are at substation, mid-feeder and at two feeder ends. The the yearly demand of the main feeder which is 4726 kW.
PV systems are of three-phase and rated 500 kW each. The For sympathetic tripping simulation study, initially a large-
number of PV systems installed in the system is increased scale PV system is connected to the bus 1 and a bolted three-

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

13

Phase-A fault current seen by relay (A)

Ground fault current seen by relay (A)


2000
14.4 MW 1000
Ip = 1500 A 14.8 MW
1500 f 800 Ipn = 750 A
I a,ESS
16.2 MW IRN,PV+ESS
IfPVa =Ifa,noESS 16.2 MW
1000 600
IRN,PV
400
IfESSa IfESSn
500
200
00 2 4 6 8 10 12 14 16 18 20 00 2 4 6 8 10 12 14 16 18 20
PV rating (MW) PV rating (MW)

Fig. 20. Fault current seen by ground overcurrent relay as the PV size is
Fig. 19. Fault current seen by phase overcurrent relay without and with ESS increased.
as the PV size is increased.

It is observed that as the PV size is increasing, its ground


phase fault is simulated at a bus on adjacent feeder. Both the fault current contribution is also increasing, going above the
buses are closest to the substation on the respective feeders. ground overcurrent pickup value of 750 A at a PV size of
Fig. 19 shows the fault current through the phase overcurrent 16.2 MW. At this point, the feeder currents in all the three
relay as the large-scale PV size is increased from 0 MW phases are Iaf = 1500.3∠ − 24.5◦ A, Ibf = 848.49∠40.4◦ A
to 20 MW. The figure also shows the effect of ESS on the and Icf = 889.76∠ − 88.7◦ A and the residual current seen
relay fault current. It is observed that, when the ESS is not by the relay is IRN,P V = Iaf + Ibf + Icf = 753.83∠ − 22◦ A.
connected, the fault current through the phase overcurrent The large-scale PV rating to cause sympathetic tripping can
relay is increased as the PV size is increased and reached be estimated from (17), i.e., 16.2 MW.
the pickup value of 1500 A at 16.2 MW of PV size. The fault Fig. 20 also shows the simulation results when three single-
current in the phase-A of the feeder at this point is noted as phase ESS of 1 MW rating each are also connected to bus
f
Ia,noESS = IPf V a = 1500.2∠153.2◦ A. The large-scale PV 1. It can be observed that the sympathetic tripping now
size for causing sympathetic tripping can also be estimated occurs at a large-scale PV size of 14.8 MW which is lower
from (15), i.e., 16.2 MW. than the previous case due to the additional fault current
When the ESS is also connected, it would also inject fault contribution from the ESS. When the ground fault current
current more than its rated current during the fault conditions. through the feeder goes above the pickup value, the ground
The effect of the fault current contribution from the ESS is fault current contributions from the PV and the ESS are
studied by connecting an ESS of size 3 MW to bus 1 along IPf V n = 718∠ − 16.8◦ A and IESSn f
= 226.1∠ − 111.46◦
with the large-scale PV. The simulation results are shown in A respectively. The residual current seen by the relay is
Fig. 19. When the ESS is also connected to the system along IRN,P V +ESS = Iaf + Ibf + Icf = 751∠ − 39◦ A. The PV
with PV, it is observed that the sympathetic tripping occurs at and ESS combined size in the simulation for the sympathetic
14.4 MW of large-scale PV rating which is less compared to tripping is 17.8 MW. The PV and ESS size conservative
the case without ESS. This is due to the additional fault current estimate from (17) is 16.2 MW. The conservative estimate
contribution from the ESS. At this point, total 17.4 MW of PV is slightly lower than the simulated result because the ground
and ESS present in the system. The fault current contributions fault current injections by the PV and ESS are out of phase.
from the large-scale PV and the ESS in the phase-A are noted However, the deviation of estimated PV and ESS size from
as: IPf V a = 1333.4∠155.9◦ A and IESSa
f
= 321.03∠92.2◦ A the simulated size in this case is less than 7%.
respectively. The fault current in the phase-A of the feeder is
Iaf = IPf V a + IESSa
f
= 1503.6∠ − 35.1◦ A. We can make a
conservative estimate of the combined PV and ESS rating for VI. C ONCLUSIONS AND D ISCUSSION
the possibility of sympathetic tripping using (15) also which In this paper, comprehensive analysis of relay insensitivity
is 16.2 MW. Note that the conservative estimate of the PV and sympathetic tripping problems in a distribution system is
and ESS rating for the likelihood of sympathetic tripping is provided with an aim to conservatively estimate the large-scale
slightly lower than the simulated result. This is due to the fact PV and ESS accommodation limits of a utility distribution
that the fault current injections from the PV and the ESS in feeder. Based on the analysis, the factors influencing the im-
the simulation are out of phase. pact of large-scale PV and ESS on the overcurrent protection
The sympathetic tripping study of the utility feeder for schemes are discussed. The proposed analysis-based approach
unsymmetrical faults is done by simulating an SLG fault on the is scalable and thus can be applied to large distribution circuits
adjacent feeder as shown in Fig.18. The ground fault current also. The analytical results are validated by simulation studies
seen by the ground overcurrent relay is shown in Fig. 20 using a detailed distribution circuit model of a utility in
as the large-scale PV size is increased from 0 to 20 MW. OpenDSS.

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

14

Normally, in addition to the breaker at the substation, [11] T. Sidhu and D. Bejmert, “Short-circuit current contribution from large
the distribution circuits can have few reclosers placed along scale PV power plant in the context of distribution power system protec-
tion performance,” in IET Conference on Renewable Power Generation,
the feeder. In such cases, the expected fault current can Sept 2011, pp. 1–6.
be computed at each recloser using the proposed method. [12] M. E. Baran and I. El-Markaby, “Fault analysis on distribution feeders
Once we have the expected fault currents with large-scale with distributed generators,” IEEE Transactions on Power Systems,
vol. 20, no. 4, pp. 1757–1764, Nov 2005.
PV and ESS, the possibility of relay/recloser insensitivity can [13] S. Essakiappan et al., “A utility scale battery energy storage system
be checked quickly by comparing with the pickup current for intermittency mitigation in multilevel medium voltage photovoltaic
setting. Based on the expected fault currents and pickup system,” in Energy Conversion Congress and Exposition (ECCE), 2015
IEEE, Sept 2015, pp. 54–61.
current settings of the breaker and the reclosers, the possibility
[14] A. Barnes, J. Balda, A. Escobar-Mejia, and S. Geurin, “Placement of
of miscoordination problems can also be studied. Note that energy storage coordinated with smart PV inverters,” in IEEE Innovative
protection device miscoordination is not in the scope of this Smart Grid Technologies, Jan 2012, pp. 1–7.
study. [15] G. Huff, “DOE global energy storage database.” Sandia National Labora-
tories (SNL-NM), Albuquerque, NM (United States), Tech. Rep., 2015.
In case of sympathetic tripping, the reclosers play a limited [16] I. Gyuk et al., “Grid energy storage,” U.S. Department of Energy, Tech.
role as faults beyond the reclosers do not create sympathetic Rep., 2013.
tripping. When the faults are beyond the reclosers, usually [17] W. S. Moon, J. N. Won, J. S. Huh, and J. C. Kim, “A study on
the application of a superconducting fault current limiter for energy
the reclosers perform reclosing operations when the fault is storage protection in a power distribution system,” IEEE Transactions
detected in their protected zone creating momentary outages on Applied Superconductivity, vol. 23, no. 3, p. 5603404, June 2013.
or nuisance tripping. Relay in the faulted feeder clears the [18] A. Dubey, S. Santoso, and A. Maitra, “Understanding photovoltaic
hosting capacity of distribution circuits,” in IEEE Power Energy Society
fault before these reclosing operations finish and sympathetic General Meeting, July 2015, pp. 1–5.
tripping happen. Sympathetic tripping is a severe problem [19] D. V. Tu, S. Chaitusaney, and A. Yokoyama, “Maximum-allowable
compared to nuisance tripping or momentary outages as it distributed generation considering fault ride-through requirement and
results in permanent outage of a complete feeder. reach reduction of utility relay,” IEEE Transactions on Power Delivery,
vol. 29, no. 2, pp. 534–541, April 2014.
[20] J. Seuss, M. J. Reno, R. J. Broderick, and S. Grijalva, “Maximum PV
size limited by the impact to distribution protection,” in IEEE 42nd
ACKNOWLEDGMENT Photovoltaic Specialist Conference, 2015, pp. 1–6.
[21] B. Mather et al., “Southern California Edison high-penetration photo-
The work was supported in part by Electric Power Research voltaic project–year 1,” Tech. Rep., 2011.
Institute, the National Science Foundation Industry/University [22] A. Hoke, R. B. J. Hambrick, and B. Kroposki, “Maximum photovoltaic
Cooperative Research Center on Next Generation Photo- penetration levels on typical distribution feeders,” Tech. Rep., 2012.
[Online]. Available: http://www.nrel.gov/docs/fy12osti/55094.pdf
voltaics (IIP−1134849 and IIP−1540028), and the Colombian [23] M. J. Reno, K. Coogan, R. Broderick, and S. Grijalva, “Reduction of
Department of Science, Technology and Innovation (Colcien- distribution feeders for simplified PV impact studies,” in IEEE 39th
cias) in cooperation with Universidad de los Andes. Photovoltaic Specialists Conference, June 2013, pp. 2337–2342.
[24] V. Scaini, “Whitepaper: Grid support stability for reliable, renewable
power,” Eaton Corporation, 2012.
[25] H. L. Willis, Power distribution planning reference book. CRC press,
R EFERENCES 2004.
[26] T. Gonen, Electric Power Distribution Engineering. CRC press, 2014.
[1] D. Feldman, G. L. Barbose, R. Margolis, and T. James, “Photovoltaic
(PV) pricing trends: Historical, recent, and near-term projections,” [27] “Distribution system feeder overcurrent protection.” [Online]. Available:
National Renewable Energy Laboratory, Tech. Rep., November 2012. http://www.geindustrial.com/publibrary
[2] B. Tsuchida, S. Sergici, B. Mudge, W. Gorman, P. Fox-Penner, [28] M. H. Bollen and F. Hassan, Integration of distributed generation in the
and J. Schoene, “Comparative generation costs of utility-scale and power system. John wiley & sons, 2011, vol. 80.
residential-scale PV in Xcel Energy Colorado’s service area,” Tech. Rep., [29] R. Jafari, M. Naderi, G. Gharehpetian, and N. Moaddabi, “Compensation
2015. of DGs impact on overcurrent protection system of smart micro-grids,”
[3] J. Bank, B. Mather, J. Keller, and M. Coddington, “High penetration in 22nd Int. Conf. and Exhibition on Electricity Distribution, June 2013.
photovoltaic case study report,” National Renewable Energy Laboratory, [30] M. Baran, H. Hooshyar, Z. Shen, and A. Huang, “Accommodating high
Tech. Rep., November 2013. PV penetration on distribution feeders,” IEEE Transactions on Smart
[4] P. Chiradeja and R. Ramakumar, “An approach to quantify the tech- Grid, vol. 3, no. 2, pp. 1039–1046, June 2012.
nical benefits of distributed generation,” IEEE Transactions on Energy [31] H. Hooshyar, M. Baran, and L. Vanfretti, “Coordination assessment of
Conversion, vol. 19, no. 4, pp. 764–773, Dec 2004. overcurrent relays in distribution feeders with high penetration of PV
[5] R. A. R. Walling, R. Saint, S. Member, R. C. Dugan, J. Burke, and L. A. systems,” in IEEE PowerTech, June 2013, pp. 1–6.
Kojovic, “Summary of distributed resources impact on power delivery [32] V. A. Papaspiliotopoulos, V. A. Kleftakis, P. C. Kotsampopoulos, G. N.
systems,” vol. 23, no. 3, pp. 1636–1644, 2008. Korres, and N. D. Hatziargyriou, “Hardware-in-the-loop simulation of
[6] “IEEE guide for conducting distribution impact studies for distributed protection blinding and sympathetic tripping phenomena in modern
resource interconnection,” IEEE Std 1547.7-2013, pp. 1–137, Feb 2014. distribution grids,” ENERGY, vol. 2012, pp. 1–1.
[7] H. Yazdanpanahi, W. Xu, and Y. W. Li, “A novel fault current control [33] G. Bernardi and J. de Carvalho Filho, “High-resistance neutral grounding
scheme to reduce synchronous DG’s impact on protection coordination,” in industrial systems and the ground fault protection,” in 2013 Brazilian
IEEE Trans. on Power Delivery, vol. 29, no. 2, pp. 542–551, April 2014. Power Electronics Conference, Oct 2013, pp. 1276–1282.
[8] H. Yazdanpanahi and W. Xu, “Contribution of induction-machine [34] H. Ravindra, M. Faruque, P. McLaren, K. Schoder, M. Steurer, and
distributed generators to fault current and assessing their impact on R. Meeker, “Impact of PV on distribution protection system,” in North
overcurrent protection,” in 26th Annual IEEE Canadian Conference on American Power Symposium, Sept 2012, pp. 1–6.
Electrical and Computer Engineering, May 2013, pp. 1–4. [35] M. McGranaghan, T. Ortmeyer, D. Crudele, T. Key, J. Smith, and
[9] S. Bhattacharya, T. Saha, and M. J. Hossain, “Fault current contribution P. Barker, “Renewable systems interconnection study: Advanced grid
from photovoltaic systems in residential power networks,” in IEEE planning and operations,” Sandia National Laboratories, 2008.
Australasian Universities Power Engg Conf., 2013, pp. 1–6. [36] R. Meeker et al., “High penetration solar PV deployment Sunshine
[10] J. Keller and B. Kroposki, “Understanding fault characteristics of state solar grid initiative (SUNGRIN),” Florida State University, Tech.
inverter-based distributed energy resources,” National Renewable Energy Rep., May 2015. [Online]. Available: http://www.caps.fsu.edu/pdfs/
Laboratory, Tech. Rep., January 2010. Final Report SUNGRIN 20160104.pdf

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
This article has been accepted for publication in a future issue of this journal, but has not been fully edited. Content may change prior to final publication. Citation information: DOI 10.1109/ACCESS.2016.2589545, IEEE Access

15

[37] D. Jones and J. Kumm, “Future distribution feeder protection using


directional overcurrent elements,” IEEE Transactions on Industry Ap-
plications, vol. 50, no. 2, pp. 1385–1390, March 2014.
[38] A. Sinclair, D. Finney, D. Martin, and P. Sharma, “Distance protection
in distribution systems: How it assists with integrating distributed
resources,” IEEE Transactions on Industry Applications, vol. 50, no. 3,
pp. 2186–2196, May 2014.
[39] P. Naik, M. Bahadornejad, N. Nair, and V. Vyatkin, “IEC 61850 based
smart distribution protection: Solutions for sympathetic tripping,” in
IEEE PES Innovative Smart Grid Tech. Asia, Nov 2011, pp. 1–7.
[40] R. Seguin et al., “High-penetration PV integration handbook for distri-
bution engineers,” National Renewable Energy Laboratory, Golden, CO
(United States), Tech. Rep., 2016.
[41] T. Seegers et al., “Impact of distributed resources on distribution relay
protection.”
[42] R. Hebner et al., “Energy storage on future electric ships,” ESRDC
report, March, 2008.
[43] C. R. Mason, The art and science of protective relaying. John Wiley
and Sons, 1967.
[44] R. J. Broderick, J. E. Quiroz, M. J. Reno, A. Ellis, J. Smith, and
R. Dugan, “Time series power flow analysis for distribution connected
PV generation,” Sandia National Laboratories, Tech. Rep., 2013.
[45] R. C. Dugan, “OpenDSS Manual.” [Online]. Available: http://smartgrid.
epri.com/SimulationTool.aspx
[46] “IEEE guide for protective relay applications to distribution lines,” IEEE
Std C37.230-2007, pp. 1–100, 2007.

2169-3536 (c) 2016 IEEE. Translations and content mining are permitted for academic research only. Personal use is also permitted, but republication/redistribution requires IEEE permission. See
View publication stats http://www.ieee.org/publications_standards/publications/rights/index.html for more information.

You might also like