TOOLING QUOTATION
Quotation Number: PQMX0414 RFQ141-20131007x-03
Customer Name: Marquardt
Date: 8/Oct/13
Customer Address: Mexico
Validity 30days.

Attention: Mr.Praveen P. Currency USD

Number of pages: 1

Tooling Lead-time
Picture Part Size(mm) Est. Cycle-Time- Insert Steel Mould Base
S/N Part Name Drawing Nos Plastic Resin No. Of Cav (Upon Tool Design Est.M/C Ton Tool Life Gate Type Tool Type Tool Cost (USD) Remarks
sec Mat'l Steel Mat'l
Approval)

ULTRAMID AB plate - S50C 4 slider per cav.


217.785.011- semi-
1 41 * 21.5 * 40 HOUSING 02
A3K BLACK 2 8 weeks 26 80 800K shots 1.2344 Other plates -
hotrunner
2-plate US$29,000.00 2 drops hot-runner
00464 S50C Moldmaster

ULTRAMID
AB plate - S50C
215.508.011- B3EG
2 31.65 * 14.8 * 30.59 BASE 02 BLACK
4 8 weeks 26 60-80 800K shots 1.2344 Other plates - sub gate 2-plate US$26,400.00 2 slider per cav.
S50C
00564

ULTRAMID AB plate - S50C


WORKING 190.535.011-
3 33.4 * 16.54 * 10.76 A3EG5 4 8 weeks 26 60-80 800K shots 1.2344 Other plates - sub-gate 2-plate US$24,500.00 2 * slider per cav.
ROCKER 04
NATURE S50C

HOSTAFOR AB plate - S50C


248.195.011-
4 30.4 * 13 * 11.25 STEERING 01
M C9021 SW 4 8 weeks 26 60-80 800K shots 1.2344 Other plates - sub-gate 2-plate US$24,500.00 2 * slider per cav.
BLACK S50C

POCAN KU AB plate - S50C


198.528.011-
5 10.5 * 7.57 * 8.15 SLIDE 03
2-7317 8 8 weeks 24 60-80 800K shots 1.2344 Other plates - sub-gate 2-plate US$18,100.00 base on no undercut
NATURE S50C

AB plate - S50C
ROCKER 190.533.031- MAKROLON
6 40.96 * 20.98 * 16.5 4 8 weeks 26 60-80 800K shots 1.2344 Other plates - sub-gate 2-plate US$22,000.00 2 * slider per cav.
PAINTED 02 2405
S50C

TOTAL US$144,500.00
Terms and Conditions:
1) Prices are quoted in USD

2) Payment term:
a) For New Tool
i) 50% upon receipt of Purchase Order/Confirmation as downpayment.
ii) 40% upon submission of 1st sample.
iii) 10% upon approval of sample prior for tool shipment.
b) Engineering Change
100% upon submission of sample
c) For Parts
100% upon parts receive
3) Credit term :
i) 7 days from date of invoice for downpayment.
ii) 14 days from date of invoice for final billing.
iii) L/C on sight prior to delivery of tool, subject to SPI Finance department approval.
4) Tool quoted price does not include spare insert
5) Tool quoted price does not include sample build.
6) Tool quoted price does not include shipping cost to production site.
7) Tool price quoted does not include raw material for testing and sample build purposes. Customer to provide.
8) Tool quoted price does not include making the measuring fixture.
9) Tool quoted price does not include sending engineer to production site for mould commissioning.
10) Tool price does not include special texturing cost, special texture cost to be advised and finalise upon project confirmation and design review.
11) Tool price quoted does not include hand carry sample to customer.
12) Tool price quoted does not include any air fright cost for part due to late delivery.
13) Tool price quoted does not include any cost incur for part rework.
14) Job shall commence upon receipt of downpayment.
15) Lead time is based upon receipt of Purchase Order or first payment, whichever is later.
16) Mode of payment: Telegraphic transfer. All payments should be made payable toSunningdale Precision Mold Industries(Tianjin)Co.,LTD.
17) An official written document is required if the job is cancelled during the construction of tools.
Marquardt needs to compensate for the costs incurred up to the date of cancellation.
18) If we are instructed to put on hold any job that is started for more than two weeks period, we reserved the right to treat the job as “cancelled” and act according to point 16.
19) Ownership of the good is transferred only upon the full payment received.
20) Cycle time & machine tonnage are base on calculation, subject to mold design and cosmetic packing during the actual testing.
21) Once tool buy-off approved, Sunningdale will not be responsible for any cost charged for line down caused during production.
22) Other terms: interest at 1.5% per month will be imposed on late payment.
23) Tool warranty: As quoted or 1 year, whichever is earlier.
24) Shipment term : Ex-factory,Sunningdale Tianjin - China

Jinghailong Customer's Acceptance


date: Date :