Signature of authorised person of Contractor / Signature of authorised person of pmc / Date : Signature of authorised person of Client / Date :
Date :
NAME OF THE CLIENT : ACCORD INFOTECH PRIVATE LIMITED
NAME OF THE PMC : CONSYNC INFRA PVT. LTD.
NAME OF THE CONTRACTOR : M/S S.M NIRMAN INFRASTRUCTURE & DEVELOPMENT PVT. LTD.
PROJECT : DN 50 , SALTLAKE
NAME OF THE CONTRACTOR : M/S S.M NIRMAN INFRASTRUCTURE & DEVELOPMENT PVT. LTD.
NAME OF THE CLIENT : ACCORD INFOTECH PRIVATE LIMITED NAME OF THE PMC : CONSYNC INFRA PVT. LTD.
11/13/2021 RA-25
As per BOQ Upto Previous Bill This Bill Cummulative Total
SL No. Description of work (SUPER- Structure) UNIT Rate
QTY Amt. Rs. QTY Amt. Rs. QTY Amt. Rs. QTY Amt. Rs.
All charges for providing, fabricating, erecting and fixing in position plained timber, plywood centering and shuttering true to
line and level, including making provision for cut out (plan area of cut out shall be paid as per provision of relevant IS code)
steel propping, staging of required height, shuttering removal, applying shuttering oil, including required bracing, chamfering
1 corners (of exposed edges) of beams, columns, walls, mullion post (if any) etc. complete to the entire satisfaction of
Sqm 306.00 28248.000 8643888.00 22085.165 6758060.51 331.744 101513.74 22416.909 6859574.25
PMC/Owner. Rate shall include removal and dismantling the aforesaid assembly after specified period complete at all levels
and leads for all items e.g. columns, beams, slabs, lintels, staircase, wall etc. of all profile coming above Plinth level.
All charges for providing & laying 1:3:6 plain cement concrete (PCC) of required thickness at all levels and leads coming
above Plinth level using 20 mm nominal size well-graded approved quality aggregate including vibrating / compacting,
2 scaffolding as required establishing dewatering system by pumping / bailing out water, cleaning, preparing surfaces, Cum 3630.00 50.000 181500.00 0.000 0.00 0.000 0.00 0.000 0.00
junctions etc. including shuttering, curing complete to the entire satisfaction of PMC/Owner. (cement/ RMC shall be supplied
All charges for laying M40 grade cement concrete/reinforced cement concrete (excluding cost of shuttering & reinforcement)
by the developer)
at all levels and leads for all items e.g. columns, beams, slabs, lintels, staircase, wall, pockets etc. of all profile coming above
Plinth level using 20 mm nominal size & down graded good quality aggregate as per design mix approved by PMC/Consultant
including vibrating / compacting, curing, scaffolding as required, dewatering (if any), cleaning, preparing surfaces, junctions
3 etc. including curing complete to the entire satisfaction of PMC/Owner. Cement concrete should have an ultimate crushing
strength of not less than 400 Kg/sq.cm on 15cm X 15cm X 15cm cube at 28 days and source of concrete will be RMC ( RMC
shall be supplied by the developer) Special conditions:-Rates are quoted for all levels & heights. For material/cube testing, the
contractor shall maintain QC lab, cube testing machine, sieves, slump cones, graduated cylinder, weight scales etc. in good
The rate shall include the cost of plasticiser / super plasticiser of an approved brand to get the required workability /
working condition cost of which shall be included in the rate.
3.01 strength. The column beam junctions shall be with the grade of concrete as in column up to a distance of depth of beam in Cum 600.00 4259.000 2555400.00 1218.9236 731354.17 5.899 3539.40 1224.823 734893.57
all directions & rate shall be inclusive of this.
All charges for laying M25 grade cement concrete/reinforced cement concrete (excluding cost of shuttering & reinforcement)
at all levels and leads for all items e.g. columns, beams, slabs, lintels, staircase, wall, pockets etc. of all profile coming above
Plinth level using 20 mm nominal size & down graded good quality aggregate as per design mix approved by PMC/Consultant
including vibrating / compacting, curing, scaffolding as required, dewatering (if any), cleaning, preparing surfaces, junctions
etc. including curing complete to the entire satisfaction of PMC/Owner. Cement concrete should have an ultimate crushing
strength of not less than 250 Kg/sq.cm on 15cm X 15cm X 15cm cube at 28 days and source of concrete will be RMC. ( RMC
shall be supplied by the developer) Special conditions:- Rates are quoted for all levels & heights. For material/cube testing, the
contractor shall maintain QC lab, cube testing machine, sieves, slump cones, graduated cylinder, weight scales etc. in good
working condition cost of which shall be included in the rate.
The rate shall include the cost of plasticiser / super plasticiser of an approved brand to get the required workability /
3.02 strength. The column beam junctions shall be with the grade of concrete as in column up to a distance of depth of beam in Cum 600.00 150.000 90000.00 2003.5912 1202154.75 12.585 7550.74 2016.176 1209705.49
all directions & rate shall be inclusive of this.
All charges for fixing & removal of scaffolding & gangway at peripheral area of building to the entire satisfaction of Post
4 tensioning agency/PMC/Owner to enable the post tensioning agency to stress the tendons at all levels. Payment will be made Cum 90.00 9600.000 864000.00 1703.014 153271.23 0.000 0.00 1703.014 153271.23
after full completion of post tensioning work.
All charges for providing, making & placing the chairs made with reinforcement bar for placement of tendons in required
5 profile at all level coming above Plinth level including transportation, decoiling, straightening, removing loose rust and No 12.00 9500 114000.00 5047.00 60564.00 0.000 0.00 5047.000 60564.00
binding with 18 gauge annealed wire to the entire satisfaction of PMC/Owner.
All charges for making structural inserts as per I.S. 2062, including supplying, fabricating, and installing in concrete coming
7 till Roof level with anchors in the form of rods or flats including necessary welding and applying one coat of zinc chromate MT 54000.00 0.500 27000.00 0.013 679.19 0.000 0.00 0.013 679.19
primer to the entire satisfaction of PMC/Owner.
All charges for fixing steel reinforcement (Tor Steel as per IS-1786, Fe 500) for RCC work including transporting, decoiling,
straightening, removing loose rust, cutting, bending and placing for all profile and for all lead & lift above Plinth level and
binding with 18 gauge annealed wire to the entire satisfaction of PMC/Owner. Payment of steel shall be made as per drawing
8 and approved bar bending schedule with permissible laps and paid on the basis of the sectional weights of bar as per MT 5700.00 405.000 2308500.00 546.18 3113212.88 0.000 0.00 546.178 3113212.88
relevant I.S. Code. The rate shall include cost of binding wire, chairs, spacers, pins, cover blocks which will not be measured
separately for payment. (steel shall be supiled by the developer)
Providing & Fixing of staging Slab Height more than 3.6 m and method of erection shall be approved by the structural
9 consultant. Staging shall be kept for a period as given in the de-shuttering scheme no. extra paid lead & lift. Cum 84.00 1000.000 84000.00 4438.455 372830.24 0.000 0.00 4438.455 372830.24
All charges for fixing reinforcement bars including drilling & chemical injection in the concrete surface till Roof level as per
the manufacturer's specification either Fischer or Hilti product. At least 10% of the reinforcement shall be tested by Pull Out
10 test as per the instruction of Structural Consultant. The rate shall be inclusive of all labour, material, scaffolding, gangway
etc. involved for rebar grouting however cost of reinforcement steel will be paid as per item no 15
10.01 8mm dia No. 48.00 50 2400.00 0.00 0.00 0.00 0.00
10.02 10mm dia No. 60.00 50 3000.00 704.5 42270.00 213.00 12780.00 917.500 55050.00
10.03 12mm dia No. 84.00 60 5040.00 649.000 54516.00 55.00 4620.00 704.000 59136.00
10.04 16mm dia No. 132.00 20 2640.00 412.000 54384.00 24.00 3168.00 436.000 57552.00
10.05 20mm dia No. 195.00 15 2925.00 0.00 0.00 0.00 0.000 0.00
10.06 25mm dia No. 240.00 10 2400.00 0.00 0.00 0.00 0.000 0.00
Providing and making core cut of any shape (maximum size 150mmX150mm or of 150mm dia) in RCC slab of any level with
core cutting machine inclusive of filling of core with fire retardant sealant of Hilti make as per the manufacturers specification,
11 cleaning etc. complete. The contractor shall determine the location of beam/post tensioned tendons before carrying out core Nos 240.00 40 9600.00 0.00 0.000 0.00 0.00
cutting operation and take prior approval from PMC/Owner. The rate shall include cutting of reinforcement by gas cutting
machine or as directed etc. complete.
All charges for providing, making holes and fixing M.S. sleeves of various dia in RCC surface for services or any other
12 purpose as per design/drawing/instruction of PMC/Owner till Plinth level and complete in all respect to the entire satisfaction 0.00 0.000
of PMC/Owner. The rate shall include the cost of supply & fixing of necessary flange.
12.01 100mm dia M.S. pipe medium duty No. 270.00 40 10800.00 65.00 17550.00 0.000 0.00 65.000 17550.00
12.02 150mm dia M.S. pipe medium duty No. 300.00 50 15000.00 20.000 6000.00 0.000 0.00 20.000 6000.00
12.03 200mm dia M.S. pipe medium duty No. 420.00 30 12600.00 0.000 0.00 0.000 0.00 0.000 0.00
12.04 300mm dia M.S. pipe medium duty No. 570.00 20 11400.00 0.000 0.00 0.000 0.00 0.000 0.00
13 A 250 mm thick Brick work. Cum 4410.00 672 2963520.00 328.601 1449130.27 58.862 259583.62 387.463 1708713.90
13 B 125 mm thick Brick work. Sqm 585.00 1590 930150.00 388.815 227456.78 153.175 89607.38 541.990 317064.15
13 C Inside 15 mm thick Plaster Sqm 162.00 8710 1411020.00 6480.590 1049855.58 955.693 154822.27 7436.283 1204677.85
13 D outside wall 20 mm thick Plaster Sqm 255.00 7895 2013225.00 0.000 0.00 219.520 55977.60 219.520 55977.60
Round Off
11/13/2021 RA-25
All charges for providing, fabricating, erecting and fixing in position plained timber, plywood centering and
shuttering true to line and level, including making provision for cut out (plan area of cut out shall be paid as
per provision of relevant IS code) steel propping, staging of required height, shuttering removal, applying
1 shuttering oil, including required bracing, chamfering corners (of exposed edges) of beams, columns, walls, Sqm 204.00 28248.000 5762592.00 22085.165 4505373.68 331.744 67675.83 22416.909 4573049.50
mullion post (if any) etc. complete to the entire satisfaction of PMC/Owner. Rate shall include removal and
dismantling the aforesaid assembly after specified period complete at all levels and leads for all items e.g.
columns, beams, slabs, lintels, staircase, wall etc. of all profile coming above Plinth level.
All charges for providing & laying 1:3:6 plain cement concrete (PCC) of required thickness at all levels and
leads coming above Plinth level using 20 mm nominal size well-graded approved quality aggregate including
2 vibrating / compacting, scaffolding as required establishing dewatering system by pumping / bailing out Cum 2420.00 50.000 121000.00 0.000 0.00 0.000 0.00 0.000 0.00
water, cleaning, preparing surfaces, junctions etc. including shuttering, curing complete to the entire
satisfaction of PMC/Owner. (cement/ RMC shall be supplied by the developer)
All charges for laying M40 grade cement concrete/reinforced cement concrete (excluding cost of shuttering
& reinforcement) at all levels and leads for all items e.g. columns, beams, slabs, lintels, staircase, wall,
pockets etc. of all profile coming above Plinth level using 20 mm nominal size & down graded good quality
aggregate as per design mix approved by PMC/Consultant including vibrating / compacting, curing,
scaffolding as required, dewatering (if any), cleaning, preparing surfaces, junctions etc. including curing
3 complete to the entire satisfaction of PMC/Owner. Cement concrete should have an ultimate crushing 0.000 0.00 0.000 0.00 0.000 0.00
strength of not less than 400 Kg/sq.cm on 15cm X 15cm X 15cm cube at 28 days and source of concrete will
be RMC ( RMC shall be supplied by the developer) Special conditions:-Rates are quoted for all levels & heights.
For material/cube testing, the contractor shall maintain QC lab, cube testing machine, sieves, slump cones,
graduated cylinder, weight scales etc. in good working condition cost of which shall be included in the rate.
The rate shall include the cost of plasticiser / super plasticiser of an approved brand to get the required
3.01 workability / strength. The column beam junctions shall be with the grade of concrete as in column up to a Cum 400.00 4259.000 1703600.00 1218.924 487569.45 5.899 2359.60 1224.823 489929.05
distance of depth of beam in all directions & rate shall be inclusive of this.
All charges for laying M25 grade cement concrete/reinforced cement concrete (excluding cost of shuttering
& reinforcement) at all levels and leads for all items e.g. columns, beams, slabs, lintels, staircase, wall,
pockets etc. of all profile coming above Plinth level using 20 mm nominal size & down graded good quality
aggregate as per design mix approved by PMC/Consultant including vibrating / compacting, curing,
scaffolding as required, dewatering (if any), cleaning, preparing surfaces, junctions etc. including curing
complete to the entire satisfaction of PMC/Owner. Cement concrete should have an ultimate crushing 0.000 0.000 0.000 0.00
strength of not less than 250 Kg/sq.cm on 15cm X 15cm X 15cm cube at 28 days and source of concrete will
be RMC. ( RMC shall be supplied by the developer) Special conditions:- Rates are quoted for all levels &
heights. For material/cube testing, the contractor shall maintain QC lab, cube testing machine, sieves,
slump cones, graduated cylinder, weight scales etc. in good working condition cost of which shall be
included in the rate.
The rate shall include the cost of plasticiser / super plasticiser of an approved brand to get the required
3.02 workability / strength. The column beam junctions shall be with the grade of concrete as in column up to a Cum 400.00 150.000 60000.00 2003.591 801436.50 12.585 5033.82 2016.176 806470.32
distance of depth of beam in all directions & rate shall be inclusive of this.
All charges for fixing & removal of scaffolding & gangway at peripheral area of building to the entire
4 satisfaction of Post tensioning agency/PMC/Owner to enable the post tensioning agency to stress the Cum 60.00 9600.000 576000.00 1703.014 102180.82 0.000 0.00 1703.014 102180.82
tendons at all levels. Payment will be made after full completion of post tensioning work.
All charges for providing, making & placing the chairs made with reinforcement bar for placement of
tendons in required profile at all level coming above Plinth level including transportation, decoiling,
5 No 8.00 9500.000 76000.00 5047.000 40376 0.000 0.00 5047 40376.00
straightening, removing loose rust and binding with 18 gauge annealed wire to the entire satisfaction of
PMC/Owner.
All charges for doing miscellaneous structural works, including supplying, preparation of fabrication
drawings based on Consultants drawings, obtaining approval, fabrication, erections as per IS 800 etc
complete for miscellaneous structural steel stairs, ladders, platforms, monorails, gratings, chequered plates,
6 MT 36000.00 7.000 252000.00 0.000 0.00 0.000 0.00 0.000 0.00
hand rails etc. coming upto Plinth level including surface preparation, cleaning, welding and applying one
coat of zinc chromate primer to the entire satisfaction of PMC/Owner. (Structural Steel shall be supplied by
the developer.)
All charges for making structural inserts as per I.S. 2062, including supplying, fabricating, and installing in
7 concrete coming till Roof level with anchors in the form of rods or flats including necessary welding and MT 36000.00 0.500 18000.00 0.013 452.79 0.000 0.00 0.013 452.79
applying one coat of zinc chromate primer to the entire satisfaction of PMC/Owner.
All charges for fixing steel reinforcement (Tor Steel as per IS-1786, Fe 500) for RCC work including
transporting, decoiling, straightening, removing loose rust, cutting, bending and placing for all profile and
for all lead & lift above Plinth level and binding with 18 gauge annealed wire to the entire satisfaction of
8 PMC/Owner. Payment of steel shall be made as per drawing and approved bar bending schedule with MT 3800.00 405.000 1539000.00 546.178 2075475.25 0.000 0.00 546.178 2075475.25
permissible laps and paid on the basis of the sectional weights of bar as per relevant I.S. Code. The rate
shall include cost of binding wire, chairs, spacers, pins, cover blocks which will not be measured separately
for payment. (steel shall be supiled by the developer)
Providing & Fixing of staging Slab Height more than 3.6 m and method of erection shall be approved by the
9 structural consultant. Staging shall be kept for a period as given in the de-shuttering scheme no. extra paid Cum 56.00 1000.000 56000.00 4438.455 248553.49 0.000 0.00 4438.455 248553.49
lead & lift.
All charges for fixing reinforcement bars including drilling & chemical injection in the concrete surface till
Roof level as per the manufacturer's specification either Fischer or Hilti product. At least 10% of the
10 reinforcement shall be tested by Pull Out test as per the instruction of Structural Consultant. The rate shall 0.000 0.000 0.000
be inclusive of all labour, material, scaffolding, gangway etc. involved for rebar grouting however cost of
reinforcement steel will be paid as per item no 15
10.01 8mm dia No. 32.00 50.000 1600.00 0.000 0.00 0.000 0.00 0.000 0.00
10.02 10mm dia No. 40.00 50.000 2000.00 704.500 28180.00 213.000 8520.00 917.500 36700.00
10.03 12mm dia No. 56.00 60.000 3360.00 649.000 36344.00 55.000 3080.00 704.000 39424.00
10.04 16mm dia No. 88.00 20.000 1760.00 412.000 36256.00 24.000 2112.00 436.000 38368.00
10.05 20mm dia No. 130.00 15.000 1950.00 0.000 0.00 0.000 0.00 0.000 0.00
10.06 25mm dia No. 160.00 10.000 1600.00 0.000 0.00 0.000 0.00 0.000 0.00
Providing and making core cut of any shape (maximum size 150mmX150mm or of 150mm dia) in RCC slab
of any level with core cutting machine inclusive of filling of core with fire retardant sealant of Hilti make as
11 per the manufacturers specification, cleaning etc. complete. The contractor shall determine the location of 6400.00 0.000 0.00 0.000 0.00 0.000 0.00
no 160.00 40.000
beam/post tensioned tendons before carrying out core cutting operation and take prior approval from
PMC/Owner. The rate shall include cutting of reinforcement by gas cutting machine or as directed etc.
complete.
12.01 100mm dia M.S. pipe medium duty No. 180.00 40.000 7200.00 65.000 11700.00 0.000 0.00 65.000 11700.00
12.02 150mm dia M.S. pipe medium duty No. 200.00 50.000 10000.00 20.000 4000.00 0.000 0.00 20.000 4000.00
12.03 200mm dia M.S. pipe medium duty No. 280.00 30.000 8400.00 0.000 0.00 0.000 0.00 0.000 0.00
12.04 300mm dia M.S. pipe medium duty No. 380.00 20.000 7600.00 0.000 0.00 0.000 0.00 0.000 0.00
13 A 250 mm thick Brick work. Cum 2940.00 672.00 1975680.00 328.601 966086.85 58.862 173055.75 387.463 1139142.60
13 B . 125 mm thick Brick work Sqm 390.00 1590.00 620100.00 388.815 151637.85 153.175 59738.25 541.990 211376.10
13 C Inside 15 mm thick Plaster Sqm 108.00 8710.00 940680.00 6480.590 699903.72 955.693 103214.85 7436.283 803118.57
13 D Outside wall 20 mm thick Plaster Sqm 170.00 7895.00 1342150.00 0.000 0.00 219.520 37318.40 219.520 37318.40
Round Off
SHUTTERING ABSTRACT
M/S S.M NIRMAN INFRASTRUCTURE & DEVELOPMENT PVT. LTD.
PROJECT :- OFFICE BUILDING (B+G+XXI) OF DN 50 , SALTLAKE, SECTOR-V, KOLKATA.
NAME OF THE CLIENT : ACCORD INFOTECH PRIVATE LIMITED NAME OF THE PMC : CONSYNC INFRA PVT. LTD.
SL. NO. DESCRIPTION OF ITEM UNIT QUANTITY REMARKS
All charges for providing, fabricating, erecting and fixing in position plained timber, plywood centering and shuttering true
to line and level, including making provision for cut out (plan area of cut out shall be paid as per provision of relevant IS
code) steel propping, staging of required height, shuttering removal, applying shuttering oil, including required bracing,
1 chamfering corners (of exposed edges) of beams, columns, walls, mullion post (if any) etc. complete to the entire
satisfaction of PMC/Owner. Rate shall include removal and dismantling the aforesaid assembly after specified period
complete at all levels and leads for all items e.g. columns, beams, slabs, lintels, staircase, wall etc. of all profile coming
above Plinth level.
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
SHUTTERING ABSTRACT
RA-25 PAGE NO -7
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
SHUTTERING ABSTRACT
RA-25 PAGE NO -8
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
SHUTTERING ABSTRACT
RA-25 PAGE NO -9
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
SHUTTERING ABSTRACT
RA-25 PAGE NO -10
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
R.C.C ABSTRACT
RA-25 PAGE NO -11
The rate shall include the cost of plasticiser / super plasticiser of an approved brand to get the required workability / strength. The column
3 beam junctions shall be with the grade of concrete as in column up to a distance of depth of beam in all directions & rate shall be inclusive
of this.
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
R.C.C ABSTRACT
RA-25 PAGE NO -12
QUANTITY REMARKS
SL.
DESCRIPTION OF ITEM UNIT M-25 M-30 M-35 M-40 M50
NO.
3.02 3.01
4TH FLOOR TO 5TH FLOOR M3
1 COLUMN (+15700 TO +18850) LEV. M3 0.000 0.000 0.000 0.000 40.300
2 LIFT (+15700 TO +18850) LEV. M 3
0.000 0.000 0.000 0.000 11.041
3 5TH FLOOR BEAM (+18850) M 3
0.000 0.000 20.751 0.000 0.000
4 5TH FLOOR SLAB (+18850) M 3
0.000 0.000 45.966 0.000 0.000
5 STAIR (+ 15700 TO +18850 LEV.) M3 6.390 0.000 0.000 0.000 0.000
TOTAL = M3 6.390 0.000 66.716 0.000 51.341 E
5TH FLOOR TO 6TH FLOOR M 3
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
R.C.C ABSTRACT
RA-25 PAGE NO -13
QUANTITY REMARKS
SL.
DESCRIPTION OF ITEM UNIT M-25 M-30 M-35 M-40 M50
NO.
3.02 3.01
2 LIFT (+31600 TO +34900) LEV. M3 0.000 0.000 0.000 0.000 11.566
3 10TH FLOOR BEAM (+34900) M3 0.000 0.000 22.417 0.000 0.000
4 10TH FLOOR SLAB (+34900) M 3
0.000 0.000 57.417 0.000 0.000
5 STAIR-1 (+31600 TO +34900 LEV.) M 3
6.435 0.000 0.000 0.000 0.000
6 STAIR-2 (+31600 TO +34900 LEV.) M 3
6.435 0.000 0.000 0.000 0.000
TOTAL = M3 12.870 0.000 79.834 0.000 53.786 J
10TH FLOOR TO 11TH FLOOR M3
1 COLUMN (+34900 TO +38650) LEV. M3 0.000 0.000 0.000 0.000 36.976
2 LIFT (+34900 TO +38650) LEV. M 3
0.000 0.000 0.000 0.000 13.144
3 11TH FLOOR BEAM (+38650) M3 0.000 0.000 26.578 0.000 0.000
4 11TH FLOOR SLAB (+38650) M3 0.000 0.000 59.657 0.000 0.000
5 STAIR-1 (+34900 TO +38650 LEV.) M3 6.891 0.000 0.000 0.000 0.000
6 STAIR-2 (+34900 TO +38650 LEV.) M 3
6.891 0.000 0.000 0.000 0.000
TOTAL = M 3
13.783 0.000 86.235 0.000 50.120 K
11TH FLOOR TO 12TH FLOOR M3
1 COLUMN (+38650 TO +42400) LEV. M3 0.000 0.000 0.000 0.000 36.976
2 LIFT (+38650 TO +42400) LEV. M 3
0.000 0.000 0.000 0.000 13.144
3 12TH FLOOR BEAM (+42400) M 3
0.000 0.000 23.339 0.000 0.000
4 12TH FLOOR SLAB (+42400) M 3
0.000 0.000 57.634 0.000 0.000
5 STAIR-1 (+38650 TO +42400 LEV.) M3 6.741 0.000 0.000 0.000 0.000
6 STAIR-2 (+38650 TO +42400 LEV.) M3 6.805 0.000 0.000 0.000 0.000
TOTAL = M 3
13.546 0.000 80.973 0.000 50.120 L
12TH FLOOR TO 13TH FLOOR M 3
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
R.C.C ABSTRACT
RA-25 PAGE NO -14
QUANTITY REMARKS
SL.
DESCRIPTION OF ITEM UNIT M-25 M-30 M-35 M-40 M50
NO.
3.02 3.01
2 LIFT (+49900 TO +53650) LEV. M3 0.000 0.000 0.000 13.144 0.000
3 15TH FLOOR BEAM (+53650) M3 0.000 0.000 26.578 0.000 0.000
4 15TH FLOOR SLAB (+53650) M 3
0.000 0.000 59.657 0.000 0.000
5 STAIR-1 (+49900 TO +53650 LEV.) M 3
6.741 0.000 0.000 0.000 0.000
6 STAIR-2 (+49900 TO +53650 LEV.) M 3
6.805 0.000 0.000 0.000 0.000
TOTAL = M3 13.546 0.000 86.235 50.120 0.000 0
15TH FLOOR TO 16TH FLOOR M3
1 COLUMN (+53650 TO +56050) LEV. M3 0.000 0.000 0.000 36.976 0.000
2 LIFT (+53650 TO +56050) LEV. M 3
0.000 0.000 0.000 13.144 0.000
3 16TH FLOOR BEAM (+57400) M3 0.000 0.000 24.717 0.000 0.000
4 16TH FLOOR SLAB (+57400) M3 0.000 0.000 46.592 0.000 0.000
5 STAIR-1 (+53650 TO +57400) LEV. M3 6.741 0.000 0.000 0.000 0.000
6 STAIR-2 (+53650 TO +57400) LEV. M 3
6.805 0.000 0.000 0.000 0.000
TOTAL = M 3
13.546 0.000 71.310 50.120 0.000 P
16TH FLOOR TO 17TH FLOOR M3
1 COLUMN (+57400 TO +61150) LEV. M3 0.000 0.000 0.000 36.976 0.000
2 LIFT (+57400 TO +61150) LEV. M 3
0.000 0.000 0.000 13.144 0.000
3 17TH FLOOR BEAM (+61150) M 3
0.000 0.000 23.339 0.000 0.000
4 17TH FLOOR SLAB (+61150) M 3
0.000 0.000 57.262 0.000 0.000
5 STAIR-1 (+57400 TO +61150) LEV. M3 6.741 0.000 0.000 0.000 0.000
6 STAIR-2 (+57400 TO +61150) LEV. M3 6.805 0.000 0.000 0.000 0.000
TOTAL = M 3
13.546 0.000 80.601 50.120 0.000 Q
17TH FLOOR TO 18TH FLOOR M 3
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
R.C.C ABSTRACT
RA-25 PAGE NO -15
QUANTITY REMARKS
SL.
DESCRIPTION OF ITEM UNIT M-25 M-30 M-35 M-40 M50
NO.
3.02 3.01
2 LIFT (+68650 TO +72400) LEV. M3 0.000 0.000 0.000 13.144 0.000
3 20TH FLOOR BEAM (+72400) M3 0.000 0.000 24.374 0.000 0.000
4 20TH FLOOR SLAB (+72400) M 3
0.000 0.000 56.353 0.000 0.000
5 STAIR-1 (+68650 TO +72400) LEV. M 3
6.741 0.000 0.000 0.000 0.000
6 STAIR-2 (+68650 TO +72400) LEV. M 3
6.805 0.000 0.000 0.000 0.000
TOTAL = M3 13.546 0.000 80.727 50.120 0.000 T
20TH FLOOR TO 21TH FLOOR M3
1 COLUMN (+72400 TO +76600) LEV. M3 0.000 0.000 0.000 41.501 0.000
2 LIFT (+72400 TO +76600) LEV. M 3
0.000 0.000 0.000 14.721 0.000
3 21TH FLOOR BEAM (+76600) M3 0.000 0.000 24.374 0.000 0.000
4 21TH FLOOR SLAB (+76600) M3 0.000 0.000 55.555 0.000 0.000
5 STAIR-1 (+72400 TO +76600) LEV. M3 6.836 0.000 0.000 0.000 0.000
6 STAIR-2 (+72400 TO +76600) LEV. M 3
6.794 0.000 0.000 0.000 0.000
TOTAL = M 3
13.630 0.000 79.930 56.222 0.000 U
21TH FLOOR TO 22TH FLOOR M3
1 COLUMN (+76600 TO +80800) LEV. M3 0.000 0.000 0.000 41.501 0.000
2 LIFT (+76600 TO +80800) LEV. M 3
0.000 0.000 0.000 16.824 0.000
3 22TH FLOOR BEAM (+80800) M 3
0.000 0.000 24.374 0.000 0.000
4 22TH FLOOR SLAB (+80800) M 3
0.000 0.000 51.851 0.000 0.000
5 STAIR-1 (+76600 TO +80800) LEV. M3 6.836 0.000 0.000 0.000 0.000
6 STAIR-2 (+76600 TO +80800) LEV. M3 6.794 0.000 0.000 0.000 0.000
TOTAL = M 3
13.630 0.000 76.225 58.325 0.000 V
22TH FLOOR TO 23TH FLOOR M 3
S.M NIRMAN INF. DEV. PVT. LTD. CONSYNC INFRA PVT. LTD.
RECORD ENTRY
RA - 25 PAGE NO - 16
MEASUREMENT SHEET
M/S S.M NIRMAN INFRASTRUCTURE & DEVELOPMENT PVT. LTD.
PROJECT : OFFICE BUILDING AT DN 50 , SALTLAKE, SECTOR-V, KOLKATA.
CLIENT : ACCORD INFOTECH PRIVATE LIMITED
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
All charges for providing, fabricating, erecting and fixing in position plained timber, plywood centering and shuttering true to line and level,
including making provision for cut out (plan area of cut out shall be paid as per provision of relevant IS code) steel propping, staging of
required height, shuttering removal, applying shuttering oil, including required bracing, chamfering corners (of exposed edges) of beams,
columns, walls, mullion post (if any) etc. complete to the entire satisfaction of PMC/Owner. Rate shall include removal and dismantling the
1 aforesaid assembly after specified period complete at all levels and leads for all items e.g. columns, beams, slabs, lintels, staircase, wall etc.
of all profile coming above Plinth level.
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
UPSTAND BEAM FOR 16TH FLOOR M2 2 25.950 0.250 12.975
M 2
TOTAL QTY. = 293.221
All charges for fixing reinforcement bars including drilling & chemical injection in the concrete surface till Roof level as per the
manufacturer's specification either Fischer or Hilti product. At least 10% of the reinforcement shall be tested by Pull Out test as per the
10 instruction of Structural Consultant. The rate shall be inclusive of all labour, material, scaffolding, gangway etc. involved for rebar grouting
however cost of reinforcement steel will be paid as per item no 15
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
For 14th & 16th floor upstand beam rebar
grouting work. NOS 213.00 213.00
For Staircase 2 mid landing beam 4th to 5th floor. NOS 12.00 12.00
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
13 A 250 mm thick Brick work.
Ground Floor :-
Electric Room M3 1.000 5.400 0.250 3.700 4.995 FRONT WALL
Do M 3
1.000 4.800 0.250 4.270 5.124
Less for RS M3 -1.000 2.200 0.250 2.450 -1.348
Car lift M3 1.000 2.550 0.250 3.850 2.454
Car lift M 3
1.000 2.550 0.250 3.850 2.454
Electric Duct. M3 1.000 1.075 0.200 3.400 0.731
ST-1 Side brick wall M 3
1.000 3.300 0.250 0.900 0.742
ST-1 outside brick wall M3 1.000 3.875 0.250 2.925 2.834
Less for D8 M 3
-1.000 1.000 0.250 2.250 -0.563
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
1st Floor :-
Car lift front side M3 1.000 3.525 0.250 3.150 2.776
Do M 3
1.000 3.550 0.250 3.150 2.796
Staircase 1 front side M 3
1.000 2.825 0.250 3.300 2.331
Less for FCD M3 -1.000 1.200 0.250 2.450 -0.735
Electric Duct. M3 1.000 1.075 0.200 3.300 0.709
Toilet area back side. M3 1.000 3.800 0.250 3.150 2.992
Less for V3 M 3
-2.000 1.200 0.250 0.350 -0.210
ST-1 outside brick wall M3 1.000 3.875 0.250 3.399 3.293
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
ST-2 outside brick wall M 3
1.000 3.275 0.250 3.300 2.702
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
Passenger lift Front side. M 3
3.000 1.900 0.250 3.300 4.702
Lift lobby side. M 3
1.000 5.800 0.250 3.300 4.785
2nd Floor :-
Car lift front side M3 1.000 3.525 0.250 3.150 2.776
Do M 3
1.000 3.550 0.250 3.150 2.796
Staircase 1 front side M3 1.000 2.825 0.250 3.300 2.331
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front side M3 1.000 6.275 0.250 3.300 5.177
Lift loby M 3
1.000 5.800 0.250 3.300 4.785
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
ST-2 outside brick wall M3 1.000 3.275 0.250 3.300 2.702
Less for SW M 3
-1.000 1.500 0.250 1.700 -0.638
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
Electric Duct. M 3
1.000 1.075 0.200 3.300 0.709
Toilet area back side. M3 1.000 3.800 0.250 3.150 2.992
Less for V3 M 3
-2.000 1.200 0.250 0.350 -0.210
ST-1 outside brick wall M3 1.000 3.875 0.250 3.445 3.337
Less for D8 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
3rd Floor :-
Car lift front side M3 1.000 3.525 0.250 2.550 2.247
Do M 3
1.000 3.550 0.250 2.550 2.263
Staircase 1 front side M 3
1.000 2.825 0.250 2.700 1.907
Less for FCD M3 -1.000 1.200 0.250 2.450 -0.735
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
Staircase-2 front site M3 1.000 6.275 0.250 2.700 4.236
Lift loby M3 1.000 5.800 0.250 2.700 3.915
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
ST-2 outside brick wall M 3
1.000 3.275 0.250 2.700 2.211
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
Electric Duct. M3 1.000 1.075 0.200 2.700 0.580
ST-1 outside brick wall M 3
1.000 3.875 0.250 2.725 2.640
Less for D3 M3 -1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Out side upstand M3 1.000 37.525 0.250 0.300 2.814
4th Floor :-
Car lift front side wall M3 1 3.525 0.250 2.400 2.115
Do M 3
1 3.550 0.250 2.400 2.130
Staircase 1 front side M 3
1 2.825 0.250 2.550 1.801
Less for FCD M3 -1 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1 6.275 0.250 2.550 4.000
Lift loby M3 1 5.800 0.250 2.550 3.698
Less for FCD M 3
-2 1.200 0.250 2.450 -1.470
Electric Duct. M3 1 1.075 0.200 2.550 0.548
Electric Duct. M 3
1 1.075 0.250 2.550 0.685
ST-1 outside brick wall M3 1.000 3.875 0.250 2.650 2.567
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
ST-2 outside brick wall M 3
1.000 3.275 0.250 2.550 2.088
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
5th Floor :-
Car lift front side wall M3 1.000 3.525 0.250 2.400 2.115
Do M 3
1.000 3.550 0.250 2.400 2.130
Staircase 1 front side M3 1.000 2.825 0.250 2.550 1.801
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 2.550 4.000
Lift loby M 3
1.000 5.800 0.250 2.550 3.698
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
Electric Duct. M3 1.000 1.075 0.200 2.550 0.548
ST-1 OUT SIDE M 3
1.000 3.875 0.250 0.600 0.581
Less door M3 -1.000 1.200 0.250 0.600 -0.180
ST-1 outside brick wall M3 1.000 3.875 0.250 2.650 2.567
Less for D3 M3 -1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Out side upstand M3 1.000 37.525 0.250 0.300 2.814
6th Floor :-
Car lift front side wall M3 1.000 3.525 0.250 2.400 2.115
Do M 3
1.000 3.550 0.250 2.400 2.130
Staircase 1 front side M3 1.000 2.825 0.250 2.550 1.801
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M 3
1.000 6.275 0.250 2.550 4.000
Lift loby M3 1.000 5.800 0.250 2.550 3.698
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
Electric Duct. M3 1.000 1.075 0.200 2.550 0.548
ST-1 outside brick wall M3 1.000 3.875 0.250 2.650 2.567
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Out side upstand M 3
1.000 37.525 0.250 0.300 2.814
ST-2 outside brick wall M 3
1.000 3.275 0.250 2.550 2.088
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
7th Floor :-
Car lift front side wall M3 1.000 3.525 0.250 2.400 2.115
Do M3 1.000 3.550 0.250 2.400 2.130
Staircase 1 front side M 3
1.000 2.825 0.250 2.550 1.801
Less for FCD M3 -1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 2.550 4.000
Lift loby M 3
1.000 5.800 0.250 2.550 3.698
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
Electric Duct. M3 1.000 1.075 0.200 2.550 0.548
AC legde wall M3 1.000 3.800 0.250 1.270 1.207
ST-1 outside brick wall M 3
1.000 3.875 0.250 2.650 2.567
Less for D3 M3 -1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Out side upstand M3 1.000 37.525 0.250 0.300 2.814
ST-2 outside brick wall M 3
1.000 3.275 0.250 2.550 2.088
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
8th Floor :-
Car lift front side wall M3 1.000 3.525 0.250 2.550 2.247
Do M 3
1.000 3.550 0.250 2.550 2.263
Staircase 1 front side M3 1.000 2.825 0.250 2.700 1.907
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 2.700 4.236
Lift loby M 3
1.000 5.800 0.250 2.700 3.915
Electric Duct. M3 1.000 1.075 0.200 2.700 0.580
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
AC legde wall M3 1.000 3.800 0.250 1.270 1.207
ST-1 outside brick wall M 3
1.000 3.875 0.250 2.650 2.567
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
Out side upstand M 3
1.000 37.525 0.250 0.300 2.814
ST-2 outside brick wall M3 1.000 3.275 0.250 2.700 2.211
Less for SW M 3
-1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
9th Floor :-
Car lift front side wall M3 1.000 3.525 0.250 2.550 2.247
Do M 3
1.000 3.550 0.250 2.550 2.263
Staircase 1 front side M3 1.000 2.825 0.250 2.700 1.907
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M 3
1.000 6.275 0.250 2.700 4.236
Electric Duct. M3 1.000 1.075 0.200 2.700 0.580
Lift loby M 3
1.000 5.800 0.250 2.700 3.915
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
ST-2 outside brick wall M3 1.000 3.275 0.250 2.700 2.211
Less for SW M 3
-1.000 1.300 0.250 1.700 -0.553
Less for DOOR M 3
-1.000 0.900 0.250 2.100 -0.473
ST-1 outside brick wall M3 1.000 3.875 0.250 2.140 2.073
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
10th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M 3
1.000 5.800 0.250 3.150 4.568
Electric Duct. M3 1.000 1.075 0.200 2.700 0.580
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
Office room C6 to C9A M 3
1.000 7.325 0.250 0.750 1.373
Office room C6 to C9A M3 1.000 1.600 0.250 1.650 0.660
Office room C6 to C9A M 3
1.000 0.125 0.250 1.650 0.052
Office room C6 to C9A M3 1.000 0.750 0.250 1.650 0.309
Office room C9A to C9 M 3
1.000 3.500 0.250 0.750 0.656
ST-1 outside brick wall M3 1.000 3.875 0.250 3.375 3.270
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
ST-2 outside brick wall M 3
1.000 3.275 0.250 3.150 2.579
Less for SW M3 -1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
11th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M 3
1.000 5.800 0.250 3.150 4.568
Electric Duct. M3 1.000 1.075 0.200 2.700 0.580
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
Office room C6 to C9A M3 1.000 7.325 0.250 0.750 1.373
Office room C6 to C9A M 3
1.000 1.600 0.250 1.650 0.660
Office room C6 to C9A M3 1.000 0.125 0.250 1.650 0.052
Office room C6 to C9A M 3
1.000 0.750 0.250 1.650 0.309
Office room C9A to C9 M 3
1.000 3.500 0.250 0.750 0.656
ST-1 outside brick wall M3 1.000 3.875 0.250 3.250 3.148
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
ST-2 outside brick wall M 3
1.000 3.275 0.250 3.150 2.579
Less for SW M3 -1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
12th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M3 -1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M 3
1.000 5.800 0.250 3.150 4.568
Electric Duct. M3 1.000 1.075 0.200 2.700 0.580
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
Office room C6 to C9A M3 1.000 7.325 0.250 0.750 1.373
Office room C6 to C9A M3 1.000 1.600 0.250 0.350 0.140
Office room C6 to C9A M 3
1.000 0.750 0.250 0.680 0.128
Office room C9A to C9 M 3
1.000 3.500 0.250 0.750 0.656
ST-1 outside brick wall M3 1.000 3.875 0.250 3.250 3.148
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
ST-2 outside brick wall M 3
1.000 3.275 0.250 3.150 2.579
Less for SW M3 -1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
13th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M3 -1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M 3
1.000 5.800 0.250 3.150 4.568
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
Office room C6 to C9A M3 1.000 7.325 0.250 0.750 1.373
Electric Duct. M3 1.000 1.075 0.200 2.700 0.580
Office room C9A to C9 M 3
1.000 3.500 0.250 0.750 0.656
ST-1 outside brick wall M3 1.000 3.875 0.250 3.250 3.148
Less for D3 M 3
-1.000 1.000 0.250 2.450 -0.613
Less for SW M3 -1.000 1.500 0.250 1.700 -0.638
ST-2 outside brick wall M 3
1.000 3.275 0.250 3.150 2.579
Less for SW M3 -1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
14th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M 3
1.000 5.800 0.250 3.150 4.568
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
Electric Duct. M3 4.000 1.075 0.200 2.700 2.322
ST-2 outside brick wall M3 1.000 3.275 0.250 3.150 2.579
Less for SW M 3
-1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
AC LEDGE 5TH FLOOR TO 15TH FLOOR M 3
11.000 3.800 0.250 1.875 19.594
15th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M 3
1.000 5.800 0.250 3.150 4.568
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
Electric Duct. M3 4.000 1.075 0.200 2.700 2.322
ST-2 outside brick wall M3 1.000 3.275 0.250 3.150 2.579
Less for SW M 3
-1.000 1.300 0.250 1.700 -0.553
Less for DOOR M 3
-1.000 0.900 0.250 2.100 -0.473
16th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M3 -1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
Lift loby M3 1.000 5.800 0.250 3.150 4.568
Less for FCD M3 -2.000 1.200 0.250 2.450 -1.470
Electric Duct. M3 4.000 1.075 0.200 2.700 2.322
ST-2 outside brick wall M 3
1.000 3.275 0.250 3.150 2.579
Less for SW M3 -1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
17th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M3 -1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M3 1.000 5.800 0.250 3.150 4.568
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
Electric Duct. M 3
4.000 1.075 0.200 2.700 2.322
ST-2 outside brick wall M3 1.000 3.275 0.250 3.150 2.579
Less for SW M 3
-1.000 1.300 0.250 1.700 -0.553
Less for DOOR M3 -1.000 0.900 0.250 2.100 -0.473
18th Floor :-
Staircase 1 front side M3 1.000 2.825 0.250 3.150 2.225
Less for FCD M 3
-1.000 1.200 0.250 2.450 -0.735
Staircase-2 front site M3 1.000 6.275 0.250 3.150 4.942
Lift loby M 3
4.000 5.800 0.250 3.150 18.270
Less for FCD M 3
-2.000 1.200 0.250 2.450 -1.470
Electric Duct. M3 4.000 1.075 0.200 2.700 2.322
18TH FLOOR TO 22ND FLOOR ST-2 OUTSIDE
M3 5.000 3.275 0.250 3.150 12.895
BRICK WALL.
Less for SW M3 -5.000 1.300 0.250 1.700 -2.762
Less for DOOR M 3
-5.000 0.900 0.250 2.100 -2.363
12th floor to 18th column C 9A to C6 outer wall M3 7.000 7.325 0.250 2.500 32.047
M3 2.000 3.750 0.250 0.250 0.469
Labour toilet brick work.
M3 4.000 1.050 0.250 0.250 0.263
M 3
TOTAL QTY. = 387.463
PREVIOUS PAID QTY. = 328.601
THIS BILL PAID QTY. = 58.862
13 B 125 mm thick Brick work.
Ground Floor :-
Electric Room Sqm 1.00 5.40 3.40 18.360
Duct Sqm 3.00 1.08 3.40 10.965
Toilet front side partition wall. Sqm 1.00 3.45 3.40 11.730
Less for opening Sqm -1.00 1.05 2.20 -2.310
1st Floor :- M2
Duct Sqm 3.00 1.08 3.30 10.642
Toilet front side partition wall. Sqm 1.00 3.45 3.30 11.385
Less for door opening Sqm -1.00 1.05 2.20 -2.310
2nd Floor :- M2
Duct Sqm 3.00 1.08 3.30 10.642
Toilet front side partition wall. Sqm 1.00 3.45 3.30 11.385
Less for opening Sqm -1.00 1.05 2.20 -2.310
3rd Floor :- M2
Duct Sqm 3.00 1.075 2.70 8.707
Toilet front side partition wall. Sqm 1.00 3.45 2.70 9.315
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
Less for opening Sqm -1.00 1.05 2.20 -2.310
4th Floor :- M2
Duct Sqm 3.00 1.08 2.55 8.224
Toilet front side partition wall. Sqm 1.00 3.45 2.55 8.798
Less for opening Sqm -1.00 1.05 2.20 -2.310
5th Floor :- M2
Duct NEAR C5 M2 3 1.075 2.550 8.224
Toilet front side partition wall. M 2
1 3.45 2.550 8.798
Less for opening M2 -1 1.05 2.200 -2.310
6th Floor :- M2
Duct Sqm 3.00 1.08 2.55 8.224
Toilet front side partition wall. Sqm 1.00 0.73 2.55 1.849
7th Floor :- M2
Duct Sqm 3.00 1.08 2.55 8.224
Toilet front side partition wall. Sqm 1.00 0.73 2.55 1.849
8th Floor :- M2
Duct Sqm 3.00 1.08 2.55 8.224
Toilet front side partition wall. Sqm 1.00 0.73 2.55 1.849
9th Floor :- M2
Duct Sqm 3.00 1.08 2.70 8.707
Toilet front side partition wall. Sqm 1.00 3.45 2.70 9.315
Less for door opening Sqm -1.00 1.05 2.20 -2.310
10 th Floor :- M2
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1.00 3.45 3.15 10.868
C6 to C9 column partition wall. Sqm 1.00 6.30 3.15 19.845
Less for door opening Sqm -1.00 1.20 2.45 -2.940
Less for door opening Sqm -1.00 1.05 2.20 -2.310
11 th Floor :- M2
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1.00 3.45 3.15 10.868
C6 to C9 column partition wall. Sqm 1.00 6.30 3.15 19.845
Less for door opening Sqm -1.00 1.20 2.45 -2.940
Less for opening Sqm -1.00 1.05 2.20 -2.310
12 th Floor :- M2
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1.00 3.45 3.15 10.868
C6 to C9 column partition wall. Sqm 1.00 6.30 3.15 19.845
Less for door opening Sqm -1.00 1.20 2.45 -2.940
Less for opening Sqm -1.00 1.05 2.20 -2.310
13 th Floor :- M2
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1.00 3.45 3.15 10.868
C6 to C9 column partition wall. Sqm 1.00 6.30 2.45 15.435
Less for door opening Sqm -1.00 1.20 2.45 -2.940
Less for opening Sqm -1.00 1.05 2.20 -2.310
14th Floor :-
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1.00 3.45 3.15 10.868
C6 to C9 column partition wall. Sqm 1.00 6.30 1.30 8.190
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
Less for door opening Sqm -1.00 1.20 1.30 -1.560
Less for opening Sqm -1.00 1.05 2.20 -2.310
15th Floor :-
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1 3.45 3.150 10.868
Less for opening Sqm -1 1.05 2.200 -2.310
16th Floor :-
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1 3.45 3.150 10.868
Less for opening Sqm -1 1.05 2.200 -2.310
17th Floor :-
Duct Sqm 3.00 1.08 3.15 10.159
Toilet front side partition wall. Sqm 1 3.45 3.150 10.868
Less for opening Sqm -1 1.05 2.200 -2.310
Staircase -2 side outer duct brick wall. Sqm 19 2.05 3.300 128.535
Sqm 4.00 1.30 2.20 11.440
Labour toilet brick work.
Sqm 2.00 3.00 2.20 13.200
M2 TOTAL QTY. = 541.990
M2 PREVIOUS PAID QTY. = 388.815
M2 THIS BILL PAID QTY. = 153.175
13 C Inside 15 mm thick Plaster
Car lift wall inside plaster 1st fl. To 9th fl. M2 1 3.550 34.700 123.185
Lvl.
Car lift wall inside plaster 1st fl. To 9th fl. M2 1 3.525 34.700 122.317
Lvl.
Staircase -1 side wall C6 ( GF Fl. To 19th.
Fl.) M2 2 6.050 72.400 876.040
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
WAIST SLAB M2 2 2.950 1.800 10.620
Staircase-1, 6th. fl. To 7th fl. M 2
ITEM NO. DESCRIPTION OF WORK UNIT NO. LENGTH WIDTH HEIGHT QUANTITY REMARKS
(M) (M) (M)
1st WAIST SLAB M2 4 3.047 1.800 21.938
2nd & 3rd Landing M 2
4 1.825 1.800 13.140
2nd WAIST SLAB M 2
4 1.825 0.634 4.628
Staircase -2 17th. fl. To 22nd fl. M2
1 st & 4th Landing M2 6 1.825 1.800 19.710
1st WAIST SLAB M 2
6 3.047 1.800 32.908
2nd & 3rd Landing M 2
6 1.825 1.800 19.710
2nd WAIST SLAB M 2
6 1.825 0.634 6.942
Ground Floor :-
Electric Room M2 1.0 5.150 4.270 21.991
DO M2 2.0 4.800 4.270 40.992
2nd Floor :- M2 1.0 17.800 3.720 66.216
3rd Floor :- M2 1.0 17.800 3.120 55.536
5th Floor :- M2 1.0 17.800 2.970 52.866
6th Floor :- M2 1.0 17.800 2.970 52.866
7th Floor :- M2 1.0 17.800 2.970 52.866
Less for FCD M2 -10.0 1.200 2.450 -29.400
1st fl. to 21st fl. Lift lobby area. M2 42 5.800 3.200 779.520
8th fl. to 17th fl. C6 to passenger Lift wall. M2 10 17.800 3.200 569.600
Less for FCD M2 -20.0 1.200 2.450 -58.800
Stair 1 Inside wall M2 1.0 2.825 57.750 163.144
Stair 1 Inside wall M2 1.0 3.875 64.800 251.100
Less for D3 M2 -8.0 1.000 2.450 -19.600
Less for SW M2 -8.0 1.500 1.700 -20.400
Stair 2 Inside wall M2 20.0 3.850 3.500 269.500
INSIDE DUCT GR. FLOOR TO 17TH FL. M2 9.0 1.075 68.650 664.189
Car lift 1 Basement area M2 1.0 18.600 1.650 30.690
Car lift 2 Basement area M2 1.0 18.650 1.650 30.772
Basement wall plaster M2 1.0 73.025 3.000 219.075
Basement Tank 1 M2 1.0 23.600 3.000 70.800
Basement Tank 2 M2 1.0 20.250 3.000 60.750
Basement Tank 3 M2 1.0 23.650 3.000 70.950
Passenger lift Front wall M2 22.0 6.250 3.200 440.000
Less for door opening M2 -66.0 0.950 2.350 -147.345
Door side M2 132.0 0.250 2.350 77.550
Door side lintel bottom M2 66.0 0.950 0.250 15.675
Car parking area upstand beam 3rd,5th,6th,7th 11.0 0.850 350.859
& 8th floor. M2 37.525
M2 TOTAL QTY. = 7436.283
M2 PREVIOUS PAID QTY. = 6480.590
M 2
THIS BILL PAID QTY. = 955.693
13 D outside wall 20 mm thick Plaster
C9 Column outside plastering work. Sqm 1.00 6.40 34.30 219.520
M 2
TOTAL QTY. = 219.520
M 2
PREVIOUS PAID QTY. = 0.000
M 2
THIS BILL PAID QTY. = 219.520
REINFORCEMENT ABSTRACT
S.M. NIRMAN INFRASTRUCTURE & DEVELOPMENT PVT. LTD.
PROJECT : OFFICIAL BUILDING (B+G+XXI) AT DN-50, SEC-V, SALTLAKE
NAME OF THE CLIENT: ACCORD INFRATECH PRIVATE LIMITED NAME OF THE PMC : CONSYNC INFRA PVT. LTD.
All charges for fixing steel reinforcement (Tor Steel as per IS-1786, Fe 500) for RCC work including transporting, decoiling, straightening,
removing loose rust, cutting, bending and placing for all profile and for all lead & lift above Plinth level and binding with 18 gauge annealed
8 wire to the entire satisfaction of PMC/Owner. Payment of steel shall be made as per drawing and approved bar bending schedule with
permissible laps and paid on the basis of the sectional weights of bar as per relevant I.S. Code. The rate shall include cost of binding wire,
chairs, spacers, pins, cover blocks which will not be measured separately for payment. (steel shall be supiled by the developer)
11 PASSENGER LIFT (+600) LEV. TO KG 1164.370 151.599 0.000 1454.535 91.654 0.000 0.000 2862.158
(+4600) LEV.
PASSENGER LIFT (+600) LEV. TO (+4600) LEV. KG 1164.370 151.599 0.000 1454.535 91.654 0.000 0.000 2862.158
12 FIRST FLOOR BEAM (+4600) KG 351.191 689.506 13.412 620.209 1451.741 1021.373 0.000 4147.432
13 FIRST FLOOR SLAB (+4600) LEV. KG 439.345 2156.201 87.783 101.300 0.000 0.000 0.000 2784.629
FIRST FLOOR SLAB (+4600) LEV. KG 790.536 2845.707 101.195 721.509 1451.741 1021.373 0.000 6932.061
14 STAIR-1 (GROUND FLOOR TO 1ST KG 121.035 0.000 1658.828 25.284 81.556 0.000 0.000 1886.703
FLOOR)
15 STAIR-2 (GROUND FLOOR TO 1ST KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (GROUND FLOOR TO 1ST FLOOR) KG 201.646 0.000 2679.082 25.284 163.111 0.000 0.000 3069.123
KG 5052.885 5372.935 2873.802 3983.847 3379.198 4873.225 3239.177 28775.069
TOTAL UPTO FIRST FLOOR SLAB =
MT 5.053 5.373 2.874 3.984 3.379 4.873 3.239 28.775 A
1ST FLOOR TO 2ND FLOOR KG
COLUMN (+4600) LEV. TO (+8500) LEV. KG
16 C-1 KG 31.791 297.185 0.000 250.994 89.679 0.000 0.000 669.649
17 C-2 KG 0.000 236.543 0.000 209.161 44.840 0.000 0.000 490.544
18 C-3 KG 526.981 0.000 0.000 0.000 672.593 507.716 0.000 1707.289
19 C-4 KG 0.000 746.420 0.000 0.000 0.000 543.981 684.740 1975.141
20 C-5 KG 488.048 201.062 167.552 501.988 0.000 0.000 0.000 1358.649
21 C-6 KG 462.886 236.049 312.256 223.106 0.000 0.000 0.000 1234.297
22 C-7 KG 195.097 80.000 0.000 0.000 0.000 108.796 995.985 1379.879
23 C-8 KG 525.431 59.580 0.000 0.000 269.037 1051.698 622.491 2528.236
24 C-9 KG 494.002 85.031 0.000 515.932 89.679 362.654 0.000 1547.298
25 C-10 KG 43.861 401.284 0.000 0.000 67.259 616.512 0.000 1128.917
ALL COLUMN +4600 LEVEL TO +8500 LEV. KG 2768.097 2343.154 479.808 1701.180 1233.086 3191.358 2303.216 14019.900
26 PASSENGER LIFT (+4600) LEV. TO KG 1134.396 147.901 0.000 1422.298 89.679 0.000 0.000 2794.274
(+8500) LEV.
PASSENGER LIFT (+4600) LEV. TO (+8500) LEV. KG 1134.396 147.901 0.000 1422.298 89.679 0.000 0.000 2794.274
27 2ND FLOOR BEAM (+8500) KG 411.936 713.358 23.456 651.833 486.272 2444.252 0.000 4731.106
28 2ND FLOOR SLAB (+8500) LEV. KG 439.345 1659.963 87.783 101.300 0.000 0.000 0.000 2288.391
41 PASSENGER LIFT (+8500) LEV. TO KG 1134.396 147.901 0.000 1422.298 89.679 0.000 0.000 2794.274
(+12400) LEV.
PASSENGER LIFT (+4600) LEV. TO (+8500) LEV. KG 1134.396 147.901 0.000 1422.298 89.679 0.000 0.000 2794.274
42 3RD FLOOR BEAM (+12400) KG 415.663 713.358 30.162 644.886 486.272 2543.210 0.000 4833.551
43 3RD FLOOR SLAB (+12400) LEV. KG 357.567 3459.753 0.000 0.000 0.000 0.000 0.000 3817.320
3RD FLOOR SLAB (+12400) LEV. KG 773.231 4173.111 30.162 644.886 486.272 2543.210 0.000 8650.871
44 STAIR (2ND FLOOR TO 3RD FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (2ND FLOOR TO 3RD FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
KG 4756.335 6664.167 1530.223 3768.364 1890.593 5734.568 2303.216 26647.465
TOTAL 3RD FLOOR SLAB =
MT 4.756 6.664 1.530 3.768 1.891 5.735 2.303 26.647 C
3RD FLOOR TO 4TH FLOOR KG
COLUMN (+12400) LEV. TO (+15700) LEV. KG
45 C-1 KG 5.299 297.185 0.000 216.860 77.827 0.000 0.000 597.171
46 C-2 KG 0.000 201.062 0.000 180.717 38.914 0.000 0.000 420.692
47 C-3 KG 447.934 0.000 0.000 0.000 583.704 442.901 0.000 1474.539
48 C-4 KG 0.000 634.457 0.000 0.000 0.000 474.537 601.303 1710.297
49 C-5 KG 399.019 201.062 144.085 433.721 0.000 0.000 0.000 1177.887
50 C-6 KG 392.069 200.642 268.523 192.765 0.000 0.000 0.000 1053.998
51 C-7 KG 165.833 68.000 0.000 0.000 0.000 94.907 874.622 1203.363
52 C-8 KG 445.504 59.580 0.000 0.000 233.481 917.438 546.639 2202.643
53 C-9 KG 412.147 85.031 0.000 445.769 77.827 316.358 0.000 1337.131
54 C-10 KG 7.310 401.284 0.000 0.000 58.370 537.809 0.000 1004.773
ALL COLUMN +12400 LEVEL TO +15700 LEV. KG 2275.113 2148.302 412.608 1469.832 1070.123 2783.951 2022.564 12182.494
55 PASSENGER LIFT (+12400) LEV. TO KG 962.622 125.716 0.000 1228.876 77.827 0.000 0.000 2395.041
(+15700) LEV.
PASSENGER LIFT (+12400) LEV. TO (+15700) LEV. KG 962.622 125.716 0.000 1228.876 77.827 0.000 0.000 2395.041
56 4TH FLOOR BEAM (+15700) KG 415.663 713.358 30.162 644.886 494.519 2543.210 0.000 4841.798
57 4TH FLOOR SLAB (+15700) LEV. KG 357.567 3093.605 0.000 0.000 0.000 0.000 0.000 3451.172
4TH FLOOR SLAB (+15700) LEV. KG 773.231 3806.963 30.162 644.886 494.519 2543.210 0.000 8292.970
58 STAIR (3RD FLOOR TO 4TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (3RD FLOOR TO 4TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
KG 4091.577 6080.981 1463.023 3343.594 1724.025 5327.160 2022.564 24052.925
TOTAL 4TH FLOOR SLAB =
MT 4.092 6.081 1.463 3.344 1.724 5.327 2.023 24.053 D
69 PASSENGER LIFT (+15700) LEV. TO KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
(+18850) LEV.
PASSENGER LIFT (+15700) LEV. TO (+18850) LEV. KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
70 5TH FLOOR BEAM (+18850) KG 415.663 713.358 30.162 644.886 494.519 2543.210 0.000 4841.798
71 5TH FLOOR SLAB (+18850) LEV. KG 542.983 2608.815 0.000 0.000 0.000 0.000 0.000 3151.798
5TH FLOOR SLAB (+18850) LEV. KG 958.647 3322.173 30.162 644.886 494.519 2543.210 0.000 7993.596
72 STAIR (4TH FLOOR TO 5TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (4TH FLOOR TO 5TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
KG 4156.613 5533.562 1471.354 3237.401 2410.247 4493.827 949.817 22252.820
TOTAL 5TH FLOOR SLAB =
MT 4.157 5.534 1.471 3.237 2.410 4.494 0.950 22.253 E
5TH FLOOR TO 6TH FLOOR KG
COLUMN (+18850) LEV. TO (+22000) LEV. KG
73 C-1 KG 0.000 288.444 12.565 231.475 0.000 0.000 0.000 532.484
74 C-2 KG 0.000 195.148 0.000 173.606 37.432 0.000 0.000 406.186
75 C-3 KG 434.759 0.000 0.000 0.000 786.074 60.957 0.000 1281.790
76 C-4 KG 0.000 615.796 0.000 0.000 449.185 60.957 0.000 1125.938
77 C-5 KG 382.420 195.148 150.784 393.507 0.000 0.000 0.000 1121.859
78 C-6 KG 379.112 194.741 257.589 185.180 0.000 0.000 0.000 1016.622
79 C-7 KG 160.955 66.000 0.000 0.000 0.000 335.262 422.141 984.358
80 C-8 KG 430.478 59.580 0.000 0.000 224.593 883.873 527.676 2126.201
81 C-9 KG 396.983 85.031 0.000 428.228 74.864 304.784 0.000 1289.889
82 C-10 KG 0.000 389.481 0.000 0.000 187.160 304.784 0.000 881.426
ALL COLUMN +18850 LEVEL TO +22000 LEV. KG 2184.707 2089.370 420.939 1411.995 1759.309 1950.617 949.817 10766.754
83 PASSENGER LIFT (+18850) LEV. TO KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
(+22000) LEV.
PASSENGER LIFT (+18850) LEV. TO (+22000)
LEV. KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
84 6TH FLOOR BEAM (+22000) KG 415.663 713.358 20.117 704.556 586.198 3168.924 0.000 5608.816
85 6TH FLOOR SLAB (+22000) LEV. KG 357.567 3158.194 0.000 0.000 0.000 0.000 0.000 3515.762
6TH FLOOR SLAB (+22000) LEV. KG 773.231 3871.552 20.117 704.556 586.198 3168.924 0.000 9124.578
86 STAIR (5TH FLOOR TO 6TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (5TH FLOOR TO 6TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
KG 3971.197 6082.941 1461.309 3297.071 2501.926 5119.541 949.817 23383.803
TOTAL 6TH FLOOR SLAB =
MT 3.971 6.083 1.461 3.297 2.502 5.120 0.950 23.384 F
6TH FLOOR TO 7TH FLOOR KG
COLUMN (+22000) LEV. TO (+25150) LEV. KG
87 C-1 KG 0.000 288.444 12.565 231.475 0.000 0.000 0.000 532.484
88 C-2 KG 0.000 195.148 0.000 173.606 37.432 0.000 0.000 406.186
89 C-3 KG 434.759 0.000 0.000 0.000 786.074 60.957 0.000 1281.790
ALL COLUMN +22000 LEVEL TO +25150 LEV. KG 2184.707 2089.370 420.939 1411.995 1759.309 1950.617 949.817 10766.754
97 PASSENGER LIFT (+22000) LEV. TO KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
(+25150) LEV.
PASSENGER LIFT (+22000) LEV. TO (+25150)
LEV. KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
98 7TH FLOOR BEAM (+25150) KG 495.068 760.765 20.117 704.556 1190.864 3168.924 0.000 6340.294
99 7TH FLOOR SLAB (+25150) LEV. KG 357.567 3226.738 192.405 0.000 0.000 0.000 0.000 3776.710
7TH FLOOR SLAB (+25150) LEV. KG 852.635 3987.503 212.523 704.556 1190.864 3168.924 0.000 10117.005
100 STAIR-1(6TH FLOOR TO 7TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
101 STAIR-2 (6TH FLOOR TO 7TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (6TH FLOOR TO 7TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 4131.212 6198.892 2673.968 3297.071 3188.148 5119.541 949.817 25558.649
TOTAL 7TH FLOOR SLAB =
MT 4.131 6.199 2.674 3.297 3.188 5.120 0.950 25.559 G
7TH FLOOR TO 8TH FLOOR KG
COLUMN (+25150) LEV. TO (+28300) LEV. KG
102 C-1 KG 0.000 288.444 12.565 231.475 0.000 0.000 0.000 532.484
103 C-2 KG 0.000 195.148 0.000 173.606 37.432 0.000 0.000 406.186
104 C-3 KG 434.759 0.000 0.000 0.000 786.074 60.957 0.000 1281.790
105 C-4 KG 0.000 615.796 0.000 0.000 449.185 60.957 0.000 1125.938
106 C-5 KG 382.420 195.148 150.784 393.507 0.000 0.000 0.000 1121.859
107 C-6 KG 379.112 194.741 257.589 185.180 0.000 0.000 0.000 1016.622
108 C-7 KG 160.955 66.000 0.000 0.000 0.000 335.262 422.141 984.358
109 C-8 KG 430.478 59.580 0.000 0.000 224.593 883.873 527.676 2126.201
110 C-9 KG 396.983 85.031 0.000 428.228 74.864 304.784 0.000 1289.889
111 C-10 KG 0.000 389.481 0.000 0.000 187.160 304.784 0.000 881.426
ALL COLUMN +25150 LEVEL TO +28300 LEV. KG 2184.707 2089.370 420.939 1411.995 1759.309 1950.617 949.817 10766.754
112 PASSENGER LIFT (+25150) LEV. TO KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
(+28300) LEV.
PASSENGER LIFT (+25150) LEV. TO (+28300) KG 932.648 122.019 0.000 1180.520 74.864 0.000 0.000 2310.051
LEV.
113 8TH FLOOR BEAM (+28300) KG 415.663 713.358 20.117 704.556 586.198 3168.924 0.000 5608.816
114 8TH FLOOR SLAB (+28300) LEV. KG 357.567 3111.068 0.000 0.000 0.000 0.000 0.000 3468.635
8TH FLOOR SLAB (+28300) LEV. KG 773.231 3824.426 20.117 704.556 586.198 3168.924 0.000 9077.451
115 STAIR-1(7TH FLOOR TO 8TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
116 STAIR-2 (7TH FLOOR TO 8TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (7TH FLOOR TO 8TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 4051.808 6035.815 2481.563 3297.071 2583.481 5119.541 949.817 24519.096
TOTAL 8TH FLOOR SLAB =
MT 4.052 6.036 2.482 3.297 2.583 5.120 0.950 24.519 H
8TH FLOOR TO 9TH FLOOR KG
COLUMN (+28300) LEV. TO (+31600) LEV. KG
117 C-1 KG 5.299 297.185 144.085 0.000 0.000 0.000 0.000 446.569
118 C-2 KG 0.000 201.062 98.240 24.096 0.000 0.000 0.000 323.397
119 C-3 KG 447.934 0.000 235.776 96.382 0.000 0.000 0.000 780.092
120 C-4 KG 0.000 634.457 0.000 240.956 116.741 0.000 0.000 992.154
121 C-5 KG 395.503 201.062 379.861 0.000 0.000 0.000 0.000 976.426
ALL COLUMN +28300 LEVEL TO +31600 LEV. KG 2271.598 2148.302 1565.291 361.434 836.642 1360.340 546.639 9090.246
127 PASSENGER LIFT (+28300) LEV. TO KG 962.622 125.716 0.000 1228.876 77.827 0.000 0.000 2395.041
(+31600) LEV.
PASSENGER LIFT (+28300) LEV. TO (+31600) KG 962.622 125.716 0.000 1228.876 77.827 0.000 0.000 2395.041
LEV.
128 9TH FLOOR BEAM (+31600) KG 412.361 803.165 20.117 704.556 515.827 3813.696 0.000 6269.723
129 9TH FLOOR SLAB (+31600) LEV. KG 357.567 3291.046 0.000 0.000 0.000 0.000 0.000 3648.614
9TH FLOOR SLAB (+31600) LEV. KG 769.928 4094.212 20.117 704.556 515.827 3813.696 0.000 9918.336
130 STAIR-1(8TH FLOOR TO 9TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
131 STAIR-2 (8TH FLOOR TO 9TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (8TH FLOOR TO 9TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 4165.370 6368.230 3625.915 2294.866 1593.407 5174.035 546.639 23768.463
TOTAL 9TH FLOOR SLAB =
MT 4.165 6.368 3.626 2.295 1.593 5.174 0.547 23.768 I
9TH FLOOR TO 10TH FLOOR KG
COLUMN (+31600) LEV. TO (+34900) LEV. KG
132 C-1 KG 5.299 297.185 144.085 0.000 0.000 0.000 0.000 446.569
133 C-2 KG 0.000 201.062 98.240 24.096 0.000 0.000 0.000 323.397
134 C-3 KG 447.934 0.000 235.776 96.382 0.000 0.000 0.000 780.092
135 C-4 KG 0.000 634.457 0.000 240.956 116.741 0.000 0.000 992.154
136 C-5 KG 399.019 201.062 379.861 0.000 0.000 0.000 0.000 979.942
137 C-6 KG 392.069 200.642 373.312 0.000 0.000 0.000 0.000 966.023
138 C-7 KG 165.833 68.000 0.000 0.000 214.025 253.086 0.000 700.944
139 C-8 KG 445.504 59.580 0.000 0.000 247.704 967.785 572.429 2293.002
140 C-9 KG 412.147 85.031 334.016 0.000 0.000 0.000 0.000 831.193
141 C-10 KG 7.310 401.284 0.000 0.000 272.395 189.815 0.000 870.804
ALL COLUMN +31600 LEVEL TO +34900 LEV. KG 2275.113 2148.302 1565.291 361.434 850.864 1410.687 572.429 9184.120
142 PASSENGER LIFT (+31600) LEV. TO KG 962.622 125.716 0.000 1228.876 77.827 0.000 0.000 2395.041
(+34900) LEV.
PASSENGER LIFT (+31600) LEV. TO (+34900)
LEV. KG 962.622 125.716 0.000 1228.876 77.827 0.000 0.000 2395.041
143 10TH FLOOR BEAM (+34900) KG 381.189 770.964 32.341 627.123 621.778 3105.208 0.000 5538.603
144 10TH FLOOR SLAB (+34900) LEV. KG 397.787 3936.029 0.000 0.000 0.000 0.000 0.000 4333.816
10TH FLOOR SLAB (+34900) LEV. KG 778.976 4706.994 32.341 627.123 621.778 3105.208 0.000 9872.419
145 STAIR-1(9TH FLOOR TO 10TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
145 STAIR-2 (9TH FLOOR TO 10TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (9TH FLOOR TO 10TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 4177.933 6981.012 3638.139 2217.432 1713.580 4515.895 572.429 23816.420
TOTAL 10TH FLOOR SLAB =
MT 4.178 6.981 3.638 2.217 1.714 4.516 0.572 23.816 J
146 C-1 KG 26.493 297.185 161.685 0.000 0.000 0.000 0.000 485.363
147 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
148 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
149 C-4 KG 0.000 727.759 0.000 269.400 130.074 0.000 0.000 1127.234
150 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
152 C-7 KG 225.140 78.000 0.000 0.000 238.469 280.864 0.000 822.473
153 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
154 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
155 C-10 KG 36.551 401.284 0.000 0.000 303.506 210.648 0.000 951.989
ALL COLUMN +34900 LEVEL TO +38650 LEV. KG 1677.390 2467.704 1575.264 404.101 672.049 491.512 0.000 7288.020
156 PASSENGER LIFT (+34900) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+38650) LEV.
PASSENGER LIFT (+34900) LEV. TO (+38650) LEV. KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
157 11TH FLOOR BEAM (+38650) KG 493.601 834.421 32.341 616.608 1226.889 3294.483 0.000 6498.343
158 11TH FLOOR SLAB (+38650) LEV. KG 397.787 4046.560 192.405 0.000 0.000 0.000 0.000 4636.752
11TH FLOOR SLAB & BEAM (+38650) LEV. KG 891.388 4880.981 224.747 616.608 1226.889 3294.483 0.000 11135.095
159 STAIR 1 (10TH FLOOR TO 11TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
160 STAIR-2 (10TH FLOOR TO 11TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (10TH FLOOR TO 11TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
161 C-1 KG 26.493 297.185 161.685 0.000 0.000 0.000 0.000 485.363
162 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
163 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
164 C-4 KG 0.000 727.759 0.000 269.400 130.074 0.000 0.000 1127.234
165 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
166 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
167 C-7 KG 225.140 78.000 0.000 0.000 238.469 280.864 0.000 822.473
168 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
169 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
170 C-10 KG 36.551 401.284 0.000 0.000 303.506 210.648 0.000 951.989
ALL COLUMN +38650 LEVEL TO +42400 LEV. KG 1677.390 2467.704 1575.264 404.101 672.049 491.512 0.000 7288.020
171 PASSENGER LIFT (+38650) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+42400) LEV.
PASSENGER LIFT (+38650) LEV. TO (+42400)
LEV. KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
172 12TH FLOOR BEAM (+42400) KG 414.197 787.014 32.341 616.608 622.222 3294.483 0.000 5766.865
173 12TH FLOOR SLAB (+42400) LEV. KG 397.787 3936.029 0.000 0.000 0.000 0.000 0.000 4333.816
12TH FLOOR SLAB & BEAM (+42400) LEV. KG 811.984 4723.043 32.341 616.608 622.222 3294.483 0.000 10100.681
174 STAIR 1 (11TH FLOOR TO 12TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
175 STAIR-2 (11TH FLOOR TO 12TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (11TH FLOOR TO 12TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
176 C-1 KG 26.493 297.185 161.685 0.000 0.000 0.000 0.000 485.363
178 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
179 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
180 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
181 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
182 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
183 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
184 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
185 C-10 KG 36.551 401.284 0.000 0.000 433.580 0.000 0.000 871.415
ALL COLUMN +42400 LEVEL TO +46150 LEV. KG 1677.390 2467.704 1626.709 538.801 607.012 0.000 0.000 6917.617
186 PASSENGER LIFT (+42400) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+46150) LEV.
PASSENGER LIFT (+42400) LEV. TO (+46150) KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
LEV.
187 13TH FLOOR BEAM (+46150) KG 414.197 787.014 32.341 616.608 622.222 3294.483 0.000 5766.865
188 13TH FLOOR SLAB (+46150) LEV. KG 397.787 3927.543 0.000 0.000 0.000 0.000 0.000 4325.330
13TH FLOOR SLAB & BEAM (+46150) LEV. KG 811.984 4714.556 32.341 616.608 622.222 3294.483 0.000 10092.194
189 STAIR 1 (12TH FLOOR TO 13TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
190 STAIR-2 (12TH FLOOR TO 13TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (12TH FLOOR TO 13TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
191 C-1 KG 26.493 297.185 161.685 0.000 0.000 0.000 0.000 485.363
192 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
193 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
194 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
195 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
196 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
197 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
198 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
199 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
200 C-10 KG 36.551 401.284 0.000 0.000 433.580 0.000 0.000 871.415
ALL COLUMN +46150 LEVEL TO +49900 LEV. KG 1677.390 2467.704 1626.709 538.801 607.012 0.000 0.000 6917.617
201 PASSENGER LIFT (+46150) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+49900) LEV.
PASSENGER LIFT (+46150) LEV. TO (+49900)
LEV. KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
202 14TH FLOOR BEAM (+49900) KG 414.197 787.014 32.341 616.608 622.222 3294.483 0.000 5766.865
203 14TH FLOOR SLAB (+49900) LEV. KG 397.787 3919.485 0.000 0.000 0.000 0.000 0.000 4317.272
14TH FLOOR SLAB & BEAM (+49900) LEV. KG 811.984 4706.498 32.341 616.608 622.222 3294.483 0.000 10084.136
204 STAIR 1 (13TH FLOOR TO 14TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
205 STAIR-2 (13TH FLOOR TO 14TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (13TH FLOOR TO 14TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
206 C-1 KG 26.493 297.185 161.685 0.000 0.000 0.000 0.000 485.363
207 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
208 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
209 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
210 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
211 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
212 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
213 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
214 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
215 C-10 KG 36.551 401.284 0.000 0.000 433.580 0.000 0.000 871.415
ALL COLUMN +49900 LEVEL TO +53650 LEV. KG 1677.390 2467.704 1626.709 538.801 607.012 0.000 0.000 6917.617
PASSENGER LIFT (+49900) LEV. TO
216 (+53650) LEV. KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
PASSENGER LIFT (+49900) LEV. TO (+53650) KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
LEV.
217 15TH FLOOR BEAM (+53650) KG 509.546 834.421 32.341 616.608 1226.889 3294.483 0.000 6514.288
218 15TH FLOOR SLAB (+53650) LEV. KG 397.787 4017.137 192.405 0.000 0.000 0.000 0.000 4607.330
15TH FLOOR SLAB & BEAM (+53650) LEV. KG 907.333 4851.558 224.747 616.608 1226.889 3294.483 0.000 11121.617
219 STAIR 1 (14TH FLOOR TO 15TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
220 STAIR-2 (14TH FLOOR TO 15TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (14TH FLOOR TO 15TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
222 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
223 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
224 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
225 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
226 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
227 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
228 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
229 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
230 C-10 KG 36.551 401.284 0.000 0.000 433.580 0.000 0.000 871.415
ALL COLUMN +53650 LEVEL TO +57400 LEV. KG 1677.390 2467.704 1626.709 538.801 607.012 0.000 0.000 6917.617
231 PASSENGER LIFT (+53650) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+57400) LEV.
PASSENGER LIFT (+53650) LEV. TO (+57400) KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
LEV.
232 16TH FLOOR BEAM (+57400) KG 317.080 901.977 32.743 1018.905 384.506 3032.948 0.000 5688.158
233 16TH FLOOR SLAB (+57400) LEV. KG 397.787 3244.252 0.000 0.000 0.000 0.000 0.000 3642.039
16TH FLOOR SLAB & BEAM (+57400) LEV. KG 714.867 4146.229 32.743 1018.905 384.506 3032.948 0.000 9330.197
234 STAIR 1 (15TH FLOOR TO 16TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (15TH FLOOR TO 16TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
237 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
238 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
239 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
240 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
241 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
242 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
243 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
244 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
245 C-10 KG 36.551 401.284 80.843 121.230 0.000 0.000 0.000 639.908
ALL COLUMN +57400 LEVEL TO +61150 LEV. KG 1677.390 2467.704 1707.552 660.031 173.432 0.000 0.000 6686.109
246 PASSENGER LIFT (+57400) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+61150) LEV.
PASSENGER LIFT (+57400) LEV. TO (+61150)
LEV. KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
247 17TH FLOOR BEAM (+61150) KG 430.142 787.014 32.341 616.608 622.222 3302.392 0.000 5790.718
248 17TH FLOOR SLAB (+61150) LEV. KG 397.787 3888.189 0.000 0.000 0.000 0.000 0.000 4285.976
17TH FLOOR SLAB & BEAM (+61150) LEV. KG 827.928 4675.203 32.341 616.608 622.222 3302.392 0.000 10076.694
250 STAIR-2 (16TH FLOOR TO 17TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (16TH FLOOR TO 17TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
252 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
253 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
254 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
255 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
256 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
257 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
258 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
259 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
260 C-10 KG 36.551 401.284 80.843 121.230 0.000 0.000 0.000 639.908
ALL COLUMN +61150 LEVEL TO +64900 LEV. KG 1677.390 2467.704 1707.552 660.031 173.432 0.000 0.000 6686.109
PASSENGER LIFT (+61150) LEV. TO
261 (+64900) LEV. KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
PASSENGER LIFT (+61150) LEV. TO (+64900) KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
LEV.
262 18TH FLOOR BEAM (+64900) KG 430.142 787.014 32.341 616.608 622.222 3302.392 0.000 5790.718
263 18TH FLOOR SLAB (+64900) LEV. KG 397.787 3877.455 0.000 0.000 0.000 0.000 0.000 4275.241
18TH FLOOR SLAB & BEAM (+64900) LEV. KG 827.928 4664.468 32.341 616.608 622.222 3302.392 0.000 10065.960
264 STAIR 1 (17TH FLOOR TO 18TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (17TH FLOOR TO 18TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 3770.962 7276.376 3780.400 2650.581 1045.481 3302.392 0.000 21826.193
TOTAL 18TH FLOOR SLAB =
MT 3.771 7.276 3.780 2.651 1.045 3.302 0.000 21.826 R
18TH FLOOR TO 19TH FLOOR KG
COLUMN (+64900) LEV. TO (+68650) LEV. KG
266 C-1 KG 26.493 297.185 161.685 0.000 0.000 0.000 0.000 485.363
267 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
268 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
269 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
270 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
271 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
272 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
273 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
274 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
275 C-10 KG 36.551 401.284 80.843 121.230 0.000 0.000 0.000 639.908
ALL COLUMN +64900 LEVEL TO +68650 LEV. KG 1677.390 2467.704 1707.552 660.031 173.432 0.000 0.000 6686.109
276 PASSENGER LIFT (+64900) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+68650) LEV.
PASSENGER LIFT (+64900) LEV. TO (+68650) KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
LEV.
278 19TH FLOOR SLAB (+68650 MM) LEV. KG 397.787 3877.455 0.000 0.000 0.000 0.000 0.000 4275.241
19TH FLOOR SLAB & BEAM (+68650) LEV. KG 907.333 4711.876 32.341 616.608 1226.889 3302.392 0.000 10797.438
279 STAIR 1 (18TH FLOOR TO 19TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
280 STAIR-2 (18TH FLOOR TO 19TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (18TH FLOOR TO 19TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 3850.366 7323.783 3780.400 2650.581 1650.148 3302.392 0.000 22557.671
TOTAL 19TH FLOOR SLAB =
MT 3.850 7.324 3.780 2.651 1.650 3.302 0.000 22.558 S
19TH FLOOR TO 20TH FLOOR KG
COLUMN (+68650) LEV. TO (+72400) LEV. KG
281 C-1 KG 26.493 297.185 161.685 0.000 0.000 0.000 0.000 485.363
282 C-2 KG 0.000 230.630 110.240 26.940 0.000 0.000 0.000 367.810
283 C-3 KG 513.806 0.000 264.576 107.760 0.000 0.000 0.000 886.142
284 C-4 KG 0.000 727.759 51.445 255.930 0.000 0.000 0.000 1035.135
285 C-5 KG 471.449 201.062 426.261 0.000 0.000 0.000 0.000 1098.772
286 C-6 KG 316.512 230.148 352.768 0.000 0.000 0.000 0.000 899.429
287 C-7 KG 225.140 78.000 0.000 148.170 173.432 0.000 0.000 624.743
288 C-9 KG 55.912 192.068 164.192 0.000 0.000 0.000 0.000 412.172
289 C-9A KG 31.526 109.568 95.541 0.000 0.000 0.000 0.000 236.635
290 C-10 KG 36.551 401.284 80.843 121.230 0.000 0.000 0.000 639.908
ALL COLUMN +68650 LEVEL TO +72400 LEV. KG 1677.390 2467.704 1707.552 660.031 173.432 0.000 0.000 6686.109
291 PASSENGER LIFT (+68650) LEV. TO KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
(+72400) LEV.
PASSENGER LIFT (+68650) LEV. TO (+72400) KG 1104.422 144.204 0.000 1373.943 86.716 0.000 0.000 2709.284
LEV.
292 20TH FLOOR BEAM (+72400 MM) KG 430.142 787.014 32.341 616.608 622.222 3302.392 0.000 5790.718
293 20TH FLOOR SLAB (+72400 MM) LEV. KG 193.142 3987.985 192.405 0.000 0.000 0.000 0.000 4373.533
20TH FLOOR SLAB & BEAM (+72400) LEV. KG 623.283 4774.999 224.747 616.608 622.222 3302.392 0.000 10164.251
294 STAIR 1 (19TH FLOOR TO 20TH FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
295 STAIR-2 (19TH FLOOR TO 20TH KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR (19TH FLOOR TO 20TH FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 3566.317 7386.906 3972.805 2650.581 1045.481 3302.392 0.000 21924.484
TOTAL 20TH FLOOR SLAB =
MT 3.566 7.387 3.973 2.651 1.045 3.302 0.000 21.924 T
20TH FLOOR TO 21ST FLOOR KG
COLUMN (+72400) LEV. TO (+76600) LEV. KG
296 C-1 KG 42.389 297.185 179.285 0.000 0.000 0.000 0.000 518.859
297 C-2 KG 0.000 254.284 122.240 29.784 0.000 0.000 0.000 406.308
298 C-3 KG 566.504 0.000 293.376 119.138 0.000 0.000 0.000 979.018
299 C-4 KG 0.000 802.401 57.045 282.953 0.000 0.000 0.000 1142.399
300 C-5 KG 534.330 201.062 472.661 0.000 0.000 0.000 0.000 1208.053
301 C-6 KG 492.819 253.753 464.512 0.000 0.000 0.000 0.000 1211.084
302 C-7 KG 250.470 86.000 0.000 163.815 191.210 0.000 0.000 691.495
303 C-9 KG 69.890 192.068 180.992 0.000 0.000 0.000 0.000 442.950
304 C-9A KG 39.407 109.568 105.941 0.000 0.000 0.000 0.000 254.917
305 C-10 KG 58.482 401.284 89.643 134.030 0.000 0.000 0.000 683.439
ALL COLUMN +72400 LEVEL TO +76600 LEV. KG 2054.291 2597.605 1965.696 729.720 191.210 0.000 0.000 7538.522
PASSENGER LIFT (+72400) LEV. TO (+76600) KG 1224.318 158.994 0.000 1519.009 95.605 0.000 0.000 2997.926
LEV.
307 21ST FLOOR BEAM (+76600 MM) KG 430.142 787.014 32.341 616.608 622.222 3302.392 0.000 5790.718
308 21ST FLOOR SLAB (+76600 MM) LEV. KG 397.787 3877.455 0.000 0.000 0.000 0.000 0.000 4275.241
21ST FLOOR SLAB & BEAM (+76600) LEV. KG 827.928 4664.468 0.000 616.608 622.222 3302.392 0.000 10033.619
309 STAIR 1 (20TH FLOOR TO 21ST FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
310 STAIR-2 (20TH FLOOR TO 21ST FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (20TH FLOOR TO 21ST FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 4267.759 7421.067 4006.203 2865.337 1072.148 3302.392 0.000 22934.906
TOTAL 21ST FLOOR SLAB =
MT 4.268 7.421 4.006 2.865 1.072 3.302 0.000 22.935 U
21ST FLOOR TO 22ND FLOOR KG
COLUMN (+76600) LEV. TO (+80800) LEV. KG
296 C-1 KG 42.389 297.185 179.285 0.000 0.000 0.000 0.000 518.859
297 C-2 KG 0.000 254.284 122.240 29.784 0.000 0.000 0.000 406.308
298 C-3 KG 566.504 0.000 293.376 119.138 0.000 0.000 0.000 979.018
299 C-4 KG 0.000 802.401 57.045 282.953 0.000 0.000 0.000 1142.399
300 C-5 KG 534.330 201.062 472.661 0.000 0.000 0.000 0.000 1208.053
301 C-6 KG 492.819 253.753 464.512 0.000 0.000 0.000 0.000 1211.084
302 C-7 KG 250.470 86.000 0.000 163.815 191.210 0.000 0.000 691.495
303 C-9 KG 69.890 192.068 180.992 0.000 0.000 0.000 0.000 442.950
304 C-9A KG 39.407 109.568 105.941 0.000 0.000 0.000 0.000 254.917
305 C-10 KG 58.482 401.284 89.643 134.030 0.000 0.000 0.000 683.439
ALL COLUMN +76600 LEVEL TO +80800 LEV. KG 2054.291 2597.605 1965.696 729.720 191.210 0.000 0.000 7538.522
306 PASSENGER LIFT (+76600) LEV. TO KG 1224.318 158.994 0.000 1519.009 95.605 0.000 0.000 2997.926
(+80800) LEV.
PASSENGER LIFT (+76600) LEV. TO (+80800)
LEV. KG 1224.318 158.994 0.000 1519.009 95.605 0.000 0.000 2997.926
307 22ND FLOOR BEAM (+80800 MM) KG 430.142 787.014 32.341 616.608 622.222 3302.392 0.000 5790.718
308 22ND FLOOR SLAB (+80800 MM) LEV. KG 397.787 11361.336 0.000 0.000 0.000 0.000 0.000 11759.123
22ND FLOOR SLAB & BEAM (+80800) LEV. KG 827.928 12148.350 0.000 616.608 622.222 3302.392 0.000 17517.500
309 STAIR 1 (21ST FLOOR TO 22ND FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
STAIR (21ST FLOOR TO 22ND FLOOR) KG 161.222 0.000 2040.507 0.000 163.111 0.000 0.000 2364.839
KG 4267.759 14904.948 4006.203 2865.337 1072.148 3302.392 0.000 30418.788
TOTAL 22ND FLOOR SLAB =
MT 4.268 14.905 4.006 2.865 1.072 3.302 0.000 30.419 V
22ND FLOOR TO 23RD FLOOR KG
COLUMN (+80800) LEV. TO (+84300) LEV. KG
296 C-1 KG 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
297 C-2 KG 0.000 212.889 116.907 28.520 0.000 0.000 0.000 358.316
298 C-3 KG 474.283 0.000 280.576 114.081 0.000 0.000 0.000 868.940
299 C-4 KG 0.000 0.000 7.467 36.030 0.000 0.000 0.000 43.496
300 C-5 KG 449.793 201.062 452.039 0.000 0.000 0.000 0.000 1102.894
301 C-6 KG 410.566 212.444 444.245 0.000 0.000 0.000 0.000 1067.255
302 C-7 KG 210.508 72.000 0.000 156.862 183.309 0.000 0.000 622.678
303 C-9 KG 69.890 192.068 173.525 0.000 0.000 0.000 0.000 435.484
304 C-9A KG 39.407 109.568 101.319 0.000 0.000 0.000 0.000 250.294
ALL COLUMN +80800 LEVEL TO +84300 LEV. KG 1712.928 1401.315 1661.810 463.834 183.309 0.000 0.000 5423.196
306 PASSENGER LIFT (+80800) LEV. TO KG 1388.021 181.179 0.000 1712.431 107.457 0.000 0.000 3389.088
(+85600) LEV.
PASSENGER LIFT (+80800) LEV. TO (+85600) KG 1388.021 181.179 0.000 1712.431 107.457 0.000 0.000 3389.088
LEV.
307 23RD FLOOR BEAM (+84300 MM) KG 322.667 727.162 12.224 394.551 511.235 2928.819 0.000 4896.659
308 23RD FLOOR SLAB (+84300 MM) LEV. KG 526.788 3019.261 0.000 0.000 0.000 0.000 0.000 3546.048
23TH FLOOR SLAB & BEAM (+84300) LEV. KG 849.455 3746.423 0.000 394.551 511.235 2928.819 0.000 8430.483
309 STAIR 1 (22ND FLOOR TO 23RD KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
FLOOR)
STAIR1 (22ND FLOOR TO 23RD FLOOR) KG 80.611 0.000 1020.253 0.000 81.556 0.000 0.000 1182.420
KG 4031.015 5328.916 2682.063 2570.817 883.556 2928.819 0.000 18425.186
TOTAL 23RD FLOOR SLAB =
MT 4.031 5.329 2.682 2.571 0.884 2.929 0.000 18.425 W
EXTRA REINFORCEMENT KG 50.054 151.009 75.083 470.635 311.852 915.702 755.282 2729.618
KG 50.054 151.009 75.083 470.635 311.852 915.702 755.282 2729.618 V
TOTAL EXTRA REINFORCEMENT =
MT 0.050 0.151 0.075 0.471 0.312 0.916 0.755 2.730
X=(A+B+C+D+E+F+G
GRAND TOTAL = MT 93.653 160.957 72.414 67.297 41.059 95.260 15.542 546.182 +H+I+J+K+L+M+N+O
+P+Q+R+S+T+U+V+
W)
PREVIOUS PAID QUANTATY = MT 89.622 156.252 69.732 64.726 40.176 92.331 15.542 528.38 Y
THIS BILL QUANTATY = MT 4.031 4.705 2.682 2.571 0.884 2.929 0.000 17.802 Z=X-Y
NAME OF THE CONTRUCTOR : M/S S.M. NIRMAN INFRASTRUCTURE & DEVELOPMENT PVT. LTD.
C-2
VERTICAL 3.500
16 3.500 4 1 16.000 1.580 25.284 - - - 25.284 - - -
LAP 0.512
16 0.512 4 1 2.048 1.580 3.236 - - - 3.236 - - -
VERTICAL 3.500
12 3.500 30 1 120.000 0.889 106.667 - - 106.667 - - - -
LAP 0.384
12 0.384 30 1 11.520 0.889 10.240 - - 10.240 - - - -
1.130
STIRRUPS 0.280 0.280
10 100 1.130 2.940 36 1 105.840 0.617 65.333 - 65.333 - - - - -
STIRRUPS
10 100 0.790 36 2 56.880 0.617 35.111 - 35.111 - - - - -
C-3
VERTICAL 3.500
16 3.500 16 1 64.000 1.580 101.136 - - - 101.135802 - - -
LAP 0.512
16 0.512 16 1 8.192 1.580 12.945 - - - 12.9453827 - - -
VERTICAL 3.500
12 3.500 72 1 288.000 0.889 256.000 - - 256 - - - -
LAP 0.384
12 0.384 72 1 27.648 0.889 24.576 - - 24.576 - - - -
1.493
STIRRUPS 0.178 0.178
8 100 BE MAIN 1.493 3.438 36 2 247.536 0.395 97.792 97.792 - - - - - -
LINKS
C-4
VERTICAL 0.600
16 0.600 38 1 22.800 1.580 36.030 - - - 36.030 - - -
LAP 0.000
16 0.000 38 1 0.000 1.580 0.000 - - - 0.000 - - -
VERTICAL 0.600
12 0.600 14 1 8.400 0.889 7.467 - - 7.467 - - - -
LAP 0.000
12 0.000 14 1 0.000 0.889 0.000 - - 0.000 - - - -
C-5
VERTICAL 3.500
12 F7 3.500 34 1 136.000 0.889 120.889 - - 120.889 - - - -
LAP 0.384
12 0.384 34 1 13.056 0.889 11.605 - - 11.605 - - - -
1.130
STIRRUPS 0.280 0.280
10 100 Z1 MAIN 1.130 2.940 34 1 99.960 0.617 61.704 - 61.704 - - - - -
LINKS
STIRRUPS
10 100 Z1 OTHERS 0.790 34 2 53.720 0.617 33.160 - 33.160 - - - - -
1.128
STIRRUPS 0.278 0.278
8 125 Z2 MAIN 1.128 2.908 8 1 23.264 0.395 9.191 9.191 - - - - - -
LINKS
STIRRUPS
8 125 0.762 8 2 12.192 0.395 4.817 4.817 - - - - - -
F8 VERTICAL 3.500
12 3.500 82 1 328.000 0.889 291.556 - - 291.556 - - - -
LAP 0.384
12 0.384 82 1 31.488 0.889 27.989 - - 27.989 - - - -
1.668
STIRRUPS 0.178 0.178
53.874 - - - - - -
S.M. NIRMAN INFRASTRUCTURE DEVELOPMENT PVT. LTD.
CONSYNC INFRA PVT. LTD.
REINFORCEMENT RECORD ENTRY
PAGE NO - 46
23RD RA
1.493
STIRRUPS 0.178 0.178
8 100 1.493 3.438 36 1 123.768 0.395 48.896 48.896 - - - - - -
C-6
F6 VERTICAL 3.500
12 3.500 34 1 136.000 0.889 120.889 - - 120.889 - - - -
LAP 0.384
12 0.384 34 1 13.056 0.889 11.605 - - 11.605 - - - -
1.130
STIRRUPS 0.280 0.280
10 100 Z1 MAIN 1.130 2.940 36 1 105.840 0.617 65.333 - 65.333 - - - - -
LINKS
STIRRUPS
10 100 Z1 OTHERS 0.780 36 2 56.160 0.617 34.667 - 34.667 - - - - -
F5 VERTICAL 3.500
12 3.500 80 1 320.000 0.889 284.444 - - 284.444 - - - -
LAP 0.384
12 0.384 80 1 30.720 0.889 27.307 - - 27.307 - - - -
1.628
STIRRUPS 0.178 0.178
8 100 BE MAIN LINK 1.628 3.708 36 1 133.488 0.395 52.736 52.736 - - - - - -
1.493
STIRRUPS 0.178 0.178
8 100 BE MAIN LINK 1.493 3.438 36 1 123.768 0.395 48.896 48.896 - - - - - -
6.328
STIRRUPS 0.178 0.178
8 125 MID MAIN 6.328 13.108 29 1 380.132 0.395 150.176 150.176 - - - - - -
LINKS
C-7
VERTICAL 3.500
20 3.500 16 1 64.000 2.469 158.025 - - - - 158.025 - -
LAP 0.640
20 0.640 16 1 10.240 2.469 25.284 - - - - 25.284 - -
VERTICAL 3.500
- - - 139.061728 - - -
S.M. NIRMAN INFRASTRUCTURE DEVELOPMENT PVT. LTD.
CONSYNC INFRA PVT. LTD.
REINFORCEMENT RECORD ENTRY
PAGE NO - 48
23RD RA
LAP 0.512
16 0.512 22 1 11.264 1.580 17.800 - - - 17.7999012 - - -
0.470
STIRRUPS 0.280 0.280
10 100 BE MAIN 0.470 1.620 36 2 116.640 0.617 72.000 - 72.000 - - - - -
LINKS
C-9
F1 VERTICAL 3.500
12 3.764 42 1 179.088 0.889 159.189 - - 159.189333 - - - -
LAP 0.384
12 0.384 42 1 16.128 0.889 14.336 - - 14.336 - - - -
F1 0.705
STIRRUPS 0.280 0.280
10 100 Z1 MAIN 0.705 2.090 25 1 52.250 0.617 32.253 - 32.253 - - - - -
LINKS
F1 1.430
F1
LINKS 0.110 0.110
10 100 Z1 OTHERS 0.280 0.460 25 4 46.000 0.617 28.395 - 28.395 - - - - -
F1
LINKS 0.110 0.110
10 100 Z1 OTHERS 0.180 0.360 25 10 90.000 0.617 55.556 - 55.556 - - - - -
F1 0.703
STIRRUPS 0.278 0.278
8 125 Z2 MAIN 0.703 2.058 15 1 30.870 0.395 12.196 12.19555556 - - - - - -
LINKS
F1 1.428
STIRRUPS 0.178 0.178
8 125 Z2 MAIN 1.428 3.308 15 1 49.620 0.395 19.603 19.60296296 - - - - - -
LINKS
F1
STIRRUPS
8 125 Z2 OTHERS 0.760 15 2 22.800 0.395 9.007 9.007 - - - - - -
F1
LINKS 0.088 0.088
8 125 Z2 OTHERS 0.278 0.422 15 4 25.320 0.395 10.003 10.003 - - - - - -
F1
LINKS 0.088 0.088
8 125 Z2 OTHERS 0.178 0.322 15 10 48.300 0.395 19.081 19.081 - - - - - -
C-9A
F2 VERTICAL 3.500
12 3.500 26 1 104.000 0.889 92.444 - - 92.444 - - - -
LAP 0.384
12 0.384 26 1 9.984 0.889 8.875 - - 8.875 - - - -
F2 1.330
STIRRUPS 0.180 0.180
10 100 Z1 MAIN 1.330 3.140 25 1 78.500 0.617 48.457 - 48.457 - - - - -
LINKS
F2
LINKS 0.110 0.110
10 100 Z1 OTHERS 0.180 0.360 25 11 99.000 0.617 61.111 - 61.111 - - - - -
F2 1.328
STIRRUPS 0.178 0.178
8 125 Z2 MAIN 1.328 3.108 15 1 46.620 0.395 18.418 18.41777778 - - - - - -
LINKS
F1
LINKS 0.088 0.088
8 125 Z2 OTHERS 0.178 0.322 15 11 53.130 0.395 20.990 20.990 - - - - - -
C-10
VERTICAL 3.500
16 3.500 18 1 72.000 1.580 113.778 - - - 113.778 - - -
LAP 0.512
16 0.512 18 1 9.216 1.580 14.564 - - - 14.564 - - -
VERTICAL 3.500
12 3.500 22 1 88.000 0.889 78.222 - - 78.222 - - - -
LAP 0.384
12 0.384 22 1 8.448 0.889 7.509 - - 7.509 - - - -
1.130
STIRRUPS 0.530 0.530
10 100 Z1 MAIN 1.130 3.440 34 1 116.960 0.617 72.198 - 72.198 - - - - -
LINKS
1.128
STIRRUPS 0.528 0.528
8 125 Z2 MAIN 1.128 3.408 8 1 27.264 0.395 10.771 10.771 - - - - - -
LINKS
PASSENGER LIFT
VERTICAL 4.800
20 4.800 8 1 38.400 2.469 94.815 - - - - 94.815 - -
LAP 0.640
20 0.640 8 1 5.120 2.469 12.642 - - - - 12.642 - -
VERTICAL 4.800
16 4.800 204 1 979.200 1.580 1547.378 - - - 1547.378 - - -
LAP 0.512
16 0.512 204 1 104.448 1.580 165.054 - - - 165.054 - - -
F9 1.668
F9
LINKS 0.178 0.178
8 100 MID MAIN 6.428 6.912 49 2 677.376 0.395 267.605 267.605 - - - - - -
F9
LINKS 0.088 0.088
8 100 MID OTHERS 0.178 0.322 49 10 157.780 0.395 62.333 62.333 - - - - - -
F10 0.693
STIRRUPS 0.178 0.178
8 100 BE MAIN 0.693 1.838 49 1 90.062 0.395 35.580 35.580 - - - - - -
LINKS
F10 0.568
STIRRUPS 0.178 0.178
8 100 BE MAIN 0.568 1.588 49 1 77.812 0.395 30.741 30.741 - - - - - -
LINKS
F10
LINKS 0.088 0.088
8 100 BE OTHERS 0.178 0.322 49 8 126.224 0.395 49.866 49.866 - - - - - -
F10 2.528
STIRRUPS 0.178 0.178
8 125 MID MAIN 2.528 5.508 39 1 214.812 0.395 84.864 84.864 - - - - - -
LINKS
F10
LINKS 0.088 0.088
8 125 MID OTHERS 0.178 0.322 39 4 50.232 0.395 19.845 19.845 - - - - - -
F11 0.650
STIRRUPS 0.110 0.110
10 100 BE MAIN 0.650 1.640 49 1 80.360 0.617 49.605 - 49.605 - - - - -
LINKS
F11 0.550
STIRRUPS 0.110 0.110
10 100 BE MAIN 0.550 1.440 49 1 70.560 0.617 43.556 - 43.556 - - - - -
LINKS
F11
F11 2.528
STIRRUPS 0.108 0.108
8 125 MID MAIN 2.528 5.368 39 1 209.352 0.395 82.707 82.707 - - - - - -
LINKS
F11
LINKS 0.088 0.088
8 125 MID OTHERS 0.178 0.322 39 4 50.232 0.395 19.845 19.845 - - - - - -
F12 0.620
STIRRUPS 0.110 0.110
10 100 BE MAIN 0.620 1.580 49 1 77.420 0.617 47.790 - 47.790 - - - - -
LINKS
F12 0.495
STIRRUPS 0.110 0.110
10 100 BE MAIN 0.495 1.330 49 1 65.170 0.617 40.228 - 40.228 - - - - -
LINKS
F12
LINKS 0.088 0.088
8 100 BE OTHERS 0.108 0.252 49 6 74.088 0.395 29.269 29.269 - - - - - -
F12 2.528
STIRRUPS 0.108 0.108
8 125 MID MAIN 2.528 5.368 39 1 209.352 0.395 82.707 82.707 - - - - - -
LINKS
F12
LINKS 0.088 0.088
8 125 MID OTHERS 0.178 0.322 39 5 62.790 0.395 24.806 24.806 - - - - - -
F13 0.643
STIRRUPS 0.178 0.178
8 100 BE MAIN 0.643 1.738 49 1 85.162 0.395 33.644 33.644 - - - - - -
LINKS
F13 0.518
STIRRUPS 0.178 0.178
8 100 BE MAIN 0.518 1.488 49 1 72.912 0.395 28.805 28.805 - - - - - -
LINKS
F13
LINKS 0.088 0.088
8 100 BE OTHERS 0.178 0.322 49 6 94.668 0.395 37.400 37.400 - - - - - -
F13 2.528
LB1,LB2,LB3 (250X600)
BOTTOM
16 0.422 0.422 7.188 2 1 14.376 1.580 22.718 - - - 22.718 - - -
6.440
BOTTOM
12 0.254 0.254 6.876 1 1 6.876 0.889 6.112 - - 6.112 - - - -
6.440
250X600 0.550
STIRRUPS 0.200 0.200
10 100 0.550 1.620 20 3 97.200 0.617 60.000 - 60.000 - - - - -
B1 (300X600)
BOTTOM
16 & 0.422 0.322 6.988 5 1 34.940 1.580 55.214 - - - 55.214 - - -
TOP 6.340
BOTTOM
20 0.590 0.490 7.300 1 1 7.300 2.469 18.025 - - - - 18.025 - -
6.340
300X600 0.548
STIRRUPS 0.248 0.248
8 100 0.548 1.688 10 2 33.760 0.395 13.337 13.337 - - - - - -
300X600 0.548
STIRRUPS 0.248 0.248
8 150 0.548 1.688 27 1 45.576 0.395 18.005 18.005 - - - - - -
B3 (300X600)
BOTTOM
20 0.600 0.600 7.420 3 1 22.260 2.469 54.963 - - - - 54.963 - -
6.340
300X600 0.558
STIRRUPS 0.248 0.248
8 150 0.548 1.698 40 1 67.920 0.395 26.833 26.833 - - - - - -
BOTTOM
25 15.750 3 1 47.250 3.858 182.292 - - - - - 182.292 -
15.750
BOTTOM
25 lap 0.875 3 1 2.625 3.858 10.127 - - - - - 10.127 -
0.875
BOTTOM
16 10.822 3 1 32.466 1.580 51.304 - - - 51.3042963 - - -
10.822
TOP
25 15.750 2 1 31.500 3.858 121.528 - - - - - 121.528 -
15.750
TOP
25 12.250 1 1 12.250 3.858 47.261 - - - - - 47.261 -
12.250
TOP
25 lap 0.875 3 1 2.625 3.858 10.127 - - - - - 10.127 -
0.875
- - - - - 41.088 -
S.M. NIRMAN INFRASTRUCTURE DEVELOPMENT PVT. LTD.
CONSYNC INFRA PVT. LTD.
REINFORCEMENT RECORD ENTRY
PAGE NO - 57
23RD RA
TOP 3.550
25 EXTRA 3.550 3 1 10.650 3.858 41.088 - - - - - 41.088 -
C10
TOP 3.340
20 EXTRA 3.340 3 1 10.020 2.469 24.741 - - - - 24.741 - -
C10
TOP 5.050
25 EXTRA 5.050 3 1 15.150 3.858 58.449 - - - - - 58.449 -
C9
TOP 3.550
25 EXTRA 3.550 3 1 10.650 3.858 41.088 - - - - - 41.088 -
C9
TOP 2.100
25 EXTRA 2.100 3 2 12.600 3.858 48.611 - - - - - 48.611 -
C9A
300X750 0.710
STIRRUPS 0.260 0.260
10 100 C10 TO C9 0.710 2.060 88 1 181.280 0.617 111.901 - 111.901 - - - - -
300X750 0.710
STIRRUPS 0.260 0.260
10 100 C9 TO C9A 0.710 2.060 36 1 74.160 0.617 45.778 - 45.778 - - - - -
BOTTOM
25 0.450 24.020 4 1 96.080 3.858 370.679 - - - - - 370.679 -
23.645
LAP 0.800
25 0.800 4 2 6.400 3.858 24.691 - - - - - 24.691 -
LAP 0.800
25 0.800 2 2 3.200 3.858 12.346 - - - - - 12.346 -
TOP 20.150
25 20.150 2 1 40.300 3.858 155.478 - - - - - 155.478 -
LAP 0.800
25 0.800 2 1 1.600 3.858 6.173 - - - - - 6.173 -
TOP 3.450
25 EXTRA 3.450 3 1 10.350 3.858 39.931 - - - - - 39.931 -
OVER C1
TOP 3.240
20 EXTRA 3.240 1 1 3.240 2.469 8.000 - - - - 8.000 - -
OVER C1
TOP
LAYER 0.240
25 PIN 0.240 9 1 2.160 3.858 8.333 - - - - - 8.333 -
TOP
20 EXTRA 5.450 5.450 4 1 21.800 2.469 53.827 - - - - 53.827 - -
OVER C4
TOP
LAYER 0.240
25 PIN 0.240 18 1 4.320 3.858 16.667 - - - - - 16.667 -
TOP
25 EXTRA 6.000 6.000 3 1 18.000 3.858 69.444 - - - - - 69.444 -
OVER C7
TOP
20 EXTRA 6.000 6.000 1 1 6.000 2.469 14.815 - - - - 14.815 - -
OVER C7
TOP
LAYER 0.240
25 PIN 0.240 15 1 3.600 3.858 13.889 - - - - - 13.889 -
300X750 0.698
STIRRUPS 0.132 0.132
4L 8 100 B4A 0.698 1.756 16 4 112.384 0.395 44.399 44.399 - - - - - -
300X750 0.698
STIRRUPS 0.132 0.132
4L 8 150 B4A 0.698 1.756 28 2 98.336 0.395 38.849 38.849 - - - - - -
300X750 0.700
STIRRUPS 0.250 0.250
10 100 B4 0.700 2.020 76 1 153.520 0.617 94.765 - 94.765 - - - - -
300X750 0.700
STIRRUPS 0.250 0.250
10 100 B5 0.700 2.020 58 1 117.160 0.617 72.321 - 72.321 - - - - -
B6 (250X600) TO B9 (350X600)
BOTTOM
25 0.275 23.695 3 1 71.085 3.858 274.248 - - - - - 274.248 -
23.495
LAP 0.800
25 0.800 3 1 2.400 3.858 9.259 - - - - - 9.259 -
BOTTOM
25 EXTRA 4.375 3 1 13.125 3.858 50.637 - - - - - 50.637 -
B6 4.375
BOTTOM
25 EXTRA 0.275 9.695 3 1 29.085 3.858 112.211 - - - - - 112.211 -
9.495
BOTTOM
LAYER 0.190
25 PIN 0.190 16 1 3.040 3.858 11.728 - - - - - 11.728 -
TOP 23.445
25 0.275 23.645 3 1 70.935 3.858 273.669 - - - - - 273.669 -
LAP 0.800
25 0.800 3 1 2.400 3.858 9.259 - - - - - 9.259 -
TOP 3.250
20 EXTRA 3.250 3 1 9.750 2.469 24.074 - - - - 24.074 - -
C3
TOP
LAYER 0.190
25 PIN 0.190 11 1 2.090 3.858 8.063 - - - - - 8.063 -
TOP 8.325
25 EXTRA 8.325 3 1 24.975 3.858 96.354 - - - - - 96.354 -
C5 to C6
TOP
LAYER 0.190
25 PIN 0.190 22 1 4.180 3.858 16.127 - - - - - 16.127 -
TOP 4.450
25 EXTRA 4.450 3 1 13.350 3.858 51.505 - - - - - 51.505 -
C6
TOP
LAYER 0.190
25 PIN 0.190 9 1 1.710 3.858 6.597 - - - - - 6.597 -
250X600 0.548
B6 STIRRUPS 0.100 0.100
8 100 0.548 1.392 11 4 61.248 0.395 24.197 24.197 - - - - - -
250X600 0.548
B6 STIRRUPS 0.100 0.100
8 125 0.548 1.392 35 2 97.440 0.395 38.495 38.495 - - - - - -
300X600 0.548
B7 STIRRUPS 0.140 0.140
8 100 0.548 1.472 36 2 105.984 0.395 41.870 41.870 - - - - - -
250X600 0.550
B8 STIRRUPS 0.100 0.100
10 100 0.550 1.420 29 2 82.360 0.617 50.840 - 50.840 - - - - -
350X600 0.548
B9 STIRRUPS 0.150 0.150
4L 8 100 0.548 1.492 14 4 83.552 0.395 33.008 33.008 - - - - - -
350X600 0.550
B9 STIRRUPS 0.150 0.150
4L 10 150 0.550 1.520 26 2 79.040 0.617 48.790 - 48.790 - - - - -
B11 (250X750)
BOTTOM
25 & 4.100 3 3 36.900 3.858 142.361 - - - - - 142.361 -
TOP 4.100
BOTTOM
20 & 3.890 5 1 19.450 2.469 48.025 - - - - 48.025 - -
TOP 3.890
250X750 0.700
STIRRUPS 0.200 0.200
10 100 0.700 1.920 19 1 36.480 0.617 22.519 - 22.519 - - - - -
B12 (300X750)
BOTTOM
16 0.422 0.422 4.998 2 1 9.996 1.580 15.796 - - - 15.796 - - -
4.250
BOTTOM
20 0.590 0.590 5.310 2 1 10.620 2.469 26.222 - - - - 26.222 - -
4.250
B13 (300X750)
BOTTOM
20 0.590 0.590 8.825 3 1 26.475 2.469 65.370 - - - - 65.370 - -
7.765
BOTTOM
16 5.325 3 1 15.975 1.580 25.244 - - - 25.244 - - -
5.325
BOTTOM
LAYER 0.240
25 PIN 0.240 25 1 6.000 3.858 23.148 - - - - - 23.148 -
TOP
LAYER 0.240
25 PIN 0.240 8 2 3.840 3.858 14.815 - - - - - 14.815 -
300X750 0.698
B13 STIRRUPS 0.140 0.140
8 100 0.698 1.772 11 2 38.984 0.395 15.401 15.401 - - - - - -
300X750 0.698
B13 STIRRUPS 0.248 0.248
8 150 0.698 1.988 36 1 71.568 0.395 28.274 28.274 - - - - - -
PTB1 (600X450)
BOTTOM
16 0.500 9.872 4 1 39.488 1.580 62.401 - - - 62.401 - - -
9.420
BOTTOM
16 EXTRA 4.800 4 1 19.200 1.580 30.341 - - - 30.341 - - -
4.800
BOTTOM
25 EXTRA 4.800 2 1 9.600 3.858 37.037 - - - - - 37.037 -
4.800
BOTTOM
LAYER 0.540
25 PIN 0.540 17 1 9.180 3.858 35.417 - - - - - 35.417 -
TOP
LAYER 0.540
25 PIN 0.540 9 1 4.860 3.858 18.750 - - - - - 18.750 -
TOP
LAYER 0.540
25 PIN 0.540 9 1 4.860 3.858 18.750 - - - - - 18.750 -
4L
BOTTOM
8 150 SHORTER 0.100 0.100 2.777 44 1 122.188 0.395 48.272 48.272 - - - - - -
U 2.625
BOTTOM
8 200 LONGER 0.100 0.100 6.477 12 1 77.724 0.395 30.706 30.706 - - - - - -
g 6.325
TOP
8 200 LONGER 0.100 0.100 6.477 12 1 77.724 0.395 30.706 30.706 - - - - - -
S 6.325
TOP
8 150 SHORTER 0.100 0.100 2.777 44 1 122.188 0.395 48.272 48.272 - - - - - -
f 2.625
STAIRCASE 2 ROOF SLAB (150THK.)
BOTTOM
10 300 SHORTER 0.100 0.100 4.440 37 1 164.280 0.617 101.407 - 101.407 - - - - -
X1 4.300
BOTTOM
10 300 SHORTER 2.695 37 1 99.715 0.617 61.552 - 61.552 - - - - -
Y1 2.695
- 76.117 - - - - -
S.M. NIRMAN INFRASTRUCTURE DEVELOPMENT PVT. LTD.
CONSYNC INFRA PVT. LTD.
REINFORCEMENT RECORD ENTRY
PAGE NO - 65
23RD RA
BOTTOM
10 300 LONGER 0.100 0.100 6.490 19 1 123.310 0.617 76.117 - 76.117 - - - - -
m 6.350
BOTTOM
10 300 LONGER 4.130 19 1 78.470 0.617 48.438 - 48.438 - - - - -
n 4.130
EXTRA
10 150 TOP 0.100 2.115 20 2 84.600 0.617 52.222 - 52.222 - - - - -
1 2.045
BINDER
8 300 2.304 2.304 7 2 32.256 0.395 12.743 12.743 - - - - - -
BINDER
8 300 1.150 1.150 8 2 18.400 0.395 7.269 7.269 - - - - - -
S2 (150THK.)
BOTTOM
8 300 SHORTER 0.100 0.100 3.202 22 1 70.444 0.395 27.830 27.830 - - - - - -
j 3.050
BOTTOM
8 300 SHORTER 2.170 22 1 47.740 0.395 18.860 18.860 - - - - - -
k 2.170
BOTTOM
8 400 LONGER 0.100 0.100 6.502 9 1 58.518 0.395 23.118 23.118 - - - - - -
a 6.350
BOTTOM
8 400 LONGER 4.480 9 1 40.320 0.395 15.929 15.929 - - - - - -
b 4.480
EXTRA
8 150 TOP 0.100 1.911 10 1 19.110 0.395 7.550 7.550 - - - - - -
f 1.835
EXTRA
8 150 TOP 0.100 2.511 10 1 25.110 0.395 9.920 9.920 - - - - - -
f 2.435
EXTRA
8 125 TOP 0.100 1.281 43 2 110.166 0.395 43.522 43.522 - - - - - -
r 1.205
BINDER
8 300 3.530 3.530 5 2 35.300 0.395 13.946 13.946 - - - - - -
BINDER
8 300 1.490 1.490 7 2 20.860 0.395 8.241 8.241 - - - - - -
TOP
BOTTOM 0.075
8 200 MAIN 0.875 0.950 23 2 43.700 0.395 17.264 17.264 - - - - - -
TOP
BOTTOM
8 200 BINDER 4.250 4.250 4 2 34.000 0.395 13.432 13.432 - - - - - -
S3 (175THK.)
BOTTOM
10 300 SHORTER 0.100 0.100 6.440 37 1 238.280 0.617 147.086 - 147.086 - - - - -
X1 6.300
BOTTOM
10 300 SHORTER 4.025 37 1 148.925 0.617 91.929 - 91.929 - - - - -
Y1 4.025
BOTTOM
10 300 LONGER 0.100 0.100 7.915 19 1 150.385 0.617 92.830 - 92.830 - - - - -
m 7.775
BOTTOM
10 300 LONGER 5.128 19 1 97.423 0.617 60.137 - 60.137 - - - - -
n 5.128
EXTRA
10 150 TOP 0.100 2.070 99 2 409.860 0.617 253.000 - 253 - - - - -
1 2.000
20.625 - - - - - -
S.M. NIRMAN INFRASTRUCTURE DEVELOPMENT PVT. LTD.
CONSYNC INFRA PVT. LTD.
REINFORCEMENT RECORD ENTRY
PAGE NO - 67
23RD RA
BINDER
8 300 3.729 3.729 7 2 52.206 0.395 20.625 20.625 - - - - - -
BINDER
8 300 3.100 3.100 8 2 49.600 0.395 19.595 19.595 - - - - - -
PT SLAB
BOTTOM
10 250 SHORTER 0.100 0.100 10.240 40 1 409.600 0.617 252.840 - 252.840 - - - - -
B 10.100
BOTTOM
10 250 LONGER 0.100 0.100 9.900 40 1 396.000 0.617 244.444 - 244.444 - - - - -
A 9.700
lap
10 250 0.350 40 1 14.000 0.617 8.642 - 8.642 - - - - -
0.350
BOTTOM
10 250 EXTRA 4.300 4.300 40 2 344.000 0.617 212.346 - 212.346 - - - - -
BOTTOM
10 250 EXTRA 3.800 3.800 40 1 152.000 0.617 93.827 - 93.827 - - - - -
TOP
10 250 EXTRA 2.700 2.700 40 1 108.000 0.617 66.667 - 66.667 - - - - -
OVER B2
BINDER
TOP
10 250 EXTRA 5.550 5.550 10 1 55.500 0.617 34.259 - 34.259 - - - - -
OVER B2
TOP
10 250 EXTRA 4.300 4.300 40 1 172.000 0.617 106.173 - 106.173 - - - - -
OVER PTB1
BINDER
TOP
10 250 EXTRA 5.550 5.550 18 1 99.900 0.617 61.667 - 61.667 - - - - -
OVER PTB1
TOP
10 250 EXTRA 2.450 2.450 40 1 98.000 0.617 60.494 - 60.494 - - - - -
OVER B2A
TOP
10 250 EXTRA 2.900 2.900 35 1 101.500 0.617 62.654 - 62.654 - - - - -
C1 TO C4
PROJECTION C7 TO PASSENGER LIFT :-
1200 MAIN
PROJ 8 150 BOTTOM 0.100 1.827 1 151 275.877 0.395 108.988 108.988 - - - - - -
U 1.775
BINDER
10 200 BOTTOM 10.715 1 7 75.005 0.617 46.299 - 46.299 - - - - -
10.775
BINDER
10 200 BOTTOM 13.590 1 7 95.130 0.617 58.722 - 58.722 - - - - -
13.650
1200 MAIN
PROJ 10 150 TOP 0.100 3.045 1 151 459.795 0.617 283.824 - 283.824 - - - - -
2.975
BINDER
10 200 BOTTOM 10.715 1 7 75.005 0.617 46.299 - 46.299 - - - - -
10.775
BINDER
10 200 BOTTOM 13.590 1 7 95.130 0.617 58.722 - 58.722 - - - - -
13.650
PROJECTION C10 TO C9A
500 MAIN
PROJ 10 200 BOTTOM 0.100 0.100 0.890 79 1 70.310 0.617 43.401 - 43.401 - - - - -
0.750
BINDER
10 200 BOTTOM 0.100 0.100 15.540 4 1 62.160 0.617 38.370 - 38.370 - - - - -
15.400
500 MAIN
PROJ 10 150 TOP 0.100 1.045 107 1 111.815 0.617 69.022 - 69.022 - - - - -
0.975
BINDER
10 200 BOTTOM 0.100 0.100 15.540 4 1 62.160 0.617 38.370 - 38.370 - - - - -
15.400
500 MAIN
PROJ 10 200 BOTTOM 0.100 0.100 0.890 48 1 42.720 0.617 26.370 - 26.370 - - - - -
0.750
BINDER
10 200 BOTTOM 0.100 0.100 9.590 4 1 38.360 0.617 23.679 - 23.679 - - - - -
9.450
500 MAIN
PROJ 10 150 TOP 0.100 1.045 109 1 113.905 0.617 70.312 - 70.312 - - - - -
0.975
BINDER
10 200 BOTTOM 0.100 0.100 9.590 4 1 38.360 0.617 23.679 - 23.679 - - - - -
9.450
BOTTOM
12 100 0.100 0.77 0.300 3.159 19 1 60.021 0.889 53.352 - - 53.352 - - - -
2.025
BINDER
8 200 BOTTOM 0.100 0.100 2.152 9 1 19.368 0.395 7.652 7.652 - - - - - -
2.000
TOP
12 100 0.300 2.25 0.300 2.778 19 1 52.782 0.889 46.917 - - 46.917 - - - -
BOTTOM
12 100 0.100 0.300 2.614 19 1 49.666 0.889 44.148 - - 44.148 - - - -
2.250
TOP
12 100 0.300 2.05 0.850 3.128 19 1 59.432 0.889 52.828 - - 52.8284 - - - -
TOP
8 200 BINDER 0.100 0.100 2.152 4 1 8.608 0.395 3.401 3.401 - - - - - -
2.000
BOTTOM
12 100 0.100 3.145 0.300 5.534 19 1 105.146 0.889 93.463 - - 93.4631 - - - -
2.025
LANDING
12 100 TOP 0.300 0.300 2.778 19 1 52.782 0.889 46.917 - - 46.9173 - - - -
BINDER 2.250
TOP
8 200 BINDER 0.100 0.100 2.152 24 1 51.648 0.395 20.404 20.404 - - - - - -
2.000
- - 42.4587 - - - -
S.M. NIRMAN INFRASTRUCTURE DEVELOPMENT PVT. LTD.
CONSYNC INFRA PVT. LTD.
REINFORCEMENT RECORD ENTRY
PAGE NO - 71
23RD RA
BOTTOM
12 100 0.100 0.300 2.514 19 1 47.766 0.889 42.459 - - 42.4587 - - - -
2.150
BINDER
12 100 BOTTOM 0.100 0.100 4.453 20 1 89.060 0.889 79.164 - - 79.1644 - - - -
4.325
TOP
12 100 BOTTOM 0.100 0.100 4.453 20 1 89.060 0.889 79.164 - - 79.1644 - - - -
4.325
BOTTOM
12 100 0.100 3.145 0.300 5.659 19 1 107.521 0.889 95.574 - - 95.5742 - - - -
2.150
TOP
8 200 BINDER 0.100 0.100 2.152 24 1 51.648 0.395 20.404 20.404 - - - - - -
2.000
BOTTOM
12 100 0.100 0.300 2.514 19 1 47.766 0.889 42.459 - - 42.4587 - - - -
2.150
BOTTOM
12 100 0.100 0.77 0.300 3.159 19 1 60.021 0.889 53.352 - - 53.3520 - - - -
2.025
BINDER
8 200 BOTTOM 0.100 0.100 2.152 9 1 19.368 0.395 7.652 7.652 - - - - - -
2.000
TOP
12 100 0.300 2.25 0.300 2.778 19 1 52.782 0.889 46.917 - - 46.9173 - - - -
BOTTOM
12 100 0.100 0.300 2.614 19 1 49.666 0.889 44.148 - - 44.1476 - - - -
2.250
MID LANDING BEAM MB 2 (250X750)
BOTTOM
20 & 0.650 0.650 5.505 3 2 33.030 2.469 81.556 - - - - 81.556 - -
TOP 4.325
250X750 0.258
STIRRUPS 0.708 0.708
8 150 0.208 1.978 27 1 53.406 0.395 21.099 21.09866667 - - - - - -
Total Comsumed Quantity (B) CUM 1,173.946 121.350 1732.380 565.536 732.836 4326.048
5 Working Progress CUM 0.000 0.000 4.500 0.000 0.000 4.500
7 Wastage F=C-(D+C) CUM -5.196 -2.850 0.870 -1.036 18.164 0.952
9 Wastage Percentage % -0.44% -2.41% 0.05% -0.18% 2.42% 0.02%
Allowable Wastage %
Wastage beyond limit %