Summary Progress Precast Fabrication BM#1 - 2 Up To July 26, 2022

You might also like

You are on page 1of 2

PT.

MITRA SARANA MEMBANGUN


Summary Precast Fabrication Board Machine - 1

Location : Board Machine 1


Project : Precast Fabrication and Erection Works of Package 10A - BM-1 Project, Pelalawan, Riau
Period : Up to July 26, 2022

Last Period This Period In This Period


Rough Rough Rough
Qty Concrete Rebar BRC Mesh Strand Anchor Bolt M16 Embedded Qty Concrete Rebar BRC Mesh Strand Anchor Bolt M16 Embedded Qty Concrete Rebar BRC Mesh Strand Anchor Bolt M16 Embedded
No Description Formwork Formwork Formwork

(Pcs) (M³) (Kg) (M²) (M²) (Kg) (Nos) (Kg) (Pcs) (M³) (Kg) (M²) (M²) (Kg) (Nos) (Kg) (Pcs) (M³) (Kg) (M²) (M²) (Kg) (Nos) (Kg)

1 Column 223.00 2,548.41 988,158.06 3,017.97 153,790.73 37.00 487.20 189,122.35 - - 560.34 - 27,411.03 260.00 3,035.61 1,177,280.41 3,578.31 181,201.76
2 Beam 204.00 1,107.60 187,947.60 - - 21,572.99 - 37,055.88 - - - - - - - - 204.00 1,107.60 187,947.60 - - 21,572.99 - 37,055.88
3 Slab 586.00 2,319.74 307,668.75 663.11 33,923.49 84,554.20 30,306.41 127.00 518.10 73,012.37 158.77 7,590.77 13,880.90 - 5,065.03 713.00 2,837.84 380,681.12 821.88 41,514.26 98,435.10 35,371.45
4 Panel Wall 9.00 164.56 2,487.21 - - 115.76 - 394.93 9.00 164.56 2,487.21 115.76 394.93
- - - - - - - -
-
Grand Total: 1,013.00 5,975.76 1,483,774.41 663.11 33,923.49 109,145.16 - 221,153.02 173.00 1,169.86 264,621.92 158.77 7,590.78 14,557.00 - 32,870.99 1,186.00 7,145.61 1,748,396.34 821.88 41,514.26 123,702.16 - 254,024.02

Prepared by, Checked by, Approved by,


PT. MSM PT. MSM PT. RAPI

Syamsul Zamri M. Firdian


Site Engineer Construction Manager
Summary Precast Fabrication Fiberline Building

Location : FL3B
Project : Precast Fabrication and Erection Works of Package 10 & 10A - FL3B Project, Pelalawan, Riau
Period : Up 27 April, 2021

No Description Cummulative
Smooth Rough
Qty Concrete
Formwork Formwork
Rebar BRC Mesh Strand Embedded Remarks

(pcs) (m3) (m2) (m2) (kg) (m2) (kg) (kg)


1 Column 72.00 595.69 0.00 #N/A 252768.79 #N/A 363.46 40009.99
2 Beam
3 Slab 57.00 200.32 28.28 24.31 26669.13 4349.64 12356.47 2254.67
Grand Total: 129.00 796.01 28.28 24.31 279437.92 4349.64 12719.94 42264.66

You might also like