Summary Progress Precast Fabrication BM#1 - 2 Up To July 26, 2022
Summary Progress Precast Fabrication BM#1 - 2 Up To July 26, 2022
Summary Progress Precast Fabrication BM#1 - 2 Up To July 26, 2022
(Pcs) (M³) (Kg) (M²) (M²) (Kg) (Nos) (Kg) (Pcs) (M³) (Kg) (M²) (M²) (Kg) (Nos) (Kg) (Pcs) (M³) (Kg) (M²) (M²) (Kg) (Nos) (Kg)
1 Column 223.00 2,548.41 988,158.06 3,017.97 153,790.73 37.00 487.20 189,122.35 - - 560.34 - 27,411.03 260.00 3,035.61 1,177,280.41 3,578.31 181,201.76
2 Beam 204.00 1,107.60 187,947.60 - - 21,572.99 - 37,055.88 - - - - - - - - 204.00 1,107.60 187,947.60 - - 21,572.99 - 37,055.88
3 Slab 586.00 2,319.74 307,668.75 663.11 33,923.49 84,554.20 30,306.41 127.00 518.10 73,012.37 158.77 7,590.77 13,880.90 - 5,065.03 713.00 2,837.84 380,681.12 821.88 41,514.26 98,435.10 35,371.45
4 Panel Wall 9.00 164.56 2,487.21 - - 115.76 - 394.93 9.00 164.56 2,487.21 115.76 394.93
- - - - - - - -
-
Grand Total: 1,013.00 5,975.76 1,483,774.41 663.11 33,923.49 109,145.16 - 221,153.02 173.00 1,169.86 264,621.92 158.77 7,590.78 14,557.00 - 32,870.99 1,186.00 7,145.61 1,748,396.34 821.88 41,514.26 123,702.16 - 254,024.02
Location : FL3B
Project : Precast Fabrication and Erection Works of Package 10 & 10A - FL3B Project, Pelalawan, Riau
Period : Up 27 April, 2021
No Description Cummulative
Smooth Rough
Qty Concrete
Formwork Formwork
Rebar BRC Mesh Strand Embedded Remarks