You are on page 1of 10

WEEKLY REPORT

1
Progress Summary up to 4-May-17
Start Date 5-Feb-17 Contract Dates
5-Aug-18
Data Date 4-May-17 5-Feb-17
0 100 200 300 400 500 600
Elapsed Duration Contract Project Duration
Start Date 5-Feb-17
Completion Date 4-Aug-18 16%
Contact Dates

Project Duration 547 Elapsed


Time

Elapsed Duration 88
84%

Elapsed Period % 16.1%


9
Remaining Period % 83.9%
7 Overall
Planned
6 Progress %
Previous
Week This Week Overall Actual
4 Progress %
Overall Actual
Progress % 3.19 3.47 3 Variance %

Overall Planned 15.00


Progress % 1.99 2.32 2.32 3.47 1.15

Variance % 1.2 1.15 Overall Progre...

• Progress Update as at 4.05.2017


2 2
Construction PVA -- up
Construction PVA up to
to 44thth May
May 2017
2017
Planned % Actual % Variance %
Constructio
n 2.28 % 3.88% 1.60%
Zone 1 Zone 2 Zone 3
Planned % Actual % Variance % Planned % Actual % Variance % Planned % Actual % Variance %

4.91% 6.28% 1.37% 4.15% 5.08% 0.93% 0% 5.85% 5.85%

VJ 01 TO
08

3
VH01 TO
08

VA 01 TO VC 01 TO
12
Substation 2 Zone 4 04 05
VE 01 TO
04
ZoneVG501 TO
08
Planned % Actual % Variance % Planned % Actual % Variance % Planned % Actual % Variance %
VB 01 TO
VD 01 TO VF 01 TO
0% 0.49% 0.49% 04
0% 0.52% 0.52%
0.23% 0.72%05 0.49% 04

Substation 1
Planned % Actual % Variance
11
0% 0.00% 0.00%

3
Manpower Histogram
A ve rage M anpow e r/D ay

180

156
160 Planned

Actual
140

11 5
120 1 12

100
87
84

80
65

55

60
51

48
45

40
1 2 27
1 18

18
14

20
3
81 2
57
0
0

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

Week

Progress Update as at 4.05.2017


4
A ve rage Equipm e nt/D ay

Equipment Histogram

30
27
25 Planned Actual

20
14
1 2 14

15
12
12

8 10

10

10
8
8

8
7
6

6
3 5

5
4
3
3
12

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 32

Week

Progress Update as at 4.05.2017


5
MAJOR
MAJOR CONCERNS
CONCERNS
SN DESCRIPTION RISK CATEGORY
Work at Zone 4&5 and part of Zone 3 (from grid 29 to grid 56) on hold
due to found
Cavity at zone 4&5 and part of Zone 3 HIGH
1
And subject to M/S ACES instruction given at site until finish their soil
investigation

Still awaiting for authorities approval to close the intermediate road


2 HIGH
3 Receiving Permanent building permit on 20/Apr/2017
IFC Drawings and DC1, DC2 Drawings received on 6/Apr/2017 and ICT to
4 study any change with the tender drawings

CATEGORY HIGH MEDIUM LOW


CATEGORY::
Major
Major Activities
Activities ongoing
ongoing
Activity Zone/Location
Ground beam concrete curing ZONE# 1
Concreting for slab on grade ZONE# 1
Removal of form work for Ground beam ZONE# 1
water proofing bitumine for Ground beam ZONE# 1
Backfilling under slab on grade ZONE# 1
Backfilling ZONE# 2
Blinding concrete under the ground beam ZONE# 2
Shuttering + steel fixing for ground beams ZONE# 2
Water proofing for Blinding concrete footing substation 2 ZONE# 1
Blocks work under the ground beam ZONE# 2

7 7
ZONE#1A Ground beam waterproofing ZONE#1A slab-on-grade

ZONE#1A slab-on-grade
ZONE#1A Ground beam waterproofing

8
ZONE#2 A ground beam Formwork
ZONE#2 A ground beam Reinforcement

ZONE#4 A– waterproofing for Foundation Footings& ZONE#3 A– waterproofing Foundation Footings&


Necks columns Work Necks columns Work

9
Thank You

10

You might also like