BARWA VILLAGE EXTENSION

PROGRESS UPDATE

27th April 2017


Barwa
Barwa Village
Village Extension
Extension –– AlWakra
AlWakra –– Project
Project Overview
Overview
PROJECT
PROJECT DESCRIPTION
DESCRIPTION

 Barwa Village Extension is additional strip of


land attached to the existing Barwa village
with 11,100 square meter plot developed into
mixed-use building. The Strip Building A
having Ground and Mezzanine 56 Core & Shell
shops +10 F&B shops + 4 anchor stores +
main showroom in addition to 3 residential
floors ( 81 - 1 bedroom apartment + 90 - 2
bedroom apartments + 6 Studios).

 Total Number of Apts. 177 units.

 Total BUA (G+M+3 floors) area for all the


developments approximately 34,492.47 m2
including ancillary buildings.

LOCATION
LOCATION MAP
MAP

2
Site Plan

3
Progress
Progress Summary
Summary up
up to
to 27
27thth April,
April, 2017
2017
Elapsed Time
Start Date 05-Feb-2017 Elapsed Duration 82
Data Date 27th April , 2017 Contract Project Duration 546
0 100 200 300 400 500 600
Start Date 05-Feb-2017
Completion Date 04-Aug-2018
Contract Dates

Project Duration 546


Elapsed
Remaini
,
Elapsed Duration 82
ng,
[PERC
[PERC
ENTAG
ENTAGE]
Elapsed Period % 15.02%
E]
Remaining Period % 84.98 % Elapsed Remaining

Previous Month This Month


Chart Title
Overall Actual Progress % 1.50% 3.19%
Overall Planned Progress 4 3.19
% 0.65% 1.99 %
3 1.99
Variance % 0.85 % 1.2% 2
1.5 1.2
0.65 0.85
1
SPI = EV/PV
0
EV= 2,006,745.09 QR Previous current
PV= 1,256,546.43 QR Planned Actual Variance
SPI= 1.60  
4
DC2 Status
Item Description status Comment
ACMV Approved  
Fire Fighting Approved  
QCDD
Fire Alarm Approved  
Life Safety Approved
MOI CCTV Approved
QRAIL QRAIL Approved  
Clean Site Plan Approved

Oredoo Telecom Approved

WOQOD WOQOD Approved

Drainage Approved
PWA
Roads Approved

Water Approved

KH

Electrical Approved

Temporary building permit Issued On 19th February


BP
Building Permit Issued On 19th April

5
Barwa
Barwa Village
Village Extension
Extension Planned Actual%% Variance
Planned%%Actual Variance %
%

Planned Versus Actual (PVA) 4.16%


OVERALL 1.99
OVERALL 4.15%
% 3.19% -0.01%
1.2%

Zone 1 Zone 2 Zone 3


Planned % Actual % Variance Planned % Actual % Variance Planned % Actual % Variance
4.5% 5.59% 1.09%
3.47% 4.69% 1.22% 0% 4.88% 4.88%

VJ 01 TO
08

3
VH01 TO
08

VA 01 TO VC 01 TO
VE 01 TO
12
Substation 1 04 05 Zone 4 04 VG 01 TO
08

Planned % Actual % VB 01 TO
Variance
04
Planned VF
VD 01 TO %01 TOActual % Variance
05 04

0% 0.00% 0.00% 0.13% 0.70% 0.57%11


Substation 2 Zone 5
Planned % Actual % Variance Planned % Actual % Variance

0% 0.08% 0.08% 0% 0.52% 0.52%


6
16.00%
Overall percentage up to
S _ Curve % 120%

14.66%
27/Apr/2017 14.17%
14.00% planned 1.99%
Actual 3.19%
100%
12.75%

12.00%

80%
10.00% 9.66%

8.07%
8.00% 60%
7.09%

6.00%
5.18%
4.97% 4.97% 4.95% 40%

4.00% 3.72%
3.26%
2.68%
20%
2.00% 1.69%1.62%
1.58%
1.35%
0.53%
0.15%
0.12% 0.01% 0.00%
0.00% 0%

6
77
800 4500
Manpower S _ Curve

699 4000
700
661

3500
600

513 3000
504
500
446
2500

400

335 2000

300
1500

206
200
169 1000
147 143
115 117 123
100
100
500
54
40 37
12 4
1 2 0
0 0

8
Equipment
16 100

14 90
14

80
12
12

11 70

10
10
60
9 9

8 8
8 50

6 40
6

30
4 4
4

3 3 20

2 2 2 2
2
10
1

0 0 0
0 0

9
Variance Chart
Weekly Variance
1.4
1.38

1.35
1.31
1.3
Variance
1.25

1.2 1.2

1.15

1.1
10 11 12

10
Elapsed Time

Elapsed Duration 82
Contract Project Duration 546

0 100 200 300 400 500 600

Material Submittals Pre-Qualification

50% 50 %
42%
58%

Total Total Submitted


Submitted Total Remaining

11
Major Activities Look A Head
STRIP BUILDING - Block 1 Start Finish
Ground Beams Concrete Casting 2/May/17 2/May/17
slab-on-grade -Concrete Pouring 10/May/17 10/May/17
Ground Floor Columns.- Concrete Casting 15/May/17 15/May/17
Mezzanine Floor Slab - Concrete Casting 22/May/17 22/May/17
STRIP BUILDING - Block 2 Start Finish
Ground Beams Concrete Casting 14/May/17 14/May/17
slab-on-grade -Concrete Pouring 24/May/17 24/May/17
Ground Floor Columns.- Concrete Casting 29/May/17 29/May/17
Mezzanine Floor Slab - Concrete Casting 5/Jun/17 5/Jun/17
STRIP BUILDING - Block 3 Start Finish
Footing-Concrete 9/May/17 10/May/17
Neck column-Concrete 16/May/17 17/May/17
Waterproofing For Footings & Column Necks 20/May/17 23/May/17
STRIP BUILDING - Block 4 Start Finish
Footing-Concrete 21/May/17 22/May/17
Neck column-Concrete 28/May/17 29/May/17
STRIP BUILDING - Block 5 Start Finish
Excavation On Going
Blinding Concrete Pouring On Going
Footing-Concrete On Going
12 12
Project Obstacles

Activity Status

Removal of Existing 22 Light poles Completed

Removal & Transfer of Existing 60 Palm & Trees Completed

Rerouting of Existing TSE 6” Line (approx.. length 300 LM) Completed

Re-routing of Existing Fiber optic Cables (approx.. length 150 LM) In progress

Re-routing of existing LPG Gas Filling Points Completed

Road Closure in Zone 3 In Progress

13
Area of Concerns

   
Proposed Mitigation
S.no Description

Coordination with MOI traffic department/ Closer Follow Up from all concerned
1 ASHGHAL for road closure/ traffic diversion. project parties with the Authorities and
client support required
KM additional scope (not covered under Client to issue site instruction to the
2 connection fees) & relocation of existing contractor
services
Cavity discovered in zone 5 during - More site investigation by ICT & ACES
3 excavation - ACES Revised Geotechnical report
- Designer review and recommendation

14
Summary for NCR’s

NCR Description Date


N/A N/A

15
HS&E Summary Report
Till 25/04/2017

Project: BARWA VILLAGE EXTENTION

Month: April Dates From / To : 01/04/2017 To 25/04/2017

MANPOWER RETURNS PRESENT MONTH CUMULATIVE

TOTAL NUMBER OF INSHA EMPLOYEE 1,775 2,781

TOTAL NUMBER OF SUBCONTRACTROR EMPLOYEE 910 1,436

TOTAL NUMBER OF EMPLOYEE CUMULATIVE 2,685 4,520

NUMBER OF MAN HOURS WORKED    

TOTAL FOR INSHA 17,750 29,480

TOTAL FOR SUB-CONTRACTOR 910 6,270

TOTAL MAN HOURS OF THE MONTH 25,390 42,490

TOTAL MAN HOURS YEAR TO DATE 42,490 42,490

CUMULATIVE SAFE MAN HOURS PROJECT TO DATE   42,490

16
Zone 1, 2 and 3A

Zone 3B, 4 and 5

17
ZONE#1A Ground beam formwork and ZONE#1A Ground beam waterproofing &
Reinforcements formwork & reinforcements

ZONE#1A Ground beam waterproofing &


ZONE#1B backfilling
reinforcements
18
ZONE#3 A– Foundation Footings& Necks columns
ZONE#2 A block work for ground beam
Work

ZONE#4 A– waterproofing for Foundation


ZONE#5A — Blinding work
Footings& Necks columns Work
19
Thank You

20