Northern Region Directorate

Contractors' Performance Report (End of June 2019)


Reporting Period until:- 28-Jun-19

Contract Amount (Birr) Date of Contract Contract Completion date This period 28-Jun-19

Duration of This Month To date


Total length Contract period in This Month To date actual
I.No. Project Name Contractor's Name Mobilization progress in progress in Remark
in KM Calendar days in % progress (%)
in months KM KM
Revised completion
Commencement Period Elapsed
Original Revised contract signing date Original date after % of time elapsed
Date in Calendar days
Approved EOT

China First Highway


2 Billbila - Sekota 98.7 2,042,059,919.33 2,041,313,289.84 14-Apr-15 12-Jun-15 3.00 9-Sep-18 11-Jan-20 1674.00 1477.00 88.23 0.63 68.95 0.62 68.05
Eng. Co.Ltd

3 Aykel – Km 69+000 Sur Construction 69 1,954,142,081.60 2,357,157,719.87 26-May-16 20-Oct-16 4.00 18-Feb-20 18-Feb-20 1216.00 981.00 80.67 0.00 #VALUE! 0.00 #VALUE!

4 Dabat-Ajire Powercon 43.2 931,304,149.54 931,304,149.54 19-May-16 10-Oct-16 4.00 9-Oct-19 9-Oct-19 1095.00 991.00 90.50 0.25 77.66 0.11 33.55

5 Mota-Jaragedo Zhongmei 63.04 1,618,179,826.58 1,618,179,826.58 23-May-17 12-Jul-17 3.00 10-Jan-21 10-Jan-21 1278.00 716.00 56.03 2.27 #VALUE! 1.43 #VALUE!

6 Zema River Felegbrhan CRSG 82.83 1,130,938,771.88 1,244,361,405.80 21-Mar-15 10-Jun-15 3.00 9-Jun-18 4-Nov-19 1608.00 1479.00 91.98 1.40 92.03 1.16 76.23

7 km 69+000-Angereb/Ashere Chinawuyi Co, Lid. 71.15 1,955,438,532.41 1,955,438,532.41 23-May-17 21-Jun-17 4.00 19-Oct-20 19-Oct-20 1216.00 737.00 60.61 1.26 #VALUE! 0.90 #VALUE!

8 Wukro-Nebelt Sur Construction 79.62 1,250,636,416.10 1,250,636,416.10 30-Oct-17 29-Nov-17 4.00 28-Nov-20 28-Nov-20 1095.00 576.00 52.60 4.81 #VALUE! 3.83 #VALUE!

9 Nebelt-Flafel Sur Construction 57.02 1,004,289,005.74 1,004,289,005.74 30-Oct-17 29-Nov-17 4.00 28-Nov-20 28-Nov-20 1095.00 576.00 52.60 6.33 50.40 3.61 28.74

Contractor has requested


Kunzila Horticulture farm EOT of 172 Cal.days
10 Marcon Trading Plc. 21.80 554,487,294.06 554,487,294.06 29-Nov-18 24-Jan-18 4.00 24-Jul-20 23-Dec-20 1064.00 520.00 48.87 1.89 #VALUE! 0.41 #VALUE!
zebe Town which is under review by
Engineer
Powercon Plc in JV
11 Ajire-Keraker with Tesfaye Legesse 57.26 1,158,659,797.00 1,158,659,797.00 18-Jun-18 21-Sep-18 4.00 20-Sep-21 20-Sep-21 1095.00 280.00 25.57 1.71 8.21 0.98 4.70
Construction
Satacon Construction
12 Buhait-Dilyibza 72..89 947,920,000.00 951,231,102.56 29-Mar-11 25-Apr-11 4.00 25-Apr-14 26-Dec-18 2802.00 2835.00 >100 0.43 95.78 0.00 #VALUE!
PLC

Defense Construction
13 Beles-Mekane Birehan 39.00 1,018,952,362.90 1,018,952,362.90 26-May-16 1-Nov-16 4.00 1-Nov-19 1-Nov-19 1095.00 850.00 77.63 0.56 #VALUE! 0.22 #VALUE!
Enterprise

Zeluel Yohannes
14 Woldiya Town Section 5.36 304,850,794.33 304,850,794.33 24-Jan-18 24-Feb-18 3.00 24-Feb-20 24-Feb-20 730.00 370.00 50.68 0.32 #VALUE! 0.017 #VALUE!
General Contractor

Tekleberhan Ambaye
15 Maychew-Mehoni 17.43 378,614,038.16 378,614,038.16 23-May-17 29-Sep-17 3.00 27-Mar-20 27-Mar-20 910.00 518.00 56.92 4.02 #VALUE! 0.70 #VALUE!
Construction plc

The Engineer has


recommonded 502
16 Gashena - Bilbila CRTG 105 1,442,916,047.83 1,442,916,047.83 15-Jan-14 12-Feb-14 3.00 18-Jan-18 18-Jan-18 1464.00 1962.00 134.02 1.43 #VALUE! 1.50 #VALUE! Cal.days of EOT which is
under review by the
Employer.

17 Pawi Junction-km69 CRTG 69 887,759,651.45 887,759,651.45 26-Jan-17 1-Jul-17 3.00 30-Jun-20 30-Jun-20 1095.00 727.00 66.39 1.55 #VALUE! 1.07 #VALUE!

18 Azezo-Gondar Rama Construction 12.6 871,565,791.41 871,565,791.41 23-May-17 14-Aug-18 2.00 13-Aug-20 13-Aug-20 730.00 318.00 43.56 1.38 #VALUE! 0.17 #VALUE!

19 Quiha-Maymekden Afro Tsion 24 552,000,000.00 552,000,000.00 23-May-17 14-Jun-17 3.00 1-Dec-19 1-Dec-19 900.00 744.00 82.67 0.92 #VALUE! 0.22 #VALUE!

20 Mekele Industrial Park China Ticjju 18.26 913,224,109.15 913,224,109.15 15-Aug-17 20-Oct-17 2.00 20-Apr-19 13-Jun-19 547.00 616.00 112.61 10.08 #VALUE! 1.84 #VALUE!

21 Adiremet-Adihardi-Beakel Sur Consrrction 69.37 1,025,550,000.00 1,025,550,000.00 7-Jun-17 16-Oct-17 4.00 15-Nov-20 15-Nov-20 1095.00 620.00 56.62 2.25 #VALUE! 1.56 #VALUE!
Mekele -Dengolat - Samre -
22 Defense Const. 94 1,594,387,610.14 1,594,387,610.14 1-Jun-16 1-Nov-16 3.00 31-Oct-19 31-Oct-19 1094.00 969.00 88.57 0.65 #VALUE! 0.61 #VALUE!
Finariwa

23 Debark-Buhait AKIR 61.80 699,465,650.00 699,465,650.00 29-Mar-11 4-Jul-11 4.00 2215.00 2916.00 131.65 0.26 #VALUE! 0.16 #VALUE!
4-Jul-14 27-Jul-17

24 Metema-Abrehajira SUR Construction Plc 117.3 1,548,000,000.00 1,548,000,000.00 23-May-17 19-Oct-17 4 18-Apr-21 not revised 1278 617 48.2785602504 1.83290708 #VALUE! 2.15 #VALUE!

25 Soroka-Ergoye Sur Construction Plc. 92.00 1,432,205,652.00 1,432,205,652.00 26-May-16 30-Nov-16 4.00 30-Nov-19 not revised 1095.00 940.00 85.84 0.14 #VALUE! 0.13 #VALUE!

26 Adiremet-Kulita-Adigoshu Melcon Construction 57.00 953,000,000.00 953,000,000.00 23-May-17 26-Oct-17 4 25-Oct-20 not revised 1095.00 610.00 55.71 2.09 #VALUE! 1.19 #VALUE!

Jiangxi Water and


27 Fiyelweha-Tekeze Hydropower 39.50 1,166,300,000.00 1,166,300,000.00 7-Jun-17 26-Sep-17 4.00 25-Sep-20 26-Sep-20 1095.00 640.00 44.47 0.82 #VALUE! 0.33 #VALUE!
Construction
Afro Tsion
28 Adiabun-Rama 47 807,500,000.00 807,500,000.00 23-May-17 3-Oct-17 4.00 2-Oct-20 not revised 1095.00 633.00 57.81 0.79 31.09 0.37 14.61
Construction

29 Abiadi-Semema Sur Construction Plc. 87.40 1,748,000,000.00 1,748,000,000.00 7-Jul-17 20-Dec-17 4.00 20-Jun-21 20-Jun-21 1278.00 555.00 34.04 1.27 #VALUE! 1.11 #VALUE!

30 Semema-Endabaguna Sur Construction Plc. 83.26 2,252,000,000.00 2,252,000,000.00 7-Jul-17 20-Dec-17 4.00 20-Jun-21 20-Jun-21 1278.00 555.00 43.43 4.01 #VALUE! 3.34 #VALUE!

Wukro-Atsbi-Koneba Sur Construction Plc. 63.02 1,745,722,493.86 1,745,722,493.86 25-Oct-18 1-Jan-19 4.00 15-Jun-22 15-Jun-22 1261.00 14.12 0.60 #VALUE! 0.38 #VALUE!
31 178
Beijing Urban
Debark-Zarima Construction Group 68.62 2,412,000,000.00 2,412,000,000.00 31-May-18 1-Jan-19 4.00 31-Dec-22 31-Dec-22 1460.00 12.19 0.16 2.00 0.11 1.37
32 LTD 178

Adisheru-Dila-Samre Defence Construction 76.60 2,114,048,067.84 2,114,048,067.84 13-Dec-18 9-May-19 4.00 8-May-22 8-May-22 1095.00 4.57 Under Mobilization
33 50

Melcon Construction
Rama-Chilla
PLC
91.13 1,479,881,513.14 1,479,881,513.14 15-Jan-19 1-Apr-19 3.00 31-Mar-22 31-Mar-22 1095.00 8.04 Under Mobilization
34 88

Tenta Junction-Wegeltena- Hebei Construction


Kurba (31+500-110+740) Group Co.Ltd
79.24 1,873,489,476.53 1,873,489,476.53 7-Mar-19 1-Apr-19 4.00 31-Mar-22 31-Mar-22 1095.00 8.04 1.05 1.05 0.83 0.83
35 88
China Communications
Kombolcha-Industrial Park
Access Road
Construction 3.28 478,975,000.00 478,975,000.00 29-May-19 4.00 Under Mobilization
Company(LTD)
36

Yencomad
Adiarkay-Telemt
Construction PLC.
80.00 1,981,378,049.64 1,981,378,049.64 31-Oct-18 17-Jan-19 4.00 16-Jan-22 16-Jan-22 1095.00 14.79 0.20 #VALUE! 0.16 #VALUE!
37 162

FAL General
Debre Markos-Debre Elias
Construction PLC.
81.00 1,299,644,371.61 1,299,644,371.61 19-Apr-18 4.00 Under Mobilization
38

Mekaneyesus/Este-Simada CCCC 53.40 1,925,451,264.45 1,925,451,264.45 24-Oct-18 21-Feb-19 4.00 20-Feb-22 20-Feb-22 1095.00 11.60 Under Mobilization
39 127
Northern Region Directorate
Contractors' Performance Report (End of July 2019)
Reporting Period until:- 28-Jul-19

Contract Amount (Birr) Date of Contract Contract Completion date This period 28-Jul-19

Duration of This Month


Total length Contract period in This Month To date actual To date progress
I.No. Project Name Contractor's Name Mobilization progress in Remark
in KM Calendar days in % progress (%) in KM
in months KM
Revised completion
Commencement Period Elapsed
Original Revised contract signing date Original date after % of time elapsed
Date in Calendar days
Approved EOT

1 Aykel – Km 69+000 Sur Construction 69.00 1,954,142,081.60 2,357,157,719.87 26-May-16 20-Oct-16 4.00 18-Feb-20 18-Feb-20 1216.00 1011.00 83.14 0.00 73.67 0.00 50.83

2 Dabat-Ajire Powercon 43.20 931,304,149.54 931,304,149.54 19-May-16 10-Oct-16 4.00 9-Oct-19 9-Oct-19 1094.00 1021.00 93.33 0.06 77.78 0.04 33.60

3 Abiadi-Semema Sur Construction Plc. 87.40 1,748,000,000.00 1,748,000,000.00 7-Jul-17 20-Dec-17 4.00 20-Jun-21 20-Jun-21 1278.00 585.00 45.77 2.13 52.92 1.47 46.25

Afro Tsion
4 Adiabun-Rama 47 807,500,000.00 807,500,000.00 23-May-17 3-Oct-17 4.00 2-Oct-20 2-Oct-20 1095.00 663.00 60.55 1.33 32.04 0.92 15.06
Construction

Yencomad
5 Adiarkay-Telemt
Construction PLC.
76.03 1,981,378,049.64 1,981,378,049.64 31-Oct-18 17-Jan-19 4.00 16-Jan-22 16-Jan-22 1095.00 192.00 17.53 0.26 0.91 0.18 0.69

6 Adiremet-Adihardi-Beakel Sur Consrrction 69.37 1,025,550,000.00 1,025,550,000.00 7-Jun-17 16-Oct-17 4.00 15-Nov-20 15-Nov-20 1126.00 650.00 57.73 0.86 55.99 0.59 38.84

7 Adiremet-Kulita-Adigoshu Melcon Construction 57.00 953,000,000.00 953,000,000.00 23-May-17 26-Oct-17 4 25-Oct-20 25-Oct-20 1095.00 640.00 58.45 1.22 40.05 0.84 22.83

8 Adisheru-Dila-Samre Defence Construction 76.60 2,114,048,067.84 2,114,048,067.84 13-Dec-18 9-May-19 4.00 8-May-22 8-May-22 1095.00 80.00 7.31 0.00 0.00 0.00 0.00

Powercon Plc in JV
9 Ajire-Keraker with Tesfaye Legesse 57.26 1,158,659,797.00 1,158,659,797.00 18-Jun-18 21-Sep-18 4.00 20-Sep-21 20-Sep-21 1095.00 310.00 28.31 1.06 9.69 0.73 5.55
Construction

10 Azezo-Gondar Rama Construction 12.6 871,565,791.41 871,565,791.41 23-May-17 14-Aug-18 2.00 13-Aug-20 13-Aug-20 730.00 348.00 47.67 0.10 14.38 0.07 1.81

Defense Construction
11 Beles-Mekane Birehan 39.00 1,018,952,362.90 1,018,952,362.90 26-May-16 1-Nov-16 4.00 1-Nov-19 1-Nov-19 1095.00 999.00 91.23 0.09 32.44 0.06 12.65
Enterprise

China First Highway


12 Billbila - Sekota 98.7 2,042,059,919.33 2,041,313,289.84 14-Apr-15 12-Jun-15 3.00 9-Sep-18 11-Jan-20 1674.00 1507.00 90.02 0.32 67.83 0.22 66.95
Eng. Co.Ltd

14 Debark-Buhait AKIR 61.80 699,465,650.00 699,465,650.00 29-Mar-11 4-Jul-11 4.00 2215.00 2946.00 133.00 0.00 85.37 0.00 52.76
4-Jul-14 27-Jul-17

Beijing Urban
15 Debark-Zarima Construction Group 68.62 2,412,000,000.00 2,412,000,000.00 31-May-18 1-Jan-19 4.00 31-Dec-22 31-Dec-22 1460.00 208.00 14.25 0.06 1.95 0.04 1.34
LTD

FAL General
16 Debre Markos-Debre Elias
Construction PLC.
81.00 1,299,644,371.61 1,299,644,371.61 19-Apr-18 4.00 0.00 0.00 0.00 0.00 0.00

Jiangxi Water and


17 Fiyelweha-Tekeze Hydropower 39.50 1,166,300,000.00 1,166,300,000.00 7-Jun-17 26-Sep-17 4.00 25-Sep-20 26-Sep-20 1096.00 670.00 61.13 0.42 19.95 0.29 7.88
Construction

18 Gashena - Bilbila CRTG 105 1,442,916,047.83 1,442,916,047.83 15-Jan-14 12-Feb-14 3.00 18-Jan-18 18-Jan-18 1436.00 1992.00 138.72 1.43 71.95 0.99 75.55

19 km 69+000-Angereb/Ashere Chinawuyi Co, Lid. 71.15 1,955,438,532.41 1,955,438,532.41 23-May-17 21-Jun-17 4.00 19-Oct-20 19-Oct-20 1216.00 767.00 63.08 0.75 24.62 0.52 17.52

China Communications
Kombolcha-Industrial Park
20
Access Road
Construction 3.28 478,975,000.00 478,975,000.00 29-May-19 4.00 0.00 43674.00 #DIV/0! 0.00 0.00 0.00 0.00
Company(LTD)
Kunzila Horticulture farm
21 Marcon Trading Plc. 21.80 554,487,294.06 554,487,294.06 29-Nov-18 24-Jan-18 4.00 24-Jul-20 23-Dec-20 1064.00 550.00 51.69 0.07 23.44 0.05 5.11
zebe Town

Tekleberhan Ambaye
22 Maichew-Mehoni 17.43 378,614,038.16 378,614,038.16 23-May-17 29-Sep-17 3.00 27-Mar-20 27-Mar-20 910.00 667.00 73.30 0.12 54.27 0.08 9.46
Construction plc

23 Mekaneyesus/Este-Simada CCCC 53.40 1,925,451,264.45 1,925,451,264.45 24-Oct-18 21-Feb-19 4.00 20-Feb-22 21-Feb-22 1096.00 157.00 14.32 0.19 0.54 0.13 0.29

Mekele -Dengolat - Samre -


24 Defense Const. 94 1,594,387,610.14 1,594,387,610.14 1-Jun-16 1-Nov-16 3.00 31-Oct-19 31-Oct-19 1094.00 999.00 91.32 0.68 43.73 0.47 41.11
Finariwa
25 Mekele Industrial Park China Ticjju 18.26 913,224,109.15 913,224,109.15 15-Aug-17 20-Oct-17 2.00 20-Apr-19 13-Jun-19 601.00 646.00 107.49 0.17 61.34 0.12 11.20

26 Metema-Abrehajira SUR Construction Plc 117.3 1,548,000,000.00 1,548,000,000.00 23-May-17 19-Oct-17 4 18-Apr-21 44304 1277.00 647.00 50.67 0.99 56.54 0.68 66.32

27 Mota-Jaragedo Zhongmei 63.04 1,618,179,826.58 1,618,179,826.58 23-May-17 12-Jul-17 3.00 10-Jan-21 10-Jan-21 1278.00 746.00 58.37 1.10 38.61 0.76 24.34

28 Nebelt-Flafel Sur Construction 57.02 1,004,289,005.74 1,004,289,005.74 30-Oct-17 29-Nov-17 4.00 28-Nov-20 28-Nov-20 1095.00 606.00 55.34 1.32 51.39 0.91 29.30

29 Pawi Junction-km69 CRTG 69 887,759,651.45 887,759,651.45 26-Jan-17 1-Jul-17 3.00 30-Jun-20 30-Jun-20 1095.00 757.00 69.13 0.52 24.23 0.36 16.72

30 Quiha-Maymekden Afro Tsion 24 552,000,000.00 552,000,000.00 23-May-17 14-Jun-17 3.00 1-Dec-19 1-Dec-19 900.00 774.00 86.00 0.23 52.33 0.16 12.56

Melcon Construction
31 Rama-Chilla
PLC
91.13 1,479,881,513.14 1,479,881,513.14 15-Jan-19 1-Apr-19 3.00 31-Mar-22 31-Mar-22 1095.00 118.00 10.78 0.00 0.00 0.00 0.00

32 Semema-Endabaguna Sur Construction Plc. 83.26 2,252,000,000.00 2,252,000,000.00 7-Jul-17 20-Dec-17 4.00 20-Jun-21 20-Jun-21 1278.00 585.00 45.77 0.45 63.55 0.31 52.91

Tenta Junction-Wegeltena- Hebei Construction


34
Kurba (31+500-110+740) Group Co.Ltd
79.24 1,873,489,476.53 1,873,489,476.53 7-Mar-19 1-Apr-19 4.00 31-Mar-22 31-Mar-22 1095.00 118.00 10.78 0.99 1.91 0.68 1.51

Zeluel Yohannes
35 Woldiya Town Section 5.36 304,850,794.33 304,850,794.33 24-Jan-18 24-Feb-18 3.00 24-Feb-20 24-Feb-20 730.00 519.00 71.10 0.04 13.08 0.031 0.70
General Contractor

36 Wukro-Atsbi-Koneba Sur Construction Plc. 63.02 1,745,722,493.86 1,745,722,493.86 25-Oct-18 1-Jan-19 4.00 15-Jun-22 15-Jun-22 1261.00 208.00 16.49 0.36 4.21 0.25 2.65

37 Wukro-Nebelt Sur Construction 79.62 1,250,636,416.10 1,250,636,416.10 30-Oct-17 29-Nov-17 4.00 28-Nov-20 28-Nov-20 1095.00 606.00 55.34 1.23 46.40 0.85 36.94

38 Zema River Felegbrhan CRSG 82.83 1,130,938,771.88 1,244,361,405.80 21-Mar-15 10-Jun-15 3.00 9-Jun-18 4-Nov-19 1608.00 1509.00 93.84 1.12 92.96 0.77 77.00
Northern Region Construction Projects Management Directorate
Projects Plan Vs Actual Progress for July 2019 and Plan up to June 2020
Total Physical Plan in KM Planed for 2011 Ethiopian Fiscal Year Under North Region Directorate

Unit

Planned by ERA Km 401.00

Total ERA's Plan upto the reporting Period Km 6.80

Total Contractor's Plan upto the reporting Period Km 15.21

Total Actual Executed upto the reporting Period Km 13.57


Actual/Plan (ERA) % 199.60
Actual/Plan (CON.) % 89.24

Month
Accomplishment Up Total plan Up to the
Total Project Total plan for this EFY Total to date
I.No. Project Name Contractor's Name Unit to the Past EFY Reporting Period for this
length in KM Vs Accomplishment Accomplishment in Km
reported July August September October November December January February March April May June EFY Vs Accomplishment

Planned by ERA Km
Team I
0.00 0.00 0.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 8.00
Planned by CON. Km 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ###
1 Aykel – Km 69+000 Sur Construction 69.00 Actual Km 50.83 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 50.83
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.00
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 0.50 1.00 1.00 1.50 1.00 1.50 1.00 1.00 1.00 0.50 0.00 10.00
Planned by CON. Km 0.01 0.01 0.32 1.01 1.20 0.96 1.18 1.84 1.74 0.99 1.47 0.78 0.01 11.51 ###
2 Dabat-Ajire Powercon 43.20
Actual Km 33.55 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.04 0.04 33.60
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.40
Actual/Plan (CON) % 400.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 400.00 0.35

Planned by ERA Km 0.50 0.50 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 20.00
Planned by CON. Km 1.37 0.53 1.44 2.24 2.64 2.79 2.69 2.82 3.03 2.12 2.70 2.82 1.37 27.19 ###
3 Abiadi-Semema Sur Construction Plc. 87.40 Actual Km 44.78 1.47 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.47 1.47 46.25
Actual/Plan (ERA) % 294.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 294.00 7.35
Actual/Plan (CON) % 107.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 107.30 5.41

Planned by ERA Km 0.20 0.20 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.60 0.20 10.00
Planned by CON. Km 0.27 0.35 0.75 1.96 2.31 2.06 2.98 3.16 3.73 7.37 3.24 2.44 0.27 30.62
4 Adiabun-Rama Afro Tsion Construction 47.00 Actual Km 16.61 0.92 0.92 0.92 15.06
Actual/Plan (ERA) % 460.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 460.00 9.20
Actual/Plan (CON) % 340.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 340.74 3.00

Planned by ERA Km 0.00 0.00 0.50 0.50 0.50 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.00 8.00
Planned by CON. Km 0.36 0.26 1.49 3.05 3.62 3.88 4.08 3.88 3.99 3.94 4.06 3.06 0.36 35.67
5 Adiarkay-Telemt Yencomad Construction PLC. 76.03 Actual Km 0.51 0.18 0.18 0.18 0.69
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 2.25
Actual/Plan (CON) % 50.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 50.00 0.50

Planned by ERA Km 1.00 1.00 1.00 2.00 2.00 3.00 2.00 3.00 2.00 1.00 1.00 1.00 1.00 20.00
Planned by CON. Km 1.00 1.13 1.38 3.58 3.53 3.61 3.52 3.21 2.76 2.38 2.32 2.33 1.00 30.75
6 Adiremet-Adihardi-Beakel Sur Consrrction 69.37 Actual Km 38.25 0.59 0.59 0.59 38.84
Actual/Plan (ERA) % 59.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.00 2.95
Actual/Plan (CON) % 59.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 59.00 1.92

Planned by ERA Km 0.50 0.50 1.00 1.50 1.50 2.00 1.50 1.50 1.50 1.50 1.50 1.00 0.50 15.50
Planned by CON. Km 1.17 1.36 0.67 3.44 3.83 4.05 4.01 3.70 3.80 3.30 3.14 2.08 1.17 34.55 ###
7 Adiremet-Kulita-Adigoshu Melcon Construction 57.00 Actual Km 21.99 0.84 0.84 0.84 22.83
Actual/Plan (ERA) % 168.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 168.00 5.42
Actual/Plan (CON) % 71.79 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 71.79 2.43

Planned by ERA Km 0.00 0.00 0.50 0.50 0.50 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.00 8.00
Planned by CON. Km 0.00 1.02 1.27 1.58 1.54 1.84 2.12 2.29 2.25 2.32 2.18 1.93 0.00 20.34
8 Adisheru-Dila-Samre Defence Construction 76.60 Actual Km 0.00 0.00 0.00 0.00 0.00
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.00
Actual/Plan (CON) % #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.00
Planned by ERA Km 0.20 0.20 0.50 1.00 1.00 1.30 1.00 1.30 1.00 1.00 1.00 0.50 0.20 10.00
Planned by CON. Km 0.36 0.36 0.48 2.42 3.13 2.97 3.32 3.45 3.50 2.04 1.40 0.42 0.36 23.85
Powercon Plc in JV with Actual Km
9 Ajire-Keraker 57.26 4.70 0.73 0.73 0.73 5.55
Tesfaye Legesse Construction Actual/Plan (ERA % 365.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 365.00 7.30
Actual/Plan (CON) % 202.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 202.78 3.06

Planned by ERA Km 0.00 0.00 0.20 0.50 0.50 0.80 0.50 0.80 0.50 0.50 0.50 0.20 0.00 5.00
Planned by CON. Km 0.16 0.16 0.16
Actual Km 1.74 0.07 0.07 0.07 1.81
10 Azezo-Gondar Rama Construction 12.6 Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 1.44
Actual/Plan (CON) % 44.44 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! 44.44 44.44

Planned by ERA Km 0.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 10.00
Planned by CON. Km 0.42 0.38 0.64 1.17 1.27 1.39 1.53 1.53 1.47 1.29 1.22 0.48 0.42 12.78
Defense Construction
11 Beles-Mekane Birehan 39 Actual Km 12.59 0.060 0.06 0.06 12.65
Enterprise Actual/Plan (ERA % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.60
Actual/Plan (CON) % 14.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.39 0.47

Planned by ERA Km 0.50 0.50 1.00 1.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 0.50 0.50 15.00
Planned by CON. Km 0.69 0.65 5.39 7.43 8.24 8.06 3.31 0.00 0.00 0.00 0.00 0.00 0.69 33.77
China First Highway
12 Billbila - Sekota 98.7 Actual Km 66.18 0.22 0.22 0.22 66.95
Eng. Co.Ltd 44.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 44.00 1.47
Actual/Plan (ERA %
Actual/Plan (CON) % 31.88 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! 31.88 0.65

Planned by ERA Km 0.00 0.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.50 0.00 8.00
14 Debark-Buhait AKIR 61.80 Planned by CON. Km 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ###
Actual Km 52.76 0.00 0.00 0.00 52.76
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.00
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 0.00 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.00 8.00
Beijing Urban Construction Planned by CON. Km 0.38 0.21 0.34 0.55 0.69 1.37 2.06 2.06 2.06 2.06 2.06 0.69 0.38 14.53 ###
15 Debark-Zarima 68.62 Actual Km
Group LTD 1.30 0.04 0.04 0.04 1.34
Actual/Plan (ERA) % #DIV/0! #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.50
Actual/Plan (CON) % 10.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10.53 0.28
N/A N/A
Planned by ERA Km 0.00 0.00 0.00 0.00 0.50 1.00 0.50 1.00 0.50 0.50 0.50 0.50 0.00 5.00
FAL General Construction Planned by CON. Km 0.00 0.00 ###
16 Debre Markos-Debre Elias 81.00 Actual Km
PLC. 0.00 0.00 0.00 0.00 0.00
Actual/Plan (ERA) % #DIV/0! #DIV/0! #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.00
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 10.00
Jiangxi Water and Hydropower Planned by CON. Km 0.86 1.14 2.08 2.68 2.94 3.52 3.30 3.61 3.79 2.84 3.01 1.64 0.86 31.41 ###
17 Fiyelweha-Tekeze 39.50 Actual Km
Construction 7.75 0.29 0.29 0.29 7.88
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 2.90
Actual/Plan (CON) % 33.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33.72 0.92
Unit
Planned by ERA Km 0.50 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.50 0.50 10.00
Planned by CON. Km 0.11 0.11 0.11 ###
18 Gashena - Bilbila CRTG 105.00 Actual Km 74.56 0.99 0.99 0.99 75.55
Actual/Plan (ERA % 198.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 198.00 9.90
Actual/Plan (CON) % 900.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! 900.00 900.00

Planned by ERA Km 0.20 0.20 0.50 1.00 1.00 2.00 2.00 2.00 2.00 2.00 2.00 0.60 0.20 15.50
Planned by CON. Km 0.65 0.65 1.20 3.19 4.55 4.46 4.87 5.02 4.86 2.45 2.62 2.08 0.65 36.60 ###
19 km 69+000-Angereb/Ashere Chinawuyi Co, Lid. 71.15 Actual Km 16.98 0.52 0.52 0.52 17.52
Actual/Plan (ERA % 260.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 260.00 3.35
Actual/Plan (CON) % 80.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.00 1.42

Planned by ERA Km 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Kombolcha-Industrial Park Access China Communications Planned by CON. Km 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 ###
20 3.28 Actual Km
Road Construction Company(LTD) 0.00 0.00 0.00 0.00 0.00
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 0.50 0.50 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.50 0.00 8.00
Kunzila Horticulture farm zebe Planned by CON. Km 0.01 0.01 0.31 0.98 1.17 0.94 1.15 1.81 1.71 0.98 1.45 0.77 0.01 11.29 ###
21 Marcon Trading Plc. 21.80 Actual Km
Town 5.06 0.05 0.05 0.05 5.11
Actual/Plan (ERA % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.63
Actual/Plan (CON) % 500.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 500.00 0.44
Planned by ERA Km 0.00 0.00 0.50 0.50 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.50 0.00 8.00
Tekleberhan Ambaye Planned by CON. Km 0.28 0.05 0.35 0.70 1.00 1.00 1.00 1.10 0.50 0.85 1.00 0.63 0.28 8.46 ###
22 Maichew-Mehoni 17.43 Actual Km
Construction plc 9.38 0.08 0.08 0.08 9.46
Actual/Plan (ERA % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 1.00
Actual/Plan (CON) % 28.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.57 0.95

Planned by ERA Km 0.00 0.00 0.00 0.00 0.20 0.20 0.50 0.50 0.50 0.50 0.30 0.30 0.00 3.00
Planned by CON. Km 0.27 0.27 1.58 1.54 1.95 1.72 1.72 1.72 1.82 1.82 1.82 1.82 0.27 18.05
23 Mekaneyesus/Este-Simada CCCC 53.40 Actual Km 0.00 0.13 0.13 0.13 0.29
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 4.33
Actual/Plan (CON) % 48.15 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 48.15 0.72
Planned by ERA Km 0.50 0.50 1.00 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.00 0.50 15.00
Planned by CON. Km 0.19 0.19 4.65 9.41 9.36 9.46 6.87 4.58 3.65 2.97 2.95 1.49 0.19 55.77
Mekele -Dengolat - Samre - Actual Km
24 Defense Const. 94 41.36 0.47 0.47 0.47 41.11
Finariwa Actual/Plan (ERA) % 94.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 94.00 3.13

Actual/Plan (CON) % 247.37 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 247.37 0.84

Planned by ERA Km 0.00 0.00 0.50 0.50 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.50 0.00 8.00
Planned by CON. Km 0.15 0.20 0.62 1.36 1.30 1.24 0.95 0.90 0.38 0.04 0.01 0.01 0.15 7.16
25 Mekele Industrial Park China Ticjju 18.26 Actual Km 11.08 0.12 0.12 0.12 11.20
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 1.50
Actual/Plan (CON) % 80.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.00 1.68
Planned by ERA Km 0.50 0.50 1.00 2.00 2.00 3.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 20.00
Planned by CON. Km 1.91 0.35 2.71 2.79 4.16 3.07 2.88 2.88 2.85 2.68 3.18 2.54 1.91 32.00
Actual Km 0.68 0.68 0.68 66.32
26 Metema-Abrehajira SUR Construction Plc 117.30 63.49
Actual/Plan (ERA) % 136.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 136.00 3.40
Actual/Plan (CON) % 35.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 35.60 2.13

Planned by ERA Km 0.50 0.50 0.50 1.00 1.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 0.50 15.00
Planned by CON. Km 0.37 0.28 0.78 1.15 1.38 1.54 1.88 2.21 2.84 2.66 2.65 2.41 0.37 20.15
Actual Km 23.75 0.76 0.76 0.76 24.34
27 Mota-Jaragedo Zhongmei 63.04 Actual/Plan (ERA % 152.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 152.00 5.07
Actual/Plan (CON) % 205.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 205.41 3.77

Planned by ERA Km 0.50 0.50 1.00 2.00 2.00 3.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 20.00
Planned by CON. Km 0.00 0.00 1.81 3.75 3.47 3.63 2.63 2.49 2.44 1.19 1.52 1.68 0.00 24.61
28 Nebelt-Flafel Sur Construction 57.02 Actual Km 28.74 0.91 0.91 0.91 29.30
Actual/Plan (ERA % 182.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 182.00 4.55

Actual/Plan (CON) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 3.70

Planned by ERA Km 0.00 0.00 0.50 1.00 2.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 0.00 15.00
Planned by CON. Km 1.54 1.54 2.69 5.08 5.08 5.52 5.41 5.22 4.05 3.38 0.46 0.46 1.54 40.43
29 Pawi Junction-km69 CRTG 69.00 Actual Km 16.16 0.36 0.36 0.36 16.72
Actual/Plan (ERA % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 2.40
Actual/Plan (CON) % 23.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.38 0.89
Planned by ERA 0.20 0.20 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.60 0.20 10.00
Planned by CON. Km 1.00 1.11 1.52 2.21 2.62 2.42 0.00 0.00 0.00 0.00 0.00 0.00 1.00 10.88
30 Quiha-Maymekden Afro Tsion 24.00 Actual Km 13.29 0.16 0.16 0.16 12.56
Actual/Plan (ERA Km 80.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 80.00 1.60
Actual/Plan (CON) % 16.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! 16.00 1.47

Planned by ERA Km 0.00 0.00 0.00 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.00 8.00
Planned by CON. Km 0.05 0.39 0.83 1.25 1.55 2.24 4.69 2.86 3.23 3.23 3.21 3.82 0.05 27.35
31 Rama-Chilla Melcon Construction PLC 91.13 Actual Km 0.00 0.00 0.00 0.00 0.00
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 0.00
Actual/Plan (CON) % 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Planned by ERA Km 0.50 0.50 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 20.00
Planned by CON. Km 0.35 0.18 1.19 5.11 4.11 4.27 3.73 3.17 3.50 2.85 2.63 0.62 0.35 31.71
32 Semema-Endabaguna Sur Construction Plc. 83.26 Actual Km 52.60 0.31 0.31 0.31 52.91
Actual/Plan (ERA % 62.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 62.00 1.55
Actual/Plan (CON) % 88.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 88.57 0.98
Planned by ERA Km 0.00 0.00 0.00 0.50 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.50 0.00 8.00
Tenta Junction-Wegeltena-Kurba Hebei Construction Group Planned by CON. Km 0.68 1.35 1.94 1.29 1.60 1.91 2.51 2.60 2.52 2.68 2.47 2.68 0.68 24.23
34 79.24 Actual Km 0.83 0.68 0.68 0.68 1.51
(31+500-110+740) Co.Ltd
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 8.50
Actual/Plan (CON) % 100.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.00 2.81
Planned by ERA Km 0.00 0.00 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.00 2.00
Zeluel Yohannes General Planned by CON. Km 0.11 0.06 0.06 0.17 0.18 0.19 0.17 0.20 0.16 0.24 0.41 0.46 0.11 2.41
35 Woldiya Town Section 5.36 Actual Km
Contractor 0.67 0.03 0.03 0.03 0.70
Actual/Plan (ERA % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 1.55
Actual/Plan (CON) % 28.18 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 28.18 1.29

Planned by ERA Km 0.00 0.00 0.50 1.00 2.00 2.50 3.00 3.00 2.50 2.50 2.00 1.00 0.00 20.00
Planned by CON. Km 0.49 0.27 0.80 1.88 1.97 1.95 1.95 1.89 2.05 1.52 1.74 1.96 0.49 18.47
36 Wukro-Atsbi-Koneba Sur Construction Plc. 63.02 Actual Km 2.40 0.25 0.25 0.25 2.65
Actual/Plan (ERA % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 1.25
Actual/Plan (CON) % 51.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 51.02 1.35

Planned by ERA Km 0.50 0.50 1.00 2.00 2.00 3.00 2.00 2.00 2.00 2.00 2.00 1.00 0.50 20.00
Planned by CON. Km 0.00 0.00 1.85 3.84 3.55 3.74 2.73 2.58 2.52 1.33 1.71 1.87 0.00 25.72
37 Wukro-Nebelt Sur Construction 79.62 Actual Km 36.10 0.85 0.85 0.85 36.94
Actual/Plan (ERA % 170.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 170.00 4.25
Actual/Plan (CON) % #DIV/0! #DIV/0! 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 #DIV/0! 3.30

Planned by ERA Km 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5.00
Planned by CON. Km 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
38 Zema River Felegbrhan 0.00 0.00 Actual Km 76.23 0.77 0.77 0.77 77.00
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! 15.40
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 6.80 6.80 21.90 32.70 40.40 50.00 44.70 47.30 44.20 42.20 36.50 22.50 6.80 401.00
Planned by CON. Km 15.21 14.30 41.14 76.81 83.94 85.80 79.24 72.78 71.20 61.52 56.63 43.97 15.21 702.54
Actual Km 826.22 13.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.57 13.57 838.23
Actual/Plan (ERA) % 199.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 199.60 3.38
Actual/Plan (CON) % 89.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 89.24 1.93 ###
Northern Region Directorate
Contractors' Performance Report (End of July 2020)
Reporting Period until:- 28-Jul-20

Contract Amount (Birr) Date of Contract Contract Completion date This period 28-Jul-20
Duration of To date To date
Total length Contract period in This Month in This Month
I.No. Project Name Contractor's Name Mobilization actual progress in Remark
in KM Calendar days % progress in KM
in months progress (%) KM
Revised completion
Commencement Period Elapsed
Original Revised contract signing date Original date after Approved % of time elapsed
Date in Calendar days
EOT

Team-1

1 Abergele-Agbe Sur Consrrction 75.6 1,021,953,000.00 1,021,953,000.00 14-Aug-19 1-Oct-19 4 30-Sep-22 30-Sep-22 1095.00 301.00 27.49 3.04 19.87 2.30 15.02

2 Adiremet-Adihardi-Beakel Sur Consrrction 69.37 1,025,550,000.00 1,025,550,000.00 7-Jun-17 16-Oct-17 4 15-Oct-20 15-Oct-20 1095.00 1016.00 92.79 1.74 82.50 1.21 57.23

3 Adiremet-Kulita-Adigoshu Melcon Construction 59.60 953,000,000.00 953,000,000.00 23-May-17 26-Oct-17 4 25-Oct-20 25-Oct-20 1095.00 1006.00 91.87 0.84 55.40 0.50 33.02

4 Adishehu-Dela-Samre Defence Construction 75.00 2,114,048,067.84 2,114,048,067.84 13-Dec-18 9-May-19 4 8-May-22 8-May-22 1095.00 446.00 40.73 1.00 5.41 0.75 4.06

5 Azezo-Gondar Rama Construction 12.5 871,565,791.41 871,565,791.41 23-May-17 14-Aug-18 2 13-Aug-20 29-Nov-20 838.00 714.00 85.20 1.97 32.78 0.25 4.10

6 Bahirdar-Tisesat Melcon Construction 21.2 767,050,000.00 767,050,000.00 15-Aug-19 16-Dec-19 4 15-Jun-22 15-Jun-22 912.00 225.00 24.67 0.33 1.27 0.07 0.27

7 Gashena - Bilbila CRTG 105 1,442,916,047.83 1,442,916,047.83 15-Jan-14 12-Feb-14 3 18-Jan-18 25-May-20 2294.00 2358.00 102.79 0.06 87.10 0.06 91.46

Tekleberhan Ambaye
8 Maichew-Mehoni 17.43 378,614,038.16 378,614,038.16 23-May-17 29-Sep-17 3 27-Mar-20 15-Sep-20 1082.00 1033.00 95.47 0.00 60.47 0.00 10.54
Construction plc

Mekele -Dengolat - Samre -


9 Defense Const. 94 1,594,387,610.14 1,594,387,610.14 1-Jun-16 1-Nov-16 3 31-Oct-19 31-Jan-21 1552.00 1365.00 87.95 0.17 54.09 0.16 50.84
Finariwa

10 Mekele Industrial Park China Ticjju 18.26 913,224,109.15 913,224,109.15 15-Aug-17 20-Oct-17 2 20-Apr-19 19-Jun-20 973.00 1012.00 104.01 0.38 86.36 0.07 15.77

11 Quiha-Maymekden Afro Tsion 23.33 552,000,000.00 552,000,000.00 23-May-17 14-Jun-17 3 1-Dec-19 20-Sep-20 1194.00 1140.00 95.48 0.21 72.57 0.05 16.93

Tenta Junction-Wegeltena- Hebei Construction


12
Kurba (31+500-110+740) Group Co.Ltd
79.24 1,873,489,476.53 1,873,489,476.53 7-Mar-19 1-Apr-19 4 31-Mar-22 31-Mar-22 1095.00 484.00 44.20 0.80 15.33 0.63 12.15

Zeluel Yohannes
13 Woldiya Town Section 5.36 304,850,794.33 304,850,794.33 24-Jan-18 24-Feb-18 3 24-Feb-20 12-Jan-21 1053.00 885.00 84.05 6.16 37.13 0.33 1.99
General Contractor

14 Wukro-Atsbi-Koneba Sur Construction Plc. 63.02 1,745,722,493.86 1,745,722,493.86 25-Oct-18 17-Dec-18 4 14-Jun-22 14-Jun-22 1275.00 589.00 46.20 1.24 29.24 0.78 18.43

Team Leader Hulunayehu Weji Signature ____________ Date ____________________

Team-2

Powercon Plc in JV
15 Ajire-Keraker with Tesfaye Legesse 57.26 1,158,659,797.00 1,158,659,797.00 18-Jun-18 21-Sep-18 4 20-Sep-21 20-Sep-21 1095.00 676.00 61.74 0.94 32.59 0.540 18.66
Construction

China First Highway


16 Billbila - Sekota 99.75 2,042,059,919.33 2,102,829,450.89 14-Apr-15 12-Jun-15 3 9-Sep-18 11-Nov-20 1979.00 1873.00 94.64 0.50 79.71 0.50 79.51
Eng. Co.Ltd

The ER has recommended 389


17 Dabat-Ajire Powercon 43.20 931,304,149.54 931,304,149.54 19-May-16 10-Oct-16 4 9-Oct-19 9-Aug-20 1399.00 1387.00 99.14 0.24 79.49 0.10 34.34 Cal.days which is commented by the
Employer .

Kunzila Junction- Horticulture


18 Markan Trading Plc. 21.80 554,487,294.06 554,487,294.06 29-Nov-18 23-Jan-18 4 24-Jul-20 16-Apr-21 1179.00 917.00 77.78 0.18 35.55 0.04 7.75
farm- Zege Town

19 Korem-Lalibela Junction Sur Construction 71.70 2,121,050,000.00 2,121,050,000.00 15-Aug-19 14-Feb-20 4 13-Feb-23 13-Feb-23 1095.00 165.00 15.07 3.15 11.98 2.26 8.59

20 Lalibela Junction-Abergle Defence Construction 94.00 1,568,831,426.39 1,568,831,426.39 29-Aug-19 26-Sep-19 4 25-Sep-22 25-Sep-22 1095.00 306.00 27.95 0.07 0.14 0.07 0.13
21 Mekaneyesus/Este-Simada CCCC 53.08 1,925,451,264.45 1,925,451,264.45 24-Oct-18 21-Feb-19 4 21-Feb-22 21-Feb-22 1096.00 523.00 47.72 0.51 11.38 0.27 6.04

22 Metema-Abrehajira SUR Construction Plc 117.3 1,548,000,000.00 1,548,000,000.00 23-May-17 19-Oct-17 4 18-Apr-21 19-Apr-21 1278.00 1013.00 79.26 0.55 75.61 0.64 88.69

Todate progress is reduced due to


23 Mota-Jaragedo Zhongmei 58.22 1,618,179,826.58 1,640,366,117.06 23-May-17 14-Jul-17 3 11-Jan-21 19-Nov-21 1589.00 1110.00 69.86 0.79 52.37 0.46 30.49
variation

Team Leader Gizachew Tadele Signature ____________ Date ____________________

Team-3

24 Abiadi-Semema Sur Construction Plc. 89.07 1,748,000,000.00 1,748,000,000.00 7-Jul-17 20-Dec-17 4 20-Jun-21 20-Jun-21 1278.00 951.00 74.41 0.69 71.45 0.62 63.64

The ER has recommended 325


Afro Tsion
25 Adiabun-Rama 47 807,500,000.00 807,500,000.00 23-May-17 3-Oct-17 4 2-Oct-20 2-Oct-20 1095.00 1029.00 93.97 0.13 36.28 0.06 17.05 Cal.days which is under review by the
Construction
Employer .

Jiangxi Water and


26 Fiyelweha-Tekeze Hydropower 39.50 1,166,300,000.00 1,166,300,000.00 7-Jun-17 26-Sep-17 4 25-Sep-20 11-Nov-20 1142.00 1036.00 90.72 0.23 32.96 0.09 13.02
Construction

China Communications
Kombolcha-Industrial Park
27
Access Road
Construction 3.28 478,975,000.00 478,975,000.00 29-May-19 27-Jun-19 1 26-Jun-20 22-Oct-20 483.00 397.00 82.19 1.25 19.24 0.04 0.63
Company(LTD)

28 Nebelt-Flafel Sur Construction 57.02 1,004,289,005.74 1,004,289,005.74 30-Oct-17 29-Nov-17 4 28-Nov-20 28-Nov-20 1095.00 972.00 88.77 0.14 89.18 0.08 50.85

Melcon Construction
29 Rama-Chilla
PLC
91.13 1,479,881,513.14 1,479,881,513.14 15-Jan-19 1-Apr-19 3 31-Mar-22 9-Jun-22 1165.00 484.00 41.55 2.11 25.72 1.92 23.44

30 Semema-Endabaguna Sur Construction Plc. 83.26 2,252,000,000.00 2,252,000,000.00 7-Jul-17 20-Dec-17 4 20-Jun-21 20-Jun-21 1278.00 951.00 74.41 0.75 81.83 0.62 68.13

31 Wukro-Nebelt Sur Construction 79.57 1,250,636,416.10 1,250,636,416.10 30-Oct-17 29-Nov-17 4 28-Nov-20 28-Nov-20 1095.00 972.00 88.77 1.16 75.05 0.92 59.72

Team Leader Rahel Endashaw Signature ____________ Date ____________________

Team-4

Yencomad
32 Adiarkay-Telemt 76.03 1,981,378,049.64 1,981,378,049.64 31-Oct-18 17-Jan-19 4 16-Jan-22 16-Jan-22 1095.00 558.00 50.96 0.59 12.19 0.45 9.27
Construction PLC.

The Engineer has recommended 200


Defense Construction
33 Beles-Mekane Birehan 39.00 1,018,952,362.90 1,018,952,362.90 26-May-16 1-Nov-16 4 1-Nov-19 27-Mar-20 1242.00 1365.00 109.90 0.00 40.44 0.00 15.77 Cal.days which is under reviewe by the
Enterprise
Employer .

Beijing Urban
34 Debark-Zarima Construction Group 68.62 2,412,000,000.00 2,412,000,000.00 31-May-18 1-Jan-19 4 31-Dec-22 31-Dec-22 1460.00 574.00 39.32 0.17 11.17 0.12 7.67
LTD

FAL General
35 Debre Markos-Debre Elias 81.00 1,299,644,371.61 1,299,644,371.61 19-Apr-18 18-Sep-19 4 16-Jan-23 16-Jan-23 1216.67 314.00 25.81 0.32 8.23 0.26 6.67
Construction PLC.

36 km 69+000-Angereb/Ashere Chinawuyi Co, Lid. 71.15 1,955,438,532.41 1,473,670,095.45 23-May-17 20-Jun-17 4 18-Oct-20 18-Oct-20 1216.00 1134.00 93.26 0.77 51.02 0.55 36.30

todate progress amended due to change


37 Pawi Junction-km69 CRTG 69 887,759,651.45 887,759,651.45 26-Jan-17 1-Jul-17 3 30-Jun-20 19-Mar-21 1357.00 1123.00 82.76 0.04 28.35 0.03 19.56
in quantity of earthwork.

38 Aykel-Km 69+000 Sur Construction 69.00 1,954,142,081.60 2,357,157,719.87 26-May-16 20-Oct-16 4 18-Feb-20 18-Feb-20 1216.00 1377.00 113.24 0.00 73.67 0.00 50.83

NINGXIA
39 Hamusit-Este Communications 76.64 1,395,881,640.48 1,395,881,640.48 22-Jan-20 14-Feb-20 4 14-Feb-23 14-Feb-23 1096.00 165.00 15.05 0.26 0.50 0.20 0.38
Construction Co., Ltd.

Amara Road Works


40 Gonji - Kolela 10.73 333,027,799.74 333,027,799.74 20-Feb-20 15-Apr-20 2 7-Oct-21 7-Oct-21 540.00 104.00 19.26 0.00 0.00 0.00 0.00
Enterprise

Yosef Worku Signature ____________ Date ____________________


Northern Region Construction Projects Management Directorate
Projects Plan Vs Actual Progress for July 2020 and Plan up to June 2021
Total Physical Plan in KM Planed for 2012 Ethiopian Fiscal Year Under North Region Directorate

Unit

Planned by ERA Km 427.15

Planned by CONTRACTORS. Km 446.24

Total ERA's Plan upto the reporting Period Km 8.20

Total Contractor's Plan upto the reporting Period Km 23.96

Total Actual Executed upto the reporting Period Km 17.99


Actual/Plan (ERA) % 219.43
Actual/Plan (CON.) % 75.08

Month
Total plan Up to the
Accomplishment Up
Total Project Reporting Period for Total plan for this EFY Total to date
I.No. Project Name Contractor's Name Unit to the Past EFY
length in KM this EFY Vs Vs Accomplishment Accomplishment in Km
reported July
Accomplishment

Team I

Planned by ERA Km 0.50 0.50 15.00


Planned by CON. Km 0.02 0.02 0.02 ###
1 Abergele-Agbe Sur Consrrction 75.60 Actual Km 12.71 2.30 2.30 2.30 15.02
Actual/Plan (ERA) % 460.00 460.00 15.33
Actual/Plan (CON) % 11,500.00 11,500.00 11,500.00

Planned by ERA Km 0.50 0.50 15.00


Planned by CON. Km 2.29 2.29 2.29 ###
2 Adiremet-Adihardi-Beakel Sur Consrrction 69.37 Actual Km 57.64 1.21 1.21 1.21 57.23
Actual/Plan (ERA) % 242.00 242.00 8.07
Actual/Plan (CON) % 52.84 52.84 52.84

Planned by ERA Km 0.50 0.50 15.00


Planned by CON. Km 1.18 1.18 1.18
3 Adiremet-Kulita-Adigoshu Melcon Construction 59.60 Actual Km 32.52 0.50 0.50 0.50 33.02
Actual/Plan (ERA) % 100.00 100.00 3.33
Actual/Plan (CON) % 42.37 42.37 42.37
Planned by ERA Km 0.50 0.50 15.00
Planned by CON. Km 0.75 0.75 29.41
4 Adishehu-Dela-Samre Defence Construction 75.00 Actual Km 3.71 0.75 0.75 0.75 4.06
Actual/Plan (ERA) % 150.00 150.00 5.00
Actual/Plan (CON) % 100.00 100.00 2.55
Planned by ERA Km 0.00 0.00 5.00
Planned by CON. Km 0.00 0.00
Actual Km 4.86 0.25 0.25 0.25 4.10
5 Azezo-Gondar Rama Construction 12.5 Actual/Plan (ERA) % #DIV/0! #DIV/0! 4.92
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 8.00


Planned by CON. Km 0.16 0.16 0.16
Actual Km 0.20 0.07 0.07 0.07 0.27
6 Bahirdar-Tisesat Melcon Construction 21.2 Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.88
Actual/Plan (CON) % 43.75 43.75 43.75
Unit
Planned by ERA Km 0.00 0.00 5.00
Planned by CON. Km 0.00 0.00 ###
7 Gashena - Bilbila CRTG 105.00 Actual Km 97.60 0.06 0.06 0.06 91.46
Actual/Plan (ERA % #DIV/0! #DIV/0! 1.20
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 5.00


Tekleberhan Ambaye Planned by CON. Km 0.45 0.45 0.45 ###
8 Maichew-Mehoni 17.43 Actual Km
Construction plc 10.54 0.00 0.00 0.00 10.54
Actual/Plan (ERA % #DIV/0! #DIV/0! 0.00
Actual/Plan (CON) % 0.00 0.00 0.00
Planned by ERA Km 0.00 0.00 15.00
Planned by CON. Km 0.46 0.46 0.46
Mekele -Dengolat - Samre - Actual Km
9 Defense Const. 94 50.83 0.16 0.16 0.16 50.84
Finariwa Actual/Plan (ERA) % #DIV/0! #DIV/0! 1.07

Actual/Plan (CON) % 34.69 34.69 34.69

Planned by ERA Km 0.00 0.00 0.00


Planned by CON. Km 0.10 0.10 0.10
10 Mekele Industrial Park China Ticjju 18.26 Actual Km 15.70 0.07 0.07 0.07 15.77
Actual/Plan (ERA) % #DIV/0! #DIV/0! #DIV/0!
Actual/Plan (CON) % 70.00 70.00 70.00

Planned by ERA 0.00 0.00 5.00


Planned by CON. Km 1.24 1.24 1.24
11 Quiha-Maymekden Afro Tsion 23.33 Actual Km 16.88 0.05 0.05 0.05 16.93
Actual/Plan (ERA Km #DIV/0! #DIV/0! 1.00
Actual/Plan (CON) % 4.04 4.04 4.04
Planned by ERA Km 0.50 0.50 15.00
Tenta Junction-Wegeltena-Kurba Hebei Construction Group Planned by CON. Km 0.28 0.28 30.24
12 79.24 Actual Km 11.04 0.63 0.63 0.63 12.15
(31+500-110+740) Co.Ltd
Actual/Plan (ERA % 126.00 126.00 4.20
Actual/Plan (CON) % 227.71 227.71 2.08

Planned by ERA Km 0.00 0.00 2.00


Zeluel Yohannes General Planned by CON. Km 0.23 0.23 0.23
13 Woldiya Town Section 5.36 Actual Km
Contractor 1.66 0.33 0.33 0.33 1.99
Actual/Plan (ERA % #DIV/0! #DIV/0! 16.50
Actual/Plan (CON) % 143.48 143.48 143.48

Planned by ERA Km 0.50 0.50 25.00


Planned by CON. Km 0.49 0.49 23.52
14 Wukro-Atsbi-Koneba Sur Construction Plc. 63.02 Actual Km 17.58 0.78 0.78 0.78 18.43
Actual/Plan (ERA % 156.00 156.00 3.12
Actual/Plan (CON) % 159.18 159.18 3.32
Team II
Planned by ERA Km 0.50 0.50 15.00
Planned by CON. Km 0.83 0.83 29.33
Powercon Plc in JV with Actual Km
15 Ajire-Keraker 57.26 19.17 0.54 0.54 0.54 18.66
Tesfaye Legesse Construction Actual/Plan (ERA % 108.00 108.00 3.60
Actual/Plan (CON) % 65.06 65.06 1.84
Planned by ERA Km 0.00 0.00 15.00
Planned by CON. Km 2.97 2.97 2.97
China First Highway
16 Billbila - Sekota 99.75 Actual Km 79.02 0.50 0.50 0.50 79.51
Eng. Co.Ltd #DIV/0! #DIV/0! 3.33
Actual/Plan (ERA %
Actual/Plan (CON) % 16.78 16.78 16.78

Planned by ERA Km 0.00 0.00 10.00


17 Dabat-Ajire Powercon 43.20 Planned by CON. Km 0.65 0.65 8.70 ###
Actual Km 34.24 0.10 0.10 0.10 34.34
Actual/Plan (ERA % #DIV/0! #DIV/0! 1.02
Actual/Plan (CON) % 15.69 15.69 1.17
Planned by ERA Km 0.00 0.00 8.00
Planned by CON. Km 0.07 0.07 10.31 ###
Kunzila Junction- Horticulture
18 Markan Trading Plc. 21.80 Actual Km 0.04 0.04 0.04 7.75
farm- Zege Town 7.71
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.50
Actual/Plan (CON) % 61.16 61.16 0.39

Planned by ERA Km 0.50 0.50 15.00


19 Korem-Lalibela Junction Sur Construction 71.70 Planned by CON. Km 1.19 1.19 58.90 ###
Actual Km 4.62 2.26 2.26 2.26 8.59
Actual/Plan (ERA % 451.60 451.60 15.05
Actual/Plan (CON) % 189.75 189.75 3.83

Planned by ERA Km 0.00 0.00 0.00


Planned by CON. Km 0.26 0.26 0.00
20 Lalibela Junction-Abergle Defence Construction 94.00 Actual Km 0.06 0.07 0.07 0.07 0.13
Actual/Plan (ERA % #DIV/0! #DIV/0! #DIV/0!
Actual/Plan (CON) % 26.92 26.92 #DIV/0!

Planned by ERA Km 0.50 0.50 0.00


Planned by CON. Km 0.13 0.13 0.00
21 Mekaneyesus/Este-Simada CCCC 53.08 Actual Km 5.84 0.27 0.27 0.27 6.04
Actual/Plan (ERA % 54.00 54.00 #DIV/0!
Actual/Plan (CON) % 212.03 212.03 #DIV/0!

Planned by ERA Km 0.50 0.50 20.00


Planned by CON. Km 0.00 0.00 0.00
22 Metema-Abrehajira SUR Construction Plc 117.30 Actual Km 88.12 0.64 0.64 0.64 88.69
Actual/Plan (ERA % 128.00 128.00 3.20
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.50 0.50 20.00


Planned by CON. Km 0.13 0.13 0.13
Actual Km 0.46 0.46 0.46 30.49
23 Mota-Jaragedo Zhongmei 58.22 35.69
Actual/Plan (ERA) % 92.00 92.00 2.30
Actual/Plan (CON) % 353.85 353.85 353.85

Team III

Planned by ERA Km 0.50 0.50 20.00


Planned by CON. Km 0.03 0.03 21.04 ###
24 Abiadi-Semema Sur Construction Plc. 89.07 Actual Km 63.03 0.62 0.62 0.62 63.64
Actual/Plan (ERA) % 123.40 123.40 3.09
Actual/Plan (CON) % 2,125.86 2,125.86 2.93

Planned by ERA Km 0.00 0.00 10.00


Planned by CON. Km 0.70 0.70 29.98
25 Adiabun-Rama Afro Tsion Construction 47.00 Actual Km 16.99 0.06 0.06 0.06 17.05
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.60
Actual/Plan (CON) % 8.57 8.57 0.20

Planned by ERA Km 0.20 0.20 12.00


Jiangxi Water and Hydropower Planned by CON. Km 1.03 1.03 18.58 ###
26 Fiyelweha-Tekeze 39.50 Actual Km
Construction 12.93 0.09 0.09 0.09 13.02
Actual/Plan (ERA) % 45.00 45.00 0.75
Actual/Plan (CON) % 8.76 8.76 0.48

Planned by ERA Km 0.00 0.00 1.65


Kombolcha-Industrial Park Access China Communications Planned by CON. Km 0.39 0.39 2.71 ###
27 3.28 Actual Km
Road Construction Company(LTD) 0.59 0.04 0.04 0.04 0.63
Actual/Plan (ERA % #DIV/0! #DIV/0! 2.48
Actual/Plan (CON) % 10.51 10.51 1.51
Planned by ERA Km 0.00 0.00 2.00
Planned by CON. Km 0.00 0.00 4.84
28 Nebelt-Flafel Sur Construction 57.02 Actual Km 50.25 0.08 0.08 0.08 50.85
Actual/Plan (ERA % #DIV/0! #DIV/0! 4.00

Actual/Plan (CON) % #DIV/0! #DIV/0! 1.65

Planned by ERA Km 0.50 0.50 15.00


Planned by CON. Km 2.94 2.94 36.80
29 Rama-Chilla Melcon Construction PLC 91.13 Actual Km 21.52 1.92 1.92 1.92 23.44
Actual/Plan (ERA % 384.00 384.00 12.80
Actual/Plan (CON) % 65.32 65.32 5.22

Planned by ERA Km 0.50 0.50 12.00


Planned by CON. Km 0.94 0.94 15.76
30 Semema-Endabaguna Sur Construction Plc. 83.26 Actual Km 67.51 0.62 0.62 0.62 68.13
Actual/Plan (ERA % 124.80 124.80 5.20
Actual/Plan (CON) % 66.38 66.38 3.96

Planned by ERA Km 0.00 0.00 5.00


Planned by CON. Km 0.20 0.20 28.97
31 Wukro-Nebelt Sur Construction 79.57 Actual Km 59.17 0.92 0.92 0.92 59.72
Actual/Plan (ERA % #DIV/0! #DIV/0! 18.40
Actual/Plan (CON) % 460.00 460.00 3.18
Team IV
Planned by ERA Km 0.50 0.50 15.00
Planned by CON. Km 0.24 0.24 39.87 ###
32 Adiarkay-Telemt Yencomad Construction PLC. 76.03 Actual Km 8.82 0.45 0.45 0.45 9.27
Actual/Plan (ERA % 90.00 90.00 3.00
Actual/Plan (CON) % 187.50 187.50 1.13

Planned by ERA Km 0.00 0.00 10.00


Defense Construction Planned by CON. Km 0.00 0.00
33 Beles-Mekane Birehan 39.00 Actual Km
Enterprise 15.77 0.00 0.00 0.00 15.77
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0!
Planned by ERA Km 0.50 0.50 15.00
Beijing Urban Planned by CON. Km 0.00 0.00
34 Debark-Zarima Construction Group 68.621 Actual Km 7.55 0.117 0.12 0.12 7.67
LTD Actual/Plan (ERA % 23.40 23.40 0.78
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 12.00


FAL General Construction Planned by CON. Km 0.56 0.56 37.18 ###
35 Debre Markos-Debre Elias 81.00 Actual Km
PLC. 6.41 0.26 0.26 0.26 6.67
Actual/Plan (ERA) % #DIV/0! #DIV/0! 2.17
Actual/Plan (CON) % 46.43 46.43 0.70

Planned by ERA Km 0.00 0.00 20.00


Planned by CON. Km 2.80 2.80 2.80 ###
36 km 69+000-Angereb/Ashere Chinawuyi Co, Lid. 71.15 Actual Km 35.59 0.55 0.55 0.55 36.30
Actual/Plan (ERA) % #DIV/0! #DIV/0! 2.75
Actual/Plan (CON) % 19.64 19.64 19.64

Planned by ERA Km 0.00 0.00 15.00


Planned by CON. Km 0.04 0.04 0.04 ###
37 Pawi Junction-km69 CRTG 69.00 Actual Km 24.06 0.03 0.03 0.03 19.56
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.20
Actual/Plan (CON) % 75.00 75.00 75.00
Planned by ERA Km 0.00 0.00 7.00
Planned by CON. Km 0.00 0.00 0.00 ###
38 Aykel-Km 69+000 0.00 0.00 Actual Km 50.83 0.00 0.00 0.00 50.83
Actual/Plan (ERA) % #DIV/0! #DIV/0! 0.00
Actual/Plan (CON) % #DIV/0! #DIV/0! #DIV/0!

Planned by ERA Km 0.00 0.00 7.50


Planned by CON. Km 0.23 0.23 0.23 ###
39 Hamusit-Este 0.00 0.00 Actual Km 0.00 0.20 0.20 0.20 0.38
Actual/Plan (ERA) % #DIV/0! #DIV/0! 2.67
Actual/Plan (CON) % 86.96 86.96 86.96

Planned by ERA Km 0.00 0.00 0.00


Planned by CON. Km 0.00 0.00 7.80 ###
40 Gonji - Kolela 0.00 0.00 Actual Km 0.00 0.00 0.00 0.00 0.00
Actual/Plan (ERA) % #DIV/0! #DIV/0! #DIV/0!
Actual/Plan (CON) % #DIV/0! #DIV/0! 0.00

Planned by ERA Km 8.20 8.20 427.15


Planned by CON. Km 23.96 23.96 446.24
Actual Km 1,030.95 17.99 17.99 17.99 1,048.94
Actual/Plan (ERA) % 219.43 219.43 4.21
Actual/Plan (CON) % 75.08 75.08 4.03 ###