SIEVE ANALYSIS

Consultant Contractor

APPENDIX: 4

GENERAL SPECIFICATION
SIEVE ANALYSIS

Consultant Contractor

APPENDIX: C

ALL QUALITY TEST

AGGREGATE BASE COURSE


SIEVE ANALYSIS

Consultant Contractor

APPENDIX: B

1- SOIL CLASSIFICATION

2- MOISTURE DENSITY RELATION SHIP

3- C.B.R
SIEVE ANALYSIS

Consultant Contractor

APPENDIX: A

1- SIEVE ANALYSIS

2- BLENDING OF AGGREGATE

JOB MIX FORMULA


MIX DESIGN FOR AGGREGATE. BASE COARSE CLASS "1"

TABLE OF CONTENTS

SL. # TEST DESCRIPTION PAGE No.

1 MIX DESIGN DATA FORMS & SUMMARY 1-2

2 CBR CURVE. 3

3 CBR CURVE. 4

4 PROCTOR CURVE. 5

5 COMBINED AGGREGATE GRADATION. 6

7 COMBINED GRADATION CHART (PROPORTIONING OF AGGREGATE) 7

8 COMBINED BLENDING WORK SHEET. 8

9 WORKSHEET FOR SAND EQUIVALENT 9

10 WORKSHEET FOR CLAY LUMPS & FRIABLE PARTICLES 10

11 WORKSHEET OF THIN & ELONGATED PIECES 11

12 WORKSHEET OF SODIUM SOUNDNESS 12

13 WORKSHEET OF ABRASION TEST. 13

14 WORK SHEET OF L.L & P.L . 14

15 SIEVE ANALYSIS OF AGGREGATES 15 - 26


MIX DESIGN SUMMARY

AGGREGATE BASE COARSE GRADING-1

SIEVE # 11/2" 1" 3/4" #4 #40 #200


GRADATION

PASS % 100 77.1 63.4 42.4 17.8 3.4


JMF Tolerance 100 68.1 - 85 54.4 - 72.4 34.4 - 50.4 11.8 - 23.8 3 - 7.4
SPECIF. 100 55 - 85 50 - 80 30 - 60 10 - 25 3 - 10

DESCRIPTION RESULTS SPECIFICATION


SOUNDNESS 1.859 12% MAX
ABRASION 19 45% MAX
SAND EQUIVALENT 52% 45% MIN
CLAY LUMPS 0.158% 0.25% MAX
THIN & ELONGATED 3.23% 10% MAX
PLASTICITY N.P
M.C 6.7
PROCTOR
M.D.D 2.290
C.B.R 140 100 MIN
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
MIX DESIGN

AGGREGATE BASE COARSE GRAD "1" & ENGINARING FILL

PROJECT

CONSULTANT

CONTRACTOR
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 1

Description AGGREGATE (( 1 /2"))


1
Sampled Date 4/4/2011
Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 6251.2 Wash O.D.Wt 6251.2

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2½" 0 0.0
2" 0 0.0
1½" 61 6190.2 99.0
1" 3527.7 2723.5 43.6
3
/4 " 5675 576.2 9.2
1
/2" 6238.9 12.3 0.2
3
/8" 6246.6 4.6 0.1
1
/4" 0 0.0

No. 4 6246.6 4.6 0.1


No. 8 6246.6 4.6 0.1
No. 10 6246.6 4.6 0.1
No. 16 6246.6 4.6 0.1
No. 30 6246.6 4.6 0.1
No. 40 6246.6 4.6 0.1
No. 50 6246.6 4.6 0.1
No. 60 0 0.0
No. 80 0 0.0
No. 100 6246.6 4.6 0.1
No. 200 6246.6 4.6 0.1
Pan 4
Wash No. 200
TOTAL 6250.6

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 2

Description AGGREGATE (( 1 1/2")) Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 6251.2 Wash O.D.Wt 6251.2

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2½" 0 0.0
2" 0 0.0
1½" 61 6190.2 99.0
1" 3527.7 2723.5 43.6
3
/4 " 5675 576.2 9.2
1
/2" 6238.9 12.3 0.2
3
/8" 6246.6 4.6 0.1
1
/4" 0 0.0

No. 4 6246.6 4.6 0.1


No. 8 6246.6 4.6 0.1
No. 10 6246.6 4.6 0.1
No. 16 6246.6 4.6 0.1
No. 30 6246.6 4.6 0.1
No. 40 6246.6 4.6 0.1
No. 50 6246.6 4.6 0.1
No. 60 0 0.0
No. 80 0 0.0
No. 100 6246.6 4.6 0.1
No. 200 6246.6 4.6 0.1
Pan 2.4
Wash No. 200
TOTAL 6249

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 3

Description AGGREGATE (( 1 /2"))


1
Sampled Date
Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 6251.2 Wash O.D.Wt 6251.2

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2½" 0 0.0
2" 0 0.0
1½" 61 6190.2 99.0
1" 3527.7 2723.5 43.6
3
/4 " 5675 576.2 9.2
1
/2" 6238.9 12.3 0.2
3
/8" 6246.6 4.6 0.1
1
/4" 0 0.0

No. 4 6246.6 4.6 0.1


No. 8 6246.6 4.6 0.1
No. 10 6246.6 4.6 0.1
No. 16 6246.6 4.6 0.1
No. 30 6246.6 4.6 0.1
No. 40 6246.6 4.6 0.1
No. 50 6246.6 4.6 0.1
No. 60 0 0.0
No. 80 0 0.0
No. 100 6246.6 4.6 0.1
No. 200 6246.6 4.6 0.1
Pan 2.4
Wash No. 200
TOTAL 6249

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS SUMMARY

11/2"

SIEVE SIZE SAMPLE 1 SAMPLE 2 SAMPLE 3 SAMPLE 4 AVEREGE

2½" `
2"
1½" 99.0 99.0 99.0 99.0
1" 43.6 43.6 43.6 43.6
3
/4 " 9.2 9.2 9.2 9.2
1
/2" 0.2 0.2 0.2
3
/ 8" 0.1 0.1 0.1
1
/4" 0.0 0.0 0.0
No. 4 0.1 0.1 0.1 0.1
No. 8 0.1 0.1 0.1
No. 10 0.1 0.1 0.1 0.1
No. 16 0.1 0.1 0.1
No. 30 0.1 0.1 0.1
No. 40 0.1 0.1 0.1 0.1
No. 50 0.1 0.1 0.1
No. 60 0.0 0.0 0.0
No. 80 0.0 0.0 0.0
No. 100 0.1 0.1 0.1
No. 200 0.1 0.1 0.1 0.1

REMARK

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 1

Description AGGREGATE ((3/4")) Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 3233.3 Wash O.D.Wt 3233.3

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1"
3
/4 " 26.8 3206.5 99.2
1
/2" 1995.6 1237.7 38.3
3
/8" 3045.3 188 5.8
1
/4" 0 0.0

No. 4 3209.8 23.5 0.7


No. 8 3215.9 17.4 0.5
No. 10 0 0.0
No. 16 3227.3 6 0.2
No. 30 0 0
No. 40 0 0.0
No. 50 0 0
No. 60 0 0
No. 80 0 0
No. 100 0 0
No. 140 0 0
No. 200 3227.3 6 0.2
Pan 8
Wash No. 200
TOTAL 3235

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 2

Description AGGREGATE ((3/8")) Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 3233.3 Wash O.D.Wt 3233.3

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1"
3
/4 " 26.8 3206.5 99.2
1
/2" 1995.6 1237.7 38.3
3
/8" 3045.3 188 5.8
1
/4" 0 0.0

No. 4 3209.8 23.5 0.7


No. 8 3215.9 17.4 0.5
No. 10 0 0.0
No. 16 3227.3 6 0.2
No. 30 0 0
No. 40 0 0.0
No. 50 0 0
No. 60 0 0
No. 80 0 0
No. 100 0 0
No. 140 0 0
No. 200 3227.3 6 0.2
Pan 4
Wash No. 200
TOTAL 3231

Remarks

Tested By: Checked By:


Date: 5/4/2011 Date: 5/4/2011
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 3

Description AGGREGATE ((3/4")) Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 3233.3 Wash O.D.Wt 3233.3

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1"
3
/4 " 26.8 3206.5 99.2
1
/2" 1995.6 1237.7 38.3
3
/8" 3045.3 188 5.8
1
/4" 0 0.0

No. 4 3209.8 23.5 0.7


No. 8 3215.9 17.4 0.5
No. 10 0 0.0
No. 16 3227.3 6 0.2
No. 30 0 0
No. 40 0 0.0
No. 50 0 0
No. 60 0 0
No. 80 0 0
No. 100 0 0
No. 140 0 0
No. 200 3227.3 6 0.2
Pan 4
Wash No. 200
TOTAL 3231

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS SUMMARY

3/8"

SIEVE SIZE SAMPLE 1 SAMPLE 2 SAMPLE 3 SAMPLE 4 AVEREGE

2½" `
2"
1½"
1"
3
/4 " 99.2 99.2 99.2 99.2
1
/2" 38.3 38.3 38.3 38.3
3
/8" 5.8 5.8 5.8 5.8
1
/4" 0.0 0.0 0.0 0.0
No. 4 0.7 0.7 0.7 0.7
No. 8 0.5 0.5 0.5 0.5
No. 10 0.0 0.0 0.0 0.0
No. 16 0.2 0.2 0.2 0.2
No. 30 0 0 0 0.0
No. 40 0.0 0.0 0.0 0.0
No. 50 0 0 0 0.0
No. 60 0 0 0 0.0
No. 80 0 0 0 0.0
No. 100 0 0 0 0.0
No. 140 0 0 0 0.0
No. 200 0.2 0.2 0.2 0.2

REMARK

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 1

Description AGGREGATE ((3/8")) Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 3416.4 Wash O.D.Wt

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1"
3
/4 " 0 3416.4 100.0
1
/2" 11 3405.4 99.7
3
/8" 365.8 3050.6 89.3
1
/4" 0 0.0

No. 4 2843.3 573.1 16.8


No. 8 3389.1 27.3 0.8
No. 10 0 0.0
No. 16 3401.9 14.5 0.4
No. 30 3412.8 3.6 0.105374078
No. 40 0 0.0
No. 50 0 0
No. 60 0 0
No. 80 0 0
No. 100 0 0
No. 140 0 0
No. 200 3416.3 0.1 0.0
Pan 4
Wash No. 200
TOTAL 3420

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 2

Description AGGREGATE ((3/8")) Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 3416.4 Wash O.D.Wt

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1"
3
/4 " 0 3416.4 100.0
1
/2" 11 3405.4 99.7
3
/8" 365.8 3050.6 89.3
1
/4" 0 0.0

No. 4 2843.3 573.1 16.8


No. 8 3389.1 27.3 0.8
No. 10 0 0.0
No. 16 3401.9 14.5 0.4
No. 30 3412.8 3.6 0.1
No. 40 0 0.0
No. 50 0 0
No. 60 0 0
No. 80 0 0
No. 100 0 0
No. 140 0 0
No. 200 3416.3 0.1 0.0
Pan 3.1
Wash No. 200
TOTAL 3419.4

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 3

Description AGGREGATE ((3/8")) Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 3416.4 Wash O.D.Wt

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1"
3
/4 " 0 3416.4 100.0
1
/2" 11 3405.4 99.7
3
/8" 365.8 3050.6 89.3
1
/4" 0 0.0

No. 4 2843.3 573.1 16.8


No. 8 3389.1 27.3 0.799086758
No. 10 0 0.0
No. 16 3401.9 14.5 0.42442337
No. 30 3412.8 3.6 0.105374078
No. 40 0 0.0
No. 50 0 0
No. 60 0 0
No. 80 0 0
No. 100 0 0
No. 140 0 0
No. 200 3416.3 0.1 0.0
Pan 3.1
Wash No. 200
TOTAL 3419.4

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS SUMMARY

3/8"

SIEVE SIZE SAMPLE 1 SAMPLE 2 SAMPLE 3 SAMPLE 4 AVEREGE

2½" `
2"
1½"
1"
3
/4 " 100.0 100.0 100.0 100.0
1
/2" 99.7 99.7 99.7 99.7
3
/8" 89.3 89.3 89.3 89.3
1
/4" 0.0 0.0 0.0 0.0
No. 4 16.8 16.8 16.8 16.8
No. 8 0.8 0.8 0.8 0.8
No. 10 0.0 0.0 0.0 0.0
No. 16 0.4 0.4 0.4 0.4
No. 30 0.105374078 0.105374078 0.105374078 0.1
No. 40 0.0 0.0 0.0 0.0
No. 50 0 0 0 0.0
No. 60 0 0 0 0.0
No. 80 0 0 0 0.0
No. 100 0 0 0 0.0
No. 140 0 0 0 0.0
No. 200 0.0 0.0 0.0 0.0

REMARK

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 1

Description CRUSHED SAND -1 Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 1885.4 Wash O.D.Wt 1729

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1" 0 0
3
/4 " 0 0.0
1
/2"
3
/8" 0 0.0
1
/4" 0 0.0

No. 4 3 1882.4 99.8


No. 8 352.3 1533.1 81.3
No. 10 583.3 1302.1 69.1
No. 16 692.3 1193.1 63.3
No. 30 882.2 1003.2 53.2
No. 40 1212.3 673.1 35.7
No. 50 1502.3 383.1 20.3
No. 60 0 0.0
No. 80 0 0.0
No. 100 1532.3 353.1 18.7
No. 140 0 0
No. 200 1603.2 282.2 15.0
Pan 32
Wash No. 200 250.2
TOTAL 1885.4

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 2

Description CRUSHED SAND -1 Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 1885.4 Wash O.D.Wt 1729

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1" 0 0
3
/4 " 0 0.0
1
/2"
3
/8"
1
/4" 0 0.0

No. 4 3 1882.4 99.8


No. 8 352.3 1533.1 81.3
No. 10 583.3 1302.1 69.1
No. 16 692.3 1193.1 63.3
No. 30 882.2 1003.2 53.2
No. 40 1212.3 673.1 35.7
No. 50 1502.3 383.1 20.3
No. 60 0 0.0
No. 80 0 0.0
No. 100 1532.3 353.1 18.7
No. 140 0 0.0
No. 200 1603.2 282.2 15.0
Pan 25
Wash No. 200 257.2
TOTAL 1885.4

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS

Consultant Contractor
Project Sample No 3

Description CRUSHED SAND -1 Sampled Date


Location Sampled By
Source Method ASTM C 136

Original Wt. Oven Dry Wt. 1885.4 Wash O.D.Wt 1729

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING CUM.RETAINED RETAINED SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent) (Percent)

2" 0 0
1½" 0 0
1"
3
/4 "
1
/2"
3
/8"
1
/4"
No. 4 3 1882.4 99.8
No. 8 352.3 1533.1 81.3
No. 10 583.3 1302.1 69.1
No. 16 692.3 1193.1 63.3
No. 30 882.2 1003.2 53.2
No. 40 1212.3 673.1 35.7
No. 50 1502.3 383.1 20.3
No. 60 0 0.0
No. 80 0 0.0
No. 100 1532.3 353.1 18.7
No. 140 0 0.0
No. 200 1603.2 282.2 15.0
Pan 25
Wash No. 200 257.2
TOTAL 1885.4

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SIEVE ANALYSIS SUMMARY

C.S-1

SIEVE SIZE SAMPLE 1 SAMPLE 2 SAMPLE 3 SAMPLE 4 AVEREGE

2½" `
2"
1½"
1"
3
/4 "
1
/2"
3
/8"
1
/4"
No. 4 99.8 99.8 99.8 99.8
No. 8 81.3 81.3 81.3 81.3
No. 10 69.1 69.1 69.1 69.1
No. 16 63.3 63.3 63.3 63.3
No. 30 53.2 53.2 53.2 53.2
No. 40 35.7 35.7 35.7 35.7
No. 50 20.3 20.3 20.3 20.3
No. 60 0.0 0.0 0.0 0.0
No. 80 0.0 0.0 0.0 0.0
No. 100 18.7 18.7 18.7 18.7
No. 140 0.0 0.0 0.0 0.0
No. 200 15.0 15.0 15.0 15.0

REMARK

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
BLENDING WORKSHEET

Consultant Contractor
Project SAMPLE
Description BLENDING MATERIALS Date
Source METHOD ASTM C 136

Aggregate -1 Aggregate -2 Aggregate -3 Aggregate -4 Aggregate -5 Combined


Material
11/2" 3/4" 3/8" c/s NATURAL SAND-2 Gradation
Specification
Percent Used 35% 15% 10% 40% 0% 100% JMF TOLERANCE
Limits
% % % % % % % % JMF
U.S. Sieves
Passing Batch Passing Batch Passing Batch Passing Batch
2" 100.0 35.0 100 15.0 100 10 100 40 0 0 100 100 100
1 1/2" 100.0 35.0 100 15.0 100 10 100 40 0 0 100.0 ---------- ----------
1" 43.6 15.3 100 15.0 100 10 100 40 0 0 80.3 71.3 89.3 55
3/4" 9.2 3.2 99.2 14.9 100 10 100 40 0 0 68.1 59.1 77.1 50
1/2" 0.0 0 0
3/8" 0.0 0 0
No. 4 0.1 0.0 0.7 0.1 16.8 1.7 99.8 40 0.0 0 41.7 33.7 49.7 30
No. 10 0.0 0.0 0
No. 40 0.1 0.0 0.1 0.0 0.1 0.0 35.7 14.3 0.0 0.0 14.3 8.3 20.3 10
No. 80 0.0 0.0
No. 200 0.1 0.0 0.1 0.0 0.1 0.0 15.0 6.0 0.0 0.0 6.1 3.0 10.1 3.0

General Remarks:-

Tested By Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT

TOTAL 10000

3/4 3/8 C.S 11/2 1


% 12 7 55 Err:522 16 10

WT. 1200 700 5500 Err:522 1600 1000


Specification
Limits

100
----------
85
80 15

60

25

10.0
M.E CONSULTANT
GRADATION CHART

INCH #200 #40 #4 3/4" 1" 1 ½"


SIEVE SIZE
MM 0.075 0.425 4.76 9.52 19.1 25.4
% PASSING 6.1 14.3 41.7 68.1 80.3 100.0
LOWER 3.0 8.3 33.7 59.1 71.3 100.00
J.M.F TOLERANCE
UPPER 10.1 20.3 49.7 77.1 89.3 100.00
LOWER 3.00 10.00 30.00 50.00 55.00 100.00
SPECIFICATION
UPPER 10.00 25.00 60.00 80.00 85.00 100.00

J.M.F
J.M.F TOL-
ERANCE
SPEC. LIMIT

120.0

100.0 6

80.0
% PASSING

60.0

40.0

20.0 2

0.0
0 5 10 15 20 25
SEIVE IN (mm)

Plotted By:
Date:

M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT


12.5 61 55 70
9.52 52 46 58
4.76 38 32 44
2 23 18 28
0.425 8 5 11
0.18 6 3 13
0.075 4.9 3.4 6.4
SIEVE ANALYSIS

Consultant Contractor
Project Sampled Date
Description ABC GRADATION - 1 Sampled No 1
Location Sampled By

Original Wt. Oven Dry Wt. 5281 Wash O.D.Wt

SIEVE SIZE WT. RETAINED CUM WT. CUM. PASSING JMF SPECIFICATIONS REMARKS
(grams) PASS'G (gm) (Percent) (Percent) (Percent)

2" 0 5281.0 100 100 100


1½" 203.0 5078.0 96.2
1" 1489.4 3791.6 71.8 68.1 - 85 55 - 85
3
/4 " 1826.9 3454.1 65.4 54.4 - 72.4 50 - 80
1
/2 " 2234.6 3046.4 57.7
3
/8 " 2490.3 2790.7 52.8
0.0 0.0
No. 4 2767.6 2513.4 47.6 34.4 - 50.4 30 - 60
No. 8 3636.0 1645.0 31.1
No. 16 3954.9 1326.1 25.1
No. 30 4423.5 857.5 16.2

No. 40 4589.0 692.0 13.1 11.8 - 23.8 10 - 25


0.0 0.0
No. 50 4698.6 582.4 11.0
0.0 0.0
No. 100 4765.5 515.5 9.8

No. 200 4992 289 5.5 3.0 - 7.4 3 - 10


Pan 32
Wash No. 200 257
TOTAL 5281

Remarks

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
SOUNDNESS OF AGGREGATE BY ( SODIUM SULPHATE )

Consultant Contractor
Project
Description A.B.C GRADING - 1 Date
Location METHOD

Grading Weight Test Weight Test Loss in Weight Actual Loss Corrected Average
Sieve Size
Original Sample Fraction Before Fraction After After Test After Test Weighted Loss

% Retained Test g. Test g. g. % %


Passing Retained
(A) (B) (C) (D) (E) (F)
No. 100 - 9.8
No. 50 No. 100 1.8 100.4 96.3 4.1 4.08 0.07
FINE AGGREG.

No. 30 No. 50 4.8 100.18 94.80 5.38 5.37 0.26


No. 16 No. 30 8.3 100.12 94.60 5.52 5.51 0.46
No. 8 No. 16 8.2 100.80 92.30 8.5 8.43 0.69
No. 4 No. 8 8.5 100.46 92.70 7.76 7.72 0.66

TOTALS 41.4 2.137

3/8" #4 12.1 300.40 293.40 7 2.33 0.28


COARSE AGGREG.

3/4" 3/8" 14.5 1001.20 984.60 16.6 1.66 0.24


1½" 3/4" 30.2 1502.60 1486.7 15.9 1.06 0.32

TOTALS 56.8 0.842

TOTAL 2.979

NOTE :
D = B - C ( 3/8 to 3/4 in consist of 33% 3/8 to 1/2 in material & 67% 1/2 to 3/4 in material )
E = ( D / B ) x100 ( 3/4 to 1 1/2-in consist of 33% 3/4 to 1-in material & 67% 1 to 11/2-in material )
F = ( A x E ) / 100 (11/2 to 21/2-in consist of 50% 11/2 to 2 in material & 50% 2 to 21/2-in material )

Specification = 12 % Max.
Remarks :

Tested By: Checked By:


Date: Date:

M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT


LOS ANGELES ABRASION

Consultant Contractor
Project
Description A.B.C GRADING - 1 Date
Location METHOD

Test Class A B C D
Abrasive Change ( No of Sphere ) 12 11 8 6
Sieves SAMPLE MASS
Passing Retained g.
mm in. mm in
37.5 11/2 in 25 1in 1250
25 1in 19 3/4in 1250
19 3/4 in 12.5 1/2in 1250 2500
12.5 1/2 in 9.5 3/8in 1250 2500
9.5 3/8 in 6.35 1/4in 2500
6.35 1/4 in 1.75 No.4 2500
4.75 No.4 2.36 No.8 5000
TOTAL 5000 5000 5000 5000
Mass of Sample Before Test g. 5012.3 5014.2
Mass of Sample Retained on 1.70mm(No 12) 4008.3 3892.4

Los Angeles Wear (%) = 5000 - Mass Retained x 100 20.0% 22.4%
5000

Remarks: SPECIFICATION REQUIREMENTS 45% MAX.

Tested By: Checked By:


Date: Date:

M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT


CLAY LUMPS AND FRIABLE PARTICLES IN AGGREGATE

Consultant Contractor
Project Sample No. 1
Description A.B.C GRADING -1 Date
Location METHOD ASTM C 142

RETAINED % WT. OF WT. OF QTY


OF ORIGINAL DRY SAMPLE SAMPLE AFTER LOSS OF WT % OF LOSS CORRECTED
ASTM SIEVE SIZE
SAMPLE BEFORE TEST 24 H SOAKING AFTER TEST AFTER TEST % LOSS
GR. GR. GR.
PASSING RETAINED A B C D E F

COARSE AGGREGATE
1½"(37.5mm) 3/4"(19.0mm) 32.7 1504.50 1501.80 2.700 0.179 0.059
3/4"(19.0mm) 3/8" (9.50mm) 14.5 1506.30 1499.80 6.500 0.432 0.063
3/8" (9.50mm) #4 (4.75 mm) 12.1 1004.70 1003.70 1.000 0.100 0.012

FINE AGGREGATE
# 4 # 16 17.7 100.70 100.60 0.10 0.10 0.018
TOTAL 77.0 0.151

CLAY LUMPS = 0.196

NOTE :
D=B-C
E = ( D/ B) 100
F = ( A x E ) / 100 ( FOR COARSE AGGREGATE ONLY )
REMARKS :
Specification = 0.25% Maximum

Tested By: Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
Kingdom of Saudi Arabia ‫المملـكــــــة العـربيــه السعـوديـــة‬
Ministry of Transport ‫وزارة النقل‬
Materials Testing Division ‫قسم فحص المواد‬

THIN AND ELONGATED PIECES

Consultant SAUDCONSULT Contractor AL MASAR AL HADEETH CO.LTD.

Project COMPLETION OF SOME ROADS (GROUP-4)

Description A.B.C GRADING - 1 Sample No. 1

Location A.B.C Basita Date 5/18/2014

SIEVE SIZE MASS "B" (g)


TEST MASS "A" (g) WEIGHED
THIN PERCENTAGE OF THIN
PORTION TEST PERCENT
ELONGATED ELONGATED PIECES
PERCENT SAMPLE B/A X 100
PASSING RETAINED PIECES

1½" (37.5 mm) 3/4" (19mm) 32.7 3008 128.6 4.275 1.398

3/4" (19mm) 1/2" (12.5 mm) 4.5 2007 98.4 4.903 0.221

1/2" (12.5 mm) 3/8" (9.5mm) 10.0 1522 98.3 6.459 0.646

3/8" (9.50mm) No.4 (4.75mm) 12.1 1012.0 120.5 11.907 1.441

TOTAL 59.3 3.71

PERCENT OF THIN AND ELONGATED PIECES 6.25

REMARKS :
Specification - Max 15 %

Tested By: Checked By:


Date: 5/18/2014 Date: 5/18/2014
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
Kingdom of Saudi Arabia ‫المملـكــــــة العـربيــه السعـوديـــة‬
Ministry of Transport ‫وزارة النقل‬
Materials Testing Division ‫قسم فحص المواد‬

SAND EQUIVALENT

Consultant SAUDCONSULT Contractor AL MASAR AL HADEETH COMPNAY LTD.

Project COMPLETION OF SOME ROADS (GROUP-4) Sampled Date 4/4/2011

Description A.B.C GRADING - 1 Sampled No 1

Location SAKAKA AL JOUF REGION Sampled By Muhammad Abrar

DESCRIPTION OF SAMPLE :

1 2 3

A SAND READING 3.2 3.4

B CLAY READING 6.2 6.6

C SAND EQUIVALENT(A:Bx100) 51.6 51.5

D AVERAGE % 51.6
F CORRECTED % 52

REMARKS:

Specification Requirement - 45 % Min.

Tested By: Muhammad Abrar Checked By: Wael Helmy Badawy

Date: 7/4/2011 Date: 7/4/2011


Muhammad Abrar Wael Helmy Badawy Ayman Mahmoud
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT
MOISTURE-DENSITY RELATION OF SOIL

Consultant Contractor
Project Sample Date
Description A.B.C GRADING - 1 Sample No 1
Location Testing Date

A Trial No. No. 1 2 3 4 5


B Wt. Mold. Wet Soil g. 9355 9665 9820 9930 9900
C Wt. Mold g 4725 4725 4725 4725 4725
D Wt. Wet Soil B-C g 4630 4940 5095 5205 5175
E Volume of Mold cc. 2124 2124 2124 2124 2124
F Wet Density (B-C)/E g/cc 2.180 2.326 2.399 2.451 2.436
G Container No. B D A C G
H Wt. Cont. + Wet Soil g 345.9 313.5 325.7 338.2 310.4
I Wt. Cont. + Dry Soil g 338.4 302.2 310.5 318.1 287.0
L Wt. Water H-I g 7.5 11.3 15.2 20.1 23.4
M Wt. Container g 37.9 26.5 33.9 37.2 27.3
N Wt. Dry Soil I-M g 300.5 275.7 276.6 280.9 259.7
2.50 4.10 5.50 7.16 9.01
P Moisture Content 100 x L/N % 2.5 4.1 5.5 7.2 9.0

R Dry Density 100 x F/(100+P) g/cc 2.127 2.234 2.274 2.286 2.235

2.35

Soil Classificat
2.30

Weight of Ham 10 lbs


Dry Density g/cc

Drop of Hamm 18" 2.25

No. of Layers 5

2.20
No. of Blows 56

2.15

Max. Dry Dens 2.290

2.10
1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0
Optimum Moist 6.7%

Moisture Content %
Moisture Content %

M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT


CALIFORNIA BEARING RATIO

CONTRACT CONTRACTOR
PROJECT Date Sampled
DESCRIPTION A.B.C GRADING -1 Sampled By
Location Testing Date

MOISTURE CONTENT DENSITY DETERMINATION

CAN No D B C MOLD NO. A B C

Can + Wet Soil gr 323.2 328.6 366 Mold + Wet Soil gr 10970 11100 11545

Can + Dry Soil gr 306 311.0 346.5 Wt. Mold gr 6283 6281 6621

Wt. of Can gr 33.4 31.2 35.6 Wt. Wet Soil gr 4687 4819 4924

Wt. of Water gr 17.2 17.6 19.5 Mold Volume cc 2098 2108 2125

Wt. of Dry Soil gr 272.6 279.8 310.9 Wet Density gr/cc 2.234 2.286 2.317

Moisture Content % 6.31 6.29 6.27 Moisture Content % 6.31 6.29 6.27

Average % 6.3 Dry Density gr/cc 2.102 2.151 2.180

NO OF BLOWS 10 30 65 4.3135
BLOWS 65 BLOWS 30
%C.B. %C.B.
Unit Unit
Time Pent Load Stnd % R Time Pent Load Stnd % R
Reading Load Reading Load
Min. mm. (Kg) Load C.B.R Correct Min. mm. (Kg) Load C.B.R Correct
Kg/Cm2 Kg/Cm2
ed ed
1/2 0.635 118.0 509.0 26.3 1/2 0.635 36.0 155.3 8.0

1 1.27 180.0 776.4 40.1 1 1.27 125.0 539.2 27.9

2 2.54 420.0 1811.7 93.6 70.3 133.1 2 2.54 288.0 1242.3 64.2 70.3 91.3

3 3.81 562.0 2424.2 125.3 3 3.81 386.0 1665.0 86.0

4 5.08 625.0 2695.9 139.3 105.5 132.0 4 5.08 430.0 1854.8 95.9 105.5 90.9

6 7.62 810.0 3493.9 180.6 133 6 7.62 600.0 2588.1 133.8 133

8 10.16 900.0 3882.2 200.6 161 8 10.16 660.0 2846.9 147.1 161

.
BLOWS 10
%C.B. 250
Unit
Time Pent Load Stnd % R
Reading Load
Min. mm. (Kg) Load C.B.R Correct
Kg/Cm2
ed
1/2 0.635 18.0 77.643 4.0
225

1 1.27 58.0 250.18 12.9


200
2 2.54 138.0 595.26 30.8 70.3 43.8

3 3.81 138.0 595.26 30.8


175
4 5.08 199.0 858.39 44.4 105.5 42.1

6 7.62 267.0 1151.7 59.5 133


150
8 10.16 315.0 1358.8 70.2 161

125
Test no. 1 2 3
No. Of Blows 10 30 65
100
Date Of Test 5/23/2014
Mold No. A B C
75
FINAL HEIGHT mm 0.25 0.18 0.15
INITIAL HEIGHT mm 0 0 0
50
DIFFRENCE mm 0.25 0.18 0.15
SAMPLE LEGNTH mm 116.43 116.43 116.43 25
PERCENT OF SWELL (%) 0.2147 0.1546 0.1288
0
0.00 2.00 4.00 6.00 8.00 10.00 12.00
250

225

200

175

150

125

100

75

50

25

0
0.00 2.00 4.00 6.00
1.27 2.54 3.81 5.08 7.62 8.00 10.00
10.16 12.00
0.635
Penetration in mm.

PROCTOR MODIFIED
O.M.C. 6.3%
M.D.D. 2.168 A.B.C Basita
M.E CONTRACTOR M.I CONSULTANT M.I CONSULTANT
CALIFORNIA BEARING RATIO

Project COMPLETION OF SOME ROADS (GROUP-4) Sample No. 1

Description A.B.C GRADING -1 Date Sampled 5/19/2014

Location A.B.C Basita Testing Date 5/19/2014

Testing By Mohamed Ali METHOD

CBR - Values
C.B.R No OF CBR AT
170.0
Va;ue of C.B.R

BLOWS 2.54 mm 5.08m

150.0
10 43.8 42.1

130.0
30 91.3 90.9
110.0

65 133.1 132.0
90.0

70.0

50.0
SWELL DATA

30.0 Dry
Blows
2 2.05 2.1 2.15 2.2 2.25 2.3 2.35 2.4
Max.Dry Density Density

10 2.102

30 2.151

65 2.180

Max. Density: 2.168

Opt. Moisture: 6.3%


CBR AT COMPACTION 100% 118

M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT


BLENDING WORKSHEET

Consultant Contractor
Project SAMPLE
Description BLENDING MATERIALS Date
Source METHOD ASTM C 136

Aggregate -1 Aggregate -2 Aggregate -2 Aggregate -4 Aggregate -2 Combined


Material
11/2" 3/4" 3/8" CRUSHED SAND-1 NATURAL SAND-2 Gradation
Specification
Percent Used 40% 0% 35% 15% 10% 100% JMF TOLERANCE
Limits
% % % % % % % % JMF
U.S. Sieves
Passing Batch Passing Batch Passing Batch Passing Batch
2" 100.0 40.0 100 0 100 35 100 15 100 10 100 100 100
1 1/2" 92.7 37.1 100 0 100 35 100 15 100 10 97.1 ---------- ----------
1" 42.8 17.1 100 0 100 35 100 15 100 10 77.1 68.1 85.0 55
3/4" 8.5 3.4 100 0 100 35 100 15 100 10 63.4 54.4 72.4 50
1/2"
3/8"
No. 4 0.4 0.2 49.6 0.0 49.6 17.4 99.4 15 100.0 10 42.4 34.4 50.4 30
No. 10
No. 40 0.3 0.1 13.0 0.0 13.0 4.6 34.8 5.2 79.2 7.9 17.8 11.8 23.8 10
No. 80
No. 200 0.2 0.1 3.9 0.0 3.9 1.4 19.3 2.9 4.7 0.5 4.8 3.0 8.8 3.0

General Remarks:-

Tested By Checked By:


Date: Date:
M.E CONTRACTOR MATERIAL INSPECTOR M.E CONSULTANT

TOTAL 10000

3/4 3/8 C.S 11/2 1


% 12 7 55 Err:522 16 10

WT. 1200 700 5500 Err:522 1600 1000


Specification
Limits

100
----------
85
80

60

25

10.0
M.E CONSULTANT