Project in Glance
• Integrated Slope Maintenance Systems (ISMAS) was developed
for Jabatan Kerja Raya (Semenanjung) under project
“Penyelenggaraan Cerun di Jalan Persekutuan Semenanjung
Malaysia melalui kontrak Jangkamasa Panjang mulai tahun 2017”.
Its begins in May, 2019 and should be completed in 31st October
2020.
• ISMAS objective is to become a single web based platform that
could be used to manage, update and analyse all the slope related
information in one single web application. Basically, it is used to
prioritize slope preventive maintenance works based on risk rating.
• It offers the users a single window interaction
through web browser where users can create,
update and monitor all slope maintenance activity.
2
Why maintenance?
3
Who are the users ?
1. Administrator – Able to access all of the pages in the system except maintenance page
2. JKR Bahagian Keselamatan Cerun – Able to view all of the change of data from JKR Negeri,
JKR Daerah and Contraktor in Proforma Page and Maintenance Page. Dashboard and Map
page are also viewable
3. JKR BPPBC, CKC – Able to view all of the change of data from JKR Negeri, JKR Daerah and
Contraktor in Proforma Page and Maintenance Page. Dashboard and Map page are also
viewable
4. JKR Negeri – Able to view data in Proforma page based on state that have been assigned.
Dashboard and Map page are also viewable
5. JKR Daerah – Able to view and edit some data in Proforma and maintenance page based on
district that have been assigned. Dashboard and map page are also viewable
6. Slope Maintenance Provider – Able to view and edit some data in Proforma and
maintenance page based on state that have been assigned. Dashboard and map page are
also viewable
4
Support Information
1.Maps Information
• Slope polygons
• Proformas
• Roads lines
• Buildings footprints
• KM Posts
• Orthophotos
• Fly through video
5
Project
ISMAS Modification
Project
Plan
Initiation
Project
Requirements
(20 June 2019) Modification
plan Implementation
Modification
Requirements Study
Approved
Stage
(15 July 2019)
Requirements
Installation,
Data 2 – Provider 2 Data 3 – Provider 3 Testing and
CURRENT STAGE
1.Soil Slope polygon Rock Slope polygon Training USERS
with hazard and risk with hazard (Nos?) UAT : 2 & 3 July 2020
rating (Nos?) FAT : 26 August 2020 Modified ISMAS
handing over Modified
2. ISMAS system T1 : TBA
ISMAS
T2 : TBA
Deployment
T3 : TBA
Corrective Maintenance
6
ISMAS System Infrastructure
Tile Cache for USER (Jurutera Daerah, Kontraktor, INTERNET
map viewer JKR Negeri, BKC, BPPBC) https://ismas.jkr.gov.my
Web, Mobile & Desktop
ISMAS Server
(previously used for ISIS system)
SAN Storage
Managing Raster (LiDAR, Orthophoto,
Database Raster Data, Map
Desktop Cache, Backup Data)
(QGIS Desktop)
7
ISMAS System Architecture
Responsive Web App
Slope Database
8
ISMAS Main Modules
ISMAS
Authentication / Authorization
Slope General
Generate/ Map Layer Routine User
Maintenance Management Dashboard
Update
Slope Primary Map navigation Inspection
Hazard Map tools Lookup Table
Engineer Reports
Slope Structure Management
Map query Inspection
tools
Slope Incident Risk Map Audit Trail
Routine
Searching Maintenance
Slope Geology Work
Slope identify Budget
Query
Slope Instrument tools
Incidents
Slope Valley
Works Order Legend
Available through ISMAS
Web web application
9 Desktop
Available through QGIS
desktop application
10
ISMAS Module - Dashboard
Number of Slope by Slope Hazard & Risk and by State Number of very high and high hazard slope by State
13
ISMAS Module – Maintenance
Maintenenance
Submodule
14
ISMAS Module – Maintenance
Maintenenance
Submodule
15
DEMO
https://ismas.jkr.gov.my
16
THANK YOU