Detailed Request

Requisitioning Department
Manager Fiber Ops-I LTR S Lahore
Works
Re-routing of Cable at MCB House
Title:
Budget
Line Item PR # Location
Code
MCB House

Store Required

Code
50006117
47003868
47003883
Detailed Request

of Cable at MCB House

Services/ Material Rate

Excavation of Trench along with Backfilling & proper (4 FEET) Compaction 320
Bore for 4" dia HDPE (1 Way) 525
Hauling / Pulling of O.F Cable through PTCL Duct / HDPE Pipe / G.I Pipe / PVC Pipe 30
Jointing / Splicing of O.F Cable 12F 300
Laying of HDPE / PVC / G.I Pipe in new trenches / bore / road cut ( 1 WAY) 12
Pits for Tracing on all type of soil HH/MH 1100
Transportation of O.F Cable, PVC Pipe, Joints, ODFs & Poles from PTCL Regional store to 8500
site

Store Required

Name of Item Unit


HDPE Pipe 57mm (Recycled) WT 3.5mm M
OFC Joint Enclosure - 12 Fiber EA
OFC Duct Type 12F M
Deliver To: G.M NOD LHR

Unit Of Estimated
Quantity
Measure Total Cost

50 M 16,000
15 M 7,875
400 M 12,000
12 Per Fiber 3,600
50 M 600
2 Each 2,200
1 Per Trip 8,500
Total 50,775

Rate Quantity Amount


103 50 5,150
4706 2 9,412
145 400 58,000
Total 72,562