RETILING WORKS AT THE 4th FLOOR OFFICE (RUBY OFFICE)

PROPOSED WORK SCHEDULE

Mobilization on Saturday, February 18, 2023

PHASE 1: Room 1,2 and 4


*Note: Start with Room 2 and 4 then proceed to Room 1 once the area is cleared and is workable. Schedule will depend
on workability of given areas.

Saturday & Sunday (February 18-19, 2023; 8AM-5PM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area

Monday-Friday (February 20-24, 2023; 7PM-5AM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area

PHASE 2: Entrance and Common Area

Saturday & Sunday (February 25-26, 2023; 8AM-5PM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area

Monday-Friday (February 27-March 3, 2023; 7PM-5AM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area

PHASE 3: Room 3,5,6 and 8

Saturday & Sunday (March 4-5, 2023; 8AM-5PM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area

Monday-Friday (March 6-10, 2023; 7PM-5AM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area

PHASE 4: Room 7,9,10 and 11

Saturday & Sunday (March 11-12, 2023; 8AM-5PM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area

Monday & Tuesday (March 13-14, 2023; 7PM-5AM)

- Installation of SPC flooring


- Installation of baseboard
- Clearing and cleaning of the area
- Hauling out of debris

Demobilize on Tuesday March 14, 2023