GROUP 4 GROUP 4 GROUP 4 GROUP 4

COLUMN
ESTIMATION
(CIVIL WORKS, CONCRETE WORKS, AND REBAR
WORKS TECHNOLOGY)
MAIN BARS
Length of Main Bars (L) =
Height - 75mm - 2db - 40mm + H1 + H2 + Elongation or Extension
WHERE:
Height = 5.9m
db = 16 mm or 0.016m
H1 = Hook #1 (UNKNOWN)
H2 = Hook#2 (UNKNOWN)
Concrete Cover = 40mm & 75mm / 0.040m & 0.075m
Elongation/Extension = 12 db
MAIN BARS
SOLVING FOR HOOK 1 SOLVING FOR HOOK 2
Ø of main bars is 16 mm H2 = 0.25 - 0.04 (2) - 0.01 (2)
H1 = 6db 2
= 6 (0.016m)
H2 = 0.075m
H1 = 0.096m

LENGTH OF MAIN BARS (L):


5.9m-0.075m-2(0.016)-0.04+0.096m+0.075+12(0.016)
L = 6.116m or 6m
MAIN BARS
MAIN BARS
CUTTING LIST FOR MAIN BARS
Example:
4 pieces of main bars in a column.
Having 4 main bars, each has a length of 6.0m
So, 6.2x4 = 24.0m, TOTAL LENGTH
Available length of rebars are 6m or 7.5m, so 6m
will be use because each main bars has also 6m.
Therefore, the number of main bars needed in a
column = 4 pieces @ 16mm Ø x 6m
LATERAL TIES
Length of Lateral Ties (L) =
24 + 2B + Hook (2) - 3 (db) - 2(6db)
WHERE:
A = 250-40mm(2) B = 250mm - 40mm(2)
A = 170mm / 0.17m B = 170mm / 0.17m

db = 10mmØ
Hook: 6db / 60mm