Solan Development project

OVERVIEW

LOCATION PLAN

> West of Shetland, UKCS Block 205/26a > Oil stored over ballast water in
> 135m water depth steel subsea tank – 300,000bbl capacity
> 4 well base case development > Offloaded by shuttle tankers
(2 producers and 2 injectors) > Not-permanently-manned operation,
> P50 reserves of 44mmbo following initial
> Topsides supported on conventional > 12 months manned
steel lattice jacket > Zero overboard discharge of any
> Design throughput of 28,000bopd oil contaminated water
> Maximum 3mmscfd gas, used > First Oil Q3 2014
for fuel or flared > 25 to 30 year field life

www.premier-oil.com

PremierOil_Portrait_HSE_(A3).indd 2 25/07/2012 14:39:46


Solan Development project

DRILLING

> Four well development – two production wells /


two water injection wells

> Subsea Trees / wells will be remotely controlled


from onshore via the Production platform

> Complex well trajectories with 5000ft – 6000ft horizontal sections through the
Solan reservoir sand

> The weak reservoir formation sands require wire wrap screens to provide sand control

> Dual electrical submersible pumps will be installed to boost production rates
to circa 15,000bfpd / well

www.premier-oil.com

PremierOil_Portrait_HSE_(A3).indd 3 25/07/2012 14:39:49


Solan Development project

SUBSEA

> Minimalised subsea architecture with ~ > Oil to DP tanker via offloading system
4.5km of flow lines and pipeline with
1.8km of umbilical > Tank displacement and oil export via 24”
carbon steel concrete weight coated
> Production and water injection wells tied s-lay pipeline
into individual risers
> Oil to tank and ballast return via 10”
> Combination of Vetco and FMC trees and 12” flexible pipelines
using an integrated Vetco control system
> Subsea infrastructure protected by
> Two production wells supplied by concrete link block mattresses
individual umbilicals with two WI wells
daisy chained via control jumpers

www.premier-oil.com

PremierOil_Portrait_HSE_(A3).indd 4 25/07/2012 14:39:52


Solan Development project

TOPSIDES

> Topsides Nett Lift Weight 4019 te > Topsides Gross Operating Weight 6589 te
> Topsides Gross Lift Weight 4547 te > Topsides Footprint 46m L x 25m W x 30m H
> Topsides Nett Operating Weight 6028 te
(includes future 1013 te)

www.premier-oil.com

PremierOil_Portrait_HSE_(A3).indd 5 25/07/2012 14:39:54


Solan Development project

JACKET
> Four legged steel construction
with four pile sleeves per leg

> Jacket Design by Mustang


Engineering

> Foundation Design by Fugro


on behalf of Mustang

> Nominal water depth at jacket


location – 136.5 metres

> Top of jacket plan dimensions,


20 metres x 20 metres

> Jacket mudline footprint,


45 metres x 45 metres

> Jacket target weight in region


of 7,500t, to be finalised in
conjunction with ongoing heavy
lift design

www.premier-oil.com

PremierOil_Portrait_HSE_(A3).indd 6 25/07/2012 14:39:57


Solan Development project

TANK

> Steel construction with Eight 96 “pile > Dropped object protection frame to
sleeves and mud mats East and West protect Valves and piping
Sides
> Tank target weight in region of 8000t
> Tank Design by Atkins Engineering
> Key design requirements, codes and
> Nominal water depth at Tank location – standards
136.5 metres > To meet the requirements of the IVB
> Tank dimensions, 45 metres x 45 metres
x 25 metres

www.premier-oil.com

PremierOil_Portrait_HSE_(A3).indd 7 25/07/2012 14:40:02