Daily Operations Log


Doc: TSI-OPS-F-010 Rev. 00 Effective Date: 4 Jan 2021

Client BP Berau Ltd Start Date 29 Aug 2023 Project No.


Projec
Leak Test Service Regular Location Tangguh LNG
t
Date Time Log
29 Aug 2023 05:30 Bambang Yan went to New MCB for Meeting with client
06:00 Gunawan & Tarjo preparation container will be sent to Jakarta
07:00 Tarjo went to Instrument Workshop to calibrate PSV
09:30 Went to Train 1 utility taking picture for TAR N2 Spread
11:00 Emergent call from NUI regarding Leak Test job planning for 31st Aug 2023
11:30 Lunch break
13:30 Back to Admin Office
14:00 Tarjo Wartono & Gunawan went to Shore Base prepare Instrument & Tools for WDA
offshore job
15:00 Tarjo cease Gas Booster need to be use for WDA Leak Test on 31st of Aug 2023
16:30 Crew back to Steenkool
17:00 Back to Admin office
17:30 Paper work
18:00 End of shift
19:00 Tarjo contact Agustinus – Workshop Coordinator

OPTIONS ON Customer Acceptance TSI Supervisor/Engineer


SIGNATURES

A FULL signature is required Name: Company: Name:


only on the last page.
Gunawan Wibisono
The remaining pages MUST be
initialed by the client & TSI Signature: Signature:

Date: Date: 29 Jul 2023

Page 1 of 1