CI-PR3-LP-F11-Rev00
Daily liner installation report
Local Workers CITILOG National Workers CITLOG Expatriate Workers ESSAKANE EQUIPMENT
ESSAKANE SITE ESSAKANE SITE ESSAKANE SITE ESSAKANE SITE
Number of workers 14 Number of workers 1 Number of workers 3 Manitou 1
Hours worked per day 9 Hours worked per day 9 Hours worked per day 9 Vehicles 1
Total sum of hours worked 126 Total sum of hours worked 9 Total sum of hours worked 27 Generators 4
06:00 We arrive at TSF Essakane, after a safety briefing, our activities will focus on APT, repairs and vacuum testing to complete
the installation process of textured HDPE 1.5 geomembrane in this project.
06:40 Tensiometer samples show perfect calibration of the PX 06 extruder, so we will continue with the repairs (patches).
7:10 The PX 06 extruder is in optimal conditions to be used, this is deduced by values of samples made in a tensiometer that have
been totally satisfactory.
08:25 We have vacuum tested the repairs to ensure the correct application of the extrusion. The results have been satisfactory in
each of them.
13:30 after lunch, repairs by extrusion continue. The PX 06 extruder is in optimal conditions to be used, this is deduced by the
values of samples carried out in a tensiometer that have been totally satisfactory.
vacuum tests are continued to ensure the correct application of the extrusion. The results have been satisfactory in each of them.
Citlog supervisor Ulises Lázaro, assisted by personnel from the Essakane mine, continues today with repairs at the BWS
This morning the Geocrest quality supervisor tells me that there is a fault in the air pressure gauges, the needles need to be changed.
Photographic report
Date and place Date and place Date and place Date and place