Professional Documents
Culture Documents
SUMMARY OF DISCUSSIONS
TOPICS DISCUSSIONS RECOMMENDATIONS/
REMARKS
Overall Accomplishment
.
Target: 12.69%
Actual: 25.91%
Slippage: (+)13.22%
Bldg 1
Target: 24.18%
Actual: 39.97%
Slippage: (+)15.79%
Bldg 2
Target: 9.33%
Actual: 33.10%
Slippage: (+)23.77%
Bldg 3
Target: 0.00%
Actual: 4.67%
Slippage: (+)4.67%
Building 1
Ground Floor
1. Reconducting of compaction
for Field Density Test.
Second Floor
1. Installation of roughing-ins of
waterline.
2. Installation of sewerline.
Third Floor
1. Plastering of interior walls.
2. Installation of C-Purlins and
sagrod.
3. Installation of ceiling framings.
Building 2
1. Installation of reinforcement of
stairs.
2. Installation of roughing-ins for
electrical and auxiliary.
3. Installation of reinforcement of
third floor slab.
Building 3
Prepared by: