You are on page 1of 10

SPE/IADC 107305

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


Successful Application of Underbalanced Coiled-Tubing Drilling in Horizontal
Short-Radius Re-Entry Well To Enhance Oil Production in Hassi Messaoud Field, Algeria
Bachir Ben Amor, Ali Ferhat, and Rafik Messas, Sonatrach, and Maurizio Arnone, Michael Stulberg, Rashid Khan, Fritz
Schoch, Charles Fordyce, Hani Qutob, and James Chopty, Weatherford International

Copyright 2007, SPE/IADC Middle East Drilling Technology Conference & Exhibition
re-entry wells drilled with coiled tubing are highly reduced
This paper was prepared for presentation at the SPE/IADC Middle East Drilling Technology due to the elimination of pipe connection procedures, the
Conference & Exhibition held in Cairo, Egypt, 22–24 October 2007.
increase in rate of penetration, the prevention of conventional
This paper was selected for presentation by an SPE/IADC Program Committee following
review of information contained in an abstract submitted by the author(s). Contents of the
drilling problems such as fluid circulation loses and related
paper, as presented, have not been reviewed by the Society of Petroleum Engineers or differential sticking events, the increase in the bit life and
International Association of Drilling Contractors and are subject to correction by the author(s).
The material, as presented, does not necessarily reflect any position of the SPE, IADC, their reduction in time and drilled distance to reach the profitable
officers, or members. Electronic reproduction, distribution, or storage of any part of this paper
for commercial purposes without the written consent of the Society of Petroleum Engineers
production level.
and International Association of Drilling Contractors is prohibited. Permission to reproduce in
print is restricted to an abstract of not more than 300 words; illustrations may not be copied.
The abstract must contain conspicuous acknowledgment of where and by whom the paper This paper describes the technical basis for the design and
was presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836 U.S.A.,
fax 1.972.952.9435.
implementation of the Coiled Tubing Underbalanced Drilling
project in Hassi Messaoud and highlights the operational key
Abstract factors and challenges faced during this particular and
successful application in Algeria.
Drilling in the Cambrian Reservoir, in the peripheral zone of
Hassi Messaoud field, specifically the 1A, 1B and 1C zones Introduction
(Figure 1) is a real challenge, basically due the petrophysical
reservoir complexity, the low reservoir pressure, the extremely The Hassi Messaoud field (Figure 2), discovered in 1956, is
hard and abrasive sandstone and quartzite formation the largest oil field in Algeria, covering about 2000 Km2 and
associated with numerous vertical and sub vertical fractures currently including over 1000 Wells. The field is divided
that connect the reservoir with deeper formations leading to aerially into 25 zones that are separated from each other by
major problems related with the salt saturated water low permeability barriers, usually faults. The Cambrian
production. Many of the vertical wells drilled in that zones Reservoir is subdivided into four lithological zones designated
have more than 30 years from completed and a large from base to top as R3, R2, Ra and Ri. The Ra sub reservoir
proportion of them have been shut in since being drilled. shows the best petrophysical properties with a maximum
thickness of 150 m in the western part of the field. The Ra is
Well E was the 5th re-entry well in the Sonatrach Coiled farther subdivided into five sub zones: D1, ID, D2, D3, and
Tubing – Underbalanced Drilling campaign. A total of 372 m D4 based on reservoir properties and depositional conditions.
from KOP and 316 m from landing point were successfully
drilled in a continuous underbalanced condition inside D1 This is the first of its kind Coiled Tubing - Underbalanced
formation. As a result, the well productivity while drilling, the Drilling project undertaken in Hassi Messaoud field. The
Reservoir characterization and rate of penetration was candidates wells are from a pool of vertical shut in wells
significantly improved, compared with offset wells, due to the drilled in the western area of the field and have seized to
positive impacts of UBD operations. produce with varying completion string and production casing.
The increase in number of candidates for thru tubing re-entries
The combination of Underbalanced and Coiled Tubing added to the depletion of the reservoir have raised the
Drilling technologies has been proven to be a viable solution importance of use the combined technologies Coiled Tubing -
to successfully drill horizontal re-entry wells in mature fields Underbalanced drilling in Hassi Messaoud field. The original
where the reservoir pressure is adequate to induce reservoir pressure was 6860 psi and the average permeability
underbalanced conditions using single phase or multiphase ranges from 0.5 to 1.0 mD but can reach up to 1000 mD in
drilling fluid. cases where open fractures are encountered. Production is
43.7 – 45 º API oil with original average GOR of about 200
The experience in this field has validated the benefits of the m3/m3 and a formation temperature of approximately 120 ºC.
combination of these technologies and has been attributed to Until 1964, the production mechanism was only depletion
the excellent balance between drilling cost and improved above bubble point. Gas injection and water injection started
productivity. For example, the drilling cost in the short radius after that year to improve the production.
2 SPE/IADC 107305

Original Well E was drilled in September 1977 and completed 2- Petro-physical criteria:
with 5” slotted liner in open hole and 4 ½” production tubing. • Evaluation of formation lithology
The first well DST results was 12.35 m3/hr at WHP of 1750 • Evaluation of petro-physical properties
psi and the reservoir pressure was 5775 psi. The well was put
in production until May 1979 and shut in for rapid production 3- Reservoir criteria
decline due to tubing collapse caused by 7” casing corrosion • 2130 psi (3.68 ppg EMW) of Reservoir pressure was
and high pressure water invasion. The total oil produced was

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


set as minimum
52811 m3. In April 2006 the well was re-completed with 4 ½” • Gas/water breakthrough in well and offset wells
cemented casing to surface with shoe at 3424m and • Performances of fractured, horizontal and short
programmed for horizontal thru tubing re-entry in the D1 with radius existing offset wells
target 3426m-3431m. • Well test interpretation.
Well E is just one of the successful Coiled tubing –
Geological / Reservoir Characteristic
Underbalanced drilling re-entry well drilled in Hassi
Messaoud field during year 2006. The Initial estimated
Geologically the zone of interest for side track and drilling
formation pressure was sufficiently high (4544 psi) to induce
lateral is Cambrian sandstone of Ra. These sandstones are
underbalanced conditions with native crude (45ºAPI, 0.80
highly heterogeneous in nature. Among the pilling of these
S.G.) without the necessary injection of any gas phase. For
structures shale breaks are encountered, the thickness of which
those Underbalanced Drilling operations that involve a straight
is 1 to 5 m and lateral extension of 30 m approx.
liquid fluid the term reserved is “flowdrilling”. The real
formation pressure calculated while drilling resulted in
Ra formation has an average depth of 3400 m, covered with
approximately 3700 psi being necessary to inject a multiphase
production liner. Ra is characterized by largely variable petro-
drilling fluid to reach the underbalanced condition (13%
physical properties (Porosity, Permeability and Shaliness)
drawdown).
impacting productivity. Ra is further divided into five drains
that vary in productivity and are classified based on
Project Objective percentage of permeable sandstone present versus
discontinuous shale lenses relative to overall package. The
The main objective of this project is to recover and enhance target sandstone is extremely hard and abrasive, resulting in
the oil production from existing shut in vertical wells drilling continuous MWD failures due to bottom hole vibrations and
horizontal thru tubing re-entries, having better and real time very poor bit performance.
assessment of the producing zone in the reservoir while
drilling and test flowing the reservoir using the advantages of The reservoir is under pressured, resulting in losses when the
the Underbalanced Drilling technology. Due to the proximity first fractures are encountered, damaging formation. The mud
of the 7” casing shoe to target vertical depth and related loss also runs the risk of opening up fractures leading to
aggressive built up rate during drilling the curve section, the premature water break through. To limit the formation
small production casing/tubing available size, the extremely damage, and improve the drilling performance, UBD was
hard and abrasive formation and inherent formation damage made an integrated part of the project.
obtained using conventional drilling techniques, it was
planned to combine Coiled Tubing Drilling with the
Drilling Plan
Underbalanced Drilling technologies to perform the
operations.
The drilling plan can be divided into 3 basic steps:
To achieve the objective of the project, it is planned to exit
1. Exit casing using whipstock: Wells are completed
thru production tubing and drill in underbalanced conditions, a
with three different types of completion string:
single horizontal side track open hole using coil tube in
Cambrian Reservoir, predominantly in Ra. Hole lenght target
a. Casing exit through 4 ½” cemented liner: for casing
to be drilled is approximately 400 m depending on the
exit through 4 ½” cemented liner, a packer type
geological complexity.
whipstock is anchored in the well bore through the use
of a permanent style big bore packer. A survey tool is
Well Selection Criteria run down hole to determine the exact orientation of the
packer. An orienting latch assembly is made up to the
Wells are selected based on following three criteria: bottom of the concave and adjusted to the direction
required from the information provided from the
1- Mechanical criteria: wireline survey. The whipstock and starting mill
• 35 m was set as requirement for re-entry from Top of assembly can now be run in the hole and latched into a
Cambrian/KOP to top of target. Max BUR of 55º/30 matching profile inside the casing packer. Once the
m (58º/30 m was obtained in this well).. assembly is latched into the packer, the whipstock face
• Completion suitable for available whipstock size will be oriented to the desired direction automatically.
• Well – reservoir configuration.
SPE/IADC 107305 3

b. Casing exit through 4 ½” slotted, un-cemented liner: 2. Controlled Pressure Services


in this type of casing exit, liner is first squeeze The Controlled Pressure Drilling Services includes
cemented to have cement behind the liner. The cement provision of equipments for pressure control, nitrogen
is drilled out and an anchor is run with whipstock, generation, separation, storage and cleaning of the fluid.
motor and gyro tool on coil to orient the whipstock The flow parameters are measured and analyzed using
concave in desired direction prior to setting. computer based flow model.
c. Casing exit through 5” slotted, un-cemented liner: 3. Casing Exit Services

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


for these wells, an anchoring assembly is run in and set It includes provision of anchor packer, whipstock and
with cement prior to wire line survey. Whipstock is run mills required for casing exit.
conventionally on coil. 4. Directional Drilling Services
Includes provision of mud motors and directional
Milling of window is done in single run using diamond speed drilling services.
mill and water melon string mill. 5. MWD Tools and Services
Includes provision of MWD tools and spares. The tools
Original Well E is adjusted to case “a”, casing exit through are maintained in field by the MWD crew.
4 ½” cemented liner set at 3424 m TVD. Original well and 6. Bits
final sidetrack configuration is depicted on Figure 3. The project has tried bits from 3 different
manufacturers. The bits are selected depending upon
2. Controlled Pressure Drilling BUR and land as per the area to be drilled and performance.
the targets provided by operator:
The build section is kicked off with steering gyro and Drilling Fluid Selection
3 ¾” monocone / tri-cone bit on low RPM – High
Torque motor. The AKO angle of the motor is adjusted All the candidates selected for this project are planed to be
as per requirement. The build section is planned to be drilled with native crude oil. This drilling fluid was chosen
drilled with 2 monocone bits. Under-balance condition over diesel or other fluid because it is the natural reservoir
can be induced by single phase of multi phase fluid. fluid. It would minimize chances of formation damage in the
Formation in certain areas of Hassi Messaoud has event of pressure transient and/or from fluid imbibitions. The
unconsolidated shale sections. To avoid hole problems, native crude oil is readily available and is supplied by the
underbalanced condition is avoided during of BUR. The Sonatrach production facilities in the Hassi Messaoud field.
MWD tool is 4.5m away from the bit. As the real reservoir pressure observed while drilling was less
than the expected, the injection of single phase drilling fluid
3. Controlled Pressure Drilling of single was not a viable option. Nitrogen generated in situ was
horizontal/slanted drain to TD specified by combined with the native crude oil in order to achieve the
operator: underbalanced condition.
The lateral is drilled using 3 ¾” impregnated bit and
high speed motor with thruster added in the BHA. Flow Modeling
Thruster pushes MWD tools by 1m away from the bit,
resulting in survey readings with a lag time of 5.5 m Operating Envelope – Bottom Hole Circulating Pressure
drilling. This is acceptable in drilling lateral as the Underbalanced conditions simulations are perform in the
unwanted change in hole inclination and azimuth are planning as well as during the drilling phase of the project to
not expected. achieve the following objectives:

Equipments and Services • Maintaining underbalanced conditions at all times


while drilling the reservoir
1. Coiled Tubing Drilling Rig • Achieving good hole cleaning in the horizontal and
The drilling rig is fit for purpose, newly designed coiled vertical hole sections.
tubing drilling rig with 2 3/8” coil having capillary and • Maintaining Equivalent Liquid Volume (liquid + gas)
e-line inside. The capacity of the rig is of 200 Tons, flow inside the optimum operating values for down
equipped with two numbers of hydraulic injectors with hole motors and to obtain the minimum directional
100 Tons of continous lifting capacity, CAT engines drilling parameters to reach the reservoir targets.
and SCR, providing electric supply to most of the
equipment, two number triplex mud pump. The coil The Flowdrilling Hydraulic planning phase examined the
control cabin is fully automated with hydraulic controls effect of different surface choke pressure on the
for injector and coil drum. It has coil life monitoring underbalanced bottom hole conditions using different native
capabilities and integrated display system for the crude oil injection rates. This type of hydraulic simulation is
display of critical well parameters. All the major loads realized at total depth planned (worst case scenario)
are trailerized for fast moving in desert condition. The considering the effect on the bottom hole circulating pressure
lease area required is similar to that of any conventional induced by a variety of wellhead pressures and different native
rig of similar capacity and tower can be rigged up on crude oil injection rates in cases for no production events
existing cellar.
4 SPE/IADC 107305

(Figure 4). Production case was also evaluated, assuming • Bottom Hole Circulating Pressure (BHCP)
expected average values for oil production, 4 m3/hr, and Gas
production, 10000 m3/day (Figure 5). These plots are The nitrified drilling fluid reduced the bottom hole
normally referred to as the operating envelope. Various circulating pressure from 3900 psi obtained on the first
constraints that must be fulfilled during the underbalanced leg to 3200 psi in average. Hydraulic simulations were
drilling operations were plotted on this operating envelope. performed on location during the complete UBD
These constraints include: a minimum and maximum operation (flow drilling and Multiphase sections). The

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


drawdown at the bit level to ensure adequate underbalanced difference between the calculated and real pressure data
conditions in the well and at the same time minimizing any obtained from the Pressure While Drilling (PWD) tool
near wellbore depletion effect; minimum annular fluid was within the expected tolerance of 5%. In Figure 7 is
velocity in the vertical and horizontal section of the well; and represented the real and simulated BHCP.
the maximum down hole positive displacement motor flow
rate limitation. • Production while drilling

From the initial simulations, the optimum liquid rate and The complete second leg was drilled underbalanced
wellhead pressure in no production scenario were selected to using the D1 crude oil and nitrogen as the gasified
be 350 l/min – 50 psi (10% drawdown), and for Oil / Gas drilling fluid. The multiphase flow operation started at
production scenario in 370 l/min – 200 psi (10% drawdown). 3482.5 m MD and the first traces of oil and gas
production were observed at 3520 m MD, 70 m after the
Hole cleaning simulations landing point. A higher oil production rate was obtained
In horizontal wells, hole cleaning is an important issue. Thus, at 3600 m MD and the well produced 7 m3/hr of oil
in a low viscosity scenario, liquid velocity is the critical steadily for the rest of the drilling operation. During the
parameter that controls a circulation system’s ability to UBD operation in second leg, a total of 806.83 m3 (5076
transport solids. The criteria used is based on the annular fluid bbl) or crude were produced. Figure 8 shows the oil
velocity that for operational experience is set in 55 m/min for production behavior while drilling.
annular liquid velocity in the vertical portion of the well and
65 m/min in the horizontal section. Hole cleaning could also • Rate of penetration (ROP) and hole cleaning
be a concern, upon the degree of washout encountered. The
use of appropriate hole cleaning practices such as wiper trips In average, the rate of penetration for Well E was 2.5
and viscous sweeps minimizes the risk of having severe hole m/hr. The first 212 m including cement, built and
cleaning problems. Figure 6 depicts the velocity profile horizontal section were drilled with an average ROP of
obtained using specialized hydraulic simulators. 2.1 m/hr. The following 167 m of horizontal section was
drilled with an average ROP of 2.8 m/hr. In Figure 9 is
The design parameters used for UBD modeling can be represented the ROP behavior versus depth.
summarized as follow:
• Drilling fluid: native crude oil (0.80 S.G.). No drilling problems due to bottom hole cuttings
• Injection rates: 100 – 450 l/min. accumulation was reported in the UBD operation.
• Wellhead pressure variation: 0 – 400 psi. During most of the operation, the liquid velocity in the
• Reservoir pressure: 4544 psi. annular space varied between 100 – 110 m/min and 95 –
• Minimum drawdown: 10%. 105 m/min for the horizontal and vertical hole intervals
• Maximum drawdown: 20%. respectively. No hole cleaning issues were foreseen and
• Maximum motor equivalent flow rate: 450 l/min. experienced.
• Minimum annular liquid velocity in horizontal
section: 55 m/min. • Productivity index while drilling (PIWD)
• Minimum annular liquid velocity in vertical section:
65 m/min. The purpose of calculating productivity index while
• Coiled tubing and BHA dimension: 2 3/8” x 3 1/8”. drilling (PIWD) is to quantify the reservoir deliverability
during the drilling phase. During UBD, the reservoir will
flow at various rates depending on the amount of
Results obtained
drawdown and the reservoir characteristics. If there is
limited effective hydrocarbon in the reservoir from
A total of two legs were drilled. The first leg was of 54 m
compartmentalized formations, then the reservoir’s static
open hole length and drilled with a single phase fluid,
bottom hole pressure may change over the period of the
continuous circulation losses were experienced. This leg was
drilling of the well and will affect the PIWD plot of the
plugged back with cement and a second leg was sidetracked.
well.
Due to the lower reservoir pressure encountered, the sidetrack
Hydrocarbon production was first recorded at 3520 m
was drilled with a multiphase drilling fluid system (Nitrogen
MD (70 m after the landing point). From this depth, the
plus Crude Oil). The nitrified drilling fluid reduced the
productivity index was relatively constant at an average
bottom hole circulating pressure from 3900 psi obtained on the
value of 0.008 m3/day/psi. However, at 3600 m MD, 185
first leg to 3200 psi in average.
SPE/IADC 107305 5

m away from the original vertical well, the PIWD started Conclusions
to increase gradually up to 0.14 m3/day/psi at the total
depth of 3766 m MD. Figure 10 shows the PIWD • Coiled Tubing and Underbalanced Drilling
behavior. technologies have obtained successful results applied
together in this well. Rate of penetration was
• Flow Test improved (comparing the 2.5 m/hr obtained in UBD

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


with 1 m/hr during the overbalanced periods in the
At total depth (3766 m MD), a 99 hours flow test was first leg) and from the production point of view, this
conducted with a ½” choke diameter. During this period, re-entry well is considered as a good producer in
the well produced 1179.85 m3 (7421 bbl) of crude oil with Hassi Messaoud field.
a rate of 11.65 m3/hr. Figure 11 depicts the wellhead and
production values behavior versus time seen during the • Proper planning and design phases are demonstrating
flow test. the success obtained during field application.

Performance review – issues and solutions • UBD operations were maintained during the
complete production section drilling in second leg,
• Bit – motor incompatibility during curve section using the same D1 crude oil (0.8 S.G.) and Nitrogen
drilling: as multiphase fluid system (nitrified fluid). A total
High RPM motors were incompatible with tri-cone bits production section length of 316 m (from landing
and resulted in premature bit failure. The use of 3 1/8” point) was drilled.
low RPM - high torque motor address the issue
• No bottom hole cuttings accumulation events was
• Excessive vibrations: obtained during the UBD operation.
Excessive vibrations coming from motor was identified as
the cause behind MWD failure and loss of cutting • It was possible to drill short radius with the required
structure of impregnated bit causing premature gauge build rates (58º/30m as in this well) using coiled
failure and resulted poor life. Weight transferred to bit in tubing, drilling 372 m of 3 ¾” production hole
horizontal drain sections, as the bit drill off formation was section.
second major contributor to damaging vibrations. The
use of large motor diameter (3 1/8” OD compared to 2 • After start this project in Hassi Messaoud field, the
7/8” OD) to make BHA assembly stiffer thereby reducing combination of Underbalanced and Coiled Tubing
vibrations. After introduced “Thruster” in the BHA, Drilling technologies has been proven to be a viable
string vibrations were appreciably reduced, improving bit solution to successfully drill horizontal re-entry wells
life. Thruster is a down hole tool that provides Pump where the reservoir pressure is adequate to induce
Open Force (POF) to apply hydraulic Weight On Bit underbalanced conditions using a single phase
(WOB) during drilling operations. Thruster also absorbs drilling fluid and where the reservoir pressure is
weight transfer from the drill string and keeps the positive extremely low, requiring the use of gasified fluids.
displacement motor from stalling out. It is also improved
the impregnated bit life making possible to drill 150 m of
Acknowledgments
horizontal drain with single bit.
The authors wish to extend their appreciation to the
• MWD failure: management of Sonatrach in Algeria and to Weatherford
A new design, more robust MWD tools with better tool International Ltd. for the permission to publish this paper. The
stabilization and robust electronics were tried, improving authors also thank the many individuals within Sonatrach and
MWD performance. Weatherford who have contributed to the success of this work.
• Bit performance: References
Tried 3 ¾” monocone bit with dramatic improvement in
1. Moore, D., Bencheikh, A., and Chopty, J. (2004):
bit life. The gauge retention is very robust and none of
“Drilling Underbalanced in Hassi Messaoud”, SPE/IADC
the bit had bearing failure. The bit gave desired build 91519.
rates and excellent direction control. The combination of
2. Durst, D., Hart, S., Brown, W., (2001): “Drilling,
3 1/8” low RPM motor and monocone bit reduced the
Completion, Isolation and Thru Tubing Re-entry of
vibration and associated MWD failures. Multilaterals in Hard Open Hole Formations”, OTC
13285.
3. IADC Underbalanced and Managed Pressure Drilling
Operations Committee “IADC Fluid selection for
Underbalanced Operations”, adopted by the IADC boards
of directors August 2005.
6 SPE/IADC 107305

150000

9
4

8 Algiers
140000

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


1C 10
3 12
11
1A 6 13 Hassi Messaoud
130000

20B 15
2

23 2X 20A
19 17 16 14
ALGERIA
1B
120000
24

25

110000
790000 800000 810000 820000 830000 840000

Figure 1: Hassi Messaoud field, producing zones


Figure 2: Hassi Messaoud field location

Coiled tubing
OD 2 3/8 in
ID 2.026 in

BHA
OD 2 7/8 in
Motor 7:8, 3.6 stg
BIT
OD 3 3/4 in
7" casing shoe at 3380 m

KOP = 3394 m TVD


BUR = 58°/30 m

Production Casing
OD 4 1/2 in
Set Depth 3424 m 56 m
316 m
landing point= 3428 m TVD slant section (90° inc)
TD = 3430.41 m TVD
= 3450 m MD
= 3766 m MD

Figure 3: Well E original and Re-Entry configuration


SPE/IADC 107305 7

4900

65 m/min 450 lpm 150 psi WHP


4700 minimum flow maximum flow
100 psi WHP
velocity through motor
Reservoir Pressure = 4544 psi 50 psi WHP

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


4500

4300
BHCP (psi)

10% Draw dow n = 4095 psi


4100

3900 15% Draw dow n = 3868 psi

WHP = 50 psi
350 lpm crude injection
3700
flow range BHCP = 4089 psi (10.1% DD)
recommended Min. Horizontal velocity = 89 m/min
Min. Vertical velocity = 72 m/min
3500
0 100 200 300 400 500 600 700
Crude Injection Rate (lpm)

Figure 4: Initial UBD Operating Envelop with planned injection rates and wellhead pressure for no production case

5000

65 m/min 450 lpm


4800
minimum flow maximum flow
velocity through motor
4600 Reservoir Pressure = 4550 psi

4400

4200
10% Draw dow n = 4095 psi
BHCP (psi)

4000
15% Draw dow n = 3868 psi
3800
20% Draw dow n = 3640 psi
3600
200 psi WHP WHP = 200 psi
370 lpm crude injection
150 psi WHP
3400 BHCP = 4090 psi (10% DD)
100 psi WHP flow range Min. Horizontal velocity = 96 m/min
recommended Min. Vertical velocity = 100 m/min
3200 50 psi WHP

3000
0 100 200 300 400 500 600 700
Crude Injection Rate (lpm)

Figure 5: Initial UBD Operating Envelop with planned injection rates and wellhead pressure for production case
(4 m3/hr Oil – 10000 m3/day Gas)
8 SPE/IADC 107305

Liquid Velocity (m /m in)


0 50 100 150 200 250 300 350 400 450
0

500

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


1000

Vertical Depth (m) 1500 No production case


Production Case
2000 Minimum Vertical Velocity
Minimum Horizontal Velocity
2500

3000

3500

4000

Figure 6: Annular fluid velocity

5000 500

Initial Reservoir Pressure


4500 450

4000 Real Reservoir Pressure 400

WHP (psi); Liq. inj. (lpm); N2 Inj. (m3/min)


3500 350
Bottom Hole Circulating Pressure (psi)

3000 300
BHCP (sensor)

2500 BHCP (simulated) 250


WHP
2000 Liq. inj. 200
N2 Inj.
1500 150

1000 100

500 50

0 0
3380

3400

3420

3440

3460

3480

3500

3520

3540

3560

3580

3600

3620

3640

3660

3680

3700

3720

3740

3760

3780

3800

Measured Depth (m)

Figure 7: Real and Simulated BHCP


SPE/IADC 107305 9

1950
During Drilling Operations During Flow Test
1850

1750

1650
Flow Drilling Nitrogen Injection
1550
1450

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


1350
1250

1150
Gain / Loss (m3)

1050

950
850
750
650

550
450

350
gain/losses

250
150
50

-50
-150

-250

01 Jun

02 Jun

03 Jun

04 Jun

05 Jun

06 Jun

07 Jun

08 Jun

09 Jun

10 Jun

11 Jun

12 Jun

13 Jun
14 May

15 May

16 May

17 May

18 May

19 May

20 May

21 May

22 May

23 May

24 May

25 May

26 May

27 May

28 May

29 May

30 May

31 May
Time

Figure 8: Oil Gain and Losses curve

Vertical Section (m)


0 50 100 150 200 250 300 350
12 3000

ROP 3100
10
Trajectory

3200
8

True Vertical Depth (m)


3300
ROP (m/hr)

3400

4
3500

2
3600

0 3700
3388 3408 3428 3448 3468 3488 3508 3528 3548 3568 3588 3608 3628 3648 3668 3688 3708 3728 3748 3768 3788
Measured Depth (m)

Figure 9: Rate of penetration behavior versus depth


10 SPE/IADC 107305

Vertical Section (m)


0 50 100 150 200 250 300 350
3000 0.25

3050

Downloaded from http://onepetro.org/SPEMEDT/proceedings-pdf/07MEDT/All-07MEDT/SPE-107305-MS/2778108/spe-107305-ms.pdf by Kazakh-British Technical University user on 08 April 2024


3100 0.2

3150
PIWD
Trajectory
True Vertical Depth (m)

3200 0.15

PIWD (m3/d/psi)
3250

3300 0.1

3350

3400 0.05

3450

3500 0
3400
3410
3420
3430
3440
3450
3460
3470
3480
3490
3500
3510
3520
3530
3540
3550
3560
3570
3580
3590
3600
3610
3620
3630
3640
3650
3660
3670
3680
3690
3700
3710
3720
3730
3740
3750
3760
3770
3780
Measured Depth (m)

Figure 10: Productivity Index While Drilling versus depth

700 70

600 60

500 50

e3 m 3/day Gas; m 3/day Oil


Pressure (psi)

400 40

WHP
300 Gas Production Rate 30
Oil production rate

200 20

100 10

0 0
08/06 08/06 08/06 08/06 09/06 09/06 09/06 09/06 10/06 10/06 10/06 10/06 11/06 11/06 11/06 11/06 12/06 12/06 12/06 12/06
00:00 06:00 12:00 18:00 00:00 06:00 12:00 18:00 00:00 06:00 12:00 18:00 00:00 06:00 12:00 18:00 00:00 06:00 12:00 18:00
Flow Test Tim e

Figure 11: Flow test result

You might also like