Proposed 900mm to 1600mm Diameter Industrial

Water Pipelines along Tembusu Avenue and


Jurong Island Highway – Contract 4

Assessment Report of Utility Settlement Marker LUC45010 for Open Cut Pipe Laying from S4 to S5
Introduction
This is assessment report for the utility settlement marker (LUC45010)
that are showing down trend and reached to alert level at forest area
(S4 to S5).

The approved review levels for utility settlement marker are as below:
1) Alert level: 10mm
2) Work suspension level: 15mm
Chronological Event at Forest Area (S4 to S5)
1) Open Cut Pipe Laying Work (Pipe No. 62):
23/6/2023
Instrumentation Plan
Monitoring Report of LUC45010 (1)
Monitoring Report of LUC45010 (2)
Monitoring Report of LUC45011
Monitoring Report of LUC45012
Monitoring Report of LUC45013
• Refer to the IM report of LUC45010, the LU reported 10.2mm of settlement
which exceeded the approved AL on 23/6/2023.

• An open cut trench was excavated for laying of Pipe No. 62 (HY) on 23/6/2023.
However, the open cut trench was 65m away from the affected LU.

• Thus, the settlement of LUC45010 unlikely caused by the open cut pipe laying
work.

• Refer to the IM report of LUC45011 to LUC45013 of 23/6/2023, which are


nearer to the open cut trench, the LU reported normal and stable settlement.

• LUC45010 shows stable reading from 24/6/2023 onwards.


Subsequent Action
• Since the LU (LUC45010) shows stable reading from 24/6/2023
onwards and it is no longer required for monitoring any open cut pipe
laying work, the affected LU can be terminated.