Pipe line is installed from 25th November to 28th November 2015.

Hydro Test activities started on 05th March & Completed on 08th March 2016 for Subsea Pipeline.

Pipe line Installation Punch Points dated on 28th November are given below.

S.No Punch Point Description Status


01 ABS IV marked DCI drawings (critical drawings) to be submitted Open
for Review and approval
02 Subject to approval of drawing No.PRP4-S1-PPD-HR-HRG-PLR- Open
DRW-7002 Rev.0
03 DNV GL and ABSIV IRN to be submitted Open
04 Saturation density & Compressive Test is balance for HDPUF Open
foam sample taken from every 100 joints
05 No Temporary Sleeper is installed on Rigid Crossings. As Per Open
temporary crossing Support Installation Report
PRP4/SWIBER/ONGC/PH-1/CONQUEST/0020 temporary
supports are provided over soft crossings, however the
temporary supports ( 18” x 4M, 18” x 6M bare Pipes) are not
approved by ONGC. All crossings to be installed with
Permanent Supports as per ONGC Specification and drawings.
06 DNV GL Comments are not closed in Procedure No. PRP4-S1- Open
SOC-GNPL-PLR-PRC-0202 Rigid Pipeline Installation Procedure
Rev_C0
07 Anode type Mentioned in drawing No. PRP4-S1-PPD-HR-HRG- Open
PLR-DRW-7002 Rev.C0 is A1, But Anode type mentioned in
annexure sheet of Jindal Saw Ltd is A9 & A10
08 As laid line of HR-HRG is found 3.9M off track near the Platform Open
HRG and 33M off track near HR Platform from the proposed
Pipeline route given in drawing No.PRP4-S1-PPD-HR-HRG-PLR-
DRW-7001 Rev.C0. As per ONGC Specification, the Pipeline
shall be laid within 2M on either side of the Pipeline route
shown in the company approved drawings for a distance of up
to 1000 meters from the Platform / PLEM or other Subsea
Installation

DLB Swiber Resolute completed the work related to the 10” Riser stalk on with Pipeline and Installation of
10” Riser in to the preinstalled subsea Riser clamps on 24th January 2016 at HR Platform, East Face in Heera
field for 10” WF HR-HRG Rigid line
10” WF Rigid Pipe Line - HR to HRG (KP 0.000 to KP 2.673)
12th March 2016

Punch Point of 10”WF Riser for 10”WF HR-HRG Rigid line at HR Platform dated on 24 th January

S.No Punch Point Description Status


01 Subjected to Satisfactory Results of dry density, Saturated Open
density and compressive strength of HDPUF Sample

02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp doubler Plate with Platform jacket member
and Hanger clamp Stub with doubler Plate to be carried out as
per ONGC Specification No.2005 Rev.04,after removing the
temporary Paint.

03 Installation of HR-AC-A2 Clamps Open

04 As-Built to be incorporated Open

AWB Swiber Chateau completed the work related to the 10” Riser stalk on with Pipeline and Installation of
10” Riser in to the preinstalled subsea Riser clamps on 20th February 2016 at HRG Platform, for 10” WF HR-
HRG Rigid line

Punch Point of 10”WF Riser for 10”WF HR-HRG Rigid line at HRG Platform dated on 20 th February

S.No Punch Point Description Status


01 Subjected to Satisfactory Results of dry density, Saturated Open
density and compressive strength of HDPUF Sample

02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp joint section with Platform member to be
carried out as per ONGC Specification No.2005 Rev.04, after
removing the temporary Paint.

03 Torque Tightening and Final Inspection of Hanger Clamp Open

04 Temporary Sand Bag Support to be replaced by Permanent Open


Grout Bag as per ONGC Specification

05 As-Built drawing to be approved Open

06 Inspection Release Note and Report of Activity from CA for Open


transition bend to be submitted.

07 During as-built survey, 4 Nos of washer for Hinge bolts for Open
clamp No.HRG-AC-A5 are found missing and need to be
10” WF Rigid Pipe Line - HR to HRG (KP 0.000 to KP 2.673)
12th March 2016

installed

08 ABS Comment : Subject to clearance of IMIR comments Open

09 ABS Comment : Revised Installation Procedure Rev.C1 to be Open


submitted for Review from ONGC TPI / CA

10 ABS Comment :Torque Test witness balance for HRG-HC-A1 Open

11 Subject to availability of Release Note & Report of Activity by Open


Third Party Inspector and Certified Agency for welding of
Hanger Clamp.

12 NDT and Painting is balance for Hanger Clamp Open