10" WF Rigid Pipe Line - HR To HRG
10" WF Rigid Pipe Line - HR To HRG
673)
12th March 2016
Hydro Test activities started on 05th March & Completed on 08th March 2016 for Subsea Pipeline.
Pipe line Installation Punch Points dated on 28th November are given below.
DLB Swiber Resolute completed the work related to the 10” Riser stalk on with Pipeline and Installation of
10” Riser in to the preinstalled subsea Riser clamps on 24th January 2016 at HR Platform, East Face in Heera
field for 10” WF HR-HRG Rigid line
10” WF Rigid Pipe Line - HR to HRG (KP 0.000 to KP 2.673)
12th March 2016
Punch Point of 10”WF Riser for 10”WF HR-HRG Rigid line at HR Platform dated on 24 th January
02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp doubler Plate with Platform jacket member
and Hanger clamp Stub with doubler Plate to be carried out as
per ONGC Specification No.2005 Rev.04,after removing the
temporary Paint.
AWB Swiber Chateau completed the work related to the 10” Riser stalk on with Pipeline and Installation of
10” Riser in to the preinstalled subsea Riser clamps on 20th February 2016 at HRG Platform, for 10” WF HR-
HRG Rigid line
Punch Point of 10”WF Riser for 10”WF HR-HRG Rigid line at HRG Platform dated on 20 th February
02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp joint section with Platform member to be
carried out as per ONGC Specification No.2005 Rev.04, after
removing the temporary Paint.
07 During as-built survey, 4 Nos of washer for Hinge bolts for Open
clamp No.HRG-AC-A5 are found missing and need to be
10” WF Rigid Pipe Line - HR to HRG (KP 0.000 to KP 2.673)
12th March 2016
installed