12th March 2016
Swiber is Performed transition Bend Golden Joint welding at HS Platform today (12/03/2016).
Pipe line Installation Punch Points dated on 10th December are given below.
AWB Swiber Chateau completed the work related to the 12” Riser stalk on with Pipeline and Installation of
12” Riser in to the preinstalled subsea Riser clamps on 22nd February 2016 at HRG Platform, for 12” WF HS-
HRG Rigid line
12” WF Rigid Pipe Line - HS to HRG (KP 0.000 to KP 5.442)
12th March 2016
Punch Point of 12”WF Riser for 12”WF HS-HRG Rigid line at HRG Platform dated on 22 nd February
02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp joint section with Platform member to be
carried out as per ONGC Specification No.2005 Rev.04, after
removing the temporary Paint.
09 Modification done for Riser clamps for drg No. PRP4-S1-PPD- Open
HS-HRG-PLR-DRW-7009 Rev.C0 to be approved by client
10 ABS Comment : DCI drawings (critical Drgs.) not submitted for Open
Review and approval
Hanger Clamp.
12 ”WF Riser for 12” WF HS-HRG Rigid lines at HS Platform Certification to be submitted for verification