12” WF Rigid Pipe Line - HS to HRG (KP 0.000 to KP 5.

442)
12th March 2016

Pipe line is installed from 07th December to 10th December 2015.

Swiber is Performed transition Bend Golden Joint welding at HS Platform today (12/03/2016).

Pipe line Installation Punch Points dated on 10th December are given below.

S.No Punch Point Description Status


01 ABS IV marked DCI drawings (critical drawings) to be submitted Open
for Review and approval
02 Subject to approval of drawing No.PRP4-S1-PPD-HS-HRG-PLR- Open
DRW-7002 Rev.0. Crossing details are not matching with
Alignment sheet and changes to be incorporated and approved
copy to be submitted for Review
03 Saturation density & Compressive Test is balance for HDPUF Open
foam sample taken from every 100 joints
04 No Temporary Sleeper is installed on Rigid Crossings and only Open
installed for soft crossings. All crossings to be installed with
Permanent Supports as per ONGC Specification and drawings.
05 DNV GL Comments are not closed in Procedure No. PRP4-S1- Open
SOC-GNPL-PLR-PRC-0202 Rigid Pipeline Installation Procedure
Rev_C0
06 Anode type Mentioned in drawing No. PRP4-S1-PPD-HS-HRG- Open
PLR-DRW-7002 Rev.C0 is A2, But Anode type mentioned in
annexure sheet of Jindal Saw Ltd is A11 & A15
07 As laid line of HS-HRG is found 5.4M off track near the Platform Open
HS and 33.7M off track near HS Platform from the proposed
Pipeline route given in drawing No.PRP4-S1-PPD-HS-HRG-PLR-
DRW-7001 Rev.C0. As per ONGC Specification, the Pipeline
shall be laid within 2M on either side of the Pipeline route
shown in the company approved drawings for a distance of up
to 1000 meters from the Platform / PLEM or other Subsea
Installation
08 Subject to approval of anode sequence lay document No. PRP4- Open
S1-PPD-GNPL-PLR-REP-7014 Rev.C0
09 As Per ONGC Specification, Survey by diver after 12 hours of Open
Installation Pending
10 Video of as-built survey shall be carried out and to be Open
submitted
11 Subjected to clearance of comment in conclusion in ABSIV IRN Open

AWB Swiber Chateau completed the work related to the 12” Riser stalk on with Pipeline and Installation of
12” Riser in to the preinstalled subsea Riser clamps on 22nd February 2016 at HRG Platform, for 12” WF HS-
HRG Rigid line
12” WF Rigid Pipe Line - HS to HRG (KP 0.000 to KP 5.442)
12th March 2016

Punch Point of 12”WF Riser for 12”WF HS-HRG Rigid line at HRG Platform dated on 22 nd February

S.No Punch Point Description Status


01 Subjected to Satisfactory Results of dry density, Saturated Open
density and compressive strength of HDPUF Sample

02 Complete Painting of Riser section above the Hang off sleeve Open
and Hanger Clamp joint section with Platform member to be
carried out as per ONGC Specification No.2005 Rev.04, after
removing the temporary Paint.

03 Complete welding, NDT and Painting of Transition bend to Open


monel section Joint (OFW 01)

04 Torque Tightening and Final Inspection of Hanger Clamp Open

05 As-Built drawing to be approved Open

06 Inspection Release Note and Report of Activity from CA for Open


Pipe and Riser Bends to be submitted

07 20 Nos of washer need to be installed on clamp bolts and Open


hinge Bolts for Clamp No.HRG-AC-A2

08 During as-built survey, 1 No of washer for Clamp bolts for Open


clamp No.HRG-AC-A4 is found missing and needs to be
installed

09 Modification done for Riser clamps for drg No. PRP4-S1-PPD- Open
HS-HRG-PLR-DRW-7009 Rev.C0 to be approved by client

10 ABS Comment : DCI drawings (critical Drgs.) not submitted for Open
Review and approval

11 ABS Comment : Subject to Submission of ABSIV IRN and Open


clearance of IMIR comments

12 ABS Comment : Revised Installation Procedure Rev.C1 to be Open


submitted for Review from ONGC TPI / CA

13 Torque Test witness balance for HRG-HC-A1 Open

14 Subject to availability of Release Note & Report of Activity by Open


Third Party Inspector and Certified Agency for welding of
12” WF Rigid Pipe Line - HS to HRG (KP 0.000 to KP 5.442)
12th March 2016

Hanger Clamp.

15 NDT and Painting is balance for Hanger Clamp Open

16 ABS Comment : MOC for Clamps to be approved Open

12 ”WF Riser for 12” WF HS-HRG Rigid lines at HS Platform Certification to be submitted for verification