Professional Documents
Culture Documents
CIVIL WORKS
( SPECIFICATION )
S-AAA-CIV-OHL (Rev.0-2015)
Page 1 of 28
CIVIL WORKS
Civil Works for Overhead Distribution Lines
CONTENTS
1 GENERAL ....................................................................................................................... 3
2 TECHNICAL DESCRIPTION ...................................................................................... 3
2.1 Soil Investigation............................................................................................................... 3
2.1.1 Execution of Borings and In-Situ Tests (SPT) .................................................................. 4
2.1.2 Bore Logs .......................................................................................................................... 6
2.1.3 Laboratory Tests ................................................................................................................ 6
2.1.4 Reports .............................................................................................................................. 7
2.1.5 Change of Investigation Program ...................................................................................... 8
2.2 Foundations ....................................................................................................................... 9
2.2.1 General .............................................................................................................................. 9
2.2.2 Foundation Types .............................................................................................................. 9
2.2.3 Soil Characteristics .......................................................................................................... 10
2.2.4 Protection of Tower Foundations .................................................................................... 10
2.2.5 Caps ................................................................................................................................. 11
2.3 Gantries ........................................................................................................................... 12
2.4 Access.............................................................................................................................. 12
2.5 Design of Foundations..................................................................................................... 13
2.5.1 Pile Foundation................................................................................................................ 13
2.5.2 Pad and Chimney Foundation ......................................................................................... 14
2.6 Erection of Foundations .................................................................................................. 15
2.6.1 General ............................................................................................................................ 15
2.6.2 Earth and Rockwork ........................................................................................................ 15
2.6.3 Concrete Work ................................................................................................................ 16
2.6.4 Bored Pile Foundations ................................................................................................... 23
2.6.5 Foundation Load Tests .................................................................................................... 24
2.6.6 Additional Civil Work ..................................................................................................... 27
2.6.7 Sign Boards for Road Crossings...................................................................................... 27
2.7 Factors of Safety.............................................................................................................. 28
1 GENERAL
For Conceptual Foundations reference shall be made to:
S-AAA-CIV 03 03 - Conceptual Foundations
This part of the Specification shall cover all items related to civil works within overhead and
overhead transmission line projects.
Works shall include, but not be limited to the following: geo-technical investigations, soil
resistivity measurements, selecting, design, setting out, installation and testing of all required
types of tower foundations for the different types tower types and location conditions. Provision
of tower platforms and/or stabilising of tower locations, access roads and provision of revetment
protection as/and where required.
For applicable technical standards, tests, reference shall be made to:
S-AAA-CIV-GEN - General Requirements
(Applicable Technical Standards, Tests, etc.)
2 TECHNICAL DESCRIPTION
For pole lines of 33 kV and below, initially only dead-end towers, angle towers and tension
towers and at every third suspension tower location shall be investigated, provided that the
resulting spacing between boreholes does not exceed 200 m. At locations where boreholes are
not being carried out, results of adjacent boreholes may be interpolated. If severe variations of
the ground conditions between boreholes are recorded, additional interim locations shall be
investigated.
2.1.1.1 Borings
The methods of boring shall enable undisturbed sampling as well as rotary coring. The minimum
borehole diameter for undisturbed sampling shall be 100mm. The equipment shall allow the
execution of Standard Penetration Tests and undisturbed sampling, for instance by using piston
sampler.
For the drilling works in cohesive and/or hard soils, a double tube core barrel of at least 3"
(7.5 cm) inside diameter shall be used exclusively, provided that this kind of boring can be
continued to the final bottom of the borehole in question. A 95 % core recovery is required.
Beyond this, the Bidder/Contractor may choose for his own convenience the type of equipment
and accessories to be used at each individual borehole and depth, provided that in
ADWEA/ADDC/AADC's opinion, the equipment chosen is suitable for the drilling. The
Bidder/Contractor may also choose the initial and intermediate diameters of each borehole for
his own convenience, provided that he will secure the aforementioned minimum acceptable size
of core.
Adequate casing has to be used to ensure the stability of the borehole. The Bidder/Contractor
will not be entitled to any compensation or additional payment for casing.
The method of drilling, casing and flushing shall be described in the offer. Bentonite shall be
added to the drilling fluid only after the explicit permission of ADWEA/ADDC/AADC.
It is to be emphasised that the Bidder/Contractor shall supply an equipment to take undisturbed
samples from cohesive and non-cohesive soils for laboratory tests, according to international
standards. The samples shall be treated in an adequate manner to avoid disturbances and drying
out.
All boreholes shall after completion of the investigation be refilled with sand and not left open.
2.1.1.2 Sampling
All soils sampled by SPT, undisturbed sampling or core barrel have to be properly stored. Non-
cohesive soils have to be kept in water-tight boxes or bags. Borehole number and depth of
sample shall be written on the cover of the bags and boxes, and the cores must be placed in the
order as taken. The corresponding depth of the material shall continuously be written on the
partition walls of the boxes. Undisturbed samples shall be of 100mm dia and 450mm length.
Samples shall be collected in such a manner that the structure of the soil and its moisture content
are not changed.
The borders between different strata, and the sections of core boxes shall be fixed with thin
boards, and marked with the depth. Core boxes shall be designed for approximately 7 metre of
continuous soil samples. Before shifting the soil samples to the laboratory, the boxes shall be
stored accessible at any time for ADWEA/ADDC/AADC.
Ground-water and disturbed soil samples taken for the chemical analysis shall be kept in
watertight, durable plastic jars.
Color print photographs shall be taken of all cores packed in the core boxes, suitably labelled.
Negatives and six sets of postcard size prints shall be provided.
2.1.4 Reports
Field reports have to be handed over to ADWEA/ADDC/AADC at site including bore-logs with
all pertinent data, SPT results, ground water levels, cone penetration diagrams, test pit logs, as
well as readings of groundwater levels within three days after completion of the corresponding
work.
2.2 Foundations
2.2.1 General
a) Tower foundations shall normally be single leg foundations of reinforced concrete each
tower foundation selected has to be proposed and justified by the Bidder/Contractor and
shall be approved by ADWEA/ADDC/AADC.
b) The Bidder/Contractor shall stake out the tower locations and submit to
ADWEA/ADDC/AADC the foundation conditions including permissible bearing pressure
assumed at each tower, together with the type of foundation considered applicable.
ADWEA/ADDC/AADC may require the Bidder/Contractor to make additional soil
investigations at tower sites to verify the foundation conditions at no additional cost.
c) For his final foundation design the Bidder/Contractor has to perform the required soil
investigations and has to base his design calculations on the detailed information obtained.
The Bidder/Contractor is requested to quote firm unit rates for the different types of
foundations and towers as set out in the Bills of Quantities. These unit rates will be
considered as flat rates covering all foundation costs for any type of soil encountered along
the line and no adjustment of the rates will be permitted.
d) The number of towers set out in the Bills of Quantities against each type may change, as
well as the numbers of specific types of foundations. Their numbers will be adjusted and
remunerated according to the quoted unit rates. This will, however, not entitle the
Bidder/Contractor to a change of the quoted unit rates or to any other additional claim.
Where special ground conditions exist, which do not allow any of the above types in original or
modified form, special types of foundation have to be considered and proposed, and after
ADWEA/ADDC/AADC’s approval have to be applied.
Prior to the selection of foundation types the Bidder/Contractor shall submit all relevant
drawings and data for approval. The decision of ADWEA/ADDC/AADC as to which type of
foundation shall be employed at a given location shall then be final.
Fill used for such platforms, as well as the stone pitching, shall be paid according to the
respective item in the Pricing Schedule.
2.2.5 Caps
In locations not liable to flooding of bearing surface water, all steelworks, whether part of the
tower or part of the stub-angle foundation shall be completely encased in concrete to ensure a
concrete cover of 100 mm for any part of the stub leg/tower steel in the ground. This shall apply
from a point 450 mm above ground down to the toe of the stub angle. Cleats fitted to the stub-
angles shall be considered.
All concrete foundations shall be at least 75 cm above the final ground of the tower location.
Free-standing length of pile foundations shall be limited to 2.0 m above Finished/ Natural
Ground Level. Foundations shall be of dense concrete, adequately sloped off around the steel leg
/ stub angle section and smoothly finished to ensure drainage of water away from the steel work.
No capping shall be commenced in any portion of the work until the designed portion has been
approved by ADWEA/ADDC/AADC.
Final (future) finished ground level/elevation at the tower location shall be obtained from the
concerned local authorities during route approval, i.e. to consider future filling and development
works. In areas adjacent to roads (within 200 meters centreline to centreline), the tower location
level shall not be lower than the road level.
All tower foundation concrete above ground is to be protected equivalent to the concrete below
ground.
2.3 Gantries
The gantry will be located at a distance of about 50 to 120 m from the terminal tower. As
protection against entrance of unauthorised persons, a fence of galvanised and plastic coated
steel mesh of an approved type and with a minimum height of the mesh of 3.0 m with galvanised
plastic coated steel posts and gates, shall be provided around the gantry. Unless a gantry is
located within a Sub or Power Station area, inclined holders with 4 strands of galvanised or
stainless steel barbed wire shall additionally be installed at the top of the perimeter fence. Proper
earthing of the fence shall be provided if required.
Foundation design, grounding and painting of the gantry, and for the design of its foundation the
same stipulations are valid as for towers and foundations.
An earthing grid up to outside of the fence has to be provided with stranded tinned copper
conductor of at least 95 mm² and conforming to the requirements of VDE 0141.
All areas of the gantry shall receive topping with gravel and shall be excavated to a depth of not
less than 150 mm referring to finished ground level. The bottom of the excavated area shall be
plain, topped and levelled with coarse gravel of 25-51 mm in size and of a thickness of not less
than 150 mm. Alternative solutions may be proposed by the Bidder/Contractor for
ADWEA/ADDC/AADC’s approval.
Fencing, earthing and gravelling of the gantry areas according to Gantry layout is deemed to be
included in the items “gantry” and “foundation for gantry” of the Price Tabulation Sheet.
2.4 Access
The Bidder/Contractor shall be responsible for the provision and maintenance of all access to the
transmission line routes and the tower locations as required for his erection work.
Access for later maintenance of the transmission line shall be instructed by
ADWEA/ADDC/AADC and paid according to P.T.S. Such access may be used by the
Bidder/Contractor for his construction purposes, but shall be maintained to a standard in
compliance with the specification up to FAC and at no extra cost. All access provisions shall be
submitted for ADWEA/ADDC/AADC’s approval prior to construction. Access provisions over
and above access instructed by ADWEA/ADDC/AADC for future maintenance of the
transmission line shall be at the Bidder’s/Contractor's responsibility and at his own cost.
Maintenance roads along the line route instructed by ADWEA/ADDC/AADC shall be routed at
a minimum distance between the edge of the road and the longest crossarm plus 5m. The
crossing of the line centreline by such maintenance road shall if possible be avoided.
Maintenance roads shall have a clear width of 4m at the top and with side slopes at a gradient not
steeper than 1:1. They shall be constructed from and approved gatch material and compacted by
roller to a minimum final thickness of 100cm. The final surface level shall be at least 70cm
above the existing ground level.
No separate payment shall be made to the Bidder/Contractor on account of slight changes on the
line routings such as they may be required in shifting the transmission line route due to the
requirements of local Authorities and ADWEA/ADDC/AADC. Further reference is made to the
Special Conditions. Notice has to be given that the line routes contained in this Tender
Document are of tentative and preliminary purpose.
Material to be used for the construction of maintenance road shall fulfil the requirements listed in
article 2.2.4.3(material for fill and backfill).
For Typical Section of Gatch Road details, reference shall be made to the below listed drawings,
which are provided in the Drawing Section:
Drawing No. Title
DWG AAA CIV 11 04 Typical Section of Gatch Road
2.6.1 General
Tower foundation installation shall include tower site preparation, excavation, any measures
required to ensure slope stability or free drainage dewatering, foundation placement
measurements, assembly and placement of the approved foundation, foundation protection, as
well as backfill and clean-up.
The Bidder/Contractor shall employ templates for stub setting for each tower and gantries. In
general, all four stubs shall be set simultaneously using templates. However, in case of
undulating terrain or due any other specific problem, each stub may be set separately using
templates.
The Bidder/Contractor shall remove all vegetation and other debris from the tower site, which
will interfere with his operation. Vegetation and debris removed from the tower site shall be
disposed off outside the right of way as directed by ADWEA/ADDC/AADC and/or in
accordance with local regulations.
The ground levels existing before the installation of foundations have to be considered in
determining tower platform heights.
The Bidder/Contractor shall dispose of material and regulate the movement of equipment so that
grades shall not be exposed, and slopes necessary to develop required loading characteristics
shall be maintained, especially in side-hill locations.
The depth of pile foundations shall always be related to the lowest ground (not platform/fill
elevation in the area occupied by the foundation.
2.6.2.1 General
There will be no classification of excavated materials, and the term “Excavation” shall include
all materials to be excavated or to be removed within the Project, regardless of the type,
character, composition, or conditions of the material excavated and shall further include all
debris, junk, broken concrete, bricks, logs, stumps, roots, and all other material encountered
within the specified excavation limits.
The Bidder/Contractor is responsible for all necessary safety measures. He is liable for any
damage and accidents occurring while earth work is being carried out. Proper standing, including
any necessary re-arrangement protection of slopes or cribbing, preparation of design
calculations, etc. shall be deemed included in the prices.
In the event of soil slides occurring during earth and rock work, all damage will be to the
Bidder’s/Contractor’s debit. This also implies that no payment will be made for the additional
moving of soil resulting from such damage.
2.6.2.3 Backfilling
Refilling around the pile head pits shall be carried out only after all works within the excavations
have been inspected and approved by ADWEA/ADDC/AADC.
Unless otherwise directed all filling shall be approved selected material, and shall be deposited
and compacted using approved material in layers not exceeding 150 mm thick for hand
compaction and 250 mm for mechanical compaction, loose depth.
During the placing of backfill the hole shall be kept free from water. All temporary timbering
and all decomposable material shall be removed from the excavations prior to backfilling.
2.6.2.4 Settlement
The Bidder/Contractor shall be responsible for making good all settlements of filling due to any
cause whatever which may occur up to the end of the period of maintenance.
2.6.3.2 Aggregates
Aggregates shall be crushed rock type and conform to the relevant applicable standard BS
882:1992. The combined aggregate shall be as coarse-grained and dense-graded as possible and
shall be according to the guidelines of BS 882. The maximum particle size shall be so chosen as
to be compatible with mixing, handling, placing and workability of the concrete.
For underwater concrete, proof shall be given that the mix is adequately cohesive and maintains
this property during placing by using under-water admixtures.
Aggregates shall - for all groups except the dune sand - be a product of crushed rock, with the
source and type being subject to ADWEA/ADDC/AADC´s approval. Only for exceptional cases
and upon ADWEA/ADDC/AADC´s specific written approval, aggregates of other origin may be
used for certain parts of the work.
Size of aggregate used in concrete: maximum aggregate size shall be 20mm, except for thick
elements (>900mm) where particular heat of hydration control is required. There, aggregate of
28mm max size may be used. For the required concrete of Grade 40 (C28 = 40 N/mm2), at least
one particle size fraction shall be in the 0-4 mm range.
Aggregates shall be of limestone source and shall be subject to ADWEA/ADDC/AADC´s
approval.
2.6.3.3 Cement
a) Type of Cement
The type of cement to be used shall depend on the constructional circumstances and on the
prevailing local conditions. Portland cement, Type I, may be used at places not exposed to
chemical aggressiveness, whereas Portland cement, Type V, shall in general be used for all
concrete work in foundations and plinths and in concrete structures covered by soil.
Moderate sulphate resistant cement as per ASTM C 150, type 2, may be used only after
ADWEA/ADDC/AADC's explicit written approval to replace the type V cement.
Cement shall be of recent manufacture and shall be used within a period of 3 months from
production.
Total cementitious contents in the mix shall be limited to avoid excessive risk of thermal and
shrinkage cracking. It shall always be in the range of 350 – 400 kg/m3, unless otherwise
approved by ADWEA/ADDC/AADC. The proportioning of mixes for durability will be
primarily controlled through the specified limits on free W/C ratio. The W/C ratio shall always
lie in the range of 0.36-0.45. Appropriate use shall be made of approved admixtures to
simultaneously meet the requirements for W/C ratio and workability.
Before supplying cement to Site or receiving ready-mixed concrete, the Bidder/Contractor shall
submit to ADWEA/ADDC/AADC, the manufacturer’s statement of Specification and test
certificate together with date of manufacture of any cement to be used. ADWEA/ADDC/AADC
reserves the right to take samples and order any additional / re-tests in accordance with BS EN
196-7 : 1992, BS EN 196-6, BS 4450 and ASTMC 186.
In mix designs with an emphasis on durability, ground granulated blast furnace slag as per BS
6699 or EN 197 or microsilica may be incorporated in the mix. Proportions of slag shall
normally not exceed 60 %, those of microsilica shall not exceed 8%, for items thicker than 1.2m,
these proportions shall not exceed 10%.
The cement shall be selected according to the recommendations of BRE-Digest 363 of 1991 and
as summarised here:
SO4 IN SOIL OR FILL SO4 IN CEMENT TYPE
GROUNDWATER
Soil Class by 2:1 water/soil extract – g/l
g/l
1 and 2 ≤ 2.3 ≤ 1.4 OPC
3 2.3 ≤ 3.7 1.4 ≤ 3.0 SRC / MSRC
4 and 5 ≥ 3.7 ≥ 3.0 SRC
b) Delivery and Storage
All accepted cement shall be properly protected, delivered and stored in dry weather-proof sheds
or covers. Cement shall be delivered in quantities sufficient to ensure continuity of the work, and
to enable all the necessary tests to be carried out before it is used, but should not be stored for
more than 6 weeks.
ADWEA/ADDC/AADC may reject any cement as a result of any tests thereof, notwithstanding
the manufacturer’s certificate. He may also reject cement, which has deteriorated owing to
inadequate protection or other causes or in any other case where the cement is not to his
satisfaction. The Bidder/Contractor must remove all rejected cement from the site without delay
and expenses for ADWEA/ADDC/AADC.
2.6.3.5 Reinforcement
a) Epoxy Coated Reinforcement
Reinforcement is to be hot-rolled deformed high yield steel in accordance with DIN 488,
DIN EN ISO 15630 or BS 4449 – Grade 460 or higher. Only epoxy coated reinforcement shall
be used for foundations of transmission line towers.
The reinforcement steel shall be protected against corrosion with a fusion-bonded epoxy coating.
The coating shall be applied in accordance with ASTM A775/775M-01, and shall be supplied
from an approved coating factory using approved epoxy resins.
All handling and bending procedures shall be to the coating factory’s recommendations and
instructions, and as agreed with ADWEA/ADDC/AADC. A coating factory representative shall
ensure his product is used fully in accordance with his recommendations.
The Bidder/Contractor shall furnish to ADWEA/ADDC/AADC a certificate of compliance for
each shipment of coated bars.
b) Repair of Damaged Epoxy Coating
When the epoxy coating is damaged, (cut ends, accidental damage etc.) the coating shall be
repaired with parching material conforming to ASTM A775/A775M-01 and shall be carried out
in accordance with the manufacturer’s recommendations.
The repair to the damaged area shall be carried out as soon as possible, and before oxidation of
the surface occurs. In no case shall the repair be delayed more than 8 hours. Any trace or rust or
oxidation must be removed by grinder or wire brush prior to touch-up.
c) Fabrication
All reinforcements shall be bent cold unless otherwise permitted by ADWEA/ADDC/AADC.
Bar cutting equipment shall have padded supports and contact areas. Bar bending equipment
shall have padded supports and contact areas and shall be fitted with nylon or plastic mandrels
supplied by, or approved by, the coating factory representative.
d) Site Installation and Handling
Reinforcement of all types shall be stored on Site in protected racks above ground in an
approved manner so as to avoid damage to the coating. Direct metal to coating contact should be
avoided wherever possible.
The number, size, form and disposition of bars shall be strictly in accordance with the drawings
and bending schedules or as directed by ADWEA/ADDC/AADC. Reinforcement shall be
checked after being fixed and no concrete shall be placed around the reinforcement until such
checking has taken place.
Equipment for handling epoxy coated bars shall have padded contact areas. Bundles shall be
lifted with a strong-back or have multiple supports to prevent bar-to-bar abrasion from sags in
the bundle. Bars or bundles shall not be dragged or dropped. Any coating damage due to
handling, shipment and placing shall be repaired as described above.
All tie-wires or other devices used to connect, support, secure or fasten epoxy coated
reinforcement shall be made of, or coated with, a dielectric material such as nylon, epoxy or
plastic. All bundles shall be identified at the factory with durable tags to allow checking of
coating quality control at site. Reinforcement shall not be straightened or re-bent in a manner,
which may cause injury to the material. Bars with shapes not shown on the drawings shall not be
used.
All reinforcing bars shall be bent in accordance with the relevant standard. In particular, no
reinforcement shall be heated. All reinforcement shall be rigidly fixed in position to the concrete
cover specified by an approved means.
Prior to concreting the Bidder/Contractor shall ensure that the reinforcement is cleaned of all
concrete from previous pours and any damage to the coating is repaired.
2.6.3.6 Concreting
Concreting for pile foundation shall be done through tremie-pipes or equivalent devices to
prevent segregation. Alternatively pumping methods may be proposed by the Bidder/Contractor.
For concreting in hot weather, ACI Standard 305R "Hot Weather Concreting" and the "CIRIA –
“Guide to the construction of reinforced concrete in the Arabian Peninsular”. and its
recommendations shall be followed and various means may be employed to lower the
temperature of concrete such as:
Cooling coarse aggregate with water by sprinkling and shading
Using chilled water
Using crushed ice
Avoiding the use of the hot cement
Shading mixer drums, facilities and material by use of permanent wet burlap coverings
Adequately watering of sub-grade, form-work and reinforcement
Insulating water supply lines and tanks and/or painting exposed portions white
Working only at cooler daytime
Covering freshly poured concrete with polythene sheets
Intensive moist-curing with potable water of the concrete placed.
Curing the concrete continuously with water at least for 7 days and as detailed in CIRIA’s
“Guide to the construction of reinforced concrete in the Arabian Peninsular”. Attention to
curing requirements is important at all times; it is especially in hot, dry weather because of
greater danger of cracking. The use of ice to lower the temperature of fresh concrete must
be carefully controlled. If flaked ice is used in the mix, it must be of such a size that it will
melt completely in the mix and that no ice remains once the batching is complete. The
temperature of fresh concrete must in no case exceed + 30°C. When discharged in the
form-work, particular care shall be given for thick section (>900mm) where insulation
boards shall be used to reduce temperature gradient.
2.6.3.7 Testing
Throughout the construction period the quality of concrete mixed at and/or delivered to Site has
to be controlled. Tests shall be carried out in the presence of ADWEA/ADDC/AADC or under
the supervision of an approved office for testing of such kind of works. The following minimum
numbers of tests shall be carried out:
a) Water
One chemical water analysis every 3 months of construction. First analysis before start of
foundation works.
b) Cement
b1) For site mixed concrete if applicable and or approved by ADWEA/ADDC/AADC
One setting test to vicat per car-load
One boiling test per car-load.
Notes:
* Water retaining structures and Basements in areas with high water table
** Marine structures and structures in areas with highly aggressive soil conditions, classified
as class 4 & 5 as per the BRE Digest 363
Aggregates contamination limits shall be as follows:
Chlorides Sulphates Reference
Coarse Aggregates < 0.03% < 0.4% CIRIA
Fine Aggregates < 0.06% < 0.4% CIRIA
RC with SRC < 0.20% < 4.0% CIRIA
RC with OPC < 0.30% < 4.0% CIRIA
Not Reinforced Concrete < 0.60% < 4.0% CIRIA
Either a temporary or a permanent casing, as per design, shall be provided. This shell shall
remain partly or as a whole in the ground to:
Protect the fresh (“green”) concrete
Prevent loosening of soil in vicinity of the pile
Avoid contamination of the concrete
Prevent penetration of aggressive components into parts of the concrete structure.
Prior to commencement of piling the Bidder/Contractor shall install one test piles of each type
proposed. The piles shall be test loaded by tension, compression and horizontal forces applied in
the direction of the resultant of the vertical and horizontal forces on the pile.
Tested piles shall be considered as acceptable in case the obtained load-settlement/heave-
diagrams do not indicate movements beyond permissible limits as per the approved design or
relevant and approved Standards.
Working piles shall not be installed until the load tests have been conducted and evaluated and
unless authorised by ADWEA/ADDC/AADC.
Unless otherwise directed by ADWEA/ADDC/AADC, the following guidelines shall be applied
for pile tests:
3 pile configuration with the reaction piles of the same length as the test piles is to be used with
the middle pile being tested for tension and the reaction piles being used to evaluate compression
to a minimum of 1.25 times working load.
The pile test loads shall be as mentioned in Schedules ‘Factor of Safety’. The test load shall be a
product of maximum ultimate uplift load, i.e. 1.5 times maximum uplift load under broken wire
or 2.5 times the maximum uplift load under normal conditions, and the factor of safety. The pile
testing procedure and method of statement including loading cycle shall be submitted to
ADWEA/ADDC/AADC for approval.
If the pile test results are not to the satisfaction of ADWEA/ADDC/AADC, the
Bidder/Contractor shall change the pile type and choose an other type of pile approved by
ADWEA/ADDC/AADC for which test piles will be constructed and the load test performed until
the Bidder/Contractor gets successful results without extra cost or extension of time.
75 1 hr S≤0.25 mm
100 1 hr S≤0.25 mm
50 15 min OFFLOADING
0 15 min OFFLOADING
100 1 hr S≤0.25 mm
125 1 hr S≤0.25 mm
150 1 hr S≤0.25 mm
175 1 hr S≤0.25 mm
200 1 hr S≤0.25 mm
225 1 hr S≤0.25 mm
250 24 hrs S≤0.25 mm
200 15 min S≤0.25 mm
150 15 min OFFLOADING
100 15 min OFFLOADING
50 15 min OFFLOADING
0 1 hr OFFLOADING
On every increment, settlements shall be recorded after 30”, 2’, 4’, 8’, 15’, 30’, 1h. Movement of
the pile head shall be less than 0.25 mm within that hour , or until 2 hours have elapsed,
whichever occurs first, before the application of the new load increment.
For working piles, the load cycles will be terminated at a maximum of 150 %.
For arrangement of Pile Load Tests details, reference shall be made to the below listed drawings,
which are provided in the Drawings Section:
Drawing No. Title
DWG AAA CIV 03 01 Pile Loading Test: Compression (Proposal 1)
DWG AAA CIV 03 02 Pile Loading Test: Compression (Proposal 2)
DWG AAA CIV 03 04 Arrangement of Pile Load Test
The design for the signboard has to be submitted for the approval of ADWEA/ADDC/AADC
and other authorities concerned.