You are on page 1of 2

DAILY REPORT

29/2/2020
daily report
1-using cutter machine for cutting saw cut for first floor for panels between
axis (14-18)& (a-c) zone 2 . and (18-20) &(a-c ) zone 1 .

2- finish shuttering and steel work for three remaining grid beem zone 1 .

3- steel fixer fix finish steel work for fourth floor between axis (12-14) & (f-d)
zone 2 . and work for fourth floor between axis (09-12) &(f-d) and (14-18 ) &(f-
d) zone 2 . and (18-20 )&(f-d) zone 1 .and for fifth floor between axis (09-22) &
(f-d) zone 1& 2 .

4- survey finish work for fourth floor between axis (12-14) & (f-d) zone 2 . and
fix level for ground floor for slab on grade work zone 2 .

5- some site cleaning and closing some openings for double T slab.

6- some painting works for the first floor sanding and put stocco on the ceiling
zone 1 . and touch up by stucco for zone 2 . and second floor sanding and put
stucco on the ceiling zone 1. and touch up by stucco for zone 2 .
7- using JCB for excavate beem for slab on grade for ground floor zone 2 .
and use it for some site cleaning .

worked Done :
1-using cutter machine for cutting saw cut for first floor for panels between
axis (14-18)& (a-c) zone 2 . and (18-20) &(a-c ) zone 1 .

2- finish shuttering and steel work for three remaining grid beem zone 1 .

3- steel fixer fix finish steel work for fourth floor between axis (12-14) & (f-d)
zone 2 .

4- survey finish work for fourth floor between axis (12-14) & (f-d) zone 2 .
Expected works:
1-casting panels between axis (9-12) &(f-d) zone 2 .in the third floor and second
floor between axis (14-18)& (a-c) zone 2 &(18-20)& (a-c) zone 1.and fourth floor
between axis (20-22)&(f-d) zone 1 . and casting three grid beem.
2-continue screed woks (steel work , survey,..).
3-continue slab on grade work for ground floor.

You might also like