Professional Documents
Culture Documents
SECTION 16950
PART 1 - GENERAL
B. In case of conflict among the referenced standards and codes, the more
stringent provision will govern.
1.4 SUBMITTALS
PART 2 - TESTING
A. The consultant shall inspect and test at the makers' works, during
manufacture and after completion, all or any particular manufactured
material, apparatus or equipment ordered by the contractor for
incorporation in the works, in order to prove that the material, apparatus
or equipment meets the requirements of this specification. The contractor
shall notify the Owner's authorized representative in advance of all such
inspections and tests.
Each such order shall clearly state whether the item(s) which it covers is
or are subject to inspection or test before despatch to site.
D. The results of each and every test carried out in accordance with the
provisions of this specification shall be accurately and comprehensively
recorded on a form of test certificate signed by the person in charge of the
testing procedure and countersigned by the contractor and four copies of
every such test certificate shall be submitted to the Owner's Authorized
Representative.
K. The Owner's Consultant shall have the right to waive, at his sole
discretion, the requirements relating to his inspection of materials,
apparatus, and equipment at the makers' works. The exercise by the
Owner's authorized Representative of this right shall not in any way
relieve the contractor of his obligation to carry out the prescribed tests
and to submit test certificates.
M. When one or more of the Contractor's purchase orders covers the supply
of a number of like components or items of equipment, the Owner's
authorized representative shall have the right to select that one item or
component of each type and rating be subjected to type tests as described
in the relevant National Standard. Other similar items may then be
subjected only to routine tests.
A. The Contractor shall carry out all necessary checks and tests to prove that
the completed installations fully comply with specified requirements.
C. All of the required checks and tests shall be carried out in accordance
with a program to be agreed with the Owner's Authorized Representative,
and facilities shall be made available for the Owner's Authorized
Representative to be present at all such checks and tests if he so desires.
G. No work shall have a final paint finish until it has been inspected by the
Owner's Authorized Representative or painting has been authorized,
unless the final paint finish is necessary to provide the necessary
climatprotection.
C. The above tests shall be carried out both before and after any voltage tests
and the insulation resistance shall not be less than the figures in British
Standard for all cables up to 11kv. The Contractor shall submit insulation
resistance figures for cables up to 11kv.
F. An earth continuity test shall be carried out to verify that the cable
armouring and metal sheath, if any, have been properly bonded to earth.
With all control circuits disconnected but with all isolators closed and
power fuses fitted, the panels shall be subjected to a voltage test across
the following points:
The voltage levels and test direction shall be in accordance with the
relevant National Standard for the equipment provided.
A. The Contractor shall inspect and carry out tests on all the system and
equipment earthing provisions in accordance with the requirements of the
IEE Wiring Regulations.
B. The method of test and the selection of suitable test instruments shall
conform to the guidelines given in the IEE Wiring Regulations, 16 th.
Edition.
C. These tests shall be carried out on all system and equipment earthing
supplied, installed and connected under this Contract.
E. The Contractor shall inspect and re-test the system and equipment
earthing provided under this Contract thirty days prior to the end of the
Defects Liability period. The Contractor shall give the Owner's
Authorized Representative seven days notice of his intent to carry out
these tests.
PART 3 - COMMISSIONING
(ii) The setting of electrical protective devices and systems, where relevant,
in accordance with the directions of the Owner's Authorized
Representative or, failing such directions, in accordance with sound
electrical engineering practice.
(iv) The verification of the performance of all such plant and equipment by
the carrying out, where required, of further tests and the making of all
necessary adjustments so as to obtain optimum performance.
B. Compliance with the requirements of this Section of the Specification shall not,
by itself, in any way relieve the Contractor of any of his obligations under the
Contract.
C. The Contractor shall ensure that all connections and adjustments are made
correctly, and that the installations and equipment are in a completely safe and
satisfactory condition.
G. The Contractor shall be wholly responsible for ensuring that all switching
operations and all work on electrical circuits and equipment which have once
been energized are carried out in a thoroughly safe manner and shall operate, and
rigidly adhere to, an approved 'permit-to-work' system. For this purpose, the
Contractor shall appoint an 'authorized person' as defined in the Electricity
(Factories Act) Special Regulations, and shall communicate the name of such
person in writing to the Owner's Authorized Representative.
Q. The Owner's Authorized Representative shall have power to require that the hole
of the plant, equipment and installations, or selected parts thereof, be re-inspected
and, if necessary, re-tested immediately before the end of the contractual
maintenance period, and the Contractor shall be responsible for making all
necessary arrangements with the Owner.