Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and

Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

Spec Section Description of Requirement Shop Drawing # & Status


B. Field Service shall be provided by an authorized,
factory trained representative of the Pump
Manufacturer. Services shall include, but not
necessarily be limited to, inspection of the
completed installation to ensure that it has been
performed in accordance with the manufacturer’s
instructions and recommendations, supervision of
all field-testing and activation of the
Manufacturer’s Prescribed Warranties.
C. The Contractor shall be responsible for
coordinating the required field services with the
Pump Manufacturer. The manufacturer shall be
responsible for checking power cables, seal
lubrication, proper rotation, power supply voltage
Close Coupled Pumping and amperage draw and general pump operation.
Equipment Minimum manufacturer field visits shall include
the following individual visits:
11312-1.8.A-C 1. One (1) Day – Installation Assistance
2. One (1) Day – Installation Inspection
3. Two (2) Days – Contractor Testing
(Operational Testing per Section 01650)
4. Two (2) Days – Owner Testing/Training (to be
held on a separate day from the Contractor
Testing). Manufacturer’s representative will
be required through written notice to the
Engineer that they have completed
Contractor Testing and found the pumping
equipment to be fully operational in
accordance with the Contract Documents
prior to scheduling Owner Testing (Final
Acceptance Testing per Section 01650).
including Electrical and Controls.
H. After installation, an Operational Testing shall be
Close Coupled Pumping performed jointly by the supplier and installer on
Equipment each installed pump. The pump manufacturer’s
11312-3.2.H authorized representative shall be present for the
field test…
Product Delivery, Storage A. General:
and Handling 1. Provide manufacturer’s field services in
accordance with this subsection for those tasks
01600-1.7.A-D specified in other Sections.
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22
2. Provide training as specified in other Sections.
3. Include and pay all costs for suppliers’ and
manufacturers’ services, including, but not
limited to, those specified.
1) That equipment is installed in
accordance with the manufacturers’
recommendations, approved shop
drawings and the Contract
Documents.
2) That nothing in the installation voids
any warranty.
3) That equipment has been operated in
the presence of the manufacturer’s
representative.
4) That equipment, as installed, is ready
to be operated by others.
B. Installation Instruction: Provide instruction by
competent and experienced technical
representatives of equipment manufacturers or
system suppliers as necessary to resolve assembly
or installation procedures which are attributable
to, or associated with, the equipment furnished.
2. Provide manufacturer’s representatives to
perform initial equipment and system
adjustment and calibration conforming to the
manufacturer’s recommendations and
instructions, approved shop drawings and the
Contract Documents.
3. Obtain Owner’s approval before start-up of
equipment. Execute start-up under supervision
of applicable manufacturer’s representative in
accordance with manufacturers’ instructions.
4. Furnish Engineer with three copies of the
following: When training is specified, furnish the
copies at least 24 hours prior to training.
a. “Certificate of Installation, Inspection and
Start-up Services” by manufacturers’
representatives for each piece of equipment
and each system specified, certifying:
b. Detailed report by manufacturers’
representatives, for review by Engineer of
the installation, inspection and start-up
services performed, including:
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22
1) Description of calibration and adjustments
if made; if not in Operation and
Maintenance Manuals, attach copy.
2) Description of any parts replaced and why
replaced.
3) Type, brand name, and quantity of
lubrication used, if any.
4) General condition of equipment.
5) Description of problems encountered, and
corrective action taken.
6) Any special instructions left with
Contractor or Engineer.
D. Field Test Participation: Provide competent and
experienced technical representatives of all
equipment manufacturers and system suppliers
as necessary to participate in field testing of the
equipment.
E. Trouble-Free Operation: Provide competent and
experienced technical representatives of all
equipment manufactures and system suppliers as
necessary to place the equipment in trouble-free
operation after completion of start-up and field
tests.
B. Site Visit: Provide the services of an authorized
service representative for each equipment
manufacturer or system supplier to make a final
site visit after the equipment or system has been
in operation for at least 6 months, but no longer
Product Delivery, Storage
than 11 months. Furnish assistance to Owner’s
and Handling
operating personnel in making adjustments and
calibrations required to determine that the
01600-1.8.B
equipment and system is operating in
conformance with design, manufacturers, and
Specification requirements. Instruct the personnel
in a review of proper operation and maintenance
procedures.
D. Personnel Training:
1. Conduct all personnel training after completion
of Initial Equipment Start-up for the equipment
for which training is being conducted.
a. Personnel training on individual equipment
or systems will not be considered
completed unless:
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22
1) All pretraining deliverables are
received and approved before
commencement of training on the
individual equipment or system.
2) No system malfunctions occur during
training.
3) All provisions of field and classroom
training specifications are met.
b. Training not in compliance with the above will be
performed again in its entirety by the
manufacturer at no additional cost to the Owner.
Replace proposed training instructor if not
acceptable to the Owner or Engineer.
c. Organize training sessions as shown in the Training
Schedule (Operations, Maintenance and Electrical
/ Instrumentation and Control). Provide general
training to all sessions as part of the specific
training required for each group. Training
material and sessions shall be specifically
developed and tailored to the group being
trained.
d. Plan for minimum class attendance of 12 people at
each session and provide sufficient classroom
materials, samples, and handouts for those in
attendance.
e. Instructors to have a typed agenda, outline and
well prepared instructional material. The use of
visual aids, e.g., films, pictures, and slides is
recommended for use during the classroom
training programs. Submit proposed training
agendas and outlines to the Owner and Engineer
for approval a minimum of 15 business days prior
to the training. Revise until acceptable. Provide
equipment required for presentation of films,
slides, and other visual aids. Training materials
shall be related to the specific equipment; general
sales brochures are not acceptable.
f. In the on-site training sessions, cover the
information required in the Operation and
Maintenance manuals and the following areas as
applicable to the PCS.
1) Operation of equipment.
2) Lubrication of equipment.
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22
3) Maintenance and repair of equipment.
4) Troubleshooting of equipment.
5) Preventive maintenance procedures.
6) Adjustments to equipment.
7) Inventory of spare parts.
8) Optimizing equipment performance.
9) Capabilities.
10) Operational safety.
11) Emergency situation response.
12) Takedown procedures (disassembly and
assembly).
g. Maintain a log of classroom training provided
including: Instructors, topics, dates, time, and
attendance.
h. Provide an electronic copy (pdf or PowerPoint
format) of the training handouts.
Shoring A. Provide surveys to monitor movements of critical
02151-1.3.A facilities.
A. The Contractor shall retain the services of an
independent Professional Engineer registered in
the State of Virginia who is experienced with
grouted helical pull-down pier foundations to act
as the Contractor's representative responsible for
conducting soil boring, test pile installation, load
testing and observing all job pile installation. The
Engineer shall assist the Owner in determination
of the depth and torque required to achieve the
indicated pile capacities in compression based on
Helical Pulldown Piers
the soil boring, test pile installation records and
load test data. After determination of the
02370-3.1.A
installation depth required for the job pile and
Owner approval, the Owner shall observe the
installation of all job piles to ensure compliance
with the drawings and specifications. The
Engineer shall notify the Owner 14 days in
advance of the anticipated test pile installation,
and shall meet and consult with the Owner when
requested, either during the work or subsequent
there to, for the purpose of discussing the pile
installation.
Soil Stabilization A. A qualified Manufacturer's field representative
shall be on-site at the start of construction to
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22
02780-3.3.A-B observe the installation of the porous pavement
system is in accordance with the Contract
Documents and Manufacturer's
recommendations.
B. The time for on-site observation shall be indicated
in the Contract Documents and included in the
base bid price.
A. Engage a full time site representative qualified by
the waterproofing membrane manufacturer to
inspect substrate conditions, surface preparation,
and application of the membrane, flashings,
protection, and drainage components; and to
furnish daily reports to Architect.
Cold Fluid-Applied
Waterproofing 4. Closeout Documents: Submitted upon Project
07141-3.8.A completion and prior to final payment.
a. Submit a letter from the CSM indicating that a
representative portion of all major steps in
the coating Work were inspected by the CSM
and that all that work was performed in
accordance with the CSM’s
recommendations and instructions.
A. The Contractor shall provide the services of a
factory trained representative of the sluice gate
manufacturer to assist in installation and testing
of the sluice gate. Provision shall be made for a
Sluice Gate minimum of two (2) visits of not less than two (2)
hours each on site. The first visit shall be to assist
11283 – 3.4.A the Contractor in proper installation. The second
shall be to verify proper operation and inspect the
installation. The Contractor shall be responsible
for scheduling with the Owner, HRSD
Representative, and the manufacturer.
B. Field Service shall be provided by an
authorized, factory trained representative of
Close Coupled Pumping the Pump Manufacturer. Services shall
Equipment include, but not necessarily be limited to,
inspection of the completed installation to
11312- 1.8.B ensure that it has been performed in
accordance with the manufacturer’s
instructions and recommendations,
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

supervision of all field-testing and activation


of the Manufacturer’s Prescribed Warranties.
C. The Contractor shall be responsible for
coordinating the required field services with
the Pump Manufacturer. The manufacturer
shall be responsible for checking power
cables, seal lubrication, proper rotation,
power supply voltage and amperage draw
and general pump operation. Minimum
manufacturer field visits shall include the
following individual visits:
1. One (1) Day – Installation Assistance
2. One (1) Day – Installation Inspection,
Close Coupled Pumping including Electrical and Controls
Equipment
3. Two (2) Days – Contractor Testing
11312- 1.8.C.1-4 (Operational Testing per Section 01650)
4. Two (2) Days – Owner Testing/Training
(to be held on a separate day from the
Contractor Testing). Manufacturer’s
representative will be required through
written notice to the Engineer that they
have completed Contractor Testing and
found the pumping equipment to be fully
operational in accordance with the
Contract Documents prior to scheduling
Owner Testing (Final Acceptance Testing
per Section 01650).
A. Pumps shall be protected against corrosion at
the factory for the period between shipment
and installation. All equipment delivered and
placed in storage shall be stored with
protection from the weather, excessive
Sump Pump
humidity and excessive temperature
11330 - 1.6.A
variation; and dirt, dust, or other
contaminants. All machined surfaces shall be
slushed with heavy, non-corrosive oil, and all
bearings shall be lubricated. If the pumps are
to be stored for more than 90 days, the
interior of the pump shall be filled with a
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

high-grade non-corrosive oil, and all bearings


shall be lubricated. The Contractor shall
inspect the stored pumps weekly, manually
rotate or slide all moving parts, and renew
the slush oil as necessary. Before the pumps
are put into operation, they shall be cleaned.
Failure to maintain the pumps in like-new
condition during storage and installation will
be cause for rejection of the pumps.
A. The Contractor shall furnish the services of
the tank and leak sensor manufacturer’s
qualified field representative to inspect the
Fuel Supply System equipment after installation, instruct Owner’s
personnel in its operation and maintenance,
11500 - 1.6.A and supervise its initial operation for a
minimum of two 8 hour days
(nonconsecutive) as specified under Section
01340 – SUBMITTALS.
A. Installation of all equipment shall be in strict
accordance with the manufacturer's
recommendations as approved by the
OWNER and National Fire Protection
Association, Underwriters Laboratories, State
Fuel Supply System and Local applicable codes and ordinances.
Contractor shall furnish services of the
11500 – 3.1.A manufacturer's technical representative to
supervise the initial phase of setting and
aligning of the equipment; and after the
installation is completed for start-up, testing
and to instruct the OWNER in proper
maintenance.
2. A representative of the Manufacturer who has
thorough knowledge of proper operation and
Odor Control Biotrickling maintenance shall be provided for three
Filter System eight-hour days to inspect the installation,
perform startup operations and instruct
11585 – 1.4.D.2 representatives of the OWNER on proper
operation and maintenance at the same time
as start-up and perform odor sampling. Each
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

site visit trip shall be scheduled separately,


independent of other visits.
A factory representative who has a complete
knowledge of the proper operation and
maintenance shall be provided as specified
herein. Qualifications of the representative shall
be submitted for approval. Workday
requirements listed are exclusive of travel time
Odor Control Biotrickling
and do not relieve the Contractor of obligation
Filter System
to provide sufficient service to place equipment
11585 – 1.6.B in satisfactory operation. The factory
representative shall provide a minimum of two
(2) training sessions (typically early morning and
late evening) to accommodate plant staff.
Owner and Engineer shall be notified in writing a
minimum of fourteen (14) calendar days prior to
the scheduled training.
A. …Manufacturer shall retain the services of an
Odor Control Biotrickling independent inspector who is responsible to
Filter System confirm the prefilter has been manufactured
in accordance with this specification and all
11585-2.14.A FRP work meets or exceeds ASME RTP-1 level
2 visual inspection criteria…
A. The manufacturer shall furnish field services
in accordance with the following:
1. A minimum of one (1) day field services to
Odor Control Biotrickling inspect the installation and observe
Filter System
Contractor Operational Testing.
11585 – 3.1.A.1-2
2. A minimum of one (1) day field services to
complete Acceptance Testing and
provide operation and training.
(See Specification Section for details)
Odor Control Biotrickling …The manufacturer or Authorized
Filter System Representative shall have a technical
representative, who is experienced in installing
11585 – 3.1.C the equipment, on-site at the time of
installation.
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

Odor Control Biotrickling E…At the discretion of the manufacturer, a


Filter System manufacturer's technical representative may
11585 – 3.1.E be present during the installation.
C. CPS shall observe installation of, or inspect
Cathodic Protection
following installation, all equipment required
13110-3.1.C
by this section. CPS to provide written
certification of successful installation.
1. CPS to determine location of test stations
Cathodic Protection
based on actual site conditions and as shown
13110-3.2.C.1
on project plans.
F. Insulated Joint Testing:
Cathodic Protection 1. Test each insulation joint after assembly CPS
shall monitor the tests. Contractor shall
13110-3.2.F.1 replace damaged or defective insulation
parts at no cost to the Owner.
1. Provide CPS to visit site throughout
installation of the basic corrosion monitoring
system including, pipe joint bonds, insulating
flanges and couplings, test stations, reference
Cathodic Protection
electrodes, and other system components.
13110-3.4.A.1
CPS shall be responsible for certifying
compliance with these specifications, and for
observation and testing services. Certification
shall be submitted to the Engineer and Owner
for the project record.
2. The CPS shall visit the site during the
installation of the galvanic anode system and
Cathodic Protection shall be responsible for certifying compliance
with these specifications and the design
13110-3.4.A.2 provided. Certification shall be submitted to
the Owner and Engineer as part of the project
record.
Cathodic Protection
c. Have CPS monitor tests of bonded joints.
13110-3.4.A.4.c
Bridge Crane A. The crane manufacturer must provide
14534-3.2.A supervisory erection services.
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

Under each applicable section of the detailed


mechanical specifications, the Contractor shall
instruct the representative of the Owner in the
proper operation and maintenance of all
elements of the mechanical systems. A
Basic Mechanical competent representative of the Contractor
Materials and Methods shall spend not less than two days in such formal
instruction and shall spend such additional time
15050 – 3.12.A as directed by the Engineer to fully prepare the
Owner to operate and maintain the mechanical
systems. The Contractor shall provide letter of
instruction upon completion to the Engineer
stating the date of instruction and the names of
those in attendance.
A. Field services for valves shall be coordinated
by the Contractor.
B. Provide the following services for each
different type of valve:
1. Inspect, test, calibrate, and adjust all
Interior Valves and equipment.
Related Products 2. Certify that the equipment installation is
complete and ready for operation.
15280-3.3.A-B
3. Adjust positioners and actuators for proper
control.
4. Correct any malfunctions appearing during
the testing by replacement of defective
components or adjustments of maladjusted
parts and equipment.
(See Specification Section for
Fiberglass Reinforced details)…CONTRACTOR shall obtain training by
Plastic Duct the pipe manufacturer’s field representative in
15892-3.2.A.1 the correct installation and support of all FRP
piping.
Fiberglass Reinforced A. Manufacturer’s Representative: Present at
Plastic Duct Site or classroom designated by Owner, for
minimum person-days listed below, travel
15892-3.6.A-B time excluded:
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

1. 1 person-days for installation assistance,


including pre-installation training of
Contractor personnel in joint assembly and
inspection.
2. 1 person-days for functional testing and
completion of Manufacturer’s Certificate
of Proper Installation.
B. Refer to Division 1.
L. A factory representative for the main
distribution switchboard shall be present
General Requirements – when the Contractor adjusts, tests and
Electrical calibrates devices as required in the field
after the installation is complete. The number
16010-3.2.L of days required to do this work shall be the
manufacturer's responsibility and shall be
included in the bid.
4. The Supplier shall be a factory trained and
certified manufacturer's representative and
shall maintain a complete service facility. The
service facility shall be capable of making
delivery to the generator set site all generator
Emergency Generator
set parts within 48 hours of placing the order.
System
The Supplier shall employ a manufacturer
16230-1.2.B.4 trained and certified technician on a full-time
basis at the service facility capable of making
repairs and responding to service calls within
24 hours of notice. Certified proof of this
requirement shall be available from the
Supplier.
K. Diagnostic Software:
1. Provide diagnostic software and all
Emergency Generator required cables for the engine and the
System generator. Software shall be furnished on a
CD.
16230-2.1.K.1-2
2. Provide four (4) hours of training on the
use of the diagnostic software.
Emergency Generator A. The manufacturer of the emergency
System generating equipment shall furnish a qualified
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

technician, whose qualifications are


16230-3.1.A-B acceptable to the Owner, to provide the
following services:
1. Inspection of the installation of the
generator system complete
2. Start-up
3. Performance testing
4. Operating adjustments
5. Instruction of Owner's personnel
6. Assistance at final inspection
B. These services shall include not less than two
(2) 8-hour workdays on-site comprising a
minimum of two trips.
B. Training:
1. Provide eight (8) hours of training on the
switchboard including operation of circuit
Main Distribution breakers, power monitor, surge protective
Switchboard device, and automatic transfer switch.
2. Training shall be conducted on two (2)
16315-3.2.B.1-2 separate days with four (4) hours of
training being provided on each day.
Training shall be performed by a qualified
manufacturer's representative.
A. System Installation:
1. The System Supplier shall provide on-site
supervision and advice to the installing
contractor to ensure the system is installed
Process Control System in accordance with the specifications and
General Requirements the manufacturer's requirements.
2. All field wiring to the equipment furnished by
17010-3.3.A & C the System Supplier shall be performed under
the electrical portion of the Contract unless
(See Specification Section noted otherwise on the Drawings.
for details)
C. System Commissioning:
2. The System Supplier shall include in their
cost for this Contract a minimum of 24
hours for the commissioning of the scenario
described in Section 17500.
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

3. The System Supplier shall provide two


people on-site for the length of time
necessary for system installation, start-up,
and commissioning.
A. During the final acceptance test, the System
Supplier shall arrange for the instruction and
training of District personnel at the pump
Process Control System station site in the operational procedures of
General Requirements the system. At the end of this period, District
personnel shall have, as determined by the
17010-3.5.A Engineer, sufficient knowledge to operate the
system. This training shall consist of two (2)
(See Specification Section hour training sessions with each session being
for details) attended by six individuals from the District.
This training shall be in addition to the
training specified in the other Division 17
sections.
A. Testing:
1. Contractor shall have a factory-authorized
representative present with required test
equipment to test the ground fault
protection devices and explain the
operation in the presence of the Owner and
submit results of the test in writing.
B. Training:
Motor Control Center 1. Provide eight (8) hours of training on the
motor control center including operation of
17100-3.2.A-B circuit breakers, power monitor, surge
protective device, and automatic transfer
switch.
2. Training shall be conducted on two (2)
separate days with four (4) hours of training
being provided on each day. Training shall
be performed by a qualified manufacturer's
representative.

Variable Frequency
B. 24-hour technical support shall be provided at
Drives
17110-1.5.B
no additional cost.
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

A. Start-up and Testing:


1. Provide the services of a manufacturer's
representative to program, start-up, adjust
and test each variable frequency drive.
Demonstrate start/stop control, fault
diagnostics and variation of motor speeds in
response to both the manual and automatic
variable speed controls.
2. All start-up and testing shall be performed
by an authorized manufacturer's
Variable Frequency representative, and shall be performed in
Drives the presence of the Owner and the
Engineer.
17110-3.1.A-B B. Training:
1. Provide eight (8) hours of on-site training on
the variable frequency drives. Training shall
be specific for the VFDs provided and shall
include theory of operation, maintenance,
and troubleshooting procedures.
2. Training shall be conducted on two separate
days, with four (4) hours of training being
performed each day. All training shall be
performed by a qualified training specialist
from the VFD manufacturer.
B. Training:
Control Panels
1. Provide four (4) hours of training for the
17200-3.1.B.1
Owner on the control panels. Training shall
be conducted at the station.
A. Provide the services of manufacturer’s service
representatives to assist in installation for all
instrumentation specified herein.
B. Each manufacturer’s representative shall
Instrumentation
inspect the installation of each of their
17300-3.1.A-B
instruments and shall issue an installation
certificate to the Owner and the Engineer for
each instrument certifying that the
instrument has been installed in accordance
with the manufacturer’s recommendations.
Willard Avenue Pump Station Replacement (BH013020/VCWRLF NO C-515663G) and
Hampton Trunk Sewer Extension Division K Gravity Improvements (BH014900/VCWRLF NO C-515663G)

Training, Manufacturers Representative & Storage Requirements per Conformed


Specifications Date 7-23-22

A. Provide the services of manufacturer's service


representatives to calibrate all
instrumentation provided. All calibration shall
Instrumentation
be performed in the presence of the Owner
17300-3.2.A
and the Engineer. The calibration of each
instrument shall be performed after the
instrument installation certificate has been
issued.
A. Provide eight (8) hours of training on the
instrumentation provided. Training shall be
performed on two separate days with four (4)
hours of training being provided on each day.
Instrumentation B. All training shall be performed by a
representative from the manufacturer and
17300-3.3.A-B shall be specific to the instruments provided.
Training shall include theory of operation,
maintenance requirements, calibration
methods and function of instrument in the
Process Control System.
A. On-Site Training:
Programmable Controller 1. Provide two (2) hours of training for the
System Owner on the operation of the PLC System
and the operator interface terminal.
17400-3.3.A.1 Training shall be conducted at the pump
station.