BACKUP DATA

PEKERJAAN : PERENCANAAN PEMBUATAN RUANG ARSIP DINAS


LOKASI : KOTA BARU, KEC. KUTA ALAM, KOTA BANDA ACEH

DIVISI : PEKERJAAN TANAH


PEKERJAAN : GALIAN TANAH PONDASI

DETAIL PONDASI POT 1 DETAIL PONDASI POT 2


SKALA 1:20 SKALA 1:20

DIMENSI VOLUME
UNIT PEKERJAAN UNIT
P (m) L (m) T (m) (m3)

GALIAN TANAH 57.50 0.70 0.55 1.00 22.14

URUGAN PASIR
57.50 0.70 0.05 1.00 2.01
BAWAH PONDASI

AANSTAMPING 57.50 0.70 0.13 1.00 5.23

PONDASI BATU
57.50 0.50 0.43 1.00 12.22
KALI

BERAT TOTAL
UNIT PEKERJAAN DIA BESI SPACE PANJANG UNIT
(Kg/m) PANJANG

POLOS 12 mm 12.00 1000.00 0.88 0.600 57 34.20

TIMBUNAN TANAH
7.25 6.00 0.70 1.00 30.45
EL. -0.2 m
TIMBUNAN TANAH
1.75 2.75 0.60 1.00 2.89
EL. -0.3 m
TIMBUNAN TANAH
1.25 8.50 0.60 2.00 12.75
EL. -0.3 m
TIMBUNAN TANAH
1.50 6.00 0.60 2.00 10.80
EL. -0.3 m
TOTAL VOLUME TIMBUNAN 56.89

PASIR URUG
BAWAH LANTAI 7.25 6.00 0.10 1.00 4.35
EL. -0.2
PASIR URUGm
BAWAH LANTAI 1.75 2.75 0.10 1.00 0.48
EL. -0.3 m
PASIR URUG
BAWAH LANTAI 1.25 8.50 0.10 2.00 2.13
EL. -0.3
PASIR URUGm
BAWAH LANTAI 1.50 6.00 0.10 2.00 1.80
EL. -0.3 m
TOTAL VOLUME PASIR URUG BAWAH LANTAI 8.76

BETON COR t = 5
7.25 6.00 0.05 1.00 2.18
cm EL. -0.2 m
BETON COR t = 5
1.75 2.75 0.05 1.00 0.24
cm EL. -0.3 m
BETON COR t = 5
1.25 8.50 0.05 2.00 1.06
cm EL. -0.3 m
BETON COR t = 5
1.50 6.00 0.05 2.00 0.90
cm EL. -0.3 m
TOTAL VOLUME BETON COR t= 5 Cm 4.38

SL1 (15/25)

DIMENSI VOLUME
UNIT PEKERJAAN UNIT
P (m) L (m) T (m) (m3)
BETON K-125 89.50 0.15 0.25 1.00 3.36
BEKISTING (3 KALI
89.50 0.15 0.25 1.00 14.94
PAKAI)

BERAT TOTAL
UNIT PEKERJAAN DIA BESI SPACE PANJANG UNIT
(Kg/m) PANJANG

POLOS 12 mm 12.00 0.88 89.50 6.00 537.00


POLOS 10 mm 10.00 100.00 0.61 0.810 895 724.95
TOTAL VOLUME BESI SL1 (15/25)
KOLOM K1 (13 X 24 )

DIMENSI VOLUME
UNIT PEKERJAAN UNIT
P (m) L (m) T (m) (m3)
BETON K-250 0.19 0.19 4.65 4.00 0.64
BEKISTING (3 KALI
0.19 0.19 4.65 1.33 4.59
PAKAI)

BERAT TOTAL
UNIT PEKERJAAN DIA BESI SPACE PANJANG UNIT
(Kg/m) PANJANG

POLOS 12 mm 12.00 0.88 4.95 32.00 158.40


POLOS 10 mm 10.00 100.00 0.61 0.750 46 34.50
TOTAL VOLUME BESI K1

KOLOM KP (13 X 13 )

DIMENSI VOLUME
UNIT PEKERJAAN UNIT
P (m) L (m) T (m) (m3)
BETON K-125 0.13 0.13 4.65 10.00 0.79
BETON K-125 0.13 0.13 2.55 12.00 0.52
TOTAL VOLUME BETON 1.30
BEKISTING (3 KALI
0.13 0.13 4.65 3.33 8.06
PAKAI)
BEKISTING (3 KALI
0.13 0.13 2.55 4.00 5.30
PAKAI)
TOTAL VOLUME BEKISTING 13.36

BERAT TOTAL
UNIT PEKERJAAN DIA BESI SPACE PANJANG UNIT
(Kg/m) PANJANG

POLOS 12 mm 12.00 0.88 4.95 80.00 396.00


POLOS 10 mm 10.00 100.00 0.61 0.530 92 48.76
POLOS 12 mm 12.00 0.88 2.85 48.00 136.80
POLOS 10 mm 10.00 100.00 0.61 0.530 25 13.25
TOTAL VOLUME BESI KP
BALOK LATAI BLT (12/15)

DIMENSI VOLUME
UNIT PEKERJAAN UNIT
P (m) L (m) T (m) (m3)
BETON K-125 17.50 0.12 0.15 1.00 0.32
BEKISTING (3 KALI
17.50 0.12 0.15 1.00 1.76
PAKAI)

BERAT TOTAL
UNIT PEKERJAAN DIA BESI SPACE PANJANG UNIT
(Kg/m) PANJANG

POLOS 10 mm 10.00 0.61 17.50 4.00 70.00


POLOS 6 mm 6.00 100.00 0.22 0.550 116 63.80
POLOS 6 mm 6.00 150.00 0.22 0.550 39 21.45
TOTAL VOLUME BESI BLT (12/15)
RING BALK RB2 (15/20)

DIMENSI VOLUME
UNIT PEKERJAAN UNIT
P (m) L (m) T (m) (m3)
BETON K-125 67.00 0.15 0.20 1.00 2.01
BEKISTING (3 KALI
67.00 0.15 0.20 1.00 8.95
PAKAI)

BERAT TOTAL
UNIT PEKERJAAN DIA BESI SPACE PANJANG UNIT
(Kg/m) PANJANG

POLOS 12 mm 12.00 0.88 67.00 4.00 268.00


POLOS 10 mm 10.00 100.00 0.61 0.710 446 316.66
POLOS 10 mm 10.00 150.00 0.61 0.710 149 105.79
TOTAL VOLUME BESI BLT (12/15)

Ø10-200 Ø10-200
Ø10-200 Ø10-200
Ø10-200
Ø10-200

Ø10-200
Ø10-200

PLAT DAK BETON t=10cm

DIMENSI VOLUME
UNIT PEKERJAAN UNIT
P (m) L (m) T (m) (m3)
BETON K-125 4.25 3.00 0.10 2.00 2.55
BEKISTING (3 KALI
4.25 3.00 0.10 1.00 4.25
PAKAI)

BERAT TOTAL
UNIT PEKERJAAN DIA BESI SPACE PANJANG UNIT
(Kg/m) PANJANG

POLOS 10 mm 10.00 200.00 0.61 3.000 84 252.00


POLOS 10 mm 10.00 200.00 0.61 4.250 60 255.00
TOTAL VOLUME BESI BLT (12/15)

PEKERJAAN
DINDING 1:4

DIMENSI VOLUME
VOLUME
UNIT PEKERJAAN UNIT TOTAL
P (m) L (m) T (m) (m2)
UNIT
DR1 1.80 3.00 1.00 5.40 5.40
DR2 0.80 3.00 2.00 2.40 4.80
DR3 1.20 1.20 2.00 1.44 2.88
DR4 0.80 0.40 2.00 0.32 0.64
PJ1 3.05 2.20 2.00 6.71 13.42
P2 0.80 2.20 2.00 1.76 3.52
PJ3 3.05 2.20 2.00 6.71 13.42
P1 0.80 2.20 2.00 1.76 3.52
P3 0.80 2.20 2.00 1.76 3.52

AREA SHALAT PASS 1:4


UNIT
A 10.00 4.45 1.00 44.50
B 1.50 4.45 1.00 6.68
C 5.75 4.45 1.00 25.59
D 6.00 4.45 1.00 26.70
VOLUME AREA SHLAT
UNIT
1 =A 1.00 44.50
2 = B - P1 2.00 9.83
3 = C - PJ2 - DR2 2.00 32.96
4 = D - PJ3 - DR1 - DR3 1.00 13.15
TOTAL PASANGAN BATA 1:4 AREA SHALAT 100.44

KAMAR MANDI UNIT


A 1.75 2.35 1.00 4.11
B 1.75 2.35 1.00 4.11
C 1.75 2.35 1.00 4.11
D 4.25 2.35 1.00 9.99
E 4.25 2.35 1.00 9.99

VOLUME KAMAR MANDI


UNIT
1 = A - DR4 2.00 7.58
2 = B - DR3 2.00 5.35
3 = C - P3 2.00 4.70
4 = D - P2 2.00 16.46
5=E 2.00 19.98
VOLUME PASANGAN BATA 54.07

PASANGAN BATA 1:2


1.00 7.58
2.00 3.15
3.00 1.71
4.00 6.21
5.00 19.98
TOTAL PASANGAN BATA 1:2 38.63
TOTAL PASANGAN BATA 1:4 115.87

VOLUME PLASTERAN 1:4 231.74


VOLUME PLASTERAN 1:2 77.26
PASANGAN KERAMIK DINDING KERAM WUDUK 4.95
ACIAN 304.05
KERAMIK
TOTAL
UNPOLISHED 40 X LUAS UNIT
LUAS
40
SELASAR 31.50 1.00 31.50
KAMAR MANDI 4.92 2.00 9.84
TOTAL KERAMIK UNPOLISED 40 X 40 41.34

GRANITE 60 X 60 TOTAL
LUAS UNIT
POLISHED LUAS
41.13 1.00 41.13
TOTAL GRANITE 60 X 60 POLISHED 41.13

KERAMIK
UNPOLISHED 25 X
25
KLOSET 0.56 2.00 1.12
TOTAL KERAMIK UNPOLISHED 25 X 25 1.12
PEKERJAAN ATAP DAN PLAFOND
TOTAL
UNIT
LUAS
RANGKA ATAP FURING 8.50 9.75 1.00 82.88

PENUTUP ATAP
8.50 9.75 1.00 82.88
GENTENG MONIER

RABUNG 5.40 1.00 4.00 21.60


Listplank GRC Terpasang 8.50 9.75 2.00 36.50
PLAFOND GYPSUM 8.50 9.75 1.00 82.88
TOTAL
BERAT
(Kg)
30.10
TOTAL
BERAT
(Kg)
472.56
442.22
914.78
TOTAL
BERAT
(Kg)
139.39
21.04
160.44

TOTAL
BERAT KETERANGAN
(Kg)
348.48
TINGGI 4,65 m
29.74
120.38
TINGGI 2,55 m
8.08
506.69
TOTAL
BERAT KETERANGAN
(Kg)
42.70 POKOK
14.04 TUMPUAN
4.72 LAPANGAN
61.45
TOTAL
BERAT KETERANGAN
(Kg)
235.84 POKOK
193.16 TUMPUAN
64.53 LAPANGAN
493.53

Ø10-200
Ø10-200
Ø10-200
Ø10-200
TOTAL
BERAT KETERANGAN
(Kg)
153.72 ARAH X
155.55 ARAH Y
309.27