Estimation in terms of time:

For this project, the DIVI Theme will be used. Leaving two days between delivery and start date for client
check and to discuss next phases.

First Milestone – 8 – 9 days. Start: Monday, July 11 th – End: Thursday, July 19th.

ITEM DATE QA
Homepage design (Except services, membership,
search locations functionality)
Inside TGP page
Testimonials
Brands
Blog pages (Listing & single page)
Contact US page
Careers page with from
Terms & conditions
Privacy Policy

Kayla will be doing testing on each item as each item is delivered.

Second Milestone – 5 – 6 days. Start: Monday, July 18 th – End Monday, July 30th.

ITEM DELIVERY DATE QA


Registration
Login
Forgot password
Book now popup
Newsletter subscription
Donation page with the form
Tweets widget on the blog listing space

Third Milestone – 8 – 10 days. Start: Thursday, August 2 nd – End Wednesday, August 15th.

ITEM DELIVERY DATE QA


Woo commerce integration on Wordpress
Service page: product listing per category
Service book functionality
Service / product search filter (location, prices…)
Cart page
Checkout page
Success order page
Fourth Milestone – 2 days. Start: Monday, August 20 th – End Wednesday, August 22nd.

ITEM DELIVERY DATE QA


Shop page: e-gift management & purchasing
functionality
Shop page: search product functionality.
Location page: search based on state, city and
service type.
Location page: single service view detail page with
owner info and Google map.
Location page: booking service functionality

Fifth Milestone – 4 days. Start: Monday, August 27 th – End Thursday, August 30th.

ITEM DELIVERY DATE QA


Membership functionality: membership pop=up and
purchasing process
Membership page: rewards functionality like referral
credit and 5% credit
Membership backend management if membership
process will be integrated by custom code
Location page: single service view detail page with
owner info and Google map.
Location page: booking service functionality

Sixth Milestone – 4 days. Start: Tuesday, September 4 th – End: Friday, September 7th.

ITEM DELIVERY DATE QA


Make all pages responsive

Seventh Milestone – 1 day. Start: Tuesday, September 11th – End: Tuesday, September 11th.

ITEM DELIVERY DATE QA


Deploy on client’s server