Professional Documents
Culture Documents
DAVID W. JOHNSTON
Edward I. Weisiger Distinguished Professor Emeritus
8'hEdition
First Printing: August 2014
Second Printing: December 2014
Printed in Chelsea, Michigan
ISBN 978-0-87031-912-9
Copyright© 2014 by the American Concrete Institute.
All rights reserved.
This eighth edition has been revised to agree with NGuide to Formwork for Concrete (ACI
347R-14),"which is reprinted in full in the appendix. Other revisions have been made
for consistency with ACI documents undergoing revision since previous editions of this
manual were issued. Wood design stresses and procedures have been updated to agree
with the 2012 National Design Specification" issued by the American Wood Council."
The drawings and examples in this book are based on typical designs and should not be
used as working drawings or in place of making calculations for a particular project. They
are intended to be helpful in the preparation of complete formwork plans that should be
adapted to local conditions and comply with all applicable legal requirements. In no way
is this book able to, or intended to, supplant the qualified designer or engineer to whom
formwork should be entrusted.
limitations of space and time make it impossible to show all of the methods, materials,
and products available for formwork construction. Omission of any item therefore should
not be regarded as a judgment that it is inferior or unsuitable.
�� - - r --
�
�;q-=l
.....��,. ___,
'RA' OUTSIOE-4
I'!UJIIUNlYW"" I'NIH EUY
,,.._,.-0'
FOREWORD
Following in the footsteps of Mary K. Hurd is a challenge. My respect for her knowledge
of formwork included recent decades of interaction with her on ACI Committee 347, but
also extended back to my days as a student specializing in construction engineering and
structural engineering. In 1965, I encountered the first edition of Formwork for Concrete
as a construction engineering undergraduate student at North Carolina State Univer
sity. During my years in industry and later as a faculty member, my appreciation of her
pioneering and dedicated work on Formwork for Concrete and her contributions to ACI
Committee347 continued to grow.
The eighth edition, as all previous editions, follows the most recent guidelines estab
lished by ACI Committee347 and documented in the committee report, now ACI347R-
14, which is reprinted in full in the appendix. This new edition of Formwork for Concrete
considers the updated lateral pressure provisions now provided by ACI347. Expanded
coverage is provided for wind loads, analysis of the shoring and reshoring process,
evaluation of concrete and structure strength to withstand shoring loads, and design of
shoring and bracing elements.This edition also reflects the latest changes in wood design
recommendations of the American Wood Council and introduces LRFD in addition to the
primary coverage based on ASD procedures. The recent recommendations of other ACI
committees have also been considered in the manual revisions and some related provi
sions of ACI318 and OSHA have been extracted for convenient reference in the appendix.
The growing number of standards related to design of the construction process and
design of temporary structures, as well as a number of formwork industry products and
practices adopted since the last edition was published, have been considered during
development of the revisions. For instructional use, a series of problems and review ques
tions have been provided following the appendix.
Drafts of revisions have been submitted for review and comment by members of ACI
Committee347, whose suggestions and advice have been most constructive. I am very
grateful to the many committee members who shared their expertise and cOunsel during
the preparation of the eighth edition. My special thanks to colleague Matthew Poisel, for
his development of the data for the span tables of Chapter 9. The author is also grateful
to the many individuals and organizations who have contributed nearly 500 new illustra
tions, drawings, and photo images to this first edition to be printed in color and to the
many contractors who have provided access to their construction sites for photographs by
the author, particularly United Forming, Inc., and Clancy & Theys Construction Co.
3: OVERALL PLANNING
9: DESIGN TABLES
APPENDIX &-NOTATION
APPENDIX C-GLOSSARY
APPENDIX D-CONVERSIONS
APPENDIX H-PROBLEMS
INDEX
CONTENTS
1: INTRODUCTION
3: OVERALL PLANNING
3.1 Development of o Basic System 3·1
3.1.1 Compare Alternate Methods 3·2
3.1.2 Examine form Pion in Relation to Total Job 3·2
3.2 Key Areas of Cost Reduction 3·2
6.7 Determining Concrete Strength for Stripping and Loading for Cycle Times 6-22
6.7.1 Analysis and Design Process for Slab Strength 6-22
6.7.2 Alternative Load Oi!otribution!o 6-26
6.7.3 N!ore Concentrated Shore Load!. 6-26
6.7.4 Structures Designed for Composite Action 6-26
6.7.5 Post-Tensioned Structures 6-27
6.8 Effect of Early loading on Slob DeRection 6-27
9: DESIGN TABLES
9.1 Equations for Calculating Safe Spon 9·1
11.6Columnforms 11-19
11.6.1 Erection Practices 11-19
11.6.2 Square or Rectangular Columns 11-21
11.6.3 Round and Flared Columns 11-21
11.6.4 ColumnHeods 11-22
11.6.5 ACI Column Tolerances 11-24
I 5: BRIDGE FORMWORK
15.1 Foundations 15-2
15.1.1 Caissons 15-2
15.1.2 Piles 15-4
15.1.3 Rock or Soil Offering Direct Support 15-4
15.2 Piers 15-5
15.2.1 Forms Moved for Reuse 15-5
15.2.2 Round Piers 15-6
15.2.3 Stonework Facing 15-6
15.2.4 Massive Piers 15·6
15.2.5 Vertical Alignment 15-6
15.2.6 Access for Workers 15-7
15.2.7 External Ties 15-7
15.2.8 Pier Caps and Tie Struts 15-7
15.3 Superstructures 15-8
15.3.1 Monolithic-Simple Slab, Boom, and Girder 15-8
15.3.2 Cast-in-Place Deck Supported on Steel or Precast Girders 15-9
15.3.3 Expansion Joints 15-10
15.3.4 Overhang, Sidewalks, Parapets, and Median Barriers 15-10
15.3.5 Support for Superstruci\Jre Farms 15-10
15.3.6 Stripping Bridge Forms 15-11
15..4 Arch Bridges 15-12
15.5 Segmental Box-Girder Bridge Construction 15-12
15.5.1 Cast-in-Place Segmental Construction 15·13
15.5.2 Precast Segmental Construction 15-13
15.5.3 Principal Erection Methods 15·14
15.5.4 Making Precast Bridge Segments 15-17
15.5.5 Voids, Inserts, Attachments 15-19
15.5.6 Joint Surfaces 15-19
15.5.7 Vibration 15-19
15.5.8 Heat Curing Considerations 15-19
15.5.9 Tolerance Requirements 15-20
16.5 facings for Roller-Compacted Moss Concrete and Dam Repair 16·8
16.9Toleronces 16·11
18.3T;It-Up 18-12
18.3.1 Curing and Bond-Breaking Compounds 18-13
18.3.2 Curved Tilt·Up Panels 18-13
APPENDIX B-NOTATION
APPENDIX C-GLOSSARY
APPENDIX D-CONVERSIONS
APPENDIX H-PROBLEMS
INDEX
1: INTRODUCTION
Formwork development has paralleled the growth of concrete construction from its
earliest uses through its many applications today. As concrete has been used for increas
ingly complex and significant structural and architectural tasks, formwork engineers
and contractors have had to keep pace. Projects involving rapid construction schedules
create challenges for the form designer and for the control of field forming operations.
The increasing use of concrete as an architectural medium presents the form builder with
several challenges, ranging from the selection of appropriate sheathing materials to the
maintenance of rigid tolerances.
Sawn lumber, manufactured wood products, plywood, steel, aluminum, reinforced
polymers, and other materials are widely used as formwork components. In addition, new
and specialized accessories are frequently introduced by manufacturers. Form designers,
builders, and manufacturers must keep abreast of advancing technology in other material
fields to develop and implement the creative and innovative solutions required to main
tain both quality and economy.
In the early days of the concrete industry, formwork was frequently built in place, used
once, wrecked (or stripped), and discarded. Because of high labor costs in the United
States and many other countries, the trend over the last several decades has been toward
increased prefabrication, assembly in large units, erection by mechanical means (such
as Nflying� forms into place by crane), and reuse of the forms. These developments are in
harmony with the increased mechanization often found in other fields and the desired
use of sustainable systems. Consequently, the forming system selection is often a primary
factor in locating cranes and in allocating site space for storage and fabrication.
Not all of the important ideas are new, however. As early as 1908, members of the
American Concrete Institute (then called the National Association of Cement Users) were
debating the relative merits of wood and steel formwork at their annual convention.
The discussion followed a presentation proclaiming the advantages of a modular metal
panel forming system.l.l It could be adapted for most any project, had its own connecting
hardware, and was good for extensive reuse. By 1910, steel forms for paving were being
produced commercially and used in the field. Continuing refinement of basic ideas such as these
represents another area of ongoing progress within the formwork industry. Today, formwork and
forming systems have become an integral part of the entire equipment array on site and of the
overall construction planning process. The comparison of metal versus wood and job�built versus
manufactured systems (Fig. 1.1 and 1.2) continues today with many varieties in use and the deci
sion ultimately based on factors of quality, safety, and economy for the individual project.
There are differences in forming practice details from one country to another and
even from one region of the United States to another. Some of the differences are due to
prevalent local material use, regional or country limits on supplies for manufacturers, or
preference of a contractor for a particular system due to their own inventory and profi
ciency of their workers with the system. However, a trend of consolidation among form
and accessory manufacturers is also resulting in several form manufacturers with broad
international supply capability. Variations in formwork application are often most visible
to the public in buildings (Fig. 1.3) and bridges (Fig. 1.4). Formwork is also extensively used
for residential construction, stadiums, airports, harbors, water treatment plants, tunnels,
dams, and other facilities. Although the information presented in this manual has been
drawn from many sources worldwide, it is intended for application primarily in the United
States. Suggestions for formwork economy have been based on conditions in countries
where labor costs are high compared to material costs. In countries where labor costs are
substantially lower in relation to the price of construction materials, many of the ideas
presented regarding formwork economy likely will not have the same validity.
Many individuals, firms, and companies are usually involved in the design of the facility
to be built and in the design and construction of the formwork. The facility team typi
cally involves structural engineers and architects who determine the requirements for the
concrete structure. For simplicity, the facility design team will usually be referred to as the
engineer/architect, although they may be referred to separately in some situations. The
formwork team may include the general contractor, formwork specialty subcontractors,
formwork engineers, form manufacturers, and form suppliers. The participating compa
nies and firms also have formwork designers and skilled workers executing many detailed
tasks. For simplicity, the formwork team will usually be referred to as the formworkengi
neer!contracror, although they may be referred to separately in some situations.
Form building requires both job-site innovation and engineering understanding. There is
certainly no substitute for the skill and sense of�know-how" that come with job-site experi
ence. In a similar manner, many engineering principles can be used to improve the safety,
quality, and economy of formwork.
CHAPTER 7
The primary objective of this manual is to
provide the reader with a convenient and
concise resource containing much of the
available knowledge on concrete formwork.
In no way will it supplant the experienced
formwork designer or form builder. The infor·
mation presented will be useful in planning,
designing. construaing, and using concrete
formwork. For the experienced formwork engi·
neer/contractor. this manual provides consid·
erable help by bringing together a multitude
of properties, design data, and construction
suggestions in a convenient, single-source
reference volume. For the engineer/archi-
tect this manual offers the opportunity for
improved execution of concrete construction
details through a bener understanding of the
problems and possibilities in form building. For
the novice, this manual will serve as an intro
duction to many common forming practices,
provide an explanation of basic principles of
form design, and encourage a rational rather
than rule-of-thumb approach.
With this audience in mind, three basic
objectives in form building are established
early in the text:
1. Quality-To design and build forms accu
rately so the size, shape, and position
meet the specified tolerances and the
required formed concrete surface of the
cast concrete is attained;
2. Safety-To build substantially so that
formwork is capable of supporting all
dead and live loads without collapse or
danger to workers, the concrete struc
ture, and the public; and
3. Economy-To build efficiently, saving
time and money for the contractor and Fig. I .3: Compressed schedules require design of the construction process to include engi
owner alike. neering of the formwork system and control of the construction operation loads within the
Cooperation and coordination between early strength of the concrete structure (Photo courtesy Atlas Construction Supply)
the engineer/architect and the formwork
contractor are necessary to achieve these
objectives. Chapter 2 concentrates on
economical aspects of formwork design
and discusses the relationship of contractor
to engineer or architect. Overall planning
for profitable construction with formwork
in mind is covered in the next chapter,
directed particularly to the problems of the
contractor (Fig. 1.5).
The remaining chapters are divided
into three main categories: 1) detailed
planning and design of forms; 2) building
the forms: and 3) using the forms. Design
principles and methods are explained
considering materials. loads, analysis of
multi-story operations, and sizing of form
work members and connections. A chapter
of design tables has been included that
allows designers to quickly select common Fig. 1.4: Specialized formwork systems for concrete bridge construction (Photo courtesy PERl
formwork members without the need for a Formwork Systems, Inc.)
INTRODUCTION
computer. Since the previous edition of this
manual, many standards impacting form
work design have been revised and new
ones have been adopted. The manual has
been thoroughly updated in this regard.
Materials and proprietary products for
forming are described, along with manu
factured systems of steel, aluminum, engi
neered wood, and reinforced polymers.
Job-built forms emphasize sawn lumber
wood members often mixed with manu·
factured accessories and components.
Form manufacturers sometimes use special
steel and aluminum shapes unique to their
systems and thus offer pre-engineered
components and systems. Job-built forms,
for either general use or as special segments
or fillers between manufactured compo
nents, are designed by the formwork engi
neer/contractor. Often, these elements are
Fig. 1.5: Planning for the sequence of form work erection and reuse must be integrated with designed in wood, but may be constructed
planning for other construction operations such as reinforcement placing and concrete from a variety of materials. While this manual
placing (Photo courtesyCECOConcrete Construction, LLC) covers loading and analysis appropriate to
all systems, the design of specific elements
focuses on wood materials.
Suggestions for form construction cover buildings, special requirements for formed concrete
surfaces, and architectural concrete. The section on using the forms covers care and maintenance,
inspection, and reshoring, as well as special considerations for construction in cold weather.
The subsequent sections on bridges, tunnels, and mass concrete deal with special
forming problems encountered in building these structures. Alternate techniques for
concrete placement-such as slip forming, preplaced aggregate, and shotcrete-are
discussed in terms of the unusual requirements they present for formwork. Because
many of the terms encountered in formwork practice are local or regional, or relate to the
vocabulary of special trades, a glossary has been included.
Throughout the manual, the term "formwork" has been employed in its broadest sense to
include the total system of support for the freshly placed concrete, including form sheathing
plus all supporting members, hardware, and bracing. Discussion of concrete construction
practices is limited to items that have a direct bearing on the formwork requirements.
The entire text follows recommendations of ACI Committee 347, Formwork for
Concrete. This eighth edition has been updated for consistency with the latest revision
of the committee's ACI347R-14, "Guide to Formwork for Concrete," ACI347.2R-OS, "Guide
for Shoring/Reshoring of Concrete Multistory Buildings," and ACI 347.3R·13, "Guide
to Formed Concrete Surfaces." ACI347R is included in the Appendix along with other
related documents. ACIdocuments are referenced frequently in this document, and
reference is made to design specifications and product standards on matters of wood
design. The text includes information gathered and contributed by ACI347 members
over B editions. To some extent, FormworkforConcrere has become the source for information
on practical aspects of formwork construction.
REFERENCES
1.1. Caldwell, W. L., "Metal Forms in Reinforced Concrete Construction," Proceedings of
the Fourth Annual Convention, National Association of Cement Producers, Buffalo, NY, Jan.
20-25, 1908, pp. 286-291, Discussion pp. 292-302.
2: GENERAL OBJECTIVES IN
FORMWORK BUILDING
Quality, safety, and economy are achieved by adherence to standards, specifications, and
guides related to formwork and by providing a system for careful planning, design, erec
tion, supervision, and inspection of the forms {Fig 2.1 ). Failure of the formwork
during erection of the forms or placement of the concrete can result in major expense for
reconstruction and injury or death of construction workers and others on or near the site.
CHAPTER 2
ACI347.2R-05, "Shoring/Reshoring of Concrete Multistory Buildings," covers procedures
and analysis methods for the shoring and reshoring of multi-story concrete buildings
under construction. This publication, ACI SP-4, is a manual to guide both the engineer/
architect and the formwork engineer/contractor in the design and construction of form
work consistent with these documents.
Determination of appropriate loads for design of formwork has been evolving. Form
work loads are very different from the loads required for permanent structures. ACI 347R
is generally recognized as the source of recommendations for loads on formwork.lt links
its recommendations for wind and seismic loads to the provisions of ASCEJSEI37-14,
"Design Loads on Structures During Construction," which similarly adopts the lateral pres
sure recommendations of ACI 347R. Knowledge of all these regulations, specifications,
guides, and standards is critical for attaining quality, safety, and economy in the concrete
construction process.
CHAPTER 2
should understand that reshores must not be wedged in so tightly
as to cause a stress reversal that might crack the concrete. (Refer to
Chapter 6 for reshoring recommendations.)
2.4.2/nadequate Bracing
The forces that cause forms to fail are usually not simple cases of vertical overloading. The
more frequent causes of formwork failure are other effects that introduce lateral forces or
induce displacement of supporting members. Inadequate cross bracing and horizontal
bracing of shores is one of the factors involved in formwork accidents.
The main exhibition floor of the New York Coliseum collapsed when concrete was
being placed during construction in 1955. Forms for the floor slab were supported on
two tiers of shores.1.1 Bottom shores were wood 4x4s, capped with horizontal 4x4s and
cross-braced horizontally. Adjustable metal shores were placed directly over the 4x4 posts
to form the second tier. There was little diagonal cross-bracing or horizontal bracing on
the adjustable shores. At the time of the collapse, there were eight or nine motorized
buggies transporting concrete to the area, and about 700ydl of concrete had been placed
by 2:00p.m. Apparently, a horizontal thrust developed through the combined effect of
the movement and sudden stopping of the buggies, dumping of concrete, operation of
concrete agitating machines, and other activities on the floor. If there had been sufficient
diagonal, horizontal, and end bracing of the temporary supporting structure, the collapse
could have been prevented or its area held to a minimum. After the accident, new two-tier
shoring in the coliseum was braced horizontally and diagonally on both tiers.
When a failure occurs at one point, inadequate bracing may permit the collapse to extend
to a large portion of the structure and multiply the damage. For example, suppose a worker
accidentally rams a wheelbarrow into some vertical shores and dislodges a couple of them.
This may set up a chain reaction that brings down the entire floor. One major objective of
bracing is to prevent such a minor accident or failure from becoming a disaster.
Shores can buckle under vertical load if they require bracing to support the imposed load
and that bracing is not adequate. When lacing is used between shores, the lacing must be
restrained from horizontal movement by either connecting it to a rigid element or to diagonal
bracing. Many single-post shores and legs of forming systems can be extended; however, this
reduces the buckling resistance and can cause failures, such as the one shown in Fig. 2. 6.
CHAPTER 2
Fig. 2.6: High shoring with a heavy load at the top is vulnerable to buckling, eccentric loading, or latera/loading (Photo courtesy Lawrence C.
Bank)
Fig. 2.7: Failure of concrete with inadequate maturity supporting a hoisting and form system resulted in 51 deaths during construction of a
cooling tower (Photo courtesy National Institute of Standards and Technology)
CHAPTER2
Fig. 2.8: Four workers were seriously injured when forms for a pan joist floor system collapsed due to concrete overload (Photo courtesy
Aviad Shapiro)
Fig. 2.9: The five-story Harbor Cay condominium collapsed while under construction, killing 11 workers and injuring 23 (Photo courtesy National
Institute of Standards and Technology)
CHAPTER 2
If camber is desired for slab soffits or structural members to compensate for elastic
deflection or deflection due to creep of the concrete, the contract drawings must so indi
cate and state the amounts. Measurement of soffit camber attained should be made afrer
initial set and before stripping supporting formwork.
If architectural features, embedded items, or the work of other trades change the
location of structural members such as joists in one-way or two-way joist systems, such
changes or conditions should be indicated on the structural drawings.
In addition, criteria for and some details of the forming practices will be specified,
depending in part on the type of structure being erected. General minimum requirements
should be stated to assure the owner and their architect or engineer that the formwork
will provide adequate support during concreting and until the concrete has gained suffi
cient strength to permit form removal. The following items should be clearly covered in
the engineer/architect specifications and drawings:
a. By whom the formwork will be designed;
b. By whom, when, and for what features formwork will be inspected;
What approvals will be required for:
• Formwork drawings;
CHAPTER2
On small projects where tests are not practicable
or where form reuse is not planned, the forms will lormwork Structure•
be left in place for a specified period of time. For
larger projects, the time of removal will be deter
I
mined by strength of test specimens. Assessing if
the concrete has achieved the necessary strength
to remove the forms is the preferred approach •structure Materials
and should be used whenever possible. In the
former case, the engineer/architect will include
•structure labor
the period of time the forms are to remain in
place in the specifications or refer to applicable
codes. If form removal is to be based on strength D Formwork labor
tests, the specification should indicate the 0
_Q
acceptable test methods and required concrete ro
_J
strength. • Formwork Materials
In the case of the more complex structures.
such as shells, arches, and folded plates, to
ensure the structure will assume its deflected
shape without damage, the decentering and
handling procedure for the formwork should be Fig. 2.10: Cost components for concrete structural construction
worked out carefully. These procedures should be
described in the contract drawings and specifica-
tions or, if worked out by the contractor, the procedures should be shown on the form
work drawings and approved by the engineer/architect.
2-14 CHAPTER2
span at least as far as the minimum
reinforcement will permit. Walls of
minimum thickness and reinforce
ment may carry column loads, act as
grade beams or transfer girders, resist
lateral loads, and serve as petitions or
exterior walls-all at the same time.
Use small drop panels in flat plates
rather than tapered column capitals Pay for
(Fig. 2.12) to save on forming cost. If these areas
the slab is at least 8 in. thick, it may be
possible to use steel shear heads and
avoid the capitals and drop panels
DO
entirely.
d. Use a flat plate for spans up to about
25ft because it is the cheapest, fastest,
Do not pay for
and shallowest framing method
available.
When one-way systems are used,
!llil
try to orient all framing in one direc
tion to save time (and money) in
construction. recess
Bulkhead
Use standard form sizes for one-way Bin. deep
joists and two-way domes to avoid
special form fabrication charges, and Fig. 2.1 1: Suggested basis of measurement of form area for payment purposes
use a single joist pan size to reduce
shipping and handling costs incurred when more than one size has to be provided.
g. Make all beams and joists the same depth. The savings in formwork and shoring will
orr
exceed any cost increase in concrete and steel. Heavily loaded beams on long spans
can be made as wide as necessary-up to four or five times their depth.
h. Keep the same beam concrete outlines even though loads and spans are not the
same, and vary the reinforcement to accommodate the load.
Make beams wider than columns on each side by at least 2 in. This helps reinforcing
bars in the corners of beams and columns to pass without obstruction. Remember, Taperedcolumncapti al Oroppanel
(expensive) (lusexpensive)
it is easier and cheaper to cut a hole in the bottom of a beam form for a column
penetration than it is to cut holes in the side of a column form for beam penetration. Fig. 2.12: Use of square drop panel rather
(
Space columns uniformly. This will result in uniform sizes for columns, joists, and than hard-to-form tapered column capital
beams, thus saving money by simplifying forming.
k. Make all columns the same size, vertically in one stack as well "===cr====:! 314" Plywood sheathing
as horizontally in one story. Adjust the amount of reinforce
ment or concrete strength as necessary for the loading. This
�;9
will maximize interchangeability and reuse of forms.
Keep floor-to-floor heights constant. If changes are necessary,
reduce the height in the upper stories. It is easier and cheaper
T l Focm '"mboc h• :II
=:!:::':=======d
to cut off a column form than it is to extend it.
m. Make the height of drop panels fit standard lumber dimen L Drop panel height
sions as shown in Fig. 2.13 and Table 2.1.
Allow reasonable tolerances. Specify tight tolerances only
where they are needed, or required by code, such as for loca- Fig. 2.13: Sizing drop panel to fit form materials
tion of bars in beams and columns. Tight tolerances require
more field labor, and hence increase cost. Table 2.1: Standard lumber dimensions and drop
Specify when forms may be stripped. Use a time limit for panel height
walls and columns and a strength requirement for beams and Lumber size
slabs, but consider requiring reshoring until design strength
Nomrnal Actual, rn. Drop panel herght, rn.
has been reached to prevent excessive deflection.
1�
6'/.o
CHAPTER3
times as long, the per-use cost will only be
one-fifth to one-tenth as much as using
the cheaper material. A form designed for
maximum reuse may have to be stronger
and more expensive than one designed for
a single use, but it can save a great deal on
the total form investment. Extra features
that make erection, stripping, and cleaning
easier will add to original form costs, but
labor savings may outweigh the extra cost.
It is poor economy to strive for minor
savings that can cause big losses elsewhere.
For example, increasing design stresses
beyond safe limits usually results in small
overall savings while greatly increasing the
risk of damage and severe loss. Careless
assembly or low-cost materials might save
a little in form cost but require more labor
and extensive amounts of expensive hand
finishing of the concrete afterwards.
3.3 Planning for Maximum Fig. 3.2: Planning formwork for maximum reuse reduces forming cost and increases labor
Reuse productivity (Photo courtesy PERl Formwork Systems, Inc.)
The plan or procedure to be followed in
getting maximum reuse of forms will vary greatly depending on the conditions of the
individual job. Generally, the sooner the forms can be stripped, the more economical and
practical it becomes to schedule many reuses of a form (Fig. 3.2). Thus, project specifica
tion or local code requirements for stripping and reshoring are an important factor in
planning form reuse. The requirements may impose either a time or a level of concrete
strength attainment before stripping. In multistory buildings where forms and shores will
be supported by the recently built structural members, special issues must be considered
(see Chapter 6).
Minimum investment in forms is achieved by constructing the least number of forms
required for a smooth work flow and then reusing these forms as often as necessary until
the job is completed. Because the stripping time for the sides of a beam or girder is much
shorter than for the bottom, it is often economical to build fewer side forms and plan
on early stripping and frequent reuse of the side panels while the bottom forms are left
in place. Chimneys, towers, and cylindrical or rectangular concrete cores for multi-story
buildings can be built quicker and less expensively using slip forms or climbing forms that
are reused for many lifts from bottom to top of the structure.
Mass concrete placements with a gradually changing cross section can be built using
rugged cantilever form panels that are raised and reused for lift after lift. Piers for bridges
or viaducts are frequently cast by repeated use of a form or series of forms. Building
columns can use the same forms over and over if the building designer has had the
foresight to make columns the same size, or with few dimensional changes, and vary the
reinforcing to meet strength needs. Ready-made modular panels can be moved from one
job to another and are adaptable to many different types of structures.
The amount of work involved in reusing a form may depend on whether it has to be
disassembled for stripping and reuse. In some cases, the form can be moved intact. This
is inherent in slip forms, of course, and may be possible with climbing forms or with pier
forms that can be loosened and lifted off the pier by a crane and set into position at the
next pier.
More often, the form must be taken apart and moved section by section. This may
be required by the shape of the concrete structure, which makes it impossible either
to loosen the form or to withdraw it without taking it apart. Sometimes, the weight of
the whole form is beyond the capacity of the crane and handling equipment, so it must
be transported in sections. Crane capacities must always be considered during the
planning stages.
Traveling forms (Chapter 16) eliminate much of the disassembly and reassembly in
reusing formwork. In long-barrel construction, for example, it is possible to build the barrel
arch form and shoring as a unit with a roller-equipped base. At stripping time, the form is
OVERALL PLANNING
lowered from the cast concrete member and simply rolled forward to the next position.
This sequence is repeated until the full length of the barrel has been cast. Shoring alone
may be assembled and braced in units that can be shifted from bay to bay as forms are
moved for reuse. Such shoring units must be rugged enough to withstand any extra
handling and moving stresses and are practical only where the conditions and equipment
available permit easy, safe handling.
CHAPTER3
on-hand and compare with the economics
of purchasing or renting new materials. For
example, if large quantities of 2x4 studs are
available, it may prove more economical to
use them, spaced closer together, than to
purchase 2x6s.
Using plywood panels for large surfaces
usually saves money (as compared with
board sheathing) because there is less
assembly work. With fewer joints in the
form surface, less formed concrete surface
finishing is required after the forms are
removed. The use of 4x4s for floor joists
instead of 2x4s on edge may be more
economical because the 2x4s would have
to be held in good alignment at sheathing
edges and toenailed into place.
The contractor may have to choose
between partially absorptive form
materials like standard plywood and
dressed lumber that produce a slight
texture; hardboard, plastic, plastic-coated Fig. 3.4: Site-built wall formwork
plywood, or metal forms that produce
smooth surfaces; or purposely rough wood forms or form liners that produce a distinctive
texture. Specifications must be carefully studied and possibly discussed with the engineer/
architect to see just what formed surface effects are desired. ACI347.3R, NGuide to Formed
Concrete Surfaces,w can be helpful in specification development and interpretation.
Casting a mock-up panel or locating a reference surface on another project may provide a
basis for comparison.
Better grades of lumber and plywood can be counted on for minimum waste and to a
great extent are reusable, but sometimes savings can be made by purchasing a lower grade
of lumber and culling at the building site. Whether this reduces overall cost depends on how
much labor must be expended in the culling and in cutting and splicing to get maximum use
of material. The decision may depend on the location of the project and the supply available.
Where good materials are required, savings can be realized by obtaining materials for
the current project that can be reused on future projects. It may be economical to invest
in high-grade reusable panels, sections, materials, and hardware and prorate only a part of
their cost to the current project.
conditions and in the purchase and use of materials and machinery is obtained by fabri and-tie wing nut, have an important effect
cating form sections in a central form shop maintained by the formwork contractor and on form assembly and stripping costs (Photo
shipping the forms to the site for erection (Fig. 3. 6). The cost of transporting form sections courtesy MEVA Form work Systems)
to the site may make this plan uneconomical if the shop is located too far from the project,
or the form sections are too large for shipping. In the latter case, the forms must be built
at the site. At times, however, space on the site is limited and off-site fabrication is the only
feasible method regardless of transportation costs. Limited site space is often a problem
for urban downtown projects and can be a problem even at remote sites (Fig.3.7).
For small projects, or where forms must be fitted to the terrain, it may be economical
to cut and assemble at the point of installation where cut-and-try methods can be
used, in spite of the waste that usually occurs under such conditions. Most job-site form
building will benefit from the creation of a sheltered area equipped with power tools and
assembly benches. If necessary, a platform can be built alongside the shop for assembly
of large form sections. The job-site shop should be located so that form materials can be
conveniently stored near the shop and where there is access for transport equipment to Fig. 3.6: Prefabrication of parking garage
pick up the finished form sections. deck panel formwork reduces less-productive
Possible savings through reduced waste of material, consistent quality, and better elevated work (Photo courtesy Symons by
productivity of labor are usually in direct proportion to the amount of work that can be Dayton Superior)
OVERALL PLANNING
shop-performed. Shop fabrication improves productivity planning and control because
supervision is easier if the only work done at the point of installation is assembly of forms.
CHAPTER3
concrete and thus eliminate or minimize the need for prying it loose.lihing eyes and
other hardware make it easy to transport the form sections from one placing location to
the next. Work platforms to make both erection and stripping more convenient and safe
for workers should be part of the formwork plan.
In comparing the expected erecting and stripping costs for various formwork plans,
estimates may be based on worker-hours per square foot as shown by previous experi
ence with similar types of forms. A more detailed comparison might be made through an
analysis of crew size, specific operations, and time from start of stripping of a form until it
�r _ _
- e «: 1
Fig. 3.8: Shipping costs and delivery dates for
is ready for the next placement. This detailed approach would be particularly valuable for
formwork materials and accessories impact
the major forms on a job, including those with a large number of reuses.
project costs and schedule (Photo courtesy
Total time in hours multiplied by the number of workers in the crew gives the total
expected worker-hours. The contact area formed at each placement divided by the
Atlas Construction Supply)
estimated worker-hours gives a production rate in square feet per worker-hour. This
figure should reflect average conditions over a representative period and therefore
should include allowance for delays resulting from poor weather, equipment breakdowns,
and other causes. Allowance should be made for any miscellaneous expense normally
incurred, including the cleaning and oiling of forms between uses. Some allowance must
also be made for the routine nonproductive time of the workers.
Many formwork plans will anticipate raising a form and locating it by inserts in
the previously placed concrete or using inserts as a means of anchoring, lifting, or
attaching it. Ties, spacers, and other hardware items also may be left in the concrete.
Allowance must therefore be made for hardware lost or left in place in the concrete
plus other non-reusable materials expended during the process of placing and
removing the forms.
Concreting
The ease and speed of placing concrete is related to the planned sequence and, to some
extent, to the choice of form design. High lifts in wall construction may save money
in setting and stripping forms but make placing and vibrating difficult. High rates of
placing may require a heavier form to withstand the loads, and conversely, the placing
rate is limited by the form design.The size of placements for floor slabs is frequently
controlled by what can be completed within a day with the crew available without
encountering overtime. Concreting of floor slabs requires some lapse of time after
placing and screeding before finishing operations can begin. The finishing process itself
may require several passes.
OVERALL PLANNING
If the planned placing schedule will not permit the concreting crew to spend a full day
on the job, the contractor is faced with a choice of:
Increasing the placing schedule by making forms and lifts larger or using more forms
with fewer reuses;
Making other assignments available to the concreting crew; or
Allowing for less than full effectiveness on the job.
Size of placement units may be predetermined by construction joint specifications. In
such a case, the contractor should plan changes only in consultation with the architect or
engineer.
Bar Setting
Crews installing reinforcing steel will be used most efficiently if their work can be sched
uled to fit the concreting sequence without causing lost time in either the concreting or
bar-setting schedule. If the form design can permit the reinforcement to be preassembled
before installing, the reinforcing crew may be able to work under more favorable condi
tions as they can work at their own pace. Their work can then be scheduled ahead of form
setting, so that forms can be set one day and concrete placed the next, thus speeding the
schedule and possibly increasing the number of form reuses.
Other Trades
The contractor's concreting schedule plan should include coordination of the work by
other trades, such as electrical and mechanical, to permit these other trades to perform
their work efficiently and to minimize interruptions in placing.
CHAPTER 3
girder erection may encounter delays in
the winter months. Starting steel erection
in November, the deck concreting may
commence in the early spring a month or TopofcapEiev." 130
so before the steel erection is complete, Bottom ofcap Elev.:: 120
and the job can be finished within the Cap length z 67
allowable time. If completion of the bent Capwidth :9
caps for the second roadway can overlap Pierdia. "8
the steel erection underway on the first
roadway by 4 months, this leaves 11
months for the excavation and concrete
substructure. 80.0
Because considerable site preparation 40.0
and excavation is necessary before pier 0.0
footings may be constructed, it is decided 0.0
that pier construction cannot be carried
40.0
60.0
out on any kind of production scale until
90.0
around May 1. Rainy spring conditions may
also influence this schedule. Further, severe
winter conditions may render concreting . . . .
F1g. 3.9: Planmng example-bndge p1ers for eastbound lanes
after December 1 erratic and too costly
to be practical. Therefore, the bidder concludes that the schedule demands that the
substructure be started and essentially completed during the months of April through
November with allowance of remaining overlap months toMtail outwthe top pier cap
placement, which may lag because of the time required for the supported form to remain
in place. Assuming a start on foundations during April, this leaves approximately 30 weeks
to place the pier and cap concrete except for a few tail-out pier caps. Assuming a 5-day
week with some holidays, miscellaneous delays, and lost days to weather, there are about
130 work days available.
Because the footing forms depend on the excavation and suitability of the sides of the
excavation as forms, they are not subject to reuse analysis and probably will be built in
place. The bidder assumes sufficient foundation placement lead may be attained in April
so that pier shaft concrete may start on May 1.
The ideal situation is to find that set of circumstances which would permit one crew
to be placing concrete regularly all day every day while a crew of carpenters and one of
reinforcing steel workers were continuously employed preparing the forms for concrete.
This is rarely obtained and provision must be made for rainy days or other contingencies
that would throw the sequence off schedule. Shaft forms in this hypothetical case may be
stripped the day after placing while the supported cap beam forms must be left in place
14days.
Trial Plans
Because so many variables are involved, it is necessary to adopt a trial plan that fits the
circumstances and then compare it to any alternative ideas that may evolve. Many of
these comparisons and the subsequent analysis of alternatives are accomplished without
detailed work due to the ability and experience of the estimator. However, in cases where
all the factors are not so clearly seen, it is necessary to evaluate each detail of an alternate
plan. As a result, the contractor may decide the advantages of working through the winter
and completing the work ahead of schedule outweigh the added cost of attempting steel
erection during cold weather. In developing and evaluating the trial plan, the contractor
has involved the formwork engineer, formwork supplier, estimator, expected project
manager, and an experienced formwork crew leader.
Project specifications indicate that the contractor is to submit the location of pier
construction joints for approval. The one requirement is that all but the bottom lift are
to be equal height so that the joints are at the same elevations from pier to pier. The
contractor has developed a tentative plan for the joint elevations listed in Table 3.1. There
are 2B double-shaft lift placements on the piers to be accomplished if the construction
joint layout is used as listed. This would require almost 1SO yd3per placement. There are 14
cap placements, each requiring about 225 yd3•
OVERALL PLANNING
Planning Form Sizes
To meet this schedule as outlined so far, all operations
should be checked thoroughly for timing.Cap beam forms
must remain in place for 14days, whereas the pier forms can
be stripped after 1day.Thus, the pier forms can be reused
several times while the cap forms remain in place. The size of
the piers and the concrete that can be reasonably placed in
a day in a deep pier leads to evaluation of using lifts of about
40ft. This requires only one lift on the short piers and two or
three lifts on the taller piers.Figure 3.10illustrates the height
of steel round column form sections that could be used on
the 120ft tall piers. The layout for each 120h pier calls for
three 10ft tall sections, one 8ft tall section, and one 2ft
tall section to make up the 40ft, plus one extra 2ft section.
Double this number is needed for casting each lift of the pair
of piers at the same time. Figures 3.11to 3.13 show forms and
construction for a similar, but different, bridge project.
To stabilize the second 40h lih, the 2h section is leh in
place and the stripped 38ft portion is set in place for the second lift with an additional
i:
2ft section added at the top.When the second lift is stripped, including the lower 2ft
section, the upper 2ft section remains in place.The sections stripped are then set for
�
the third lift.Guying cables are employed to align and further stabilize the forms for the
placements.These section sizes and numbers provide the needed form sections for reuse
to accomplish the various pier heights.
�
Study of trial schedules indicates that two complete cap beam forms appear to be
needed.This is driven by the much longer time before stripping is allowed.For the
tentative form design, the steel plate girder side forms are supported on brackets
attached to the piers with 3 in.through bolts.Soffit forms are supported by the side forms.
An alternate-to shore the cap from the ground or otherwise from the piers, allowing the
side forms to be stripped earlier-was considered but not found to be economical.
!
Crane Size
10ft-#3 The contractor proposes to have two tall, high-capacity cranes on the project. Due to site
10ft-#2 terrain, crawler-mounted mobile cranes will be needed. A rough weight calculation is
made on the tentative cap beam form that is to be raised as an assembled unit using both
10ft-#1 cranes.Its weight is compared to that of the steel girders and other major items, and the
needed crane capacity, reach, and boom length are determined to allow erection of all
Fig. 3.10: Reuse ofform sections in three members and stripping of all forms.
concrete lifts for 120ft pier Analysis is made of each operation for pier bent construction involving crane time to
determine their availability for other activities.It is found that the two heavy cranes will be
in good use lifting cages, setting and stripping
forms, and moving materials.Because both
cranes are available, concrete will be placed by
crane and bucket rather than pumping. On the
hilly side, their reach will be desirable even for
light loads. From this analysis, it appears the rig
requirements for the scheme contemplated will
be in reasonable balance. Having two cranes
also assures concrete placement will not be
imperiled if one breaks down. However, further
analysis of various miscellaneous operations
brings out the desirability of having a general
purpose crane, such as a small truck crane
for small jobs.These may include building
forms, handling materials, and fabricating
reinforcing cages.Production operations of the
large cranes for moving forms and concreting
preclude using these pieces of equipment for
any operations that take them away from the
pier shafts during the critical forming or placing
activities. Therefore, it is decided to use the
CHAPTER 3
truck crane to fabricate the reinforcing steel into cages for individual lifts so that the cage
may be delivered to the pier ready to set into place as soon as the form is removed from
the previous lift.
Efficient Scheduling
In cases where maximum reuse of the form is emphasized, every operation must be
scheduled precisely so that the form may be stripped and reset as soon after concreting as
possible. Otherwise, it will be difficult to sustain continuity of effective employment of the
various crafts involved. Ideal production rates are attained when crews can be set up to do
the same operation day after day; that is, one crew concreting or preparing to do so every
day, one crew stripping and setting forms, one crew fabricating and placing reinforcing
cages, and so on.
Figure 3.14 shows a preliminary bar chart schedule for the first 5 weeks focusing on
placing reinforcing steel, setting forms, casting concrete, and stripping forms for the pier
bents. The bar chart may have been produced from network scheduling software or from
rough sketches as a preliminary analysis. Codes further define the location of the activity:
P2-L2-E =Pier bent 2, lift 2, Eastbound series of double piers.
(1-E =Cap beam on pier bent 1, Eastbound series of double piers.
The plan envisions starting at one end of the eastbound roadway, proceeding to the far
end, and then working back for the seven pier bents of the westbound lanes. This will allow
setting of the bearings for the girders, and eventually setting girders for the eastbound lanes
first while pier construction is nearing completion for the westbound roadway.
From an examination of the schedule, it appears that some crews are idle on some days.
Fig. 3.12: Cap beam form preparation for
However, only principal activities are shown. for example, between placing reinforcement
tallest piers (Photo courtesy EFCO Corp.)
for the pier lifts or caps, the crew would be tying cages on jigs or placing steel in the
preceding foundations. The formwork crew would be cleaning and reassembling form
sections as needed. The casting crew would have other placements for foundations
and preparation work for the next concrete placement, each being a major activity that
must go smoothly. Thus, the crews will be fully active and no allowance for less than full
effectiveness needs to be taken. Because the piers have a different number of lifts, the
activities do not repeat in a rigid cycle. The work on the cap beam interrupts the cycle of
work on the piers. Thus, in some cases, the pier forms are stripped, cleaned, and reset on
different days and sometimes all on the same day. Weather has not been considered in
this schedule. Delays can be expected due to weather, equipment breakdown, and other
unpredictable events that will stretch out this simplified schedule.
Expected crane time on the activities is again considered and found to be consistent
with the schedule. Two cranes will be needed for major placements and the small truck
crane can handle parallel activities on those
days. The major placements are expected
to require the entire day.
Duration
The schedule in fig. 3.14 only covers the
first 5 weeks. However, it can be seen
that 3 of 14 caps have been constructed
in 4 weeks and 8 of 28 pier lifts have
been constructed in 5 weeks. Extrapo
lating this pace for the caps, it can be
estimated 14 caps x 4 weeks/3 caps=
18.6 weeks for total cap construction
duration, plus 2 weeks final curing or
20.6 weeks. for the piers, 28 lifts x5
weeks/8 lifts= 17.5 weeks for all piers.
An adjustment must be made for initial
assembly, holidays, bad weather, and
breakdowns. This includes:
3 holidays;
20 days bad weather;
5 days for other delays; and
2 days for initial assembly. Fig. 3.13: Sequential placement of bridge pier lifts, cap beams, and girders (Photo courtesy
EFCOCorp.)
OVERALL PLANNING
Mo�th 5 5 5 5 5 5 5 5 5 s s 5 5 5 5 5 5 5 5 5 5 5 s 5 5 s 5 5 5 5 5
This adds up to 30 work days total or
Oo 7 8 91 11 121314151 171819 21 22 2]242526272829 l1 1 2
6 weeks. Thus, for the piers, forms will
Ploce errelni.PI-ll·E
be needed for 2 3.5 weeks/4. 3 3 weeks/
Set erformPJ.LH
Plocerelni.PHI-E
month = 5.4, or say 6 months. For the
cap beams, forms will be needed for
26.6 weeks/4.3 3 weeks/month= 6.2,
or say 7 months. Extending the schedule
shown in Fig. 3.14 would provide a more
accurate estimate of the duration.
CHAPTER3
Recheck Plan Details
Once the complete schedule has been worked out and the general plan developed, the
bidder must go back over each step to check out the details of the form design. Rein
forcement details should be checked to make sure that there is no conflict with the form
placing method and that the assumption of fabricating cages of one-lift units is feasible.
Ladders and stairs for access to and on the forms must be provided. Provision must be
made for working platforms for concrete crews and their equipment. Safety features
figure prominently here as crews are more productive when they are in a safer working
environment.
Details of corner connections, aligning devices, and handling hooks or slings must be
made to assure fast action of removing and erecting the form to permit the production
rates assumed. Specifications on chamfer, rustication strips, finish, anchor bolts, and other
embedded items must be investigated to be sure they are consistent with the proposed
form plan. The formwork engineer must recheck and finalize the sizing of structural
members. The weight of the form is then rechecked to ascertain if it is still within the
capacity of the selected cranes. A re-evaluation of other construction operations that will
be in progress during this period is necessary to determine if any will adversely affect the
forming operation.
OVERALL PLANNING
d) Linear schedule of concrete construction activities linked to cost
and resource data
Fig. 3. l 5: Form work material, labor, and schedule information extracted from formwork 8/M (Images courtesy Klarman Construction)
CHAPTER 3
IL� 11 " 1
,
/11• - � I
Fig. 3.16: 4-0 program validation of formwark activities for multistory building construction
with flying table forms and three levels of reshores (Image courtesy Klarman Construction)
OVERALL PLANNING
internal workflow and reduces duplication of effort for layout, detailing, shop drawings,
prefabrication on and off site, drawing production, bills of material, tracking, and change
management. If used in pursuit of or bidding for projects, additional advantages are
found. There is significant investment in startup, but these costs are expected to lessen as
more standard components are modeled by producers and become generally available.
Several native BIM software packages are currently in use. Ultimately, a contractor
will use one as its main system and several others for various specialty purposes. These
should not be confused with viewing software. The viewing software allows one to query,
view, compare, and extract information and combine several models for coordination
and clash detection, among other things, but they do not let the user create native
elements. The native BIM tools are used to actually create the model and add intelligence
to the geometry (such as surface finishes, tolerances, design parameters, mixture design,
testing, formwork, production rates, fabrication and erection information, scheduling,
maintenance, and warrantee). There are also other BIM tools that allow the user to do
quantity takeoffs, estimating, and scheduling along with constructability reviews from BIM
models provided to, or created by, the user.
4: MATERIALS, ACCESSORIES, AND
PROPRIETARY PRODUCTS
The selection of materials suitable for formwork should be based on maximum economy
to the contractor consistent with safety and the quality required in the finished work.
The primary structural components of formwork may be of dimension lumber, plywood,
structural composite lumber, steel, or aluminum. Due to the varied needs of a concrete
construction project, many of these materials are often found in use on a single job site
(fig. 4.1 ). Some are job-built systems, while others are manufactured systems.
Prefabricated, reusable form panels and shoring units have become standard items of
construction equipment. Panels are ganged into larger units for efficient wall forming,
and large"flyingH deck forms have become commonplace. Tying, fastening, bracing, and
support accessories continue to increase in number and variety. New materials have
been adapted to form construction, and new ways to use conventional materials have
been found. Plastics, glass fiber, steel, aluminum, and rubber, both as raw materials and in
patented, prefabricated shapes, have simplified the forming of concrete to meet the chal Fig. 4.1: Dimension lumber and plywood
lenges of contemporary architectural demands. dominate this construction view of a three
The purpose of this chapter is to describe the various products and materials currently story parking structure, but aluminum beams,
in use for formwork. In the case of patented panels, shoring, ties, and other accessories, steel shoring frames, and steel-framed panels
some generalizations have been made because of the enormous number of individual are also in use
items. The illustrations have been selected as representative of a class of items, and their
inclusion does not imply superiority of the product pictured. With globalization, some
form and accessory suppliers operate on an international scale, although practices in
countries vary as a function of the relative cost and availability of materials and labor. For
practical reasons, the present discussion focuses on U.S. practice.
4.1 Lumber
Practically all formworkjobs, regardless of the varied or exotic form materials that may be
used, require some lumber. Although availability of the species, grades, sizes, and lengths
vary geographically, the local supplier wilt advise what material and sizes are in stock or
promptly obtainable. Any lumber that is straight and structurally strong and sound may
be used for formwork, although the wide distribution and abundance of softwoods make
them generally most economical for all types of formwork. The softwoods are usually
lighter and are easier to use, though not necessarily softer than hardwoods. Hardwood
caps and wedges may be introduced where additional compressive strength perpendic·
ular to the grain is needed. The choice of lumber species is a question of local availability.
Usually, there are several kinds that will serve equally well for a given job, and the cost may
be the deciding factor in the selection process.
Partially seasoned stock is preferred for formwork because fully dried lumber swells
excessively when it becomes wet, and green timber will dry out and warp during hot
weather, causing difficulties of alignment and uneven surface. Green lumber is also signifi·
cantly heavier than dry lumber-a factor that should be considered when determining
which lumber to select. Depending on the species, most commercially available lumber
is either sold kiln-dried to 19% moisture content (MC) or less, or sold as green. Attention
should be paid to the moisture content being used and consistency should be an objec·
tive. Old and new boards should not be used together in the same panel if uniform finish
is important. Although final choice of wood for forming will depend on the local market,
the following brief description of some of the commonly used woods may be of value.
4. 1. 1 Kinds of Lumber
There are many individual species of trees used to produce lumber.•-1 However, agencies
grading lumber frequently group species for grading and marketing. As a practical matter,
it is the technical information for a commercial species group that is used most often in
structural design. Some of the more commonly used species groups for formwork and
their approximate regions of availability are:
Douglas Fir-larch-may be either Douglas fir or western larch; primarily available in
pacific, mountain, central, and midwest states.
Southern Pine-may include loblolly, longleaf, shortleaf, or slash pines; primarily avail·
able in eastern and central states.
Douglas Fir (South)-only Douglas fir from southwestern growth areas; primarily
available in pacific, mountain, and central states.
Spruce-Pine-Fir-may be alpine or balsam fir, black or Engelmann spruce, jack pine
or lodge-pole pine, red spruce, and white spruce; from Canada, generally available
throughout the United States.
Hem-Fir-includes western hemlock and the following firs: grand, noble, white,
California red, and Pacific silver; primarily available in pacific, mountain, central, and
midwest states.
Spruce-Pine-Fir (South)-may include balsam fir, black or Engelmann spruce, jack
pine or lodge-pole pine, red (Norway) pine, red spruce, Sitka spruce, and white spruce;
primarily produced and available in the northeast and northwest states. In this group,
South is to differentiate from Canada, not to indicate southern United States.
In addition to the major species groups, there are regional pockets where individual
species like ponderosa pine, aspen, and Norway (red) pine are produced on a large scale
and are commonly used for formwork. Southern Pine and the species groups including
Douglas fir are most widely used in structural concrete forms and are equally suitable
for architectural concrete. They are easily worked and are the strongest in the softwood
group. Both hold nails well and are durable. They are used for sheathing, studs, and wales.
Douglas fir is sometimes used for milled wood forms. Kiln-dried Douglas fir is appreciably
lighter and a little softer than Southern Pine, but is often sold green. For this reason,
attention should be paid when specifying and ordering Douglas fir to ensure all parties
understand what material is being requested and supplied. Southern Pine has moderately
large shrinkage but stays in place well when properly seasoned. The choice between the
two should be primarily one of cost and availability, as the differences between them are
generally insignificant. Many markets, particularly in the middle of the United States, may
find greatest economy by switching between Southern Pine and Douglas fir depending on
the state of the lumber market.
Western Hem-Fir, including western hemlock, is comparable to Douglas fir as form
lumber and may generally be used wherever Douglas fir or Southern Pine are used,
although it is not quite as strong. The species of hemlock growing on the Pacific Coast
should not be confused with eastern hemlock, which is not generally considered suitable
CHAPTER4
for architectural concrete forms due to its tannin content that can produce staining. It is,
however, used for structural concrete forms.
Spruce-Pine-Fir, often abbreviated SPF, is a Canadian species group available
throughout the United States. SPF is the most common species group used in wood
framed construction. Because of its availability, workability, and price, it is commonly used
in formwork construction. SPF is not as strong as Southern Pine, Douglas fir, or Hem-Fir,
but is usually sufficient for formwork construction, particularly in applications requiring
2x4 and 2x6 nominal sizes of dimension lumber. SPF is soft and straight-grained and can
be milled easily, making it a good choice for architectural concrete forms. SPF (South) is Table 4.1: Specific gravity G of
usually marked SPFs or SPF{s) in the grade stamp. Northern white, Idaho white, sugar, some wood species used for
and ponderosa pines are also excellent woods for architectural concrete forms. Because formwork
they are not as abundant, the four main species of pine are used for purposes for which Spec1f1e grov1ty,
the latter are not so well-suited. They are generally not economical for forms except for Wood spec1es oven dry
special uses or in regions where they are locally produced. Because the white pines are DouglasFirL
- arch 0.50
soft and straight-grained, they are especially well-suited for moldings and milled shapes DouglosFir-lorch
for forming concrete ornamentation. The white pines stay in place well, as they are not {NorthI
0.46
inclined to warp and twist. This characteristic is especially desirable for forms made up of DouglosFirS
- outh 0.49
an assembly of milled pieces, as they will remain tight and will ensure sharp detailing. Red
Eastern Hemlock 0.41
(Norway) pine and eastern spruce have many of the qualities of the white pines and may
EasternSoftwoods 0.36
be used, provided satisfactory grades can be obtained.
Occasionally, form lumber contains enough tannin, sugar, or other organic substances EasternSpruce 0.41
to cause staining or softening of the surface concrete. For example, the U.S. Army Corps of Hem-fir 0.43
Engineers has reported4-l cases of mass concrete failing to harden where it was in contact Mountain Hemlock 0.47
with forms made of new ponderosa pine. When this condition is recognized, it can be NorthernPine 0.42
remedied by treating the form surfaces with whitewash or lime water before applying a
SouthernPine 0.55
form oil coating. The condition also disappears after one or two reuses of the form.
For additional information on these and other species of wood, consult References 4.1, 4.3,
Spruce-Pine-Fir 0.42
and 4.4. Spruce-Pine-Fir(Southl 0.36
The specific gravity of woods suitable for formwork varies from 0.36 to as high as 0.55 Western Hemlock 0.47
when oven dry, as shown in Table 4.1 based on values from AWC NDS-12, �National Design Western WhitePine 0.40
Specification for Wood Construction.ffBroadly speaking, heavier or denser woods are
Western Woods 0.36
stronger and hold nails or other fasteners better. Increased moisture content increases all
Specoes names fottowed by"(North)"indoc.:He lumber gr�ded
of the specific gravities shown in Table 4.1. The density of the wood as a function of the bytheCanadi a nN ationatlumberGrade�Authoo i ty.Values
oven-dry specific gravity, G, and the percent moisture content, m.c., can be determined as basedonpoovisionsofAWCNDS-2012.
follows
Density=62.4 [ G
1+G(0.009)(m.c.)
][
1+
m.c
100
. l lb/ft 3 (4.1)
·B"--1
minimum nominal thickness of 1-1/2 in. or less, dimension lumber has a minimum nominal
thickness from 2 to 4-1/2 in., and timbers have a minimum nominal thickness ofS in. '"'
or more. However, it is not unusual for dimension lumber to be referred to as boards in
t
545, t9Percenl Moi51ure
everyday discussion.
Lumber that has been surfaced in a planer to attain smoothness of surface and unifor
�-
mity of size is called �dressedu lumber. The surfacing may be on one side {515), one edge
19/16
(51E), two sides (525), two edges {52E), a combination of sides and edges {51SIE, 51S2E,
L
5251E) or on all four sides (545). Dressed lumber is generally used for formwork because it ROu<;th,t9PercentMo<slure S4S,More Thllni9
is easier to handle and work, but rough-sawn dimension lumber and timbers may be used Percent Moisture
in bracing and shoring or as a form-surfacing material to secure a special texture effect in Fig. 4.2: Specified actual size of a 2x4 for
the finished concrete. different moisture contents and finishes
Minimum sizes of both rough and dressed lumber are specified in NIST PS 20-10, uAmer
ican Softwood Lumber Standard.ff Lumber is commonly referred to by its nominal size,
which at one time was the same as the rough-sawn measurements. However, the actual
sizes in effect since 1970 were adopted in an attempt to equate green and dry lumber.
That is, minimum sizes for green lumber were selected so green lumber becomes the
same size as dry lumber after the moisture is lost (fig. 4.2). Rough lumber is now generally
required to be 1/8 in. thicker and 1/8 in. wider than its finished counterpart. Often, rough
sawn lumber is requested in custom sizes; so when requesting or ordering rough-sawn
lumber, the actual size should be clearly communicated so all parties involved know what
is expected.
CHAPTER4
'Based on a unit dry weight of 35 lb/ft'. Actual weights vary depending on species and moiswre contents. At 15% moOsture content, the unit weight of Douglas Fir-Larch is 34 lblft:', and that of
Southern Pine is 371b/ft'. The other species commonly used in formwork in North America weigh less.
CHAPTER4
an adjustment for cumulative load duration, C0. The reference design values correspond
to normal load duration, which is presumed to stress the member to its full allowable load
for a period between 2 months and 10 years. Formwork maximum loading is typically of
much shorter duration.
In the case of lumber for formwork, this is often interpreted to mean the adjustment
factor of 1.25 shown in Table 4.S for 7 days or less duration of load. The AWC NOS indi
cates the 7-day load duration is the cumulative duration at full maximum load, so any
formwork likely to see more than 168 hours of maximum loading would not qualify for
the 25% stress increase (CD= 1.2S). However, because the live load of personnel is gener
ally very brief during placement, the cumulative duration at maximum load may not be
the same as the duration that the forms are in place until stripping. As a result, assuming
a duration of less than 7 days is often reasonable. When there is substantial reuse, a
longer cumulative load duration may be appropriate. In such cases, the 15% increase for
maximum loading exceeding 7 days but not exceeding 2 months could be considered as
an alternate. When wood forms are being reused from prior projects (such as when they
are pulled out of storage from prior use) with unknown loading history, it is prudent not to Table 4.6: Wet service factors, Cw
apply the load duration increase (CD= 1.0). for sawn lumber
For short-duration loads such as wind, earthquake, or impact, higher adjustment
factors are permitted based on the ability of wood to absorb significant overload for
short periods.
'When (f.)(C,J,;; 1150psi,C�� 1.0.
!.M
'When (F)K,l :!i 750psi, C�= 1.0
Adjustment for Wet Service, eM
Reference design values in Table 4.3 are subject to possible adjustment for wet service
conditions. For wood moisture content.,:; 19%, C.,.= 1.0. When moisture content is
greater than 19% for an extended period of time, adjustment factors ranging from 1.0
to 0.67 apply to dimension lumber of 2 to 4 in. nominal thickness, as shown in Table 4.6.
Other wet service adjustments, listed in the AWC NOS, apply to timbers SxS or larger.
The moisture content of initially dry wood may or may not exceed 19% from expo-
sure to rain depending on the frequency and field storage conditions. Wood that will
be in direct contact with fresh concrete should be considered to be in wet service. A
conservative assumption for other wood formwork members is to assume wet service.
However, actual field experience for the environment of use based on checking form
components with a moisture meter (Fig. 4.3) can serve as a basis for concluding that the
wet service reduction is not normally needed.
Size Factor, CF
Except for Southern Pine, the reference
design values for lumber commonly
used for formwork are subject to a size
adjustment for bending and compression
parallel to grain {see Table 4.8). Southern
Pine reference design values have size
adjustments already included in their
reference design values, and Construction
and Standard-grade lumber require no
adjustment {C� = 1).
Incising Factor, C;
Some treated wood is incised to improve penetration of preservatives. Incising involves
making shallow, slit-like penetrations parallel to the grain in the surfaces. Douglas fir
is among those species that tend to be resistant to side penetration of preservatives.
Because Douglas fir species are more prevalent in the western states, incised wood is more
frequently seen in that region. Incising
factors are listed in Table 4.9.
CHAPTER4
Predictability: less distortion such as
bow, twist, crook, and splitting and
more predictable cup and swell asso
ciated with wood response to changes
in moisture.
Reference design values, adjustment
factors, and design procedures are defined
by the AWC NDS for some manufactured
wood products. However, other product
standards continue to be developed by
APA- The Engineered Wood Association.
Finish: There are four appearance grades for glued laminated beams: industrial, framing,
architectural, and premium. In typical formwork applications where appearance of the form·
work is not important and load is being applied perpendicular to the glue lines (referred to
as beam orientation for glue laminated members), industrial appearance is usually appro
priate. Several different grade designations for glulam beams exist depending on species
and intended applications.
CHAPTER4
Table 4.12: Representative reference design values for structural composite lumber with loads applied
parallel to gluelines for or parallel to wide face of strands for LSL and PSL (beam orientation)•
750psi
Compression perpendicular to 750to 900psi 750to 9500to 30to 1500psi
(Iced porollel ta wide foce of
groin (Iced porollel to glue lines) (Iced porollel to wide face of slfands)
slfonds)
Compression pom!lel to groin 2500to 3200psi 1400to 2050psi 2500to 2900 psi
Width ,example availability 1-1/2, 1-3/4, 2-1/2,and 3-1/2 in 1-1/4, 1-1/2, 1-3/4,ond 3-1/2in. 3-1/2, 5-1/4,and 7in.
Depth,example availability 3-1/2 in. and greater 3-1/2in. and greater 9-1/4in. and greater
Applw::�bte v�tue'S v�ryW>th �oes, gr�de, �nd or�en��Uon of use. The des�gner !hoold U§e v�tues suppt•ed by �h.e m.lnuf.Kturer ofrh.espe.:ific producf being used. Value'S are based oo dry use and
pe1manen� toad dur�tion. wirh new or like-new producf, �nd must be mulriplied by<lpplic�ble adjustmenr f<KfO<S
'U should be nored th,t LSlls someti� used <ls an � fo<m fo< elev<lted mbs. where load Is applied perpendicular ro wide f<Ke of strands (plank o•ientarlon).
4.2.31-Joists
Wood I-joists are built-up members consisting of two rectangular flanges glued to
a web that is often positioned in a routed slot in the flanges. There are two types of
1-joists commonly used in formwork: those intended for handset applications, and those
intended to be used in a form table (Fig. 4.7). 1-joists used in handset systems are typically
built in depths ranging from 7 to 9 in.and often have a relatively thick web. These joists
are typically built with either LVL or sawn lumber flanges and either plywood or edge
laminated built-up wood webs. These joists feature lateral stability from the relatively low
depth-to-width ratio and can carry relatively high loads over short spans.l- joists used in
table systems are built in depths ranging from 10 to 20 in.and are often built with camber
in simple span applications.These 1-joists are typically built withLVL flanges and oriented
strand board (OSB) webs.Together with sheathing, they are commonly used to make form
tables for supporting horizontal elevated slabs. As some 1-joists are produced for formwork
applications and some are produced for other applications (such as framing lumber in resi
dential floors), the designer should obtain and use the manufacturer's recommendations
to ensure proper selection, sizing, and use of 1-joist products.
Fig. 4.7: Assembly of flying table form using
wood /·joists for beams and joists (Pharo
courtesy MEVA Formwork Systems)
4.2.4 Wood Trusses
Trusses featuring wood members as both
the chords and the webs (Fig.4.8) can be
used as vertical strongbacks or slab form
supporting members.These members
are often supplied for handset systems in
depths ranging from 7 to 9 in. for standard
formwork or in a special size or shape as
part of a custom form component.For
these specialized fabricated products, the
designer may rely on the recommendations
of the manufacturer.
4.3 Plywood
Plywood made with waterproof glue
is the most widely used sheathing for
job-built forms and prefabricated form
panel systems. Relatively large sheets of
plywood save labor in form building, and
the correspondingly large areas of joint
free concrete reduce the cost of finishing
and rubbing exposed surfaces.With proper
care and treatment of form surfaces and
panel edges, five to 10 reuses are common Fig. 4.8: Engineered wood truss joists used in formwork for bridge box-girder web and flange
with standard form grades of plywood (Pharo courtesy PERl Formwork Systems, Inc.)
Fig. 4.9: Plywood is assembled by gluing thin joined under pressure with glues that make the joints stronger than the wood itself. The
wood plies or layers with grain direction number of layers, allowable layer defects, and species of wood affects the structural prop
alternating in adjacent layers erties {Fig. 4.10). Alternating direction of the grain of adjoining layers called crossbands
equalizes strains and thus minimizes shrinkage and warping of plywood panels. Standard
North American plywood generally has the grain of the outer layers parallel to the long
dimension of the panel with crossbands running perpendicular to the long dimension of
the panel.
In the United States, commercial and industrial plywood used for concrete forms is
manufactured from several species and species groups of wood, including Douglas fir,
western larch, western hemlock, Southern Pine, and various other species of pine, spruce,
fir, cedar, maple, birch, beech, and other hardwood species.
Hardwood plywood products are increasingly available in the United States from
sources in Europe, South America, and Australia. Birch plywood from Europe {Fig. 4.10),
with 13 plies in a 3/4 in. thickness, has recommended bending reference design values
ranging from 2500 to 3500 psi and a modulus of elasticity of 1,800,000 to 2,000,000 psi.
Its premium price may be offset by the many reuses that are possible with a smooth and
durable phenolic resin film surface.
Less expensive imported plywood has outer plies of birch and inner plies of spruce
or other softwood, but also has a phenolic resin film surface. Unlike Canadian and U.S.
plywood, European panels typically have the face grain running in the short direction.
To use plywood the strong way, face grain should run parallel to the span (Fig. 4.11). The
detailed information presented in this volume is intended for plywoods manufactured to
U.S. product standards.
The 1/2, S/8, and 3/4 in. thicknesses of plywood in 4 x 8ft sheets are most commonly
used for formwork with sheets of 1/4 in. plywood frequently used as form liners. Scant
Fig. 4.10: Plywood structural properties are thicknesses of plywood are equally if not more common than full-thickness panels. Many
affected by characteristics of the layers and times the scant size panels are loosely referred to as the same thickness as the full thick
reuse is affected by surface durability. From top ness so some confusion can develop between parties. For example, many will refer to
to bottom: U.S. MOO plywood with five layers; a 23/32 in. panel as 3/4 in. despite it being 1/32 in. thinner. In many circumstances, the
U.S. MDO plywood with seven layers; and slight difference doesn't affect the use, but it may for some applications like architectural
European PSF HDO plywood with 131ayers formwork, high form pressure situations, or form systems with tight tolerances. A greater
range of thicknesses is obtainable when needed {refer to Table 4.13).1n addition to the
standard 4 x 8ft sheet, 5 ft widths and lengths ranging from 5 to 12 ft are often available
from stock, although production of these sizes is limited to a few mills in the United States
and Canada, so cost per square foot may be higher and availability may be lower than
standard 4x8ft sheets, particularly with overlaid plywood. Some contractors cut the 5 ft
width to 2-1/2 x 10 ft panels that are easier for one worker to handle than the 4 ft width.
a) Face grain parallel to plywood span - Table 4.13 shows the weight of 4 x 8ft panels of various thicknesses, as well as the weight
strong direction of use per square foot.
Manufacturing tolerances for length and width of plywood panels are +0 and -1/16
in. The thickness tolerance is ±1/64 in. for sanded panels (including certain presanded
overlaid panels) 3/4 in. thick or less, and ±3% of specified thickness for thicker panels.
Unsanded overlaid form-grade plywood panels have a ±1/32 in. tolerance for 13/16 in. or
thinner panels, and ±S% for panels thicker than 13/16 in. Product standards require panels
to be square within 1/64 in. per foot for 4 x 4 ft and larger panels. They must be manufac
tured so that a straight line drawn from one corner to the next falls within 1/16 in. of the
panel edge.
b) Face grain perpendicular ro plywood span
- weak direction of use
4.3.2 Types and Grades
Fig. 4.11: Plywood face grain direction relative Construction and industrial plywood are made in two types: interior and exterior. The exte
to its span direction affects strength and stiff rior type is bonded with waterproof glue, and the interior type is bonded with water-resis
ness to resist loads tant glue. Both types may be used for formwork, but the exterior type is necessary where
CHAPTER4
any reuse is desired. Plywood grades and types are defined in a commercial standard,
NIST PS 1-09, •structural Plywood.• The product standard defines grades of veneer-N and
A through 0-depending on the freedom of the surface from knots and other defects.
Grades 8-8 and 8-C are commonly used for formwork. B-B has both faces of B-grade
veneer, which is a smoothly sanded solid surface sheet with repair plugs and small tight
knots permitted. 8-C has one face of C-grade veneer, which allows small knots, knot holes,
and patches. The product standard also establishes three classes of plywood depending
on the kinds of woods used in manufacture-Class I, Class II, and Structural I. Class I and
Structural I are stronger and stiffer than Class II, and also the most widely available.
The standard further provides that plywood labeled as concrete form-grade shall be mill
oiled unless otherwise agreed between buyer and seller. Mill oiling does not eliminate the
need for oiling on the job, but mill-oiled plywood does give better service than that which
is job treated only. Some form release agents require an unoiled base. If the use of such
agents is planned, it is important to specify unoiled plywood. Edge sealing of plywood
adds protection against moisture and is recommended before the first use of any concrete
form plywood. Moisture ingress through unprotected edges may cause swelling and dete
rioration of wood layers even though the glue itself is waterproof. Plywood designated
OES indicates it has been oiled and edge-sealed during manufacture. Resealing the edges
and tie holes after a number of uses, or sealing freshly cut edges, helps prolong the life of
the forms.
It is a good practice to specify panels carrying the mark of an approved inspection and
testing agency that indicates type and grade, species of veneer, and conformance with
applicable standards. If there is any doubt as to quality of plywood purchased, a certifica
tion of type and grade may be requested. Structural properties of Class I and Structural I
Plyform are listed in Table 4.13 based on APA V345V-2012, ·concrete Forming- Design/
Construction Guide.·
4-14 CHAPTER4
4.3.4 Textured Surfaces
Plywood textures range from the very smooth PSF and HDO to striations, wood grain, or
patterned board-and-batten siding panels. The pattern or design of the plywood is trans
ferred to the concrete, providing decorative surfaces that may have a marked reduction in
light reflection and glare.
Exterior-type textured plywood may be used as a form liner or as the basic forming
panel. Fewer reuses of textured panels can be expected because the repeated stripping
damages plywood. Coating the plywood with a film-forming material such as epoxy or
polyurethane, along with the use of a proper release agent, will make stripping easier and
allow more reuses of the material.
Materia ls
��J f>1���!Tt�:i�c:J'�!�r�!�g
The lumber industry has expanded production of reconstituted wood panels for economic
reasons as well as to conserve forest resources. Wood particle products generally make
more efficient use of trees than plywood, and they are made from younger or faster
growing trees than those commonly used for plywood.
Some of the stronger reconstituted wood panel products are suitable for load-carrying
formwork sheathing. Properly backed with supporting members, the weaker ones may
be used as liners to impart a desired finish to the concrete. These products must be
purchased on the basis of physical properties, not just panel thickness. Only those mate
rials specially manufactured for forming applications-with edge sealing and surface
treatment-can be expected to give durability comparable to concrete form plywoods.
Several categories of products are described in the following paragraphs, using the names
that appear most widely accepted. Some are not yet officially standardized.
Hardboard is a fibrous-felted board, usually made from wood fibers consolidated under
heat and pressure. Tempered hardboard, impregnated with materials such as drying oils,
may be used as a form liner or facing material.
Waferboard is a structural panel made from large thin wafers cut along the grain of
the wood, mixed with waterproof phenolic resin, interleaved in random directions in
thick mats, and bonded under heat and pressure. Its strength, uniformity, and weather
resistance make it suitable for many of the same uses as exterior plywood and soft
wood lumber.
Oriented Strand Boord (058) is a panel product made of layers of thin wood strands cut
in the direction of the grain and bonded with waterproof resin under heat and pressure.
Strands of each layer are aligned parallel to one another, but perpendicular to those in
adjacent layers. A special-grade OSB has been developed for form panel applications,
and some grades of thicker OSB have been used as edge forms for non-elevated slabs.
Performance requirements for both OSB and waferboard are established by NIST PS 2-10,
"Performance Standard for Wood-Based Structural-Use Panels.�
Particleboard or fiberboard panels have limited applications for forming, but may be suit
able as liners under some conditions.
4.4.2 Steel
Steel has long been an important material for the fabrication of special-purpose forms.
Steel framing and bracing are important in the construction of many wood and plywood
panel systems described later. Steel pan components for slab forming, stay-in-place steel
forms, steel braces, and vertical shores are widely used.
Standard lightweight structural steel members-channels, angles, 1-beams, and
others-are used in framing or supporting formwork, often permitting greater spans or
heavier loads than would be possible with timber members. A comprehensive list of steel
members available for this purpose will not be attempted herein, but several handbooks
CHAPTER4
Fig. 4.12: Trapezoidal tubular steel beam,
designed with cutouts to reduce weight, can ocr Fig. 4.13: Adjustable steel beams for slab Fig. 4.14: Plate girder forms of steel have
as joist or stud support; plywood can be nailed formwork spanning between precast concrete strength and stiffness to form both the canti
or screwed directly to the beam (Photo courtesy girders (Photo courtesy Ellis Manufacturing lever and the riser beam for this stadium project
EFCOCorp.) Co., Inc.) without shoring (Photo courtesy EFCOCorp.)
4.4.3 Aluminum
The use of aluminum for forming and shoring applications has
increased because higher initial material costs can be offset by
reduced handling costs and longer service life. Design prin
ciples for aluminum structures are provided in The Aluminum
Association's ADM 1-2010, "Aluminum Design Manual." Lighter
weight aluminum formwork components produce individual
forming units larger than practical with other materials. For
example, welded aluminum basement forms can be made 50% Fig. 4.15: Aluminum form panels ganged into larger units (Photo courtesy
wider than conventional steel-framed plywood panels and yet Western Forms)
weigh about the same. Panels can also be assembled into large
units (Fig. 4.15). Aluminum wall forms are available with an integral pattern to reproduce
brick, stone, and other textures on the finished concrete wall.
Aluminum beams are produced with specially designed flanges (Fig. 4.16) to facilitate
their use as a joist, stringer, or wale. The bottom flange is slotted to receive heads of bolts
connecting it to other components. Top flanges can be shaped to hold wood nailing
strips, 2x2s, and flat 2x4s. Adjustable-length telescoping beams are also manufactured in
aluminum. Aluminum truss supports for flying forms make it possible to move lengths of
deck form in excess of 80 ft at one time. Tubular aluminum has been used for form bracing
and shoring frames.
Aluminum alloys 6061-T6 and 6063-T6, whose properties are given in Table 4.16, are
suitable for use as concrete forms. Initially, a mild etching takes place, and a layer of
oxidized aluminum forms on the form surface. This prevents any further reaction with
fresh concrete and also provides a relatively smooth surface for the concrete. Standard
form oils used to facilitate stripping of steel forms work satisfactorily on aluminum forms,
but an oleic acid-based release agent has been recommended for use on some cast
aluminum forms.
CHAPTER4
stay-in-place insulating polymer forms later
in this chapter.)
Because the polymeric and polymer
surfaced form panels are impervious to
moisture and have smooth faces. concrete
may have more surface air voides than
that cast against absorbent form faces.
Careful selection of release agent and
good consolidation can minimize unde
sirable effects. Manufacturers frequently
recommend that these polymer-faced
panels be used with a reduced amount
of release agent, sometimes without a
release agent. Most users find that a light
coating of release agent protects the
forms as well as facilitates stripping.
For damaged polymeric form surfaces,
repair kits and repair materials are available
for patching and polishing to restore the
smooth surface. Expansion is a possible
problem with polymer and glass fiber
Fig. 4. I 8: Double-woven fabric mar forms for protection of reservoir sloping bank; flowing fine
reinforced polymer forms. Prolonged
aggregate concrete was pressure-injected through the upper layer of fabric on 8 to 10ft centers
exposure to hot sun or the heat of hydra
(Photo courtesy Synrherex)
tion of cement in massive members can
sometimes cause enough expansion to produce misalignment or faulty dimensions. The
designer who is aware of this possibility can detail forms to compensate.
CHAPTER4
It is best to avoid temperature extremes with polymeric liners. Even though stan-
dard polymers are satisfactory up to about 140 to 150°F, they expand with temperature
increases on the job. A 10ft wide polymeric liner can grow about 0.006 in. for every 1°F
temperature increase. Installing the liners warm prevents buckling and pulling out of
nails or staples. Spraying with cold water before placing the concrete helps eliminate liner
bulges due to expansion. The ABS plastics have lower thermal expansion than some of the
other plastics, but they can become brittle and susceptible to damage at temperatures
below0°F.
A number of claims have been made about stripping plastic forms and liners without
using a release agent. Usually, this is possible when the liners are new, but it is preferable
to use a release agent to assure uniformity of the concrete surface and to protect liners
from deterioration.
Information on decorative effects attainable with plastic liners is presented in Chapter 14,
Architectural Concrete.
Rubber Liners
Neoprene and other types of rubber mat have been successfully used as base liners in
repetitive factory precasting work. Rubber liners are characterized by a long life and high
reuse value. Patterned rubber materials intended for other purposes, such as bus plat
forms or industrial floor mats, have been adapted for lining purposes. liquid rubber can
be cast against intricately sculpted patterns and become the mold or form for ornamental
concrete. Pourable mold rubbers can be thickened for use in making brush-on molds.
The rubber is usually brushed in several layers onto a pattern that has been coated with
a release agent. To reduce the amount of rubber needed and to strengthen the form, a
secondary mold of plaster or glass fiber-reinforced polymer is used to support the rubber
contact surface that serves as a liner.
Vacuum Liners
Vacuum treatment removes water and air bubbles from the surface layer of freshly placed
concrete. It is sometimes specified to improve the resistance of a concrete surface to the
action of water flowing at a high velocity. The vacuum treatment also improves appear
ance and durability, but it is generally too expensive to be justified for the latter purpose
alone.
The vacuum treatment is achieved on formed surfaces by using a special form liner
made of two layers of screen or wire mesh covered by a layer of cloth. The liner is sealed
with rubber or caulking material around the edges of the form panel or unit. A series I
of openings in the form panel backing is connected to the vacuum pump. Individual I
vacuum areas are usually several feet long and 12 to 18 in. high so that each area may be I Water extractN!J
I=�/�,.
_
quickly covered by concrete and the vacuum can be applied after concrete placement and
consolidation. One method of vacuum liner construction is shown in Fig. 4.22. I
I
Absorptive Form Liners I
I
At one time, there was keen interest in the use of absorptive materials for lining forms. I
Wallboard of various compositions, canvas and other cotton cloth, blotter-type paper, and 12-Wiremesh
muslin-covered chipboard were among the materials successfully used. The absorptive I
I
linings proved practical in eliminating voids and other common imperfections on concrete
I
surfaces, and also produced surfaces with greater durability and resistance to abrasion!.1
Several government agencies conducted extensive investigations•11and contributed 1----t-��
to development of various absorptive lining products. Millions of square feet of these
materials were used to line vertical or sloping forms for dams, powerhouses, spillways,
pumping plants, and other structural and architectural concrete. In spite of the real advan
Fig. 4.22: One method of constructing o
tages obtained with absorbent form liners, the high cost, misuse, and difficulty in installa
vacuum form lining
tion and removal discouraged their widespread use.
A 1970 reappraisal4-9suggested that the absorptive form liner technique was a useful
concrete casting method that might again be applied as materials technology evolved.
That prediction proved correct in the 1980s with the development of controlled-perme
ability formwork using some of the improved geotechnical fabrics such as nonwoven,
thermally bonded polypropylene. Reports of some successful applications4-10•4-11 weigh the
advantage of more durable concrete surfaces and possible reduction of lateral pressure
against increased forming costs.
Fig. 4.23: Insulating concrete form unit with example, is sometimes used where the
interconnecting ties (Photo courtesy Fox Blocks) roof deck is made of lightweight concrete.
Normal construction with this form board
involves placing the boards, finished face
down, on a system of subpurlins securely
welded to a steel structural frame.The
whole area is then covered with wire mesh
reinforcement and the lightweight roof
deck concrete is placed.
A development based on polystyrene
foam insulation is the growing use of
insulating concrete forms (ICFs) that stay
in place as a permanent part of the wall
assembly (Fig. 4.23 and 4.24).There are
two major configurations for stay-in
Fig. 4.25: Wall and floor system cast in
place ICFs: either block or panel type.ln
polystyrene floor elements form shape of Fig. 4.26: ICF system forming concrete joists
the block system, molded interlocking
joists similar to pan joists; engineering design and slab; shores and stringers below support
blocks of polystyrene are stacked to the
determines spacing for supporting stringers forms, placed concrete, and construction
desired wall height, with window and
and shores during construction (Image cour loads (Photo courtesy lnsui-Deck LLC)
door openings blocked out, often with
tesy Quad-Lock Building Sy5tems Ltd.)
wood or other materials that are left in
place to create nailing surfaces for installation of window and door components.Workers
set any necessary reinforcing steel before placing concrete in cavities in the blocks.The
resulting concrete structure may be post and beam, an open grid, or a solid waffle panel of
concrete, depending on the internal molded structure of the block forms. Face dimensions
of the blocks typically range from 8x 16 in.to 16 x 48 in.A typicai iCF block produces a
wall10 in.thick with 6 in.of concrete in the center.
The panel-type forms are larger than the block type. The units typically range from1x
8ft to 4 x12ft.The inside and outside faces of the form have flat edges, and are joined by
various patented connector ties that maintain the desired wall thickness and sometimes
aid in supporting reinforcing steel.Concrete placed in these forms becomes a solid, flat
concrete wall. The Insulating Concrete Form Association identifies a third type, the plank
system, similar to the panel system but generally with smaller face dimensions ranging
in height from 8 to 12in.and in length from 4 to 12ft. The planks are joined by plastic
ties as part of the erection sequence, while the larger panel systems are assembled into
units before setting into place. Exterior finish materials are applied over or attached to the
insulating forms.
ICF deck forms are also available for constructing either flat floors (Fig. 4.25 and 4.26)
or gabled roofs.Typically, these forms contain some embedded metal stiffeners, and they
usually must be shored to support the freshly placed concrete.
Foam insulation can also be integrated into concrete walls that are formed with conven
tional systems.A tie/shear connector is used in one method to place several inches
of polystyrene insulation at the center of a concrete wall with 3 to 4 in.of concrete on
CHAPTER4
each side. The nonmetallic tie structur
ally connects the two layers of concrete.
Another system places the insulation layer
against the inside wall form. Proprietary
plastic devices embedded in the insulation
layer extend into the concrete to make a
permanent connection.
Welded wire sandwich panels containing
a core of expanded polystyrene can also
serve as support for surfaces to which shot
crete is applied. The core insulation remains
Fig. 4.27: Insulating concrete forms for walls
permanently in place. Conventional steel or
of a residence; forms were braced at intervals
wood framing is also used in combination
around the entire perimeter to ensure stability
with ICF construction as shown in Fig. 4.27.
and alignment during concrete placement
The Insulating Concrete Forms Construction
(Photo courtesy of Fox Blocks)
Manuatm provides step-by-step instruc
tions for those planning to build with ICFs.
CHAPTER4
Table 4.19: Moisture and duration adjustment factors for nail, screw, and bolt connections
WITHDRAWAL LOADS
Equal or less than 19%ot fabrication but more than 19% in service 0.25
Table 4.20: Withdrawal load reference design values, • lb per in. of penetra·
tion, for common wire nails, box nails, and common wire spikes
Comparisons of holding power may be made for softwoods with Tables 4.20 and 4.21,
which show reference design values for nailed joints subject to withdrawal and lateral
loads, respectively. Values tabulated are for one nail. When more than one nail is used, the
load-carrying capacity of the joint is the sum of the values of the individual nails used.
However, if nail installation causes splitting, nails in the split have no strength contribution
to the connection. The end distance and edge distance should be such that splitting does
not occur. Recommendations put forth by the AWC NOS Commentary for end and edge
distances depend on orientation of loading relative to wood grain and nail diameter. It is
not good practice to place nails in long rows in a tension splice.
Design values in Tables 4.19 and 4.20 are for engineered construction where structural
design depends on specific design values for each nail. The AWC NOS for Wood Construction
Nail length
Nails in Plywood
Nailing characteristics of plywood are
"N�il length is insufficient to provide 100 penetr�tion into m�in member. much the Same aS those Of SOlid WOOd.
Note: Based on data from AWC NDS-1011. Tabulated design v�lues must be mu�iplied by applic;�ble adjustment fact<><s(Tabl<>4.18) The advantage of plywood is its greater
resistance to splitting when nails are driven
near the edge. The resistance to withdrawal of nails in plywood is 15 to 30% less than that
of solid wood with the same thickness because the fiber distortion is less uniform than in
solid wood. Grain direction of the face ply has little influence on the withdrawal resistance
along the end or edge of a piece of plywood. When nails driven through sheathing into a
wood supporting member to create a diaphragm are subjected to lateral loading, Cd, = 1.1.
Additional design information can be found in AWC NOS for Wood Construction.
CHAPTER4
Table 4.23: Wood screw reference lateral design value (Z), lb, for single-shear (two-member) connections
Design values based on 10 diameters (100) penetration of screw into the main member receiving the point. Minimum penetration for any strength is 60. For penetration. p,
between 60 and 100, multiply listed values by p/100. No increase for penetration > 100.
design load is the sum of loads for the individual screws. However, if screw installation
causes splitting, screws in the split have no strength contribution. Lateral design values
are based on attaching a 3/4 in. wood side member to a thicker main member. Load values
are subject to adjustment factors given in Table 4.19 for duration of load and moisture
conditions. Note that withdrawal design values in Table 4.22 are given in pounds per inch
of penetration of the screw into the member receiving the point, while the lateral loads in
Table 4.23 are the total per screw. The calculation of a screw connection capacity is illus
trated in Example 4.1.
I#Tiift1tjl4131§ IC.!.!.!Jgt!.!.if!Q
Three 3 in. long No. 10 wood screws are used to attach a 3/4 in. thick Hem-Fir
diagonal brace to a 4x4 S4S Southern Pine wood shore side face. Determine
the ASD capacity of the connection in lateral load due to wind under dry
conditions.
Required penetration= 10(0.190 in.)= 1.90 in.
Actual penetration= 3 in.- 0.75 in.= 2.25 in. OK.
From Table 4.23, Z= 86 lb/screw. Z'= ZC0CM= 86 lb(1.6)(1.0) = 138 lb/screw.
Capacity= 138 lb/screw(3 screws)= 4141b.
Select screw locations to meet appropriate end and edge distances to avoid
splitting.
Fig. 4.30: Connection loaded at angle to grain For main member perpendicular to grain and side member parallel to grain
z1;z�J.
Z' (4.2)
& z; sin2 e + z�J. cos2 a
For main member parallel to grain and side member perpendicular to grain
zljz;J.
Z' (4.3)
a z1; sin1 e + z;.�_ cos2 e
Reference design values in Tables 4.24 through 4.27 are subject to adjustment factors
given in Table 4. 18. Spacing, edge distance, and member end distances of bolts or lag
screws have significant influence on the geometry factor, ell. For a multi-bolt connec
tion, the allowable load is the sum of individual bolt strength values modified by the
group action factor, C g. Refer to AWC NOS for these adjustment factors. AWC NOS also
gives strength data for connections made with split ring and shear plate connectors for
heavy timber falsework. The calculation of a bolted connection capacity is illustrated in
Example 4.2.
lrtfiiffltt*l:ffl@li.!.i11§3![.]11£1!2J!U
A wall form constructed with vertical double 2x6 Douglas Fir-larch strongbacks is braced by 2x6 Douglas Fir larch braces attached
at an angle of 30 degrees by two 1/2 in. bolts, as shown in the figure. Assume load duration less than 7 days, normal ambient
temperature, and wet service conditions. Determine the maximum axial load that can be transmitted to the brace based on the
ASD connection strength.
The connection is loaded in double shear. The main member, the diagonal brace,
will be axially loaded so that Eq. (4.3) applies. From Table 4.25 with 1.5 in. main and
side members and 0.5 in. diameter bolts, z11 = 1050 lb and Zn = 730 lb. Review of AWC
NOS indicates that the connection can be assembled meeting requirements for edge,
end, and spacing distances so that ell= 1.0 and cg = 1.0. From Table 4.19, eM= 0.7, CD
= 1.25, and C1 = 1.0. Other possible adjustments listed in Table 4.18 do not apply and
can be taken as 1.0. Thus
Z11'= 1050 lb(1.25)(0.7)(1.0) = 919 lb Strongback _
z,J.'= 730 lb(1.25)(0.7)(1.0) = 6391b two 2x6s
(9191b)(6391b)
Z' BlSib
)0 (9191b)sin2(30)+{639lb)cos1(30)
For two bolts, the axial load that can be transmitted by the connection to the brace
ftp
Is
P= 2(8281b) = 16561b Brace supporting wall form strongback
The ability of wood braces to carry such loads will be discussed in later chapters.
CHAPTER4
�
�"' � ='¥§d-+
Table 4.24: Bolt reference lateral design values (Z), lb, for single-shear {two
member) connections of sawn lumber or SCL with both members of the same
species
"'
II indicates value when bolt bearing in both members is parallel to grain.
�
sl_ indicates value when bolt bearing in side member is perpendicular to grain and in main member is p<!rallel to gr<tin
�"'
�
:ll
�
'il
';1
�
9
Table 4.25: Bolt reference lateral design value (Z), lb, for three�member (double·
shear} connections of sawn lumber or SCL with all members of the same species
II indicate\valuewhen bolt bearing inboth members is parallel to grain.
sl .indicate\valuewhen bolt bearing in si de members is perpendicular to grain and inmainmember is parallel to grain
�::::::
ml.indicate\valuewhenbolt bearingin
�
�
Table 4.26: Lag screw reference withdrawal design values (W), lb per in. of thread penetration into side
grain of main member
4.5.4 Ties
A concrete form tie is a tensile unit adapted to holding concrete forms secure against the
lateral pressure of unhardened concrete, with or without provision for spacing the forms
to a definite distance apart, and with or without provision for removal of metal to a speci
fied distance back from the concrete surfaces. Twisted wire and band iron are sometimes
used, but because of low strength and the labor of assembly and installation, they are
considered acceptable only for simple structures. A wide variety of ready-made ties, as
shown in Fig. 4.31, with safe load ratings ranging from 1000 lb to more than 50,000 lb, are
in general use. Safe loads, taken from manufacturers'recommendations, are based on a
safety factor of 2. Wedges, nuts, or other holding devices are shown schematically and
may vary from that pictured. The wide range of safe loads indicates that there are several
diameters, grades of steel, or different fastener details. Ties consist of an internal tension
unit and an external holding device and are manufactured in two basic types:
Continuous single member, in which the tensile unit is a single piece and a specially
designed holding device is added for engaging the tensile unit against the exterior of the
form. These ties may be rod, band, channel, or angle in cross section, and may be cut to
length on the job or completely prefabricated. Form-spreading devices are an integral part
of some of these ties. Some single-member ties may be pulled as an entire unit from the
concrete. Others are broken back at a weakened section and a predetermined distance to
facilitate snapping. Some are cut off flush with the concrete surface.
Internal disconnecting rype, in which the tensile unit has an inner part with threaded
connections to removable external members (bolts) that complete the tensile unit and
have varied devices for holding them against the outside of the form. This type of tie is
available with or without spreading devices. The internal member generally remains in
the concrete.
These two types of tying devices are often identified as form clamps, snap ties, he bolts,
she bolts, wedge damps, coil ties, or rod damps. Except for taper ties, the continuous
single-member type is generally used for lighter loads, ranging up to about 5000 lb safe
load. The internal disconnecting type of tie is available for light or medium loads but finds
its greatest application under heavier construction loads up to about 70,000 lb.
ACI 347R recommends a minimum safety factor of 2 based on the ultimate strength of
the assembly for all concrete form ties. This makes form tie safety more consistent with
that of other components of the formwork.ln the past, a safety factor of 1.5 was used and
may still appear in some catalogs. To comply with ACI 347R recommendations, use only
75% of any allowable loads that are based on a 1.5 safety factor. Where the ultimate load
rating for a tie is given, the form designer can use design loads based on any required
safety factor. However, in no case should the maximum load applied to the tie cause stress
equal to or exceeding the yield point of the steel.
m.l indicates value when lag screw bearing in main member is perpendicular to grain and in side member is pilrallel to grain.
�
�
Flat Tie
Used to secure and space modular panel forms. Avail·
able in several configurations in both steel and fiber
reinforced polymers.
Safe loads: 1SOO, 22SO, 3000, and3SOO lb
Loop Tie
Secures and spaces prefabricated modular forms.
Notched for a 1 in. breakback. Crimp is anti-turn
iitQ iQt feature.
Safeloads:2250and30001b
Snap Tie
Used for job-built forms. lighter construction. May have
cone spreader and waterseal washer. Notched for 1 in.
breakback.Aiso available in stainlesssteel.
Safeloads:2250;�nd33501b
Pencil RodTie
Mild steel rod available in IOor 20ft lengths or 600ft
coils. Safe working load dependent on tightened set
screw and 90-degree bend of rod at each end.
S;�fe loads: 1125 to 3750 lb
Taper Tie
Used where specs require or permit complete removal
of tie from concrete.Tie is reusable.
Safe loads:7500 to 58,000 lb
She-Bolt Tie
Heavy duty, with reusable end bolts. No internal
spreader,but e�ternalspreaderbracket available
Safe loads:4900 to 64,000 lb;
up to 155,000 in high-strength steel
CoiiTle wlthCone s
Designed for medium to heavy construction. With or
withoutcone spreaders.Boltsreusable
Safe loads:
two-strut. 3000 to 13,500 lb;
four-strut. 9000 to 37,000 lb
Fig. 4.31: Some common one-piece and internally disconnecting ties; safe loads are examples of ranges available, which vary by manufacturer
and grade of steel (Images courtesy Meadow Burke, LLC, and Williams Form Engineering Corp.)
Fig. 4.35: Representative of the many special-purpose tying devices are these for attachmenr of
slab edge form to formed deck or structural steel members (Images courtesy Meadow Burke)
Regardless of the type of tie, the external holding device, such as those shown in Fig.
4.32 through 4.34, should have an adequate bearing area so that when the tie is loaded
to its maximum safe load, crushing of the wood or other bearing material would not take
place. This is further explained in the section on tie design in Chapter 7.
In some situations, ties are anchored to a slab form or to structural steel. Figure 4.35
shows examples sometimes used near the tops of beam forms, slab edge forms, and
wall forms.
CHAPTER4
Fig. 4.38: One of the several available anchors for
off-rock tying (Image courtesy Meadow Burke)
Anchor bolt
Ties For Water-Retaining Structures
Where ties are permitted in construction Anchorage unit
of water-retaining structures, they should
be designed to prevent seepage or flow
(b)
of water along the embedded tie. What
constitutes a leak-proof tie varies with the
head of water retained and the resultant
pressure on the concrete surface. Under
some circumstances no ties are permitted
at all. If ties are used, they are not usually
pulled completely out of the wall because
the resultant hole is difficult to seal. The
ends of tie metal should be at least 1 in.
back from the wall face.
The process of breaking back or discon
( • • •
necting tie ends may loosen the tie in
Fig. 4.39: Simple screw anchor: (a) showing unit assembled in concrete and individual parts;
the wall, providing a channel for water
and (b) several other types of anchorage units (Images courtesy Dayton Superior)
seepage. To overcome this problem, some
manufacturers have crimped or otherwise deformed the tie to improve bond and have
attached round metal or neoprene washers as waterstops at the middle of the ties. Plug
ging tie holes with grout is helpful, but sealing them with epoxy resin injected under pres
sure is more effective. Several manufacturers have developed rubber or other synthetic
compression plugs to minimize water seepage through tie holes (Fig. 4.37). Keeping the
ties free of oil helps maintain watertightness.
4.5.5Anchors
Form anchors are devices used to secure formwork to rock or to previously placed concrete
of adequate strength. Rock anchors are also used to support forms by off-rock tying (Fig.
4.38). The anchor unit is placed in a hole drilled in the rock. When the bolt or external
fastener is inserted, it expands the anchor, thus tightening it in the rock. Some rock anchors
are designed to be surrounded by grout in the rock cavity. Concrete anchors are normally
embedded in concrete during placement. A number of the various types of anchors avail
able for embedment in fresh concrete are shown in Fig. 4.39. There are two basic parts:
n
concrete, where extra holding power is achieved by increasing anchor length.
Load ratings for anchors are commonly based on pullout loads. Design must consider
bending of anchors due to form loads. ACI347R recommends a safety factor of 2 or 3 for
form anchors, depending on project conditions. Safe working loads or ultimate strengths
of anchoring devices in shear and tension are often given in manufacturers' literature. The
tensile capacity of the anchor depends on the strength of the concrete in which they are
embedded, shape of the anchor and area of contact between the concrete and anchor,
depth of the embedment, edge distance to the anchor, effect of group behavior if there
are multiple anchors, and interaction with any shear force acting simultaneously. ACI
Fig. 4.40: Hangers used to support forms from 318-11, NBuilding Code Requirements for Structural Concrete," has methods for evaluating
existing structural members (Image courtesy strength of cast-in-place anchors. ACI318, Appendix D, Anchoring to Concrete, states
Dayton Superior) that its provisions are for in-service conditions, rather than for construction conditions.
However, the ACI318 provisions can provide helpful understanding of these strength
reducing factors.
Many form anchors are set in the relatively low-strength concrete used for massive
structures, and development of adequate tension and shear capacity may be a limiting
factor in early reuse of the cantilever forms that the anchors support. Some manufacturers'
strength data for their anchorage products are based on tests in actual concrete speci
mens at various low strength levels. Using data of this sort and the estimated compres
sive strength of the concrete at early ages (3 to 7 days), tentative selections of anchoring
devices needed for a given job can be made {see also Chapter 16 on mass concrete).
Specific selections for any large job should be field tested under conditions anticipated for
the duration of the project.
4.5.6 Hangers
There are a number of ready-made devices for hanging forms from steel or precast
concrete structural members, as shown in Fig. 4.40. Such forming may be used for the
construction of a supported slab, for building the fireproofing required for the steel
members, or for construction of a slab composite with beam framing. Applications
of these and similar devices are shown in Chapter 11. Actual working loads vary with
dimensions and strength of the material used, as well as hanger design details, but some
representative values are: for the snap tie hanger, 3000 lb total load; for the threaded rod
hanger, 6000 to 13,500 lb total load; for the coil bolt with dual rods, 4500 to 15,000 lb
total load; and for the adjustable joist hanger, 3000 lb. These figures based on manufac
turers' suggestions show a probable range of strengths for typical commercially available
devices; the user must verify the strength of their specific selection.
External holding devices are similar to those used for tie rods. ACI347R recommends a
safety factor of 2 for hanger assemblies. When checking manufacturers' safe load ratings,
note carefully whether suggested working load is given on a per leg basis or as the total
capacity of the hanger. Two-sided hangers must be loaded equally on both sides of the
supporting beam, or the hanger will not stay in the correct position. Form hangers should
also closely fit the flange or bearing surface of the supporting member so that applied
loads are transmitted properly.
Under some field conditions, use of a jack supported on the lower flange of the steel
beam may be preferable to hanging the forms. Several devices available for this purpose
may also be adapted for use with precast concrete girders.
Fig. 4.41: Round friction collar carries brackets 4. 5.7 Friction Collars and Support Brackets
that adjust to support forms for construction Vertical support for forms may also be provided by devices attached to columns or
above. Load capacity may be 50,000 lb or more bearing walls of the structure. Such hardware includes friction collars (Fig. 4.41) and
per side; collars are also made ro fit rectan support brackets {Fig. 4.42) that are attached to columns or walls with through-bolts or
gular columns (Photo courtesy EFCO Corp.) heavy embedded anchorages. Both the brackets and collars have adjusting screws to
CHAPTER4
Fig. 4.44: Plastic-tipped bar form spreader for wall
forms that can be clipped to horizontal rein
forcing bars to maintain correct spacing berween
the forms (Image courtesy Dayton Superior)
Fig. 4.42: Bracket attached to column or wall Fig. 4.43: Plastic side form spacers, designed
supports slab form assembly without vertical to snap onto reinforcing bars, are generally
shores. This one has roller head to facilitate pierced with large openings to facilitate flow
movement of flying forms (Photo courtesy of concrete and minimize thermal expansion
Symons by Dayton Superior) of spacer (Image courtesy Dayton Superior)
make minor changes in form elevation before placing the concrete. Rollers on some of
these brackets facilitate horizontal movement of forms-for example, sliding out a flying
form assembly (see Chapter 11 ). Supporting a slab-forming system on such brackets may
make it possible to eliminate reshoring because most construction loads are transmitted
directly to walls or columns and not to the new slabs.
CHAPTER4
Specialized hardware is a major compo
nent of many panel systems. Clamps, such
as those shown in Fig. 3.5, 4.34, and 4.48,
join panels into larger units frequently
requiring only limited alignment members.
There are four basic panel system types:
1. Unframed plywood panels sometimes
backed by steel braces. locking and
tying hardware are essential parts of
the system, and the lock that holds
ties is frequently part of the waler
support (Fig. 4.33).
2. Hand-set panels with metal frames and
a plywood face, with or without metal Fig. 4.48: Steel-framed panel ganged with
bracing on the back.They are also quick-acting clamps for wall construction
available in both steel and aluminum (Photo courtesy Symons by Dayton Superior)
(Fig. 4.49) configurations.
3. All-metal panels, sometimes hand-set
depending on size, having a metal
face supported by a metal frame.
They are available in both aluminum
{Fig. 4.50) and steel (Fig. 4.51)
configurations.
4. Heavier metal-framed panels,
frequently having tubular metal
frames (Fig. 4.52 and 4.53) with facing
of plywood, steel, or full plastic.These
panels are suitable for greater loads.
They are often ganged together for
crane handling in large units with
limited external bracing and align
ment members.
Although panel systems were developed
primarily for wall forming, many of them
are adaptable to slab and column forming,
and smaller ones have been successfully
used in forming beams. Users should
Fig. 4.49: Steel-framed plywood-faced panels,
carefully select a system, based on manu Fig. 4.50: Aluminum-framed panels with
2 ft wide and up to 8fthigh, have handles
facturers' data that is best suited to their aluminum or plywood facing are the basis
for convenience in carrying, not for tie-off
particular project conditions. Prefabricated for lighter-weight forming system strong
or attaching fall protection devices (Image
panels ofTypes 1 and 3 are most often used enough for commercial use (Photo courtesy
courtesy Brand Energy& Infrastructure)
for general and light construction where Western Forms)
CHAPTER4
concrete is being placed. These laminated
tubes are available in two types: one with
a weather-resistant ply designed for use in
cast-in-place construction in exposed areas,
and the other one for use where they are
completely protected from weather during
storage and use. Spirally wound steel ducts
are frequently used for large post-tensioning
tendon ducts and other applications where
cables or other material must be fed through
concrete structures after concrete place
ment. They must be tied in place to prevent
floating and assure correct alignment.
Corrugated paper units, much like card
board boxes, are used for forming voids in
stabs, brick ledges, blackouts, pockets, and
other shapes. The units are either left in
place or removed depending on the applica
tion. Inflatable rubber tubing units have
been used for forming voids. The rubber
forms are laid in position and then inflated.
A loose wire coil is used to hold the tube in
place. Reinforcing mesh lain on top of forms Fig. 4.56: Slab and girder voids are often Fig. 4.57: One-piece glass fiber-reinforced
also helps keep them from floating. When formed by laminated fiber tubes equipped polymer round column forms that bolt or
the concrete has hardened, the form is with end closures and tied down with wire to clamp along a single joint can be reused
deflated and withdrawn through a bulkhead prevent movement during concreting (Photo many times
or edge form of the slab. Specially woven courtesy Sonoco Products Company)
nylon or cotton reinforcement governs the
way the tube contracts on deflation and thereby aids in breaking bond with the concrete.
For large-diameter sewer and industrial work, duct formers have been made of several
plies of rubberized fabric. The hose-like form is open at both ends to contain airtight
bulkheads through which the form is inflated. These large forms are inflated at low pres
sure sufficient to maintain the shape and carry loads imposed on the form, but without
stretching the form material.
Expanded polystyrene has been frequently used as a void form material because it is
rigid, lightweight, easily handled, and easily cut on site. It is strong enough to withstand
usual concrete pressures, and because it is a closed-cell material, it does not absorb water
during storage or concrete placement. The material does not rot or decay and can remain
in the cavities. If it is necessary to leave the cavities hollow, the polystyrene can be cut out.
Metal Deck
Ribbed or corrugated steel sheet is used
both as a permanent form for cast concrete
and as a combined form and reinforce
ment. In roofs, it may be the permanent
supporting member for lightweight
insulating concrete fills. Any steel deck
Fig. 4.60: Two-piece steel round column form and two-piece capital form available in a variety
providing continuing support as reinforce-
of diameters (Photo courtesy EFCO Corp.)
ment should be galvanized. Steel forms
acting only as stay-in-place forms are generally"black" or uncoated.
Metal deck forms are used for concrete floor (Fig. 4.61) and roof slabs cast over steel joists
or beams and for bridge decks on both steel and precast concrete girders (Fig. 4.62). They
also may be used to form the top slab over pipe trenches or other inaccessible locations
where it is impractical and expensive to remove wood forms. Metal deck forms can be set
in short lengths between precast joists where shear connectors project from the top of the
precast members, or over several spans just as with steel members with no stirrups.
CHAPTER4
When the forming material is installed,
it is usually secured by clips attached to
the top of the joist, by welding to the tops
of steel beams, or welding to inserts cast
in the concrete members. Varying gauges
Fig. 4.6 1: One type of stay-in-place cold
and corrugation styles make these forms
formed steel floor deck; in this example,
usable on a range of clear spans depending
web indentations indicate it will become
on the number of spans over which the
composite by interlocking with the concrete
deck is continuous, slab thickness, concrete
to provide horizontal shear transfer (Image
unit weight, and construction live load.
courtesy CS/ and Oswald Design)
Frequently, the objective is to use a deck
depth, configuration, and gauge that can support the fresh concrete and construction live
load without placement of shoring under the deck to further reduce its clear span.
Some galvanized steel deck-forming materials combine form and positive reinforcing
in one piece. This is achieved by deeper corrugations and raised lugs on the corrugations.
Transverse wires welded across the corrugations in one such product take the place of
temperature steel reinforcing, whereas others require added temperature steel to reduce
the potential for shrinkage cracks. Regardless of manufacturers' claims, these products
cannot take the place of negative reinforcing bars (top steel) in continuous slabs over
beam, girder, or wall supports.
Wherever metal deck forms are to become a structurally active part of the permanent
structure, the engineer/architect should specify gauge, thickness, depth, physical dimen
sions, and properties, as well as special shoring requirements, if any.
Precast Concrete
Precast concrete panels or units serve as stay-in-place or permanent forms for various struc
tural elements (see also Chapter 14 on architectural concrete and Sections 7.4 and 7.7 of
ACI347R reproduced in the Appendix of this book). In some applications, these are exposed
aggregate panels that produce a specified architectural surface. Lightweight concrete dome
pans have been used as stay-in place forms for two-way concrete joist systems. The precast
Fig. 4.62: Corrugated metal forms that stay
units may also be used as self-supporting form panels or as form liners to produce a special
in place are shown supported on precast
surface on the concrete. For bridge decks, concrete form panels may act compositely with
concrete bridge girders (Photo courtesy CSI
the cast-in-place concrete and become part of the load-bearing structure.
and Oswald Design)
Glass fiber-reinforced concrete (GFRC) panels are also used as stay-in-place forms for
bridge deck soffits, beam and column sheathing, and in areas where an architectural
quality surface is desired. The GFRC is made of chopped glass fibers and cement mortar
combined in a spray-up process to a thickness of about 1/2 in. for formwork applications.
4.7 Shoring
A number of shoring systems have been developed with features for adjustment, mating
members to be supported, and increasing productivity. Miscellaneous hardware is avail
able for joining components; connecting braces; adjusting height; and leveling, releasing,
and lowering components when stripping.
When proprietary shores or methods of shoring are used, manufacturers' recommenda
tions as to load-carrying capacity should be followed and checked that all recommenda
tions are supported by test reports from a qualified and recognized testing laboratory.
CHAPTER4
Fig. 4.66: Shores made of two pieces of Fig. 4.67: Metal fitting slips over the end of a Fig. 4.68: One of the many designs of all
dimension lumber are joined by a proprietary 4x4 or a 6x6, converting it into an adjustable metal adjustable shores; bracing can be
clamping device that permits length adjust shore (Photo courtesy Ellis Manufacturing attached when needed with special clamps
ments. (Photo courtesy Ellis Manufacturing Co., Inc.) (Photo courtesy EFCO Corp.)
Co., Inc.)
Fig. 4.69: Shoring towers assembled for support of concrete bridge superstructure during place
ment (Photo courtesy PERl Formwork Systems, Inc.)
Cot+C,Mt+CVMI. (5.1)
cot+c,Mt +c
v.w, +CPf+c�� (5.2)
c" (5.6)
ASCE/SEI7-1 0, HMinimum Design loads for Buildings and Other Structures; calibrates
calculation of wind and earthquake loads so their load factors are 1.0 in lRFD combina
tions. Thus, in ASD combinations, reducing factors of 0.6 and 0.7, respectively, are applied.
lateral pressure of concrete is indicated as a separate load without combination in Eq. (5.6)
as it does not combine with the other loads in most cases. However, there are situations
where lateral pressure can combine with other loads and these situations have to be
recognized by the form designer when this occurs. For example, if a freestanding concrete
wall must be cast without form ties, the external braces must resist not only the wind and
eccentric personnel loads on the work platform but also the concrete lateral pressure.
Some loads have a low probability of occurring at the same time. As noted in ASCE/SEI 37,
the most unfavorable effects from both wind and earthquake loads should be considered
where appropriate, but they need not be considered simultaneously. Similarly, CH need not
be assumed to act simultaneously with wind or seismic loads.
(5.8)
CHAPTER 5
The load factor applying to eDt is 0.9 when counteracting wind or seismic loads, 1.4 when
combined with only construction and material loads, and 1.2 for all other combinations.
For LRFD, ASCE/SEI 37 provides arbitrary point in time (APT) factors of 0.3 that can be
multiplied by W (instead of 1.0), 0.5 by ePf (instead of 1.6), and 0.5 by eH (instead of 1.6)
in combinations where two or more variable loads appear. The effect of the APT factors
is seen in Eq. (5.9), (5.10), and (5.11). At least one of the variable loads must appear at full
value and the other variable loads, if not correlated to be their maximum at the same
time, are multiplied by their APT value. This reduction recognizes that maximum wind and
maximum personnel load will not occur at the same time when both are considered. A
combination involving o.sePf + 1.0W might govern for some components, while a combi
nation involving 1.6ePf + 0.3W might govern in others, as shown in Eq. (5.9) and (5.10}.
lateral pressure can combine with other loads as discussed previously. Similary, eHneed
not be assumed to act simultaneously with wind or seismic loads.
5. 3. I Dead Loads
While concrete unit weight may range
anywhere from 40 to 375 lb/ft1, the majority
of all formwork is for concrete with a unit
weight of 140 to 150 lb/ft3. Minor variations
in this weight are not significant, and for
most cases 150 lb/ft3 including reinforcing
steel is commonly assumed for horizontal
formwork design.
Assuming a unit weight including an
allowance for reinforcing steel is reasonable
in most situations because the volume
of steel is often less than 1 or 2% of the
total concrete member volume. The use of
higher-strength prestressing steel typically
results in even lower steel volume. The rein
forcing steel unit weight, 490 lb/ftl, is higher
but it also displaces its equivalent volume
of concrete. For formwork supporting
concrete with an unusually high concentra
tion of steel reinforcement, adjustments to
account for the actual amount of rein- Fig. 5.1: Loads of material and equipment placed on the form during construction must be
forcing steel should be investigated. Rein- within the design limits of the formwork system
forcing bar properties are given in Table 5.1.
Formwork loads often vary from as little
as 31b/ft1 to about 151b/ft1• However, loads Table 5.1: ASTM standard steel reinforcing bars
of some steel heavy-duty forms for special
applications may approach 25 lb/ft1. For
0.375 0.11 0.376
design, a uniformly distributed load allow
ance is often assumed for the formwork.
0.500 0.20 0.668
Formwork load is sometimes neglected 0.625 0.31 1.043
when its contribution is very small in rela 0.750 0.44 1.502
tion to the concrete load and the construc 0.875 0.60 2.044
tion live load. Whatever assumed formwork
1.000 0.79 2.670
load is used, it should be verified once the
1.128 1.00 3.400
final formwork has been designed.
Normalweight concrete, with a density 10 1.270 1.27 4.303
of 150 lb/ft1, will place a load on the forms II 1.410 1.56 5.313
of 12.5 lb/ft2 for each inch of slab thick 14 1.693 2.25 7.650
ness. Thus, a 6 in. slab would produce a
18 2.257 4.00 13.600
dead load of 12.51b/ftl x 6 in. or 7Sib/ft1,
5. 3. 2 Live Loads
ACI 347R- 14, �Guide to Formwork for
Concrete," recommends that both vertical
supports and horizontal framing compo
nents of formwork should be designed for
a minimum live load, Cl'f' of so 1b/ft1 of hori
zontal projection to account for workers,
runways, screeds, and other equipment
(Fig. 5.2). When motorized carts are used,
the minimum load should be 75 lb/ftl.
Regardless of slab thickness, the minimum
design value for combined placed concrete
dead load and personnel and equipment
live load for ASD should be 100 lb/ft1, or
125 lb/ft1 if motorized carts are used. For
LRFD, the minimum factored dead plus live
load from Eq. (5.8) should be 140 lb/ft1, or
180 lb/ft1 if motorized carts are used.
Table 5.2, showing vertical load on
forms for various kinds of slabs of varying
thickness, has been developed using the
minimum live load of 50 lb/ft1 recom
Fig. 5.2: Live load includes concrete crew, placing equipment and finishing equipment which mended by ACI 347R, and neglecting
may be temporarily concentrated in small areas the formwork dead loads, which must be
added by the designer.
Where slab form members are continuous over several supporting shores, placing
concrete on one span of the form member may cause uplift of the form in other spans, as
shown in Fig. 5.3. Forms must be designed to resist such conditions. If the form members
are not secured to accommodate this uplift, such as by shore dips, they should be
designed and built as simple spans.
On slabs inclined no more than about
�
45 degrees, the sliding tendency of a
relatively thin layer of fresh, low-slump
concrete is resisted by internal friction
within the concrete and by friction between
the concrete and the form. However, the
slab form must be rigidly connected to its
supports. Where there is a significant head
CHAPTER 5
Table 5.2: Vertical load for design of slab forms, lb/ft2
16
10
12
14
20
r��
begins to stiffen and the lateral pressure is reduced to less
than full liquid pressure by the time concrete placement
is completed in the upper parts of the form. The effective
lateral pressure-a modified liquid pressure-has been
found to be influenced by the concrete density, rate of
1'.:--::-"--� placement, temperature of the concrete, the admixtures and
cementitious materials used, and effect of vibration or other
consolidation methods. How these factors affect lateral
pressure will be discussed briefly before considering the
magnitude of pressure to be used in form design. The lateral
pressure information in this chapter applies to formwork
that is stationary. For information on concrete lateral pres
sure for slipform work, refer to Chapter 18.
Rote of Placement
The average rate of rise of the concrete in the form is referred to as the rate of placement.
As the concrete is being placed, lateral pressure at a given point increases as concrete
depth above this point increases {Fig. 5.5). Finally, by consolidation, stiffening, or by
a combination of the two, the concrete at this point tends to support itself, no longer
causing lateral pressure on the forms. The rate of placement has a primary effect on lateral
pressure, and the maximum lateral pressure is proportional to the rate of placement, up to
a limit equal to the full liquid pressure.
-
Vibration
Internal vibration is the primary method of
consolidating concrete. It causes concrete
to behave as a fluid for the full depth of
vibration and results in temporary local
10 to
lateral pressures that are at least
20% greater than those occurring with
simple spading. Because internal vibration
is a common practice, forms should be
designed to withstand the greater pressure
and depth of vibration must be controlled
during concrete placement. Forms must
also be made tight at joints to prevent
leakage due to vibration.
Revibration and external vibration
are also accepted practices for certain
types of construction, producing even
higher loads on the forms than normal
internal vibration and requiring specially
Fig. 5.5: Pumping permits rapid placement of concrete but can increase lateral pressure when
designed forms. During the process of
forms are filled to full height before any stiffening of the concrete takes place
CHAPTER 5
revibration, the vibrator is forced down through freshly placed concrete into layers
that have stiffened. local total pressures up to 300 lb/ft1 per ft of head of concrete
have been recorded with vigorous revibration.
External vibration, also called form vibration, is performed by attaching vibrators to the
outside of the form (Fig. 5.6). The form itself is vibrated and in turn transmits this vibration
to the concrete. External vibration hammers the form against the concrete, causing wide
fluctuation in lateral pressure. The frequency and amplitude of external vibration must be
adjusted in the field to avoid damaging the forms, and yet be sufficient to consolidate the
concrete. Recommendations for selection and use of form vibrators are given in ACI309R-05,
"Guide for Consolidation of Concrete.�
The effects of revibration and external vibration have not been sufficiently investigated
to be expressed in a standard formula, and therefore pressure formulas in this manual are
limited to concrete vibrated internally at the time of placement.
Temperature
The temperature of the concrete at the time of placing has an important influence
on pressures because it affects the setting time of concrete. At low temperatures, the
concrete takes longer to stiffen, and therefore a greater depth can be placed before the Fig. 5.6: Use of external form vibrators results
lower portion becomes firm enough to be self-supporting. The greater depth of liquid in concrete lateral pressures that cannot be
head that develops in the form results in higher lateral pressures. It is particularly impor predicted by the AC/347R formulas (Photo
tant to keep this in mind when designing forms for concrete to be placed in cold weather. courtesy Vibco Vibrators)
Concrete Chemistry
Cement type, use of retarding admixtures, and use of fly ash or slag cement as a cement
replacement can all have a significant effect on lateral pressure. The chemistry coefficient
of ACI347R provides a way to quantify the effect of retarding admixtures, cement type,
and use of fly ash or slag cement on lateral pressure.
Concrete Slump
The slump of conventional concrete in a workable range less than 7 in. does not have
a major influence on the lateral pressure of concrete. Because data on conventional
concrete with slump greater than 7 in. indicates higher pressures can result, ACI347R
recommends a liquid head pressure for that greater slump range.
Self-consolidating concrete (SCC) consistency is measured by slump flow rather than
slump. SCC has some advantages for placement, but its high flow characteristic has an
impact on the lateral pressure. Studies of SCC have produced several different methods for
controlling its behavior and estimating its lateral pressure. However, because this is still an
area being advanced through active research, ACI347R continues to recommend the use
of a full liquid head unless project-specific understanding of the behavior is developed or
pressures are controlled by measurement to assure safety.
Other Variables
Other variables measured at various times that have been found to have an effect on lateral
pressures include amount and location of reinforcement, ambient temperature, pore water
pressure, maximum aggregate size, placing procedures, depth of placement, cross section
of forms, and smoothness and permeability of the forms. However, with usual concreting
practices, the range of these variable effects is generally small and is usually neglected.
�: ?·
EqUIIIillenl
llydro&ta!IC ,' same formulas were given again in ACI347-68 and ACI 347-78, with an equivalent liquid
head formula added in ACI 347-78 for walls with placement rates greater than 10 ftlh. These
.. documents restricted application of the formulas to mixture and placement conditions on
which the original formulas were based, and cautioned about other mixtures and placement
conditions without giving specific guidance for them.
Meanwhile, as admixtures and cement replacements proliferated, ACICommittee 347
recognized that a form-pressure recommendation with too small a margin of safety could
result in form failures, given current construction practices. Thus, in ACI347R-88, the basic
lateral pressure formula, Cc,=wh, with no controlling maximum or minimum was recom
Fig. 5.7: Concrete lateral pressure distribution mended for all placements that did not fit the specific limiting conditions set for the original
formulas-Type Icement, unit weight 150
lb/ft1, no pozzolans or admixtures, slump 4
Table 5.3: Applicable lateral pressure equations for concrete other
in. or less, and normal vibration to a depth
than sec
of 4 ft or less. These same pressure recom
mendations were repeated in ACI347R-94.
However, by that time, virtually no concrete
was being produced without admixtures
and a variety of cement types and cement
replacements such as fly ash and slag
cement were in active use so that only the
liquid head formula realistically applied. In
S.7in.
ACI347-01 and 347-04, ACICommittee 347
used accumulating data and researchs-9.s.lo
on lateral pressures to present revised
pressure formulas using chemistry and
unit weight coefficients to cover a variety
of mixtures. ACI347R continued the same
basic provisions but clarified the presenta-
tion of the recommendations.
cc,=wh (S.lSa)
[9000R
Cc-=CcCw 1 5 0 +--
l (S.lSb)
T
with a minimum of 600Cw lb/ft2, but in no case greater than wh
CHAPTER 5
R = rate of placement, ft/h; Table 5.4: Chemistry coefficient, Cc
T = temperature of concrete, °F; and
w = unit weight of concrete, lb/ft3.
None 1.0
I, ll, or Ill N one None
Included 12
ACI347R also recognizes that, alternately,
a method based on appropriate experi
None 1.2
<70% <40%
mental data can be used to determine Included 1.4
Aoy
the lateral pressure used for form design None 1.4
?:70% 2:40%
or a project-specific procedure can be Included 1.5
implemented to control field-measured
'Retarders include any admixture, such as a retarder, retarding water reducer, retarding mid-range water
pressures in instrumented forms to the reducing admixture, or high-range water-reducing admixture (superplasticizer), that delays setting of
maximum pressure for which the form was concrete.
CHAPTER 5
ift1tirt14*1!ft.!§·'
t!ftffllmtt1J14l'''"Jm:tmt'A6'3§· ·'if1'
For the same column as in Example 5.1 using the same concrete mixture at the same
temperature, but at a rate of 20 ft/h, the base value is 3150 lb/ft2 fromTable 5.6.
Applying the same coefficients as before results in
but this is greater than wh= (145 lb/ft1 x 20 ft)= 2900 lb/ft1
so 2900 lb/ft1 is taken as the maximum, with the distribution as shown in Fig. 5.8{b).
ift1tirt1411if!!M1mtt1Ji4l''''4 ili!l@ff#l§
For a 10 ft column made with normalweight concrete with a slump of 4 in.
containing Type I cement, a retarder that is placed at 2 ft/h, a temperature of 70°F,
and is vibrated to depths less than 4ft,Table 5.6 gives a base value of4071b/ft2•
From Table 5.5, the density coefficient is 1.0 and the chemistry coefficient is 1.2.
Applying the coefficients
This is less than the 600Cw lb/ft1 minimum specified for Eq. (5.15b), so 600 lb/ft1 will
be used. The pressure of 600 lb/ft1 will occur at a depth of (600 lb/ft2)/{145 lbfftl), or
4.1 ft, below the top of the concrete, and the 600 lb/ft1 value applies for all points
below this depth. The pressure envelope for design is shown in Fig. 5.8(c).
§]
more than 15 ft/h.
Table 5.7 gives base values of the
expressions
[ 9000R l [
O 43,000 2800R
15 0 +-- an d 1 S +--+--
T T T
l
2
600 lbft
/
to which the chemistry coefficient and unit
weight coefficient ofTables 5.4 and 5.5 must
al h =20ft b)h=20ft c) h =10ft
be applied to get maximum pressure values
for form design. See Examples 5.4 to 5.6. Fig. 5.8: Example column concrete lateral pressure diagrams
Remember that the pressure given by Eq.
{5.15a) through (5.15c) and shown in Fig.
5.8 and 5.9 represent envelopes of maximum pressure exerted during the total time required to
fill the form.The figures do not show pressure distribution at any single point in time. Because
studs and wales are ordinarily uniform in size and spacing throughout their entire height. only
the maximum pressure value will be needed for their design. However, wale and tie spacings may
be increased near the top of the forms to take advantage of lower maximum lateral pressures
there.
Examples 5.4 to 5.6 are for placement conditions represented by Eq. (5.15c). lf wall place
ment is faster than 15 ft/h, Eq. (5.15a) must be used. Equation (5.15b) can be applied for walls
where placement height is 14 ft or less, and the rate of placement is less than 7 ft/h. Base
values for Eq. (5.15b) are shown in the boxed-out areas ofTable 5.7. See Example 5.7.
mmt11t¥$!1,!f111tff1tt1Qi¥!jlli§fti,fj
If a wall form 6 ft high is filled under the same conditions shown fromTable 5.7 with adjustment.The resulting pressure envelope
in Example 5.4, the limit ofwh-that is, 1451b/ft1 x 6 ft= 870 lb/ is presented in Fig. 5.9(b).
ft2-applies because it is less than the 14041b/ft2 determined
mmt1141il$'f111tff1ttl4i¥i''''4 !Uij!ffU1Jtf-ffldl'i.1d*§l
Suppose a 50°F concrete is placed into forms for a 15ft tall wall Camo..= 1410 lb/ft1 X 1.2 X 0.95= 16071b/ft2
at a rate of 7 ftlh. The concrete density is 130 lb/ft3, concrete
This is greater than the minimum of 600Cw = 600 lb/ft1 x 0.95=
slump is 5 in., it does not contain a retarding admixture, and the
570 lb/ft2 and less than the maximum wh = 130 lb/ft3x 15 ft=
cement blend contains 20% fly ash. It will be internally vibrated
1950 lb/ft1. Because the pressure is considered comparable to
to depths less than 4 ft. UsingTables 5.4 and 5.5, the chemistry
liquid pressure, any point within (1607 lb/ft2)/(130 lb/ft3), or 12.4
coefficient C,= 1.2 and the unit weight coefficient Cw = 0.95.
ft, from the top of the form will have proportionately less pres
These two coefficients are applied to the base value of 1410 lb/
sure, and the pressure envelope will be as shown in Fig. 5.9(c).
ft2 fromTable 5.7.
D�
weighted or tied down to counteract this
uplift effect. For design, lateral pressure is
calculated the same as for vertical forms,
measuring rate of placement and pressure
bA
head vertically, not along the sloping form
face.
For sloping wall or slab bottom forms,
the pressure at a right angle to the form
2 2 surface is the component of vertical pres
870 lb/ft 6641b/ft
sure due to the weight of the concrete plus
the component of the concrete lateral pres
a) h =15ft b) h =6ft c) h =15ft d) h =12ft
sure, both taken normal to the surface.
mmt114D'r'l'''tff1ttl4'41''4 iliijdt·tltff1Dd"·,'9'4'
Consider a 12 ft tall wall with concrete placed at 4 ftlh at 70°F.
Again, we consider that the pressure is comparable to liquid
The concrete will have a 4 in. slump and will be internally
pressure for a depth of (664 lb/ft2)/(145 lb/ft3), or 4.6 ft, from the
vibrated to a depth of less than 4 ft. Suppose this is a normal
top.The maximum 664 lb/ft2 controls for the rest of the form
weight mixture weighing 145 lb/ft3 with no admixtures or
depth, producing a pressure envelope for design, as shown in
cement replacements, so that both chemistry and density coef
Fig 5.9(d).
ficients are 1.0.Therefore, the base value of 664 lb/ft2 found in
the boxed-out area ofTable 5.7 is not changed by coefficients,
and will be used for design.
CHAPTERS
5.5 Horizontal Loads Table 5.7: Base wall form pressure for concrete other than SCC
Forms and shores must be braced to resist
all anticipated horizontal loads, such as
from wind, cable tension and inclined
support attachments, and dumping of
concrete or other impact, such as starting
and stopping of equipment. Bracing should
be provided to withstand the sidesway
effects that occur when concrete is placed
unsymmetrically on a slab form. ACI347R
recommends that formwork exposed to
the elements should be designed for wind
pressures determined in accordance with
ASCE/SEI7 with adjustment as provided in
ASCEJSE137 for shorter recurrence interval.
Alternately, formwork can be designed for
the local building code required lateral
wind pressure but not less than 151b/ft1•
Hurricane-Prone Regions
For construction between November 1 and June 30 (outside of the hurricane season),ASCEJSEI
37 permits a basic wind speed of 115 mph for structures sited near the Gulf Coast and Eastern
Seaboard where the mapped basic wind speed exceeds 115 mph. The 115 mph wind speed
is permitted to be reduced by the short Construction Period factors only for construction
between November 1 and June 30. If the construction activity shifts into the period between
July 1 and October 31,the design is to be reviewed and modified,as appropriate,to conform
to the requirements for construction between July 1 and October 31.
Between July 1 and October 31,a basic wind speed of 115 mph is permitted for struc·
tures sited near the Gulf Coast and Eastern Seaboard,where the mapped basic 3-second
gust wind speed exceeds 115 mph provided additional bracing is prepared in advance
and applied in time before the onset of an announced hurricane. During these months
and in these coastal regions the permitted 115 mph wind speed is not reduced by the
Construction Period factors for the short construction period. The additional bracing is to
be designed for the full wind load determined using the unreduced mapped wind speed
CHAPTERS
exceeding 115 mph. Because warnings
are generally available before the onset of
a hurricane, contractors disassemble and
secure some forms, such as wall forms,
rather than leaving them erected and
providing additional bracing.
(5.16)
where
K6 =wind directionality factor from ASCE/
SEI 7, typically 0.85 for structures
similar to formwork;
K, =velocity pressure exposure coefficient
from ASCEISEI7; refer toTable 5.11;
K" =topographic factor from ASCEISEI 7,
most typically 1.0 except when the
formwork is located on a hill top or
escarpment; and
"Wind l)lessure l)lncribed by ASCE/SE137 �fter <K!justment by 0.6W ASD multiplier i� used whenever it would require a lateral
Vc =construction period design wind force for d�ign gre�ter th.ln the ACI347R 1001blft minimum shown.
speed, mph.
'15 lblft' minimum applie1 if using local code wind pr�sure Insteadof ASCE/SEI37
Table 5.9: Minimum lateral force for design of slab form bracing Table 5.1 0: Construction period
factors
le5slhan6weeh 0.75
6weeh Ia I yeor 0.80
llo2 years 0.85
2to5 yeors 0.90
NOTE: Oo not interpol�te in rar.gM th�t �in with 100 lb minimum lnad
-�
$ f�g��
0:
�
...
f£�§8
-� "'
bl- �
"'
I
E
_g
·�
g �
.g�
� ffi
1
I
�
� �H�
s 8;; .d'
i
•
t
§
"'
i
�
i
8
t-
��
'2
-E
t
N l·"
; �
�
"'
"
"
CHAPTER 5
The velocity pressure exposure coefficient,Kris a function of the terrain surrounding
the site and the height above ground of the formwork in the structure. One criterion is the
surface roughness of the terrain:
Surface Roughness B: Urban and suburban areas,wooded areas,or other terrain with
numerous closely spaced obstructions having the size of single-family dwellings or larger.
Surface Roughness C: Open terrain
with scattered obstructions having heights generally less than 30ft. This category
includes flat open country and grasslands.
Surface Roughness D: Flat,unobstructed areas and water surfaces. This category
includes smooth mud flats,salt flats,and unbroken ice.
Exposure categories, defined for building height but relatable to formwork at a similar
height within a structure,are as follows:
Exposure B: For buildings with a mean roof height of less than or equal to 30ft. Exposure B
applies where the ground surface roughness,as defined by Surface Roughness B, prevails
in the upwind direction for a distance greater than 1500ft. For buildings with a mean roof
height greater than 30ft,Exposure B applies where Surface Roughness B prevails in the
upwind direction for a distance greater than 2600ft or 20times the height of the building,
whichever is greater.
Exposure C: Exposure C applies for all cases where Exposures B or D do not apply .
ExposureD: Exposure D applies where the ground surface roughness,as defined
by Surface RoughnessD, prevails in the upwind direction for a distance greater
than 5000ft or 20times the building height,whichever is greater. Exposure D also
applies where the ground surface roughness immediately upwind of the site is B or
(,and the site is within a distance of 600ft or 20times the building height,which
ever is greater, from an Exposure D condition as defined in the previous sentence.
For a site located in the transition zone between exposure categories,the category resulting
in the largest wind forces is used.
The wind effect on objects after the ninth is assumed to be the same
as on the ninth
The cumulative shielding coefficient 11m is applied to the projected face area A� for an
individual object in a series of repetitive objects. When latticed or trussed frames are used
in series and shielding is considered, then '1m is applied to the A6 value for one instance of
the latticed frame to determine the A1 for the group of repetitive frames.
The gust effect factor G considers the flexibility of the structure. Flexibility of some tall
buildings and tall towers can magnify the wind effect. Formwork, however, is typically
rigid because it is generally short and heavily braced. For rigid structures, G=0.85.
ASCE/SEI7 provides C,values for several object shapes similar to those occurring in
formwork, including square or round chimney-like structures, lattice frameworks, and
trussed towers. (1 values for other individual member shapes used in formwork design can
be found in Reference 5.22.
Wind load should be determined in a minimum of two perpendicular directions, one of
which being the exposed face with the greatest projected area. For each direction of wind
loading, formwork should be designed to resist the full force of wind load calculated along
that direction as well as SO% of the wind load calculated for the perpendicular direction
acting simultaneously.
CHAPTERS
the highest 8/h expected in the use of a particular form. Column
forms of typical heights can be considered as very short walls of
height, h, and width, 8, where wind eccentricity is minimaL The (1
values in Table 5.12 have been reduced from the more extensive
Elevation View Cross-section View
data in ASCEISEI 7 assuming the wall or column form extends
upward from a footing, slab level, or a previous wall or column
placement. It is possible that less conservative results can be deter
mined by direct use of that reference for particular cases. Consistent
with ASCE/SEI 7, the force calculated is applied to the wall form
slightly above mid-height as shown in Fig. 5.15 because the wind
pressure is somewhat higher near the top of the wall than the
��
bottom. See Example 5.8. I Wind
Plan VIews
Wind \
5.5.6 Wind Loads on Elevated Slab Formwork Fig. 5. 15: Wind force configurations for wall forms
Elevated slab formwork typically has three features that accumu-
late lateral load from wind as illustrated in Fig. 5.16.
British Standard BS 5975s.1J provides a simplified method for shielding of repetitive
members of elevated stab forms and edge forms. This method multiplies the projected area Table 5.13: C1 for elevated slab
of the formwork by a factor depending on the orientation of the supporting members. (1 for
elevated slab formwork is determined from Table 5.13. This force coefficient applies to the ··=--����--·�·�
formwork
slab formwork only and acts through the midheight of the slab formwork. � Case 1 (Fig. 5_17) 2_0
For the slab formwork, A1 of the windward face of elevated slab formwork is
Cose2 [Fig. 5.18] 2.2
A1= d x length of formwork considered (5.20)
where
d =depth of windward face depending Mtf1rt1ftlj:IWHftiiff7tjffAWjllj.ii.1
on applicable case, as shown in Fig. 5.17 Assume the following condition for a wall form (as shown in the illustration):
and 5.18. Form height= 20 h, length= 60 h
The wind force calculated based on these i 5
C1 values is only considered to act on the �:�� :�:�:�==��; � �:�
s a rm not
- H +
windward face of elevated slab formwork located at the top of a hill in an special
and includes the cumulative effects on all wind region.
repeated joists and stringers of elevated Construction period < 6 weeks for
slab formwork. No additional shielding form single use
From the applicable tables and wind
information:
Construction period wind speed factor
= 0.75 (Table 5.10) 0.55h
Table 5.12: Force coefficients for Directionality factor K; 0.85
wall and column forms Terrain factor Kn: 1.0
Exposure Category: B, coefficient K, at
20 ft: 0.62 (Table 5.7)
Wind force acting on wall form and
Gust factor G: 0.85 for a rigid structure
Force coefficient C;. 2.08 for a free required minimum equivalent horizontal
standing wall with aspect ratio of 3
overturning force acting or rop of form
{Table5.12)
Substituting in Eq. (5.16) and {5.19):
In an A5D calculation, the multiplying factor of 0.6 is applied to the wind force F.,.
This load can also be compared to the minimum of 100 lb/ft applied at the top of the
form by summing moments about the base of the form:
where
a = average acceleration or deceleration of equipment, ftls2
F = average force, lb
g = acceleration of gravity, 32.2 ft/s2
W = weight of loaded equipment, lb
Fig. 5. 18: Case 2: wind parallel to girders/ In the notation of horizontal construction load, CH=F. See Example 5.10.
stringers
5.5.8 Seismic Loads
ASCE/SE137 states that earthquake loads need not be considered unless required by the
authority having jurisdiction and the mapped Risk-Targeted MCER' 5% damped, spectral
response acceleration parameter at a period of 1 s, 51, defined in Section 11.4.1 of ASCE/SEI
7 equals or exceeds 0.40. The area of the United States equaling or exceeding this acceler
ation level is very small. Owners of facilities having structures built in areas of high seismic
Fig. 5. I 9: Slab edge form dimensions probability may impose requirements for protection of the public. An example might be
for bridge construction where traffic is being maintained under or immediately adjacent
to the construction. ASCE/SEI 37 provides guidance for determining seismic loads during
Table 5.14: C, for slob edge forms construction.
CHAPTERS
Assume the following condition for a slab form similar to the l'")-0.75,m= 19,
system shown In Fig. 5.16:
Floor-to-floor height: 11 ft; slab thickness:8 in.; joist depth: Tlm = .!.:....!L +(m-9)T]8 for more than nine frames
1-�
7.25 in.; 3/4 in. plywood; stringer depth:61n.;
Slab form plan dimensions: 72 x 72 ft;
Jlm 1-0.759 1 0.075
Highest form elevation set up for fifth floor at 50 ft above = +(19-9)(0.758)= - +(10){0.10)
1-0.75 0.25
grade;
Shores 4x4 545 wood at 4 ft ole each way with five sets of 2x4 =3.7+1.0=4.7
X-braces on alternate lines of shores in each direction; Note that this means that significant shielding occurs
Braces overlay two shore spaces, as shown in Fig. 5.17; because there are 19 sets of lattice frames.
Basic wind speed:115 mph; (1- 1.9 from Table 5.11 for E=0.103; conservatively use 1.9
Exposure category B and form not located at the top of a hill because on borderline between 1.8 and 2.0.
in a special wind region; A,= '1mA6=4.7(68.8 ft2)=323 ft2
Construction period< 6 weeks for form single use. Substituting in Eq. (5.16) and (5.19)
From the applicable tables and wind information: Q,= 0.00256Kl,ldV/=0.00256(0.81)(1.0){0.85)[{115)
Construction period wind speed multiplier=0.75 (Table 5.10) (0.7S)J2=13.11 lb/ft2
Directionality factor K;. 0.85 F.=q,GC(',
Terrain factor K": 1.0 For edge forms, F=13.11 lb/ft2(0.85){1.8)(2)(0.67 ft)(72 ft)
Exposure Category B, coefficient Kr at 50 ft: 0.81 (Table 5.11) = 1930 lb
Gust factor G: 0.85 for a rigid structure For slab forms (Case 1), F=13.11 lb/ft1(0.85)(2.0)(1.17 ft)(72 ft)
=18801b
Force coefficient for edge form (Table 5.14):
For slab forms (Case 2),F=13.11 lb/ft2(0.85)(2.2)(0.67 ft)(72 ft)
windward C,= 1.8; leeward C,= 0.11i(Ljd1)- 3] =
=11801b
0.111(72 ft/0.67 ft)- 3] = 11.4, use 1.8 maximum.
For shores and braces, F=13.11 lb/ft1(0.85)(1 .9)(323 ft1) =
Force coefficient for slab form (Table 5.13):Case 1 C,= 2.0;
6838 lb (half in friction to slab below)
Case 2 C,= 2.2.
Total F=1930+ 1880+ (6838/2) =7230 Ib at slab form
Force coefficient for shores and bracing:
elevation (worst direction)
shore height=11 ft- 0.67 ft- 0.67 ft- 0.5 ft=9.2 ft; brace
Use ASD multiplying factor=0.6
length=(9.22+ 82)0·5=12.2 ft
Equivalent lateral force per foot of slab form edge H=
A,= 19 (9.2 ft) (3.5/12) ft+ 5(2)(12.2 ft)(3.5!12)ft/2= 51+
0.6 (7230 lb)/72 ft= 60 lb/ft
17.8= 68.8 ft2
Minimum lateral load=2% of dead load or 100 lb/ft. Assume
Used one-half of braces because on alternate lines of
forms weigh 10 lb/ft2 and concrete slab at 150 lb/ftl.
shores.
H,;,= 0.02[10 lb/ft1 + 0.67 ft (150 lbfftl)J(72 ft)=
A9=9.2 ft (72 ft)=662 ft2
0.02[110 lb/ft2](72 ft) =158 lb/ft. Controls.
c= A,/A9=68.8/662=0.103
gain strength consistent with the load, as well as sufficient sets of forming, shoring, and
reshoring to distribute the load to enough floors. Quality may impose limitations on
deflection and cracking that can be aggravated by early loading of low-strength concrete
floors. Thus, the construction engineer must design a system of shoring and reshoring
satisfying these needs and constraints. ACI347.2R-05, "Guide for Shoring/Reshoring of
Concrete Multistory Buildings," provides information and analysis methods based on
research results and the experience of formwork designers.
Whether a formwork system including shores alone or a combination of shores and
reshores is used depends on the project schedule, project plan for reuse of materials, avail
ability of formwork, and the overall design of the structure.
Shores in the lowest stories should be designed to carry the full weight of concrete, form
work, and construction loads of all the floors above them prior to removal of the lowest story
of shores supported on the ground or other unyielding support. Once the first floor of shores
supported by the ground has been removed and replaced by reshores, the shores and reshores
must be designed to carry all loads transmitted from the slabs above. Because the building
slabs become part of the support system, the shoring/reshoring designer must consider their
ability to support or transfer loads to and from the shores and reshores and to the building
columns. ACI347R- 14, ffGuide to Formwork for Concrete,w states (Section 4.5) that the structure's
capacity to carry these loads should be reviewed or approved by the engineer/architect, while
the plan for shoring and its execution remain the responsibility of the contractor.
In preparing a shoring/reshoring system design, ACI 347R recommends that the analysis
should consider, but not be limited to, the following:
Structural design load of the slab or member including live load, partition loads, and
other loads for which the engineer of the permanent structure designed the slab.
Where the engineer included a reduced live load for the design of certain members
and allowances for construction loads, such values should be shown on the struc
tural plans and be taken into consideration when performing the shoring/reshoring
system design;
b. Dead-load weight of the concrete and formwork;
c. Construction live loads such as placing crews and equipment or stored materials;
d. Specified design strength of concrete;
e. Cycle time between placements of successive floors;
f. Strength of concrete at time it is required to support shoring loads from above;
g. Distribution of loads between floors, shores, and reshores or backshores at the time
of placing concrete, stripping formwork, and removal of reshoring or backshoring;
h. Span of slab or structural member between permanent supports;
Type of formwork systems-that is, span of horizontal formwork components, indi
vidual shore loads;
CHAPTER6
j. Concrete age and strength below which creep deflection is a concern; and
k. loads applied by post-tensioning transfer. OSHA 1926 Requirement for
It is difficult to recommend a single general procedure for shoring and reshoring multi safety:
story structures because the interrelationships of variables listed previously differ widely 701 (a) Construction Loads
from one job to another. However, there are some useful methods of analysis that take No construction loads shall be
into account different speeds and cycles of construction, different ratios of structural live placed on a concrete structure or
load to dead load, and different rates of concrete strength development. There are four portion of a concrete structure
analytical processes necessary in the design of the shoring/reshoring construction system. unless the employer determines,
1. Analyze the shoring and reshoring system proposed to determine slab, shore, and based on information received from
reshore loads at each step; a person who is qualified in struc
2. Analyze the capacity of the slabs at the ages when critical loads are to be supported; tural design, that the structure or
3. Compare slab early-age strength to applied loads; and portion of the structure is capable
4. Desi gn forms, shores, and reshores for maximum loads applied during the of supporting the loads.
construction process.
This may be an iterative process in which the initially assumed number of levels to be
shored or reshored may have to be changed to optimize load or the cycle time may need
to be changed to yield required strength.
Shores
leveli-1
Shores
f�=:�;· =�==:i==:::i;=�·
D • dead load of concrete slab
levell-3
Fig. 6.3: Representation of vertical equilibrium of each floor level in the system (the number of
levels varies with the number of shored levels and reshored levels)
AutoReshore 1S-2R
AutoReshore 1S-3R
AutoReshore 25·1R
AutoReshore 2S-2R
CHAPTER6
AutoReshore is made available as a part of the package for this manual. The program is
limited to the listed analysis assumptions and the sequence of operations and load paths
indicated. The electronic supplements to the package can be found in the ACI bookstore
at www.concrete. org by searching for•Formwork for Concrete.·
As in ACI347.2R, the loads for analysis and resultants are expressed as a proportion of
the slab deadload, D. Forthecaseof an 8 in. thick slab of 150 lblft3 concrete, 0= 100 lb!ft2 so that
1.00= 100 lb/ft2 and a 50 lb/ft21ive load would be a load ofO.SOD. Inputs to AutoReshore
can either be in a proportion of 0 or actual loads such as kip/ft1 but must be of consistent
units. An example of a simple shoring load analysis with two levels of forms/shores and
one level of reshores simplified by considering dead load of the slab only is shown in
Example 6.1.1n Example 6.2, all loads are considered. In Example 6.3, all loads are consid
ered with one level of forms/shores and two levels of reshores.
In Example 6.3 with one level of forms/shores and two levels of reshores, the maximum
slab loads are:
This suggests, perhaps contrary to initial thinking, that it is better to use only one rather
than two or more sets of forms/shores. Indeed, examination of many combinations has
indicated increasing the number of formed/shored levels increases the maximum slab
load. Increasing the number of reshored levels reduces the maximum load supported
by the slabs. As will be seen in the later analysis of load capacity and cycle interval, the
maximum load does not always control, depending on the relative ages of the slabs.
However, the combination of the greater load to be supported and the cost of providing
more than one set of forms/shores has made the option of one set of forms and multiple
levels of reshores the frequently selected solution.
tion live load or the separate allowances for the weight of forms,
lmJ
ll
���;::;, :�� ����=�:! ���� ���=����: �� ; � ��! ; �:
a e s a a o o the
[I 2,_�-.:
-I
-:::J I-.- -
1 r 5 xa 0
considers slab weight, the only load at each slab level is 1.OD, and
CPE =CDf =CDR= 0. Analysis parameters are shown in the input
screen shown to the right for the case of two levels of forms/shores
and one level of reshores. The list of load factors= 1.0 indicates
that this analysis will be based on allowable strength design (ASD).
If the spacing of the shores and reshores is known, this informa
tion can be entered but is not necessary for the load distribution
analysis.
The following AutoReshore spreadsheet screen captures show
Inputs for analysis presented in this example with loads expressed
intermsofD
how the method is applied with two levels of shores and one
level of reshores. (The AutoReshore spreadsheet is available for
download from the American Concrete Institute website. Search "Formwork for ConcreteM at www.concrete.org.) Several columns
are shown. The steps correspond to the five operations that are typically associated with the slab levels. Three columns indicate the
load carried by the slab at a particular level before that operation, the load change during the operation, and the load carried at
the end of the operation. The unit load carried by the shores is then indicated, for this example in terms of D. Next. an illustration of
the structure is provided showing the various slabs, shores, and reshores. Finally, a column provides the calculated total individual
shore and reshore loads for the spacing entered in the input screen. If the load carried by the shores at the end of an operation is
2.000 {meaning 2.000D) and the regular spacing is 5 ft in each orthogonal direction, the individual shore load would be 2.0D x 5
ft x S ft =SOD ft2 and for D= 100 lb/ft1 becomes 5000 lb. Knowing the shore spacing and reshore spacing is not required for the
analysis. Input of a unit spacing of 1.0 results in a unit shore load rather than a total shore load.
The analysis processes and AutoReshore screen captures for several example steps are described as follows:
1-A: Slab 1 is shored, formed, and placed. A fresh concrete slab cannot carry load. Slab dead load, D, is transmitted directly to the
ground.
F81 = C,MI.= l.OOD
1-B: In this example there is no live load, so the shore support is unchanged.
F81 = 1.00D
ltUJLUJ .
2-A: Slab 2 is shored, formed, and placed. Because Slab 1 cannot deflect, it transmits load but does not support load.
FB2 = c,MI = 1.ooo =FA,
FB, =FA,+ l.OOD= 1.00D + 1.000 = 2.000
2-B: In this example there is no live load, so the shore support is unchanged.
c::::::JHardenedslab
Story of shOJes
IIIII andlormwork
��
�, �, , , , Story of reshOfes
l.l.l..l.l Ofbackshores
CHAPTER6
2-C: Forms and shores are removed from below Slab 1. The shore support of 2.00 under Slab 1 is removed, Slabs 1 and 2 deflect
equally, and the load each carries increases by 2.00/21evels= 1.OO.loads carried by the slabs are transferred to the columns.
"""
'
1
� � tt!HHlj'
·�
U IOO
0.�
0.000
' ·�
UXlO
0.000
1
:::"'"
,.....,..
�
2-0: Reshores are installed snug-tight to the Slab 1 soffit. As the reshares are placed, they carry no load, but are ready for the loads to be
transmitted from operations above. The load carried by Slab 1 remains 1.00 because the reshares are intentionally only snug-tight.
I I I I I I I
0.000 I I I I I I I 0
3-A: Slab 3 is shored, formed, and placed. Because Slab 1 is reshored to the rigid base, Slabs 1 and 2 cannot deflect, so all the new
load goes through shores and reshores to the ground.
§
'
'
�
'
"
3�C: Forms and shores are removed from below Slab 2. The shore support of 1.00 under Slab 2 is removed, Slabs 2 and 3 deflect
equally, and the load each carries increases by 1.00/2 levels= 050. Note that Slab 2 is supporting 1.50, its own self-weight, and
half the weight of Slab 3. The shore load on Slab 1 is removed so that the reshore load reduces to zero.
;=' ;
"
I I I I I I I
I I I I I I I 0
Rg i d
i support
3-0: Slab 1 reshores are removed. Because reshores were unloaded, there is no change in load supported by Slab 1. 7T77777T7atgroundlevel
=: Freshlyplaced
= slab
c:::::::JH ardenedslab
��
. ,�
, �,
, S toryofreshores
l..l.l..l. orbaekshores
1111111
I I I I I I I
I I I I I I I
4-A: Slab 4 is shored, formed, and placed. Because Slab 1 is no longer shored to the rigid base, Slabs 1, 2, and 3 deflect equally under
the added load and carry an additional 1.00/31evels = 0.3330. Tracking the shore forces from the top downward
FB4= C,MI. = 1.00= FA3
F 83 =FA3 + 0-RF3 =1.00+ 1.00-0.8330= 1.1670 =FA2
F8 =FA2+ O-RF = 1.1670+ 1.00-1.8330= 0.3330= FA1
2 2
FB, =FA,+ 0-RF, = 0.3330 + 1.00-1.3330 =0.00 correctly corresponding to no shores or reshores under Slab 1.
�� �
7777777n Rigdi support
at ground level
N
I I I I I I I
I I I I I I I 8 c::::::JHardenedslab
I I I I I I I
.
IIIII Stor yolshOfes
andformwOfk
��
., �
, �
, S
, toryolreshores
Ul.l..l. or backshores
Analysis results for other steps are determined in a similar manner. Results for additional steps can be seen
by accessing the AutoReshore spreadsheet.
mtttmtJif4MMfi®Mf,
i.!.!i!.!. mtmmc.m;mmmc«Mftmm·'''*'
This example demonstrates the method with all loads consid
ered, including slab dead load, construction live load, and sepa
rate allowances for the weight of forms and shores and reshores.
All loads are expressed as a portion of the uniform load of the
floor slab, 0. Assume the slab is an 8 in. thick flat plate of normal
, __ _
weight concrete weighing 150 lb/ft3 x 8 inJ12 inJft =100 lb/ft2•
Thus, the assumed loads can be stated as:
EmEl
Slab dead load 100 lb/ft2 1.000 �
Construction live load SOib/ft2 0.500
I
Form and shore load 10ib/ft2 0.100
CHAPTER6
to an understanding of the analysis process. The analysis processes and AutoReshore screen captures for several notable steps are
described as follows:
1-A A fresh concrete slab cannot carry load. Dead, live, and form/shore load is transmitted directly to the ground.
FBI= 1.000+0.500+0.100= 1.600
1-B: live load is removed at the end of placing and finishing operations.
FBI= 1.000 + 0.100= 1.100
tHJ1riu ,
2-A: Because Slab 1 cannot deflect, it transmits load but supports no load.
FB2= 1.000+0.500 + 0.100 = 1.600 = FA1
FBI= 1.600+1.000+0.100= 2.700
Rigid support
7777777
at gro und level
= Freshlyplaced
= slab
2-B: live load is removed at the end of placing and finishing operations.
IIIII Storyof shores
a ndlormwork
2-C: Forms and shores are removed from below Slab 1. The shore support of 2.200-0.100 form/shore weight under Slab 1 is
removed. Slabs 1 and 2 deflect equally and the load each carries increases by 2.10/2 levels= 1.050. Determine shore load
FB2= 1.000-1.050+0.100= 0.050=FAI
In this step, dividing the load from the removed support between the two slabs results in load of the forms/shores indicated as
partially supported by both the first- and second-level slabs. This anomaly is a result of the analysis assumptions. Some adhe
sion of the forms to the underside of the upper slab can occur or a small gap can open between the forms and the upper slab.
This gap closes when other loads are applied. Because any error is small, it has been ignored in practice.
'�
1
�·'�'� �� �·= �
0.000 l.o&l l.o&l
0.000
I
2-D:Reshores are installed snug-tight. As the reshores are placed, they carry only their self-weight of 0.050, but are ready for the
loads to be transmitted from operations above.
'�
·
�'�'� ��
-··
-
'�
I "'
"'
3-B: Construction live load is removed with a consequent reduction in shore and reshore forces.
3-C: Forms and shores are removed from below Slab 2. The shore support of 1.1SO less form/shore weight of 0.100 under Slab 2 is
removed, Slabs 2 and 3 deflect equally, and the load each carries increases by 1.050/2 levels= 0.5250. The shore load on Slab 1
is removed so that the reshore load reduces to 0.050, its self-weight.
1111111
' ' ' ' ' ' '
777n77n �;��o:�����
' ' ' ' ' ' '
�=::�htyptaced
3-D:Reshores are removed from under Slab 1. Because they were originally installed only snug-tight and
Slab 1 is supporting all its self-weight, there is no change in the Slab 1 load. c:::::::=::JHardened slab
IIIIStory of shores
I a ndlormwork
�.�..�,�, Story of reshores
l...l.J.o..J..l rbact.shores
3-E: Reshores removed in Step 3-D are relocated and installed snug-tight under Slab 2. The load carried by Slab 1 increases by 0.050
tol.OSO.
1111111
I I I I I I I
I I I I I I I
4-A: Slab 4 is shored, formed, and placed. Because Slab 1 is no longer shored to the rigid base, Slabs 1, 2, and 3 deflect equally under
the added load and carry an additional 1.600/3 levels= 0.5330. Tracking the shore forces from the top downward
FB. = C"+ C,IAI. + C01= 0.500 + 1.00+ 0.100= 1.600= FA3
CHAPTER6
FB3 = FA1 + 0- RF3 +COl'= 1.60+ 1.00- 1.0580+ 0.100= 1.6420 = FA1
FB1 = FA1 + 0-RF2 +CDR=1.6420+ 1.00- 2.1080+ 0.050= 0.5830= FA,
FB, =FA,+ 0-RF, = 0.5830+ 1.00- 1.5830 = 0.000 corresponding to no shores or reshores under Slab 1.
Analysis results for other steps are determined in a similar manner. As construction moves upward and further away from the
effect of the rigid ground level, the resultants for the cycle of steps begins to attenuate toward repeated values, as can be seen
in the extracted values shown for Steps 5-A, 6-A, and 7-A. Results for additional steps can be seen by accessing the AutoReshore
spreadsheet.
..!....l...l orbad<$hores
1-B: live load is removed at the end of placing and finishing operations.
FB1 = 1.000+0.100= 1.100
llUJJJJJ ,
1-C: Forms and shores are removed from below Slab 1. The shore support of 1.100- 0.100 form/shore weight under Slab 1 is
removed. Slab 1 deflects and the load carried by the slab increases to 1.00.
llLUliU , � El
�i�� ����:
, I·� 1·� I, I
77777777? o et
��t:�hlyplaced
..
�- 1
I
I
I
I
I
I
I
I
I
I
I
I
I
CHAPTER6
2-B: Live load is removed at the end of the placing and finishing operations.
FB2=1.000+ 0.100= 1.100=FA,
FB, = 1.100+ 1.000-1.000+ O.OSO=l.lSO
LM<l<arrio>db",'ola� Unit!OIId<arrio>db",'shore
�chgdur
2-C: Forms and shores are removed from below Slab 1. The shore support of 1.100- 0.100 form/shore weight under Slab 1 is
removed. Slab 2 deflects and the load carried by the slab increases to 1.000. Determine reshore load.
FB, =1.000-1.000+ 0.050=O.OSO
'�
1
@·�·� ��·
1.000 0.000 1.000
0.050
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2-D:Reshores are installed snug-tight under Slab 2. As the reshores are placed, they carry only their self-weight of O.OSO, but
are ready for the loads to be transmitted from operations above. Slab 1 cannot deflect and transmit the new reshore load
downward.
FB, =0.050+ 1.000-1.00+ 0.050 =0.100
'�
�·'
�··� �
0.050
0.100
3-A: Slab 3 is shored, formed, and placed. Because Slab 1 is reshored to the rigid base, Slabs 1 and 2 cannot deflect, so all the new
load goes through shores and reshores to the ground.
I
1111111
' ' ' ' ' ' '
. ' ' ' ' ' ' '
00 : : : : : :
3-B: Construction live load is removed with a consequent reduction in shore and reshore force.
�i��o������el
77777777?
��r:�hlyplaced
1111111 c::::::JHardenedslab
: : : : '' '' '' IIIII and Storyof shores
formwork
3-D:Reshores are removed from under Slab 1. Support of 0.100- O.OSO reshore weight is removed so that Slab 1 deflects slightly
under the increased load of O.OSO. Because the reshore cannot hang from Slab 2, there is the possibility of reshore separation
from Slab 2 unless spring dips are used or the reshores are resnugged.
3-E: Reshores removed in Step 3-0 are relocated and installed snug-tight under Slab 3. The load carried by Slabs 1 and 2 increases
by O.OS0/21evels= 0.0250.
; ..
'
4-A: Slab 4 is shored, formed, and placed. Because Slab 1 is no longer shored to the rigid base, Slabs 1, 2,
and 3 deflect equally under the added load and carry an additional 1.600/3 levels=0.5330. Tracking
Freshlyplaced
� slab
c::::::J Hardenedslab
the shore forces from the top downward
F84=C.ot:+CfMI.+(01'=0.500+1.00+0.100=1.600=FA3
IIIJI Story ol shores
andlormwork
F83 =FA1+0- RF1 +COl'= 1.60+1.00- 1.5330+0.050= 1.1170= FA
2 ��
. , �
, �
, , storyofreshores
FB2= FA2+0- RF2 +COR= 1.1170+1.00- 1.5580+0.050= 0.6080=FA1 l.ll.l.l orbackshores
FB1 = FA1 +0- RF1 =0.6080+1.00- 1.6080=0.000 correctly corresponding to no shores or
reshores under Slab 1.
lllllrT
�
' ' ' ' ' ' '
' ' ' ' ' ' '
'
CHAPTER6
Analysis results for other steps are determined in a similar manner. Results for additional steps can be seen by accessing the
AutoReshore spreadsheet. Extracted values for Steps 5-A, 6-A, and 7-A are shown.
Jllllll
' ' ' ' ' ' '
' ' ' ' ' ' '
: : : : : : :
1111111
' ' ' ' ' ' '
' ' ' ' ' ' '
1111111
'
: : ' : : : :
= Freshlyplaced
�� ,�, Storyofreshores
l...!...l....Ll orbackshores
. , �
.
A second important observation in comparing Examples 6.2 and 6.3 is that the slab loads
in Step 4-A at the various levels differ significantly in Example 6.2 but are almost equal in
Example 6.3. When using only one level of forms/shores plus reshored levels, some form
work engineers simplify the problem and assume that the total load in the system (live load;
fresh concrete weight; and slab dead load plus the weight of forms, shores, and reshores)
is simply distributed equally to all slabs interconnected by shores and reshores. Using this
approach in Example 6.3, Step 4-A:
Total toad= 4(1.000) + 0.500+ 0.100 + 2(0.050) = 4.700
Slab load supported at each level= 4.70013 levels= 1.5670
This result is similar to the range of 1.5330 to 1.6080 from the Step 4-A analysis and
certainly reasonable considering the uncertainty in estimating the applied loads. Again,
as will be seen in the later analysis of load capacity and cycle interval, the maximum load
does not always control, depending on the relative ages of the slabs.
When less stiff shores/reshores are used, analytical studies&.•AJAio have indicated a shift of
as much as 10 to 15% of the slab loads from lower interconnected floors to the uppermost
6.3 Backshoring
Backshores are shores placed snugly under a concrete slab or structural member after
the original formwork and shores have been removed from a small area at a time,
without allowing the slab or structural member to deflect significantly. During this
process, the slab or other member does not yet support its own weight or existing
construction loads from above. The purpose is to retrieve the forms for earlier reassembly
at the next level, allowing a reduction in the schedule. Clearly, if a shore is removed locally,
the load it supported is transferred to other nearby shores and the backshore installation
does not relieve this load. As the process continues, previously placed backshores pick up
some load as other shores are removed. This causes the distribution of load among the
backshores to vary slightly. The process has been employed in practice successfully as an
alternate to complete shore removal and has the safety advantage of maintaining support
under the slab and delaying the time when the slab must be fully self-supporting. A disad
vantage is that higher loads can accumulate in the lower interconnected floors.
CHAPTER6
4. Placement of concrete for slab at level i;
5. Removal of the live load immediately following placement and gradual strength-
ening of the slab;
6. Removal of form panels and beams from level i; and
7. Removal of lowest level of reshores from under level i-2.
The process can be understood by reviewing Example 6.4.
load Factor
The variable material load, CVMt, could be fresh concrete during placement that has not
been fully distributed. Thus, the factor of 1.4 could be appropriate for design of the form
because it may be subject to a temporary localized greater thickness of concrete. However,
for the overall shoring/reshoring analysis, the distributed concrete is considered to be fixed
material dead load, c,Mt' with a load factor of 1.2.1n some combinations, ASCEISEI 37 indi
cates a load factor of 1.4 on completed members of the structure whereas ACI347.2R uses a
factor of 1.2. Similar to C,Mt' 1.2 will be used in Examples 6.5 through 6.7.
mtftftjtjiJiiiiMftMMU1ft1Mintrt!lijfffijMLj1i.!iJ
This example demonstrates the drophead shore method with all
loads, including slab dead load, construction live load, and sepa
rate allowances for the weight of forms and shores and reshores.
All loads are expressed as a portion of the uniform load of the
SM<• - - !R --
floor slab, D. Thus, the assumed loads can be stated as:
Slab dead load 100 lb/ft2 1.000 (includes
reinforcement and
misc.)
Analysis parameters are shown in the input screen shown to the right. The list of load factors= 1.0 indicates that this analysis will be
for allowable stress design (ASO) resultants.
The following AutoReshore spreadsheet screen captures show how the method is applied with all loads for one level of forms
and drophead shores and two levels of reshores (drophead shores after being released and re-snuggedl. In the analysis, the load of
ULUlUJ .
1-B: Form/reinforcement erection live load is removed.
FB, = 0.400-0.200= 0.200
ULLULU .
1-C: Concrete is placed (the reinforcement load is replaced by the concrete slab load that includes the reinforcement).
FB, = 1.000+0.500+0.050+0.050= 1.600
· 1·-�·-1·-1 8 �tiill�IIII
1-D:Concrete placing live load, 0.500, is removed.
llU1UJ,I
1-E: Form beams and panels are removed without releasing shore load but reducing shore load by 0.050.
�i�� ��'::
7777777 o el
��
, , �,
l...l.J....L.!.
,�S
, toryolreshores
orbackshores
--Formworkpanels
2-C: Drophead shores under Slab 1 are released throughout the entire bay. Slab 1 deflects and begins to support load but cannot
deflect additionally after drophead shores are re-snugged to become reshores. The slab load increase is equal to the support
··-
';;;
1 0.000 1.200 1.200
• ; •
o__
..... ''.
�.- ; ;. ·. ' ;
2-D:Concrete and placing live load pass through shores and reshores to the ground because Slab 1 cannot deflect additionally.
FB� = 1.000+0.500+0.100= 1.600= FA,
FB, = 1.600+ 1.000 - 1.000+0.050= 1.650
CHAPTER6
Steps 2-E through 3-F continue in a similar pattern.
�,.�,.� �� m·
·
·� R«no.oo2tldlloo<
-
:
1200 0.000 1.200 '
0 900 I I I I I I I
3-G:Reshores are removed from under Slab 1. Slab support of FB1 less the reshore self-weight, 0.900-0.050 = 0.850, is removed and
the load carried by the three elevated slabs increases by 0.850/3 = 0.2830.
;�3-'""""' �
0� ·�
I� �m: �
Freshlyplaced
�
slab
��
. ,�
,�, , Storyofreshores
�'�'
�: : � :orbackshores
--Formworkpanels
Resnugged
shores
Shore loads and slab loads can be tracked by summing forces in the vertical on each slab starting at the top and working down
ward as in previous examples. Analysis results for other steps are determined in a similar manner. Aher Step 4-8, several steps have
been omitted but Steps 4-0 and 5-A are shown. For this example, the maximum slab loads of 1.6670 occur in Slab 3 at Step 4-D and
of 1.7110 in Slab 3 at Step S-A. The load of 1.6670 may control because it occurs at an earlier slab age. Results for additional steps
can be seen by accessing the AutoReshore spreadsheet.
I Form- - ! Reshcft--
• a
' '
' '
II
Inputs for LRFD analysis with loads expressed in terms ofD
Selected LRFD analysis results with two levels of shores and one level
of reshores with resultants in terms of D
-�=""-�
e ; � �·
-
· ·
.
2
111110 0000 111110
e ; �:·:::::: �:
-
· '
1200 0 000 1200
- ·
· � � -
·
:i�� ����e
7777777
� �r:�
o
hlyplaced
l
· = := := =
·
'
1200 ooeo 1no
c:=::::J Hardened slab
-
·
· .
IIIII Story ol shores
andlormwork
� �.�· �
. ,,�,�, storyolreshores
��
.l...l..l...l.. Orbaekshores
Example 6.5 shows selected results for a factored load analysis with the same basic loads
and shoring system, as used in Example 6.2. Only the steps identifying certain maximum
slab loads carried are shown.
Example 6.6 shows selected results for a factored load analysis with the same basic
loads and shoring system as used in Example 6.3. Only the steps identifying certain
maximum slab loads carried are shown.
CHAPTER6
mtttmtt!ltf:i'·lM'Mf.tmmam.mmmJ1.1.1iJf•·•·•mmm•;m·'·'H
Selected results from the AutoRe-
shore spreadsheet for the system SHORING AND RESHORING ANALYSIS AutoReshore 1S·2R
2 I
CuredslaD�t
FonM/lofe-igh1
...
....
LRFD analysis inputs with loads expressed in terms ofD for example with one level
of shores and two levels of reshores
LRFD analysis results with one level of shores and two levels of
reshores with resultants in terms of D
l-carriedbywt>
-::-1.-:1 �g ITJJTIIIJ .
� I B rliiHIII'
·� ·�
)/))))J/?J/JJ?))
EJ lmn>nnnJ '
.
8 lJJLllHJ
7777Rigid
777 support
a tground level
�
� �:�hlyplaced
�Hardened slab
II
,.... shores are designed for loads anticipated
during the service life of the completed
structure. There is little or no attention
11 given to loads that must be carried during
construction, often before slabs have
II attained their full design strength. The
form designer must evaluate the probable
v T mpertu ""'
load-carrying capacity of the structure
as construction proceeds and select a
rr I Ill I
Many multi-story buildings have been
built following a rule of thumb or local
10 12 14 16 18 20 22 24 26 28
custom of using a certain number of stories
of shores and reshores, often progressing at
Concrete Age (Days) one story per week. However, construction
processes have become more mechanized
Fig. 6.6: Examples of concrete compressive strength development as a function of age and and often significantly faster at the same
concrete temperature. Form work designers should obtain job-specific strength development time that design practices are tending to
data for actual project conditions and concrete mixture used produce buildings without the margin of
extra strength once available. Under these
conditions, it is prudent to make a more
rational judgment of how many stories of shores and reshores are needed for a given rate
of construction. This is more important for structures where the live load to dead load
ratio is small (say, in the range ofO.S to 1.0). These structures have less reserve strength to
accommodate loads imposed during construction.
In planning for a multi-story project, it is necessary to determine the capacity of slabs
to support the loads that will be transmitted to them through shoring/reshoring systems.
Field measurements of shore loads during construction have shown fair agreement with
the simplified load analysis, which is widely used for preliminary planning. However, ACI
347.2R cautions that when more compressible (less stiff) shores are used, the system
tends to shift more of the imposed construction loads to the upper floors, which have less
strength. Thus, consideration should be given to the load resultant increases discussed
previously in Section 6.2.2.
Considering that the simplified method is based on loads acting at a single point, a
more rigorous analysis introducing actual stiffnesses of slabs and shores is advisable for
structures with low live-to-dead-load ratios or when fast cycling of formwork is desired.
One such study is the equivalent frame analysis by computer reported in Reference 6.10.
CHAPTER6
1. LOADS: Perform a shoring/reshoring analysis considering construction live load, form
load, and shoring load, in addition to the dead load of the slabs. A simplified method
has been presented, but a more precise analysis may be necessary for cases where the
slab's strength is marginal at the time of construction load application.
2. SLAB STRENGTH: Evaluate the amount of load that can safely be placed on the slabs
depending on their ages, available concrete strengths, and proposed rate of construc
tion. This requires knowledge of the slab's structural design loads and any load reduc
tions taken by the engineer/architect in preparing the design, as well as the concrete
strength development during construction.
3. SAFETY EVALUATION: Compare the expected applied construction loads with the slab
early-age capacities to be sure that the anticipated construction loads do not exceed
the available slab load-carrying capacities at any stage during the construction.
4. CHECK LOCAL PUNCHING SHEAR: Evaluate local punching shear in the slab under the
shore loads based on available concrete strength (more likely a concern with truss
supported formwork where leg loads are more widely spaced).
The strength of a floor slab at an early age may be determined by one or more of several
available methods:
A. Structural analysis using methods of ACI 31 B to determine the floor load capacity
at the concrete compressive strength corresponding to the early age. This method
involves relatively long calculations but is accurate.
B. Slabs having concrete at less than the full specified compressive strength may
conservatively be assumed to have an ultimate load capacity in proportion to the
percentage of specified concrete strength developed at different ages. This method is
relatively quick but very conservative compared to Method A.
C. Slabs having concrete at less than the full specified compressive strength may conser
vatively be assumed to have an ultimate load capacity in proportion to the square
root of the percentage of specified concrete strength developed at different ages. This
method is relatively quick and moderately conservative compared to Method A.
To show how these steps are applied, an example will be worked out for a multi-story flat
plate structure using loads developed in the previous examples. This example is based on use
of steel shores that are uniformly spaced and uniformly loaded over the entire slab area. It is
also assumed, consistent with common U.S. practice, that forms and shores are removed bay
by bay, allowing the slab to deflect and carry its own weight before reshoring is installed. Some
project specifications require 70 to 7S% of the specified compressive strength to be devel
oped before forms and shores are removed. Because strength development is slower at lower
temperatures, this may limit the rate of construction. For this reason, use of high-early-strength
concrete may be preferable for construction in cold climates. With appropriate engineering
evaluation of the slab loads, deflections, and required stripping structural strength, the percent
of specified compressive strength required can sometimes be lower and allow more efficient
and economical construction. The use of supplementary cementitious materials (SCMs) can
alter the rate of slab concrete strength development, and mixtures containing SCMs may have
specified strength requirements at later ages than the typical
2B-day period.
The formwork engineer/contractor must select the method
to be used for determining strength of the floor slabs. As 100
discussed previously, Method A is based on ACI 31 B and any
additional information on its assumptions can be found in the
ACI 31 B commentary. Method B is based on the assumption
of linear relationship between concrete compressive strength
and slab capacity. The basis of Method C requires some expla
nation to understand the basis from ACI 31B. Consider the
material strength relationships with concrete age, as illus
trated in Fig. 6.7. The concrete tensile strength f, and modulus
of elasticity f< increase at a rate greater than the concrete
compressive strength f<. Both f, and f< are typically taken as
functions of ..J1: as follows
(6.1)
Time (days) 28
(6.2)
Fig. 6.7: Concrete material strength and stiffness rate of development
!VI -r-FieJcure,p•O.S%
---F�uure,p•1.0%
forcing steel. Figure 6.9 illustrates this rela
tionship for singly reinforced beams and
lj --Fiexure,p•1.5%
slabs for a range of reinforcement levels
-+-Fiexure.p•2.0%
�1------1 =�=:��:-�·pyndlilg) based on an assumed concrete strength
development curve. The results indicate
-[W1c28)"0.7
--compressiYI!sTencth that the proportion of flexural strength
gained is always greater than the propor-
tion of compressive strength or square root
of compressive strength gained, except at
strengths less than 30% of r; with a high
Fig. 6.9: Concrete structural strength development
percentage of reinforcement.
Example 6.7 considers the portion of a
flat-plate structure where slabs are essentially the same from one floor to the next. Addi
tional steps would be necessary for many mixed-use buildings where lower floors may
be designed for retail, parking, public assembly, or other uses.
Timing of stripping operations requires careful consideration of the strength gain. The
formwork engineer/contractor will also need to evaluate the required time to erect the
forms for the next level and place reinforcing steel and embedded items to determine
Investigate a construction rate of one story per week at Concrete structures are designed by a strength or ultimate
a concrete temperature of 60°F. The 8 in. thick slabs were strength method. Under ACI 318 requirements consistent with
designed for 100 lb/ft� self-weight, 20 lb/ft1 moveable parti ASCE/SEI 7-10 NMinimum Design Loads for Buildings and Other
tion dead load, 10 lb/ft1 ceiling and mechanical dead load, and Structures,Nthe ultimate load capacity-the largest load the
50 lb/ft21ive load. During the construction cycle, loads include structure was designed to carry based on specified concrete
the 100 lb/ft2 self-weight of the new slab, 50 lb/ft1 construction strength-can be expressed as
live load recommended by ACI347R, 10 lb/ft1 formwork!shore
U28 = 1 .2 0L + 1.6LL
load, and 5 lb/ft� reshore load on each reshored level.
CHAPTER6
where LL is the design live load on the slab and OL is the slab the structure strength to be developed. If the 60°F concrete
weight, plus any superimposed dead load. Because load factors strength relationship in Fig. 6.6 was developed for the project's
have varied over the years, the formwork engineer/contractor concrete, the strength at 2 days is 35%, at 3 days is 47%, and at 4
must determine what load factors were used in design by the days is 56% of r;.
engineer/architect. Many jurisdictions require assumed live and Based on structure strength proportional to portion of
dead loads to be listed on the structural drawings for buildings. concrete strength gained (Method 8):
Any live or dead load reductions that may have been taken by U3 = 0.47(2.360) = 1.110 < 1.200 No good.
the engineer/architect also need to be determined. U� = 0.56(2.360) = 1.320 > 1.200 OK.
For the example structure, the ultimate factored load Based on structure strength proportional to square root of
assuming no live load reductions is portion of concrete strength gained (Method C):
U3 = (0.47)o.s(2.360) = 0.68(2.360) = 1.620 > 1.200 OK.
U18 = 1.2{100 + 20 + 101 + 1.6(501 = 236 lbtfe= 2.360
U2 = (0.3SJ0·5(2.360l = o.s9(2.360l = 1.4oo > 1.200 OK.
when the slab is at 28-day strength. Examining factored results
in Example 6.5, Step 4-A, it can be seen that Slab 2 would need
to support 2.5970 at 14 days, which is greater than the 28-day
strength. Thus, the system with two levels of forms/shores and
one of reshores is not acceptable.
Examining the factored results in Example 6.6, Step 4-A, Slab
3 would need to support 1.9070 at 7 days. This is less than
the 28-day strength but needs to be
checked for the 7-day strength by one of
SHORING AND RESHORJNG ANALYSIS AutoReshore 1S-3R
the reduction methods.
Method B: Based on structure
strength proportional to portion of
concrete strength gained at 7 days - -
from Fig. 6.6:
a a
U7 = 0.74(2.360) = 1.75 0 <
' '
' '
1.9070 No good. . .
Method C: Based on structure
strength proportional to square
root of portion of concrete
strength gained at 7 days from Fig.
6.6:
U7 = (0.74lo.s{2.360l = o.a6(2.36Dl
= 2.030 > 1.9070 OK.
Alternately, if structure strength evalu
ation proportional to concrete strength Inputs for factored load onolysis results presented in the spreadsheet below.
(Method B) is preferred, consider the
system of one level of forms/shores and
three levels of reshores, as shown in
the figure to the right and the spread Factored load analysis with one level of shores and three levels of
sheet below. In Step 5-A, Slab 4 would reshores
be 7 days old, and the critical loading
during the process is 1.7300.
U7 = o.74(2.360l = 1.75 o >
1.73000K 1111111
Note that other older floors may be
subjected to slightly higher loads, but
evaluation considering their higher
concrete strength at 14, 21, and 28
days would find them adequate.
Although the construction cycle
between concrete placements may
be 7 days, reuse of the forms would
require stripping at an earlier age.
For example, in Example 6.6, the
factored slab load is 1.200 in Step
1-0. Achieving this strength requires 1.200/2.360 or 51% of
CHAPTER6
6.7.5 Post-Tensioned Structures
Given the variability of design and construction methods, the formwork engineer/
contractor should plan the shoring and reshoring for post-tensioned structures in close
coordination with the engineer/architect. Information needed for development of safe
shoring and reshoring operations includes:
Members to be post-tensioned;
Design live loads and dead loads, including any allowable live load reductions used in
the structural design; and
Post-tensioning sequence and the magnitude of stressing at each stressing stage.
When a slab is post-tensioned, its shore load is relieved and the construction load
is transferred to the beams. If the beam is shored, the beam shoring should carry this
additional load. When the beams are post-tensioned, their shore loads are relieved and
the construction load is transferred to the girders or columns. Because of this load redis
tribution that can occur, shores and reshores must be designed for the post-tensioning
stage as well as the concrete placement stage. More information is given in ACI 347.2R and
Reference 6.14.
6. 9. 1 Field-Cured Cylinders
When removal of formwork, reshoring, or backshoring is based on concrete reaching a
specified compressive strength, concrete is presumed to have reached this strength when
test cylinders have reached the specified compressive strength. The test cylinders used for
this purpose are field-cured the same as the concrete they represent. Cylinders are molded
in accordance with ASTM C31/C31M, NStandard Practice for Making and Curing Concrete
Test Specimens in the Field,� and cured in the field under the same conditions for moisture
and temperature as the concrete they represent. At the planned test age, cylinders are
transported to the lab and tested for strength in accordance with ASTM C39/C39M, NStan
dard Test Method for Compressive Strength of Cylindrical Concrete Specimens.N
1.000 �T �
_.1- -=h
0.800 �
v
+ Cylinder test
0.400
0.200 I
0.000
5000 10000 15000 20000 25000 30000
Concrete Maturity (°F-hrs)
Fig. 6.11: Compressive strength development as a function of concrete maturity
Concrete Mah.Jrify
The maturity method can be applied in accordance with ASTM (1 074, NStandard Prac-
tice for Estimating Concrete Strength by the Maturity Method."The temperature of the
concrete is never a constant, as implied by Fig. 6.6. It is influenced initially by the tempera
tures of the constituent materials, then by the heat generated by the chemical reaction of
the cementitious materials and water, and finally by the ambient temperature, as shown in
Fig. 6.10. Maturity is defined as
where
M is the maturity of concrete, QF-h;
T, is the temperature of concrete as a function of time, QF;
T0 is datum temperature, °F; and
tis the time at which maturity is determined, hours.
Essentially, maturity at a given time, r, is the area between the T,curve and the datum
temperature line, TO' from r = 0 until the elapsed time of interest.
Studies have shown that the increase in maturity of concrete can be reasonably corre
lated with strength increase, as shown in Fig. 6.11. It is essential to first develop the corre
lation between strength and maturity for the specific concrete mixture planned for use on
the project by testing compressive strength cylinders at various stages of maturity.
The usual method for measuring the concrete temperature is by embedment of ther
mocouples in the concrete slab, often at multiple places. Several vendors have developed
maturity meters that connect continuously to the thermocouple wires, accumulate data
on temperature versus time, and compute the maturity for direct readout or download.
Another approach is embedding a sensor (Fig. 6.12) that tracks temperature and accu-
CHAPTER6
Fig. 6.14: Device for determining strength by
penetration resistance
mulates maturity internally and can be connected to a readout device for maturity status.
Knowing the maturity and having a correlation curve for the project-specific mixture, the
strength of the concrete can be determined.
Pullout Tests
Pullout strength, in accordance with ASTM (900, NStandard Test Method for Pullout
Strength of Hardened Concrete,N can be used to determine field concrete compressive
strength. With this method, stems with discs are attached to removable plugs of form
plywood so the discs are embedded when the concrete is cast. At the time of the desired
test, the plug is removed and the stem is unscrewed from the disc. A pulling rod is screwed
into the disc, and a handheld pull machine applies a pulling force, eventually causing the
shear failure of a cone of concrete {Fig. 6.13).
It is essential to first develop the correlation between compressive strength and the
pullout values for the specific concrete mixture planned for use on the project by testing
cylinders and pullout specimens at various ages.
As seen in Fig. 6.13, pullout tests may result in some damage to the concrete surface and
may require surface repair. If the pullout insert is stressed to the level corresponding to
the minimum required strength without failure, the test may be stopped to avoid surface
repair and it may be assumed that the required strength has been reached.
Penetration Resistance
Penetration resistance measured in accordance with ASTM C803/C803M, "Standard Test
Method for Penetration Resistance of Hardened Concrete,N can be used to determine field
concrete compressive strength. An individual test involves firing three probes into the
concrete surface. The depth of penetration of each probe is measured and averaged. The
lesser the penetration, the higher the strength. Some systems provide the option of a
digital readout device for measuring penetration and indicating strength. Example testing
equipment is shown in Fig. 6.14.
It is essential to first develop the correlation between compressive strength of labora
tory-tested specimens and the penetration values at various ages for all concrete mixtures
planned for use on the project.
Any of these methods, or their combinations, can yield compressive strength data
needed in the field to control the timing of shoring/reshoring process operations. Design
of the formwork, shores, and reshores will be discussed in Chapters 7 and 8.
7.1 Notation
The following notation is used for design parameters in the subsequent text of this and
other chapters in addition to the parameters defined in Chapters 4 through 6.
A =area of cross section
b =width or breadth of beam cross section
C" =bearing area factor
Cao =concrete lateral pressure
CP =column stability factor
d =depth of beam cross section
d1, d2 =dimensions of rectangular compression member
£ =modulus of elasticity for deflection calculations, reference design value
£' =modulus of elasticity for deflection calculations, adjusted design value
£,.,. =modulus of elasticity for beam and column stability calculations, reference design
value
Emito' =modulus of elasticity for beam and column stability calculations, adjusted design
value
F0 =reference bending design value
F' =adjusted bending design value
F: =reference compression design value parallel to grain
F/ =adjusted compression design value parallel to grain
Fu =reference compression design value perpendicular to grain
F,J.' =adjusted compression design value perpendicular to grain
F,. =reference rolling shear design value for plywood
F' =adjusted rolling shear design value for plywood
F: =reference shear design value parallel to grain (horizontal shear)
F' =adjusted shear design value parallel to grain (horizontal shear)
( =actual bending stress
f, =actual compression stress parallel to grain
CHAPTER 7
=span or length; normally measured center to center of supports, except for
plywood design,£ is the clear span,£<' when calculating shear.
=length of bearing at the supports
=dear span face-to-face of supports
=effective length of compression member as used in slenderness ratio
determination
£)d1_1 =slenderness ratio for solid column; for the pin-ended condition assumed for
shores, this is the same as £/d1 or £/d1
eu =laterally unsupported length of bending member
M""'"' =maximum induced bending moment
M, =nominal design {resisting} moment (=F�'S)
P =concentrated load or total concentric axial load
q =pressure or load
r
P a short simple beam where the shear
;&� .1, .1, .1, .1, .1, .1, .1,� case1 ! case2 and moment produced vary with the
location of point loads of equivalent
4ft 2ft 2ft
R1 I R2 R1 I< * 'I R2 magnitude to the uniform load.
These are worst-case conditions, but
LS
r r b
case3
LS
r r b
case4
they point out the need to check the
validity of simplifying assumptions.
w= 800 lbft
l
p = 600 lblft X 2ft= 1600 lb
when beams are continuous over
several spans or where spans are long
enough that multiple evenly spaced
Resultant Cae1 point loads occur along the beam's
Shear at R1, lb 1600 2000 1600 length.
Shear at R2 lb 1600 1200 1600 2. For continuous beams supported over
Maximum moment in.-lb 19 200 21 600 19,200 three or more spans, formulas for the
three-span condition may be used.
Fig. 7. I: Comparison of concentrated load and equivalent uniform load resultants
3. For beams continuous over two spans,
design values for simple spans may be used when deflection or bending moment
controls the design of the span. Although this condition prevails for many of the
load combinations common for formwork members, short heavily loaded spans are
frequently governed by shear and one- and two-span beams should be individually
checked using the formulas in Table 7.1.
CHAPTER 7
v<Nll =0.5wt
v"" =0.5wt-w ( �)
d+
wl'
M =
,..., a
5wl�
" =-
"'" 384E'I
•
f''' '"' ' �' ' "' '"'"' ' ' 'l
b
Ra=R< =0.375wt
Rt>=1.25wt
___ ,
vr:::..-.... �v_
---l'
___ ,
v<Nll =0.625wl
vdr< =0.625wt-w ( �)
d+
r==--r--=1 M =
""'. a
we'
Ra=Rd =0.4wl
Rt>=Rc=l.lwl
V,..., =0.6wl
v"" =0.6we-w ( �)
d+
wl'
M
, ..,=
. w
Ra=Rn=O.SP
v<Nll =O.SP
v"" =0.5P
PI
M =
, .., 4
.
PI'
8,._=-
V,_=wl
vdn=wt-wd
wl'
Mmox=
2
6 mox
wl'
=-
8£'1
R# =Rb=O.Swt
v,_ =O.Swt
V<�n=O.Swt-w d+� ( )
wel
M- =
8
6 moxob =�
384£'/
v..... � v..
R,=w(l+m)'/21
"I----.. ·�-·]
vr=::-
vrnoxb<=wm
V<�nt><=O.Swm-w(d+O.Slb)
v
&<- «
v-�=w(l'+m')/21
IM � I M-=:i ::::;;;J I
V��=w[(t'+m')/21]-w(d+O.SI,)
wm'
-�
Mb="14
6�
I Y.l �
M_,. =
6,
9:e, (l+m)'(l-m)'
=2::u(t-2l1x1+lx1-2m1t+2m1x1)
1--....L---Iflx ll�
a,=2:;.1( 4m1t-e+3m1)
As an example, the first interior support for plywood sheathing typically has a greater
reaction and receives greater load. However, in the case of a joist or stud, that supporting
member is not actually a vertically rigid support. When the first interior joist denects
slightly more, the plywood shifts some of the load to adjacent supports, making the reac
tions somewhat more uniform than apparent in the vertically rigid support case. For this
reason, loads on joists and stringers in slab forms and on studs and wales in wall forms
with three or more spans are often assumed to be based on simple tributary width and
taken as l.OwE. Two-span situations may need special consideration.
Shores and form ties are relatively stiff in tension and compression and provide essen
tially rigid support to stringers and wales. Procedures for calculating loads on ties will be
discussed further in this chapter, and loads on shores will be discussed in Chapter 8.
CHAPTER 7
7.4 Design Criteria for Wood Beams
7.4. 1 Stresses and Deformations
Structural properties for some of the common formwork mate
rials are given in Chapter 4. The limiting stresses are based on
applicable design specifications governing use of the particular
material that include appropriate factors of safety for ASD or
provide load factors for LRFD. AWC NOS wood design require
ments present reference design values for wood construction
that must be adjusted by numerous factors to arrive at adjusted
design values for ASD or adjusted design values for LRFD. These
adjustments are explained in Chapter 4 and detailed in the
examples of this chapter.
Established design specifications governing the use of
formwork materials, such as wood, steeL and aluminum,
6-spon example '-====;::====;::====;=:::j
J�
....., TR, ''l fo-
TRl
c____.J...___________ ___j
should always be followed. When fabricated formwork units
are used, manufacturers' recommendations for allowable
loads should be followed. These recommendations should be supported by standard
tests or by successful experience records.
Formwork is ordinarily thought of as a temporary structure because it remains in
place for only a short period of time. Limiting stresses recommended for the short-
term loads of temporary structures are often greater than those for the long-term load
duration and exposure of permanent construction. The form designer, in the interest
of economy, will want to take advantage of those greater limiting stresses whenever
possible. However, it should be remembered in the case of wood design that load dura
tion is the cumulative duration at maximum load. Because some construction personnel
and equipment live loads are of short duration, the time at maximum load may also be
shorter than the time the form is in place. If a member or a panel is to be used many
times or if it might degrade somewhat with time even though not damaged, it is appro
priate to assume longer load duration.
7.4.2 Bending
Design for bending is based on the adjusted bending stress design values for the mate
rial being used. Reference design values for bending stress for various kinds of lumber,
plywood, and other materials are given in Chapter 4. From Table 7.1, maximum bending
moment for a simply supported single-span or two-span continuous beam uniformly
loaded is
(7.2a)
whereM is the moment; fb is the stress in the extreme fiber in bending; and 5 is the section
modulus of the member. The resisting moment capacity, M" is limited to the moment that
results in the limiting extreme fiber bending stress.
M, = F;s (7.2b)
Because the resisting bending moment must equal or exceed the applied bending
moment, the maximum allowable span length is determined by equatingM, toM""'' and
solving for£. Thus, for a one- or two-span uniformly loaded beam
f= �
{7.3a)
1 = 2.83 - '1{F;S
;;;
e=3.16 v{F;S
--;- (7.3b)
The basic flexure formula, fb =M/5, can be used to check bending stress when all condi
tions of span and loading are known. Where calculations in this chapter apply specifically
to wood members, the term Fb' is used in place of fb to indicate adjusted design bending
stress, in agreement with notation of the AWC NOS.
where CO' eM' c� cl. CF' chic, and C,are adjustment factors. Most of these terms are
explained in the Chapter 4 discussion of solid sawn lumber (Table 4.4), except for C1.
The beam stability factor Ct' given in the
Table 7 3· Lateral restraint conditions for beam stability C - 1 0 AWC NOS, is applied to reference design
values to obtain a reduced adjusted
d/b value Some lumber members (bxd) Type of restramt needed
ronge m g1ven ronge of d/b volues for C, = 1.0 bending stress based on the slenderness
ratio of each beam as installed. No reduc
2x4, 4x4, 4x6, 4•8 and
d/bs2 No restraint required tion is required, however, where there is
any member used flatwise
sufficient lateral restraint to prevent lateral
2 < d/b$4 Ends prevented from lateral rotation
buckling. Table 7.3 shows how the NOS
Compression edge held in line ond
4 < d/b$5 2x10 defines this restraint based on a dlb ratio
ends prevented from lateral rotation
defined in terms of nominal dimensions of
Solid blocking, bridging, or cross
the beam cross section.
b-oeing at intervals nol exceeding 8 II,
5 < d/b$6 2x12 Formwork assemblies that meet these
compression edge held in line, ond
ends prevented from lateral rotation conditions can be designed with c, = 1.0.
Where these lateral support requirements
are not met, the beam stability factor can be
calculated using Section 3.3.3 of the AWC NOS and applied to the reference design values
along with other adjustment factors.
Concentrated Loads
The simplified design procedure developed herein is based on uniformly distributed
loads, although some form members such as wales, stringers, or ledgers actually support
a group of concentrated loads. This simplification is satisfactory for most cases, but if the
spacing of the series point loads exceeds one-half of the span length between supports of
the beam under consideration, a detailed analysis should be made for the worst loading
condition. This should be kept in mind particularly when designing heavy timber or steel
members at wide spacing.
Bending in Plywood
Calculation of plywood bending stress is similar to that for wood beam bending except
that
The direction of plywood face grain relative to plywood span direction determines the
selection of effective section modulus, KS, from Table 4.13; and
KS replaces 5 in the bending equation relationships.
CHAPTER 7
7.4.3 Deflection
The project specifications will define tolerances for formed concrete surfaces. This deter
mines the maximum deflection that can be allowed in the forms. Forms must be designed
so the various parts will not deflect beyond these prescribed limits. Otherwise, wavy lines,
unsightly bulges, and possibly even cracks will mar the appearance of the concrete. Addi
tionally, the amount of deflection can have a direct impact on the volume of the concrete
used, which affects the economy, weight, and performance of the finished concrete struc
ture. The exact amount of deflection permissible depends on the desired finish as well
as the location. A small deflection that might not be noticeable on a rough textured wall
might be objectionable on a very smooth surface. If surfaces are near eye level, or can be
observed from short distances, less deflection can be allowed than in upper stories where
irregularities are not as noticeable. Special deflection problems for architectural concrete
forms are noted in Chapter 14.
Tolerances for the finished work must be considered in determining allowable deflec-
tion of formwork. The deflection must be kept well within the specified tolerance limits for
completed construction because deviations for other reasons must also be allowed for. In
the absence of job specifications to the contrary, an acceptable and frequently used value of
allowable deflection for structural concrete work is 1/240 of the span length of the formwork
member. Note that ACI 301-10, NSpecifications for Structural Concrete.w calls for a deflec-
tion limit of 1/240 of the span length of form sheathing for structural concrete, and 1/400
of the span length for all form components in architectural concrete work. Some designers
prefer to limit deflection to 1/16 in. for sheathing and 1/8 in. for other form members. Where
the span length of the form member is relatively long-S ft or more-1/4 in. deflection is
frequently acceptable. Deflection will govern design where depth of the member is small in
relation to span length, as is often the case with sheathing. Joists, studs, and other members
should also be checked for deflection. The adjusted modulus of elasticity, E; appears in the
deflection formulas that follow. Note in the discussion of the properties of wood that this
modulus of elasticity is different for various species and grades of wood; this means that for
the same load, span, and size of lumber, some wood members will deflect more than others.
The larger the£' values, the stiffer the wood, and hence the smaller the deflection.
E' = ECIIIC,C,
When wood becomes wet, as is often the case with form sheathing, it becomes more
flexible, and this loss of stiffness is reflected in the moisture adjustment factor, CAl' of 0.9
shown in Table 4.6. This adjustment should be applied to the tabulated reference value of
£'for board sheathing or any form members that will become wet during service.
While construction live loads should be included in all strength calculations, often the
calculation of deflection does not include construction live loads. Deflection is often calcu
lated using only the load of the freshly poured concrete and weight of the form members
(where appropriate) because live load is present only during placing and finishing.
The maximum deflection for beams of various spans is
5wt•
Single simple span 6,..... = (7.4a)
384E'I
wl'
Two-span continuous = (7.4b)
.1.,.... 185£'/
{=0.738 (; (7.5)
Similarly, for a simply supported single-span beam and again setting 8,.,. equal to
t/360, the maximum span length is determined using
t Swt
=
360 384£'/
which reduces to
l= o.s97 .WI
v-;- (7.6)
If a limiting deflection of 1/16 in. or 1/8 in. has been set, a check using Eq. (7.4a), (7.4b),
or (7.4c) can be made to see if that limit has been exceeded.
Deflecfion of Plywood
Calculation of plywood deflection is similar to wood beam deflection except that the
direction of plywood face grain relative to plywood span direction (Fig. 4.11) determines
the selection of moment of inertia,/, from Table 4.13. In most formwork applications,
deflection can be based on the bending deflection with f'taken as 1,500,000 psi from
Table 4.14 for the case without considering shear deflection and e taken as the center-to
center of support span length. When it is desired to calculate deflection with more accu
racy, consult APA V345V-2012, �concrete Forming-Design/Construction Guide; and APA
0510(-2012, �Panel Design Specification.wBending and shear deflection can be calculated
separately with a span length close to the clear span and separate E'values applying to
the two components of deflection.
7.4.4 Shear
In a loaded beam, there is a tendency for one part of the beam to move vertically with
respect to an adjoining part. This tendency for movement at right angles to the beam axis
is referred to as vertical shear. There is also a tendency for fibers to slide past one another
in a horizontal direction, parallel to the length of the beam, and this is called horizontal
shear. Obviously these terms were developed when viewing the beam as a horizontal
member, but by thinking of their direction in relation to the axis of the beam, they can
easily be applied to beams positioned vertically, such as the studs in vertical formwork.
At any point in a beam, horizontal and vertical shear are of equal intensity, acting at right
angles to each other. Uniform materials such as steel can resist either type of shear equally
well, but a fibrous material such as wood does not resist splitting or shearing between the
fibers (which are generally parallel to the beam axis) as well as it resists shearing action
across the grain. Because the horizontal shearing stress is more critical for wood, and
wood has long been one of the major materials for formwork, it is common when consid
ering shear for wood member formwork design to speak in terms of horizontal shear.
The intensity of horizontal shear within the beam is calculated on the basis of vertical
shear force, V, at the section being considered. In designing formwork, only the section at
which Vis maximum needs to be considered. Maximum values of Vare shown for beam
loading conditions in Table 7.l. lf shear is being checked for other loading conditions, it
is helpful to remember that Vat any section is equal to the algebraic sum of all vertical
forces, both loads and reactions, on either side of the section.
f= _!i_ (7.7)
• 2bd
7-10 CHAPTER 7
where the shear-stress distribution is parabolic over the beam depth and f is the
maximum at the neutral axis. The theoretical maximum shear force at a su port of zero P
width is V"""' = O.Swe for uniformly loaded single-span beams, 0.625we for uniformly
loaded two-span beams, and approximately 0.6w€ for uniformly loaded beams continuous
for three or more spans (refer to Table 7.1).1t is not necessary to check shear perpendicular
to the grain in wood members because they will always fail in horizontal shear before
reaching the critical stress in vertical shear.
The maximum horizontal shearing stress, fy, must not exceed the adjusted design value
for horizontal shear, F;, for the species and grade of lumber being used. Adjustment
factors applicable for shear are as defined in Table 4.4.
F.'=F. CDCMC,CI
The resisting shear force is
v;
= 2F�bd
When calculating the shear force Vfor bending members, the design recommenda
tions of the AWC NOS permit neglecting distributed loads within a distanced (depth of
the beam) from the face of the supports if the beam is supported by full bearing on one
surface and loads are applied on the opposite surface (Fig. 7.4). Thus, the equations for
maximum design shear in wood for distributed loads can be stated as
Single span V<�n =0.5wt-w(d+%-) (7.8a) Fig. 7.4: Dimensions for shear calculations in
wood beams near supports
Two-span Vn
d =0.625wt-w(d+%-) (7.8b)
(7.9a)
Three-span . o
f= :dw[t'-(1.67d+0.83l;,)J (7.10c)
Solving for the maximum span length, e, in each case based on setting ( equal to the
adjusted design shear stress, F'.
Single span f= :�:+2d+l;, {7.11a)
d
Two-span t= F.'b +1.6d+0.8l;, (7.11b)
0.94w
d
Three-span l= F.'b +1 . 67d 0.83(" (7.11c)
0.9w
+
Shear stress may determine the size of member required where short spans are heavily
loaded. It is rarely the governing factor in sheathing but should be checked. Where
spacing of a series of concentrated loads is greater than one-half of the beam span length,
check shear on the basis of point loads, rather than using the equivalent uniform load that
is sufficiently accurate for much formwork design.
Sheoc in Plywood
Plywood panels are checked for rolling shear stress, f,, in the plane of the plies using the
formula
f=!'Q=� (7.12)
" lb lb(Q
where lb/Q is the rolling shear constant from Table 4.13. Note that Q, the first moment
of area, is not calculated separately and combined with band /when calculating shear
in plywood; rather, the tabulated values for the rolling shear constant must be used. The
shear force for plywood design is similar to that for wood beams except that the shear is
calculated at the face of the support rather than a distance dfrom the face.
Because shear is calculated at the face of the support, the clear span, e<' is typically the
basis of the shear-force calculation for plywood.
Solving for the maximum clear span based on the allowable plywood shear stress, F,'
Single span f,= F���:�o) (7.14a)
F;(Ib(Q)
Two-span f (7.14b)
< = 0_625w
(7.14c)
7-12 CHAPTER 7
The center-to-center span length,£, is the clear span plus half the total width of the
bearing member at each support
The bearing width,£11 of members supporting plywood is often either 1.5 in. or 3.5 in.
7.4.5 Bearing
Bearing stress or compression perpendicular to grain is a factor in design of timber
members of formwork. Joists rest on stringers, stringers may in turn bear on posts or
shores, and studs bear against wales. All these members must either have sufficient area
of bearing on their supports to prevent crushing of the grain of the timbers or a means of
adjustment to compensate for crushing. Otherwise, the formwork will settle out of posi
tion or have undesirable cracks and openings. The bearing stress is
R
(,, =;;;- (7.16)
where R is the reaction load transmitted in bearing; and A0 is the bearing contact area.
When calculating the bearing stress at the ends of beams, no adjustment is made for
increased pressure upon the inner edge, compared with pressure at the end of the beam
due to bending. The average bearing stress is considered adequate for design.
Hardwood caps or metal bearing plates may be placed between vertical and horizontal
bearing timbers so that the concentrated pressure from the posts may be distributed over
a large area of the weaker side grain of the horizontal member.
The reference design values for compression perpendicular to the grain require adjust
ment, as indicated in Table 4.4. The moisture and temperature adjustments were discussed
and tabulated in Chapter 4. The bearing adjustment factor C0 is a function of the member
dimensions and layout. When the bearing area is within 3 in. of the end of the member
being investigated or when the length of bearing is 2-: 6 in.
otherwise
C = lb +3/B"
• (7.17)
e,
where eo is the length of bearing in inches measured parallel to the grain direction of the
wood piece being evaluated. For round washers or bearing areas, use a length equal to
the diameter. Bearing must be investigated
for both a wood member transmitting the Table 7.4: Bearing adjustment factors, C.,
load and a wood member receiving the
load. The adjustment factors for lengths of Length of 6 or
bearing on such small areas as intersecting beormg, t, m. 1/2 1 1 1/2 2 2-1/2 3 3 1/2 4 more
wood members, plates, and washers are c.
shown in Table 7.4. Example 7.1 illustrates
the bearing stress calculations using ASD.
000 lb
f =..!!_= 4 =267 psi Totaldesignload•17Spsf
<J. -\ 15 in.2
2 � 6 S4SJoiats
CHAPTER 7
concrete columns so that no shores are
required.
If shoring support points are limited
by poor bearing or the need for large
open spaces in the work area, long-span
metal members-so-called horizontal
shoring-may be introduced, and other
components must be sized to fit them. If
shoring frames are used, their spacing may
first be determined on the basis of loading
to their recommended working limit; then
joists and stringers are selected to suit this
spacing. The latter approach will gener-
ally result in a design of heavier members
at wider spacings than the approach of
working outward from the sheathing.
Deciding to use certain materials or acces
sories already on hand may save money,
but they will also influence design of the
other formwork parts that must be adapted
to them, and can potentially affect labor
costs. Fig. 7.5: Wall formwork constructed with plywood, wood vertical studs, wood horizontal
There are several possible starting points double wales, and snap ties
for wall and slab form design. The following
suggested design procedures cover these alternatives for various members. However, the
accompanying design examples are based on a single set of assumed job conditions, and
only one of the alternative courses is fully developed for each problem.
CHAPTER7
B. If tie spacing is fixed, solve the shear formula for bd, which is the required area of wale
cross section. Select a suitable pair of members to meet this requirement. Remember that
bd is total area of two wale members.
DEFLECTION CHECK
Deflection of wales is seldom critical but should be considered for one- and two-span
conditions and for cantilevers. A check may be made based on the beam formulas of Table
7.1.
5. Tie design-Base tie design on the total load as explained in Section 7.10.1.1f the
available tie material makes it necessary to space ties closer, wales may be redesigned for
this shorter span length between supports. In some cases, the tie to be used is chosen first
(for example, using materials already on hand), and tie spacings are then set to load the
tie to its safe capacity. Framing members can then be designed to fit tie spacing, in effect
reversing the design sequence outlined previously.
6. Check bearing stresses as recommended in Section 7.4.5.
7. Lateral bracing for wall for ms Based on methods presented in Chapter
-
5, find the
lateral force for which wall form bracing must be designed. Because the force may act in
either direction, single-side bracing must be designed to take either tension or compres
sion. Bracing can be located on both sides of the wall form when fully erected. However,
bracing must be able to resist tension or compression for the stage when only one side of
the form is erected and reinforcing is being placed. Bracing design is covered in Chapter B.
The design of a wall form using ASO is shown in Example 7.2.
Several members of a wall form could alternately be designed using the LRFD method
but not presently all. Plywood design specifications are currently based on A5D only. Many
formwork hardware devices, such as ties, are rated for working (allowable) load capacity
and rating methods have not been established by ACI 347R for LRFD use. LRFD design
procedures are illustrated in Example 7.3 for the studs designed by ASD in Example 7.2.
mttm1tft4141il#ff1ttl•l§l.l,§·\i•
Design forms for a 14 ft high wall to be placed at a rate of 3 ftlh,
internally vibrated. Assume the normalweight concrete is made
with Type II cement, with no pozzolans or set-retarding admix
tures, and that the temperature of concrete at placing is 60"F.
Slump is 4 in. The forms will be used only a few times and are
often stripped after 1 day, so short-term load duration adjust
ments will apply.
Form grade 3/4 in. thick Class I BB Plyform sheathing is avail
able in 4 x 8ft sheets, and 3350 lb {safe working load) ties with
2 x 6 in. wedge plates are on hand. Framing lumber of 545 No.
p • 600 psf
2 Douglas Fir-larch is to be purchased as required. The tenta
tive plan is to use 2x4s for studs and wales. Form panels 8ft
Fig. A: Concrete lateral pressure distri
wide and 14 ft high will be assembled with plywood face grain
bution in wall form
horizontal and studs aligned out-to-out at the two vertical
edges. Deflection of sheathing and studs is limited to the lesser
of E/360 or 1/16 in. CHECK BENDING, considering a 12 in. wide strip of plywood.
Step 1. Find Pressure. This concrete will have unit weight and Maximum allowable span length, by Eq. (7.3b) modified for
chemistry coefficients of 1.0, according to Tables 5.4 and 5.5. plywood. is
�
Therefore, the pressure CcP= 600 lb/ft1 given in Table 5.7 can be
used without further modification. The lateral pressure distribu l=3.16
tion is shown in Fig. A.
Step 2. Select Sheathing. The sheathing will be the same
thickness throughout the wall height, and supports will be From Table 4.14, the adjusted bending stress for Class I 88
uniformly spaced. Because 4x8sheets of plywood are to be Plyform, used wet, is 1933 psi. KS for 3/4 in. plywood, consid
used, supports will be spaced to fall at the edges of the panels. ering a 12 in. wide strip, is 0.455 in.3 when face grain is parallel
Use plywood the·strong way�-that is, with face grain parallel to the plywood span (Table 4.13). Also, for the 1 ft wide strip
to the plywood span. In this case, it means placing the 8ft w=CCPx l.Oft = 600 lb/ft =50 lb/in.
dimension of the panel horizontally {Fig. 8). The panels will be
Then substituting to determine the maximum span length
continuous beams.
l=3.16
1933 psix0.455 in.J J
-3.16 17.s9 in.l =13.2 in.
50 lb/in.
t, F� lb/0) 2
{ 72 psix7.187 in.
= = 17_25 in.
0.6w 0.6x50 lb/in.
f=1.735 •
1,500,000 psix0.199 in.•(in.) -
�
1.735 5970 in.• =15.2 in.
SO lb/in.
CHAPTER 7
C, = 1.15 from Chapter 4 because there will be three or more Increased wale spacing is theoretically acceptable near the top of
studs spaced s; 24 in. on center; the form because the maximum design pressure declines from 600
C,., does not apply because the studs are oriented for strong lb/ft1 at a depth of 4ft to zero at the top. In this form, the top wale
axis bending; and could be spaced at a greater distance than 34.4 in. from the adja
C; does not apply because the wood is not incised. cent one. However, construction considerations often determine
The adjusted bending design value is the exact dimensions. The top and bottom wales are frequently set
approximately 1 ft from top and bottom of wall forms.
F: = FbC0C"'C,CtCfC,.,C,C,
With wales 12 in. from both top and bottom of the wall form,
F;= 900 psix1.25x1.5x1.15: 1940 psi 12ft or 144 in. remains for spacing the other wales,which can
be no more than 34.4 in. apart. Even measurements or modular
Use Eq. (7.3b) based on a three or more span continuous
dimensions are convenient for field assembly, so by trial and error
beam to determine the maximum stud span length with S =
we arrive at a selection of four spaces of 30 in. each and one of24
3.06 in.) for an S4S 2x4 from Table 4.2
in. (Fig. D). We place the smaller span length near the bottom of
the form where theoretically a higher pressure could occur if the
�=3 1940 psix3.06 in.
£ =3.16 ) 3.16.J118.7 in. 1=34.4 in. assumptions on placing conditions did not match those in the field.
v-:;- .16 50 lb/in. Step 4. Wale Size and Tie Spocing: Sketch the pressure
DEFLECTION CHECK: The allowable deflection !J. is required to diagram alongside the diagram of wale spacing, and determine
be less than the smaller of 1/360 of the span length or 1/16 in. equivalent uniform load per foot of wale. Assume that each
For the Douglas Fir-Larch 2x4, I= 5.36 in.' from Table 4.2 and E= wale carries load from the form for half the distance to each
1,600,000 psi from Table 4.3. Referring to Table 4.4 adjacent wale, a tributary width equal to the wale spacing. This
gives the equivalent uniform load per foot of wale.
E' = EC"'C,C,= 1,600,000 psi
Because 3350 lb (safe working load) ties are to be used, the
Using Eq. (7.5) fort.= f/360, the maximum allowable span tie spacing will be determined as noted in Step 5, which follows.
length is Wale design can then be developed using the calculated tie
spacing of 2ft. (Refer to Step 5,ne Design.)
e = 0.738 J£[_ = 0.738) 1,600,000 psix 5.36 in.' BENDING CHECK: Both span length and loading are known;
v-;; 50 lb/in.
thus, this is Case B. Substitute Fb'S forM,.,. in Eq. (7.1 b) and solve
for the required section modulus, S. (The equivalent uniform
= 0.738�171,SOO in.3 = 41.0 in. load is used although actual wale loading is point loading
applied where studs bear on wales.)
For .6,..,. = 1/16 in., substitute in Eq. (A) and solve to get F. ' : wt
s l
maximum allowable span length •
10
-'
r :-: --,-:-,-.,---:
--- -::-:-.,--,--;:--,-
.� 1,600,000 psix5.36 in.' (in.)
t=1.73s =1.73s • 5=� IBI
v� 50 lbfin. 10Fb'
The adjustments for bending stress in the wale are similar to
=1.735�171,500in.' =35.3 in.
those determined when checking the studs so long as we use
SHEAR CHECK: The reference design value for horizontal shear lumber 4 in. wide or less, except that the wales are not repetitive
of 180 psi fromTable4.3 is adjusted as follows (Table4.4) members because the spacing exceeds 24 in.
.'
f =F.C0C"'C,C1 =180 psix1.25=225 psi F;= 900 psix1.25xl.Sx1.0=1687 psi
When determining the center-to-center span of the studs,
length of bearing at the stud supports is often known or can be
anticipated. In this case, double S4S 2x4 wales would probably
-
.-.-·. � �:-:-·. �
·. •. [
be the minimum size so that the length of bearing is at least 1.5
in. at each end. For a three or more span continuous beam, the 02((:1U•6001'Z••U'• -� ,_,!'_,•_!.�... �
allowable span length from Eq. (7.11c) is
(800<.751•1,170 ..
spacing,
s, of 30 in. with the double 2x4s that make up the wale (Fig. E) The length
of bearing, £11 is 2 in. and Cb= 1.19 from Table 7.4. Other adjust
w(wale)=C" xs=600 lbtfe x� ment factors are either 1.0 or not applicable as before. From
12 in/ft
Table4.4
=1500 lb/ft=12Sib/in.
F,� = f.J._C,..C,C1Cb=625 psix1.19=743 psi
Substitute these values in Eq. (B)
The actual bearing stress is
125 lb/in.x 24 in.
( t
5 4_26 in.1 maximum reaction at tie 3300 lb
10x1687 psi 550 psi< 743 psi
bearing area 6_0 in.�
If a double-member wale is used, as is common to avoid drilling
of timbers, the computed 5is the required section modulus of
two members. Use Table 4.2 to select an appropriate size. Double
2x4s (S = 2 x 3.06 in.3= 6.12 in.1) meet the requirements.
5HEARCHECK: Use Eq. (7.11c) to check horizontal shear in the
proposed double 2x4 with the 2 in. wide tie wedge plate (Fig. E)
1Ylt in.
for bearing length and assuming equivalent uniform load
Bearing
2o: 25C.!:0:::
= ' .::1x.:. l .S::.::.: i, n;.:..x
2:..:
x:..: 5c: 1n
3c::
:.:: c:· +1.67x 3.5 in. +0.83x 2 in.=28.5 in.
0.9x125 lb/in.
Fig. E: Bearing area between tie wedge plate
When the series of point loads are spaced at intervals greater and double wale
than half the wale span length, a check using actual loads rather
than equivalent uniform loading is advisable. Review of the
similar cases in Fig. 7.1 where loads are spaced at half the span The actual bearing stress is within the allowable of 743 psi; thus,
length suggests that the 24 in. wale span length, with stud reac the bearing of the wedge plate on the wale is satisfactory.
tion point loads at 12 in. spacing, should be adequate. STUDS ON WALES: The bearing area between 2x4 studs and
StepS. Ti� Chsign: Assume that ties of 3350 lb safe working double 2x4 545 wales would be as shown in Fig. F.
load (allowable) capacity are available and will be used. Because
the tie provides rigid support, the load should be determined
1'Y:l in.
considering continuity of the wale at the first interior support.
When wale loading in lb per foot is known at the beginning of
Step 4, the tie spacing can then be calculated. Not all wales,
from form top to bottom, carry the same load. Tie spacing is
often designed for the heaviest loading and used uniformly 1%in.
throughout the form for concrete surface aesthetic consider
ations and convenience in drilling plywood panels.
1Y<tin.
Maximum load on the wale is w=600 lb/ft1 x 2.5 ft=1500 lb/
ft=12Sib/in. The maximum tie load from Table 7.2 for a three
Bearing
span continuous uniformly loaded beam is
area
Rb=R.=1.1wt
Setting the maximum reaction to the tie capacity and solving Fig. F: Bearing area between stud and wale
fore, the tie spacing
CHAPTER 7
f .&_
1500 lb Step 7. Lateral Bracing for this type of form is explained in
= = A, 2 =333 P si
cl
4.5 in. ChapterS.
The allowable bearing stress must consider both the length of Example summary:
bearing on the wale measured parallel to the grain of the wale, Sheathing: 3/4 in. Class I BB Plyform;
ib=1-1/2 in., and the length of bearing on the stud measured Studs:2x4 No.2 S45 Douglas Fir-Larch spaced at 12 in. on
parallel to the grain of the stud, eb=2(1-1/2 in.)+ 1/2 in.=3.5 in. center;
In the latter case, there are actually two areas of contact that Wales: double2x4 No.2 545 Douglas Fir-Larch spaced at 30
are close together. Using the total length is a conservative in. on center in maximum pressure region;
assumption because the cb factor is lower for greater bearing Ties: 3350 lb minimum capacity spaced at maximum of24
lengths. From Table 7.4, Cb = 1.11 and the allowable bearing in. with2 in. x 6 in. wedge plate washers.
stress is
•
iffmtftd@®IWjllmttlt!J1!.!.$!jlj
Use Eq. (7.3b) to determine the maximum stud span length as
As an example of LRFD design, the design for the span length of a continuous beam with 5= 3.06 in.3 for a S4S 2x4 from Table 4.2
the studs for Example 7.2 will be repeated using LRFD.
From Eq. (5.14), the factored lateral pressure becomes 1.6CCP fF:S=3.16 3016 psix3.06 in.3
t=3.16 v�
and with the 12 in. spacing of the studs based on the plywood solb/in.
maximum span length from theASD analysis J
=3.16 115.4in.1 =33.9 in.
w(studs) =1.6CcP x s = 1.6 x 600 lb/ft2 x 12 inJ12 inJft =960
SHEAR CHECK: The reference design value for horizontal shear
lb/ft = 80 lb/in.
of 180 psi from Table 4.3 is adjusted followingTable 4.4 and
BENDING CHECK: First, determine LRFD adjusted bending
Table 4.10 as follows
stress. Reference design value for bending stress Fb for No.2
Douglas Fir-Larch is 900 psi (Table 4.3). F;=F,C,�o�C,C, K, $,)..=180 psix2.88x0.75x0.9=350 psi
Possible adjustment factors from Table 4.4 are:
When determining the center-to-center span of the studs,
eM = 1.0 assuming the moisture content of the studs will not
length of bearing at the stud supports is often known or antici
exceed 19% for an extended period of time;
pated. In this case, double 5452x4 wales would probably be the
C,=1.0 because ambient temperature is unlikely to exceed
minimum size so that the length of bearing is at least 1.5 in. at
1 00°F during a concrete placement;
each end. For a three or more span continuous beam, the allow
Ct = l.OfromTable 7.3 and because nailing of plywood will
able span length from Eq. (7.11 c) is
provide lateral support to the studs;
C,=1.5fromTable4.8;
C = 1.15 from Chapter 4 because there will be three or more l= ��� +1.67d+0.83lb =
d
stu s spaced s24 in. on center;
350 psixl.S in. x3.5 in.
C��.o does not apply because the studs are oriented for strong +1.67x3.5 in.+0.83x2x1.5 in.=33.8 in.
axis bending; 0.9x80 lb/in.
C. does not apply because wood is not incised; Deflection of the studs must still be based on actual loads
K =2.54fromTable 4.10;
: rather than factored loads and therefore is calculated byASD as
$b = 0.85 from Table 4.10; and before.
>-=0.9. Comparing ASD and LRFD results for calculated span length
The selection of A is related to the duration of the dominant of the2x4 wall studs:
loads as discussed in Chapter 4. In this case, the value of 0.9 ASD LRFD
reflects the load duration less than 7 days.
Bending 34.4 in. 33.9in.
F; = 900 psi X 1.5 X 1.15x2.54 x 0.85x 0.9=3016 psi In this case, there is very little difference betweenASD and LRFD
results.
CHAPTERl
joist. If this exceeds the allowable stress, a modification to either size or span length must
be made.
4. Stringer size and span length (shore spacing)-Depending on job conditions,
either the shore spacing or the size of the stringer will have been preselected. The
other must be designed to correspond. Stringers are actually loaded with a series of
point loads from the joists, but for most cases an equivalent uniform load is sufficiently
accurate for design purposes. In cases of heavily loaded short spans, a shear check using
point loads may be desirable.
BENDING CHECK
A. If the stringer size is known, calculate the maximum allowable span length. This
establishes a maximum spacing of the shores.
B. If the span length of stringer is fixed by predetermined shore spacing, transpose the
basic equation to solve for the section modulus 5, and select a member (or members} with
the required 5.
DEFLECTION CHECK
A. If the stringer size is known, calculate the maximum allowable span length that meets
deflection requirements.
B. If the span length of the stringers is fixed on the basis of shore spacing, solve the
deflection equation for I and select a member to meet this requirement.
SHEAR CHECK
A. If the stringer size is known, calculate the maximum allowable span length that can
be used to keep shear stress r. below the allowable.
B. If the shore spacing is fixed, this in effect determines the span length of the stringers.
Use the shear formula to determine the required stringer cross-sectional area bd.
When these three checks have been made, it will be obvious which criterion governs
stringer design. If shear governs, it may be advisable to recheck the design using point
loads on the stringers instead of equivalent uniform loads because maximum horizontal
shear stress may be significantly affected by the location of the point loads.
5. Shore design to support stringers is based on principles given in Chapter 8. Shore
design (both spacing and size) may precede selection of stringers, or it may be done after
other formwork components have been designed. If available shores are not suitable to
support stringers at the designed spacing, the spacing must be revised. This may neces
sitate other design changes.
6. Check bearing stresses as recommended in Section 7.4.5, wherever loads are trans
mitted perpendicular to the grain of a wood member.
7. Design lateral bracing for shores to carry minimum lateral force prescribed in Table
5.6. Design of bracing is explained in Chapter 8.
Several members of a slab form could alternately be designed using theLRFD method
but presently not all can. Plywood design specifications are currently based on ASD only.
Many formwork hardware devices, such as manufactured steel and aluminum shores,
are rated for working {allowable) load capacity and rating methods have not been estab
lished by ACI 347R forLRFD use.LRFD design procedures for the joists designed by ASD in
Example 7.4 are illustrated in Example 7.5.
Design forms to support an 8 in. thick flat plate floor of normal Step 1: Estimate Loads
weight concrete, using construction grade Douglas Fir-larch Dead load concrete and reinforcing= CVMt= 100 lb/ft2
S4S framing members and steel shoring. Ceiling height is 8 ft 150 lb/ft3 x 8 inJ(12 inJft)
and bays are 15 x 15 ft. Shoring towers with a 5 ft leg spacing
Minimum construction live load on
each way are available and will be used so that the stringer
forms
spacing and typical span length will be 5 ft. Job conditions are
such that the wood joists and stringers will not be subject to Weight of forms, estimated eDt =Biblft1
wet service. Because the forms will have substantial reuse, do Total form vertical design load for q,=CDI. +Cw.te. +CI'£
not adjust reference design values for short-term load. Deflec strength = 1581b/ft2
tion of the sheathing is limited to the lesser of £/360 or 1/16 in.
Total form vertical design load for
between supporting form members and deflection of other
deflection
members is limited to £/360.Live load is temporary and need
The load of the fresh concrete can be considered as fixed
not be considered for vertical deflection.
material load, c,Mt' if it is placed without having temporary
This is the maximum span length based on bending strength 4.8 footnote. (Notice that if this were No. 1 or No. 21umber, a
of the plywood. However, deflection frequently governs size adjustment factor from Table 4.8 would be applied and
sheathing design and it must be checked. A shear check is also would vary with depth.)Because the forms will be used repeat
shown in the following, but it generally does not govern for edly, the cumulative load duration will be assumed >2 months so
sheathing with loads as light as this slab. thate0=1.0. From Table 7.3, (1=1.0 for a 2x4.1f a larger depth
CHECK DEFLEG/ON, considering a 12 in. width of sheathing. (2x6 or 2x8) is chosen, the joist ends will need to be restrained
Specified maximum allowable deflection I!. is the lesser of from rotation by full-depth blocking or other means fore1 to be
design load of qd =- 1081b/ft2or 1081b/ft =9.0 lb/in. Substituting The bending reference design value from Table 4.3 is Fb
in Eq. (7.5)fort.. ....... =- £/36 O =1000 psi. Assuming the temperature is below 100°F, no
temperature adjustment for either bending or shear stress is
l=0.738
Jf£. =0.738 r:-=-:-::-:-:-:-:::c:-o-
1 1,500,000 psix0.202 in:
needed. Based on stated job conditions, eM= 1.0. The joists will
v-;; 9.0 lb/in. be oriented for strong axis bending, not flat use, soC"'= 1.0,
and the wood is not indicated as being incised; thus, (1 = 1.0.
= 0.738 �33,667 in.1 23.8 in.
=
Because the joist spacing iss; 24 in., there are more than three,
and they are joined by the sheathing diaphragm, the repeti
and substituting in Eq. (A) (from Example 7.2)for l'l....,. = 1/16 in.
tive member factor can be considered, e,=1.15. The adjusted
bending stress is
l=1.735 £ 4� '/ n.)
�
=1.735 33,667 in: =23.5 in.
F;= Fbe DCMC,C1C,e��,C;C,
Maximum allowable span length on the basis of the deflec F;= 1000 psix1.15=1150 psi
tion limit of 1/16 in. would be 23.5 in. From Table 4.3, the reference design value for shear stress F. is
CHECK ROLLING SHEAR using Eq. (7.14c)for sheathing over 180 psi and forE is 1,500,000 psi. Because CD=1.0, eM =- 1.0, c, =-
at least three continuous spans. The maximum allowable clear 1.0, and (1 =1.0, the adjusted design values are
span length is
F;=F.C0CMC,C1 = 180 psi
t. _ F� b
( l / 0) _ 82 psix6.189 in.2 _
64.2 in. E' = EC, c,e, = 1,5oo,ooo psi
0.6w 0.6x13.161b/in.
The uniform load, w, on each joist using a tributary width
equal to the joist spacing, s = 19.2 in. is
CHAPTER 7
for strength calculations Trying the second option just for the exercise with d=5.5 in.
1581b/ft' . . and i"=3.5 in.
w=q, xs= l e x19.2 m.= 21.11b/m.=253 lb/ft
144 in. jf
F:= 0:'[t-(1.67d+0.83t,)]
for deflection calculations
O.Qx2� lb/in'[
180 psi 60 in.-(1.67x5.5 in.+0.83x3.5 in.)]
bd= O.Qx21·1 l�/in.[60 in.-12.1 in.]= 5.05 in.2 <�.6 =8.25 in.2
1
For the 545 2x4s, bd=5.25 in.1, = 5.36 in.•, and 5= 3.06 in.3 180 pSI
(values from Table 4.2).
CHECK BENDING: Determine required size for a continuous In this example, shear does not control design of the joist, but
beam of three spans£= 5 ft. Combining Eq. (7.1b) and (7.2b), the advantage of being able to calculate shear at distanced
rearranging, and substituting from the face of the support becomes apparent if there is a case
where it does control.
we Comparison of the three limiting criteria calculated previously
F.'5= shows that bending governs design and the minimum required
•
10
size is a 2x6 S4S. Some formwork contractors might prefer a
Solving for the unknown section modulus 4x4 S4S {that also meets the section property requirements).
Even though the larger cross-section area results in more wood
w(1 21.11b/in.x(60 in.t
5= = 6.60 in.3 volume and material cost, it might provide net savings through
10F; 10x1150 psi reduced labor and reduced materials due to not needing lateral
CHECK DEFLECTION: For a continuous beam, with deflection support for buckling.
limited to 1/360 of the span length, from Eq. (7.4c) Step 4. Stringer size and span length. The stringers are
( w(4 spaced at s=5 ft. Each stringer spans 5 ft from shore to shore
and is three-span continuous, as shown in Fig. B. First, find the
360 145E'I
equivalent uniform load on the stringers:
Solving for the unknown moment of inertia for strength calculations
360wf3 360x14.41b/in.x(60 inY _ w =q, xs=158 psfxS ft = 790 lb/ft = 65.8 lb/in.
5.15 in .•
1
145E' 145x1,500,000 psi for deflection calculations
Before checking shear, examine which sections satisfy the 5 W=qd XS=108Ib/ft1 X5ft=540 lb/ft=45 lbjin.
and I requirements for bending and deflection. Comparing the This equivalent uniform loading is usually sufficiently accu
2x S4S sections in Table 4.2, a 2x4 is insufficient; however, a 2x6 rate. However, if the stringer design selected is close to limiting
meets the requirements. 5=7.56 in.1> 6.60 in.1 and I= 20.08 in.• stresses or deflection, a recheck using point loading of joists
>> S.15 in.• on the stringers might be necessary. Rounding off span length
CHECK5HEAR: From Eq. (7.10c) with fv = Fv' values to get modular layout can result in extra capacity that
can offset differences due to the assumed load distribution.
Using construction-grade Douglas Fir-Larch S4S stringers,
F;= o:;[t-(L67d+O.S3t,)] adjusted design values will be the same as those for afore
mentioned joists except that the stringers are not repetitive
Solving for bd directly is difficult because to fully benefit from members because their spacing> 24 in. Therefore, Fb'=1000
designing for the shear force at a distancedfrom the face of psi. Obtain cross-sectional properties by the same process as
the support, one needs to know the width of the supporting used for the joists.
stringer and the depth of the joist, which might not be known CHECK BENDING:
at this point. There are two options:
Ignore the benefit of the reduced shear force at distanced we 65.81b/in.x(60 in.)2
5= = 23.7 in.3
from the support face and see if shear does not control; or 10F; 10x1000 psi
Use the knowledge of a possible size based on bending and
deflection requirements, estimate ib based on experience, CHECK DEFLECTION: Working with a deflection limit of 1/360
and verify size when the stringer is selected. of the span length
Trying the first option:
'= 0.9wl 1 360wl1 360x451b/in.x(60 in.t •
F• 16.1 in.
bd 145E' 145x1,500,000 psi
CHECK SHEAR: Simplify the initial check by using the shear at
0.9wf 0.9x21.11b/in.x60 in.
bd the support to see if shear controls.
F; 180 psi
0.9x65.8 lb/in.x60 in.
= 6.33 in.1 <AM= 8.25 in.1 shear does not control bd- 0.9wf 19.74 in.
1
F; 180 psi
The length of bearing,E,. is 11.5 in. and C�= 1.0 from Table
7.4. Other adjustment factors are either 1.0 or not applicable
4x8S4S \ as before. From Table 4.3, F,.�. =625 psi and with adjustments
s·-a·o.�.�
listed in Table 4.4
F.� =F..�.CMC,C1C� =625 psi x 1.0 =625 psi
f
= -- R -- = 4350lb =l
08psi
' .�.
4x4shofes
@60•o.c. bearing area 40.25 in.1
which is well below the A5D adjusted design value for F<.l.' of
625 psi.
Joist bearing on stringer: The two members are 1-1/2 and
3-1/2 in. wide. Contact bearing area is 3-112 x 1-112 =5.25 in.2,
Fig. 8: Slab form stringers supported by shores as illustrated in Fig. D.
Consulting Table 4.2, the objective is to find a si2e that meets all
three requirements and will not have a lateral stability problem. 1'12 in.
A 4x8 S4S has the necessary section properties and with a d!b of
2 automatically satisfies lateral stability. Comparing properties
to those needed:
be made in the next step. joist spacing x joist span length x form load
CHAPTERl
l#ittf1]tjlj@Hi1'itli!)ifflffl•l§!.!.¥!·!i•
For this example, the design for the span length of the joists for CHECK SHEAR: For purposes of comparison, calculate using
Example 7.4 will be repeated using LRFD. Fresh concrete can be the same two options considered inASD Example 7.4.Trying
considered fixed material load, c,Mt' if it is placed without having the first option(ignore the benefit of the reduced shear force at
temporary excess thickness. But it should be considered vari distance d from the support face)
able material load, CVMt' if temporarily over-deposited in local
areas.
f 0.9wf
•=
From Eq.(5.8), the controlling factored vertical load with CI"IAt bd
= 0 and CH = 0 becomes
0.9wf 0.9x30.71b/in.x60 in.
q = 1.2(01.+ 1.2(FMt + 1.4(vMt+ 1.6(1'£+ 1.6(H bd= = 5_33 in.1
= 1.2 X 8lb/ft2+ 1.4 X 100 lb/ft2+ 1.6 X 50lb/ft2 = 230 lb/h2 F; 311 psi
With the 19.2 in. spacing of the studs based on the plywood
Also trying the second option(estimating e�> based on experi
maximum span length from theASD analysis
ence and verifying the stringer is properly sized) with d =5.5 in.
w(joists) = q x s = 230 lb/ft1 x 19.2 in./12 in./ft = 368 lb/ft
andeb= 3.5 in.
= 30.7 lb/in.
The bending reference design value fromTable 4.3 is F�>=
1000 psi.As inASD Example 7.4, ("' = 1.0, C,= 1.0, (1 =1.0, C, F;= :
o w
d
[ 1- (1.67d+0.831, )]
= 1.0, C,.,= 1.0, (1= 1.0, and C,= 1.15. FromTable 4.10, KF= 2.54
and ¢1�>=0.85. For significant reuse, take A= 0.8. 311 psi
0 9x
· 3�: lb/in
" [ 60 in.-(1.67x5.5 in.+0.83x3.5 in.)]
necessary to review the planned form layout to understand how the loads are transmitted
before working out a rational design. Some of the members are often selected on the
basis of experience and local or company practices may be reflected in the final design.
Considering vertical loads, one approach is to put blocking under the ledger at each
shore to safely transmit slab load via beam action of the ledger to the supporting
shores, as discussed in Example 7.6. Although these ledgers are nailed to the beam
sides. the strength of the nailed connections is neglected in this design approach.
Another approach, however, might use the nailed connections of the ledger to transmit
slab load to the beam side. This is practical only when the beam sides are stiff and
strong enough to distribute the slab load to the shores, which is not always the case
with typical plywood forms.
In considering the latera/loads on the beam sides, the general principles used in wall
design are applicable, but experience and local practices are important in selections
made. For shallow beams, a nominal size of sheathing or plywood is frequently chosen on
the basis of experience, rather than a calculated design. One designer reports using 3/4 in.
plywood with ledger attached, then adding vertical 2x4 Hstiffeners"for these beam sides
whenever beam depth is greater than 20 in. For beams up to approximately 2 ft deep, a
mtrtf!1tjlij:ttlJi!.!.
tttfl#®fl ¥·\it
The beam form shown at right for a 12 in. wide beam with a
total depth of 20 in. is to be used twice. Assume that no unusual
weight allowance for beam reinforcement is necessary-that is,
combined steel and concrete weighs 1SO lb/ftl. Form deflection
is limited to 1/8 in. between support locations.
Step 1. Beam bottom design: First estimate the loading:
12 in. x 20 in.
Dead load of concrete and steel= (150 lb ft)) =
/
250ib/ft /
144in.2 ft2
CHAPTER 7
Design bottom of the beam form for this load by checking e 163 psix11.25 in.xl.S in.
for bending, deflection, and shear. Assuming that the beam +1.67x1.5 in.+0.83x3.5 in.=
0.9x25.4 lb/in.
form bottom is made of a 12x2 S4S board of No. 2 Spruce
Pine-Fir (SPF) running the length of the beam underside, find 120.3 in.+2.5 in.+2.9 in.=125 in.
the maximum distance it can span between shores or shoring Deflection clearly governs support spacing (42.9 in.) under this
frames that support it. Because the actual dimensions of the beam bottom. For layout convenience, set shores 3 ft 6 in. apart.
board are 11-1/4 x 1-1/2 in., a non-load-bearing filler of either Note that this should be conservative because support that
3/4 in. plywood or a 1x2 54S will be attached on one side. would be expected from nailing the side plywood sheathing to
Find the cross-section properties inTable 4.2. bd= 16.87 in.1; I the edge of the bottom board has been neglected.
= 3.16 in.4; and 5= 4.21 in.30btain reference design values from An alternate approach to design of this beam bottom form
Table 4.3. For only two uses, the duration at maximum load can
would be to select a convenient shore spacing first, then
be reasonably taken as.,:; 7 days because the live load portion
determine what cross section (in terms of I, 5, and bd) would be
of the maximum load is of very short duration so that C0= 1.25. required to span the chosen distance.
The bottom board will be in direct contact with the concrete
Step 2, Beam side design: Assume that 3/4 in. plywood
and thus subject to wet service.The bottom board will be sheathing and the 2x4 kicker have been selected on the basis of
oriented in weak axis bending or flat use so that C,.,= 1.2 from experience. Shore spacing determined in Step 1 is 42 in., and the
Table 4.8. Considering other conditions, (1= 1.0, C,= 1.0, C,= construction plan as indicated in the sketch is to place blocking at
1.0, c,= 1.0, and (= 1.0. From Table 4.3, Fb=875 psi and from each shore to support the ledger. Using this setup, the ledger will
theTable 4.6 footnote FbC,=875 psi so that C�,�= 1.0. Calculating be continuous over several spans of 40 in., neglecting strength
the adjusted design value for bending stress of the nailed connection to the sheathing. If the ledger to be
used is also No. 2 grade SPF, what size ledger will be required?
Adjust reference design values ofTable 4.3 for shorHerm load.
F;=875 psix1.25x1.2=1310 psi Adjustment for wet service is not needed because anticipated
in-use moisture content is not expected to exceed 19%. Based
For horizontal shear, the reference design value of F. is 135 on experience, estimate that a 2x41edger in strong axis bending
psi, and the wet service factor C�,� is 0.97, giving may be adequate and confirm by analysis. For a 2x4, c,=1.5 from
Table 4.8 and Ct=1.0 fromTable 7.3.These adjustments must be
confirmed based on the final size selected or revised.
For modulus of elasticity, only a wet service adjustment factor Fb'= 875 psi X 1.25 X 1.5= 1640 psi
C�,� of 0.9 is required. f.'= 135 psi x 1.25= 168 psi
E'= 1,400,000 psi (no adjustments needed)
E' = EC�,�c,c,= 1,400,000 psi x 0.9= 1,260,000 psi
Loading must first be estimated. Although the joist loads
The beam bottom will be continuous over several supports and represent a series of concentrated loads, they may be simplified
its maximum deflection between supports will be held to 1/8 in. to an equivalent uniform loading, w. lf the equivalent uniform
as required by the project specification. load was high, or if the ledger section selected were loaded at
CHECK BENDING: From Eq. (7.3b), the maximum unsupported or near its capacity, then a more precise check using point loads
length will be
J¥
would be advisable. Assume a slab form weight of 5 lb/ft1•
Ledger loading: On the right side of the beam, the ledger
1310 psix4.21in.3 .
f=3.16 =3.16 . 46.5 ln. carries a 4 in. slab plus assumed live load on a 2 ft width.There
25.41bfm.
fore, for the right ledger:
slab load= 2 ft x (4 in/12 in./ftl x 150 lb/ft'= 100 lb/ft
CHECK DEFLEUION: Use Eq. (7.4c) to determine the maximum form load= 2ft x 5 lb/ft1= 10 lb/ft
unsupported length for a deflection limit of 1/8 in. live load= 2 ft x 50 lb/ft1= 100 lb/ft
w (total on ledger for strength)= 210 lb/ft= 17.5 lb/in.
w i'
" =-� w (total on ledger for deflection)= 110 lb/ft= 9.2 lb/ln.
""" 145£'/
On the left side, the ledger carries a 2-1/2 ft slab width, so total
�-------,,- loading on left ledger is:
145x1,260,000 psix3.16 in.4 x in.
f=
l �4SE d....,
l g
\ �---:c :-::-::-;:-�--� =42·9 in.
slab load= 2.5 ft x (4 in./12 in./ft) x 150 lb/ft'= 12S lb/ft
2131b/; n. form load= 2.5 ft x 5 lb/ft1= 13 lb/ft
live load= 2.5 ft x 50 lb/ft1= 125 lb/ft
CHECK SHEAR: From Eq. (7.11c), the maximum unsupported w (total on ledger for strength)= 263 lb/ft= 21.91b/in.
length is w (total on ledger for deflection)=138 lb/ft = 11.5 lb/in.
Use the larger left-side values to determine the required section
F.'bd of the ledger.
i=- +1.67d +0.83fb
0.9w BENDING REQUIREMENT will be determined by combining Eq.
(7.1b) and (7.2b) and solving for 5, the required section modulus
The supporting crossbeam size has not been determined but
based on experience, it is likely to be a 4x 545 section so that eb wt 21.9 lb/in.x(42 in. Y
5= 3
would be 3.5 in. Substituting 2 6 in.3
10Fb' 10x1640 psi
single tie across the top, and/or knee bracing to the shore heads is considered satisfactory.
Slab sheathing may sometimes be framed into beam sides to contribute lateral support.
For heavier deep beams, ties designed for the full liquid head of fresh concrete are essen
tial. Because of the comparatively heavy reinforcement in beams, interference with the ties
is more likely to occur than in walls, and more careful tie location planning is required.
3. Shoring: Shores for beam forms are generally spaced to meet beam bottom
support requirements. However, they carry dead and live loads not only from the beam
but also frequently from adjoining slab forms whose joists bear on the ledger fixed to
the beam side (Fig. 7.7 and 7.8). Determine the total load to be supported and design
these shores according to suggestions in Chapter 8.1f the slab on one side of the beam
is concreted ahead of the beam form and opposite slab, or if the slab on one side is
considerably heavier, the unbalanced load may cause rotation of the beam form. This
is one reason many designers use double-post shores or shoring frames under beam
forms. Concreting the beams first, placing a considerable
Beam shores support this part of the shore loading concentrically in advance of
slab load and beam load slab concreting, is another way to overcome the rotation
tendency.
4. Bearing and ties: Where heavy loads are involved,
bearing stresses may require investigation, as explained
earlier in this chapter. Ties may be required for deep beams,
and their design follows suggestions presented earlier for
wall form tie design.
Beam form design calculations using ASD methods are
shown in Example 7.6.
CHAPTER 7
If proprietary column forms or column clamps are used, Beam shores support this
the manufacturer's recommendations, based on load tests
I- slab load and beam load
I
or a successful experience record, should be followed,
I I I
so long as the equipment remains in good condition.
Although ACI 347R does not have a recommended safety
I
factor for column clamps, it seems prudent to use at least t j_ I
2.0, the same factor recommended for form ties. I I II
It is important to consider the manufacturer's recom I
J�
� �
mendations. For example, if there is a recommended limit I
on concrete placement rate, it should be strictly followed.
1 Slab lo d heavier
Faster filling will produce greater pressures that may cause
/ on this side
unsightly deformation of the finished columns or form
blowout due to clamp failure. "
There are several kinds of shop-built or job-built forms " //
made by contractors, for which the following design X. Double post shore
provides greater
suggestions are applicable. Because the amount of inter " stability when loads
action between sheathing and yokes or clamps varies // are unbalanced
considerably from one kind of construction to another, and
because the degree of rigidity of connections in clamps Fig. 7.8: Unbalanced load on shores due to thicker slab on one side of beam
and yokes is also variable, a simplified approach to design
is necessary as follows.
17.18)
B. Verify rated pressure; check joining bolt tension force, T, if sectional or seamed
for bolts at spacing sb.
(7.19)
CHAPTER 7
4. Select yoke ore/amp spacing: Compare spacing requirements of both sheathing and
yokes, and determine a yoke spacing that will meet both requirements and, at the same
time, add up to total column height in increments convenient for the form builder. The
uppermost clamp is usually a fixed distance below the top of the column, depending on
the type of construction. The bottom clamp is also spaced an arbitrary distance above
the column base, from 6 in. up to approximately 12 in. {a good rule of thumb is that the
distance below the bottom clamp should not exceed 1/3 the distance of the typical clamp
spacing). Thickness of the template used to position the form at the bottom {Fig. 7.9) may
affect the distance. If a cleanout door is used, the first clamp should be located to hold it.
Example 7.7 provides an illustration of the column form design procedure using
ASD methods. Determination of the bolt tension in a round column form is shown in
Example 7.8.
7. 1 0 Form Accessories
In general, the form accessory units should provide the strength to support reactions from
the framing members. The most economical tie is one that will fully develop the strength
of the form lumber when the tie is loaded to its recommended capacity. Normally, the
best balance is achieved by using the fewest units possible to safely carry the required
Assume that a 20 in. square column is to be placed to a height can be used. If stronger plywood was used, it might be possible
of 12 ft in 1 hour with concrete weighing 145 lb/ft3 and to use only three flat 2x4s.
assuming concrete temperature of 60QF. The concrete contains The two middle 2x4s are the most heavily loaded, and column
Type II cement and 25% fly ash without a retarding admixture. clamps must be located to support them. Assuming the pressure
Where beams or girders frame into the column, placement on a 6 in. tributary width of sheathing is transmitted to each of
height will be to the bottom surface of the lowest intersecting them, we can design the damp spacing to support a 2x4 with a
beam to allow subsequent placement of beam and girder uniform load of w= Ca X 0.5 ft. Because this design is for equivalent
reinforcement. Design the form for 10 to 20 uses, with 3/4 in. fluid pressure, we can calculate a linearly reduced pressure each
B-B Plyform Class I plywood sheathing supported by S4S 2x4s of time we move up the column to select another clamp location.
No. 2 Southern Pine {or equal) used flat and clamped with metal Allowable stresses for design will be calculated from reference
Mself-squaringM clamps. design values in Table 4.3, by applying appropriate adjust-
Step 1. Lareral pressure is determined from procedures in ment factors. For bending stress Ft>' apply the flat use factor
Chapter 5 based on ACI 347R recommendations C,v = 1.1. Because columns are usually stripped in 1 to 3 days,
the average duration at maximum pressure should not exceed
CCPmc• = CcCwflSO + 9000R;n = 1.2 x 1.0 [1SO + 9000(12/60)] =
approximately 2 days for each of the 20 reuses of the forms for
2340 lb/ft2
a total durations of 40 days s 2 months. Thus, take C0 = 1.15.
but not greater than No. 2 Southern Pine requires no size adjustment and the beam
(cp= Wch = 14S lb/ft3 X 12 ft = 1740 lb/ft2 stability adjustment, Cl' is automatically 1.0 for the flat use d/b
ratio. The 2x4s qualify as repetitive members making C, = 1.15.
The concrete in this example is placed rapidly and the equiva
Wet-use conditions will vary with the site environment; assume
lent liquid head is assumed to vary uniformly from zero at the
wet service so CM is 0.8S for F"' 0.97 for F., and 0.9 forE adjust
top to 1740 lb/ft2 at the bottom of the column.
ments. Incising and temperature factors can be taken as 1.0.
Step 2. Column form sides will be assembled as in Case 1 (Fig.
Applying the factors to determine the ASD adjusted design
7.10(a)). Note that the panels are detailed holding back the
values based on Tables 4.3 and 4.4
plywood 3/4 in. on one side only. This permits all panels to be
F;= FbCDC,WCICLCFCI'uC/C,
identical, and they fit together as shown in the drawing.
=1050 psi X 1.15 X 0.85 X 1.1 X 1.1S=1300 psi
Support requirements of the plywood must be met for the
maximum lateral pressure of 1740 lb/ft2• Use the same design F; = FvCDCMC,C1 = 175 psix1.1Sx0.97=19S psi
method as for wall form sheathing, or check a design table.
Assume that plywood panels are used vertically on the column,
E' = ECMC,C1 = 1,400,000 psix0.9=1,260,000 psi
making face grain perpendicular to spans (weak way) in the
column form. From Table 9.3, the allowable plywood span in the
weak direction is 5 in. with rolling shear as the control. Because
the 2x4s are used flat, as shown in Fig. A, the allowable span
shown in Table 9.3 can be increased by 2 in. due to the larger
bearing length (as indicated by the footnote). A visual check
indicates that bending and deflection would not control with
the increased plywood span. A 6 in. center-to-center spacing
Fig. A: Column farm face panel layout
CHECK DEFLECTION:
t-
- 3. 16
r;;5 _- 3.16
v� 1300 psix1.31 in.) .
15 .6 ln.
69.s lbfin. f=l.HS• {f'i(in.)=1.735• 1,260,000 psix0.98 in.4(in.) 20_6 in.
v---;- 61.9 lb/in.
CHECK DEFLECTION substituting in Eq. (7.4c) for maximum 6 of
1/16in. CHECK SHEAR:
�
job-built yokes, steel strapping, and other methods of clamping, a
( = l.7JS f'/ {in.) 1,260,000 psi X 0.98 in.•in. general design layout is suggested by the cases shown earlier.
= l.l3S• ll.3 in. Step 4. Select yoke or clamp spacing:Compare spacing require
w 53.91b/in.
ments of the clamp manufacturer with the tentative spacing
CHECKSHEAR: calculated based on support requirements for the side panels of
f= �bd +1.67d+0.83l't. =
F the column form, as summarized in the table on the previous page.
Step S. Final clamp location. Assuming that construction
0 9w
requirements place the top clamp 6 in. below the top of the
195 ps x .2
; 5 · 25 ;n'- column, convenient spacing of the clamps should be selected
-
::';;'-':-:-':-'c- ,_ + 1.67x1.5 in.=20.8 in.
0.9 x 53.9 lb/in. to equal or less than the maximum spans of the column side.
As the table shows, there is a reasonable agreement between
Bending again governs, and Clamp 4 will be tentatively spaced calculated and manufacturer's recommended span lengths.
17 in. above Clamp 3 or 37 in.+ 17 in.= 54 in. above the base. Figure B shows the final clamp locations adding to a total
Recompute lateral pressure at Clamp 4 as a basis for deter height of 144 in., arrived at after comparing the calculated
mining the spacing to Clamp 5. spacing for stud span to the clamp manufacturer's spacing
based on clamp strength. It is desirable to have some repetitive
CCP=1740 lb/ft2-145 X 54 in. /12 inJft. =1088 lb/ft2
spacings instead of having all different spacings. The final clamp
w= 0.5 ftx 10881b/ft2/12 inlft =45.3 lb/in. locations are within both the calculated maximum spacings and
the yoke manufacturer's recommendations.
To find the allowable span length between Clamp 4 and Clamp 5:
Remember that the calculations shown for wood span length
CHECK BENDING, as before were conservatively simplified by assuming pressure at a lower
clamp as the basis for computing the spacing to the next clamp.
l'=3.16 r;;5
v � =3.16
l300psix1.3 l in.)
19.4 in. Note that if desired, it is possible to go through another iteration
45.3 lb/in. using a slightly reduced value for CCI" where C0is the liquid pres
sure halfway between clamps. This additional step may provide
CHECK OEFLEUION
slightly higher allowable spans, but will not be performed in this
example because there would be little benefit considering the
l'=1.735 . {E'i(ii1.)= .735.1,260,000 psix 0.98 in.•(in.) 223 in.
v----;- l 45.3 lb/in. spacings for clamp strength. A computer-based analysis with a
continuous beam over multiple supports at the various spans
CHECK5HEAR selected and with a ramp loading could also be used to provide an
f= ��:� +1.67d+0.83fb=
exact analysis of moments, shears, and deflections for verification.
,---- 6in
#8
195 psix 5.25 in.l
+ 1.67 x 1.Sin. =27.6in. 24 in
0.9 x 45.3 lb/in.
#7
Bending again governs, andClamp 5 will be tentatively spaced 19 in. 24 in.
aboveCiamp 4 or 54 in.+ 19 in.=73 in. from the base of the column.
Determine lateral pressure at Clamp 5 and continue calcula #8
tions in this way until the last clamp elevation is equal to or 20 in.
greater than the column height. As loads decrease, shear clearly #5
does not govern span length, so only bending and deflection 18 in.
checks must be performed. The remaining 18 in. space between
114
Clamps 7 and 8 is less than the allowable span length of 31 in.
16in.
Thus, further adjustment of clamp location can be made within
#3
the calculated limits. A spreadsheet with the various formulas 16in.
could be used to speed the entire calculation process. #2
Step 3. Strength of yokes or clamps should be investigated. In 14 in.
#1
this case, a manufactured device is used, and the manufacturer's '-- 6in.
suggested clamp spacing will be taken as evidence of clamp
Fig. 8: Layout of column clamps
Tb = Thsb = /
4500 lb ft x .j
8 inJ12 in ft = 3000 lb
maximum working loads from the framing. Compared to heavy formwork,light formwork
uses lighter form tying accessories and more of them.
ACI 347R recommends factors of safety for use by manufacturers in determining the
working capacity of formwork accessories. As shown in Table 7.5, ACI 347R recommends
a safety factor of at least 2.0 for all ties, anchors, and hangers. For anchorage of formwork
supporting weight of forms, concrete, construction live loads, and impact, a safety factor
of 3.0 is advised. Typically,these accessories are designed for tension,but the designer
must be alert to the possibility of bending or other loading conditions that may add to the
member's stress. Safety factors are based on ultimate strength with the additional provi
sion that the yield point must not be exceeded under the working load.
7.10.1 Ties
When preliminary spacing of the ties has been determined based on requirements of the
framing members,this spacing will have to be checked against the load capacity of the
ties. Use the manufacturer's load rating,adjusted if necessary, to give the desired safety
factor. To get the total load on each tie,determine the tributary area of form as shown
in Fig. 7.11, multiply by the average unit pressure of concrete on the tributary area, and
adjust for the increased reaction due to span continuity {for example, multiply by 1.1 for a
three-span case).
If the equivalent uniform load on wales has already been computed, then merely
multiply this load times the distance between ties to get total load per tie and adjust for
continuity. For example
If the total computed load exceeds the capacity of the selected tie, at least one of the
following methods, whichever may be more economical for a given job, should be
employed to reduce load per tie:
Reduce tie spacing;
Increase tie rod size;
NOTE: Ultimate strengtlls guarant� by reputable manufacturers maybe used in l�u of tests for ultimate str!'flgth. Working
toadsmusrnotexcH'Ciy; e ldpolntof materlai.Safetyfactorsglvenherein,andmanvfacturefs'load ratingsin gener.ll,arebased
onthe assumption tl\.att�sand ancllorsare loade-dintension.lf thetieor ancllor isusedin sucllawaytfl.atbendingorotller
suessesare introduced,tlle deslgnershould considerthe effect ofthe combinedstresses.
CHAPTER 7
Reduce wale spacing;
Decrease the rate of concrete placement; or
Increase the minimum concrete temperature.
If plain rods, band iron, or unrated ties are to be used, the necessary size is computed as
(7.21)
where Ali< is the net cross-sectional area of the tie; Cc, is the average lateral pressure on the
form area being considered;A,.,.m is the contributing form area including effects of conti
nuity; and F., is the allowable working stress for tie material. (21,500 psi may be used for
structural steel; for other materials, use manufacturer's rating; assure 2.0 safety factor.)
7. 10.3 Hangers
Hangers that support the weight of forms and wet concrete plus construction load from
the already in-place steel or concrete structural frame (Fig. 7.12) may be checked in much
the same way that ties are checked. Preliminary spacing will have been calculated based
on formwork requirements for support.
Determine the area of formwork to be supported by each hanger (usually the distance
of beams center to center times the spacing of hangers along the beam) and multiply by
the total unit design load for the formwork. The weight of concrete forming any irregular
haunches, overhangs, or encasement for fire protection should be included in the analysis.
For non-encased structures, the load on the hanger may be determined by permissible
spacing of formworkjoists, rather than having hangers carry their maximum load.
If the load exceeds the capacity of the hanger tentatively chosen, then a heavier one
must be found, or spacing must be adjusted accordingly. If a higher safety factor than that
indicated by the hanger manufacturer is desired, adjust the load rating. ACI 347R recom
mends a safety factor of 2 for all hangers. Caution in understanding load ratings is impor
tant; for example, some manufacturers rate hanger load capacity per leg, whereas others
rate based on total capacity of both legs.
Care is required in design to equalize the loading
on the two legs of the hanger to avoid twisting of the Totaldesignload(Dead+Live)= 175psl
steel supporting beams due to unbalanced loading. For
example, in Example 7.7(a), if the slab span from A to B
were substantially longer than the span from B to C, the
load on the left side of the hanger at B would be heavier
than the load on the right, and there would be a tendency Beamsacldl�
for the beam to twist. When one-sided hangers are used,
they should be alternated from side to side if possible I _ ';·:::..____.! ___ •. � I
along the length of the supporting beam to counteract
the rotational effect. Forms for fireproofing steel beams Fig. 7. 12: Beam saddles support forms from the steel frame; load per hanger
often have to be braced to prevent shifting sideways until here is 1751blf� x 6ft x 2ft"' 21001b; typical safe working load for such hard
concrete is placed on both sides of the web. ware is 1500lb or more per side
CHAPTERS
exceed 75; however, the higher limit is intended for components such as wood trusses
during their erection before final lateral bracing is installed.Thus, the limit ijd of SO is
appropriate for formwork compression members.
When shores are braced laterally in one or more directions (Fig. 8.4), or at different t,andt,•
Dlstancesbe-enpoin t s ol
points along their length, the slenderness ratio in each plane of lateral support must be lataralaupportolcolumnln
plan" 1 �nd 2
determined and the greater of the two ratios i/d1 or R.jd1 is used to compute allowable
loads. Figure 8.5 illustrates determination of the ijd ratio for a 3x4 shore with different
bracing plans.To be effective, such lateral bracing must be anchored to or bear against
some positive support such as permanent construction, securely placed stakes, or diag
onal bracing. Lateral braces used only for the purpose of reducing unsupported buckling
length of formwork shores and braces are commonly referred to as horizontal/acing. The
AWC NOS does not have a provision for the required strength of lateral bracing to resist
buckling of wood columns. The AISC Steel Construction Manual has a requirement for
such braces to resist 1% of steel column axial compressive strength. Some designers have
used 2% as a "rule of thumb."
Round wood poles are sometimes used for shores in falsework.ln such cases, the R.jd
Fig. 8.4: Distances between lateral supports
ratio is determined using the d dimension of a square section having the same area as the and associated cross-section dimensions
round section.
J
to project, the cumulative duration of
maximum loading may be uncertain. Thus,
many form designers assume the cumula-
(8.1)
where c O.B for sawn lumber; and F; = F, x all applicable adjustment factors, except C,..
=
= 0.822E.:W,
F
" (1,/d)' (8.2)
It is often convenient to calculate the value of (FjF,1 first, and then substitute the
resulting value into Eq. (8.1 ) .
]
F,/F,·=747 psi/2680 psi=0.279
With actual dimensions of 3-1/2 in. by 3-1/2 in., the cross
section area is 12.25 in.l 1+(F./F;) _ 1+(�,/F;) ' -�,/�·
C, =
d
tj =(9 ft x 12 inJft) / (3-1/2 in.)= 30.9 2c 2c c
which is well within the limit of 50. Note that with the assumed
pin-ended column, e. is the same as the actual unsupported
length e. Find the column stability factor CP by solving Eq. (8.2)
and then substituting in Eq. (8.1) with c= 0.8 for sawn lumber.
F; = F,·cp = 2680 psi x 0.261 = 699 psi
0.822f� 0.822 x 580,000 psi
F 500 psi
" (l,jd)' (30.9 )' P u = F; A= 699 psi x 12.25 in1=8560 lb
FjF,·=500 psi/1552 psi=0.322 The ASD and LRFD results can be compared as follows.
]
Imagine a case where an elevated slab is to be cast. Because the
concrete could have temporary excessive depth locally during
1+(�,/F,')- 1+(�,/�') '-�,/F; placement, consider it to be CVIol, for design of the supporting
CP =
2c 2c c form members.Assume the forms weigh 5 lb/ft1, the slab
weighs 951b/ft1, and the personnel and equipment weigh 50 lb/
p 1+0.322 _
C =
1.6 1.6
]
1+0.322 1 _ 0.322
0.8
=0_297
ft1.ForASD
Other conditions being equal, theAWC NOS indicates square wood columns and round
wood columns of equal cross-sectional area will carry the same loads and have equal
stiffness. Therefore, a round wood shore can be designed by assuming a square column
for analytical purposes and then using a round shore of the same cross-sectional area. An
example of determining the load a wood shore can support is provided in Example 8.1.
CHAPTERS
shore,or it may be considerably less if a narrow member rests on the shore,as shown in
Fig. 8.6. The shaded area indicates the bearing area between the supported member and
the shore. A narrow bearing area is less desirable,as it may be less stable unless blocking is
provided. Example 8.2 illustrates a check of end bearing stresses for a shore.
Table 9.12 gives ASD shore loads based on allowable stress perpendicular to the grain
of the wood member contacting the shore and full bearing. Metal or hardwood plates or Fig. 8.6: Shore bearing areas on members
fittings attached to the top of the shores may be used to increase the bearing length and perpendicular to grain
thus increase the load capacity above these bearing limits.
P, SP./0 (8.4)
For LRFD with the resistance factor $< =0.90 for compression, the strength capacity is
P,=V. (8.5)
When F� 0:: 0.44F,
[ ]
F.= 0.658f. F, (8.6)
(8.7)
where F1 is the steel yield stress, E is the steel modulus of elasticity, and
F=�
(8.8)
. (¥)'
When intermediate lateral braces, termed horizontal lacing in formwork, are provided
to reduce the compression buckling length of columns,AISC provisions require that
the braces, termed nodal braces in steel construction, must be able to resist 1% of the
required axial compression strength of the column. The requirements also include a
minimum provision for axial stiffness of the braces.An example of determining the load a
steel pipe shore can support is provided in Example 8.3.
0.791 in.
at the joints, the unsupported length e
r
cannot be accurately estimated.Assembly
of the frames in tower structures of varying
Considering Eq. (8.3) through {8.8) heights further complicates mathematical
nl(29,000,000psi) analysis. Cursory examination would indi
F• 12,390
(152)'
psi cate an unbraced length in this longitudinal
plane of 4ft. However, because of the lack
CHAPTERS
Hp
possible. The SSFI SH300-071oad test procedure, outlining duration, speed, and other loading
conditions, is an effort to help manufacturers develop uniform recommendations for allow
able loads on sectional steel shoring components. The rated load capacity, or maximum I
working load, is determined by dividing by the ANSI/ASSE A10.9 required factor of safety.
I
I
:
The best practice in designing shoring frames is to use the load capacity recommended
by the manufacturer, on the basis of load rests conducted under standardized conditions.
Manufacturer's recommendations for bracing, assembly, and erection conditions should
be carefully followed. In many cases, engineering assistance is offered by the suppliers
't1, ,'r1'
or producers of these proprietary shoring devices. Example 8.4 illustrates how to use the I
I
manufacturer's recommendations to determine if a shoring frame is adequate.
fl =!i!i.!.!i!.!.pMfltffl�!}!..f!.l.liMii*.,1mitG•H.
l#fflf@
For a typical shoring frame available for concrete shoring, the The load on a single leg is less than the manufacturer's
manufacturer recommends a maximum working load of 10,000 maximum recommended working load of 5000 lb. So, the
lb per frame, or 5000 lb on each leg under good job conditions shoring frames are adequate in these two areas.
(firm support under legs and height of assembly less than 14
ft). The frames are ordinarily assembled in "towers" consisting of
two end frames plus diagonal bracing between them.
Note that crossed lines in the plan drawing shown here do
not represent bracing location but are a typical schematic
convention for indicating a shoring tower in shoring layout
drawings. A single diagonal line on the plan drawings is another
typical schematic convention for indicating shoring tower loca
tions. The actual bracing is in planes at right angles to plane of
the frame. This particular shoring frame is 5 ft wide, and adjust
able bracing is available to allow frame spacing of 3 to 7 ft in 6
in. increments. The 10 in. thick slab and beams weigh 150 lb/ft3
and the formwork to be supported weighs 8 lb/ft1•
Assume that each leg supports the formwork area extending
halfway to the adjacent leg on each side.
12 x 27 beam= 5 ft x 3371b/ft= 1685lb Tributary areas for calculation of shoring tower leg
80ib
loads
Formwork soffit load= 2 ft x 5 ft x 8 lb/ft1 =
Foliated or lominoted rock including soond of the lateral bracing under lateral load
40,000 to 80,000
limestone, Khisl, slate criteria established by ACI 347R using
ASCEJSEI 7-10, HMinimum Design loads
Sedimentary rock including shale ond
20,000to 50,000 for Buildings and Other Structures,H and
$0ndstone
ASCEJSEI 37-14, "Design loads on Struc
Hardpon 16,000to 20,000 tures During Construction." Some possible
Soft or broken rock 10,000to 20,000 bracing layouts and design suggestions
are shown in the examples that follow and
Grovel soils 8000 Ia 20,000"
in Chapter 10. Any laterally braced system
Gravelly sends 6000 to 16,000' should be anchored adequately to insure
stability of the total system.
Sands 4000 to 13,000'
CHAPTER8
and designed to act in either tension or compression, recognizing that the wind can act in
either direction. The second are diagonal guy cables placed on both sides of the form and
designed to act only in tension because cables cannot resist compression. Several situa
tions are shown in Fig. 8.10, whereH is the lateral load perfoot of wall form length. The
braces are spaced at intervals, z, along the length of the wall form.
Figure 8.1 O(a) represents a wall form with a uniform wind pressure, q, so thatH = qh. The
brace length is
(8.9)
The brace force, P, can be determined by statics assuming a hinge at the form base and
summing moments about the base.
1
(8.10)
Figure 8.10(b) represents a wall form where the ACI347R minimum applied at the top of
the form governs.
(8.11)
Figure 8.10{c) represents the situation when determining the wind loading using ASCE/
SEI 7 and ASCE/SEI 37, where the loadH is positioned slightly above the midheight to
(b)
better represent the somewhat nonuniform wind pressure.
(8.12)
Figure 8.10 {d) is similar to Figure 8.10 (a), (b), or (c) depending on the location of the
lateral loadH, except that the guy cable is in tension only and only one cable is active
depending on the direction of the wind.
For all of these cases, the vertical reaction R1 = P(y/L) and the horizontal reaction R, = P(x!L).
For Figure 8.10(a), (b), and (c), the brace may be in either tension or compression and R,
R,
may act either upward or downward on the anchor. For Figure 8.1 O(d), the brace is always
in tension and R1 will always act upward on the anchor. Brace slope is sometimes selected R,
(c)
to meet brace length or space limitations. low slope braces must be longer and have more
Jk
problems with compression buckling and bending due to self-weight. High slope braces
must resist more axial force and therefore may be more difficult to anchor. The determina
tion of bracing loads and reactions for strut or guy wire bracing is shown in Example 8.5.
u
8.6.2 Design of Braces
· ·�
Braces may be of wood, steel, or aluminum. Steel and aluminum manufactured braces are
selected based on the manufacturers' working strength rating for the length of the brace.
Wood braces are designed to meet AWC NOS requirements. Due to the possibility of buck
ling, the compression strength usually governs design. The design process is illustrated in
Ry .,.
Example 8.6 and parallels that of wood shores. Arriving at a starting size often requires a {d)
trial-and-error process and intermediate lateral support of the brace to reduce the buck·
ling length is sometimes needed. Consideration of combined axial load and bending is Fig. 8.10: Bracing afwall forms
needed for eccentric end connections and bending due to heavy brace self weight.
1) Strut Bracjng the ground or a slab 12ft from the base of the form, a= 12ft , b
If wooden strut bracing is provided, strong enough to take =12ft, and L =17 ft. The guy wire tension force, from Eq. (8.12),
either a tension or compression load, then single-side bracing and reactions are
may be used. Nailed connections at either end must be strong P=a ft(2oo lb/ft)(o.s5)(14 ft)(17 ft)t(12ft)'= 1454 lb
enough to transmit the tension load, and wales or other form
R, =P(y/L)=14541b(12 ft/17 ft)=1026 lb
members must be strong enough to transmit accumulated
horizontal forces to the strut bracing.
R, = P(x/L) =1454 lb (12ft/17ft)=1026 lb
If the wood bracing placed at 8 ft along the length of the form
is attached 2ft below the top of the wall and anchored to the With working strength of guy material known, guys can be
ground or a slab 9 ft from the base of the form, y= 12ft , x=9ft, spaced to use their maximum safe load capacity. Stakes must be
and L = 15 ft. The brace force, from Eq. (8.12), and reactions are securely placed to provide the reaction strength, and top wales
must be able to carry horizontal forces accumulated to each
P=B ft(2oo lb/ft)(o.55)(14 ft)(15 ft)t(9 ftx12 ft)=1110 lb
point where guys are attached.
R, =P(y/L)=1710 lb(12 ft/15 ft)=1370 lb This same design approach would apply to 1 in. thick lumber
bracing be<ause it is practical only for tension loads, except in
R, = P(x/L)=1710 lb(9 ft/15 ft)=10251b short lengths of approximately 4 ft or less.
of the erection of the elevated slab formwork, the columns may contribute to the lateral
capacity if there is an adequately developed formwork diaphragm at the sheathing level
combined with appropriate X-bracing for shore stability.
Minimum loads used in designing components of this bracing are given in Table 5.9.
The loads from analysis may be greater than the minimum. Design must provide for the
force acting at the edge of the slab in either direction, and the intensity of the lateral force
depends on the slab width in the direction of the force. In applying Table 5.9, consider as
theMslabM only that part that will be placed at one time. Refer to Example 8.7.
For shoring systems comprised of steel or aluminum components, the recommenda
tions of manufacturers as to strength of their bracing systems should be followed in
designing for the specified lateral loads.
CHAPTERS
mtmrtt:!M:M•1M1•1•
Design a wood brace in No. 2 Southern Pine to resist a wind
where the ASD load combinations results in an axial load
P= 1200 lb. The brace length is 12 ft, and K= 1.0. For the case _ 0.822E;.., _ 0.822 x464,000 psi _16
F.- 5 psi
of wind only, a load duration factor C0 =1.6 applies. Other '
(1,/d) ( 48 )'
load cases may need to be investigated if work platforms are
attached to the form, and those cases would involve a longer F,/F;= 165 psi/2048 psi =0.080
load duration. A check of
= 96 >
ijd for the full 12 ft with a 2 in.
nominal thickness strut would produce ijd= 144 inJl.S in.
50 limit. Thus, if a 2x6 brace is used, it will need to be C, =
l+(F.(F;) _
2c
1+(F.(F,') '
2c
] _F
.(F,'
c
braced laterally with horizontal lacing to resist buckling at mid
length for ijd= 72 inll.S in.= 48 for weak direction and ijd=
144 inJS.S in.= 26 for strong direction. Both ratios are less than
the 50 limit. Try a 2x6 S4S brace with A= 8.25 in.2, b= 1.$ in.,
d= 5.5 in., and lacing to resist buckling at mid-length in the
weak direction. Applying this factor to the previously adjustedF,', we get an
Assume not incised, normal temperature conditions, and wet allowable F; of
use because, on this site, the braces will be stored in exposed :
F =F,' C,= 2048 psi X 0.079= 162 psi
conditions even when not in use. From Table 4.3, the reference
The area of the brace times this allowable stress gives the
value ofF<= 1600 psi and E,.,= 580,000 psi. Referring to Table
axial load capacity P of the brace
4.4 and gathering applicable adjustments, C0= 1.6, C,.,= 0.8, and
C,= 1.0 (refer to Table 4.3 footnote). Other possible adjustment ;
P=F A= 162 psi x8.25 in.2= 1336 lb
factors are either 1.0 or not applicable such as Cr, which only
applies to trusses. Determining adjusted values and applying in The lateral bracing could be provided as illustrated in the figure.
Eq. (8.2) and (8.1)
If the formwork engineer used 2% of the required brace axial
E',...,= Emln c,C1C1Cr= 580,000 psi (0.8)= 464,000 psi force as a ·rule of thumb" to determine the needed lacing resis
tance, the lacing connection at each diagonal brace would need
to resist 0.02 x1200 lb or 241b. For
the layout shown in the figure, with
six diagonal braces the X-bracing for
2x6 brace (1yp.) 2x4 lacing
the lacing would need to resist 6 x24
lb or 144 lb applied along the line of
the lacing.
Based on preliminary design and
planned connections, evaluate
possible need to examine combined
axial load and brace bending.
D�
right), 8 in. thick, is shored at 4 ft
estimate required camber or adjustment
intervals in both directions. According
more closely in terms of individual project
to Table 5.9, H""" in lb/ft is 207lb/ft
conditions.
Deflection of individual form members
along the 60 ft edge (because width of
-
slab in direction of force is 90 ft) and
�
under load has already been explained
138 lb/ft along the 90 ft edge (width of
in Chapter 7. With good form design, this
slab in direction of force is 60ft).
deflection is minimized. Where beam
If the minimums govern and bracing -
bottoms, stringers, and other form compo
is placed on alternate lines of shores
J!J!J!J!J!J!J!J!J!J!J
nents are supported at a number of points 1381b. per ft., acting in either
(8 ft apart), design load along the 90
along their length, camber for this small direction along slab edge
ft side would be 8 ft x1381b/ft, or
form deflection is generally not required. If
1104 lb per line of bracing. By spacing Example minimum slab formwork lateral
relatively long-span form members-such
bracing at every line along the 60 ft loads
as the so-called horizontal shoring-are
side, design load per line would be
used, camber to correct for form deflection
4 ft x207 lb/ft, or 828 lb.
is necessary. These manufactured members
P=
No.
;-;;ac es
l b=
/ ���c�s 12.2 ft / 8 ft= 3861b
formula
CHAPTERS
8.7. 2 Deflection of the Finished Structure
When supporting formwork is removed and the concrete structure begins to carry its own
weight, some deflection takes place. In the past, for structures of customary dimensions,
excessive deflections were rarely a problem. However, use of higher-strength materials and
more refined design methods allowing less conservative design results in members with
larger span-depth ratios. Flat-plate floor systems of long span and minimum depth are being
used more often for construction economy. Thus. deflection of finished structures is a more
common problem-one, however, that can be overcome by proper cambering.
The composite character of reinforced concrete, complicated by partial cracking of
the tensile zone and by creep, makes accurate deflection calculations difficult. Not only
is it difficult to predict deflection of reinforced concrete structures but there is also the
problem of deciding what net amount of deflection can be permitted. This is largely a
matter of judgment, and it is clearly the responsibility of the engineer/architect to specify the
amount and shape of camber desired to compensate for deflection of the finished structure.
The engineer/architect may also require additional camber for exposed long-span hori
zontal members to overcome the effect ofNoptical sagN
. Advances in methods to calculate
deflection of concrete floor slabs have been developed (refer to Reference 6. 4).
Where camber requirements may become cumulative, such as in cases where beams
frame into other beams or girders at right angles, and at midspan of the latter, the engi
neer/architect should specify exactly the manner in which this condition is to be handled.
Cast-in-place structures that are to be post-tensioned present special problems with
respect to camber, because tensioning of the tendons will produce an upward deflection
in the member being prestressed. The engineer/architect should determine and consider
those movements in specifying any camber to be built into the forms to compensate for
deflection of the concrete structural system.
8.8.1 Deodmen
Deadmen may either consist of a precast concrete block sitting on the ground surface and
frequently reused or a buried concrete mass usually cast in place and frequently aban
doned when no longer needed. A precast deadman is illustrated in Fig. 81 . 3. Although
they may have any dimension, a1ydl block (3ft x 3ft x 3ft) weighing approximately 4000
lb is popular. The case of brace tension usually governs for evaluation of the deadman.
Static equilibrium is straight forward and a factor of safety of1.5 on overturning, uplift,
and sliding is often applied.
Fig. 8.13: Forces of equilibrium on o concrete
(81
. 4) deadman
(8.16)
where� is the coefficient of friction for the surface upon which the deadman sits.
The excavation for a buried deadman is often done with an auger or an excavator hoe and
thus the shapes and sizes vary substantially. Analysis of the strength depends on the weight
of the concrete cast, dimensions of the deadman, and properties of the soil. Vertical strength
for uplift is provided by the concrete mass supplemented by soil friction around the sides.
lateral resistance to sliding and overturning are primarily provided by passive earth resis
tance. Appropriate factors of safety for the uncertainties involved should be applied.
8.8.4 Anchors
Form anchors secure formwork to rock or previously placed concrete of adequate strength.
They must have not only sufficient tensile strength to carry the load imposed upon them but
they must also have enough embedment in the concrete or rock to develop that holding
strength. Sufficient length of embedment is particularly important because anchors are
often placed in the low-strength concrete used for massive structures, or in concrete that will
have only part of its strength developed when the anchor is acting.
Calculation of the loads to be supported by these anchors depends on the details of
the form under consideration; they are usually used for cantilever forms, and for sloping
surfaces more than one row of anchorages may be necessary. MTiedM cantilever forms are
supported by a row of anchorages at the face of the concrete, plus additional ties from the
top of the form inclined down to anchors embedded in the top of the previous lift. This is
Fig. 8.14: Increase in brace load when brace is discussed more fully in Chapter 16 on mass concrete formwork. When the anchorage unit
inclined supports a cantilever form at the face of a previous lift, the bolt portion of the unit carries
the weight of the forms as well as a tension or pullout load.
Although the load on the tie or anchor may be calculated in a horizontal direction, the
embedded anchor is often inclined. In such a case, it is necessary to increase the load on
the anchor as shown in Fig. 8.14. For example, if the anchor rod is inclined 55 degrees from
the horizontal, 1741b of load for every 100 lb of calculated horizontal pull must be used in
design of the anchor rod.
REFERENCES
8.1. Fa/sework Manual, State of California Department ofTransportation, Division of Engi
neering Services, Structure Construction, Sacramento, CA, 1988, revised 2012.
8.2. Grant, M., MScaffold Falsework Design,M Cement and Concrete Association, Wexham
Springs, Slough, England, 1978.
8.3. Bowles, J. E., Foundation Analysis and Design, fifth edition, McGraw-Hill Book Co.,
New York, 1996, 1175 pp.
8.4. Borden Jr., C. W., MFailures of Slender SteelTubular Frames,M Proceedings, National
Safety Congress, 1960, pp. 6-12.
9: DESIGN TABLES
To facilitate the design process, tables following the principles presented in Chapters 7
and 8 are provided in this chapter. The tables include a summary of frequently used design
equations for maximum span in simplified form. Based on the equations, safe spans for
many wood and plywood formwork components have been calculated and arranged
in tables for use by the form designer. Calculations cover single-span beams, two-span
beams, and beams continuous over three or more spans carrying a uniformly distributed
load. The span tables are applicable for uniformly loaded form members where the design
simplification of using equivalent uniform loadings in place of point loads is regarded as
sufficiently accurate. The tables may also be used to develop a preliminary design for cases
where a rigorous structural analysis is required before finalizing the formwork design.
All span tables in this chapter are based on allowable stress design (A$0) with adjusted
design values.
!l
�
= __!____
400
1.=0.577 � 1.=0.774 � �
1.=0.713
6
�
._!___
360
1.=0.598 � f.=0.801 � �
l=0.739
6
-
._!___
240
1.=0.684 � 1.=0.917 � 08 �
1. = . 46
6_,•1/16;n. 1.=1.48
� w
( =1.8 4
� w
�
l=1.74
Horizontal shear l=
1.33F;bd
w
+2d+lo l=
l.OlF.'bd
w
+1.6d+0.8 l0 t= :,. +1.67d+0.83l0
u 'bd
l=3.84,
!_'l (in.} =3.84, l,SOO,OOO lb/in.1x20.8in.4{in.) ��
J.B4�l3o,ooo;n . • n.g;n.
(
W ftjin. ) 240 lb/ft ( ftjin. )
CHAPTER9
Table 9.!.lb: Expressions far calculating safe support spacing for uniformly loaded wood and plywood,
where W is load expressed in lb/ft
. . . . . . . . . . . .
dm•• =
f
400
f=1.32 � f=l.77 � f=l.63 �
6
�
=..!....
360
f=1.37 � f=1.83 � f=l.69 �
6
-·
=..!....
240
f=l.56 � f=2.10 � f=l.93 �
6.""'" • 1/16 in. f=2.75 � W(ft/in.)
f=3.43 � W(ft/in.)
f- 3.233'
-
�
W(ft/in.)
therein may be used for any lumber whose adjusted design values equal or exceed the
indicated values.
The design tables are in four groups:
Plywood sheathing;
Joists, studs, stringers, or any other beam components of the formwork where single
framing members are used;
Wales or other formwork components where double members are used (two pieces
side by side that share loads equally); and
Shore loading and bearing checks.
Nominal lumber sizes are shown in the tables but all calculations are based on lumber
finished on all four surfaces (545). Actual thicknesses are shown for plywood. Each table
Logd durtJtton Bendtng fb', pst HortzonttJI shegr f.', pst Modulus of eloshctty f', p$1 U$e for No. 2 lumber of tndtcoted spectes
DESIGN TABLES
, _0 1 +
shows whether the safe span is controlled by deflection, bending, or shear. Design exam
ples demonstrating the use of the tables are presented following a brief description of
-·- -·-·- allowable deflection, ASD adjusted design values, and loading conditions for each group
U
of tables. Tables 9.3 through 9.13 are provided at the end of this chapter.
4x2
9.2 Sheathing Design: Tables 9.3 to 9.5
2 X 4 Tables 9.3, 9.4, and 9.5 are applicable to plywood sheathing for columns, walls, and
elevated slabs. They cover plywood supported as a single-span beam, two-span beam,
Fig. 9.1: Strong and weak bending axis or a beam continuous over three or more spans. Theoretical deflection of spans based
designations on these tables is limited to the lesser of 1/16 in. and €/240, where e is the spacing of
supports. For spans less than 15 in., t/240 governs and deflection will be less than 1/16 in.
To obtain allowable spans with deflection limited to €/400, multiply tabulated spans by
0.84. To obtain allowable spans with deflection limited to €/360, multiply tabulated spans
by 0.87. This approach will be somewhat conservative when bending or shear previ
ously governed but safely covers situations where the governing allowable changes to
deflection.
Tables 9.3, 9.4, and 9.5 were calculated using the section properties for B-B Plyform Class
I concrete form plywood, as given in Table 4.13. However, plywood acting as a beam is
stronger when its face grain is parallel to the span than when its face grain is perpendic
ular to the span. Therefore, two divisions are necessary-one for spans with the face grain
parallel and the other for face grain perpendicular to direction of plywood span.
Calculated spans are based on adjusted design values given in Table 4.14 for B-B Plyform
ClassI. The allowable stresses are based on wet use, modified by the APA-recommended
experience factor of 1.3. In Tables 9.3 to 9.5, stress values are shown for both short-term
loading duration (C0 = 1.25) and normal load duration (C0 = 1.0). Deflection calculations in
these tables include the bending component, but do not include the shear component.
Consult the manufacturers' recommendations if shear deflection values are needed.
Plywood span limits controlled by rolling shear have been calculated assuming bearing
length t� = 1.5 in. When t� is known to be larger, the difference can be added to the tabu
lated span. For example, if e� "" 3.5 in., 2 in. can be added to the spans controlled by rolling
shear to obtain the center-to-center span, provided that bending does not become the
controlling criteria.
CHAPTER9
Note that the uniform load value shown in Tables 9.6.1 to 9.8.4 is not the form pressure,
but is an equivalent uniform loading, generally computed as uniform pressure on forms
2
(lb/ft ) times the spacing (ft) between members being considered.
Tables 9.6.1 through 9.6.4 are for beams continuous over three or more spans using the
adjusted design values (allowable stresses) shown in Table 9.2.
In developing adjusted design values from reference design values for No. 21umber,
it has been assumed that moisture content is 19% or less, temperature is 100°F or lower,
and the beam stability factor is 1.0 (refer to the discussion in Chapter 7). Bending stress
adjustments were made for size and flat use where appropriate. Repetitive use benefits
have been neglected. Because of the temperature and moisture assumptions, modulus of
elasticity values (shown as adjusted values) are the same as the reference design values.
The first set of design values in Table 9.2 can be used to check spans of No. 2 Southern
Pine and Douglas Fir-Larch under long-term loads. The second set of design values is for
the same lumber under short-term load. The third set of design values can be applied
for No. 2 Spruce-Pine-Fir and No. 2 Hem-Fir, with long-term load. The fourth set applies
to short-term loading of these same species of No. 2 lumber. The design tables can be
applied to other lumber with strength characteristics approximating or exceeding those
used. Check Table 4.3 in this text for typical reference design values, or consult Tables 4A
and 4B of the AWC NDS-2012, �National Design Specification for Wood Construction; for
greater detail.
Tables 9.7 and 9.8 are similar to Table 9.6, except that span lengths are calculated for
two-span continuous and simply supported single-span beams, respectively.
Notice that beam sizes are given in the conventional fashion with b or width of beam
face to which load is applied given first and the second number indicating d or depth of
beam. Thus a 2x4 (nominal size) is used in strong axis bending and a 4x2 (nominal) is the
same member used flat in weak axis bending, as shown in Fig. 9.1.
DESIGN TABLES
Use the design tables to make a preliminary selection of 2
W =200 lb/ft x 19.2 in. / 12 inJft=320 lb/ft, thus
stringers, joists, sheathing, and shores (see Chapters 7 and 8)
w=320 lb/ft /(12 inJft)=26.71b/in.
suitable for forming a flat slab with dead plus live load of 200 lb/fe
supported on shores spaced 4ft on center in both directions. Using Table 9.6.1, for joists continuous over three or more
The clear height between floors is 11 ft. Assume that No. 2 spans, a 2 x6 loaded at 300 lb/ft has an allowable span of 59 in.
Douglas Fir-Larch is selected based on availability. The form will and at 400 lb/ft has an allowable span of 52 in. By inspection,
have substantial reuse so CD will be taken as 1.0. the 2 x6 appears to be the lightest joist that would be satisfac
From Table 4.3, the reference design values are: Fb=900 psi; F.= tory on a 48 in. span, but also consider the 4x4 that has an
1BO psi; and E=1,600,000 psi. As e xplained in Section 9.3, Tables allowable span of 54in. at 400 lb/ft. The 4x4is often selected
9.6.1, 9.7.1, and 9.B.1 are developed with adjusted stresses that for this type of form because its shape provides inherent
lateral stability.
can be applied for No. 2 Douglas Fir-Larch or Southern Pine under
In some cases, a closer appro ximation of the span would be
long-term loads and dry service, with conditions as stated. The
required for loads not given e xactly in the tables by interpola
short-term load adjustment is not taken in this e xample because
tion. For e xample, to work out this case more precisely:
the forms are intended for many reuses. Note that bending
1. The span difference for the 400 lb/ft and 300 lb/ft loads is
stresses vary with the member size and orientation.
59 in.- 52 in., or 7 in.
Stringers 2. Actual load of 320 lb/ft e xceeds 300 lb/ft by 20 lb/ft, which
With shores spaced 4ft on center both ways, the stringers will
is 20/100 or 2/10 of the difference between 300 and 400
be 4ft apart and have a span of 4ft between supports. They will lb/h.
be designed as continuous beams (three or more spans) with
3. Take 2/10 of the span difference:
an equivalent uniform load equal to the distance between the
e 7 in. x 2/10=1.4in.
stringers (ft) times the uniform load on the formwork (lb/f ): 4. Subtract this from the allowable span at 300 lb/ft:
2
W =4ft x 200 lb/ft =BOO lb/ft, thus w=BOO lb/ft / 12 inJft= 59 in.- 1.4in.= 57.6 in. allowable span (span is shorter
66.71b/in. than span for 300 lb/ft because actual load is greater.)
The 2 x6 selected weighs less than 1% of applied load. Where
Use Table 9.6.1, since the stringers will be continuous over
the joist is heavy relative to applied load, its weight should be
three or more spans and C = 1.0. Enter Table 9.6.1 at the left
D included as part of the design loading.
on the 800 lb/ft load line and note which Douglas Fir-larch
members can be used for stringers having a 48 in. span. Among Shores
the smaller members that are suitable are the 2 x 10 with an Selection of the shores is a function of the shore load and
allowable span of 51 in. and the 4x6 with a span of 56 in. The length. If 2 x6 joists and 4x6 stringers are used, their actual
2 x10 provides the necessary span with the least lumber but depths plus the plywood thickness is 5.5 in.+ 5.5 in.+ 0.75 in.,
would require adequate lateral buckling restraint because its or about 1 ft. Thus, the shore effective length is about 11 ft- 1 ft,
dlb ratio is greater than 2. The 4x6, with dlb=1. S :S 2.0, auto or 10 ft. The load should be determined considering continuity
matically meets lateral buckling requirements and may provide of the stringer and the higher reaction e xpected at an interior
better bearing contact with the shores. local supply conditions support. Because the stringer is continuous over three or more
or construction constraints may dictate the selection. Also, note supports in this case, the stringer reaction is determined to be:
that if job-site conditions are such that one or two span condi R=R�=Rc=1.1w£ =1.1 x 800 lb/ft x4ft=3520 lb
tions might also arise, these members would need to be sized
Tabulated shore capacities for No. 2 Douglas Fir-larch are
using Tables 9.7.1 and 9. 8.1.
found in the upper section of Table 9.12.1. On the line for
Sheathing a 10 ft effective length, the 4x4 shore has a listed capacity
Shore spacing places the stringers 4ft apart, and this 4ft then
of 4670 lb. Although a laced rough-sawn 4x3 shore has a
is the span of the joists. How the joists are spaced depends on
capacity of 3B70 lb and requires less shore material, the cost
requirements of the sheathing. Assume 3/4in. Plyform Class I of the lacing required to brace the shores in their weak buck
or equal-quality plywood is used with its face grain running in
ling direction and the limited regional availability of the 4x3
the direction of the span. Because sheathing will be continuous rough size make its choice less likely.
over several spans, refer to Table 9.3. The right side of the table,
with Fb'=154S psi, applies because in this case CD has been Bearing
A check of bearing stresses where joists rest on stringers and
assumed to be 1.0. From the column for 3/4in. thickness with
where stringers rest on shores is advisable. This is e xplained
n r in.
��;; ��� �:��!� :� �� ��; � ;;��: �:���::::�f;�:���
s t f
i
_
in Chapter 7. From Table 4.3, Fe.!= 625 psi for No. 2 Douglas Fir
larch. For the 4x6 stringer bearing on the 4x4shore, full contact
efficiently and permit edge support for the plywood panels, five 2
of 12.25 in. is made between the two members. Table 9.13
equal spaces of 96/S=19.2 in. can be used.
indicates an allowable bearing capacity of 7700 lb, even without
Joists increasing the design value for bearing length adjustment, cb.
This 19.2 in. becomes the required joist spacing, and joist span Thus, bearing is adequate between the stringer and the shore.
has already been fixed at 4ft. What is the required joist size?
Joist loading=joist spacing {in feet) x load on forms {neglecting
weight of joist):
CHAPTER9
Find a trial spacing of column clamps (yokes) on a 12 ft tall tively placed23 in. above No.2, or24 in.+ 23 in.- 47 in. above
column where maximum lateral pressure is expected to be 1800 the base. Determine lateral pressure at this point and repeat the
lb/ft2 at the base of the column decreasing uniformly to zero at procedure, going up the column until the total clamp spacings
the top (see Chapter5 for procedure to estimate lateral pressure equal or exceed the desired column height of 12 ft.
and Chapter8 for example layouts). Plan that vertica12x4 studs The tentative clamp spacings based on stud strength and
will be used the strong way (not flat) to provide the support stiffness should then be checked to see that column damp
for 3/4 in. Class I plywood with face grain oriented horizontal. strength is not exceeded.
Find maximum spacing of 2x4s to support the plywood and Using plywood in its weak span direction.The example thus far
maximum spacing of clamps needed to support the2x4s. is based on using vertical2x4s to support plywood sheathing
The plywood face grain is parallel to the span. Assume the with the face grain horizontal.This is the�strong way• of the
plywood will be continuous over three or more spans and plywood and of the2x4s, but it would require three pieces of
substantial reuse of the forms is planned (C0 = 1 .0). UsingTable 4 ft wide plywood for each side of the 12 ft tall form.
9.3, enter on the 1800 lb/ft2 pressure line.The plywood requires Suppose the column is sheathed with the same Class 1 3/4 in.
supports spaced 6 in. on center. Note that horizontal shear plywood, but with the face grain of plywood running vertically, and
governs at this loading level. with2x4 studs used flat and running vertically.This requires only two
As explained in the column design example of Chapter 7 , pieces of plywood, one8 ft tall and the other 4 f t tall, for each column
column clamp spacing can be determined by working up from the side. If the maximum lateral pressure is 1800 lblft2, what clear
base of the column, assuming that pressure is uniform between distance is permissible between the supporting 4xls for a multi-use
clamps or yokes and of intensity equal to that at the lower clamp. If form? If plywood is used with face grain vertical, the grain is then
the first clamp is placed 4 in. above the base, the lateral pressure is: perpendicular to the span being considered or�weak way· of use.
At the design load level for this column form, plywood spans
ccp= 1800 lb/ft2- (4 in. / 12 in./ft )(150 lb/ft3) = 1 750 lb/ft2
are short and the continuous beam condition ofTable 9.3 will
The load on each vertical2x4 at this point is equal to the pres apply. Use the table columns for face grain perpendicular to
sure times spacing of the2x4s: the span. Reading at the 1800 lb/ft2 1evel, we find a 4 in. span,
W = 1 750 lb/ft2 x 6 in. / 12 inJft =875 1b/ft center- to-center of supports. However, this is in an area where
rolling shear governs and spans are based on supports 1 -1 /2 in.
If No.2 Douglas Fir-Larch is used with three or more spans
wide. With flat2x4 studs, 2 in. could be added to center-to
and (0 = 1 .0,Table 9.6.1 applies. EnterTable 9.6.1 on the left,
center spans, to total 6 in., if rolling shear continues to control.
with a uniform load of875 lb/ft (between the800 and 900 lb/ft
As advised in the footnote toTables 9.3, 9.4, and 9.5, a calcu
lines]. By inspection, we see that the2x4 studs require support
lated recheck of spans for bending using the equations found
spacing of about20 in. Use this distance to locate the second
inTable 9.1 a or 9.1 b suggests a maximum span ofS in. For this
clamp, which is 4 in.+ 20 in., or24 in., above the base.The
short span and wide support bearing, however, using the full
lateral pressure at this level is:
moment based on center-to-center span would be very conser
CCP = 1800 lb/ft2- (24 in. / 12 in./ft){150 lb/ft3) = 1500 lb/ft2 vative since the plywood clear span between2x4 edges is only
The vertica12x4 at the level of Clamp No.2 has a load of: 2.5 in.Thus, the 6 in. center-to-center spacing of the2x4s is still
reasonable. Column clamp spacing would be determined by
W = 1500 lb/ft2 x 6 in. I 12 in./ft = 750 lb/ft following the method described previously usingTable 9.6.1
EnteringTable 9.6.1 with this load, read a value of23 in. with a 4x2, and would also result in tighter on-center spacing
(halfway between 7 00 and800 lb/ft). Clamp No. 3 can be tenta- because the vertical2x4s are used flat.
load based on bearing stress when the full shore area directly contacts the wood member
it supports.
DESIGN TABLES
if!ttt®@ll:mttl:f,jjj,j,,
Suppose 2 in. (nominal) boards of No. 2 Spruce-Pine-Fir or equal are A 6x21oaded at 100 lb/ft can span 53 in.; with a load of 200 lb/
to be laid longitudinally for a beam bottom that is expected to have ft. the span is 42 in� a difference of 11 in. Because we have a load
a single use. What spacing of shores is required if the beam bottom is of 12Sib/ft, interpolation will decrease the 53 in. span by 25/100
22 in. wide and carries a total load of 500 tb per foot of beam? of the 11 in. difference between span values, so that a resulting
The load per foot of beam can be converted to a load per approximate span is
linear foot of boards laid flat to form the beam bottom. If 6x2
53 in.- 25/100 x 11 in.=50.25 in.
boards are selected, four will be required to make the desired
width, and the load on each board will be The beam bottom will be wet in service and the table indi
cates deflection controlled. For an exact calculation, f would
W= 500 lb/ft /4 or 1251b/ft require adjustment for moisture of CM = 0.9, as indicated in
Assuming the beam bottom will be continuous over several Table 4.6. Noting in Table 9.1a that the span for deflection is
spans, use Table 9.6.4, with stresses appropriate for the Spruce· either a 3rd or 4th root off' so that the maximum change is
Pine-Fir subject to short-term loading ((0=1.25). This solution if09=0.965times the 50.25 in. span, or 48.5 in. This maximum
will be approximate because Table 9.6.4 has been developed for allowable span for the beam bottom limits shore spacing, but
lumber under dry conditions of service. practical considerations might suggest some smaller module as
a convenient spacing. A spacing of 48 in. would be practical.
utrtttfifJIIWijll§.!i1t?
Use the tables to determine spacing of wall form members, Wales
assuming C = 1.0 for substantial reuse of the forms and No. 2 grade Double wales are often used with the tie placed between each
D
Douglas Fir-Larch or equal lumber, with sheathing of 1 in. Plyform member of the pair and the tie washer plate bearing on both. If
Class I plywood. Design a 10 ft tall wall form for a maximum lateral double wales are SJ?aCed 3 ft apart, the equivalent uniform load
2 2
pressure of 6001b!tt , assuming no reduction of pressure near the per foot is 600 lbtft x 36 in./12 inJft, or 1800 lb/ft. Assuming
top of the form. three-span continuity of wales, Table 9.9.1 would be used to
determine spacing of wale supports.
Sheathing
Entering the table from the le ft on the 1800 lb/ft load line, a
Assuming that the plywood is used with face grain vertical, the
convenient span and double member combination may be chosen
face grain will be perpendicular to the plywood span between
from the le ft side of the table where adjusted bending stresses are
the studs, and the plywood will be continuous across several
applicable for long-term loading of Douglas Fir-Larch or Southern
spans. The Table 9.3 columns for C = 1.0 apply because the
D Pine. For example, if double 2x6 wales are used, the spacing
lower stress levels are recommended when forms are designed
between ties that support the wales can be a maximum of 31 in. or
for substantial reuse, and the column for 1 in. thickness under
30 in. for convenience. A check of the load capacity of available ties
face grain perpendicular to the span matches to conditions.
2 might help in confirming the wale selection. If the double 2x6 were
Entering the table at the 600 lb/ft 1evel. we find a span of 14 in.
used with supporting ties spaced at 30 in., the tie load, considering
It is decided to set the studs 12 in. on center so that they can be
continuity at an interior reaction location, would be
uniformly spaced and also support plywood at the panel edges.
R=R0=R.= l.lwf=
Stvds 2
2 1.1 x 600 lb/ft
x (30 in. /12 inJft) x (36 in. /12 inJft) = 4950 lb
With the vertical studs 12 in. apart, the load per ft is 600 lb/ft x
12 in. I 12 inJft, or 600 lb/ft. Assuming that studs are continuous A tie with a safe working load of 5000 lb should be selected.
over three or more spans, refer to Table 9.6.1 for choice of span If double 2x6 wales were used with a tie spacing of 24 in. (less
and member. Entering table at left on the 600 lb/ft load line, the than the maximum allowed by Table 9.9.1), then the tie load
3x4 stud has an allowable span of 37 in. Support for studs {wales could be reduced to
or ties) would be needed at about 3 ft intervals. Placing top
and bottom horizontal wales 6 in. above bottom of form and �.� =·6��1, �ift2 x (24 ln. /12 ln.ift) x (36 ln. /12 ln.ift) = 3960 lb
6 in. below top of form would permit use of four wales spaced
This solution would have the advantage of being a multiple of
3 ft apart. A heavier stud selection of course could be made to
stud spacing and plywood panel dimensions, but presents the
reduce the number of wales required.
disadvantage of using many more ties.
CHAPTER9
Table 9.3: Safe spacing, in inches, of supports for B·B Plyform Class I plywood sheathing, continuous for
three or more
DESIGN TABLES
Table 9.4: Safe spacing, in inches, af supports for B-B Plyform Class I plywood sheathing, continuous for
two
Maximum deHe.:tion: 1/240of span, but not more than 1/16 in.
CHAPTER9
Table 9.5: Safe spacing, in inches, of supports for B·B Plyform Class I plywood sheathing, with single simple
Maximumdt'fl.e<;tion:1/24Ciofspan,b1Jtnotn\Ofe than1116in.
DESIGN TABLES
9.6.1: Safe spacing, in., of supports for joists, studs, or other beam components of formwork, continuous over
or more spans, CD = 1.0
Ma•imum deflectio<>:1/240of
span.butJ"IO tmore thanll4in
Be�ring stressmu�t betvaluated
�
�
�
Table 9.6.2: Safe spacing, in., of supports for joists, studs, or other beam components of formwork, continuous over
three or more spans, C0 1.25
=
Not.,.:Dry�rvi<e.F,adju<ted
for sizefactorandflat usefactor
only.Noildjustmentfor repetitive
memberfanor or wet service.
Assumedlaterally r"'trained
(Table7.3)sothatC,=l.Oand
��� u ratioo:<>7dayssothatC0
Maximumdefle<tion:1/240o
f
span.butno\morethanl/4in
Bearingstressmustbe evaluated
Table 9.6.3: Safe spocing1 in.1 of supports for joists1 studs1 or other beam components of
formwork1 continuous over three or more spans1 C0 = 1.0
onty.Noitdjustmemforr�litive
membeffactor orwet se.vice.
Assumed�terallyrestrained
tT�ble 7.3)sothatC, .. t.OJnd
cumulativeload duration>2
monthsso thatC0•1.0.
�
�
..
�
� Table 9.6.4: Safe spacing, in., of supports for joists, studs, or other beam components of
formwork, continuous over three or more spans, CD 1.25
�
=
I!!
:::
·spansli�tedan�,on�vati�fO<
Hem-Fir when bf!onding Ot shear
controlsandforSpnxt·Pine·fir
when deflection controls.
Ma•imumdellection:1/240uf
span,butnotmorethan1/4in
Table 9.7.1: Safe spacing, in., of supports for joists, studs, or other beam components of formwork, continuous over
two spans, C0 = 1.0
�
�
"'
Table 9.7.2: Safe spacing, in., of supports for joists, studs, or other beam components of formwork, continuous over
two spans, C0 = 1.25
�\IV 4� <H ..JO ..JI UY IU..J ..JU I..J U<l ..J4 IU Ill 0..,1 lUI I..JU ..JO "� 4..,1 Notes:Dryservice.F.adjusted
300 37 55 47 25 56 84 41 59 52 28 62 91 70 83 107 31 34 36 forsizefactorand�atusefactor
41 22 49 73 45 24 54 79 72 92 27 29 32 only.Noadjustmentfor repetitive
400 32 48 35 52 60
..,.., �· "- ' 0_., ..,, ..,._ ">O memberfactororwetservice
�"" ...,., ,., ,.., ...,,.., ,, �� -,1 '"- ,, ,0 ..,,..
Table 9.7.3: Safe spacing, in., of supports for joists, studs, or other beam components of
formwork, continuous over two spans, CD = 1.0
�
.,
�
"'
Table 9.7.4: Safe spacing, in., of supports for joists, studs, or other beam components of
formwork, continuous over two spans, CD = 1.25
Table 9.8.1: Safe spacing, in., of supports for joists, studs, or other beam components of formwork, single span, CD= 1.0
�
.,
;;1
"'
"'
Table 9.8.3: Safe spacing, in., of supports for joists, studs, or other beam components of
formwork, single span, (0 = 1.0
�
�
"'
Table 9.8.4: Safe spacing, in., of supports for joists, studs, or other beam components of
formwork, single span, C0 = 1.25
�
'"
�
:::
only.Noadjustmemforrepetitive
memberf�ctororwetservice
Assumedlaterallyrestr�ined
(Table7.31sothatC,"l.Oand
cumulative load durat>on>2
·
spanslisted�re comervativefor
Hem-Firwhenbendin-gor shear
Ma•imumdeflection:1/240of
span,but notmoreth�n 1/4in
Bearin-gstressmustbeevaluatecl
�
�
"'
only.No�djostmentforrepetitive
memberf�ctor orwetservice.
Assumed l�ter�lly rew�ined
(Table7.3)sothatC1=1.0and
cumulahveloadduration>2
monthsso thatC�•l.O
"
spanslistedare con�rvati,..for
Hem·Firwnenbendingorshear
controls
Muimumdenection:l/240of
span,but notmore than1/4in
Bearir>eJWess mustbe evaluat!'d
at supports
�
�
"'
j_Sheorcontrols
Notes:Ory service.F.adjusted
forsizefactor �ndfl�tuse f�ctor
only.Noadjustmentlor repetitive
memberlactororwet service
Assumed laterally restrained
(Table7.3)wtllatC,'"l.Oand
load durations7days so t llatC0
=1.25.
·
sP<lnslistedare conservativefor
Hem-Firwllenbendingorsllear
controls
Maximumdeflection:1/240of
SP<ln.butnotmoretllan1/4in
Bearingstres.must be evaluated
NOTI:S; Size �djust�t applied to No.2gr�des. Values are for cumulative load duration>2months_ C0" 1.0. The dimension uS«! in determining tid is that shown first i
this is the large< di�sion.trn.column must be laced (or bra<ed) in the othef direc:tion so that tid in that direc:tion is equal to or less th.ln that used when calculating trn.loads shown. For tile
4x2s,la<iJ19 in the plane of the2-in. dimensiO<l must be at intervals not greater th.an0.4times the unsupported length. For4x3s, la<:ing in the pl�ne of the 3 ln. dimension must be at intervals not
moreth.ln0.7timestheunwpportedlength.
CHAPTER9
Table 9.12.2: Allowable concentric axial load, lb, on construction-grade wood shores of indicated
and
DESIGN TABLES
10: FORM WORK DRAWINGS
Formwork drawings constitute the shop drawings of the formwork contractor. They may
include line drawings, shoring drawings, reshoring/backshoring drawings, and drawings
for vertical formed elements such as walls or columns and may be prepared by the form
supplier, the formwork contractor, or a combination of the two. The drawings are the
guide to how the forms will be fabricated off- or on-site and then assembled in the field.
Development of the drawings is a major effort of the formwork engineer/contractor. It is
not unusual for the number of sheets defining the temporary formwork structure to be
greater than the number of sheets defining the concrete structure being built.
Before constructing forms, the formwork engineer/contractor may be required to
submit detailed drawings, design calculations, or both of proposed formwork for review
and comment or acceptance by the engineer/architect or approving agency. If such draw
ings are not accepted by the engineer/architect or accepting agency because they are not
in conformance with the contract documents, the formwork engineer/contractor should
make such changes as may be required and resubmit for comment or acceptance before
the start of construction of the formwork. Federal OSHA regulations for construction
require, in Subpart Q 1926.703(a)(2), that drawings or plans for the formwork, including all
revisions, are to be available at the job site.
The review, acceptance, or both of the formwork drawings does not relieve the
contractor of the responsibility for adequately constructing and maintaining the forms
so that they will function properly. All major design values and loading conditions should
be shown on formwork drawings. As related to form use, these include formwork design
values of construction live load. allowable vertical or lateral concrete pressure, weight of
moving equipment that can be operated on formwork, required soil-bearing capacity,
material specification, camber required, and other pertinent information, if applicable.
: j I :Ij
E!J- the job site if simple, clear, and complete
drawings are prepared. The ideal drawings
I I
I I I 1 contain essential notes and instructions for
I I I
constructing the forms, but they are not
I I
I I cluttered with unnecessary lines, marks,
I I symbols, or dimensions.
I I
I I
1
I 1 I In addition, the quantities of form mate
I I
- �: ------ -:G:J rials, components, and hardware must be
determined so that needed items can be
It I I
CHAPTER 10
shows an example plan from a set of formwork line drawings of a parking garage
prepared for review.
Line drawings are revised based on the review response, resubmitted for approval as
necessary and, when approved, issued for field use. The forms are fabricated and assem
bled or built in the field to the dimensions shown in the line drawings.
Several observations are important when interpreting the drawing.
Locations are dimensioned from the reference fines. These lines should never be
assumed to be center lines of columns, beams, or walls. While they may locate the
center of some members, note Column C1 and the beam along Line A3 between Lines
1 and 2 that are not centered on the reference lines.
Top of slab elevations are shown adjacent to many columns. The top of slab slope is
assumed to be linear between those points. Note that there are not only slopes for
the up and down ramps but also crosswise slopes from the exterior columns to the
interior columns for drainage. While drain types and locations may be found on the
mechanical and plumbing drawings, details for slab slopes, depths, and allowable
opening sizes must be found or coordinated with the structural and architectural
drawings.
Beam sizes are indicated in inches as W x 0, with the depth measured from the top of
slab to the beam soffit. Considering that the top of the slab is sloping, this means that
many beams are also to be constructed with a slope.
A construction joint is located at the end of Level P2, Pour 2, which also defines the
beginning of Level P3, Pour 1. Note that this joint is neither at the middle nor the
face of a beam where there would be great interference with reinforcement. Rather,
it is located at approximately the bending point of inflection for the beams and slab.
Project specifications or contract drawings should provide locations or specific guid
ance for proposing joints in the structure. Where joints are not located, submit joint
locations to the engineer/architect for review and acceptance.
Several section marks are shown. Each section mark indicates the sheet where the
section can be found (for example, FS1, FS2, FSS) and the section number on that
sheet (for example, 1, 2, 4). These sections are not provided herein.
FORMWORK DRAWINGS
P2 LEVEL LINE DRAI"'IN6
"""""'
�=-�:�A�:o.�
I.UV.O.t"""'-lo:>V-�TO.,..-t
.. ��� """""'"""
OM-
t
�tm'l
· �.·:
���M�J::='n�rr:�r .J . :
-
· � ,-
---ll 1-l---
t�
, · .
'
·
i i
� �
Fig. 10.2: Formwork fine drawing ofparking structure (Drawing courtesy United Forming, Inc.)
CHAPTER 10
FOR APPROVAL
FORMWORK DRAWINGS
- (4)SETS OF X-6RAC-E5 PERRO�.
- ROI'iS 11 I0'-6'o.�. MAX
CHAPTER 10
SEE F<li<MI't::li<K LINE D!W<IN65 FOR PLAN DETAILS
PLAN- 15 FOR iSfNERAL GONCEPT AND X-flRACIN6 LAYOJT ONLY
FORMWORK DRAWINGS
Fig. 10.4: Formwork shoring for example bay of parking structure (Drawing courtesy United Forming, Inc.)
(1}1116 M EACH----t+-----;;o:<f
INTER5EC.TION
OF X-eRAGI'
Fig. 10.5: Example section view of formwork shoring and bracing for parking structure
(Drawing courtesy United Forming, Inc.)
CHAPTER 10
E�
�0.
��
I!�&
DCI(Jf' ..NI!.Ntl
�� 4'-(/'
�
M!. A ..NI!.O
'ibb�J l/��dd· I�
� Q)
s
w.��4'-0'14'-0'14'-o'l4'-o'l4'-o'l4'-o'l!l'�
"<7
<tl
W!-L FORM�K NOTES, z
�.lr!D �M
..Ne-G
J 2$-o'M .,-o'.lr!D:::::t t HAX1KM � AAre • �I'm! AHJitp.u..f CGifOIBE 1EM'EfVo'ME f7!10" (F). >-.1
ar•££Hll'rniAMitfM.M�fl!toA!RAl\ROf60"C'J.
�
ar•�l'l'lliAHINIM.H�TIM"ERA"T\,R;C1f10"/f=}.
<tl
O..l
ar• �l'rnl AMINM.H�1'&f'eRA"I\.P20f "15"(P},
!NQINEI!A'S SEAL 2. m!5 PESI6NA5StH5A MAAJ�ot.Mtei6H � CIP 121!,_, �Motr.XJH.,to1
I"''..W/YU.tEI6HT5f716'�165HOI'tl
,,1H15PES16NN'f'\..leott.'I'FORNOitMALI'EI6HTGOHC.'I2'T!�I'tll+f'l"'"f 1,11, t
Ill G&elf, �,., tot:::lRE n+AM ,., NfJ l'rnl A VleltATlOM CEPnf UH1EP TO 4'
s
PREUMINARY ·NOT 0
"""""·
FOR CONSTRUCTION 4.nt!'U5f:C1fGG'NCflf'II:ADMIXT\IH,Ir6
II!:S EHAGGO.NT!'O�IMllff5ISI6H.
u
!.I'WJ. TE5 ARE TO eE 1'�..• TH'!R TIE5"' �VY' I'WHRS.
�
�, Fig. 10.7: Wall formwork example drawing for aluminum beam ganged panel derails (Drawing courtesy United Forming, Inc.)
0
WIRE HEAD ( CABEZA. DE CANASTA) T-HEAO (CABEZA.ENT)
,..
-
f--
-
-·
TheEllitOOiftC*IY"-
Ulr\.2
3118"X31o11"
�::-�:r--
J �
RUNNER NOTES:
1) J:rE�=;;��iPERFOR.W:D TEmiC*CLAMPS
•)=H�����n:=:�����s�
RUNNER JOINTS SPECIFED ON SPECIFIC PROJECT DETAILS.
Fig. 10.8: Shoring and flat slab formwork connection and bearing details (Drawing courtesy R.H. Bordner Engineering Co.)
Figure 10.8 shows a form designer's standard details for installation of adjustable wood
shores with a specific manufacturer's hardware. The acceptable alternate types of shore
head-to-stringer connections for different situations are indicated as well as minimum
shore-bearing contact. In some designs, joists are referred to as Hrunners.u A detail indicates
the required minimum bearing lengths of the 4 x 4 runners on the 4 x 6 stringers. Note
that some wording is also indicated in Spanish.
Figure 10.9 shows a plan layout of steel shoring frame towers to support forms for a slab
and beam floor system (Fig. 10.10). Notes and standard symbols used in the drawings are
shown in Fig. 10.11. A diagonal line is drawn between pairs of shoring frames in the plan. This
diagonal line is not a connecting brace but rather a plan view schematic symbol indicating a
tower assembly. The bracing is either a part of the frame (Section A) or field- connected tube
X-braces (Section B). Adjustable leg and top jacks are indicated with their maximum exten
sions. Aluminum stringers, aluminum joists, and plywood sheathing are the main components
for the deck. The beam side forms are constructed of wood with plywood sheathing to fit the
beam dimension. Reshoring requirements are referenced to other drawing sheets.
If panel forms or other prebuilt form components are to be used for an entire project,
or for a major part of it, an assembly or layout drawing showing the location of panels is
essential. Such a drawing can be a mere skeleton or outline, showing only major dimen
sions needed for locating formwork components. Each panel should be given an appro
priate identifying mark to aid in positioning it when the forms are erected. Panels of the
same size and shape should all bear the same mark. By means of subscripts or other iden
tifying numbers, the order in which panels are to be used can also be indicated if desired.
To supplement the layout drawing, a detail or·make-up" drawing of each panel or form
component must be prepared, showing all essential dimensions so that shop and field
personnel need not refer to the engineer's or architect's drawings. The detail drawing should
FORMWORK DRAWINGS
I---6
- '-0"-l----6'-0"-l----6'-0"-l----6'·0"-l----6'·0"----l
Fig. 10.9: Partial plan of form layout supported by shoring towers for slab and beam floor
system (Drawing courtesy Atlas Construction Supply)
indicate the mark number corresponding to the basic layout drawing, and indicate the
quantities of each unique unit required. Various additional details are needed to show how
to handle intersections, corners, bulkheads, inserts, and other special conditions. Details are
frequently shown on the same drawing with the layout and other components, but it simpli
fies shop work if a single sheet is prepared for each panel or other component to be built.
When non-standard, complex items are required, the designer or detailer can often help
speed the work by giving the form carpenter a simple pictorial sketch to supplement the
conventional plan and elevation. For standard elements such as rectangular beams and
columns, some contractors have found that printed sheets with prepared outlines of beam
and column parts (Fig. 1 0.12) are helpful in giving the workers in the shop or field instruc
tions on the fabrication and placing of form parts. The designer simply pencils in dimen
sions, details, and necessary notes on the printed outline drawing. The shop foreman or
project superintendent can then use these sketches in directing the workers. These sheets
may also be made up to include a bill of materials required.
CHAPTER 10
T �
.
L
1.2
5nou1di>Ociui10<
'*'-"'-.
-.ol-- --.-.,...
lb·1S30bllq-"'-
�::����--l
OST�el
�-:0�� .. -
.......000""""'."'·
���
E·2h10'bllq.lfl.
u,,LIJM1NUM·6061·T6·
�
h•10 ..000ltiSIIo:j.on.
(o10.15•10'Ibollq.A
z.ooz� -.<lougn---
Z.1SHORI N O
�-·
� .... -�10<-00tl..ggioo
r
��� l "'':PAESENTlNGZE.ocH�I'I.OUIES
&2EACHCROSSIIRACESPERSTAGe
SEELE(lENDSTliiNGI:ROFIBENol
/loSP!'IIMNIYWEM&ER
Fig. 10.10: Section views of shoring cowers, stringers, and beams for slab and beam floor
system (Drawing courtesy Atlas Construction Supply)
C::::::C():::::::J "·DECI<GIROER"-OE:CICJOIST
shores and for retracting and resnugging drophead shores to allow the slab to deflect
and support its own weight prior to casting the next level;
2. Design allowance for construction loads on new slabs when such allowance will
affect the development of shoring, reshoring schemes, or both;
3. Anchors, form ties, shores, lateral bracing, and horizontal lacing;
4. Means to adjust forms for alignment and grade;
5. Waterstops, keyways, and inserts;
6. Working scaffolds and runways;
7. Weepholes or vibrator holes. where required;
Fig. 10. 1 1: Example notes and symbols for
B. Screeds and grade strips;
shoring tower supported forms (Drawing
9. location of external vibrator mountings;
courtesy Atlas Construction Supply)
10. Crush plates or wrecking plates where stripping can damage concrete;
11. Removal of spreaders or temporary blocking;
12. Cleanout holes and inspection openings;
13. Construction joints, contraction joints, and expansion joints in accordance with
contract documents (also refer to ACI 301);
FORMWORK DRAWINGS
<>
� ------"1
I::: I Srde
I
J I I L
l I
tJl �11 tJl tJl
�
� -------j
i:::l I
�LI J
Bottom
Shornol
r-- -----j
i:::l
0
I_ �
Srdl
u
'
Nortt'l Sour� �
--, I
BEAM FORM S COLUMN FORMS
��-·- ���-
�
C];l'�····:
Locahc --
No.Reod--
- No-Read.--
Fig. 10. 12: Example standardized sheets used by some contractors to simplify instructions for making beam and column forms
CHAPTER 10
14. Sequence of concrete placement and minimum elapsed time between adjacent
placements;
15. Chamfer strips or grade strips for exposed corners and construction joints;
16. Reveals (rustications);
17. Camber;
18. Mudsills or other foundation provisions for formwork;
19. Special provisions, such as safety, fire, drainage, and protection from ice and debris at
water crossings;
20. Special form face requirements;
21. Notes to the formwork erector showing size and location of conduits and pipes
projecting through formwork; and
22. Temporary openings or attachments for climbing crane or other material-handling
equipment.
The actual content of the formwork drawings can vary depending on project contrac
tual agreements. For example, if the formwork is a subcontract and the formwork subcon
tractor is not responsible for supplying or installing waterstops in walls or mechanical
inserts for floors, those items would not be shown on the formwork drawings.
Major design values, loading conditions, and pertinent tolerances should be shown on
formwork layout or erection drawings or accompanying notes. These include assumed
values of live load, maximum rate and order of concrete placement, temperature of
concrete, allowable unit weight of concrete, assumed values of dead and live load, weight
of moving construction equipment that may be operated on formwork, foundation
pressures, design stresses, grade and type of form materials, camber diagrams, and other
pertinent information. A list of required ties and other accessories showing the manufac
turer's name, load capacity, and so on may also be shown on the drawings. Several of the
example drawings illustrate some types of information that are frequently included in
these notes. Such information may not be required on the detailed make-up drawings or
sketches used by workers in building individual prefabricated form parts.
For projects involving elevated floors, definition of shoring/reshoring criteria is critical.
The drawing views or notes should define:
The number of floors of shores and of reshores;
The sequence of shore/reshore erection and removal;
Minimum concrete strength for stripping and acceptable methods of field strength
determination, as required by the engineer/architect;
Minimum time required before stripping (if also or alternately specified), as required
by the engineer/architect;
Stripping sequence for post-tensioned floors;
Any restraints on operations while stripping or reshoring is underway; and
Specific directions for releasing shore dropheads, retracting shores, and snugging reshores.
i er
th !�:�:�� :� � :;����: �� �:��
f b 1-'"'"-1-'"'-'+-''L'"+-"----l""-'"+--"'-+-"'-+=-
'
' +-"--
M' -+"-
'· -+"'..,· '+-'9
structural elements may be prescribed by
the engineer/architect to compensate for
deflection of the structure and is created
-
by setting the formwork to produce the
specified elevations. Camber in members
of the formwork system may also be
needed based on the form design to
compensate for form settlement, take-up
of contact parts, and elastic deformation
·�
of the form components. The portion of
the camber required by the engineer/
architect must be defined in actual dimen
sions because the behavior of the struc
ture cannot be predicted by the formwork
engineer/contractor. An example method
..
·.
.
of indicating camber for a timber truss
supporting formwork for part of an arch
bridge is shown in Fig. 10.13.
Fig. !0.!3: One method of indicating camber on formwork drawings. In this example for a
timber truss, for which ordinates are shown, supporting forms for a concrete arch ·
CHAPTER 10
1 0.7 BIM 3·0 Graphical
Views af Formwork
The graphical capabilities of BIM are gradu
ally being realized in concrete formwork
applications. Figures 10.14 through 10.16
show how the components of formwork
hardware accessories, form members,
bracing, and shoring can be integrated
to produce not only 2-D drawings but
also 3-D drawings. Individual parts could
be modeled by the formwork engineer/
contractor. However, individual proprietary
parts can also be modeled by manufac
turers and suppliers for the use of form
work engineers/contractors in assembling
the model of the formwork. The ability to
visualize the formwork structure during
design development provides the oppor
tunity to recognize situations that may
have been missed and would cause delay
in the field. With increasing portability of
computing laptops and tablets, the 3-0 Fig. 10.15: 8/M virtual 3-D drawing of shoring towers and partial floor system formwork
models can also help field crews under- (Drawing courtesy Klarman Construction)
stand the formwork design intent by
rotating the model to view from multiple
angles. Figure 10.17 shows the drawings for
a deck table form constructed of plywood,
1-joists, and lumber components. Because
BIM can also track each component, the
form bill of material has been tabulated to
assure all needed parts can be available.
The deck table form can be moved as a unit
and placed on shoring frames, as shown
in Fig. 10.16. The beveled plywood edges
10.17
indicated in the Table Side View of Fig.
facilitate stripping by forming a fillet at the
re-entrant corner between the beam and
the slab.
Fig. 10.16: 8/M virtual 3-D drawing of shoring frames, beam, and slab formwork for parking
structure (Drawing courtesy Klarman Construction)
FORMWORK DRAWINGS
�:=��
t!Ol:Jl:llNO:J
,_
� �
l.S
� "
3
I §
l 5""��-.���; t
j n�
;.
'
CD
i• �
CD
d !'
�
! u
r J�" nn�: E
;I
8
;�
g
� u
Ill . "'''""I ·�E
�
��
so i! U,UHU 8
j �»
0
�:! .§ . �
1
i� h � Hll"lH
1':
I
�
z
"' "
�
0
.s
"
:;;
§
�
8
�
·§
"'
.5
E
§
•
- -�
�� ;.
'
f.
.s
11
J, i'
�
;. "
"�- "' '
j
"'
.� tt
�
<
; :.;
"'
<
:15
E
�-�
F "I
;.
' ��
�
d t •
�
k �
�
�� �
l.
,;- �
d "'
�
11: BUILDING AND ERECTING THE
FORMWORK
How formwork is built and erected depends on many factors-the materials available
or required, the skills and cost of the local labor supply, and demands of the project for
accuracy and perfection of finish (Fig. 1 1 .1). For most formwork projects, there is no single
correct forming system; rather, there are several workable alternatives, and a choice
among them depends on cost comparisons, local customs, and contractor preferences. At
times it may be preferable to use the system and approach familiar to the available crews
rather than try to train them for a new system.
The techniques presented in this chapter are not the only way to do a given project,
but they do represent ideas that have wide current acceptance or have proven particu
larly valuable to experienced form builders. Following descriptions of the necessary shop
or yard facilities for form building and safety considerations, the discussion centers on
various formwork components in the following divisions:
Footings;
Slab-on-ground and paving;
Fig. 11.1: Formwork des,igned with board
Walls;
s.heathing for placement of complicated
Columns;
concrete roof s,tructure of a mus,eum (Photo
Beam and girder forms;
courtes,y PERl Formwork Systems,, Inc.)
Elevated slabs; and
Shoring.
Because formwork for architectural concrete, bridges, mass concrete, tunnels and shafts,
and special techniques are treated separately in Chapters 14 through 18, major emphasis is
given to conventional formwork construction in this chapter.
Sizes and spacing of form members shown in the examples are typical of good forming
practices, but they cannot be copied without making a careful analysis for conditions
peculiar to the individual project. The formwork engineer/contractor is in no way relieved
of the responsibility of checking their unique project requirements and choosing forming
members on the basis of design standards
listed in Chapter 2 and theory explained in
Chapters 4 through 8.
Fig. 1 1.4: Prefabricated and secure metal Fig. 11.5: Formwork project office space for
containers are often used for tool storage formwork contractor provides for drawing
and checkout (Photo courtesy CECO Concrete layout, CAD access, training, and site super
Construction, LLC) vision (Photo courtesy CECO Concrete
Construction, LLC)
CHAPTER JJ
tant. If a large percentage of form lumber passes through the shop, it should be located
near the material receiving point or storage point. If very little form lumber passes through
the shop, the shop can be located closer to the construction work. The space available and
location of the building site in relation to adjoining streets will influence shop layout. If at
all possible, the shop should be located so that the operation is progressive from the point
where lumber is received to the place where finished forms are delivered to the erection
crew. Similar considerations affect the interior layout of the shop. An opening is often posi
tioned at the end of a radial arm saw bench so long material can be fed from the outside.
If the building occupies an entire site, and there is no adjoining vacant land, the shop must
often be strung out along the building site on the sidewalk. A space 10 to 12ft wide, long
enough to accommodate all equipment, is required. The shop should be placed next to the
street to allow delivery of materials without interfering with pedestrians. A covered walkway
for pedestrians is then placed between the shop and the building, and a fence is erected on
the street side to protect workers from traffic. For multistory building work, it is often desir
able to place the shop inside the building, particularly if exterior space is limited.
Fig. I I .6: Safery railings at floor edges and sides of outrigger platform; safery net for foil protec tions." A complete coverage of applicable
tion at end of an outrigger platform allows lang material to be landed (Photo courtesy MEVA OSHA provisions will not be attempted
CHAPTER 7 7
placement and stacking of materials Table 11.1 : ACI 117·recommended tolerances for formed foundations
(Fig. 11.8), passageways, and distribu for buildings
tion of loads; and
removal of nails from used lumber. Deviation from location of os-<:ost edge
Providing training in these and many Where foundation pion dimension is 8ft or more :t:2 in
other applicable requirements of OSHA is Where foundation pion dimension is 8Ft or less Greater of :t:2% of spe<::ified dimension or 1/2 in.
Foundations supporting mos.onry lesser of :t:2% olloundotion width or :t: 1/2 in
part of the process of establishing a safe
workplace. Generally, it has been found Deviation in horizontal crosrse<:tioncl dimensions -1/2 in., +2 in.t
that a clean safe workplace is a more Deviation in thickness -5% of spe<::ilied thickness
productive workplace.
•Appliestoconcre(eo nly,notto relnforcingb.Jr sordowel s
'Fmunforme<ifootings,horizontaldimension positivetolerancesrangefrom3to6in.. with1/2in.n"9•tivetolerance
11 .3 Footings
Principal construction requirements for
footings are sound concrete and correct
position to match column and wall plans.
Tolerances for formed footings, based on
ACI 117-10, #Specifications for Tolerances
for Concrete Construction and Materials,w
are given in Table 11.1. Because the footing
is below grade and appearance is rarely
important, any sound old or used mate-
rial may be used for forms. When casting
concrete directly against soil without forms
(Fig. 11.9 and 11.10), additional concrete
side cover for the reinforcement is required.
When casting concrete directly against
earth, it may be desirable to form the top 4
in. of the footing.
layout methods vary. On some proj
ects, a total station surveying instrument
may be used to locate each founda-
tion element. On other projects, batter
boards are set up outside the limits of
the excavation and marked to locate
Fig. 11.8: Placement and stacking of materials Fig. 11.9: Carefully excavated trench will serve
building reference lines. A string or wire
and form components must be stable and as form for footings to be placed without side
supported by the batter boards is then
have adequate passageways (Photo courtesy forms
stretched along the reference line, as
CECO Concrete Construction, LLC)
shown in Fig. 11.11. Points below and at
intersections of the strings are located
with a plumb bob. A convenient height
should be selected for the batter boards
(an even number of feet above or below
some horizontal feature of the proposed
structure such as the finished footing
elevation) so they can be used for tempo
rary benchmarks.
For most projects, general excavation is
first done to the subgrade of the slab-on
ground. In cohesive soils that stand up well,
the footing outline is cut by hand or by Fig. 11. 10: Cast unformed footing with beams
specialized mechanical equipment to the spanning over the footing to support a
exact size and depth. lf the soil is porous or template for the reinforcing bar dowels
!! Brace
�Jj' ;!
\'
fj
\' v
Fig. 1 1. 13: Alternate bracing systems for flat footings. Footings of greater depth may require ties
Fig. 1 1. 12: Low footing form for wall can be stake about every 6ft. If the holding power of the stakes is poor because of ground conditions,
the forms can be braced as shown in Fig. 11.13. Sometimes earth can be used as a brace
braced. No ties are required, and wood spreaders
by simply backfilling around the forms, although this is a disadvantage when forms are
across the top hold sides at correct spacing
stripped. No ties are needed for shallow forms.
Deeper wall footings or grade beams (in non-cohesive soil) require more bracing or ties
to withstand concrete pressure and are constructed much like wall forms.
Stepped footings are used when the supporting ground slopes and the bottom eleva
tion of the footing needs to vary longitudinally. To avoid a tendency of the footing and
wall to slide, the footing bottom and top are stepped longitudinally with formwork as
shown in Fig. 11.14.
because of sloping subgrade For small shallow column footings, the ties are usually omitted and wood braces are
nailed across the top of the form box. Round footings may be formed with short lengths of
the fiber tubing used to form round columns.
If the entire footing is to be cast monolithically, top forms for the space between the
steps may be needed to keep the concrete from pushing out, depending upon the
(a) Ground stakes with braces (b) Strongbacks and form ties
Fig. 1 1. 15: Two methods of forming column footings; number of braced stakes or strongbacks
per side varies with plan dimensions of footing (Images courtesy United Forming, Inc.)
CHAPTER 11
concrete slump. When the area between
the steps is covered, the entire assembly
must be weighted or tied down to resist an
upward pressure on the top forms from the
freshly placed concrete.
Combined or strap footings are used to
transfer part of the load of one footing to
another or to support two columns on a
single footing. If two columns bear on one
footing, the combined footing form is built
in the same way as other spread footings. If
the load of one footing is to be partly trans
Fig. 11.16: Ribbed expanded metal used as
ferred to another, a strap or beam must
stay-in-place sheathing for pile cap and
be constructed between the two footings.
grade beam form; to provide lateral support,
Tie beams to distribute lateral loads to pile
external vertical bars are tied by drilled
groups and grade beams to support walls
boards across the top of the tie beam and
have similar configurations (Fig. 11.16).
tied to transverse reinforcing of pile cap
If the beam or strap is to be cast after the
(Photo courtesy Alabama Meta/Industries
footings, the beam forms are supported
Corporation, AM/co•;
by the previous placement. If the footing
and beam are to be cast monolithically, the
boxes for the footing forms are built with a
cutout for the beam, if necessary, and the
top form for footing portions are weighted
or tied down.
Sometimes footing bottom elevations
are set at greater-than-typical depth
because of soil conditions or stepping
down toward the elevations of deeper
nearby elevator pits or partial basements.
Depending on the conditions, it may be
necessary to protect the workers in accor
dance with OSHA trenching and excavation
requirements. Figure 11.17 shows the use
of a trenching shield coated with release
agent to the top elevation of the footing
and used as both the protective system and
the side form. An excavator is used to lift
the shield when stripping.
For large mats and slab foundations,
neither through ties nor connectors
over the top of the footing work well.
Sometimes, half ties are connected to
the reinforcing steel for side form lateral
support. Often, edge forms are braced as Fig. 11.18: Thick slab footing formed with small hand-set modular panels supported laterally
shown in Fig. 1 1.18. Forms for other large with kickers and adjustable diagonal braces (Photo courtesy Symons by Dayton Superior)
footings are described in Chapter 15 on
bridge formwork.
11.4.1 Slabs-on-Ground
Plywood, boards, and metals are common materials for edge forms. They are held in posi-
Fig. 11.79: Braced wood edge forms for
tion by stakes or braces (Fig. 11.19), much the same as simple footing forms. Occasionally,
concrete slab-on-ground placement
other materials such as concrete masonry units or plastic form components may serve as
edge forms, or the already-cast walls of the building may become the edge forms.
..--1....,.,..=-o./
ACI 302.1 R-04, uGuide for Concrete Floor and Slab Construction; has recommendations
for contraction, construction, and isolation joints-the latter to isolate floors structurally
from other building elements and thus accommodate differential movements and plastic
deformations. ACI 302.1 R recommends construction joints with dowels for load transfer
rather than keyed joints where heavy traffic is present. Keyed joints like those in Fig. 11.20
can be used for low-traffic areas where some load transfer is required.
Because columns and slabs settle differently, isolation joints are typically placed around
columns, frequently in a diamond pattern so that slab contraction joints will intersect
the point of the diamond. This also avoids binding of the slab on the column as the slab
shrinks. A slab blackout form is shown in Fig. 11 .21.
CHAPTER 11
joint should be free of play or movement in
any direction to maintain correct alignment
of succeeding sections. It should be easily
disconnected for stripping.
and worker access must be considered. The usual practice sheathing materials are indicated
,������.
The reinforcing setters may have a problem with the
�=����=�=� ties being inserted before reinforcing steel placement
L--
1 __ __,I ._
1 __ ____,1
_
as the tie ends stick out the wall thickness plus about
8 in. from the face of the form. Inserting the ties may
(a) Template as kicker (b) Template as sill
for panel have to be delayed until the reinforcement is placed
for panel
and then adjusted as required to put the ties in the
Fig. 1 1.27: Wall formwork panel alignment on footings and slabs correct locations followed by closing the wall with
the second form face.
The first step in building a wall form is often to attach a sill or template to the footing
as a base or kicker for formwork panels. The sill or template may be attached to preset
anchors, powder-actuated shot anchors, or inserts drilled into the concrete. Care must
be taken in aligning this strip because it will determine the line of the wall. It is set out
from the proposed line of the wall a distance equal to the thickness of the sheathing.
Several example arrangements are shown in Fig. 11.27. The detail shown in Fig. 11.27(b)
requires that the panel be fabricated with the sheathing edge projecting the thickness
of the sill, which may expose it to additional damage during handling. The arrangement
in Fig. 11.27(c) can be used if the resulting bottom wall formed edge surface is accept
able, otherwise the framed panel can be set as shown in Fig. 11.27(a). Panels sitting
on the sill are usually nailed to the sill after alignment (Fig. 11.28); however, wall ties,
rather than the nails, resist the concrete lateral pressure. A strip of closed-cell rubber or
PVC foam tacked to the bottom of the sill has proved effective in minimizing concrete
leakage during vibration.
CHAPTER 11
Wales may be installed as soon as the
panel is in place. Wales are attached to
the outside of the studs and held in place
by nails, dips, brackets, or proprietary
devices. When wales are constructed of two
members, this saves drilling for ties. Special
hardware like that shown in Fig. 4.33
facilitates the use of single-member wales.
In long wales, the joints between members
should be staggered. If double wales are
used, there need be no transverse joint
completely through the wale.
Permanent bracing can be installed
after the wales are in place or as the form
is plumbed (fig. 11.31). These braces
may be attached to either studs or wales
and extend to the ground or other solid
support. Ground support may be by nailing
to a 2x4 wood stake or metal stake if the Fig. 1 1.30: Partially prefabricated job-built panel with remaining studs to be set in place
brace force to be resisted is small and the
soil is adequate. Anchors, selected based on the brace force, are sometimes drilled into a
concrete slab. When a slab is not available, concrete deadmen either placed on the ground
surface or cast into an excavated hole may be used for attachment.
Due to the sequence of erection, forms are normally braced on only one side and the
braces must resist both compression and tension.Therefore, fastenings at each end of the
brace must have adequate strength to resist the expected forces. Proprietary devices are
available for attaching the brace and adjusting its length after it has been installed. If the
braces are designed to act in tension only, they must be located on both sides of the form
and securely attached at each end. A cable is well adapted to this type of bracing.Tension
braces are required on both sides when the first form face is erected.The cable length can
be adjusted during the plumbing of the forms by a turnbuckle or other device.
Plumbing is the final operation in building a wall form. Ties are usually installed and all
permanent bracing placed before plumbing begins so that the form will not need to be
disturbed after it has been plumbed. Many bracing systems have devices for adjusting
the braces to facilitate the plumbing operation.lf the braces are non-adjustable, the form
must be plumbed as the braces are installed. No time should be spent in plumbing both
sides of wall forms because the second form to be built will be automatically plumbed if
Fig. 1 I .31: Wall bracing adjustment simplified
internal spreaders are used.
with ready-made turnbuckle device arrached
After the form for one side of the wall has been built and braced, work can begin on the
at the end of ordinary wood brace
second form. The ties must be threaded through the predrilled holes, generally by probing
from the first side if the tie is a single unit.
When both forms have been erected and reinforcement has been placed, the ties are
tightened. If ties with spreading devices are not used, the forms must be held apart at the
correct spacing with spreaders that can be removed as the concrete rises in the forms. A
Wire through off
wire attached to the bottom spreader, running through all spreaders above, and anchored center holes in
to the top of the forms will aid in their removal and avoid leaving any spreaders in as the remaining spreaders
concrete rises in the forms (Fig. 11.32). Ties and spreading devices are discussed in more
detail in Chapter 4.
Where through-the-wall tying is impossible or prohibited by specifications, as is the case Tie at each pair
for some water-retaining structures, external bracing must be provided on both sides to of wales
resist the lateral pressure of the fresh concrete (Fig. 11.33).
CHAPTER 11
Fig. 11.36: Framing and assembly of
contractor-built single-wale panel for wall
forming using ready-mode formwork hard
ware (Image courtesy Meadow Burke)
I I .5.6 Pilasters
Figure 11.46 shows a wood pilaster form. Note that the edge grain of the form sheathing is
either covered or is located so its imprint will not be visible from the front of the building.
The front panel of the pilaster form laps the side panels so that if a fin is formed, it can be
removed without touching the face of the pilaster. The sides of the pilaster form should
-c"""'oc'
assembly
- �:::�:;,
-Tie
CHAPTER 11
Fig. 11.46: Plan of pilaster form where projec
tion is greater than the depth of the studs;
sheathing for wall face laps over corners
not be nailed to the wall stud sides because nailing from two sides will make the studs
difficult to strip without tearing them apart. The blocks between the wall and pilaster
Fig. 11.48: Panels ganged for setting by crone
wales should be slightly loose so that when the ties are tightened, they will pull the face
on long-radius circular wall (Photo courtesy
form tight.
EFCOCorp.)
Often, pilaster forms are integral with the wall formwork, so the pilaster is not stripped
as a separate form. This can be accomplished if there is a side draft created so that the
pilaster is wider at the wall than at its face. Many designers incorporate this in their design,
and the formwork builder should investigate whether or not it is possible, even if it is
not part of the design. A draft as small as 1/2 in. per side is often sufficient to remove the
pilaster and wall form in one operation, and is visually indistinguishable. Other systems
that hinge at the outside corners also exist for pilasters. Proprietary accessories are also
available to assist with pilaster forming.
Pilaster formwork pressure can be transferred to the nearest wall tie by means of a yoke
or offset wale that straddles the pilaster, or by passing a tie through the pilaster itself. A
system of forming pilasters should be selected based upon the formwork type being used
for the walls, the features of the pilasters with regard to the building's architecture, and the
intensity of reinforcing steel at pilaster locations that can make it preferable not to have to
pass ties through these elements. Fig. 11.49: Template for assembly of outside
form segments into a specific radius by
11. 5.7 Curved Walls and Round Corners adjustment of flange strap bolts (Photo cour
Rounded corners or curved walls of radius greater than 4 ft can be formed with plywood tesy EFCOCorp.)
attached directly to studs. Horizontal sheathing boards can be used for curves with a
radius of 18ft or larger, and vertical board sheathing is sometimes used for smaller radius
curves. Rectangular prefabricated panels, with narrow or flexible fillers added, are often
used on long radius curves. Short radius curves frequently require a smooth lining mate
rial backed up by narrow vertical members. Thickness of sheathing and details of construc
tion vary with the radius of the curve. Several of the many forming methods are described
in the following paragraphs, and information on the radius of bend for several common
materials is given in Chapter 4.
Most of the methods involve use of form ties as in straight walls. However, a few
systems, when used in a dosed ring resisting the hoop tension, function without ties. The
articulated wales act as a tension ring on the outside and as a compression ring on the
inside. Vertical wood members provide direct support for the contact face of the form.
Controlled placement of concrete, evenly distributed in shallow layers around the full Fig. l 1.50: Temp/ere for assembly of inside
perimeter of the form, is necessary. This approach is desirable when ties are not allowed in form segments into a specific radius (Photo
circular water-retaining structures. courtesy EFCOCorp.)
Long-Radius Curves
Long-radius curves, about 10 ft or longer, are easily formed with prefabricated panels (Fig.
11.47 and 11.48}. Special filler panels and accessories, as well as suggestions for erection,
are available from panel manufacturers. The assembly process varies with the system.
Support template jigs, cut to the desired outside and inside radius, are often used for effi
cient assembly in ganged panels, as shown in Fig. 11.49 and 1 1.50.
Long-radius curves may be formed with plywood or horizontal board sheathing in much
the same way straight wall forms are erected. After the wall line curve has been marked
�
the curvature of the wall, short straight
sections with shim blocks or curved
cut PLAN
sections cut from wider boards (fig. 11.51)
from standard lumber are used to span four to six studs according
to the curvature of the wall. The installation
of ties and external bracing and plumbing
ELEVATION of the form (fig. 11.52) is similar to that for
straight wall forms. More external bracing
Fig. 1 1.51: Arc segments cut from standard lumber sizes maybe laminated to form a rigid may be required for this type of form than
curved piece for wales for normal straight walls because of the
short wales.
Steel wales rolled to a range of defined
circular radiuses are used in some systems
(Fig. 11.53). Wood studs are attached to
the curved wales and then the plywood
sheathing is curved by attaching to the
studs. Adjustable radius manufactured
wales of several different designs are avail
able to simplify building of curved form
work. They are based on rigidly connecting
short wale segments to become chords
of the desired curve. Vertical studs and
sheathing are added to assemble the
completed form. Proprietary all-steel
forming systems are also available for
building circular structures. They have
steel plate contact surfaces with attached
vertical stiffening and support members.
Horizontal stiffeners provide adjustment of
the radius through a variety of connection
systems (fig. 11.48). These all-metal forms
can be adjusted to radiuses of 10 to SOft or
larger.
Shorf-Rodius Curves
Vertical board sheathing is frequently
Fig. 1 1.52: Assemblyof formwork for curved and flared retaining wall (Photo courtesyUniversal used to support the lining for short-radius
Forest Products) curves. Curved wall forms with vertical
sheathing require curved horizontal ribs
fabricated to support the sheathing. These
ribs are usually cut from wider stock; they
can be made of single or double segments.
Straight wales are then oriented vertically.
Figure 11.54 shows a short-radius corner
formed with hardboard or plywood lining.
Yokes are cut to the required curvature
from 2 in. stock and spaced about 30 in.
apart. The yokes are sheathed with vertical
2x2 dressed strips. The lining is then nailed
securely to the 2x2 backing. Because the
lining material will tend to spring back to
its original flat shape, it must be nailed at 6
Fig. 1 1.53: Steel wales rolled to curves of 6
in. intervals in both directions.
ft or forger radius, combined with plywood
Two or more thin sheets of form material
sheathing and stud lumber used flat (Photo
Fig. 1 1.54: Typical detail for small-radius comer may be used rather than one thick sheet
courtesyGates & Sons, Inc.)
form using hardboard or plywood liner (Image because they can be bent to a smaller
courtesyParr/and Cement Association) radius. Figure 1 1.55 shows one way of
using double plywood for corner forming.
CHAPTER 11
·""
t]llf f:..::: �.� """'
-.:-- -
:,··:.
�.
JA'-08
.
2-;i!;ockwhlcn
lot otn•cpoe<>ong
The corner sheathing is brought out beyond the spring line to form tighter joints where
it abuts the wall sheathing. The sheathing is supported by horizontal members cut to the
curvature of the corner.
11.5. 9 Joints
Vertical Construction Joints
Vertical construction joints are formed with a bulkhead placed in the forms at the end of
the proposed concrete placement. Because the reinforcing bars continue through the joint,
some provision must be made to allow them to pass through the bulkhead. Bulkheads may
be made of short pieces of wood, placed horizontally, cut to fit between the two faces of
the wall form, vertical boards (Fig. 11.58), plywood, or expanded metal (Fig. 11.59). Rein
forcement is passed through holes made by notching, punching, or drilling the bulkhead
material. If holes are drilled in boards or plywood for the reinforcement to pass through, a
saw cut through the center of the holes will allow the bulkhead to be stripped. Form acces
sory manufacturers provide various"form saver" systems that eliminate the need to have
the reinforcing steel penetrate the bulkhead. These systems use a mechanical splice of the
Contraction Joints
Contraction joints must be placed in concrete walls as shown on the plans. Such joints
are formed by a beveled insert of wood, metal, or other material that is tacked to the
form (see Chapter 14). This insert produces a groove in the concrete that will control
surface cracking. It is frequently designed to be left in the concrete for some time after
Fig. 11.60: Form-saver splicing devices ovoid the forms have been stripped, and in such a case it must be only lightly attached to
reinforcing bar penetrations of the form the form. If this insert or strip is removed too soon, the area around the joint may be
sheathing by allowing a mechanical splice damaged. Special care is required if control joint strips are removed along with the
after stripping main form panel. If wood strips are used, they should be kerfed to prevent swelling
that might crack or spa II the concrete.
CHAPTER 11
such forms. Best practice coordinates form design with vibration needs before purchasing
or building the forms.
Low-frequency, high-amplitude vibration has a greater impact and is harder on forms
than the high-frequency, low-amplitude type. Extremely rugged forms are required where
both high frequency and high amplitude are used.
Steel is the preferred forming material when using external vibrators because it has
good structural strength, is well-suited for attachment of vibrators, and when properly
reinforced, provides good, uniform transmission of vibration.ACI309R recommends
using steel plate 3/16to 3/8in. or thicker, stiffened with vertical or horizontal ribs, or
both. Wood, plastic, or reinforced concrete forms are generally less suitable, but will give
satisfactory results if their limitations are understood and proper allowances are made. For
more detail, see ACI309R.
I I .6 Column Forms
5, column forms are frequently subject to much higher lateral
As explained in Chapter
pressures than walls because of their comparatively small cross section and relatively
high rates of placement. Tight joints and adequate anchorage at the base are required.
A template frame of 2x 4s or steel angles fastened to the completed slab are commonly
used to position and anchor the column form (fig. 11.61). Because of the confined space
in which concrete is placed, tall columns sometimes have pour windows at midheight or
other intervals to make placing and consolidating the concrete easier. A cleanout opening
may be provided at the column base for removal of waste or debris before concreting
begins. Fig. 1 1.6 1: Wood template nailed to slab
Columns may be round, rectangular, L-shaped, or of various irregular cross sections. positions a braced column form made of
I
rregular shapes are frequently formed by attaching blackouts inside square or rectan plywood, studs turned flat, and manufac
gular forms (fig. 11.62 ), and L-shaped columns may be formed like wall corners. Round tured column clamps (Photo courtesy Gates
columns may be built in wood, but ready-made forms of metal, fiberglass, or other and Sons, Inc.)
materials are more commonly used. Prefabricated panel system parts are also used to
form square or rectangular columns (fig. 11.63), and special techniques and materials
are used for custom fabrication of special column shapes.
Detailed descriptions are limited to some of the more common column forms built
by the contractor.Typical framing and sheathing members and yoke or clamp spacings
shown in the drawings are representative of actual practice, but should not be used
without checking the proposed application on the basis of design principles discussed
earlier. Temperature, rate of concrete placement, and column size influence the design. A
detailed analysis should be made to see that sizes and spacings are adequate for actual
job conditions.
rn
set in place either before or after the forms are in position, depending on individual condi
.
tions. For example, if there are any ties that pass through the form, the reinforcing cage
.
may be set in place and wired to the column dowels, then forms set in place around steel
. and ties threaded through. For heavy bars and large columns, it is common to build the
reinforcing cage in place, although prefabrication is still an option when adequate equip
ment is available for lifting and setting.
L-shaped
If the column form sides are assembled in place, the first one is aligned and tempo
rarily braced, then the others added and full bracing completed. The other method of
assembling the entire column first is preferred if equipment is available to lift the assem
bled form because it saves some of the work of temporary bracing. Some clamping
hardware allows the form to be handled in one piece for setting but to swing open for
stripping, as shown in Fig. 11.64.
A template is generally set in place on the floor slab or footing to locate the column
form accurately. Interior dimensions of the template should be slightly larger (approxi
mately 1/8 in.) than the outside measurements of the assembled form panel to make it
easier to fit the form into proper position.
During erection of column forms, assure noHtwisting"from the square or rectangular
cross section occurs. Some methods to overcomeHtwisting"include alternating the
direction of bolt members of yokes, or the direction of tensioning for certain types of
clamps. line and thickness tolerances will not control twist unless referenced to a grid
on the floor such as column centerlines. Column tolerances for width and thickness
should not be checked from a reference point on the column form or from a single point
Cut out corners
on the floor unless twist is also checked to be within its allowable deviation.
Fig. 11.62: Irregular column cross section If columns are formed, cast, and stripped independently ahead of the forming of
shapes ore frequently formed by using inserts other structural members-a fairly common practice to permit columns to take initial
within standard square or rectangular forms shrinkage-the column concrete will be cast slightly above the elevation of the soffit
of the lowest intersecting beam or slab. Some contractors allow about 1/2 in. of extra
concrete to cover vertical shrinkage and any irregularities, but the exact amount depends
on shrinkage properties of concrete mixture, size and shape of member, and local/envi
ronmental conditions. By placing a small amount above the soffit elevation, the beam and
slab soffit sheathing can be fit fully around the column and the column joint will be in the
Cutp•nellor
cleanout"door·
Fig. 11.63: Heavy-framed prefabricated Fig. 11.64: One of several proprietary column Fig. 11.65: One method suitable for forming
panels can be used to form square or recran clamping methods permits farm to swing light columns, up to about 12 x 12 in.
gular columns; note bracing in two directions open for stripping, yet remain in one piece for Plywood is backed by battens, which are a
handling and resetting (Image courtesy Gores part of the wood and bolt column yoke
&Sons, Inc.)
CHAPTER JJ
slab placement rather than exposed at the top of the column.
The form may extend to a higher elevation as long as the
casting elevation is controlled and if the form height will not
interfere with any projecting hooked column reinforcement.
Frequently, specifications require the contractor to remove
laitance from the top of the concrete after stripping and before
casting the next lift.
If columns are to be cast with the floor system, the column
form height must be coordinated with the floor system forming
elements for the slab and beams intersecting the column.
Because of irregularities in the finished slab at column loca
tions, the made-up panels are frequently cut 1/2 in. or more
shorter than the needed height, and then shimmed up at the
bottom or pieced at the top to exact height in the field. Exact
amount of height reduction depends on local field practice and
job conditions. Sometimes elevation is checked at the base and
any necessary correction indicated by a mark on the template,
or elevation may be checked at the top of the form to make
final adjustments.
Fig. I 1.69: Cross section of form for heavy pier-type column with heavy
duty external tie bolts and heavy steel wales
Fig. 1 1.71: Round column form built in wood may be lined with
Fig. 1 1.70: Steel form sections of various heights end-connected to plywood, hardboard, or steel; two halves of such a column form
achieve round column height ro be placed (Photo courtesy EFCO Corp.) are bolted together, then strapped or clamped externally
CHAPTER 11
a) Assembly of ribs cut to flare shape b) Attachment of sheathing cut in tapered strips c) Columns after stripping
Fig. 1 1.72: Fabrication of formwork for casting a flared column section (Photos courtesy MEVA Formwork Systems)
pockets are required when beam width is less than column width. Structural systems
such as flat plates, flat slabs having uniform depth drop panels, and beam systems with
beam width at least 2 in. greater than column width are easier to form than situations with
pockets.
When difficult forming situations are encountered, the top of the column form is often
made separate from the column proper to avoid remaking the form to fit varying sizes
of beams and girders that frame in, or to facilitate the use of prefabricated capital forms
of special shapes. The flaring "mushroom" capital sometimes used in flat slab designs is
commonly formed with ready-made units. The drop panel that surrounds it is formed as a
part of the slab.
Usually, the column will be cast separate from the floor and before the floor formwork is
erected. Concrete is placed only to the elevation of the soffit of the deepest beam or slab.
Forming the portion of the column within the depth of the floor system then becomes
part of the floor system formwork. B"mbottom•nghtty
However, in some cases, the column and floor system may be placed as one activity. For shorter th antrue dimension
columns into which beams and girders frame, beam pocket openings are cut in the top of and beveled
the column form panels. The opening is generally made slightly larger than the actual size .
Columns1de
of the beam to leave some room for adjustments as the final assembly is made in the field.
The beam bottoms and sides may be placed within the pocket or merely brought up flush
with it. In the former case, the opening must be cut to allow for thickness of beam side
and bottom forms in addition to the 1/4 to 1/2in. allowed for ease in assembly. The beam
pocket may be reinforced around the edges with 1 or 2 in. nominal thickness material,
which also serves to support the ends of the beam form.
The beam forms are also cut a little short of true dimension to allow some leeway in
assembly. These beam-column intersections are difficult to form, and it is easier to fit a
small closure piece or bevel strip in the field than to have to make saw cuts to enlarge
openings or shorten panels. One contractor reports success with a field-fitted metal
closure tacked on at beam and column intersection lines to cover any gap left by approxi Beam side
mate fitting of shop-built panels. Figure 11.73 shows another method of handling this
closure, using a wedge-shaped key that also facilitates stripping.
Fig. 1 1.73: Details of one type of beam
If the plan for form reuse requires reducing column widths, it is desirable to plan the
column form intersection, showing a wedged
original layout of the vertica12x4s so that the plywood can simply be ripped to the new
vertical key as closure piece; removal of the
width. Reductions in column height may be made by cutting short at the bottom if beam
key simplifies stripping the forms later
and girder pockets are to remain the same at the top. If column cross section remains
r
assembled in boxes prior to installation, or whether they
are handled as separate bottom and sides depends on
the lifting equipment available as well as the planned
sequence of form stripping. The following examples
Fig. 11.75: Alternate details for framing of beam-side intersection with slab sheathing show some of the many ways the forms may be built.
Size and spacing of members for an actual job should
be checked according to the principles outlined in
Chapters 7 and 8.
Figure 11.74 shows a typical interior beam form with slab forming supported on the
beam sides. This drawing indicates plywood for beam bottom and beam sides. Plywood
of the beam bottom is supported on transverse joists and extends beyond the beam sides
providing access for workers during form erection. Some builders use the full 4ft width of
plywood to avoid cutting the panels, thus getting more reuses of the plywood. Figure 11.75
shows alternate details for handling the intersection of beam and slab sheathing.
On smaller beams, kickers or knee braces may be sufficient to hold beam sides in posi
tion, or metal brackets may be used. Figure 11.76 shows beam form details with deck
forms supported on the beam sides. Use of braced shoring frames or a pair of braced post
shores (as in Fig. 11.74} for beam support is important for stability under the unsymmet
rical loading that occurs as concrete placement advances across the slab.
Fig. 11.16: Beam form details when wood Figure 11.77 shows a beam form resting on aluminum framing members with steel
joists are supported on ledgers attached to shoring frame support below. Aluminum beam supports for the slab forms bear directly
beam form sides on the beam side forms. Adequate bearing or lap at the aluminum beam ends is essen
tial to safely develop the full capacity of the section. Note that the uncut plywood beam
bottom extends well beyond the base of the beam, providing access for workers while
framing the rest of the decking (Fig. 11.78).
CHAPTER 11
of the beam bottom. Length of the beam bottom depends on how it is framed into the
supporting column or girder.
If it abuts a column face, rests on formworkjoist framing around the column face, or
rests on column or girder form sides, the bottom is made the exact clear distance, less a
fraction of an inch for leeway in assembly. The panel ends are usually beveled at the face
of the supporting member to facilitate stripping.
If the beam bottom is to be butted against column or girder sheathing, its length is the
clear span less total sheathing thickness of adjacent members at both ends {less a small
allowance for field fitting). The stiffening members may be cut several inches shorter
than the beam bottom sheathing if necessary to leave room for framing of intersecting
members. Ohen, however, they rest on a yoke or ledger around a column or girder ledger
that supports the beam form.
When beam bottom panels are assembled, they are usually marked with an identifying
code number or letters to indicate their location in the structure. Shore spacing required
should also be marked on the bottom to simplify accurate positioning in the field. A
chamfer strip {unless prohibited by the specifications) can be lightly nailed to both edges
of the beam bottom. At times, it is preferable to insert these in the field.
CHAPTER 11
formed independently of the slab. For deep
beams, ties like those in wall construction
are required. Their depth and spacing are
determined according to design principles,
depending on the rate and method of
placing concrete.
Spandrel Beams
Spandrel beams (Fig. 11.83) require careful
forming because of their critical loca
tion at the outer surface of the building,
where accurate alignment is the key to
good appearance, even though they may
be covered over with other materials.
Frequently, spandrel beams tend to move
toward the outside of the building due
to movement of the shoring system. It is
wise to monitor alignment during concrete
placement to see how much movement
occurs. It is commonly about 1/2 in. or
more. The spandrel outside form can either
be tied back to the deck or externally Fig. 1 1.82: Chamfer strips provide a beveled concrete corner, ease stripping, and help avoid
braced. Spandrel beams are frequently chippedconcrerecorner
deep enough to require ties through the
beam forms, and the ties must be placed DECK TIES
so as not to interfere with reinforcement or
the inserts that are common in such beams.
__._,.-������p ost
/ du n n 0
Dou os ;� f�:�i�:�:�r�����. t� j�ists are frequently not nailed to
shor s t
/ le
their supports. However, joists that are narrow in relation to their
depth must be prevented from turning under load; nailing or
Fig. 11.85: Slab form resting on beam ledger and stringers. For short
bridging is often used. Some contractors prefer to use 4x4s that
spans between beams, intermediate stringer and shore support may
do not have the tendency to roll, and thus avoid the need of
not be required
bridging or nailing.
CHAPTER 11
Slab sheathing is applied next (Fig. 11.86). Plywood sheets,
individual boards, hardboard, or boards cleated into panels
and laid on the joists are used. A few nails at the corners keep
the sheathing panels in place; however, additional nailing is
necessary when lateral buckling of joists is to be resisted by
nailing the sheathing along each joist. To further facilitate
slab forming, joists and sheathing can be prefabricated into
large panels. The entire area between the beams can then be
formed with a few large panels in a single operation without
setting the joists separately.
Where a slab load is supported on one side of the beam
only as at spandrel beams and at openings, edge beam forms
should be carefully planned to prevent tipping of the beam
due to unequal loading.
The details of the intersection of the slab decking and the
beam side require special attention so the panels will not
become keyed into the concrete. Keying can be prevented
by cutting the sheathing 1/4 to 1/2 in. short of the inside
face of the beam side form and beveling the sheathing
panel edge. This and alternate methods are shown in
Fig. 11.75.
Wire ties
Main reinforcement
Form
Fig. 11.90: Two methods of tie-down for fiber tube void forms (Drawing courtesy Sonoco Prod
ucts Company)
CHAPTER 11
Fig. 11.91: Installation of steel lap pans for Fig. 1 1.91: Workers installing wide-module
one-way joist slab; wider gaps at ends of pans (Photo courtesy CECO Concrete
pans and between pans indicate locations Construction, LLC)
of beams, narrow gap or midlength of pan
is location of distribution rib (Photo courtesy
Titan Formwork Systems)
Fig. 11.93:0ne typeofNiong"pan form thor Fig. 1 1.94: Flanged longform pan erection;
has flange clamped to flange of adjoining pan. adjustable wood shores will be positioned
This longer pan reduces the number of seams under flanges for support (Photo courtesy
and produces smoother exposed construction CECO Concrete Construction, LLC)
where ceilings are to be exposed. Flanges of these pans are typically 3 in. wide, with a
1-1/2 in. down-turned edge. Adjacent pans are butted directly to one another, creating a
6 in. wide joist. The edges projecting below are fastened with clamps at 1 ft intervals. The
pans can be manufactured to create other joist widths.
Fig. 11.97: Two-way joist slab forming with facilitates alignment. If wider joists are required, a chalk line should mark the outside edge
CHAPTER 11
A version of this method (Fig. 11.100) uses
cross-braced post shores instead of shoring
towers.
4. Tunnel form-Another version of the flying
form combines wall and slab forms with
necessary bracing and shoring in a single
unit called a tunnel form, for use in bearing
wall structures. Wall forms are hinged or
adjustable to move inward a small amount so
the form assembly can be stripped for move
ment to the next casting position. There are
systems consisting of a full tunnel and others
composed of two half tunnels. These forms
are similar to some used repetitively in rect
angular culvert construction, but instead of
moving only horizontally to the next posi
tion they are rolled out and Nflown" upward
Fig. 1 1.99: Slab form with castellated steel beams supported on column-mounted bracket
by crane (Fig. 11.101 ).
jack units; after concrete is placed and cured, form is lowered onto rollers, which are an
integral port of the bracket, then rolled out for flying to next position (Photo courtesy Brand
11.8.5 Adiustable Steel Beams
Energy & Infrastructure)
Adjustable steel beams, also termed horizontal
shores, are used over comparatively long spans
in slab forms without intervening vertical
shores (Fig. 4.13). This reduction in the number
of shores and leaving open spaces clear for
work is one advantage of horizontal shoring,
but it frequently results in much heavier loads
on the fewer vertical shores required. Conse
quently, greater care must be taken in lacing and
bracing the vertical shores that are used, and in
providing solid footings or mudsills.
Because of the greater concentration of load
at the vertical shore, more settlement due
to compression will take place when wood
supporting members are used, and ledgers
supporting the horizontal shoring should be
set at an elevation to allow for this. The prongs
of the horizontal shoring member should
also have a minimum bearing length on the Fig. 1 1.100: Lightweight system of flying forms uses extruded shores with keyways on
supporting vertical shore or ledger as recom four sides for bracing frame attachment; wheels on legs are replaced with screw jacks
mended by the manufacturer. after rolling into position (Photo courtesy Symons by Dayton Superior)
a) Half tunnel forms lower and fold slightly b) Top slab and walls with upset curb are cast in one placement
to strip
Fig. 11.101: Tunnel forms for bearing wall buildings can be used to cast walls and ceiling slab of room at the same time; forms clamp and seal at
upset curb for wall placement (Drawing courtesy Dayton Superior)
11-34 CHAPTER JJ
11 • 9 Shoring
11. 9. 1 Shore Layout and
Installation
Regardless of the type of shoring system
single-post wood shores, adjustable
shores, drophead shores, shoring frame
towers, or horizontal shoring-the layout
or plan should be worked out in advance
by the formwork engineer/contractor, with
consideration of possible stress reversals
in partially cured slabs when construction
loads are applied later. This danger exists
particularly when long-span horizontal
shoring is used on multistory work. A copy
of the shoring layout should be kept on the
project site at all times, and it should be
followed. If changes are necessary or desir
able because of field conditions, approval
of the shoring designer or engineer/archi
tect should be secured. Permissible tower
heights (for shoring frame towers) and
necessary external lateral bracing should Fig. 11.103:Collapse of shoring frame towers under wind load due to inadequate bracing and
be shown on the layout. Failures (Fig. overturning resistance (Photo courtesy Yenon Research &Design)
- -·
0
��
�
--..,,, ,
LOADINGADJAC EN T
//.......
-
SP.a.N CAN CAUSE
/'j...J ��=�
THISSPANTO 11 RESHOREORBACKSHORE
MOVEUPWARO
RESHOREOR ESINCE
BACKSHORE ISNOT
DIRECTLY B ELOW :�����;> 1, NEGA.TIVEOEFLECTION
•L. ,'
SHORING
1":"1
Ll L:l II
Fig. 11.106: Shore top end held in position by Fig. 11. 107: Positioning of shores and reshares from floor to floor can create bending and shear
shore holder nailed to stringer at interior support stresses for which the slab was nor designed
shear. The reversal of bending moments in the slab over the shore or reshore below may
occur as shown in Fig. 11.107. If reshores do not align with the shores above, then calculate
for reversal of moments. Generally, the moment induced by the slab dead loads will not be
reversed by the effect of having the upper shore offset in location from the reshore below.
Reshores should be prevented from falling by methods such as spring clips at the tops of
reshores (Fig. 1 1.108) and positively attaching perimeter reshores back into the interior
of the structure with appropriate lacing or bracing. When stripping formwork from under
slabs, the order of shore removal should be planned to minimize stress reversal in the slab,
as shown in Fig. 11.109. The reshoring plan and stripping plan should be submitted to the
engineer/architect for review related to effects on permanent structures.
When multi-tier single-post shores are used (one shore on top of another), OSHA 29
CFR1926 requires design of the system by a qualified designer and inspection by an
engineer qualified in structural design. OSHA also calls for vertical alignment, splices to
maintain alignment, and bracing in two mutually perpendicular directions at the splice
level. Diagonal bracing must also be installed in the two directions. Multi-tier single
post shoring in two or more tiers is considered by ACI347R-14, nGuide to Formwork for
Fig. 11.108: Spring clips nailed to top of
Concrete,ffto be a dangerous practice and is not recommended (Fig. 8.7).
reshare and initially fully compressed keep
All shoring members should be straight and true without twists or bends. Shores or
shore in place when slab rebounds upward as
vertical posts must be erected so they cannot tilt, and must have firm bearing. Inclined
concrete is placed on adjacent bays or shores
shores must be braced against slipping or sliding. Shores supporting inclined formwork
above are released
members should be firmly connected to the formwork after final elevation adjustments have
cu1l .�LL.!U]
been made. Splices, couplings, or joints should be secure against
m,
bending and buckling. Connections of shore heads to other
l
framing should be adequate to prevent the shores from falling
out when reverse bending causes upward deflection of the forms.
The importance of adequate diagonal bracing to the safety and
stability of the entire shoring system cannot be overemphasized
(see also Chapter 2). Diagonal bracing must be provided in both
vertical and horizontal planes to provide stiffness and prevent
STRIPPED IN THIS MANNER WITH CAUSE
STRESS REVERSAL IN THE MIDDLE STRIP. buckling of individual members of the formwork. For multiple-tier
shoring, high shoring towers, or any other high shoring, increased
ron• nrn
attention is required to provide bracing that will prevent sway or
lateral movement of shoring and buckling at splices.
Combinations of different types of shoring are not recom
mended because there may be a problem where two kinds of
shoring are used in a single bay or section of formwork. Tubular
steel shoring does not show a gradual set or buckling as vertical
-··--- . load is applied; rather it fails abruptly when a certain maximum
MIDDLE STRIP FIRST. THE SLAB WILL
DEFLECT AND BE LOADED AS DESIGNED
load is reached. Wood shores (particularly adjustable wood
shores) take an initial set when vertical loads are applied. When
Fig. 11. 109: Stripping sequence for one- and two-way slabs
the two types are combined for shoring a single bay, if the wood
CHAPTER 11
shores are not raised to allow for this initial vertical set, part or all of the concrete load can
be transferred to the rigid steel shores. Sudden shifting of load can overload these shores
and may cause collapse. Where tubular metal shoring is used on top of wood shores, the
two assemblies must be individually braced and individually stable, as complete structural
connections between the two are not practical.
CHAPTER 11
l
8. Check that the upper adjustment screw or shore head is in full contact with the form
work. If it is not in contact it should be adjusted or shimmed until it is.
r-'····�
9. Check that the obvious mistakes of omitting joists, using the wrong size ledger, or
incorrectly orienting members, have not been made. Check that the lumber used is
equal to that specified on the shoring layout. Check the general formwork scheme - >0"0.0.-
fLF----'Ij
10. lf the shoring layout shows exterior bracing for lateral stability, check that this
bracing is in place in the locations specified on the drawing. Check that the devices
that attach this bracing to the equipment are securely fastened to the legs of the
shoring equipment. If tubing damps are used, check that they have been properly
tightened. If devices for holding timber require nails, check that sufficient nails have � -20 114" I_;:: !---sand fill
been used to hold the bracing securely to the frame legs.
CHAPTER 12
the reinforcing fabricator during the detailing process {refer to ACI SP-66, HACI Detailing
Manuai-2004H).
Release agent or other coatings should be applied before steel is placed so the coating
material does not get on the steel where it could reduce or destroy bond between the
hardened concrete and its reinforcement. Most sleeves and inserts should be securely
fastened in place before steel is set, and bar setters should take care not to remove or
dislodge them. Pipe sleeves and inserts should be held in place by the minimum number
of nails or screws of the minimum size necessary to secure them during concrete place
ment (Fig. 12.6 and 12.7). When the forms are stripped, these nails and screws tear the
form surface, and may limit the life of the form sheathing. Some manufactured sleeves are
designed for attachment to minimize damage to form sheathing.
From the point of view of the form builder, the wall reinforcing should be attached to nails
in the forms as little as possible. Nails make stripping difficult and may cause damage to
form panels. They may also cause rust streaks later on the surface of exposed structures.
Another method of spacing vertical reinforcement mats is to rip long strips of 2 in.
lumber to the required dimension and insert them at intervals between the wall sheathing
and the steel mat before concrete is placed. The strips are raised as the form is filled, and
Toleronte on bor locot10n Toleronce DeV10t10n from position when closing the form, the curtain
meo�ured from formed on m1n1mum cro�s-�edionol may move upon withdrawal of the strips
Member toto! depth concrete �urfate contrete cover d1men�1on and result in reduced concrete cover.
Wheretotoldepthis4in +3/8in.,-1/4in. For some exposed walls, small concrete
:tl/4in -3/Si.
n
or less [except lor slobs) cubes with tie wire cast in them may be
Wheretotoldepthiso\'9r used as spacers to hold reinforcing bars at
z3/8in -3/8i.
n +3/8in.,-1/4in
4in. and n ol over 12in the proper distance from the forms. The
+ 1/2in.,-3/8i.
n short lengths of embedded tie wire are
Where o
l toldepthis more [but+ 1i.
n , -3/4 i.
n used to fasten the block to the reinforcing
:tl/2i.
n -1/2in.
thon 12in. ilmorethon 36in steel before the outside wall form is posi
depth )
tioned. Plastic spacers, often in the shape
of a wheel {Fig. 4.43), that snap onto the
reinforcing bars and need not be tied, are frequently used. They are non-corroding and
available in several shades of gray or white approximating the color of concrete.
Steel in columns can likewise be positively spaced at the proper distance from the form
by snap-on plastic spacers at three or four points as near top, bottom, and midheight
as possible. For such spacing, some erectors cast concrete donuts that are slid onto the
appropriate column verticals during assembly. Others provide wire slab bolsters of suit
able height tied on the erected column cage to bear against the formwork. Any practices
that hinder stripping or damage forms should be avoided.
Although side form spacers are still considered a �construction option; the Concrete
Reinforcing Steel Institute's Manual of Standard Practice•l.l describes them and includes
illustrations along with other bar supports. Special arrangements for estimating, detailing,
and furnishing side form spacers can be made with the reinforcing steel supplier.
CHAPTER 12
on form dimensions and on effective depth (-0 and+ 1/4 in.) is a wise precaution. The
same special tolerance of -0 in. and+ 1/2 in. is also advisable for thin structural slabs.
Examination of bar placing tolerances and concrete dimensional tolerances indi
cates no serious problem of additive tolerances at critical dimensions for spandrel
beams, ordinary interior members, and exterior members not designed to minimum
size. Special spacers on spandrel beams are sometimes used, however, to maintain the
desired cover. When placing slab or other bars, chalk marks may be made on the forms,
but a soluble gypsum chalk is desirable because regular keel or wax crayon will leave
marks on the finished concrete.
It is sometimes necessary or desirable to move an entire mat of steel into a better posi
tion by sliding it along the form, or a layer of slab bars may be lifted as a unit to permit
the insertion of bars underneath. This moving may be done with a crowbar or larger lever
Fig. 12.8: Comparison of tolerances for 12 in.
tools. large lever tools require that the fulcrum bear against something solid enough to
square interior column with No. 8 bars
take the heavy thrust. If bars are being raised from slab formwork, a temporary shore may
be needed under the fulcrum point. Care should also be taken not to damage the surface
of forms for concrete that will be exposed.
Basic Requirements
ACI 301-10, "Specifications for Structural
Concrete,n gives a simple performance
requirement for release agents:
�use commercially manufactured form
work release agent that reduces form
work moisture absorption, prevents
bond with concrete, and does not stain
exposed concrete surfaces.n
There are many proprietary form release
products, both barrier and reactive types,
and new ones are still being developed in
the wake of stricter limitations on VOCs.
Many can be used on a range of mate
rials, including metal, plastics, wood, and
plywood,m while some are designed to be
specially effective on a single form mate
rial. Table 12.3 provides comments and
Fig. 12. 10: Applying release in a fine mist before form erection with a portable sprayer, which precautions in relation to various form
can be hand-pumped or pressurized by a compressed air supply (Photo courtesy of PER/ Form facing materials. In addition to assuring
work Systems, Inc.) the release agent will provide clean, easy
release without damage to the form or
concrete, the contractor will have some other concerns:
Will it help produce a stain- and blemish-free concrete surface?
�= �:::� ��� t��:������;=��� �
c i t e fresh concrete and with surface coatings that
y � er
Does it require site mixing?
Will it be easy to apply at anticipated job-site temperature?
CHAPTER 12
Table 12.3: Release agent use with specific form materials
Comments and precautions
Application of release agent prior to each use will prolong wrvice life. Saturating wood with water and omining release
Wood
agent is sometimes sotisfoctory for surfaces to be plastered later.
Many plywood panels such as unsonded COX or sanded CCPTS, BC, and AC find their way into concrete forming appli
Plywood not mill-ciled cations. A form release suitable for such surfaces should be applied in advance of each use. Plywood service life and
concrete Finish requirements often influence release type selected.
BBOES and concrete form grade medium-density overlaid (MOO) plywood panels that ore factory-treated with o release
Semi<Jbsorbent, edga-seoled, and agent/all into this category. Reactive release agents have earned a reputation for providing the greatest durability for
overlaid plywood panels in this category. Avoid release agents containing castor oil if discoloration of concrete is a consideration. Seal cut
edges to prolong service life
Includes high-density overlay (HDO) and phenolic surface film (PSF) overlaid plywood and other proprietary non
Non-absorbent edge-sealed ond absorbent overlays or coatings. Sensitive to type, amount, and application rate of release agent; ovoid release agents
overlaid or coated plywood containing fuel oils, recycled oils, or solvents; refer to plywood manufacturer's recommendations; often reactive agents
ore recommended; seal cut edges to prolong service life
Use a release agent that includes a rust inhibitor. light applications of release agent ore essential to keep molds clean
and resulting concrete free of staining and release agent related pinholes and surface voids. Reactive or combination
reactive and barrier release ogenh ore more sensitive to how they ore applied, but they ore also more likely to produce
Steel
the best results when applied correctly. Most reactive release agents are not compatible with galvanized steel and
therefore should not be used on such surfaces. Refer to te)(t paragraph lor further di�ussion on problems with galvanized
forms and reinforcement
Aluminum is reactive with concrete and must be seasoned or coated with o suitable coating prior to being e)(posed to
fluid concrete. Highly reactive release agents are frequently used in combination with seasoning compounds to minimize
Aluminum (e)(truded and cold-rolled)
the potential for a reaction between the aluminum form surface and freshly placed concrete. Avoid products containing
wa)( or paraffin
Rigid plastics, including gloss fiber Refer to mold and release agent manufacturer's recommendations. light applications of release agent generally produce
reinforced plastic the best results on surfaces of this type.
Water-based release ogenh ore frequently used when mo)(imum durability is required; however, oi�bosed release agents
Elostomeric (lle)(ible) plastic liners con also be used. Refer to mold and release agent manufacturer's recommendations. Brush application sometimes neces
sary lor deeper te)(tures
light applications of chemical bond breakers such as those used in tilt-tJp or lilt-slob construction work well in this applica
Concrete molds tion. Reactive form release agents should not be used in this application unless the concrete mold surface has been pre
sealed with a suitable non-permeable coaling.
CHAPTER 12
Reporting and record keeping by the form f01111�TQI[�R£PORT
watcher can be encouraged and simplified
by providing a blank form watcher's report Job loatlon"--------
'":�=====
such as that shown in Fig. 12.12. Actual Phtenentducrfoto
t n: rlOOI''----- r-.enenl Contra c t or
points to be checked must be suited to job Pl•c-nt rUilber'---- r.e��er•l ton
tr . Supt_
conditions, and will vary for different types Coii.I'WI 11M r-eference''-----
of construction. SUrtlng tl
Scopeof
1 KUIDmtnt:
T:neoflfOI"k tlefngoou�
1ubcontractor's
�������������
work
Typeofforuworkorstructure to wnlcn
ACI SP-2, MManual of Concrete Inspection," subcontrutor'swork Is fr•eci•-------
and the Bureau of Reclamation Concrete CI:n!1ents ong ener1l contr.ctor� fr.nlng'------
completed or forms built. If dimensions and _WedQesundtrsnorestlgllt&r.allecl _[q\llpnent awoilable lnuse ofntedfor
adjust��entorre1Rforcenent
stability are satisfactory, the contractor may _Silol"1nglllr0wirt!Stcured
_EJtraJICki
then clean the foundation or oil the forms and _Silhsolld ongrourd orshb
_Ett.-. lilciii!J
may install any reinforcement and fixtures. _L.clngln�hlled. Oitenrequlred
_E•triSilol"ts
_P•n� nslled
Semi-final or cleanup-When everything
CI!ec1for tprudrnwhen requlredln
is in place for concreting, a detailed inspec _
jotstoans __P�<�rrenged $1gnol wllh COIIC�le plt<:lg
n
tion of forms, reinforcement, founda- rorerwn to stoD OCHJr In entrQtnt)'
_Plywood ju1nt� nu s�
tions, and all equipment or parts to be - ��� ����a!�� wnerr literal _CIIeckforooss1bltl!'x1troute slncau
_C!Jtockshor
e
sfOf'Pll.mb
_FJ:�c�'!�� !::'19�:��! ���:': � f
uuedecl
have not been displaced. Surfaces must be
_Telltahslnol ace.,.,dNrlc�lll:ert
clean and, if specified, must be wetted. re
qul,.d
.. by £upedntell<lent
CHAPTER 12
The inspector should check to see that the form sheathing or lining can reasonably be
expected to yield the desired or specified finish. The inspector should also be sure that
wetting, oiling, or other specified form treatment has been adequately performed before
concreting, and that there is no form coating on the reinforcing steel.
CHAPTER 12
toad, unless provision has been made to allow for anticipated temporary construction
loads, such as in multi-story work (refer to Chapter 6).1n no case should forms and shores
be removed from horizontal members before concrete has reached the strength specified
by the engineer/architect for form removal.
Strength of concrete necessary before form stripping and the time required to attain it
vary widely with project conditions. Generally, forms for vertical members such as walls,
columns, and piers may be removed earlier than those for beams and slabs. Even when
concrete is strong enough to show no immediate distress or deflection under load, it is
possible to damage corners and edges during stripping and to develop excessive creep
deflection with time. The engineer/architect who designed the structure and understands
its behavior under load is best prepared to decide what strength is required for stripping.
If strength tests are to be the basis for the engineer/architect's instructions to the
contractor on form removal, the type of test, method of evaluating, and minimum stan
dards of strength should be stated clearly in specifications. The number of test specimens
as well as who should make them and perform tests should also be specified. Methods
for monitoring early strength gain of concrete in the field are discussed in Chapter 6.
Reference 12.6 can also be helpful in evaluating various methods. The most widely used
method has been to test cylinder specimens cured on the job site under conditions no
better than the least favorable curing conditions for actual portions of the structure which
Fig. 12. 19: External vibrators can enhance
the test specimens represent. If such specimens are used, it is advisable to keep a curing
conrere consolidation when vibration is
record including time, temperature, and method for both the concrete structure and the
activated in suitable planned patterns (Photo
test specimens. This information, together with the weather record, will assist both the
courtesy Wacker Neuson Corporation)
engineer/architect and formwork engineer/contractor in determining when forms can
be safely stripped. Specimens that are relatively small are
more quickly affected by freezing or drying conditions than
concrete in the structure, and because of their greater ratio
llliJ!��r'.�
of exposed surface to volume, the strength is frequently
lower than that of concrete in the structure. Thus, they offer
a conservative basis for determining stripping time. As
discussed in Chapter 6, ACI301 lists four alternative ASTM
test methods:
Field-cured cylinders attached to forms;
Penetration resistance;
Pullout; and
Maturity measurement.
While the convenience of the last three methods is most
attractive, and they are applied to the actual structure
instead of an approximately equal sample, they do not
measure compressive strength directly. Calibration data are
required for the given concrete mixture before any useful
inference can be made regarding strength of the concrete
tested.
Strength testing is the preferred method for determining
the appropriate time for form removal. However, when the
contract documents do not specify the minimum concrete
strength required at the time of stripping, the engineer/
architect should be consulted and the methods discussed
in ACI301 should be used for determining appropriate
form removal criteria. The elapsed times shown in Table
12.4 may be used as guidance for determining stripping
time for general planning purposes. The times shown
represent a cumulative number of days, or hours, not
necessarily consecutive, during which the temperature
of the air surrounding the concrete is above S0°F (10°C).
For high early-strength concrete, these periods can be
reduced as approved by the engineer/architect. Conversely,
if ambient temperatures remain below 50°F (10°(). or if
retarding admixtures are used, then these periods should
be increased at the discretion of the engineer/architect. Fig. 12.20: Placing concrete for floor system first in beams and then slab,
Shorter stripping times listed for live load to dead load vibrating both internally, and screeding to desired elevation (Photo courtesy
ratios greater than 1.0 are the result of more reserve CECO Concrete Construction, LLC)
CHAPTER 12
larger weight and surface areas of flying forms and ganged panel units that are handled
by crane present some difficulties in achieving the desired gradual removal, and special
devices and techniques may be needed. Most form systems include lifting devices for
attaching crane hooks. Manufacturer's recommendation must be followed for attachment
to the forms and lifting device capacities. Generally, vertical forms should be broken loose
from the concrete first and then picked by crane. Using the lifting devices for the stripping
process may overload and damage the devices or the formwork. Forms should be lifted
level and plumb above their center of gravity.
Considerable damage can be done to formwork that has not been planned for orderly
dismantling. The sequence of stripping is a consideration in how the forms are to be made
or assembled. To avoid interference between systems, columns and walls are usually formed,
placed, and stripped before erection of floor system forms. If, for example, columns are to
be placed with the floor system, column forms should be made so that they can be stripped
without disturbing adjacent beam and girder forms. Column panels can be pried out from
the bottom so that they can drop down free of beam forms. Beam and girder side forms may
be made to come out before slab soffits. The formwork engineer/contractor should provide
for crush plates or key strips to facilitate removal at difficult form intersections or where
there is danger of damage from stripping tools. Small form openings to permit introduction
of air or water under pressure sometimes simplify stripping {Fig. 12.23). Bottled nitrogen has
also been used to break forms loose where large form areas required pressures not available
from the normal construction site compressor.
Special attention required for removal of large ganged panels or flying forms is frequently Fig. l 2.21: Proper use of screw-type top (a)
planned in advance. For example, hinged parts of the form can be released before the entire and bottom (b) leg adjustments on shoring
form is moved. Jacks may be used for support and adjustment so that the form can be members makes it easier to set forms at
gradually freed by loosening the jacks. If it is necessary to let a slab form fall free, a platform correct elevation and later to lower forms
or other support should be placed to reduce the drop to a minimum distance. Special hard gradually without shock to structure
ware {Fig. 12.24) can be developed to help
out when forms stick and refuse to drop as
planned. Ingenuity of the workers on the job
often plays a major part in a successful strip
ping operation.
When stripping large wall form sections,
it is advisable to leave a few ties connected
until the crane has a secure hold, thus
preventing it from breaking loose acciden
tally. Faster stripping of wall gangs can be
accomplished by attaching a line to exert
an outward pull at the same time the boom
hitch is pulling upward; however, this prac
tice introduces additional safety concerns
that must be recognized and addressed.
Special considerations for stripping
architectural ornament or long-span thin
shells and similar structures are discussed
in the section on structures or techniques
to which they relate {architectural concrete,
Chapter 14; shell structures, Chapter 18).
Time devoted to training the strip
ping crew in the order and method of
form removal will be well spent. Strip
ping requires considerable care on the
part of workers to avoid damage to the Fig. 12.22: Careful stripping and handling pays off by keeping form panel corners and edges
green concrete, which can be marred by straight and true (Photo courtesy MEVA Formwork Systems)
scratching and chipping even though
it has sufficient structural load-bearing strength. The contractor should take care to
protect the concrete and extend the useful life of the forms by careful handling. Not
only must the forms hold together but they must also remain dimensionally accurate,
and edges should stay in good condition to make accurate alignment and clean joints
possible.
Form panels and shoring components should not be dropped but should be handed
down or lowered on stretched ropes, cables, or other devices to avoid damage. Various
12.6 Reshoring
Reshores, as defined in ACI 347R. are shores placed snugly under a stripped concrete slab
or other structural member after the original forms and shores have been removed from
a full bay, requiring the new slab or structural member to deflect and support its own
weight and existing construction loads applied before installation of the reshores. Such
Fig. 12.24: Steel pan form is supported during reshores are provided to transfer additional construction loads to other slabs or members
stripping by a rack on a forklift while worker and/or to impede deflection due to creep that might otherwise occur. Reshoring facilitates
on scissor lift and worker with a pole pulling maximum reuse of the formwork, making use of the strength of completed construction
device pry the form loose (Photo courtesy below as well as the partial development of strength in the member being reshored. When
CECO Concrete Construction, LLC) using drophead shores, the shores become reshores after the forms are stripped and the
shores are later released to activate the slab and then re-snugged to support added slab
construction loads {fig. 12.25).
Premature reshoring and inadequate size and spacing of reshores have caused a
number of construction failures. Because reshoring is such a highly critical operation, it
is essential that the procedure be planned in advance and approved by the engineer/
architect. Detailed instructions {or prohibitions) regarding reshoring may be written into
the project specifications, or the time and sequence of reshoring may be made subject to
engineer/architect approval.
When the study of form removal and reshoring is being made, the live loads for which
the completed structure is designed, as well as the actual strength of the partially cured
concrete, must be considered. Allowance must also be made for any additional Jive and
dead loads to be imposed as construction continues. The reshoring system must be
designed to carry all loads that will be imposed {refer to the example in Chapter 6). Often,
the critical limitation on temporary construction loads will not be strength but
avoidance of excessive deflection and cracking.
CHAPTER 12
locations, spacings, and the type of
reshores to be used are influenced by story
heights, speed of construction, type and
structural design of slabs, and spacing of
columns. Under proper conditions, metal
shores, 4 x 4 wood shores, or 6 x 6 wood
shores can be economically and safely used
as reshores. As is true for original shoring,
wood and metal reshores should not be
mixed at the same slab level.
All reshoring members must be straight
and true without twist or warp. Reshores
must be plumb and adequate in capacity.
When placing reshores, care should be
taken not to preload the lower floor and
also not to remove the normal deflec
tion of the slab above. The reshore is
simply a strut and should be tightened
only enough to hold it securely in place.
In no case should wedging or jacking be
permitted to lift a slab above its formed
position to the point of causing cracking.
Excessive wedging will change the load
distribution to various floors supporting
the shores and may easily relieve one and Fig. I 2.25: Formwork beams and panels are lowered by dropheads for reuse while shores
overload another. remain in place supporting early low-strength concrete until slab strength is sufficient for shore
Operations should be performed so to be retracted and then re-snugged (Photo courtesy MEVA Formwork Systems)
that at no time will areas of new construe-
tion be required to support combined dead and construction loads in excess of their
capacity as determined by design load and developed concrete structure strength at
the time of stripping and reshoring. While reshoring is under way, no new construc
tion loads should be permitted on the new construction unless the new construction
can safely support the construction loads. For high story heights, adequate provisions
should be made for lateral bracing of shores and reshores during this operation. Multi
tier shoring using single-post shores in two or more tiers is a dangerous practice and is
not recommended (refer to Chapter 11). Where possible, reshores should be located in
the same position on each floor so that they will be continuous in their support from
floor to floor. Where slabs are designed for light live loads or on long spans where the
loads on reshores are heavy, care should be used in placing the reshores so that their
loads do not cause excessive punching shear or reversed bending stresses in the slab.
Shores resting on intermediate slabs or other construction already in place need not be
located directly above shores or reshores below, unless the slab thickness and the loca
tion of its reinforcement are inadequate to take the reversal of moments and punching
shear. The reversal of bending moments in the slab over the shore or reshore below may
occur as shown in Fig. 12.26. Reversal of
moments must be considered if reshores
do not align with the shores above. Gener
ally, the moment induced by the slab dead
loads will not be reversed by the effect of
having the upper shore offset in location
Deflection and stress
from the reshore below. Reshores should pattern as designed
be prevented from falling by such means
as spring clips at the top of reshores and
positively attaching perimeter reshores
back into the interior of the structure
with appropriate lacing or bracing. The
reshoring plan should be submitted to the
engineer/architect for review related to
effects on permanent structures.
The use of expandable horizontal Fig. 12.26: Deflection and stress patrern at centerline of a flat slab column strip as designed
shores and large truss-supported flying (above) may be changed significantly by placement of a single line of reshoring (below).
CHAPTER 12
may require some light tapping with a hammer, but this can be carefully done to avoid
breaking fibers and damaging the form face.
Any open seams in panels should be filled, warped boards planed, and metal facings
straightened to close the joint. Plywood panel faces of prefabricated forms may be
reversed on the frame or replaced if badly damaged. Tie holes may be patched with metal
plates, corks, or plastic materials. Plywood nicks and gouges may be patched with poly
ester resin auto body putty.
Cleaning knives, steel scrapers, and wire brushes are satisfactory for use on steel
panels, and mechanical cleaning devices (Fig. 12.28) are sometimes used on large proj
ects. Metal forms should not be sand-blasted or abraded to a bright surface, as this may
cause sticking.
As soon as forms are repaired and cleaned, they should be coated with form oil or other
preservative (some of these coatings are described in Table 12.3). Steel forms should be Fig. 12.28: Gasoline-powered equipment for
oiled on the back as well as the face to prevent rusting and sticking of spilled concrete. cleaning steel form panels; panels placed on
With some coatings, a curing or drying period is required before the forms can be stacked a conveyor are pulled under a rapidly rotating
steel wire brush; faces ore cleaned and oiled
on one another.
and panels emerge at opposite end (photo
Following any necessary drying period for the coating material, the forms should be
courtesy EFCO Corp.)
stacked off the ground on 2 in. or heavier lumber at a slight pitch for runoff (unless indoor
storage is available). It is preferable to place strips of wood between wood forms to
promote evaporation of moisture. Panels should be stacked according to sizes and types
to simplify handling; they should be arranged so that any code markings can be read
without further moving. Old forms may be placed on top to protect the newer ones from
sun and rain.
Plywood sheets, before or after use, should be stored out of mud and water and
supported across the panel at three points. They should be covered loosely to protect
from rain or snow while permitting the plywood to breathe.
Careful techniques recommended for stripping should carry over into handling to
prevent chipping or denting edges. Forms should be piled face to face and back to back
for hauling; they must not be dumped or thrown from a truck, but should be passed from
worker to worker for stacking. On-site stacking of panels and components varies with the
superintendent and site conditions. Orderly storage {Fig. 12.29) will obviously do much to
reduce loss and damage and to prevent panels from being used for other purposes.
Dimension lumber, as well as form panels, may be saved for reuse, in which case it
should be scraped free of concrete deposits, and all nails removed. It should be sorted by
sizes and stored off the ground in a location that will minimize weathering and rotting
(Fig. 12.30).
Reusable form hardware requires careful
handling, or it will become a costly item
through losses or deterioration. Boxes or
buckets should be kept on hand to store
small parts as they are stripped. Parts can
be soaked in a mortar solvent to loosen
hardened concrete, and wire-brushed or
pressure-washed afterwards. Some reac
tive release agents, in their concentrated
form, will soften the buildup of hardened
concrete. Mechanical brushing is some
times used where large numbers of parts
are to be handled.
CHAPTER 12
material from wind, rain, snow, or other
wetting that will impair its insulating
value. Closed-cell material is particularly
advantageous because of its resistance to
wetting. Insulation must be kept in close
contact with concrete or form surfaces to
be effective. Remember that the exposed
steel frames may carry heat away from
the concrete and cause localized freezing
damage to concrete surfaces even when
surrounding areas are insulated.
Where practical, the insulation mate
rial should overlap any previously placed
cold concrete by at least 1 ft. Where tie
rods extend through the insulated form,
a 6 x 6 in. plywood washer can be placed
on top of the insulation blanket and
fastened securely.
Use Tables 12.5 and 12.6 to select the
necessary thickness of insulation for walls
and slabs aboveground, considering
concrete mixtures of different cement
contents placed at different air tempera
tures.Table 12.5 is based on use ofType I
cement.lfType II cement is used, increase
the tabulated insulation requirement by
approximately 30%.
Data in Table 12.5 are based on a
concrete placing temperature of 50°F
with wind less than 15 mph, assuming
the insulation is applied directly to the
surface of steel forms. If plywood forms
are used, add the insulating value of the
plywood to that of the insulation itself to
get a combined R-value that can be used
in applying Table 12.5. See Example 12.1.
Heated enclosures (Fig. 12.34 and 12.35),
although generally more expensive than
other protection, are recommended by ACI
306R as being the most effective.They can Fig. 12.32: Forms for a large bridge pier with insulating blankets attached to form faces (Photo
be made of various materials, such as wood, courtesy EFCO Corp.)
mtijfiitjfll#·""' !.!'!®fii!.lr
Suppose 3/4 in. plywood forms have an inch of plain expanded polystyrene
(extruded) added for insulation of concrete placed at 50°F, with a cement content of
400 lb/yd. What is the minimum surrounding air temperature permitted for 3 days
minimum protection of an 18 in. thick wall?
The polystyrene has an R of 4.00 and the plywood has an R of 3/4 times 1.25, or
0.94, for a total R of 4.94.
According toTable 12.5, an R of 4 gives protection adequate for a temperature
of 12°F, and an Rof 6 insulates for a temperature of -6°F. Because the R-value for
plywood plus polystyrene calculated previously is roughly halfway between, one can
estimate that this insulation would be adequate for a temperature (halfway between
tabulated values) of 3°F.
For higher wind velocity or longer duration of protection, recommendations of ACI
306R should be consulted. Because corners and edges are particularly vulnerable to
heat loss, insulation of these parts should be approximately three times the thick Fig. I 2.33: Example method of attaching insu
ness required for walls or slabs. Remember that insulation must be provided on both lation to vertical form, showing corner derail
sides of the wall or slab, unless one face is within a heated enclosure. and plywood washers used around tie rods
canvas, plastic, or insulating boards. Enclosures made with flexible materials are cheaper
and easier to build and remove, but more rigid enclosures are more effective in blocking
wind and maintaining perimeter temperatures. They should be designed to withstand
wind and snow loads. If insulated forms are used together with heated enclosures, it is
advisable to monitor the interior as well as the surface temperature of the concrete, so
that neither concrete temperature nor temperature differential exceed allowable values.
Refer to ACI 306R and ACt 207.4R-05, MCooling and Insulating Systems for Mass Concrete
(Reapproved 201 2),�for additional information. The possibility of fire hazard must be
considered and when fossil-fueled burners are used, the combustion products must be
vented outside the enclosure to avoid a reaction with the fresh concrete. Winter weather
conditions may also require removal of snow and ice from forms (fig. 12.36).
In addition to insulating the formwork to conserve heat, or heating an enclosure to
surround and protect concrete while it cures, it is possible to add internal heat directly
to the concrete by means of low-voltage current passed through insulated embedded
coils or to apply heat through the forms to the concrete surface. Several proprietary
systems are available, although their use for cast-in-place work has thus far been relatively
limited. One method makes use of electrical resistance wires built into fiberglass rein-
CHAPTER 12
forced plastic forms containing a hollow
heat chamber. Another uses radiant heat
directed onto metal form surfaces. A third
method involves 1/8 in. thick electrical
heater modules laminated of steel and
fiber-reinforced plastic; these modules can
be attached to or laid against steel form
surfaces. All of the heated forms elevate
temperatures of the concrete to a level of
accelerated curing that permits early form
removal. For most efficient operation, they
are supplemented by insulation to retain
the heat.
Fig. 12.34: Temporary enclosures of construction areas; at left polyethylene sheeting encloses
heated space below slab placed on metal deck; at right, blue plastic sheeting on steel studs
provides a heated space below the concrete floor being placed and a wind break above (Photo
courtesy EFCO Corp.)
REFERENCES
12.1: Placing Reinforcing Bars, 10-PLACE, ninth edition, Concrete Reinforcing Steel Insti
tute, Schaumburg, ll, 2011, 288 pp.
12.2: Manual of Standard Practice, 10-MSP, 28th edition, Concrete Reinforcing Steel Insti
tute, Schaumburg, ll, 2009, 144 pp.
12.3: Hurd, M. K., NContractors' Guide to Form-Release Agents; Concrete Construction,
Sept. 1999, pp. 18-29.
12.4: Hurd, M. K., NDusting of Formed Concrete Surfaces, N AC/ Journal Proceedings, V. 65,
No. 9, Sept. 1968, p. 720.
12.5: U.S. Bureau of Reclamation, Concrete Manual, eighth edition, 1975 (revised 1981),
627 pp.; available from http://www.usbr.gov/pmts/materials_lab/concrete/.
12.6: Harrison, T. A., NFormwork Striking Times-Method of Assessment, w Report 73,
Construction Industry Research and Information Association, London, UK, Oct. 1977, 40 pp.
13: FORMED CONCRETE SURFACE
QUALITY
One goal of the construction team is to produce as-cast concrete surfaces that meet the
requirements of the project specifications. Accomplishing this goal requires that the
specifications have unified definitions of the different concrete surfaces that are to result
from the construction process. Several standard specifications exist, and there is an effort
to integrate an improved method of formed concrete surface specification and evalua
tion. In this chapter, the provisions of ACI 301-10, �specification for Structural Concrete,"
ACI117-10, �specification for Tolerances for Concrete Construction and Materials,# and
ACI 347.3R-13, "Guide to Formed Concrete Surfaces,.. related to formed concrete surface
quality, are summarized. For architectural cast-in-place concrete, also refer to the addi
tional discussion in Chapter 14.
.. .. . .
Class A Surface................................................ +1/8 in.
Class B Surface ... ......... .... ......................... +1/4 in.
Class .. . . . . .. . .. . . . .
Class C Surface . .. ......................................... +1/2 in.
D Surface .. . .. .. .. .. .. . .. .... . . .. ... . .. +1 in.
Abrupt irregularities are to be measured within 1 in.
of the irregularity (Fig. 13.1 a). Gradual surface irregu
larities are to be measured by determining the gap
a) between concrete and near surface of a s ft straight
13-2 CHAPTER 13
13.1.2 As-Cost Surface Finishes
ACI 301 lists three types of as-cast surface and their criteria as follows:
Surface finish-1.0 (SF-1.0):
No formwork facing material is specified;
Patch voids larger than 1-1/2 in. wide or 1/2 in. deep;
Remove projections larger than 1 in.;
Tie holes need not be patched;
Surface tolerance Class D as specified in ACI117; and
Mockup not required.
Surface finish-2.0 (SF-2.0):
Patch voids larger than 3/4 in. wide or 1/2 in. deep;
Remove projections larger than 1/4 in.;
Patch tie holes;
Surface tolerance Class B as specified in ACI117; and
Unless otherwise specified, provide mockup of concrete surface appearance and
texture.
Surface finish-3.0 (SF-3.0):
Patch voids larger than 3/4 in. wide or 1/2 in. deep;
Remove projections larger than 1/8 in.;
Patch tie holes;
Surface tolerance Class A as specified in ACI 1 1 7; and
Provide mockup of concrete surface appearance and texture.
If surface finish is not indicated in the contract documents, the defaults are SF-1.0 on
concrete surfaces not exposed to view and SF-2.0 on concrete surfaces exposed to view.
CHAPTER 73
Features such as approved tie holes are not counted as voids. Voids with a diameter less
than 3/32 in., or less equivalent area than a circle of that diameter, are not counted. If voids
have a diameter greater than omo,. or greater equivalent area, the surface is evaluated and
a procedure is developed for repair of the deviation.
From Fig. 13.3b, it becomes apparent that voids have a variety of shapes. Some are
round, some are oval, and others are amorphous. For those that are round or slightly oval,
the area Av can be calculated from the average diameter as the area of a circle, A,.= '!{d2/4.
Table 13.8 provides areas for various diameters in the range of the criteria to simplify tabu
lation of total area. For other shapes, the area can be approximated based on a rectangle
having length and width of the void, as shown in Fig. 13.4.
A,=i X w
i = length Fig. 13.4: Average dimensions of void shape at
w =width concrete formed surface
In arriving at the length and width (Fig. 13.S), the objective for sizing the rectangle is to
have approximately as much void area falling outside as non-void area falling within the
rectangle. See Example 13.1 for an example of void area criteria evaluation.
The images in Fig. 13.6 provide views of concrete surfaces to aid understanding of the
concrete SVR determined in accordance with Table 13.3. These images are only provided
as examples. The overall evaluation process of ACI 347.3R provides detailed descriptions
for evaluating the single criteria and the overall impression of a given concrete surface.
The SVR is only required to be determined if the entire impression of the surface does not
meet the contract expectation or the single criteria exceeds the limits in Table 13.3.
13.2.2 Specifications
Before writing the specifications, the engineer/architect should determine the desired
appearance of the concrete surfaces and the design features the contract documents
should describe. In the contract documents, the engineer/architect chooses and speci
Fig. 13.5: Measurement of surface void
fies the expected CSC appearance and features for each specific area. The contractor
dimensions
determines the means and methods, material type and quantities, and associated costs
to achieve the specified concrete surface
finish.
The specifications should consider
constructibility, cost, and achievable expec
lrtfftfflfJFHii1iffit·ffiWI§'6
The framed area shown in the figure
tations, and describe the desired look of the has a count of 215 voids with an
formed concrete surface. In addition to CSC, average diameter ;?:3/32 in. and none
contract documents should include surface with a maximum diameter greater
features such as requirements or criteria than Om4< = 1/4 in. The total void area
related to form-facing category, formwork was found to be 2.01 in.2 According to
joints, tie holes, panel size, panel arrange Table 13.3, the determination would
ment, texture, color, chamfer, rustications, be SVR3. If other criteria were met, this
reveals, reglets, drip strips, control joints, would indicate CSC3 if an absorbent . '
expansion joints, and reinforcing bar spacer form facing had been used and CSC4 if
form contacts.
J
a non-absorbent form facing had been
Required mockups should be constructed used.
under site conditions and should have the
following minimum goals:
Validate the means and methods to be
used by the contractor; and Example wall test area
. ' .. � .,
. , .
. .
(c)CSC3 (d)CSC4
Fig. 13.6: Images representing CSCI to CSC4 without sense of scale or viewing distance
the actual structure, the engineer/architect should approve in writing a mockup for that
portion. Mockups are retained and maintained until the structure has been completed
and the concrete surface finishes have been accepted by the owner or engineer/architect.
An area in an existing building may be used as a reference area only and not as a
mockup because it is almost impossible to reproduce an area in exact detail. A mockup
should be created to illustrate the contractor's ability to reproduce the appearance of the
existing structure used as a reference. Construction should conform to the selected refer
ence surfaces and fulfill the contract requirements.
The specifier should recognize that some characteristics of surface finish cannot be
absolutely controlled, are difficult to control, or can only be partially avoided. Some objec
tionable characteristics can be minimized if the work is executed properly. These charac
teristics and limitations are discussed in ACI 347.3R.
CHAPTER 13
Fig. 13.7: Example formed surface appearance shop drawing
formed concrete surface. The use of formed surface appearance drawings can help convey
the desired appearance of formed concrete surfaces by indicating all applicable features,
such as tie hole treatments, textured surfaces, fluting, fractured fins, sandblasted surfaces,
geometric patterns, wood grain, exposed aggregates, reveals, rustications, construction
joint appearances, integral color, form joint appearances, and modularity or any other
characteristic of the surface that affects the intended visual appearance of the finished
work. •
Figure 13.7 shows an elevation of a finished wall and a plan view of a wall formwork
layout using job-built formwork. Tie hole (Fig. 13.8) and form joint patterns (Fig. 13.9) are
shown in the elevation.
The requirements for the formed concrete surface can only be met if it is possible to
place and consolidate the concrete properly. Consultations are often held between a
formwork engineer/contractor and the engineer/architect during the facility design stage.
Fig. 13.8: Sealed tie hole for execution of CSC3
Formwork design and construction considerations should include:
and CSC4 (Photo courtesy MEVA Formwork
1. Anticipating conditions that can result in air becoming trapped during placement
Systems)
and making provisions for venting of the air or modifications made to the concrete
placement method to avoid surface voids.
2. Evenly arranging pouring windows and making sure they are of sufficient size to
permit concrete placement when needed and allowed. Consider the locations and
forming details of pouring windows in CSC2 and CSC3. Pouring windows are not
recommended for CSC4.
'
FORMED CONCRETE SURFACE QUALITY 13-7
3. Verifying that spacers for reinforce
ment will not affect the appearance
of the finished surface by either
corroding, protruding; or being
recognizable at the formed concrete
surface, especially in CSC3 and CSC4.
4. Reviewing contract documents
to assure they maintain adequate
concrete cover at recesses, reveals,
flutes, or other locations where the
nominal concrete section is reduced,
or when the section may be reduced
by subsequent mechanical texturing.
5. Giving careful consideration to
the method of installation and the
aesthetic layout of inserts and embed
ments in CSC3 and CSC4.
6. Reviewing building elements to
assure they are dimensioned and
Fig. 13.9: Formjoint visual pattern (Photo courtesy MEVA Formwork Systems)
designed in such a way that the
concrete can be placed and consoli
dated without difficulty.
7. Consulting with the engineer/architect on the possibility of a reduced surface quality
requirement or the use of self-consolidating concrete where the shape and the
dimensions of the building elements, openings, or both, will result in difficulties in
placement and consolidation.
8. Designing the concrete surface to shed rainwater to avoid staining the concrete
surface for surfaces subject to weathering.
CHAPTER 13
Before each use, examine the condi�
tion of formwork and facing for imper
fections or damage that may produce
an unacceptable surface; repair or
replace as necessary and properly
store the formwork.
b. Ensure that the tolerances and char
acteristics of the formwork materials
used provide the required appearance
within specified tolerances.
Evenly tighten ties and seal if neces
sary; over-tightened ties can result in
depressions around the tie hole.
d. Depending on the CSC, the edges of
cut-to-size plywood may need to be
sealed and factory-sealed edges may
need to be checked and resealed to
achieve the required concrete surface
at the panel joints.
Seals, using silicone or compressible
closed-cell joint tapes, can reduce the
Fig. 13.10: lnconsistenr facing material can lead to color and texture variations (Photo
likelihood of leakage at the facing,
courtesy MEVA Formwork Systems)
form panel joints, or both, including
construction joints. The use of foam
tape, caulking, or both can become problematic after
the initial form use. Residual release agents remaining
on the forms may affect the tape or caulk adhesion. If
joint sealing or taping is required, it should be specified
in the contract documents.
Keep porous plywood or other porous facing materials
moist to minimize swelling and shrinking.
g. Avoid using new and old plywood sheets or sheets
from different manufacturers adjacent to one another,
or both, as different sheets (Fig. 13.10) could have an
effect on the final appearance of the concrete surface.
h. Carefully choose release agents and use in accordance
with manufacturer's instructions and spray, spread, or
spray and spread the release agents in even, thin layers
unless otherwise directed. Wipe off excess release
agents (refer to Fig. 13.11 ).
When locating concrete placement windows or other
temporary openings in formwork, avoid areas of
congested reinforcement. Consider the concrete's
finished appearance when selecting the location of
temporary openings because such openings will most Fig. 13.11 Concrete surface resulting from excess form release agent (Photo
likely leave a form imprint on the finished surface. Make courtesy MEVA Formwork Systems)
temporary openings large enough to allow the use of
internal vibrators with minimal contact with reinforcement and form-facing material.
It is difficult to attain completely tight forms unless joint sealing strips are installed
between each panel. This document attempts to address these issues and provides
limitations to the form gap and mortar leakage. The language of Table 13.2, Classifi
cation T1-T4, is intended to be consistent with ACI 301-10, which states that mortar
loss should be controlled and minimized. If mortar loss causes reinforcing bar cover
issues, patching may be required.
Other factors that impact formed concrete surface are side-form spacers for reinforce
ment, installation of inserts, the concrete mixture, and the concrete placement procedure.
These factors are further discussed in ACI 347.3R.
When CSC3 or CSC4 are specified, it is important to establish a concrete surface team
to ensure the coordination of the construction progress and management of infor
mation flow between the parties involved before and during construction. Roles of
the team members should be clearly defined. The team can discuss and resolve open
CHAPTER 13
Cl
�
"0
t'l
"
�
�<::
,� � ,
I I I I Tl
Co"""" .odo'"' ; w;� low .;,;b;l;�
j
o
I I SVRI
I SVRI I CUl I CU
I Sll CJl
I Optional I FCl low
� . ur , uMid
0 � or covered with 5ubsequent fino5h motenols
�
"'
=i
CSC2
I �t�::�::::��';,,:�:� visual appearance is
I T2 I SVR2
I SVRl I CUl I CUl
I Sl2 CJ2 I Optional I FCl
I Average
lcu2lcu2l
Com::rele surfc:lces that ore in public view or
� 1
CSCJ
I �
where appearance is im r nl, !ouch os e,.;te-
�
rior or interior expo!.ed bu,ldmg elements I TJ
I SVRJ
I SVR2 SIJ CJJ
I ����
reco ded
I FC2 High
u
�� I
lcu21cuJI
Concrete surfaces where the e11posed
concrete is a prominent feature of the
completed structure or visual appearance is
T4
I SVR4 I SVRJ Sl4 CJ4
Should be
required
FCJ
I Veryhigh
important
•For matching requiremen t s of formed concrete surfacecate9<)ries. refer toTables 13.2 through 13.7.
'lheappearanceof theformedconcretesurfaceshould onlybeju dgedin it s entirety,notbylookingat separatecrite.iaon�.Thefailureof oneagreedcr�erion accmding to thi s guide
shoul d not resultin theobligationto repair deviation s if theoverall positivelmageofthe structureorthebuil ding i s not di sturbed
'The general impres sion of existing or not existing diswlorations <;an usuallybe seen on� after a longer period of timea n d for at lea st8 week s. The uniformityof the coloring ha s to be
judgedfrom thewmmonviewing di stanceaccording toACI347.3R,Chapter7.
Acceptable gaps in adjacent lormwork components �1/2 in.; refer to Section 13.2.4.j.
·Acceptable depth of mortar loss �3/8 in
.Acceptable surface ofhets of panel joints up to 1/2 in. A
( CI 117-10, Section 4.8.3, Closs C).
T2
-Allowable projections 1/2 in. from adjacent surface
· Form-lacing material examples: Closs BBOES plywood, MOO plywood
Imprints of modular panel frames ore acceptable
·Acceptable gaps in adjacent formwork components �1/4 in.; refer to Section I 3.2.4.j.
·Acceptable depth of mortar loss � 1/4 in
-Acceptable surface offsets of panel joints up to l/4 in. A
[ CI 117-10, Sedon 4.8.3, Closs 8).
!3
Allowable projections 1/4 in. from adjacent surface (ACI 301-10, Section 5.3.3.3.b)
· Form-facing material examples: HDO plywood, phenolic surface film, full plastic, or steel.
· Imprints of modular panel frames ore acceptable
· Formwork should be grout-tight; ovoid grout/mortar leakage ond correct where it occurs.
·Permissible surface offsets of panel joints up to 1/8 in. A
( CI 117-10, Section 4.8.3, ClossA)
- Form-lacing material examples: HDO plywood, PSF plywood, lull plastic, steel, and fiberglass.
- Imprints of modular panel frames ore unacceptable unless demonstrated and approved in the mockup
· Void area not to exceed 1.2% · Void area not to exceed 1% · Void area not to exceed - Void area not to exceed 0.3% of
of the test area of the test area 0.6% of the test area the test area
Standard lormwork and place- - Release agent should be In addition to the efforts In addition to the efforts described
ment practices should yield compatible with the form-facing desoibed for the SVR2 for the SVR2 and SVR3 categories:
these results without ony special material. category
·Concrete design and formwork
effort.
. Formwork should be cleaned -Adequote vibrotion should eliminate surfaces that inhibit
-This SVR category limitation prior to the opplicotion of should be provided, the upward movement of entrapped
Suggested concrete place- should not apply to permanently release agent. especially ot leolures, oir.
men! practices to yield concealed concrete surfaces openings, and embeds.
-Apply release agent thinly -Placement rote should consider
desired results
ond uniformly. - Concrete mixture vertical ascent rote of entrapped oir
consistency is important during consolidation.
-A mockup might be
in achieving reproduc·
beneficial -Use methods of deposition that
ible results.
minimize ogitotion ot the surfoce
-Use revibrotion method that introduces entrapped oir
at top lilt.
-Mockups ore required.
-Mockupsore
recommended.
"Vood area os the summatoon of the areas of all voods wothon the sample Sp.lce of 24 x 24 on, Voods wnh �n �ver�ge do�meter of d < 3132 on. are excluded from the cakul�!lon of the vood area
Note: lfth�e criteri� are made�ppliuble to the project, then the mockup should demonstrate the ability of the contr�ctor to meet the SVR expected for these surf�ces. The gener�l appearance of
the �nal structure should be compared with the general -"suaI �ppe�rance of the mockup.
CHAPTER 13
Table 13.4: Description of visible color uniformity• on as-cast formed surfaces
-Dis.colorolions caused by concrete rource material of different kind and origin; different types or treatments of facing material$; or incon
CU3 sistent lreolmenl of concrete surfoces ore unocceptoble.1
·Rust stains, dirt stains, and visible pouring layers oro unacceptablo.
"Color uniformrtyrs subje(:tove�nd the e•pen,mons for uniformrtyshould be addres!oed before construction
'Concrete color deviations and discolorations cannot be completHyelimiM!� �n using�� best practic� If this is� concern, in addition to a mockup, use a reference structure of similar silt
and finish
'An approwd mockup of the surface is required; even the best practic� and quality control may result in minor color deviations 1nd discoloratioos.
Table 13.6: Description of visible construction and facing joints• on as-cast formed surfaces
-Acceptable offset of surfaces between Two adjacent placements �118 in. Offsets less than 1/8 in. need to be specified in design
documents
CJA -The use of chamfer strips or similar reveals ore recommended at construction joints.
-Construction joint locations should be coordinated with architecltJrol design and approved by architect or engineer.
-The mockup should contain all feotures representative to the finished product.
•constructionjojntsthat remainvisible
'Cemem residue is a thin film remaining on the form face. 19/32 0.277
'Perform and inspect reP<� irs of form facing and IT\i'lke acceptable for the intended formed concrete surface 5/8 0.307
14: FORMWORK FOR ARCHITECTURAL
CONCRETE
Architectural concrete has a twofold purpose. Not only does it serve as the structural
material, but it also becomes an architectural medium by providing the desired surface
finish. Therefore, special care is needed in the design and construction of its formwork.
Imperfections of all kinds will be open for inspection. Varying light conditions will empha
size fins, sheathing joint marks, crooked corners, "pillows," bulges, and other irregularities.
Facilities designed to incorporate concrete as a visually important feature can vary greatly
in magnitude {Fig. 14.1 and 14.2); however, the objective is consistency of the desired
visible formed concrete surface.
This chapter, along with information already presented on materials and accessories
in Chapter 4 and on methods of classifying and specifying formed concrete surfaces in
Chapter 1 3, indicates some methods of forming architectural concrete to obtain speci
fied formed concrete surfaces. Most of the general principles of formwork design and
construction discussed in Chapters 7, 8, and 1 1 also apply to architectural concrete form
work. The items that require special consideration for architectural reasons are discussed
herein.
Although formwork quality is a critical consideration, it must be emphasized that
architectural effects achieved in concrete surfaces may be affected by factors other than
formwork. Types or brands of cement; sources of coarse and fine aggregates; and lack of
uniformity in mixing and placing techniques, slump control, curing methods, time, and
temperatures may significantly affect color and texture of the exposed surfaces despite
meticulous care in the production of the formwork. Helpful information on these consider
ations is provided in ACI 303R-12, "Guide to Cast-in-Place Architectural Concrete Practice.�
ACI 303R recommends a general criteria that architecturally acceptable concrete
surfaces should be aesthetically compatible with minimal color and texture variations Fig. 14. 1: Arhitectural concrete emphasizes
and surface defects when viewed at a distance of approximately 20ft or more, as agreed consistency of concrete surface (Photo courtesy
upon by the architect/engineer, owner, and contractor, or as otherwise specified. ACI DOKAUSA)
347.3R-13, uGuide to Formed Concrete
Surfaces,M provides guidance on a system
for specifying formed concrete surfaces
as discussed in Chapter 13. Section 6 of
ACI 301-10, "Specifications for Structural
Concrete," defines requirements for archi
tectural concrete.
Fig. 14.2: Architectural concrete for auditorium complex {Photo courtesy PERl Formwork If the types are combined, certain
CHAPTER 14
A preferred approach, where the budget
permits, is to include a field mockup
(sometimes referred to as a preconstruc·
tion mockup or a test bent) as part of the
construction contract. The purpose of
the mockup is to confirm the specified
materials and methods and to demon
strate the contractor's ability to produce
the desired architectural finish. The field
mockup (fig. 14.3) is a full-scale sample
of selected portions of a project's archi
tectural concrete, usually built at the
project site by the successful bidder before
starting construction of the major work.
The mockup must be large enough to show
architectural concrete portions of concern,
such as floor, wall, and column construc
tion. Mockups are made full-scale to exhibit
and validate vertical and horizontal form,
form liner, or rustication joints, reinforce·
ment placement problems, and effects of
accessories. For walls, the mockup should
include a minimum of two lifts having
Fig 14.3: Mockups of trial wall, column. and ceiling concrete surfaces, including visual appear-
once, tie hales, rusticationjoints, recesses, and penetrations (Photo courtesy Morley Builders)
heights planned for separate placement.
The engineer/architect may indicate a
section or sections of the building that typify the most difficult areas to build. Specifying
a preconstruction mockup prepared and finished by the contractor for approval by the
architect-using proposed form materials, jointing techniques, and form surface treat
ments, such as wetting, oiling, or lacquering-should be a requirement for all architectural
concrete. Once such a mockup has been completed to the satisfaction of the architect and
owner, it should remain at the site for the duration of the work as a standard with which
the rest of the work should comply.
All forming materials and construction practices used in producing the mockup are
those planned for use during actual construction of the project. Proper vibration and
re·vibration techniques should be defined at this time because they will significantly
affect appearance of the concrete. The mockup should also include a simulated repair area
and patched tie holes to show that satisfactory color and texture match can be achieved.
Patches should be aged at least a month to give a true indication of the final color.
The mockup, viewed at an agreed-upon distance, provides a basis for written approval
by the architect and owner of the finished product before the architectural concrete work
begins.
BIM is being used for a virtual mockup by some contractors as a preliminary step before
the field mockup. An example is shown in Fig. 14.4. Through a virtual mockup, it is possible
to more clearly show joint locations, appearance of rustications, and details that are
formed in the concrete surface such as chamfer intersections, coves, and rounded corners.
The model can help reach agreement on various details that may not have been apparent
in the architect/engineer drawings. The BIM mockup is also helpful in communicating
requirements to field workers who will build forms for the field mockup. Contractors have
found that the process sometimes allows agreement to use a less-visible portion of the
actual structure to serve as the mockup. This reduces costs of building a mockup that is
not part of the structure and must be disposed. While the BIM virtual mockup can even Fig. 14.4: BIM virtual mockup of beam and
show intended surface textures, it cannot represent the construction process that yields column details (Images courtesy Klarman
the actual consistency of surface texture, surface voids, and color. Construction)
CHAPTER 14
14.2.3 Formwork Details
location, number, and details of such items as openings, control joints, rustication lines,
and expansion joints should be indicated by the architect/engineer on design drawings.
The formwork engineer/contractor uses this information to prepare details on the form
work drawings showing how these features are to be executed. Recommendations are
given later in this chapter for accessories, closure techniques, concealment of joints in
formwork materials, and sealing the forms to make them watertight for uniform surfaces.
Mortar-tight joints prevent the formation of projecting fins. Why, then, the concern over
watertight joints for architectural concrete?The uniform appearance of the concrete can
be disrupted due to a condition called hydration discoloration-variations in total water
content of concrete and moisture movement within concrete during setting can cause
variations in color of concrete. Also, when water containing cement particles leaks from
the forms, a blemish may appear that contains more than the usual amount of aggregate.
There may be streaking, mottling, or darker appearance as a result of less water available
for hydration of the cement. Loss of water alone at comparatively tight form joints can
cause the hydration discoloration, as can other conditions inherent in placing operations,
such as pumping action at the interface between concrete and form during vibration, and
bleeding near the top of lifts.
Hydration discoloration occurs in the concrete to a considerable depth and cannot
ordinarily be concealed by abrasive blasting or tooling the surface. Forms must be made
as watertight as possible to minimize the problem. Taping, caulking, blocking, backing,
gasketing, or interlocking formworkjoints may be necessary. Using lower-slump concrete
helps to reduce leakage, too.
Pressure-sensitive tape may be used on the inside of forms when further treatment of
the surface is planned. Care is needed to prevent displacement or wrinkling of the tape,
because this results in difficult-to-remove blemishes. Brush-applied gum adhesive over
the tapes has successfully held them in place. Taped joints should be inspected before
placing concrete to be sure the tape has not moved.
Form sheathing or linings should be as uniform in absorbency as possible because
hydration discoloration can be caused even by subtle differences in the absorbency
of adjoining pieces of plywood that have been used a different number of times. Even
smoothly taped form joints can sometimes be·read•in the finished concrete surface
because of the difference in absorptiveness of the tape.
CHAPTER 14
Fig. 14.7: Concrete ceiling coffers for Notional
Gallery of Art East Building were formed with
are often used to fasten the sheathing.
sanded fir board sheathing (Photo courtesy
Regardless of whether the nails or screws
Bevin E. Johnston)
are flush, recessed, or raised, they will be
visible on the concrete surface unless they
are recessed, filled, and sealed to prevent uneven moisture loss. Back fastening should be
used if the imprints from nail or screw heads are objectionable.1H
Boord Sheathing
If sheathing lumber is selected to build smooth-surfaced forms {Fig. 14.7), dressed material
is a necessity and tongue-and-groove or shiplap is desirable. The need for dressed lumber
comes from the desirability of having boards that can be easily and accurately placed.
They also must fit tightly to minimize the formation of fins.
A common problem in the construction of forms with sheathing boards is the difficulty
of keeping horizontal joints between the boards level. Sheathing lumber, even when
dressed and matched, is not always perfectly uniform in width, and joints can easily get
out of alignment. Irregularities in driving up adjoining boards may also aggravate this
condition. It is therefore necessary to check the level of joint lines at frequent intervals.
To do this, lines of levels may be set at 3 or 4ft vertical intervals. The lines can be readily
followed by carpenters if they are marked on the studs at 3 to 4ft intervals along the
length of the form.
Other Materials
When plywood or hardboard serves as a sheathing material or liner, full-size sheets are
preferred. Joints should be constructed to fit tightly. For best appearance, the joints are
caulked (Fig. 14.8), filled, or taped.
Metal forms and liners give a smooth surface, but the joints between the units are hard
to conceal. If metal form units span the total distance between control joints or architec
tural features of the structure, the joints between the units will be less noticeable. The size
of metal form panels can often be chosen from among a range of standard sizes avail
able so that there is an even number of panels or a symmetrical pattern on each face of
the architectural concrete. If such a pattern is acceptable, the joint marks will not require
concealment and costs are reduced.
When horizontal joints are required in metal lining, the sheets can either be butted or
lapped about 1/2 in. If a lap joint must be made in the lining of a vertical form, the inner
sheet of the lap should be the upper one (Fig. 14.9) so that the slight step in the concrete Fig. 14.9: Liner overlap direction to minimize
will not cast a shadow that calls attention to the joint. sun shadow effect
CHAPTER 14
mortar from getting behind the flutes. This practice facilitates ease of stripping, as does
keeping the flutes precisely parallel. It is important for the concrete to gain adequate
strength before stripping to avoid breaking fluted edges.
Use of fully sealed hardwood strips will help avoid swelling problems. If strips are lightly
nailed to the forms, they will pull away when forms are stripped, leaving the wood to be
removed after the concrete hardens. When using any kind of wood feature strips, there
is the possibility of saccharides having a detrimental effect on the concrete surface. The
saccharides can cause retardation or a lack of hydration of the concrete in contact with
the wood, even if the strips have been coated with a form release agent. This can result in
nonuniform appearance and excessive surface dusting. If using wood fluting, it is a good
practice to apply a sealer to the strips, unless it is certain that the wood will not have this
affect.
The main advantage of elastomeric strips is that they can be easily pulled from the hard·
ened concrete. Tightly stretched lengths of rope have been used in the same way as the
elastomeric strips, and they produce a considerably more ornamented concrete surface.
Corrugated sheet metal and corrugated glass fiber building material may also be attached
to forms to obtain regular fluted surfaces. However, some of these methods can be labor
intensive and difficult to reproduce consistently.
Thus, plastic form liner systems that produce continuous corrugations, from deep rib
trapezoidal shapes and undulating curves to a variety of striations, have become popular
(see Fig. 4.11 ). Liner panels come in various widths and in lengths to fit full placement
heights. Interlocking edges that conceal joints in the material are available from some
manufacturers. liner panels release rapidly and cleanly from the concrete, and the better
quality ones are suitable for numerous reuses. Flexible (elastomeric) liner materials can
also be used.
Exposed Aggregate
Several methods can be used to expose aggregate on the surface of architectural
concrete. A concrete set retarder can be applied to the forms so that after they are
stripped, the mortar between the surface aggregate particles can be washed or brushed
away. Another method is the aggregate transfer method,1u in which aggregate is
attached to the form with an adhesive. After the concrete has been cast, the forms are
removed, leaving the aggregate embedded in the concrete because the bond to the
concrete is stronger than the bond to the adhesive. Both methods work best when panels
can be precast with the finished surface down; otherwise, control becomes difficult. Care
and experience are required to achieve uniform results on vertical cast-in-place surfaces. A
mockup or series of mockups is recommended for vertical exposed aggregate surfaces.
Retarders can be formulated to achieve varying depths of etch or exposure of aggre
gate. The retarder must be applied uniformly to the form surface, avoiding runs on vertical
surfaces because they lead to nonuniform exposure of the aggregate. Concrete may
be placed any time after the retarder has dried. If placement of concrete is delayed, it is
important to protect the typical retarder from dew, rain, or other moisture that would
activate the retarder prematurely. However, some rain-resistant retarders are available. The
use of heat or accelerators during cold weather may also affect the action of the retarder.
Experimenting to determine the effect of heights of placement, form stripping times,
and methods of exposure should be done on the preconstruction mockup or in some
unexposed part of the structure, such as basement walls. ACI 303R recommends a
minimum concrete strength of 1000 to 1500 psi before removal of the retarded surface.
Because the retarder and part of the retarded surface may adhere to the forms, it may be
desirable to use a special form release agent that causes the retarder and retarded matrix
to stay on the concrete, thereby reducing form cleaning costs.
Other methods of aggregate exposure include abrasive blasting, mechanical tooling,
and high-pressure hydroblasting at 10,000 psi or higher after forms are removed. An even
simpler, older method of exposing aggregate is to use flowing water and a stiff vegetable
brush, stripping forms as early as possible, sometimes 12 to 24 hours after casting the
concrete. Just as for retarded surfaces, there is a high risk of nonuniform results unless
consistency is achieved with respect to timing and craftsmanship.
Effectiveness of any exposed aggregate surface depends on proper choice of aggre·
gates and mixture proportions, as well as special attention to vibration practices. There
must be a sufficient amount otwell-distributed aggregate near the surface to be exposed.
Fig. 14.1 1: Rustication joints create visual patterns (Photo courtesy Olympic Panel Products LLC) or geometrical (fig. 14.13), strips or blocks
attached to the forms may be sufficient
for forming the shape or decoration. Best
results are generally achieved with a pattern or mold that is beveled and free of undercuts
for easy stripping; however, even this requirement may be eliminated with flexible mate
rials or single-use shapes of rigid foamed plastic that can be chipped, brushed, dissolved,
or blasted away from the concrete after the forms are removed. If patterned molds or
inserts are used, they should be aligned and kept level to give continuity to the overall
pattern (Fig. 14.14). Symmetry with respect to liner seams and matching the modularity of
the liner are important work practices for good visual results.
A number of suppliers produce brick and concrete masonry pattern form liners and
several manufacture reusable wall form panels with the masonry design an integral part
of the form sheathing. Some of these forms are capable of producing a surface that can
be painted or stained and be virtually indistinguishable from brick at ordinary viewing
distance.
Rigid plastic foams, particularly polystyrene, can be used to create complex form liners
with repetitive over-all patterns or one-of-a-kind original works of art. Desired plastic
shapes may be cut or molded, then nailed or glued to form sheathing. Multiple cutting
machines facilitate rapid production of unique patterns for one-job use. Cut edges of
plastic foams have open cells that may cause bonding to concrete unless a coating or
membrane seal is applied over the cut surfaces.
If molded or sealed plastic is coated with a release agent, forms can be stripped and,
according to some suppliers, reused. Others working with the same type of foamed plastic
expect that it will bond to the concrete and must be destroyed during removal-scraped,
chipped, dissolved, or sandblasted away. One proprietary process treats cut shapes with
sealers, pigments, or other materials, and as soon as concrete is cured makes use of a
solvent that liquefies the plastic foam and deposits a glaze on the concrete.
The method of removal of plastic liners depends in part on site labor and form fabrica
tion costs, but also on the shapes of patterns being formed. Dissolving the plastic makes
possible patterns of almost incredible delicacy but requires an environmental plan for
disposal of the effluent. Chipping or abrading away the plastic makes it possible to form
undercut shapes from which other types of form could not be removed. Molded shapes
coated with form release leave smooth concrete and minimize stripping labor.
CHAPTER 14
Fig. 14.13: Visual pattern formed in cast-in Fig. 14.14: Alignment ofjoints and rustica
place water tank structure (Photo courtesy tions is critical to appearance (Photo courtesy
Landmark Structures) MEVA Formwork Systems)
the panels are to serve structurally as forms, they should be suitably reinforced to resist
anticipated lateral pressures from the fresh concrete placed behind them. Erection and
bracing to resist wind and other lateral forces must also be considered. If they function
merely as stay-in-place liners, they may be of lesser strength and thickness. Recommenda
tions for design and fabrication of form panels of concrete are given in Reference 14.6 and
in Section 9.7 of ACI347R (see Appendix).
In addition to the factors recommended by ACI347R, the potential effects should be
considered of differential shrinkage or creep between cast-in-place concrete and precast
forms for columns and bearing walls. Control of cracking in architectural surfaces is also
important. This may be achieved by keeping concrete stresses below the modulus of
rupture or by lightly prestressing the panels.
The panels are fabricated with lifting inserts and anchors to
attach them to the cast-in-place concrete. When the panels are
to be used as exterior forms against which concrete is cast, form
ties may be attached to embedded anchors, reinforcement,
or inserts provided in the panels for that purpose (Fig. 14.1 5),
or ties may be installed at joints between panels when suit
able backing and provision for precise alignment of the panels
is made. Any embedded metal that remains exposed to the
elements after the structure is completed should be made of
noncorrosive material.
At the intersection of horizontal and vertical jointing, a
temporary bolt through blocking is used to assure holding
corners of all four slabs in the same plane during casting of
concrete. Wales may be used on the concrete form face to main
tain alignment. Rate of rise of concrete in such forms should
be limited according to recommendations of the manufacturer
of the panels. Thorough consolidation of concrete behind the
forms is desirable to prevent voids that would interrupt the
bond of the form to the concrete, but sufficient care must be
exercised to prevent damage of concrete panels by contact
with vibrators. If horizontal construction joints are made about
3 in. below the top edge of precast concrete form panels,
instead of on the form panel line, the possibility of water
leakage through the construction joint will be reduced. Fig. 14. 15: Wall form assembly showing how precast concrete panel
serves as one face of the form
14:4.1 Walls
Wall forms for architectural concrete are built the same as for structural concrete, but more
attention is given to alignment, perfection of corners, the contact surface, and especially
to treatment of joint location (Fig. 14.16). All wales should be constructed of two members
with joints staggered to minimize deflection. Minor defects in alignment and construc
tion, which may not be objectionable in structural work, show up badly in architectural
concrete. It is difficult to get good alignment with wood wales or strongbacks when rigid
CHAPTER 14
Fig. 14.16: Tight form joint intersections produce well-defined edges (Photo courtesy Morley Fig. 14.17: Sheathing quality for reuse must
Builders) be higher to produce uniform architectural
concrete surfaces (Photo courtesy Morley
Builders)
tolerances are required. Substitution of lightweight steel studs, steel or aluminum chan
nels back to back, or laminated veneer lumber will give much better alignment.
Any amount of care exercised in securing good horizontal and vertical alignment is time
well spent. One method for aligning a long section of forms is to set points about 30ft
apart on the floor with a theodolite or total station. These points may be set 3 or 4ft back
from the face of the wall to be well out of the way. Alignment at the top of the wall can
then be accurately set by plumbing up from the floor points and measuring over to the
wall. Intermediate points are set from a chalk line on the floor between the control points.
Aligning of forms is best done when there is little wind.
Ties
Form ties for architectural concrete require special consideration. Marks left by the ties can
detract from the finished surface or they may become an integral design element in the
finished fa�ade (fig. 14.21) when properly executed. Tie holes should be bored from the
inside of the forms whenever possible to prevent the formation of burrs on the contact
face. The smallest possible hole should be used to prevent mortar leakage. Special care
should be taken during stripping so the concrete is not broken around the tie holes.
The ties should be adjustable to permit tightening of forms and should leave no metal
Fig. 14.21: Tie ho/es/ocated tobecomepart closer than 1-1/2 in. to the surface for steel ties and 1 in. for stainless steel ties. Any lugs,
of the visual design (Photo courtesy Morley cones, washers, or other fittings, if permitted, should not leave depressions of a diam
Builders) eter greater than their depth at the exposed surface of the concrete if the hole is to be
CHAPTER 14
patched. The mortar plug is less likely to become loose and leak if the side slope of the
recess hole is smaller. Twisted wire or band iron ties should not be permitted. Some
specifications also prohibit snap ties that are not fitted with spreader cones because of
the difficulty in controlling depth of breakback. When breakback can be controlled, some
architects may prefer the small holes left by snap ties without cones.
If ties do not fit tightly, holes should be sealed to prevent leakage. Tie layout should be
planned so as to be symmetrical with the member formed; and, wherever possible, ties
should be located at rustication marks, control joints, or other points where the visual
effect will be minimized unless the tie hole pattern is part of the architectural effect. Ties
penetrating a liner should be selected for visual effect and sealed at the penetration so
concrete cannot migrate between the liner and the substrate.
Where the architect specifies ties such as pencil rods, taper ties, or other bolts that are
pulled out after use, they should be coated with nonstaining bond-breaker or encased Fig. 14.22: Fiberglass ties colored to match
in sleeves to facilitate removal. These ties should incorporate positive spreading devices concrete and aligned in rusticationjoints to
instead of relying on wood spreaders that are removed as concreting progresses. Occa further minimize visibility after final trimming
sionally the architect may specify externally braced forms to eliminate surface blemishes is completed (Photo courtesy RJD Industries)
associated with ties, or go to the other extreme of emphasizing tie holes as part of the
surface design. Fiberglass ties (fig. 14.22), sometimes colored to match the concrete, can
be cut off flush with the surface.
CHAPTER 14
average project. The method of support is
the same as pictured for spandrel forms.
1 4.4.4 Soffits
If the underside of a concrete slab, beam,
or arch is to be exposed to view, either
painted or as bare concrete, extra care in
form preparation, jointing, and sealing
will be required (Fig. 14.27 and 14.28).
Flat surfaces may be formed with steel,
plywood, board sheathing, or other mate
rials; however, coffered or ribbed ceilings
are frequently selected for exposed areas
for structural as well as aesthetic reasons
(Fig. 14.28). Glass fiber-reinforced polymer
pans and dome forms-both standard and
custom sizes-have become popular for
this application because of the generally
good quality of the off-the-form finish,
favorable stripping characteristics, and
easy handling due to light weight. These
forms can be trimmed or adjusted in the
field to meet special forming requirements.
Custom-made spandrel and other beam
forms of glass fiber-reinforced polymer
are also used to achieve improved surface
finish and reduce site labor.
Exposed ceilings and beam soffits require
formwork that is kept clean and free of
rust deposits when concrete is placed.
Mill scale may flake off the reinforcing as
it is placed and accumulate on horizontal
form surfaces. If reinforcement or metal
scrap remains in position for some time
before concreting, rust may be deposited
on the soffit form and leave a stain on the
concrete. Compressed air or water jets are
sometimes used to clean surfaces of loose
rust. For highest-quality work, consider
using reinforcing bars that are resistant to
surface corrosion if they must be exposed
on slab forms for a lengthy time before
concrete is placed.
Fig. 14.17: Erection of soffit form for arch (Photo courtesy Morley Builders)
1 4.4.5 Cantilevers
Because canopies and other cantilevered structural members are such conspicuous archi
tectural features, it is particularly important that their forms provide adequate support
to maintain architectural lines. In designing the forms, the formwork engineer/contractor
will allow for any expected settlement or deflection of the forms themselves, while the
architect/engineer will specify any camber needed to compensate for deflection of the
member after forms are removed. If no camber is specified in the contract documents, the
contractor should request guidance from the architect/engineer to help them realize the
risk of a sagging span of concrete.
One or more checks should be made before concreting to be sure that proper camber
is provided. Any needed adjustment of the form by jacking and wedging must be made
before concrete placement. Adjustment of form elevation during or after concrete place
ment should not be performed. The upper surface of a cambered slab or beam should
be screeded as nearly parallel as possible to the cambered form surface, so that a level
surface results when the structure deflects. As with other soffit formwork, measure
ments of elevation to check compliance with the specifications should be made after
the concrete sets but before forms and shoring are removed. Full, continuous support
Wood Mold,
Wood molds are made of white pine, soft vertical-grain Douglas fir, or other softwood run
to size and shape in a commercial mill or a form shop with the necessary shapers. Molds of
wood are well adapted to ornamentation on belt courses, cornices, and other long details;
for such purposes, the mold is made up of several long moldings or strips run to the
needed shape. It should be made of material that does not warp or split easily. Combina·
tions of standard moldings are used whenever possible.
Special attention must be given to joint construction. Objectionable fins will be formed
in the concrete if the mold joints are not mortar tight. Each joint should be sealed with
caulk, tape, joint compound, or a compressible gasketing material before the concrete is
cast.
Longitudinal joints between the mold members should be made by overlapping at
reveals or returns whenever possible (Fig. 14.29).1f butt or miter joints are used, alternate
shrinking and swelling may open them to cause fins in the finished concrete. When joints
occur where there is no return or reveal, tongue-and-groove lumber or shiplap should
be used. Joints may also be splined or biscuited. Butt joints can be used when the pieces
are attached to a solid backing that prevents distortion of the mold due to swelling or
shrinkage of the pieces. Brackets of 2x4 and 1x6 material cut to the approximate shape of
the cornice are preassembled and scabbed to studs. Cornice form parts are then attached.
CHAPTER 14
If transverse joints between successive pieces on a long
wooden mold all occur at the same place, they are easily
detected in the finished concrete, and there will be a distinct
break in continuity that weakens the mold. Staggering joints
overcomes both of these problems, and small joints can be made
almost invisible by sealing.
Because wood swells when wet, the mold must be built so that
this property will not distort the mold or open joints. Swelling
may also break the newly formed concrete. Thin, narrow boards
should be used because they warp and swell less than thick,
wide boards. They also save lumber. Saw cuts in the back of the
mold members (Fig. 14.29) will also reduce warping and wedging
caused by swelling and will make the forms easier to strip. Proper
treatment of wood with sealer (two coats) will reduce swelling
and produce a more uniform concrete surface.
Perfectly square pieces will bind in a formed recess and will
have to be cut out with a chisel. To avoid this extra labor and
possible damage to the concrete, make wood inserts with a slight
bevel or draw and with saw cuts in the back.
Much time can be saved in erecting and stripping forms for a
detail involving many pieces of run moldings if brackets are made
in the shop to the approximate profile of the proposed mold. The
brackets can be fastened to a major part of the formwork and the
mold pieces attached without excessive blocking. Fig. 14.29: Wood mold for cornice showing how longitudinal joints are
made by overlapping pieces rather than by butting or mitering (Image
Plaster Molds courtesy Portland Cement Association)
Plaster molds for casting intricate ornamentation are called
Nwaste�molds because they are broken in stripping and cannot
be reused. However, where elements of the design are repeated a number of times,
duplicate molds, perhaps made in fiberglass, can be mass-produced from the same master
pattern or model.
These molds are usually built by the ornamental plasterer who applies plaster reinforced
with fibers to a pattern of wood, clay, or other material. The pattern is first made to the
exact form of the proposed ornament and then the mold plaster is applied. When the
mold has hardened sufficiently, it is taken off the pattern and finished to the texture of the
form sheathing that is to surround the mold so the concrete finish of the decorative detail
will match the surrounding concrete. The contact side of the mold is then waterproofed
with several coats of shellac or other sealing compound. This prevents the mold from
absorbing water from the fresh concrete, which would weaken the mold and the concrete,
as well as possibly discoloring the concrete.
A 1/4 in. layer of colored plaster placed next to the pattern when forming the mold will
aid in the stripping operation by indicating when the plaster has been chipped close to
the concrete surface. The coloring must be such that the concrete will not be stained if the
waterproofing agent fails or is chipped off the contact surface of the mold.
The contractor and plasterer should work together in developing a mold that is strong
enough to withstand the pressure of the fresh concrete. The mold maker must be given
complete instructions as to how the mold will be attached to the formwork so that exten
sive blocking will not be necessary. The mold must also be able to withstand handling
during erection.
The shape of the back of the mold varies according to the size and shape of the orna
mentation to be formed. For small molds or flat surfaces with shallow ornamentation, the
back of the mold will be made flat to bear directly against the studs or wales. Molds for
deep ornamentation would be too heavy if the plaster were brought out to a flat surface
in back, so they are made 1-1/2 to 2 in. thick with the back of the mold made to approxi
mate the profile of the contact surface. The mold is then blocked out around the edges
and other points with plaster reinforced with jute fibers or burlap to contact the formwork.
A wooden frame is often added to the back of a mold to prevent deflection and cracking
during transportation and erection. The frame is detached when the mold is set in place.
The edges of the mold require special attention. If possible, the joints between the mold
and the form sheathing should be hidden at reveals or returns. The edges of each piece
should be rabbeted so they will fit closely with the form sheathing, making a tight joint.
MefaiMolds
Curved surfaces of mullions, piers, and pilasters are occasionally formed using metal
molds. It is advantageous if the curved surfaces are designed so that the sheet metal can
be shaped on standard rolls. The metal must be reinforced with collars or diaphragms to
maintain alignment. These supports are usually spaced about 9 to 12 in. apart.
The molds should be made from black iron rather than galvanized sheets because
galvanized metal may stick to the concrete even though it is well oiled. Shapes other than
cylindrical can be formed with metal but this is a costly process and seldom used unless
a great number of forms are needed, such as metal pans in steel or aluminum for a waffle
slab floor system.
.
Bearing
•re•
Fig. 14.31: Reduced bearing area at point of contact between form members improves tightness ofjoints; abutting
plywood panels at left and corners of a column form (right) are shown
� m
Closedcengasket Caulked joint
wrth orwithout covered with
rustication ..,.
� �
Epoxy glue on
45-degreecut l t������� nd-
groove)with
caulking
Fig. 14.32: Sealing burt joints in form sheathing. In all cases, joints should be backed up with
2x4 or larger brace nailed to both pieces of sheathing
Compressible
close cell
gasket
Fig. 14.33: Three methods of sealing comer butt joints. Flexible chamfers may be nailed,
stapled, or glued to the form, or the tail can simply be pinched into place when the form is
nailed together
Where it is difficult to draw the form joints tight with only tie rods, wales, and corner
braces, liberal use of wooden wedges driven between blocking and sheathing will often
help. Studs, wales, and ties must be spaced close enough to prevent bulging of forms. In
case of doubt, it is better to space supporting elements of the form closer than necessary
rather than too far apart.
It is generally advisable to erect the outside form first because the exposed face is
usually the exterior face. The designer should avoid requiring ornamental sculpture at
opposite points in both faces. Form lining and molds are easier to apply with the outside
form erected first. Tie holes can be drilled from the face side of the forms, thus avoiding
burrs that would mar the concrete. The completely erected outside form can be inspected
and any joints or other places where leakage might occur can be corrected and sealed
more easily. Design details should be provided for formed surfaces around embedded
items, devices, or features that are mounted on or protrude from the architectural
CHAPTER 14
concrete surface, including consideration of liner effects at these locations. Reinforcing bar
installation should avoid damage to form surfaces.
Inner and outer wall forms must be aligned before the ties are tightened because
two-way continuity of the tied forms will make later accurate alignment difficult.In assem·
bling forms, one must keep in mind the steps that can be taken to aid in removing them
without injury to the concrete. Boxes, molds, rustication strips, or any insert attached to
the main wall forms should be as lightly nailed as possible so they will pull loose from the
forms during the stripping operation and remain in the concrete. After the lumber has
dried and shrunk, these items can be easily removed.lf plaster, plastic, or other molds are
used, the same light nailing technique should be used because it is desirable to leave the
molds in place as long as possible to protect the ornamentation.
Inserts should be attached with double-headed nails driven from the outside of the
forms wherever possible because they can be pulled easily, leaving embedded parts of
the form in the concrete temporarily.When applying rustication strips to the face side of
a form (Fig. 14.12), long casing nails that extend through the strip and sheathing may be
used. Because the heads of these nails are very small, the nails can be pulled through the
strip and sheathing just before removing the form, thus allowing the wood strip to remain
in place until it is thoroughly dry.
For off-the-form architectural concrete surfaces, final cleanup and application of release
agent is essential.Although many such products are said not to stain or discolor concrete,
they must be applied uniformly and in the recommended concentration for good results.
Any excess buildup of the release agent in grooves or corners must be removed. Other·
wise, variations in concrete color, or even local retardation of set, may occur. Different
release agents have different effects on final color of concrete, so a single agent should be
used throughout the job.
Form cleanliness cannot be overemphasized where high-quality surfaces are required.
Dust, dirty hand prints, and pencil marks made by workers have all been known to be
transferred to the face of the finished concrete. Rust from reinforcing bars may dust onto
the form face and also be transferred to the concrete. Snippings from reinforcement tie
wire can also leave rusty stains.The snippings should be removed.Compressed air and
water may not be effective in removing them, and it is sometimes necessary to put a
magnet wrapped in plastic on the end of a stick to reach down into deep forms.
�eooo.. ·-·
bottomolslrip is kept straight by tacking a 1x2 strip along the outside form as
shown. The concrete is brought slightly above the bottom of the
1"x2' strip in Fig. 14.35. The strip should be removed after the concrete
Strip
h has set enough to hold its position. Form sheathing for the next
" lift of concrete is placed to overlap hardened concrete about 1
.c:'T
in., with thin compressible gasketing material placed between
b.
�
1-' \ "<::.. sheathing and hardened concrete. When the next lift is placed,
]
• •
T� there will be a straight, true joint. A similar strip can be used on
Sl'leatningoverlaps · ··· ; the inside form if the inside wall surface is to be exposed.
hardenedconcrete ,, When joints between floor and wall placements are to be
architecturally exposed, some special planning may be in order. A
�
� =·
�
common approach is to cast the wall, then place the slab sepa
rately, possibly with an upstand to aid in registering the wall
above. The upper wall is added in a third placement (Fig. 14.36(a)).
This leaves two joints and three different planes, compounding
FIRST STAGE
problems of plumbness and alignment. It is possible to design the
floor so that it can be placed in a recess in the top of the wall (Fig.
Fig. 14.35: Construction joint treatment ar formed surfaces. Bulges and
14.36(b)), thereby eliminating one exposed joint. The lower wall
offsets are avoided when ties are close to the joint. The 1 in. wood strip
extends upward to cover the floor slab edge. Two large surfaces are
aids in producing a straight, true joint
easier to keep plumb and in alignment.
Contraction joints are usually required for architectural
concrete to prevent haphazard cracking. The location of these
joints should be specified by the engineer/architect. In some
cases, the joints may be planned as part of the decorative
treatment. A straight joint of even width is formed by placing a
projecting strip on the form surface that will form a depression
in the concrete. Wood, metal, and plastics are suitable for such
forming. It is important to keep the alignment of these joints true,
as any deviation from a straight line will be noticeable. The joint
may be sealed with suitably designed backer rod and caulk after
the forms have been stripped.
14.5 Stripping
Careless workers can cancel out the value of good detailing and
Fig. 14.36: Alternate methods of casting floor-wall intersection
planning by indiscriminate use of the wrecking bar. A pinch bar
or other metal tool should never be placed against architectural
concrete to wedge forms loose. If it is necessary to wedge between the concrete and the
forms, only wooden wedges should be used. Once formwork is removed (Fig. 14.37), archi
tectural surfaces must be protected from continuing construction operations.
Forms supporting concrete and construction loads are subject to the stripping limita
tions imposed for structural concrete (see Chapter 12). For vertical forms supporting only
the lateral pressure of concrete, ACI 347R suggests allowing removal after 12 hours at 50°F
or above for ordinary concrete. This limit conservatively satisfies structural safety under
usual conditions. If earlier form removal is desired to meet special finish requirements, it
must be demonstrated that safety and curing requirements can be met.
In any case, vertical forms must not be stripped so early as to cause damage to the
visual quality of any concrete that is to remain in its off-the-form condition. If adhesion
between the form face and concrete is greater than cohesion within the concrete, surfaces
may scale and corners spall. Research indicates that attaining a concrete compressive
strength of about 300 psi (research based on cube compressive strength) is sufficient to
prevent this kind of surface mechanical damage.141J However, stripping is normally done at
strength levels attained after 24 to 48 hours and the higher strength is needed to mini
mize damage to sharp corners and fluted edges. Much depends on the overall quality of
site operations. Corners and edges can be damaged even when concrete is strong enough
to show no structural distress under loading.
Fig. 14.37: Removal of ties and stripping of For high-quality surfaces, uniformity in stripping time and curing practices is essential.
forms for architectural concrete must be The longer a form remains in place, the darker the concrete. Even a few hours of difference
accomplished with care to avoid surface in stripping time between lifts may cause a color difference that will be visible for years
damage (Photo courtesy Doka USA) after the job is finished.
CHAPTER 14
Form removal should be planned with regard for possible effects on curing requirements.
Some specifications require forms to remain in place for a certain period as part of the curing.
If forms are removed before this time is up, measures must be taken immediately after form
removal to apply and maintain satisfactory curing. In hot, dry weather, wood forms remaining
in place will not provide adequate curing. Such forms can be loosened or removed so that
concrete surfaces may be kept moist or coated with appropriate curing agent.
In cold weather, removal of formwork should be deferred or formwork should be
replaced with insulation blankets to avoid thermal shock and consequent crazing of the
concrete surface. When concrete surfaces cool faster than the concrete interior, crazing
cracks can develop in the surfaces. The higher temperature of the concrete relative to
ambient temperature is due to hydration and possibly applied heating. Reducing the rate
of concrete cooling minimizes crazing. ACI303R recommends that cooling of architectural
concrete surfaces be limited to a gradual drop of 40°F in 24 hours. ACI303R also calls
attention to cracking danger from thermal shock when cool hydrant water under pressure
is used to expose aggregate on retarded surfaces of massive concrete sections.
When stripping forms in the vicinity of a belt course, cornice, or other projecting ornament,
begin stripping some distance away from the ornament and work toward it. Thus, if there is
any tendency for the forms to bind around the ornament, the pressure of the forms against
projecting corners will be relieved, so there will be less chance of spalling sharp edges.
Forms recessed into the concrete require special care in stripping. Wedging should
be done gradually and should be accompanied by light tapping on the piece to crack it
loose from the concrete. Never remove an embedded form with a single jerk. Embedded
wood forms are generally left in place as long as possible so they will shrink away from the
concrete. The embedded items should be separate from or loosely attached to the main
form so that they will remain in place when the main form is stripped.
When stripping forms for a window opening, cross braces and vertical kick strips should be
removed first. Next, take off top and bottom cleats and, for example, if jambs are full height,
wedge out the head using wooden wedges. The wedges should be driven in at one end,
forcing the head down and away from the side member. To facilitate stripping, a 45-degree cut
or miter through the sides of the frame is sometimes made when the form is built.
Plaster waste molds should be stripped by someone familiar with the detail. The plaster
will usually stick to the concrete, at least in the undercuts, even with proper greasing. It
must be carefully cut away with a chisel. If the mold has been made with a layer of colored
plaster next to the concrete, the worker doing the chipping is warned when he has
chipped dose to the concrete. Plastic, steel, or rubber molds can be stripped by intro
ducing compressed air between the concrete and the mold through an opening in the
mold for that purpose. Flexible molds are peeled off.
R== tmollt
,J-_L__j_-l, •r=Stol Thil Stl After
i1 Plo�td ond Pump
Ou t Colfer
r
:��� grr��,��H:::\v•.h
Dit
v rond Sol• ogt Top Pe
i cn
FOUNDATION
H-BEARIMG
ON
PILE
CAISS ON
Conc,.lt AqoinstSI'Itolhinq
With Liner to Pt
r .,.nl Bond
t u il
oS h tp t
fOUNDATION ON FOUNDATION ON
PRECAST PILES ROCK {UNDER WATER)
0•'•'"'' '"""'
R o ek
b�ovot• to F or m t d Arto
Salt Slope
Fig. 15.1: Schematic representations of some common types of
FOUNDATION ON
ROCK lDN LAND)
bridge foundations
15.1 Foundations
There are several different types of bridge foundations and many different designs
depending on the location of the bridge, length of span between supports (whether over
water or land), and the bearing material on which the foundation can be supported, as
shown in Fig. 15.1. Because each bridge presents its own problems in type of foundation
and the conditions under which it must be constructed, the foundations usually offer the
greatest opportunity to explore alternate methods of construction and arrive at one that is
most satisfactory and economical.
CHAPTER 15
steel-cutting shoe-a fabricated unit (Fig.
15.2) that is left in place-to produce a
hard, sharp edge. The cutting shoe may
be placed in land or within a dewatered
cofferdam, as shown in Fig. 15.3.
Forms are required for caisson walls,
cutting edges, dredge wells, working
chambers, and worker access tubes (the
latter two for pneumatic caissons). Forms
(Fig. 15.4) may be built of wood or steel,
or a combination of the two. The caisson
may be cast and sunk as a complete unit,
but for the large depths generally involved, Fig. 15.2: South Park Bridge caisson steel shoe Fig. 15.3: South Park Bridge caisson steel·
only the cutting edge portion and a small (Photo courtesy John Stamets) cutting shoe placed in cofferdam (Photo
section above it are cast initially. Then the courtesy John Stamets)
forms are raised; and as the lower part of
the caisson sinks, the next section is cast
(Fig. 15.5), adding weight to assist in the
sinking. With this method of climbing or
lifting the forms, the wall forms for outer
and dredge well walls are generally reused
many times. For example, the walls of
the South Park Bridge caisson in Seattle
extended to a depth of 100 ft.
Below the waterline, dredge wells are
open to the bottom so that muck may
be removed as the caisson sinks. When
the caisson reaches the desired elevation
below the waterline, tremie concrete is
usually placed in the bottom of the dredge
wells to seal and stabilize the structure (Fig.
15.1). Some designs call for complete filling
of the dredge wells. Dredge well forms,
Fig. 15.4: South Park Bridge caisson exterior Fig. 15.5: South Park Bridge concrete caisson
or internal forms, need not be as accurate
forms for second lift (Photo courtesy John wall lift placement (Photo courtesy John
and smooth as the forms for the external
Stamets) Stamets)
surfaces and cutting edges of the caisson.
Their main requirement is that they be
readily removable and replaceable if they
are not intended as a permanent part of
the caisson.
When a concrete caisson is to be started on soft ground, it may be necessary to provide
extra support until the first 10 or 15 ft are cast. The cutting shoe may be placed on closely
spaced transverse timbers and blocking used to support the beveled edge of the caisson,
thus spreading the load and relieving some of the pressure on the cutting edge. When the
caisson is ready for sinking, timbers must be carefully cut or removed to maintain even
pressure of the cutting edge on the ground and prevent tipping. Sand islands or cause
ways are sometimes constructed in shallow water to permit starting a caisson in the dry.
The sinking must be carefully controlled to keep a level position while the caisson is
being formed. The level can be checked by either a laser level or a water-tube level system
with indicators located at four corners of the caisson. If the caisson becomes slightly
out of plumb during sinking, it is important to cast the next lift out of plumb, parallel to
the preceding one, so that an irregularity or·dogleg•is not created in the plane of the
concrete. It is usually possible to correct a slight tip in the caisson, and it is better to keep
the walls a straight line because these·doglegs· greatly increase the frictional drag on the
sinking caisson.
In some cases, a cofferdam is attached to the outside of the caisson to permit sinking
below water before concreting. In this case, the cofferdam panels become a part of the
permanent form. Concrete is placed against them, and the panels are not stripped. lf the
upper part of the caisson is smaller than the lower part, formwork may be built inside the
cofferdam. After the upper part of the caisson is cast and the caisson has reached final
elevation, this formwork and the upper section of the cofferdam are removed.
BRIDGE FORMWORK
15.1.2Piles
Support for a bridge foundation can be provided by piles driven through the overburden
Wedge into solid bearing material, as shown schematically in Fig. 15.1. To minimize corrosion,
2 x 6 nailer
steel piles must not be exposed to seawater, acid waters, or certain types of overburden,
such as cinders or ash fill. One way to avoid continuous contact with water is to drive the
piles below the river bottom and cover with a concrete cap. When such a pile cap founda
tion is being built in water, a cofferdam is installed surrounding the piling, a clamshell is
used to remove soil to a suitable depth, and a concrete seal is placed by tremie before
dewatering. The seal counterbalances upward water pressure and provides lateral support
for the sheeting lower end to prevent "blow in" due to lateral water pressure. Tremie
Corrugated metal concrete cast against sheet piling requires no forming preparations other than clearing
or plywood debris from the sheet pile underwater within the cofferdam.
After removing water from the cofferdam and cleaning the top surface of the concrete,
forms are set for the distribution block and concrete is placed. Side forms for the rein
Fig. 15.6: Lining cofferdam sheet piling forced block may be set with working clearance from the sheet piling of the cofferdam
prior to concrete block placement to allow or the form may be simply a liner placed against the sheeting to prevent bonding of the
sheeting extraction concrete to the sheet so that the latter can be salvaged. This liner is usually a dispos-
able type, either light corrugated metal or light plywood. It is nailed to 2 x 6 nailer blocks
wedged into the recesses of the sheet pile, as shown in Fig. 15.6.
The cofferdam remains in place until all operations below water level have been
completed, including the setting of forms and concreting for the lower part of the piers.
Then, the sheet pile is either removed completely or the sheets are burned off at the top
of the tremie seal, thus salvaging the top of the sheeting while the lower part remains in
place as a guard against scouring.
Another technique is to encase part or all of each pile in concrete. This can be achieved
by using watertight forms that are placed over the tops of the piles aher they are driven.
The forms are then filled with concrete and may subsequently be withdrawn or left in
place. These forms are usually prefabricated of steel.
Concrete piling is usually used where the pier base is above the river bottom. A pile cap
Fig. 15.7: Support of cap form beams from piles is cast encasing the heads of the piles at approximately water level (Fig. 15.1) and serving
in water (Photo courtesy W. Kenneth Creech) as the foundation block for the piers. The form for this cap can be hung on the piling a
few feet below the water surface (Fig. 15.7). Another technique is to first drive some wood
piles on which the cap form is supported before the concrete piling is driven. Holes in the
form serve as templates for setting and driving piles. Aher the piles are driven, the form is
filled with concrete. The bottom or template is left in place, but side forms for the cap are
stripped. Alternates to driven piles include concrete piles cast in drilled holes, piles cast in
driven shells, and auger-cast piles. For comprehensive information on concrete piles, refer
to ACI 543R-12, "Guide to Design, Manufacture, and Installation of Concrete Piles."
Forms used underwater present unusual problems of locating, aligning, and sealing.
Elaborate methods of locating forms and piles from the surface must be developed, using
sighting towers or preplaced guides, or divers must work underwater to relay instructions
to guide the components into position. The sealing of openings to contain the concrete
must be carefully carried out in advance because corrective measures after concreting
commences are difficult and costly.
If underwater forms are to be salvaged for reuse, it is desirable that they be designed
so that the stripping may be carried out from the surface. Thus, if possible, forms should
have no undercuts or re-entrant angles that make it difficult or impossible to withdraw
them from overhead. Hydraulic cylinders are sometimes used to jack the form open and
separate it from the concrete so it may be withdrawn. Special fittings on the form may be
required to facilitate this operation.
When piles are located entirely on land, construction proceeds as for a building struc
ture either with a sloped excavation or one protected by sheet piling (Fig. 15.8). After piles
are installed and cut to final elevation, forms are erected and braced or tied, and reinforce
ment placed in preparation for concreting.
CHAPTER 15
anchored or braced to the rock, which
serves as the bottom surface of the form.
Then, the foundation concrete is placed.
In water, a sheet·pile cofferdam is first
driven through the overburden to and
sometimes slightly into the rock. Driving
sheet piling into rock is difficult but it is
hard to seal a joint at the rock surface. After
water is pumped out of the cofferdam,
muck is excavated from the cofferdam until
the rock·bearing surface is exposed. The
excavation may be continued into the rock
for a few feet so that the foundation will
key to the rock. The rock surface is cleaned,
and a form liner of sheet metal or plywood
is fastened to the sheet pile. Concrete is
placed directly on the rock, which serves as
the bottom form surface. When the concrete
has hardened sufficiently, the form for the
pier base is erected on it and braced against
the cofferdam. After pier construction rises
above the water level, the cofferdam sheet Fig. 15.8: Preparation of bridge foundation pile cap form (Photo courtesy of New York State
piling may be withdrawn. DepartmentofTransporrationO)
Whenever a cofferdam is used to back up
a form liner or the bracing for form sides, the concrete pressure against the sheet piling
is opposite to that which it is primarily designed to withstand. When an internal frame
is bracing the cofferdam sheet piling, the possibility of a net pressure outward must be
evaluated. If preplaced aggregate is being used, with high injection pressures, there could
be an extremely high outward pressure on the cofferdam, and this must be taken into
account in its design.
As in other types of construction, it is sometimes found that the soil beneath a land
bridge or the land portion of an overwater bridge is firm and capable of supporting a
pier or arch on a spread footing. Forms for such footings are relatively simple and can be
constructed in the same manner as footing forms for buildings. The ground is leveled to
serve as the form bottom, and the form sides are made of steel panels or built up of wood
sheathing braced by stakes in the ground.
15.2 Piers
A pier shaft rests on the spread foundation or pile cap and supports the bridge superstruc·
ture at the necessary height. Piers usually are rectangular or circular in cross section, but
some may have more complex shapes for visual effect. Pier sides may be vertical, battered,
or stepped. The type of formwork depends on the shape and height of the piers and the
number of similar piers.
When the bridge has many piers or the piers are quite high, careful study is justified to
achieve maximum reuse of forms. Where considerable reuse is possible, pier forms are
frequently custom·made in steel by a supplier who specializes in this work. Wood forms as
well as wood and metal forms may also be used. For smaller piers, forming materials are
much the same as for building columns described in Chapter 11.
CHAPTER 15
bottom, held in place by the hardened
concrete, supports and aligns form sections
for the next lift.
15.2.7 External Ties Fig. 15.11: Braced and guyed pier form (Photo Fig. 15.12: Pier form lapped adequately for
Visual appearance requirements may
courtesy EFCO Corp.) alignment (Photo courtesy EFCO Corp.)
prevent the use of internal tie rods for
pier shaft forms, and sometimes complex
reinforcing steel within the shaft makes
the use of internal tie rods impractical.
External bracing or tying must be used in
such cases, and various methods are readily
adaptable to pier forms (refer to Fig. 1 S.1 S).
Steel strapping is a simple method of
tying together the sectors of a circular
form, and it also may be adapted to piers
with cross sections other than circular by
using filler adapters or shaping the form
studs or wales to fit the curve of the strap
and develop its full hoop strength. Usually,
heavy steel structural angles or channels
can double as stiffeners and ties. Drilled
and bolted or nailed to wood sheathing, or
welded to a sheet metal liner, the angles
or channels may extend beyond the panel
edges to be bolted to mating stiffeners
on the adjacent panels to tie the form
together. Steel rods, sometimes called
yokes, can span across the form above the
construction joint to resist lateral pressure.
15.3 Superstructures
Bridge superstructures include girders,
a deck or roadway, curbs, sidewalks, and
railings or parapets. Concrete bridge decks
may be simple slabs for short spans or
slab and girder construction for longer
spans. They may be entirely cast-in-place,
entirely precast, or a combination of cast
in-place slab with steel or precast concrete
supporting girders. Many of the forming
problems and techniques are similar to
those for other slab work, the major differ
ence being the problem of support for
formwork when spans are at great height,
over water, or above unsatisfactory earth
support. For special considerations and
recommendations, refer to ACI345R-11,
NGuide for Concrete Highway Bridge Deck
Construction," and ACI345.2R-13, "Guide
for Widening Highway Bridges.NThe use of
mortar-tight deck and superstructure forms
provides a smooth unblemished appear
ance that will enhance public confidence in
the soundness of the structure.
Fig. 15.15: External ties and full-span wales used to avoid internal ties (Photo courtesy MEVA 15.3.1 Monolithic-Simple Slob,
Formwork Systems) Beom, and Girder
Bridges with short spans between supports
(less than 25 ft) may be built as simple slab
decks. Because these simple slab bridges
are sometimes designed with the expecta
tion that the curbs will supply part of the
bending resistance, the curbs may be cast
integrally with the deck slab. Formwork for
a slab deck is like that for any other slab;
sheathing of metal, wood, plywood, or
other material is supported on joists and
stringers. Edge forms are equal in height to
the curbing and are braced externally from
joists extending beyond the deck width.
The form is supported from below by any
one of the various types of shoring, or on
heavy horizontal members supported on
the piers. On projects where there are many
identical short spans, large one-piece forms
have been used for an entire span, then
lowered to barges and floated to the next
position for reuse.
CHAPTER 15
Fig. I 5. I 7: Round column friction collar
example (Image courtesy EFCO Corp.)
Fig. I 5. I 8: Stay-in-place steel forms attached Fig. I 5.19: Stay-in-place precast concrete deck
by self-tapping screws to angle ledgers that forms supported directly on concrete girders
15.3.2 Cast-in-Place Deck Support
have been welded to structural steel bridge
ed on Steel or Precast Girders
�--·-·--
girders (Photo courtesy of New York State
Formwork details may differ, but the
Department of Transportation�)
general method of forming slabs is
the same whether supported on steel
1 I�---
or precast concrete girders. Formwork -"1"
� - ---
,E.;
o... s.----
---r�25571
various manufactured devices from the . .
CHAPTER 15
much the same as for building construc
tion, except where greater heights call
for more diagonal bracing to stabilize the
supporting structure. If the design requires
shoring of the girders while placing the
slab for composite action, the engineer
should specify its nature and location. The
recommendations of ACI 347R should also
be consulted.
If shoring from the ground is imprac
tical or impossible, various other means
can be devised to support the formwork Fig. 15.26: Overhang frame fabricated in wood
from piers or other parts of the substruc (Image courtesy Dayton Superior)
�
.c� arch bridge forming. Careful attention must also be given by the bridge engineer to
the specified camber of arch forms to produce a finished arch at the desired elevation.
Decentering operations for arches require detailed advance planning, much the same as
decentering shell structures, so that the structure can assume its load uniformly without
being damaged.
i ;.;.
··� These issues require careful engineering of both the tall shoring system, which is
frequently a major temporary structure (Fig. 15.32), and of the process to be followed
�,
arches, metal shoring in heavily braced tower assemblies is often used (Fig. 15.32).
Where high, long-span arches cannot be suitably or economically supported on shoring,
\ J
a temporary cable-stayed support system has been used to cantilever the arch from each
side until joined at the center (Fig. 15.34 to 15.36).1ncreasingly, the cantilever method is
· · .. I
. .. • . :·
.
-·-· used for both arch and other types of bridges, reducing or sometimes eliminating shoring.
CHAPTER 15
based on the economy of the construc
tion and a knowledge of loadings to be
placed on the bridge before it is complete.
In North American practice, where design
and construction are more often done by
separate organizations, it is common to
engage construction engineers to work out
the detailed construction procedure.
The forms and form travelers are really
forming machines that must be engi
neered and manufactured by specialists
with expert knowledge. They are usually
made of steel, with jacks or other powered
devices to strip, move, and adjust the form
and any supporting gantry or traveler.
This highly skilled, specialized field of
form building is beyond the scope of this
manual. However, an overall description
is given as background for understanding
the construction alternatives now avail
able. There is a multitude of choices, and
changing techniques and technology result
in few structures being constructed in
exactly the same way.
Fig. 15.33: Form erection for bridge arch with temporary erection tower to support form until
form work arch is complete (Photo courtesy EFCO Corp.)
15.5.1 Cast-in-Place Segmental
Construction
In cast-in-place construction, segments
are cast one after another in their final
location in the structure. Special equip
ment is used, such as traveling forms for
cantilever construction or formwork units
moved along a supporting gantry for
span-by-span construction. Each segment
is reinforced with conventional reinforcing
steel and sometimes by vertical or trans
verse prestressing, or both. The segments
are joined together by longitudinal
post-tensioning.
Because segments are cast end to end,
longitudinal steel can readily be made
continuous across the joints. Concrete
strength and modulus of elasticity
development influences construction
speed and amount of structure deflection
during construction.
Fig. 15.34: Concrete arch formwork supported Fig. 15.35: Initial cast-in-place arch segments.
15.5. 2 Precast Segmental by temporary stayed cables until arch formwork travelers, and worker access provisions
Construction completion for Hoover Dam Bypass Bridge (Photo courtesy USOOTFHWA)
Precast segmental bridge construction can (Photo courtesy USOOT FHWA)
be done with joints several inches wide
for which forms are built before the joint is filled with grout, mortar, or concrete. Formed
joints are more readily built with span-by-span erection methods that provide support
for the forms. With formed joints, precast production can be speeded because match
casting is not required. However, recent practice favors joints of minimum thickness.
This calls for match casting, whereby segments are cast against one another in the same
sequence they will have in the bridge. Where the climate permits, these joints are left dry.
Elsewhere, a thin layer of epoxy is used to seal the joints. The segments are cast with one
or more integral shear keys. Usually there is no continuity of conventional longitudinal
steel; post-tensioning establishes the longitudinal continuity. When the segments are
Fig. 15.36: Completed Hoover Dam Bypass Bridge arches, piers, and deck with temporary Balanced Cantilever Erection
pylons and stayed cables removed (Photo courtesy U5DOT FHWA)
The main advantage of the balanced canti
lever or free cantilever method of erecting
segmental bridges is the elimination of shoring or falsework. It is particularly advanta
geous over navigable waterways and traveled highways or railroads. Construction begins
at permanent piers and is self-supporting at all stages. Segments are cantilevered from
a pier, alternating from one side to the other and a closure pour is made with the corre
sponding half span cantilevered from the next pier (Fig. 15.39).
Construction typically begins with a pier cap or girder segment called a pier table,
built in place on top of the pier (Fig. 15.40). The top post-tensioning tendons in the pier
Fig. 15.37: Precast segment after removal from form (Photo courtesy EFCO Corp.)
CHAPTER 15
table segment are operating at capacity during the entire erec-
tion sequence to resist the negative moments of the cantilevers.
Thus, the construction loads must not increase significantly over
what was assumed in design. Several methods are used to resist
overturning moment created by temporary imbalance of the canti
lever as segments are attached to cantilever ends. They include
post-tensioning the pier down to the pier stem, adding temporary
supports on either side of the pier, or stabilizing the cantilevers with
erection equipment. The final choice is made by the contractor, but
the designer must assume and detail a method for stress evaluation
and provide parameters for the builder.
In precast segmental work, each added segment is immediately
post-tensioned to the already-completed portion of the structure.
There are various ways to deliver segments to the cantilever position:
land- or water-based cranes, truck or crawler cranes, floating cranes,
and self-operating launching gantries are among the most common.
The launching gantry or launching girder is a machine capable of Fig. 15.39: Balanced cantilever traveler(Photo courtesy Doka USA)
transporting a segment from a completed part of the bridge or from
below the bridge to either end of the cantilever being erected. Launching girders are
made in many sizes and shapes; most can move themselves once a cantilever is completed
and another is ready to be started.
For cast-in-place segmental cantilever construction, forms are supported on a movable
carrier or form traveler (fig. 15.41) that advances on rails attached to the deck of the
completed structure and is anchored to the deck at the rear. For balanced cantilever work,
at least two travelers are needed, working simultaneously. The work sequence includes
the following steps:
1. Set up and adjust the carrier;
2. Set and align the forms;
3. Place reinforcing steel and tendon ducts;
4. Place concrete;
5. Install post-tensioning tendons in the segment and apply stress aher the concrete
has gained the required strength;
6. Remove the formwork; and
7. Move carrier or traveler to the next position and repeat the cycle.
The forms are adjusted to make changes in the box-girder depth as required.
Cantilever construction has been used for reinforced concrete bridge spans as long
as 320ft. However, balanced cantilever construction is at its most economical for posr
temioned spans of approximately 300 h up to 850ft. Cable-stayed spans, also built by the
cantilever method using cables during construction, may be used where longer spans are
desired. Fig. 15.40: Construction of pier table segment
(Photo courtesy EFCO Corp.)
Spon·by-Spon Construction, Stepping Formwork
The balanced cantilever construction described previously is advantageous for long spans,
but span-by-span erection may be the most economical technique for erecting segmental
bridges in the medium range of spans less than 250 h. Construction proceeds from one
end of the bridge to the other, one span at a time, with some kind of temporary support
set up for the span being worked on. This erection method is referred to as stepping form
work when construction is cast in place.
For cast-in-place work, the temporary support is a form traveler that may be supported
on the piers, or from the edge of previously completed construction at the joint location
and at the forward pier. The traveler is a steel structure that is moved from one span to
the next as the work progresses. For an above-deck carrier, the large formwork elements
for one bridge segment are suspended on rods during concreting. Aher the segment has
gained strength and been post-tensioned, the forms are released and rolled forward by
means of structural outriggers on both sides of the form traveler's superstructure. A similar
procedure can be followed by using a below-deck carrier (fig. 15. 42) . The form carrier
or traveler in effect provides a sort of factory operation transplanted to the job site. This Fig. 15.41: Cantilever bridge formwork craveler
method has many advantages of mass production in a plant plus the added capability for details (Image courtesy Doka USA)
field adjustments.
Progressive Placing
Progressive placing also starts at one end of a structure and proceeds continuously to the
other end. The spans cantilever as segments are added, but unlike the balanced cantilever,
the work cantilevers from only one side of the pier. The method works for precast as well
as cast-in-place segments. If the bridge is cast in place, traveling forms are used as in a
balanced cantilever.
Because the cantilever is long (an entire span) in relation to construction depth,
supports such as cable stays from above (Fig. 15.43) or pier bents below are used to
limit stresses in the cantilevers during construction. Precast segments are moved over
completed portions of the deck to the tip of the cantilever where a swivel crane places
them. The first few segments out from the
pier, perhaps as much as a third of the span,
can be erected as a free cantilever before
stays or other temporary or permanent
supports become necessary.
This method is of particular interest
where spans are in the 100to 160ft
range, but has proven practical and
economical for some spans up to 3 00ft.
It can be advantageous where site condi
tions prohibit the span-by-span method.
Where physical or environmental restric
tions impede conventional access to pier
locations, this method permits trans
porting equipment and materials for pier
construction from above, over the partially
completed structure, as was done in the
case of the linn Cove Viaduct in North
Carolina (Fig. 15.38).
Fig. 15.43: Progressive placement of precast bridge segments supported by stay cables (Photo
courtesy Doka USA)
CHAPTER 15
Incremental Launching or Pushout Method
The incremental launching method is best suited to bridges with spans up to approxi
mately 200ft, where piers can be easily located at regular intervals. Segments of the
bridge superstructure are cast in lengths of 30to 100ft in stationary forms just behind the
bridge abutment. Stringent control of dimensions is necessary at the casting site because
errors are hard to correct and add to launching costs.
Each segment-generally 1/4, 1/3, or 1/ 2of the regular span-is cast against the
previous unit and post-tensioned to it as soon as sufficient strength develops. The assem
bled units are pushed forward step by step to permit more segments to be cast or posi
tioned behind the abutment.
Incrementally launched bridges may be either straight or curved, but the method is
limited to structures with constant radius of curvature, either horizontal or vertical. Thus,
roadway geometry is sometimes dictated by the construction method, contrary to usual
practice. Hydraulic jacks are used to move the superstructure out in the longitudinal direc
tion, and special temporary sliding bearings and proper lateral guides must be provided at
both temporary and permanent piers.
To keep bending stresses down during launching, a fabricated structural steel launching
nose (Fig. 15.44) approximately 6 0% of the span length is attached to the lead segment.
This has worked well for spans up to approximately 200ft. For spans in the 200to 330ft
range, intermediate falsework in the form of temporary piers or bents may be needed.
Another way to control bending stresses in the advancing span is to use temporary stays Fig. 15.44: Incrementa/launching of post-
attached to the front part of the deck and supported from a tower that can be moved tensioned match-cast segments
from pier to pier as the bridge advances.
g�··· ELEVATION
or more formwork units move along
the line, guided by a preadjusted soffit
(Fig. 1 5.47). Formwork at the beginning
of long line casting moves to the right
�-'"' -
as each segment is cast, leaving a long
line of match-cast pieces. As the opera
tion proceeds, segments are taken in
sequence from the end of the line to be
placed in the structure.
Fig. I 5.46: Fabrication of form for bridge Fig. 15.47: Formwork and process for long line
The long line is easy to set up and
precast concrete segment (Photo courtesy casting of bridge segments
makes it easy to maintain control over the
EFCOCorp.)
segment production. After stripping it is
not necessary to take away the segments
immediately. Because the forms move
along the line, so must the equipment
for casting and curing. The line can be
designed to accommodate curved struc
tures, but usually the short line method is
more appropriate for curved and variable
structures.
Flexibility Needs
Formwork for structures with variable geometry has to be relatively flexible to allow
adaptation at various joints. Some flexibility may be needed to accommodate small
CHAPTER 15
differences of dimensions with the previously cast segment. The design must also
provide easy and accurate adjustments in desired camber, curvature, and twisting.
Special consideration must be given to parts of the formwork that have to change
dimensions. Equipment such as hydraulic jacks, screw jacks, turnbuckles, and wedges is
provided to make adjustments easier. Compressed air jets may be used to break suction
during stripping.
15.5.7 Vibration
Internal vibration is more common, but when external vibration is used, forms must be
designed to withstand the stresses it adds. External vibrators should be attached at points
that will give the best consolidation and still permit easy replacement in case of a break
down during casting.
BRIDGE FORMWORK
Table 1 5.1: PCI recommended tolerances for precast box girder
segments
Fig. 15.49: Precast segment dimensions Grode of fOJm edge ond soffit,e :tl/8in. in 10ft
covered by PC/ tolerances (Image courtesy location of past·len$ioniog di.ICt, k t1/8in.
PC/)
location of shear key, z :tl/4 in.
REFERENCES
15.1. Barker,J., �construction Techniques for Segmental Concrete Bridges,� PC/ Journal,
July-Aug. 19BO,pp. 66-B6.
15.2. Muller,J. M.,and Podolny,Jr.,W.,Construction and Design of Prestressed Concrete
Segmental Bridges, John Wiley & Sons, Inc.,New York,1982,561 pp.
15.3. libby,J. R.,and Perkins,N.,Modern Prestressed Concrete Highway Bridge Superstruc
tures: Design Principles and Construction Methods, Grantville Publishing Co.,San Diego,CA,
1976,254 pp.
15.4. Mathivat,J., The Cantilever Construction of Prestressed Concrete Bridges, John Wiley &
Sons,Inc.,New York,1983,341 pp.
15.5. Degenkolb,0. H.,Concrete Box Girder Bridges, Iowa State University Press/American
Concrete Institute, Farmington Hills, Ml,1977,106 pp.
15.6. Rosignoli, M., Bridge Construction Equipment, ICE Publishing, london, UK,2013,
488 pp.
15.7. MAASHTO Guide Specifications for Design and Construction of Segmental Concrete
Bridges,� second edition,,Washington, DC,1999,with 20031nterim Revisions.
16: MASS CONCRETE FORMWORK
The term "mass concrete" is defined in ACI301-10, "Specifications for Structural
Concrete,· as "any volume of structural concrete in which a combination of dimensions
of the member being cast, the boundary conditions, the characteristics of the concrete
mixture, and the ambient conditions
can lead to undesirable thermal stresses,
cracking, deleterious chemical reactions,
or reduction in the long-term strength as
a result of elevated concrete temperature
due to heat from hydration."Traditionally,
however, the term "mass concrete" has also
been applied to concrete used in struc
tures that derive their strength from the
weight or mass of the concrete, such as
gravity dams, gravity retaining walls, locks,
foundations, and anchorages. Most of
this chapter applies to this latter category
of gravity structures that, because of the
need to minimize cracking for water tight
ness, simultaneously fits into the ACI301
definition.
Using conventional dam construction
methods (Fig. 16.1), mass concrete is usually
deposited in the forms by large-capacity
bottom dump buckets from cableways,
cranes, and derricks. Because of the large
plan area of most mass concrete structures,
the rate of rise of concrete in the forms is
usually low, although large quantities are
being handled. Belt conveyor systems are often used for placing mass concrete and are
available to handle up to 6 00 yd1/h.Concrete buckets up to 12 yd1 capacity were used at
Glen Canyon Dam in the United States, and rates of placement of over 1000yd1per shift
are not uncommon when using 4 yd3 buckets.Such air- or hydraulically operated buckets
are capable of rapidly depositing 8 tons or more of concrete at one time.
For gravity retaining structures such as dams, the conventional approach to mass
concrete placement is now supplanted in most cases by the use of roller-compacted
concrete.This change in placing practices reduces forming requirements but generally
does not totally eliminate forms for major structures (refer to Section 16.5).
Large and thick foundation mats (Fig. 16.2) for buildings, industrial structures, and
power generation facilities are also often referred to as mass concrete because of poten
tial damaging effects of high heat of hydration. large piers for long-span bridges involve
Fig. 16.2: Preparation of reinforcing and similar concerns.For large building mat foundations, mass concrete placement is usually
form work for thick concrete foundation mat by use of multiple pumps. Depending on the mat dimensions, single-sided braced forms
(Photo courtesy MEVA Formwork Systems) may be used.
One major consideration facing the designer of mass concrete structures is control or
elimination of thermal cracking, and in the case of hydraulic structures, leakage through
construction joints.The large amounts of heat generated by hydration of the concrete
present considerably more problems than in other structural concrete, and some of the
provisions made to limit temperature rise have a vital effect on the formwork.
In warmer climates especially, the concrete temperature is kept to a minimum during
placement and hydration by the use of low-heatType Hand IV cements, fly ash or other
pozzolan replacement of part of the cement. cooling techniques, special curing tech
niques, and heat-dispersing steel forms.Cooling techniques for mass concrete are
discussed in ACI207.4R-05, ·cooling and Insulating Systems for Mass Concrete (Reap
proved2012).T - he height of lifts, plan, and sequence of placing the concrete are gener
ally selected to help control temperature. Form removal is also planned to avoid thermal
shocks that would result in cracking of the concrete surface.The most common approach
to regulating shrinkage and heat of hydration in mass concrete work is to limit the height
and area of lifts.16·1 Lifts are often placed in alternate monoliths, sections, or blocks of
the dam that are bounded by transverse contraction joints, as seen in Fig. 16.1. Heights
of lifts range from 2.5 ft for multiple lifts just above foundations to 7.5 and 10ft in many
gravity dams, and 10ft or more in thin arch dams, piers, and abutments.The trend toward
increased lift heights has been brought about by a desire to reduce horizontal construc
tion joints, thereby reducing potential leak paths and saving time and cost in joint prepa
ration and concrete placement.
Except for the initial footing or foundation lift, most formwork used on short lift mass
concrete dam and retaining wall construction is of reusable pure cantilever or tied back
(propped ) cantilever design. Low lifts require frequent reuse of forms, and cantilever
forms are most often made of steel to withstand high loads and give long service through
many reuses. Some are made of wood, however, and others with wood sheathing bolted
on steel frames may also be used.The latter permit greater flexibility in attaching recess
blackouts, but will require additional costs when worn face sheets need replacing.
CHAPTER 16
For sloping faces, such as in retaining
walls or the downstream faces of gravity
dams, a form anchored at the top of the
previous lift would tend to tilt inward if
not prevented from rotation.Thus, it is
common practice to extend each strong
back so that a second anchor bolt can be
attached to the bolt insert in the second
preceding lift (Fig. 16.5). If a sloping
cantilever form does not have this two
point attachment to previously placed
concrete, it generally must be temporarily
braced from within the form until sufficient
concrete is placed against the face of the
form to counteract the inward tilt.
The tie-down cantilever design (Fig . 16.6),
which uses a row of ties attached at or near
the top of the form in addition to anchor
units at the base attached directly to the
previous lift, is sometimes used for higher
lifts, between 7- 1/2and 10ft, to minimize Fig. 16.4: Metal panel sections with metal strongbacks used as cantilever forms for top surface
form deflection and reduce the weight of and edge barrier of mass concrete dam (Photo courtesy Contra Costa Water District)
the units. The tie-down system may also be
used with lower-lift cantilever units to accomplish the same purpose of reducing weight or
deflection.Cantilever forms for 7-1/2to 10ft lifts may be strengthened by trussed strong
backs (Fig. 16.7) or other heavier strongbacks so that tie-downs are not required.
When sloping forms are used, they often extend over the construction joint to the
extent that it is difficult to bring concrete buckets close enough to place and adequately
consolidate the concrete.ACI 207.1R-05, �Guide to Mass Concrete (Reapproved 2012),�
suggests that such forms be hinged so the top half can be swung back {Fig. 16.8) out of
the way until concrete is placed up to the hinge elevation. The top half is then lowered
into position and concrete placement continued.
For gravity arch and hollow gravity arch dams, it becomes necessary to further modify
the basic design to provide for curved profile and contour surfaces.Changing horizontal
or vertical curvature is usually accomplished by using smaller or jointed modules with
Fig. 16.5: Sloping cantilever forms require a
tension tie anchor at strongback lower ends to
filler pieces if necessary, and inserting adjusting bolts between the strongback and the
prevent overturning (Photo courtesy Doka USA)
panel, or between the strongback and the surface of the preceding lift. Alternatively, it can
be accomplished by attaching the upper end of the strongback toward
the middle of the panel with a combined pivot and screw combination.
Other cantilever form modifications can be made for special
purposes, such as the one shown in Fig. 16.9.That form has large key
blocks applied to the vertical form surface to allow concrete interlock
with subsequent lateral placements.
Cantilever form panels of precast concrete, which remain in place as
the permanent facing of the structure, are technically feasible and have
been used, but at present they do not appear economically attractive.
CHAPTER 16
sure acts perpendicular to the confining surface, uplift must be considered in designing
anchorage for inward-leaning sloping forms.
In addition to forces due to pressure of the concrete, the design must provide for
handling of forms and dead and live loads due to exterior work platforms, work crews,
and any special form attachment. A rational design of a form panel can be made for the
estimated loading, following general principles outlined in Chapter 7. The required section
modulus of the strongback is determined by calculating bending moments and deflec
tions for a beam supported as a tied or pure cantilever, depending on which arrangement
has been chosen for the form.
When form reuse is planned, the effects of cumulative load duration should be consid
ered in accordance with the applicable design specification for the material. The control
ling factor in design of the pure cantilever form is often the permissible deflection which is
compatible with the specified tolerances (refer to Section 16.9).
RAy= ci'El +CI'El +ca =sao lb+soo lb +1200 lb = 2200 lb 16.2.3 Other Design Features
The procedure to be used for accommo
The resulting anchor bolt load is a combination of tension and shear. Most manu dating changing profile of the structure,
facturer load tables are based on tension only. Anchor working load capacity should particularly abrupt changes, and also the
be based on a factor of safety of 3.0 to meet ACI 347R provisions. OSHA form scaffold intersections of face and joint formwork
requirements should also be investigated. After preliminary selection based on tension, should be fully detailed. Particular care must
the working load capacity based on the combined loading should be investigated with be taken to provide anchorage for sloping
the anchor's manufacturer. The principles provided in ACI 318, Appendix 0, Anchoring forms and wall forms tied to a rock face.
to Concrete, on interaction of tension and shear should be helpful in understanding the Drawings showing the form layout for
issues although the anchor types may be different. each lift and the scheduled movement of
the individual units are usually prepared for
each elevation of each bay as the detailed
designs are evaluated. Many agencies
require complete lift drawings in advance
showing all items to be included in the
particular lift of concrete. These guide the
builder and various crafts involved as well
as the owner's inspection forces. Form
checkout cards are frequently attached to
each lift form requiring initials from all the
individuals connected with its preparation
before placement may begin. These may
include the craft represented, the inspec
tors for each specialty, the layout crews
of the contractor, as well as the owner's
comparable group, and the concrete place
ment inspector, who performs the pre
placement inspection of the formwork.
Beveled grade strips and 1 in. or larger
triangular toe fillets can be used to
Cantilever form for vertical face mask offsets that sometimes occur near
horizontal joint lines. This will generally
CHAPTER 16
improve appearance of formed surfaces, according to ACI 207.1 R. When used at the top
and bottom of the forms, this will leave an effective and pleasing groove. A 1 in.or larger
chamfer should also be used in the corners of the forms at the upstream and down
stream ends of construction joints for the sake of appearance and to prevent chipping
of the edges. Sharp corners of the block otherwise are often damaged and are difficult
to effectively repair. The chamfers also prevent pinching and spalling of joint edges
caused by high surface temperatures.
Other aspects of cantilever form design include the provision of adequate external
work platforms,ladderways,and lifelines that enable the erection,placing, and strip
ping crews to work safely and efficiently.In this regard,forms for faces with a vertical
curvature or changing batter usually have self-adjusting walkway brackets that maintain
the walkway decking in a horizontal plane. Ladderway openings in the upper working
deck should be provided with a snap-on guard rope as a minimum and preferably a self
closing personnel barrier.
If catwalks are used for linking alternate bays, they should be built in accordance
with the appropriate design standards for temporary structures and be subject to
regular inspection.
(Photo courtesy Christopher Hicks) to 16 in.) before being compacted by heavy vibratory rollers (Fig. 16.11). If no attempt
is made to compact the edges of an RCC placement, the sides will assume a natural
angle of repose of approximately 50 degrees. Thus, forms are not needed to retain the
basic mass of RCC, but they are frequently used where this angle is not satisfactory for
the design of the structure or to install a facing layer for seepage control and improved
durability (Fig. 16.12).
Facing layers may also provide improved hydraulic performance or a more aestheti
cally satisfying structure. The facing mixture may be either conventional concrete or the
roller-compacted mixture. Among the facing construction approaches is the use of grout
enriched vibratable RCC (GEVR) and grout-enriched RCC (GERCC). For GEVR facings, grout
is placed on the previous RCC lift. Then
uncompacted RCC material is placed over
the grout and internal vibration is used to
produce the facing by drawing the grout
up into the RCC. For GERCC facings, grout is
added to uncompacted RCC and vibrated
together, basically producing a mixed-in
place conventional concrete.
Many projects have used traditional
forming systems to form the vertical,
stepped, and sloped faces of RCC. These
forming systems may be used for conven
tional concrete facing placed before or after
the RCC has been deposited, for conven
tional concrete facings placed concurrently
with the RCC, or for RCC placement directly
against the forms{Fig. 16.13and 16.14).
More detail is provided in ACI 207.5R and
References 16.2 and 16.3. Precast concrete
panels may be used as forms instead of
traditional formwork for these applications.
The formwork must be able to withstand
the forces created by internal vibration
of conventional concrete and surface
compaction of adjacent RCC. To reduce
Fig. 16. J 2: Reservoir RCC dam facing forms (Photo courtesy Olympic Panel Products LLC)
lateral pressure on the forms, smaller pan
surface vibrators are sometimes used adjacent to the formed face rather than the heavy
vibratory rollers. The choice of forms depends on the dam size and location as well as
local availability of equipment and labor. Consideration should be given to the tie system
because RCC concrete has very low concrete strengths and slow rates of strength gain.
RCC can also be placed directly against sllpformed curbing or facing elements placed by
powered equipment such as that used to construct highway median barriers. RCC place
ment can be started as early as 8 hours after the slipforming is completed. This method is
appropriate for projects that require long continuous placement of the elements. Figures
16.15 through 16.18 show some of these alternatives schematically.
Existing earthen and masonry dams are sometimes repaired by replacing or covering
their previous facing with a new concrete facing. A combination of cantilevered or braced
face forms and wood bulkheads used to place alternate monoliths are shown in Fig. 16.19.
CHAPTER 16
Fig. 16.14: Anchors for forms with RCC placed
•
Fig. 16. 13: Short cantilever form for two curb
steps of facing concrete on RCC dam (Photo directly against vertical face (Photo courtesy Fig. 16.15: Precast concrete blocks or slip·
courtesy Ahmed F. Chraibi) of Christopher Hicks) formed concrete placed by a curber may be
used to shape either vertical or stepped faces
before the RCC is deposited (Image courtesy
Portland Cement Association)
nchor
CONVENTIONAL CONCRETE Fo
PLACEO AGAINST FORMS I
IN 1· TO 2-FT LIFTS RCC
Convention
concrete
Fig. 16.16: Temporary forms can be used to Fig. 16.17: Precast concrete panels serve as Fig. 16.18: Conventional form panels may
shape conventional concrete facing after permanent forms for RCC, supported by shape a vertical face for RCC placements
placement of the RCC (Image courtesy Port· strongbacks anchored in lower lifts of RCC or form a layer of conventional concrete to
land Cement Association) (Image courtesy Portland Cement Association) prevent seepage into the RCC dam. Forms
must withstand vibration and possible
impact from placement equipment (Image
courtesy Portland Cement Association)
16.6 Foundations or Starting Lifts
Initial lifts of mass concrete structures may
be founded on rock or down in a rock cut,
which prevents the use of cantilever forms.
Special footing forms are then used, which
must be tied down to pins or anchors
drilled and grouted into the rock surface.
Forms with vertical studs and no bottom
plate may be set in place and held while
extension pieces are nailed to the studs
to fit the shape of the rock bottom. The
sheathing is then similarly cut to fit this
irregular surface. Tie rods, sometimes called
"hog rods; connect the form wales to the
grouted connection in the rock. As a reac
tion to the pull on these rods, jack pipes or
similar struts are used to resist the pull until
the concrete is in place. Threaded adjust
ment screws or a wedge device are used
for the fine adjustment of the form align
ment with these jack pipes. The pipes are
removed for reuse as the concrete is placed
against the form.
Fig. 16. I 9: Forms for Gilboa earthen dam facing replacement with concrete placed in alternate
monoliths (Photo courtesy Barnard- D.A. Collins JV)
CHAPTER 16
Providing water for curing and washing, and air for cleaning the form and vibrators is
sometimes done by mounting outlets on the form with hoses connecting them to distri
bution lines on the ground. In other cases, twin pipes (one air, one water) are carried up
through the concrete the full height of the structure.These must be grouted tight at the
completion of the job.They are frequently held in position by attachments on the form
that hold them a foot or more back from the face of the concrete.
Insulation of mass concrete forms may be required to prevent heat loss (refer also to
cold weather protection discussed in Chapter 12). This insulation is frequently sprayed on
the forms, but insulation blanket material is sometimes attached.Insulation blankets may
trail from the lower edge of the form to protect concrete of the previous lift, and tarpaulin
enclosures around formwork are sometimes used together with heaters or steam under
extremely cold conditions.
Fig. 16.22: RCC dam spillway concrete place
ment and forms (Photo courtesy Ahmed F.
16.8 Planning and Supervision Chraibi)
Because of the large volume and numerous lifts on a large mass concrete job, there are
many areas for possible human error in preparing forms for concreting, such as:
Ties not secured;
Wedges not secured;
Corners not adequately tied;
Wales not continuous across panel joints; and
Washout holes not plugged.
Good supervision and well-qualified form watchers are essential to prevent such occur
rences. The cost of correcting such errors prior to concrete placement may be incon
sequential when compared to the expense of an interruption in production sequence,
blowout cleanup, or injuries that might result.
Maintaining continuous, uniform production rates is most critical in mass concrete work.
Therefore, monoliths with special recesses such as galleries, tunnels, armor steel, and
penstock tubes must be carefully planned so as not to slow up the entire operation. Preas
sembly of all unusual form items helps greatly. On a large mass concrete job, a highly effi
cient, well-equipped shop is needed. Labor-saving tools and material handling equipment
are well worth the expense. Good coordination of material flow to the construction site is
essential. In some instances, intermediate placements are made within a lift to remove a
time-consuming operation such as a gallery floor and gutter from the overall construction
sequence. Precast gallery walls and crown
have proved economical, and precast
gallery tunnel segments are used in RCC
applications {refer to Fig. 16.23).
16.9 Tolerances
Overall quality of work in building and
erecting forms must be such that speci
fied tolerances can be maintained in the
finished structure.ACI 117-10, �specifica
tion for Tolerances for Concrete Construc
tion and Materials." presents tolerances
for all types of concrete construction in
specification format. Wherever the ACI 117
specification is used, its tolerances for mass
concrete must be met. Tolerances are also
indicated for related work such as mono
lithic water-conveying tunnels, siphons,
conduits, and spillways.
Tolerances for completed mass concrete
construction provide some guidance as to
the accuracy required in form construction
and installation.ACI117 presents toler
Fig. 16.23: Staging of precast gallery tunnel units (Photo courtesy Christopher Hicks)
ances for completed mass concrete in a
separate section, indicating that the speci-
fier should designate which portions of the structure are mass concrete.ln making the
designation, care should be taken to distinguish between designation as mass concrete
Crons.ec
- tionol dimension thickness +I in.,-3/4in.
REFERENCES
16.1. "Gravity Dam Design,� u.s. Army Corps of Engineers Engineering Manual, EM 1110-
2-2200, June 1995, 88 pp.
16.2. "Roller-Compacted Mass Concrete; U.S. Army Corps of Engineers Engineering
Manual EM 1110-2-2006, Jan. 2000,73 pp.
16.3. "Facing Systems for Roller-Compacted Concrete Dams & Spillways;EB 400, Port
land Cement Association, Skokie, ll, 2001,46 pp.
17: TUNNEL AND SHAFT FORMWORK
Many types of structures, such as tunnels, shafts, conduits, powerhouses, or defense
installations, are built underground. Each structure has different formwork requirements,
but their construction is similar in one respect-adverse working conditions such as dirt,
water, high noise level, artificial lighting, restricted access, and a confined working space.
Restricted access and limited working space are major factors in the design of formwork
for underground structures. The form designer must provide forms that are suitable for
use with the specified concrete placing procedures and the size of the structure being
cast, which can be quite large (Fig. 17.1 ) .
Most multi-use formwork for underground structures has been developed over the
years by a few form design and fabrication companies that have specialized in tunnel and
shah forms. The highly developed basic form arrangements are readily adaptable to the
vast majority of individual project requirements. Such companies can provide precise
information on proven forming arrangements.
This chapter emphasizes the techniques of underground forming for concrete linings of
tunnels and shafts. Cut and cover work-built in an excavation and later backfilled-pres
ents less rigid space limitations than true underground construction, and the concrete
placing methods are similar to those used for aboveground structures. Cut and cover
tunnels may be any shape but are more likely to be rectangular than driven tunnels,
particularly transport tunnels (Fig. 17.2).
CHAPTER 17
Rates of advancement of up to 1000 ft
per day are common. The efficiency of the
operation is predetermined by the degree
of workability and consistency of the
concrete, as well as skill of the concrete
placing crew and finishers. The number of
side form units needed is determined on
the basis of the optimum rate of advance
ment, the specified stripping time (usually
12 hours), and the speed of handling of
the units.
Arch forms or side wall forms are gener
ally extended from the traveling bridge Fig. 17.6: lnverr forming for open cut sewer
frame and pressed against the curb or the with anchorage units placed for exterior and
upward curving invert. interior forms for next stage
Designers sometimes show the longi Fig. 17.3: Typical circular and horseshoe
tudinal joints at each side of the invert at tunnel sections showing division for
right angles to the inside surface of the concreting
tunnel. Making the joint perpendicular
to the inside curved surface is often
not necessary, particularly for tunnels I
that are not for rapidly flowing water. A
horizontal joint is easier to do well on a
production basis. A 90-degree invert with
a horizontal joint along each edge makes
45-degree joints with the inside surface
of the tunnel, which are satisfactory if the
joints are properly cleaned before placing Fig. 17.4: Simplified drawing shows how both Fig. I 7.7: Circular invert bulkhead with form
the arch concrete. wood and metal may be used for curb forms for casting integral curb in background
Sometimes, a depressed keyway below (Photo courtesy MEVA Formwork Systems)
the level of the joints is also shown.
Keyways in these joints are difficult to
construct while maintaining the quality
of the joint, and are usually not needed to
resist shear. Setting a beveled strip to mold
the keyway usually involves overworking
the joint surface to the detriment of the
surface mortar and therefore to the ulti
mate quality of the joint. Also, the keyway Fig. I 7.5: Wood invert forms without previ
catches debris and adds considerably to ously placed curb, and steel invert forms
the work of joint cleanup by sandblasting attached to curb
or high-pressure water jet. It is the clean-
ness and quality of the surface and the absence of any visible water when concrete is
placed that assures a superior joint-not the keyway.
CHAPTER 17
invert. The joints are fused to create a plastic tube. Normally, the excavated soil/stone
is shotcreted to make a smooth surface to attach the liner. The liner with filter fabric is
attached to the shotcrete using watertight grommets at points of attachment. When
plastic waterproofing liners are used, the form designer may not use rock anchors or spuds
to restrain the form. Rock anchors will penetrate the liner and spuds will damage the
liner, causing leaks in the waterproofing system. For this reason, lateral and uplift forces
are resisted by anchors to the invert or curb. Depending on placement assumptions and
tunnel configuration, the forces resisted by the curb anchors may be very large.
Fig. 11. 19: Cut-and-cover construction for dual roadway runnels with temporary bridge serving to strip when it is needed at the toe of the
intersecting roadway above (Photo courtesy PER/ Formwork Systems, Inc.) advancing slope of fresh concrete.
CHAPTER 17
17.2.3 Cuf-and-Caver Consfrucfion
Cut-and-cover tunnel construction (Fig. 17.19), used largely for shallow tunnels and
conduits, is a variation of the other methods. The bulkhead placing technique is used for
cut-and-cover work, but additional external wall forms may be required in earth excava
tions. The outside forms may be braced against the excavation and the previously placed
tunnel invert. The inside forms are like those used for regular underground work. Form ties
are used to resist lateral pressure and spreaders maintain proper spacing and alignment.
Because the exterior of the structure is accessible from above, the outside forms for
cut-and-cover work are usually positioned with a crane. The outer forms are often discon
tinued near the arch crown to leave room for the placement of concrete. This area is later
finished by hand. Concrete is delivered by bucket, pipeline, or conveyor.
,
clearly indicated on the drawings. Methods
Si
l ck line
of supplemental strutting or bracing
=��-
for abnormal conditions should also be
�
indicated.
:=.:.::;;
: ;;
..... . .
Con veyor
CHAPTER 17
17.3.3 Vibration and Form Access
External vibration is often required because
of the cramped, curved space within the
form, and forms must be able to withstand
forces set up by this vibration. Several
vibrators may be attached to the forms
and moved ahead to follow the advancing
slope of fresh concrete.
Access to the space behind the forms
should not be overlooked. Access doors
and holes should be placed in the form at
convenient locations. Most commercial
forms come equipped with doors that are
dogged or wedged tight and opened as
needed for concrete placement, vibra
tion, and inspection. Smaller holes are
needed for the insertion of bolts and
grout pipes. These holes are usually
closed off by a bolt with an insert plate
attached at the end, the bolt being held
in place by a yoke arrangement.
•-� - - --
basis of experience, it can be safely predetermined by tests in the laboratory. It is recom
mended that at the start of a tunnel arch concreting operation, the minimum stripping
time be 12 hours for surfaces exposed to view and 8 hours for construction joints. If the
specifications provide for a reduced minimum stripping time based on site experience,
--
� -- such reductions should be in time increments of 30 minutes or less and should be estab
?
lished by means of laboratory tests and visual inspection and surface scratching of sample
areas exposed by opening the form access doors. The use of pullout tests or the maturity
method can provide indications of the early strength needed for stripping. Special atten
Fig. I 7.25: Wood form for transition from tion should be given to the stripping time for arch forms when there is a possibility that
square to round section (Photo courtesy unvented groundwater seepage could become trapped between the rock surface and the
Universal Forest Products) concrete lining, requiring higher concrete strength to be developed before stripping.
Table 17.1: Tolerances for monolithic water-conveying tunnels, siphons, 17.6 Tolerances
conduits, and spillways (ACI 117·10) Tolerances in underground construction
depend on the use of the finished struc·
Type of var.at1on Max1mum dev1at1on
ture. High-velocity conduits, for instance,
Horizontol deviation
require close tolerances to assure correct
Centerline alignment :tl/2in.
Inside dimensions :tO.S%times inside dimension behavior of the fluid and to prevent erosion
of concrete. Table 17.1 lists tolerances
Verticol deviotion
:�;1/2 in.
for monolithic water-conveying tunnels,
Profile grode
Surloce of invert ±1/.4 in. siphons, and conduits from ACI 117-10,
Surface of side slope ±1/2 in. MSpecification for Tolerances for Concrete
CHAPTER 17
parallel to the flow direction. Maximum
allowable gradual irregularity is typically
1/4 in. for these latter finishes.
17.7 Shafts
Shafts are usually required to provide venti
lation and speed construction of tunnels
that are greater than 3 or 4 miles in length.
They may also be an integral part of the
design, such as surge or intake shafts in a
hydraulic tunnel, or mine shafts that are
built apart from any tunnel lining opera
tion. Shafts may also be the way of access
for installing the tunnel forms, as seen in
Fig. 17.27.1f the shaft is to be permanent, a
lining of concrete is usually specified. This
construction must be carried out within a
very limited space just as in tunnel work,
but with the added hazard of exposure to
falling objects and loose rock. Work often
must be done from hanging or integrated
work platforms, depending on the lining
and excavation procedure.
Most shaft lining is done while the shaft
is being sunk because federal, state, or local
regulations often give a maximum depth
beyond which the shaft cannot be sunk
without timbering or lining. Usually, when
a depth of approximately 30ft has been
reached, the excavating is discontinued
while the shaft section is lined, the forms Fig. 17.27: Lowering tunnel form down an access shaft (Photo courtesy MEVA Formwork
being supported on a platform laid on top Systems)
of loose muck.
Shafts may also be lined from the bottom
upward, as shown in Fig. 17.28. When this
method is adopted, the forms for each
successive lift are supported on anchors
in the previously placed lift. Slip forms
(Chapter 18) can also be used in shaft lining
when it is possible to excavate full depth
before beginning the lining operation.
When the slipform method is used, the
shaft form is suspended from a number
of wire rope or tubular steel slipform jacks
that are supported from a frame at the
top of the excavation (Fig. 17.29). Cable
jacks may be lift jacks only if the system is
used just for concreting. Dual-action jacks
are provided when the system is used for
setting steel and inserts before concreting
begins. Concrete is placed in the forms
while the jacks intermittently raise the
slipform system. Some slipform jacking
systems are reversible and can raise as
well as lower the slipform system, thereby
enabling the deck to be used for setting
reinforcing steel, inserts, or blackouts
before concreting begins.
Care must be taken to assure an accurate
circular cross section of the forms because
strength of the form may be impaired
decks, concrete supply hoppers,and finishers' platforms are attached to and carried by
the moving formwork,as shown in Fig. 18.4and 18.5.1n some cases, fixed forms such as
sheathing,rock,earth, or existing concrete may be on one side,with the slip form on the
other. For shahs below grade and other special structures,jacks may climb on cables or
jack rods suspended from above.
Advantages of slip forms are speed and the production of a monolithic structure
through continuous sliding of the forms. In many cases,the cost of materials and building
of the slip forms is approximately the same as for fixed forms that would do the same
job. The economy comes from the shorter construction time and being able to install
inserts,elevator shaft beams,and other items from suspended work platforms rather
than erecting separate scaffolds (Fig. 18.6) or by riding up with the slipform,as shown
in Fig. 18.7. For vertical construction, savings often do not develop unless the structure
CHAPTER 18
is approximately 40 ft or taller. The relative costs of slip forms, jump forms, and climbing
forms are often compared when considering options for particular projects.
Slipform construction is most efficient where there are few projections perpendicular to
the direction of slide. It must also be remembered that the process requires a more expe·
rienced crew at all levels; forms should be designed and built by individuals experienced
in slipform work, and the sliding operation must be carried out under careful, experienced
supervision. Slipping also requires complete planning of delivery and installation of all
embedded items: dowels, reinforcing bars, weld plates, door bucks, plumbing blackouts,
and the like.
Slip forms used for underground construction or mass concrete structures should
comply with applicable recommendations for those types of construction in ACI347R-14,
�Guide to Formwork for Concrete,�as well as provisions therein for sliding forms.
The forms consist of three sections: yokes, wales, and sheathing. The yokes have two
primary functions: 1) to keep the forms from spreading; and 2) to transfer the load of the
Fig. 18.7: 5/ipforming of large-diameter post
forms to the jack. The wales stiffen the forms and are braced to carry the load to the yokes.
tensioned silo and simultaneously lifting the
The finishers'platform and working deck are connected to the wales, and the wale-yoke
roof structural steel with the jacking system.
connections should be designed to withstand these loads.
(Photo courtesy Scanada)
(18.1)
where c,,..... is the maximum lateral pressure, lb/ft1; c1 is the slipform vibration factor,
tb/ft1; c1 = 100 lb/ft1 for partial internal vibration in shallow layers; c1 = 150 lb/ft1 for full
internal vibration in shallow layers; R is the rate of concrete placement, ft/h: and T
is the temperature of concrete in the forms, oF. The value of c1 = 100 lb/ft1 is justified
because vibration is slight in slipform work; the concrete is placed in shallow layers of
6 to 10 in. with no revibration (Fig. 18.9). For some applications, such as gas-tight or
Yokes
The yokes (Fig. 18.1 O) may be made of metal or wood and should be stiff enough to
adequately resist lateral pressure from the concrete. They must transfer the full load of the
forms, finishers' platform, and working deck to the jacks. They should be designed with
enough clearance above the forms to allow the horizontal reinforcement and embedded
items to be installed in the correct location prior to being submerged in the rising
concrete.
Frames called dummy yokes are sometimes placed between jacking yokes to
resist lateral loads by holding the wales in place. These frames are commonly used to
support the forms at wall intersections or wherever the wales on one side are more
easily supported than those on the other side. Hence, the dummy yokes are generally
constructed to transmit their loads through the wales to the nearest main yokes on the
side that is most easily supported.
Work deck dead and live loads must be transmitted to the jacking system. Often, the
deck is framed in a combination of wood joists and steel beams. In Fig. 18. 11 , inverted
l-shaped hangers for the deck beams project up through the deck and sit on pairs of steel
channels spreading the end reactions to a pair of yokes.
space
Wales
Fig. 18.10: Yokes should be designed with The timber or steel members making up the wales (Fig. 18.10} must be stiff horizontally
adequate clearance below the yoke beam to to withstand the lateral pressure of the concrete tending to make the forms bulge out
permit efficient placement of reinforcing steel between the yokes. They must also be stiff vertically to transfer the weight of the forms
and the friction force to the yokes without excessive deflection. When the span between
jacks reaches approximately 6ft, the wales should be braced for improved rigidity. Diag
onal struts from the wales to the foot of the yoke are often used to provide this stiffness
CHAPTER 18
(Fig. 18.12). For circular shapes such as silos,
the wood wales are often segments cut to
the curve of the structure from wider S4S
2x dimension lumber and combined into
two or three layers.
Sheathing
The form sheathing is normally constructed
of 1 in.nominal board, plywood that can
adequately conform to the required shape
or radius and suitably reinforced with
backup members, 10-gauge steel sheets, or
other approved material.The 1 in.boards
should be straight-grained and finished to
minimize drag. Quartersawn lumber may
be of some advantage in resisting wear but
the increased costs for this material should
be considered. Board sheathing joints
should be vertical so the form will slide
upward without a transverse drag compo
nent {Fig. 18.13 ). Fig. 18. I 1. View showing upper platform template holes for placing vertical reinforcement;
As in other types of construction, staging of blackout form segments; and inverted L-hangers for work deck girders (Photo
swelling of wood forms must be controlled. courtesy Marietta Silos)
Swelling may present a greater problem for
sheathing in slipform work because forms are in continuous contact with fresh concrete
for a much longer period than in conventional construction. Use of pretreated sheathing
or presoaking either in water or in a waterproofing preparation will reduce swelling during
the sliding operation.A small gap (1/ 16 to 1/8 in.) at the joints between sheathing boards
may be left to take up the swelling.
The forms should provide some working space above the level of the fresh concrete but
should not be so high that they interfere with the placing of horizontal reinforcement.
The outside panel of the exterior wall forms can be constructed somewhat higher than
the inside (Fig. 18.14).This provides a splash board to protect the finishers working on the
work platform below.
Batter
The forms should be constructed with a slight batter or slope so that they will be self Fig. 18.12: Interior view of wales, braces, and
clearing as they slide (Fig. 18.14).The top of the forms should be slightly smaller than clamps transferring load to foot of steel yoke;
the required wall thickness and the bottom of the forms slightly larger. In this way, the wire rope hangers support interior work plat
concrete can take its final shape approximately halfway down the form and is completely form (Photo courtesy Marietta Silos)
free of the form at the bottom.The amount
of batter is a question upon which many
successful supervisors differ. A range from
1/8 in.to 1/2 in. in 4ft is representative of
current practice. Sometimes the form for
the outside face of an exterior wall is left
vertical.
Form Depth
The depth of the forms depends on the
rate of slide and the time required for
concrete to strengthen enough to be self
supporting.The minimum depth of forms
is 3- 1/2 ft with the most commonly used
depth being approximately 4ft. Forms up
to 5 ft have been used in winter weather
or when greater sliding speed is desired.
For special applications such as piers and
single-sided underground shaft slip forms,
Fig. 18. 13: Vertical boards attached to braced wales are the sheathing choice for this silo slip
forms up to 8 ft deep have been used.
form project; long vertical jacking rods are visible at each yoke; note wood-framed blackouts in
walls (Photo courtesy Younglove Construction, L.L.C.)
�z�"
the jack capacity. Typical slipform jacks have load ratings from 3 to 25 tons. These jacks
may be manual, pneumatic, electric, or hydraulic (Fig. 18.15).
High-capacity jacks of 15 to 2S ton lifting capacity have been used for slipforming high
rise building cores and multi-cell industrial structures. A structural steel frame or jacking
grid is located some 8 to 10ft above the main deck. High-capacity jacks push against
the grid and (by means of hang rods attached to the slipform yokes) pull the forms, work
decks, and platforms along.
Some advantages of the high-capacity jacking system are:
A smaller number of larger slipform jacks make it easier to position them to miss
major openings, areas of concentrated reinforcement, and discontinuous walls.
Plumb and twist of the form are easier to control.
Fig. 18.14: Batter strip placed between upper It leads to a multi-deck forming structure, allowing materials storage and providing a
wale and sheathing will give enough batter convenient way of stabilizing vertical reinforcing bars and prefabricated wall-column
to sheathing to help reduce friction assemblies.
The working deck can be economically enclosed to protect it from the elements.
High-capacity slipform jacks can also be used to lift heavy construction loads as well as the
slip forms (Fig. 18.16). Loads in excess of 400tons have been successfully lifted.
Usually, lifting loads are limited not by jack capacity but by possible buckling of the rods
on which the jacks climb. The jack rods must be designed for anticipated loads and be
properly braced where not encased in concrete. If they are to be used as reinforcement,
consideration must be given to splices and their low bond value as plain bars.
If the jack rods are to be retrieved, they must not bond to the concrete. Usually a thin
pipe sleeve approximately 3 or 4ft long is placed around the jack rod and attached to the
yoke or jack so that it is carried upward with the forms. Because the short length of pipe
is pulled upward with the forms, the rods are left standing in a small hole in the concrete
and can be pulled out after the slide is completed.
Jacks or other lifting devices should be equipped with mechanical dogs or other auto
matic holding devices to provide protection in the event of power outage or failure of the
lifting mechanism.
A jacking system that provides simultaneous movement of the entire form in small
preset increments of approximately 1in. at a minimum of 3-minute intervals is desirable.
Fig. 18.15: Jack in place on rod steel pushes The pumping and control system is usually placed near a central location on the work
up on lifting frame yoke; long reinforcing platform, and a backup pump is desirable (Fig. 18.17). To avoid unplanned cold joints,
bar verticals have been passed downward especially when such an occurrence would adversely affect the integrity of the struc
through holes in the top working platform ture, reserve jacking and placing equipment and standby construction service equip
(Photo courtesy Marietta Silos) ment should be available to maintain a continuous operation. If it is not feasible to keep
duplicate equipment on standby, then all materials needed to halt placement just as at
a preplanned joint should be kept ready. Such materials might include wood joint strip,
extra dowels, and waterstop joint materials for water-retaining structures or structures
requiring positive sealing.
CHAPTER 18
An adequate supply of concrete to maintain the planned rate of slide is required. Mate
rials should be conveniently stockpiled and resupplied to the deck to maintain the flow of
work activities without interruption. During the first filling of the form, the placement rate
should be limited to that for which the form was designed. Design drawings should show
a maximum initial filling rate as a function of the temperature of the concrete placed in
the form.
Although the maximum rate of slide must be carefully predicted and planned for, the
actual rate must be controlled by an experienced field superintendent who is qualified
to make adjustments when changing field conditions call for them. The superintendent
must see that the slide operation is proceeding neither too fast as to causeNblowoutsN
(soft concrete falling out from under the forms), nor too slow as to cause "liftsN(concrete
sticking to forms and ripping away from the concrete below). To establish safe lifting rates,
the level at which the concrete in the form is hardened can be checked frequently by the
use of a probe.
CHAPTER 18
has been done, but it is still regarded as
primarily an experimental technique.
Because most horizontal slipforming is
against a fixed form support such as rock or
earth, the operation is essentially a consol
idating-screeding-finishing operation. For
some projects, a series of machines are
used to trim-finish the earth; place, consoli
date, and screed the concrete; and finish
the surface (Fig. 18.21). Slipform machines
move on rails, track crawlers, wheels, or
a shaped excavation. The intake of the
machine is a trough designed to distribute
concrete uniformly to all parts of the form.
The concrete is consolidated by a vibrating
bar or a rack of vibrators parallel to and
a few inches ahead of the leading edge
of the form. The fresh concrete can also
be consolidated by hand vibrators. Most
highway and canal pavers are essentially
placers and spreaders. Edges are slipformed
and occasionally top surfaces, but most top
surfaces are spread by blades or rotating
augers and then finished by a plate or a
rotating cylinder.
Fig. 18.21: Horizontal s/ipforming is common for long canal lining operations. (Photo courtesy
18.2.1 Design and Construction
Guntert & Zimmerman)
Considerations
For the large slipform pavers or canal liners, consideration should be given to unsymmet
rical and eccentric loading and the fact that the machine must be regularly disassembled
and reassembled as it encounters siphons, bridges, and chutes along the waterway or
highway. Some of the larger machines are hinged so that sections may be passed through
or beneath structures. Vertical or lateral deflections, particularly of long span machines,
must be investigated, and sufficient rigidity provided to ensure that concrete tolerances
will be met.
Vibration may be used ahead of the slip form, but consolidation must be completed
as the concrete passes under the form. Vibration of the slip form itself does not provide
proper consolidation, apparently due to lack of means to supply additional concrete
needed to fill the voids. The trailing edge of the slip form is usually adjustable to positions
somewhat lower than that of the leading edge. This improves consolidation and tends
to mold the concrete more closely to the subgrade. Too low a setting of the trailing edge
causes tearing, rather than smoothing, of the surface. On some machines, the slip form is
followed within a few feet by an uironern plate or by a surface texturing drag that, under
favorable conditions, leaves a surface that requires little or no hand finishing.
Concrete on Slopes
Placement of concrete on slopes may be accomplished by use of a weighted, unvibrated,
steel-faced slipform screed on edge supports. An efficient screed width has been found by
experience of practice to be approximately 27 in. in the direction of movement. The screed
may be pulled up the slope by equipment located on the shoulder or by air or electric
Fig. 18.26: Canal slipforming with a conveyor spreader for placing, a cylinder finisher, and a
work bridge for touch-up and application of curing compound or membrane (Photo courtesy
Gamaco Corporation)
hoists mounted on the slip form. The concrete vibrators are manually operated just ahead
of the slip form rather than mounted on the form. If the form is vibrated, it will cause a
swell in the finished surface emerging from the trailing edge. Figure 18.22 shows the cross
section of a simple slipform screed.
CHAPTER 18
or canal supports the working platform and
distribution system. The slip form is a steel
plate, curved up at the leading edge, extending
across the bottom and up the slopes of the
canal and shaped to conform to the finished
surface of the lining. When a distributor plate
is used, it is fastened to the leading edge of the
slip form and moves upward on a steep incline
to the working platform. On some of the
machines, a continuous row of hoppers in the
working platform feeds into drop chutes, each
supplying one compartment of the trough
below. Concrete is dumped, usually from a
shuttle car or wiper conveyor on the working
platform, and is guided to the trough below by
the distributor plate or the drop chutes.
As the concrete passes out of the bottom
of the trough and under the slip form, it is
Fig. 18.27: Crawler-mounted highwaysfipform paver receives concrete from moving
consolidated by a vibrating bar parallel to and
conveyor(Photo courtesyGuntert&Zimmerman)
a few inches ahead of the leading edge of the
form. Consolidation must be accomplished as
the concrete passes under the slip form. The
trailing edge of the slip form is usually adjust
able to positions somewhat lower than that of
the leading edge. This improves consolidation
and tends to mold the concrete more closely to
the subgrade. Too low a setting of the trailing
edge causes tearing, rather than smoothing, of
the surface. On some machines, the slip form is
followed within a few feet by an•ironerwplate.
In other cases, a separate finishing and curing
jumbo follows the slip form at some distance.
For large channels {bottom widths of SO to
110ft), it is impractical to build machines to
span the entire waterway. The slope paver is
a crawler-mounted slip form that places the
concrete lining on one side slope and the adja
cent 8 to 10ft of the invert. After the opposite
side slope is similarly completed, the invert is Fig. 18.28: Sfipformed concrete pavement after vibration, screeding, finishing, and
finished by horizontal pavers. All three opera- texturing(PhotocourtesyGuntert&Zimmerman)
tions are kept on line and grade electronically
through sensors probing guide wires.
Highway Pavers
The slip form used for highway pavements1u is similar in principle to the slope form
pavers. No fixed side forms are required as the side forms of the machine slide forward
with the paver, leaving the slab edges unsupported (Fig. 18.27 and 18.28). The concrete
is deposited either on the subgrade ahead of the paver or into a hopper box. Following
spreading by a rotating auger or dozer-type strike-off blade, the concrete is consolidated
by vibration and shaped by an extrusion plate or a rotating cylinder finisher. Flat, para
bolic, or hip crowns can be provided with a quick change device for transitions in and out
of horizontal curves. Surface elevations can be maintained by electronic controls. Slipform
machines are available for curb and gutter placement and for highway barriers (Fig. 18.29).
Cast-in-Place Pipe
Cast-in-place pipe is a continuous nonreinforced concrete conduit having no joints or
seams except as necessitated by construction requirements. It is built in a previously
excavated trench that has a semicircular bottom and vertical or nearly vertical sides. The
outside lower portion of the pipe is formed by the trench and the corresponding inside is Fig. 18.29: Machine for s/ipforming
formed by a specially designed slip form commonly called a boat or a sled, or by a more highway barriers in place (Photo courtesy
complex slipform machine. The inside of the remainder of the pipe is formed by either Gamoco
CHAPTER 18
the crane. Reinforcement and inserts (Fig. 18.35) are designed and placed to allow lifting
without cracking the panel. Bracing must be provided to align and secure the panels
against wind loads until the roof diaphragm is structurally complete.
A compacted fill or temporary slab may be used in place of the floor slab for the casting
of tilt-up units as long as it meets requirements for construction loads and smoothness.
After the casting surface is completed and covered with a parting compound, the tilt-up
units are cast directly on the floor slab. The contractor must select a panel arrangement
that maximizes the available floor area and results in reliable panel joint designs. ACI117
provides tolerances for tilt-up panels and other slab dimensions. Forming the panels with
common side forms is an effective solution, but the form boards must provide enough
resistance to the pressure of concrete placement to maintain panel edges square and in
alignment within tolerances. Laminated strand lumber (LSL) has been found suitable for
this application and can be reused approximately four times. Fig. 18.34: Edge forms for tilt-up work can be
Often, successive panels may be cast one atop the other, thereby reducing the area attached to the concrete ba�e slab by nailing,
required for temporary slab casting and working space. Only edge forms and frames to drilling, or adhe�ives; ru�tication strips
form windows, doors, or other openings are needed. Occasionally, plans may call for a half provide pattern to the later exposed surface
pilaster to be cast along each edge of the wall panel. References 18.6 and 18.7 provide (Photo courtesy Tilt-Up Concrete Association)
detailed information on design and construction methods.
CHAPTER 18
the hyperbolic paraboloid18•11 with a doubly curved surface that can be generated by the
movement of a straight line. To form such a shell as a roof structure, joists can be spaced
along the path of the generating line and the sheathing can then be warped to fit the
doubly curved surface formed by the straight members. Most roof structures are formed
on curved forms supported by shoring or falsework. However, the hyperbolic paraboloid
cooling tower (Fig. 183
. 9), frequently associated with power generation facilities, is usually
constructed using jump or climbing forms. Folded plates differ from shells in geometry,
but the shape can be quite complex, requiring the same care in form design and building
as the shell.
Because the concrete of shell structures is often left exposed as an interior ceiling, atten
tion must be given to the surface texture of the forms. A test panel approved in advance
by the engineer/architect should be prepared to demonstrate the required surface texture
and provide a comparison standard for acceptance purposes.
Fig. 18.38: Concrete shell roof structure of
multiple joined hyperbolic paraboloid shapes
18.5. 1 Shell Form Design Considerations (Photo courtesy PER/ Formwork Systems, Inc.)
The engineer/architect must provide the geometry of the finished structure with coor
dinates sufficiently close together to give the desired results. For thin shell structures of
large span or unusual proportions, ACI334.1R-92, "Concrete Shell Structures- Practice
and Commentary,� recommends that the engineer/architect also provide a decentering
drawing before the formwork engineer/contractor selects the method of shoring.
Due to the special shapes involved, tolerances based on functions of these shapes
should be specified by the engineer/architect in the bidding documents. A contour
drawing of the surface to be formed may prove helpful for irregularly curved surfaces. Due
to the high cost of forming shells and folded plates, travelers or reusable form sections are
often developed for structures having recurring elements of the same shape.
Thin section structures often have a large dead load deflection when the forms
are removed. Edge members and free edges may have both horizontal and vertical
components of deflection. The engineer/architect should specify the formwork camber
required to compensate for these deflections. This same deflection may be the cause
of decentering problems, particularly where edges deflect inward and tend to pinch or
Fig. 18.39: Concrete shell cooling tower cast
bind the formwork.
using climbing forms (Photo courtesy Doka
Because a three-dimensional analysis of complex formwork shapes is required, ACI347R
USA)
recommends that this be done by engineers having the necessary special qualifications
and experience. Unsymmetrical or eccentric loadings may occur in the falsework members
during concrete placement. Stresses occurring during erection and decentering of the
falsework or movement of travelers should also be considered.
The forms and shores for shell structures must be braced to resist all foreseeable lateral
loads, particularly wind. Suction created by the wind on the leeward side of the shell form
work should be considered. Such formwork should be anchored as a whole against uplift
and sheathing should be secured.
Construction loads are very important in this type of construction because they may be
large in relation to the dead load of the concrete. For example, the dead load from a3 in.
shell is approximately40 lb/ft2, whereas the minimum recommended construction live
load is SO lb/ft1• The placement of concrete on one section of the forms may cause upward
movement of another part. The forms and falsework must be designed to resist the forces
arising from the method and sequence of placement. It is also important to accurately
estimate the dead load of the shell formwork.
Because the weight of the supporting forms and falsework may be equal to or greater
than the design live load, the form should be designed so it will not bind or hang up and
overload the structure during decentering. Joints in the forms should be planned so that
no keying action can develop because of movement during the placement of concrete.
The forms must not become keyed into the concrete in a way that would hinder stripping
or transfer the load of the falsework to the shell. Joints that can be loosened, connections
that are free to act as a hinge when a locking pin is removed, or small panels and wrecking
strips that can be removed just before decentering begins often help eliminate form
hang-up and binding.
The formwork drawings should show the camber to be provided, the recommended
sequence for placing the concrete, and the sequence for stripping or decentering. Camber
should include an allowance for settlement or deflection in the forming system as well
as any camber specified by the engineer/architect to compensate for deflection of the
structure itself. The engineer/architect should check formwork shop drawings to see that
CHAPTER 18
the structure design live loads. Thus, if for any reason the shell form clings to the shell as
the supporting falsework is loosened, it may overload the new concrete structure. Further
complications arise because shell and folded plate structures deflect appreciably when
they become self-supporting, and the forms may be caught or bind against the structure
as it begins to deflect. These problems may be even more troublesome with prestressed
shells if the shortening during post-tensioning has not been considered.
To meet these conditions, certain precautions have already been suggested in the
designing and building of the forms. The use of form joints that can be loosened, hinged
joints, or small panels that can be removed just beforedecentering begins will relieve
troublesome binding. Formwork must be designed so that it does not act as a dome or
shell itself.
Strength Requirements
ACI347R states that decentering and form removal should not be permitted until speci
fied tests demonstrate that the minimum concrete strength and stiffness (modulus of elas
ticity) specified in the contract drawings have been reached. ACI318-11, NBuilding Code
Requirements for Structural Concrete." requires the use of field-cured beam test specimens
if form removal time is based on development of a specified modulus of elasticity. The
value of the modulus of elasticity must be obtained from flexural testing of the field-cured
beam specimens, not derived as a proportion of the compressive strength of concrete in
the beam specimen.
Where elastic requirements and buckling considerations are the governing factors as
to when the decentering occurs, it may be practical to make the decentering time depen
dent on the deflection of small reinforced test beams to simulate the bending conditions
within the roof shell11
. w
Decenfering Schedule
Deflections in structures of this type may be such that a strict decentering procedure is
necessary for the structure to assume its loaded shape without damage-either to the
structure or the falsework. Oecentering sequences and methods used should be planned
to prevent any concentrated reaction on any part of the permanent structure. Generally,
decentering should begin at points of maximum deflection and should progress toward
points of minimum deflection, with the decentering of edge members proceeding simul
taneously with the adjoining shell. Where edge members are to be reshored, ACI 334.1R
recommends that the engineer/architect specify the spacing of the shoring.
When screw jacks are used in decentering, the amount of vertical movement should be
expressed as the number of turns or fractions of a turn on the jack. The engineer/architect
should provide the decentering instructions, which may be elaborate and complex.
18.6. 1 Applications
Traveling forms are suitable for many types of structures: bridges (refer to Chapter15),
sea walls, floor systems, shell roofs, tunnel linings (refer to Chapter 17 ), culverts, and
Fig. 18.42: Traveling glue-laminated wood falsework was raised 6 ft with hydraulic jacks, on chairs, wood blocks, or any device or mate
each of eight columns, and then shored on tripods during concrete placement; forms were rial that will not crush under the load of trav
lowered the same way, except that the first 4- 1/2 in. of drop was made by draining sand jacks eler, forms, and concrete can be used. Final
atop the tripods (Reprinted from Engineering News-Record, 1958, McGraw-Hill Publishing adjustments are made with screw heads or
CHAPTER 18
tricities in the connections can permit distortion or even failure of the members. These
large eccentricities most often occur in lateral bracing systems.
Detailing deficiencies are sometimes the result of efforts to simplify fabrication and
disassembly and to increase salvage value of the materials used. While there may be no
real harm in such practices, their implications must be realized.
Another common problem is a failure to appreciate and provide for the variety of
partial and eccentric loading conditions that may be encountered during concrete
placement and decentering operations. This is critical when the traveler itself has trusses
of appreciable span. Often, such trusses are designed as simply supported, but redun
dant members are added that enforce continuity between trusses or between trusses
and columns. At other times, continuous trusses or beams are used with little regard for
the effect of uneven decentering, which may result in complete stress reversal in many
members. This may be especially serious where tie rods with little compressive strength
are used as tension members. Fig. 18.43: Rail mounted suspended form
With the foregoing problems in mind, the following suggestions are made: traveler and work platform for placing
Establish the placing sequence on any traveler in advance and follow it closely, with bridge edge beam and sidewalk (Image
the falsework designed accordingly. If this is impractical, then design falsework for courtesy Ooka USA)
a number of alternate placing sequences that will cover all conditions likely to be
encountered.
Plan the decentering procedure during the design of the traveler, and check the
design for stresses during decentering, assuming reasonable variations in the actual
performance of the decentering operation.
where$ is the angle of internal friction of the aggregate, degrees; his the height of aggre
gate placement, ft; and wa is the unit weight of aggregate in a packed condition, lb/ftl.
Approximate values of 4> are 45 degrees for crushed stone and 40 degrees for rounded
gravel. No distinction need be made for larger-sized aggregate because the volumes in
such construction are so large that the aggregate size has little effect.
where R is the rate of rise, ft/h; and r is the time of initial set measured in hours.
If grout is heavier, use the actual density in place of 130 lb/ft3 in the formula. ACI 304.1 R-
92, �Guide for the Use of Preplaced Aggregate Concrete for Structural and Mass Concrete
Applications; indicates that, for most projects, it has been found conservative for form
design to assume a minimum static grout pressure of 1440 lb/ft1•
CHAPTER 18
streaking that will mar the appearance of the finished surface. When significant bleeding
is unacceptable, caulking or sealing of the joints is recommended. For unexposed
surfaces, grout-tight forms of steel or plywood are acceptable. Prefabricated panel-
type forms usually are not suitable because of the difficulty in making grout-tight seals
between panels. Absorptive form linings are not recommended because they permit the
coarse aggregate to indent the lining and form an irregular surface. Form linings, such as
hardboard on common sheathing, are not successful because they do not transmit the
external form vibration normally required.
18.8 Shotcrete
In the shotcrete method of placement, concrete is projected by an air jet (Fig. 18.44)
directly onto various types of surfaces to any desired thickness.18·14 Shotcrete can be
used in numerous ways: for example, to repair dams, retaining walls, and concrete and
masonry structures; to build walls, slabs, and shells; to coat existing brick, concrete,
steel, and masonry structures; to encase structural members for fireproofing; and to line
tunnels and sewers.
There are two shotcrete processes: wet and dry. In the dry process, cement and aggre Fig. 18.44: Pneumatic placement of concrete
gate are dry-mixed and charged into a pressurized feeder. The pressurized dry mix passes allows placement to form free-form shapes
through a delivery hose to a special nozzle where water is introduced. The moistened with limited formwork (Photo courtesy
mixture jets directly onto the surface to be shotcreted. ln the wet process, aggregate, American Shotcrete Association)
cement, and water are mixed in a pressurized chamber and fed wet into the delivery hose.
Compressed air forces a jet of the wet mix onto the surface to be shotcreted.
Shotcreting techniques reduce forming problems because only a single forming or
support surface is required. Vertical walls can be built by shotcreting with only one
backing or forming surface required to support the fresh concrete (Fig. 18.45). Even soffits
can be built up from below against a horizontal surface.
For repair or coating of existing structures, there is no formwork; the pressurized
mixture is supported adequately by the surface being covered. Because the final struc
tural value of a shotcrete repair depends on its bond with the surface on which the
mortar is shot, this surface must be sound and thoroughly cleaned. All coated, scaly, or
unsound concrete or masonry should be removed and dressed down to a solid, newly
exposed surface.
Forms may be of any rigid material such as wood, steel, paper-backed reinforcing
mesh, or sheets of expanded metal, adequately braced to prevent excessive vibration or
deflection during shotcrete placement. Where required for the support of the full weight
of shotcrete, they should be designed to permit the escape of placing air and rebound
during the gunning operations. Provision for escape of air and rebound is particularly
important for thicker structural members. Columns should be formed only on two adja
Fig. 18.45: Vertical walls and pilasters can
cent sides wherever practicable; however, satisfactory results may be obtained where
be built by shotcreting against a single form
three sides are formed provided the width is at least 1-1/2 times the depth. Pilasters may
surface (Photo courtesy American Shotcrete
be formed on two adjacent or opposite sides. The soffit and one side of the beams should
Association)
be formed; this provides the maximum area of escape for air and rebound during the
shotcrete buildup. Forms need be placed for only one side of a waiL
Forms or backing against which shotcrete is placed should be thoroughly secured
to line and dimensions. If forms are to be removed after use, a release agent should be
applied before application of the shotcrete.
Adequate ground (gauging) wires should be used to establish the thickness, surface
planes, and finish lines of the shotcrete. Ground wires should be taut, secure, and true to
line and plane.
Scaffolding should be built so that the nozzleman can hold the nozzle at the optimum
angle and distance from the surface for all parts of the work (Fig. 18.46). The scaffolding
should also give easy access to the shotcrete surface for screeding and finishing, if such is
specified. Scaffolding should be constructed to permit uninterrupted application of the
shotcrete wherever possible. For full details on the placing operation, refer to ACI 506R-05,
·Guide to Shotcrete,� and to the shotcrete machine manufacturer's specifications.
building underwater structures, and holding tunnel sections and other objects in place
underwater.18·1s-1s.16
The tremie pipe is first plugged (Fig. 18.48 and 18.49) and lowered into position. After
the pipe is filled with concrete, the plug is pushed out by the concrete as the tremie pipe
is slightly lifted. The concrete flows out and surrounds the bottom of the pipe so fresh
concrete passing through the pipe does not flow through or mix with the water. The
bottom of the pipe is kept continuously immersed in the fresh concrete.
If the pipe is lifted out of the concrete by accident or to move the pipe to a new
position, the original pipe plugging operation must be repeated. To prevent mixing
of water and concrete and to prevent stiff concrete from obstructing the flow of fresh
concrete, continuous placement is desirable. For best results, the forms are filled rapidly
to minimize laitance formation and the tremie pipe is kept immersed in concrete until
the forms are full.
Tremie forms must confine fresh concrete until it sets. Ordinarily, the forms are placed
on a gravel blanket. The seal between the forms and the blanket must prevent concrete
from flowing out under the forms. Inspection by a diver is usually necessary to ensure a
proper seal.
Good tremie concrete depends on a smooth, gentle flow of concrete into the forms. Any
turbulence will result in laitance. To produce gentle flow, concrete consistency, concrete
head, and pipe spacing must be in proper balance. The forms must be designed to arrest
water movement that would disturb the concrete before it sets.
In addition to the pressure from the concrete, the forms must withstand forces
produced by waves and currents and unbalanced pressures due to nonuniform concrete
placement. Forms for underwater work are designed with the same basic considerations
as for aboveground work, except that in calculating lateral pressure the density of the
submerged concrete can theoretically be reduced by the weight of displaced water.
Consideration should be given to local pressures that can develop due to the head of
concrete in the tremie. Some form designers prefer to ignore the effect of submergence
because this offsets some hard-to-quantify underwater conditions.
In tidal zones, forms should be designed for the lowest possible water level. Changes
in construction schedules can transform a planned submerged placement to one made
above water, thus losing the offsetting water pressure.
CHAPTER 78
Underwater forms are built on the
surface in large units because any final
positioning and fitting done underwater
by divers is slow and costly. Multiuse forms
may have special devices for positioning
from above the water and special stripping
devices such as hydraulic jacks that also
permit form release from above the water.
Accurate knowledge of the behavior
of concrete placed underwater is difficult
to obtain, and therefore fewer facts are
available than for other concreting tech
niques. For this reason, the form designer
not familiar with this type of construction
should consult an individual with tremie
experience.
Materials
Forming material should be rugged, leak-resistant, rigid, and require little or no mainte
nance. Maximum reuse with minimum repair is perhaps the most important consideration
when selecting materials. If the forms have to be repaired after only a few castings, some
of the advantages of this method of construction have been lost.
Untreated wood forms (Fig. 18.51) for complex shapes are satisfactory for limited reuse,
but for large production, they are difficult to strip and costly to keep in repair. A plastic
coating or a lining material such as plywood or hardboard will improve the stripping of
wood forms and lengthen their life. Form-grade plywood and overlaid plywood are also suit
able as sheathing for these forms. There are several liquid-applied form coatings designed
specifically for precast construction that may also aid in constructing long-lasting forms.
Metal molds are well suited to this work (Fig. 18.52). They can be fabricated from sheets
or die-pressed. The stamping method is seldom used unless a great many molds of the
same shape and size are to be made. A wide range of metal forms for standard sizes and
shapes of structural units (Fig. 18.53) is available from manufacturers who specialize in this
field. Many of these ready-made forms have provisions for adjustment to varying sizes.
Concrete molds may be cast from a wood, plaster, sand, or concrete master mold.
Special care must be taken in finishing the concrete mold so that it will have a surface
compatible with the desired finish of the precast units. Concrete molds with metal or
wood side forms are well suited for the casting of ribbed slab units.
Plastic and glass-reinforced plastics are also suitable for precast concrete forms and form
linings. These materials, like concrete and metal, will give prolonged service with proper
care. The method of making plastic molds is discussed in Chapter 4.
CHAPTER 18
Fig. 18.54: Wall panel cast horizontally but Fig. 18.55: Vibrating table for precasting wall Fig. 18.56: Fabrication of steel form with
lifted, stored, and erected vertically panels in a horizontal position but lifting with hydraulic fold-out sides for precasting
edge inserts to strip after tilting prestressed inverted tee beams (Photo cour
tesy Hamilton Form)
ahead while consideration of the layout of the yard area and scheduling of the casting
operation will be time well spent.
Casting Bed
The type of bed used will depend on the items to be cast and the type of forms used. For
shapes to be cast using the bed as a bottom form, the surface should be level, smooth,
hard, and free from cracks, holes, or crevices. A concrete slab can be used effectively as
the bed-sometimes the completed floor slab of the structure. For some items, the bed
is raised to table height for more efficient concrete placing and finishing. In all cases, the
bed must be watertight and rigid so that the weight of the concrete will not deform it and
passing equipment will not cause movement of the forms. Wall panels are often cast flat to
avoid the high concrete lateral pressures normally associated with wall construction. It is
often desirable to locate the lifting inserts in the top edge of the panel for vertical storage
and erection (Fig. 18.54). However, tilting from horizontal with an edge lift can crack
panels and damage edges. Thus, in plant precasting, a tilting table {Fig. 18.55) is often
used so that the panel can be tilted to near vertical before the edge lift.
Units such as beams may be cast in individual forms that require no special bed. The
foundations for casting beds that carry heavy loads such as stacked castings should be
designed to prevent differential settlement. Prestressed precast work presents unique
challenges, as discussed Section 18.11.
Form Construction
The forms can be built in various ways depending on the shape of the piece to be cast,
the material used, the space available, and the number of reuses required. For instance,
panels can be cast individually or one on top of the other. Where the precast units are to
be stacked as cast, the form must be designed to carry the total load of stacked units, and
the subgrade or supporting bed must also be adequate for the total load. This precau
tion must be remembered when a completed driveway or floor slab-on-ground is to
be the casting bed. Beams or other members with a constant cross section can be cast
individually in long forms, in which the length of the members is regulated by adjustable
diaphragms as in plant precast production (Fig. 18.53).
Prefabricated forms ready-made for most common shapes or custom-made for special
shapes are used in field as well as factory casting. They are usually made so the form
section can be modified by bolting on diaphragms, moving side forms, or blocking. Some
(Fig. 18.56) have special features, such as fold-down sides, that facilitate stripping.
Because an economical precasting operation frequently depends on early stripping of
forms for reuse, provisions for adequate curing without the forms should be made. The
vacuum and steam-curing techniques used in factory precasting may be adaptable to
some exceptionally large site precasting operations, but generally more conventional
methods must be relied on. Any equipment needed for curing should be arranged so that
it will not interfere with placing and stripping operations. Form dimensions should take
into account any shrinkage caused by the curing process.
Some precast elements such as box girders require inside forms. These must be prop
erly located and anchored to reinforcement and side or deck forms with ties to prevent
18.10.3 Stripping
All forms must be designed for easy stripping. Side forms are usually hinged so they can
be folded down or fastened by clamps or pins for easy removal. When the stripping opera
tion is accomplished by lifting the casting out of the form, the design of the form should
be such that it cannot become keyed or wedged to the concrete. Because the units are
usually stripped as soon as possible to free the forms for casting another piece, the green
concrete may be damaged if the mold hangs up on the casting. Some small draft in the
forms is required because friction on a surface exactly parallel to the movement may
damage the surface of the casting.
Forms should be coated with release agent or otherwise treated to facilitate strip
ping. When precast members are cast one on top of the other, appropriate separating
membranes are required. These may be sheet materials or films of plastic, but many
favor the liquid type that can be applied with power spray equipment. Any separating
membrane or form release agent should be of a clear, nonstaining type and should not
interfere with the adhesion of paint or plaster if any is to be applied to the concrete
surface after the unit is erected. Air or water introduced between casting and mold by a
water or air pipe will aid stripping.
Molds can be tied down with wire to pull them from the casting as it is lifted. In the
event of sticking, wire strength should be such that it will break before the concrete
casting is damaged by splitting away from the mold.
CHAPTER 18
compressive stress in the concrete at locations that will counteract the bending tension
due to dead and live loads imposed in service. In some cases, the strands or bars are
inserted later into the ducts cast within the concrete members. After the concrete has
hardened, the unbonded tendons are stressed and anchored to the ends of the member
(Fig. 18.59), thus prestressing the concrete. Post-tensioned strands or bars are then
protected from corrosion by grease or cement grout injected in the space around the
strands or bars within the sleeve or duct.
Post-tensioning is commonly regarded as a job-site technique, and pretensioning
is most commonly a method of manufacturing prestressed concrete in permanent
precasting plants. However, post-tensioned beams are also made in precasting plants, and
temporary pretensioning plants may be set up at or near the job site. In keeping with the
scope of this manual, discussion of both methods emphasizes work done at the construc
tion site. Only linear prestressing-prestressing of elongated structures or elements such Fig. 18.57: Pretensioned strand held at
as beams, slabs, piles, and the like-will be discussed because most circularly prestressed required elevation by bulkhead slots in steel
structures are built by a few contractor specialists using proprietary methods. formwork for precasting stay-in-place bridge
deck forms like those shown in Chapter 15
18. 11. 1 Forms for Post-Tensioning (Photo courtesy Precast/Prestressed Concrete
Because post-tensioning is applied without the use of a special tensioning bed or bench, Institute)
CHAPTER 18
Example 18.1 is representative of prob
lems that may occur in such construction. utmmlJI:Idj@l,§.(11.!.!§.1:ttf!@I•Aii§i!.!.t
Each case must be planned with coordina Assume formwork for a bridge over a waterway is to be supported by temporary
tion between the engineer/architect and steel trusses spanning between the bridge piers. The trusses were built with a 2 in.
the formwork engineer/contractor. camber and the forms were set for a 3 in. total camber, including the truss camber.
After the deck was cast, a 1 in. camber remained, indicating a 2 in. formwork deflec
18. 11.2 Forms for Prelensioning tion. Strand tendons were tensioned in two phases. The first phase was sufficient
Pretensioning tendons must remain to support the concrete bridge dead load. Thus, after the first phase strands were
stressed until the concrete-tendon bond tensioned, the falsework was lowered and moved to its next position for reuse.
and the concrete strength are capable of Prestressing was then completed. Because the bridge was much stiffer than the
accepting prestress. Stress in the tendons falsework, upward deflection from the full tensioning amounted to only 1 in.,
may be held by anchoring them at ends approximately half the downward deflection of the trusses under the weight of the
of steel molds, called �self-stressing"forms concrete. If the formwork had not been lowered, the upward force from the elastic
{Fig. 18.62 and 18.63), designed to with recovery of the truss would have overstressed the deck in reverse bending and
stand the prestressing force as well as loads possibly cracked the deck.
from the freshly placed concrete. Alter
nately, the stressed tendons are held by
massive end anchorages on pretensioning
beds or benches, which also provide a level
surface on which the members may be cast.
The pretensioning bed is usually a perma
nent installation. For this reason, preten
sioning is well suited to the factory produc
tion of precast prestressed members.
However, for large remote projects, site
pretensioning may prove economical.
The contractor who decides to undertake
the production of pretensioned members,
for reasons of economy peculiar to the
project or special site location away from Fig. 18.62: Self-stressing double-tee form with Fig. 18.63: Self-stressing dual piling form with
factory facilities, is advised to secure the anchor plates having hole pattern to accept stressed strands held by strand chucks at the
services of a consultant thoroughly familiar many possible strand locations {Photo cour end bearing plate after pretensioning (Photo
with pretensioning techniques. Because tesy Hamilton Form) courtesy Hamilton Form)
the typical contractor will not be concerned
with the design and construction of forms for pretensioned concrete, the desirable charac
teristics18·18 of pretensioned concrete forms will only be summarized briefly:
1. High resistance to damage due to rough handling. This requirement normally elimi
nates the use of wood forms that do not perform well under repeated use, particularly
if exposed to steam curing. Although concrete forms have been used successfully, the
lighter steel forms are generally preferred.
2. Adjustability. The forms, or components of the forms, should be adjustable in such a
manner that members of several shapes can be made from the form or form components.
3. Precision of form units and dimensions.
4. Ease of handling and a design that permits one side to be erected in the final position
independently of the opposite side.
5. Provision for form vibration.
6. Rigid, structural soffit form.
7. A minimum of joints.
In addition, provisions should be made for the deformation and movement of the
casting during the prestressing operation and for movement of the member without
damage during release of the prestressing force. Forms may be partially or entirely
stripped before tendons are released to stress the member because shortening, bending,
and shrinkage will occur to some degree. Where the side forms cannot be conveniently
removed, they must be designed for additional axial and/or bending loads that may be
imposed on them during the prestressing operation. Adequate horizontal and vertical
movement of the casting should be allowed during stress transfer to prevent the
casting or forms from being damaged. Provision in the soffit for attaching tie-down
devices to hold the prestressed tendons at desired depths is also required for many
pretensioned members.
REFERENCES
18.1. Camellerie,J. F., NVertical Slipforming as a Construction Tool," Concrete Construction,
V. 23, No. 5,May 1978,pp. 262-272.
18.2. Camellerie,J. F., NSiipform Details and Techniques,· AC/ Journal Proceedings, V. 55,
No. 10,Oct. 1959,pp. 1131-1140; addenda published in ACI Journal Proceedings, V. 59, No.
8,Aug. 1962,p. 1109.
18.3. "Siipformed Tower at Inches per Hour," Concrete International, V. 6, No. 4,Apr. 1984,
p. 57.
18.4. Ray,G. K., and Halm, H. J., "Fifteen Years of Slip-Form Paving," AC/ Journal Proceed
ings, V. 62, No. 2,Feb. l%S,pp. 14S-160.
18.5. NTilt-Up Concrete Buildings,N Portland Cement Association,Skokie, IL,1989.
18.6. Mays,T. W., and Steinbicker,J. J., NEngineering Tilt-Up,NTilt-Up Concrete Association,
Mt. Vernon,lA,32S pp.
18.7. NThe Construction ofTilt-Up,NTilt-Up Concrete Association, Mt. Vernon,lA,22S pp.
18.8: Russillo, M.A., Nlift Slab Construction; Its History, Methodology, Economics,
and Applications,N Forming Economical Concrete Buildings-Proceedings of the Third
International Conference, SP-107, American Concrete Institute, Farmington Hills, Ml,
1988, pp. 59-68.
18.9. Hurd,M. K., NWalls and Slab Lifted in Texas," Concrete Construction, Oct. 1989,p. 891.
18.10. Culver,C. G.; Scribner,C. F.; Marshall,RD.;Yokel,F. Y.;Gross,J. L.;Yancey,C. W.; and
Hendrickson,E. M., Nlnvestigation of l'Ambiance Plaza Building Collapse in Bridgeport,
Connecticut," NBS IR 87-3640, National Institute of Standards and Technology,Washington,
DC,Sept. 30,1987,309 pp.
18.11. Christiansen,J., "Economics of Hyperbolic Paraboloid Concrete Shells,NConcrete
International, V. 12, No. 8,Aug. 1990,pp. 24-29.
18.12. Tedesko,A., NConstruction Aspects ofThin-Shell Structures," AC/ Journal Proceed
ings, V. 49, No. 2,Feb. 1952,p. 505.
18.13. Wilson,A., "Very large Air-Formed Concrete Shells,N Concrete International, V. 15,
No. 8,Aug.1990,pp. 21-23.
18.14. Reading,T. J. et al., Shotcreting: A Symposium of Thirteen Papers on General and
Specialized Shotcreting Practices, SP-14,American Concrete Institute, Farmington Hills,Ml,
1966 (reprinted 1977),224 pp.
18.15: Gerwick, B. C. Jr., NPiacement ofTremie Concrete,N Symposium on Concrete
Construction in Aqueous Environment, SP-8,American Concrete Institute, Farmington Hills,
Ml,1964,pp. 9-20.
18.16: Gerwick, B. C. Jr.,and Holland,T. C., NUnderwater Concreting: Advancing the State
of the Art for Structural Tremie Concrete; Lewis H. Tuthill International Symposium: Concrete
and Concrete Construction, SP-104,American Concrete Institute,Farmington Hills, Ml, 1987,
pp. 123-144.
18.17: Libby,J. R., Prestressed Concrete, Ronald Press Co., New York,1961,pp. 331-332.
(reprinted by permission of the publisher)
18.18: Libby,J. R., Prestressed Concrete, Ronald Press Co., New York,1961,pp. 15-41.
(reprinted by permission of the publisher)
APPENDIX A-REFERENCED STANDARDS
AND REPORTS
The standards and reports listed below were the latest at the time this document was
prepared. Because these documents are revised frequently, the reader is advised to
contact the sponsoring group if it is desired to refer to the latest version. Some of the
publications are also listed dually with the American National Standards Institute (ANSI).
ASTM International
ASTM (31-06 Standard Practice for Making and Curing Concrete Test
Specimens in the Field
ASTM (39-05 Standard Test Method for Compressive Strength of Cylindrical
Concrete Specimens
ASTM C803-03 Standard Test Method for Penetration Resistance of Hardened
Concrete
ASTM C873-04 Standard Test Method for Compressive Strength of Concrete
Cylinders Cast in Place in Cylindrical Molds
ASTM C900-06 Standard Test Method for Pullout Strength of Hardened
Concrete
APPENDIX A#
ASTM C1074-04 Standard Practice for Estimating Concrete Strength by the
Maturity Method
ASTM International
100 Barr Harbor Dr.
PO BoxC700
West Conshohocken, PA19428
www.astm.org
Several sources have been surveyed to determine the most appropriate definitions to
include in this work on formwork for concrete. The source of the definition presented is
indicated in parentheses at the conclusion of the definition. Where the source is an ACI
document, the document designation is indicated. Where the source is ACIConcrete
Terminology, the source is indicated as (CT). Where no source is indicated, the definition
was developed for inclusion in this document or taken from previous editions of Formwork
for Concrete.
C-2 , APPEND/XC
dry tie-form tie that holds sides of form in position in an area where no concrete is
placed; for example, at the top of a wall form above a construction joint or at a bulkhead.
engineer/architect or architect/engineer-the engineer, architect, engineering firm,
architectural firm, or other agency issuing project plans and specifications for the perma
nent structure, administering the work under contract documents, or both. (ACI347R-14)
falsework-the temporary structure erected to support work in the process of construc
tion; composed of shoring or vertical posting and lateral bracing for formwork for beams
and slabs. (See also centering.) (ACI347R-14)
fascia-a flat member or band at the surface of a building or the edge beam of a bridge;
also exposed eave of a building. (CT)
filler-material used to fill an opening in or between forms.
fillet-concrete filling an inside corner between intersecting members requiring a bevel
of the form. (See also strip, chamfer.)
fin-a narrow linear projection on a formed concrete surface resulting from mortar
flowing into spaces in the formwork. (CT)
fishtail-a wedge-shaped piece of wood used as part of the support form between
tapered pans in concrete joist construction.
flashing-a thin impermeable sheet (narrow in comparison with its length) installed as
a cover to exclude water from exposed joints and at roof valleys, hips, roof parapets, or
intersections of roof and chimney. (CT)
flatness-deviation of a surface from a plane. (ACI 347.3R-13)
flying forms-see forms, flying.
form-a temporary structure or mold for the support of concrete while it is setting and
gaining sufficient strength to be self-supporting. (See also formwork.) {ACI 347R-14)
form, climbing-a form that is raised vertically for succeeding lifts of concrete in a given
structure; also called a jump form. (ACI 347R-1 4)
form, crane-climbing-a form that is raised vertically by a crane for succeeding lihs of
concrete in a given structure; also called jump form.
form, drop-panel-a retainer or mold so erected as to give the necessary shape, support,
and finish to a drop panel.
form, edge-formwork used to limit the horizontal spread of fresh concrete on flat
surfaces such as pavements or floors. {CT)
form, permanent-any form that remains in place aher the concrete has developed its
design strength; it may or may not become an integral part of the structure.
form, self-climbing or self-lifting-a form that is raised vertically by mechanical or
hydraulic lifters that are part of the formwork system for succeeding lifts of concrete in a
given structure.
form, sliding-see slipform.
form, stay-in-place-see form, permanent.
form, top-form required on the upper or outer surface of a sloping slab or thin shell. {CT)
form, trench-a form used to construct the sides and bottom of a concrete trench, such
as for trench drains or utility trenches.
form, vented-a form so constructed as to retain the solid constituents of concrete and
permit the escape of water and air.
form, wall-a retainer or mold so erected as to give the necessary shape, support, and
finish to a concrete walt. (CT)
form anchor-see anchor, form.
form coating-see coating, form.
form facing-the form material that comes in direct contact with the concrete. (ACI
347.3R-13)
form hanger-see hanger, form.
form insulation-see insulation, form.
form liner or lining-materials used to line the concreting face of formwork either to
impart a smooth or patterned finish to the concrete surface, to absorb moisture from the
concrete, or to apply a set-retarding chemical to the formed surface. (See also sheathing.)
(CTI
form oil-see release agent.
form scabbing-inadvertent removal of the surface of concrete because of adhesion to
the form.
form sealer- coating applied to the surface of a form to reduce or prevent absorption of
water from the concrete.
GLOSSARY
form spacer-see spreader.
form spreader-see spreader.
form tie-see tie, form.
forms-
forms, fl ying-large prefabricated, mechanically handled sections of floor system form
work designed for multiple reuse; frequently including supporting truss, beam, or shoring
assemblies completely unitized. (ACI347R-14)
forms, ganged-large mechanically hoisted assemblies with special lifting hardware used
for forming vertical surfaces; also called •gang forms.• (ACI 347R-14)
forms, moving-large prefabricated units of formwork incorporating supports and
designed to be moved horizontally on rollers or similar devices with a minimum amount
of dismantling between successive uses. (CTJ
formwork-total system of support for freshly placed concrete, including the mold or
sheathing that contacts the concrete as well as supporting members, hardware, and
necessary bracing. (See also falsework and centering.) (ACI347R-14)
formwork engineer/contractor-engineer of the formwork system, contractor, or
competent person in charge of designated aspects of formwork design and formwork
operations. (ACI347.2R·05)
friction collar-A clamping device that uses the friction between the device and
the concrete element to support a load.
ganged forms-see forms, ganged.
gap-space between abutting edges of the form-facing materials measured on the plane
of the form surface. (ACI347.3R-13)
glass fiber-reinforced concrete (GFRC)-concrete containing dispersed, randomly
oriented, alkali-resistant glass.
glued laminated timber (G i ulam) -an assembly of selected dimension lumber lamina
tions bound together with adhesives, with the grain of the laminations running longitudi
nally and approximately parallel.
hairpin-the wedge used to tighten some types of form ties; a hairpin-shaped anchor set
in place before concrete reaches initial setting. (CT)
hanger, form-dev i ce used to support formwork from a structural framework (the dead
load of forms, mass of concrete, and construction and impact loads must be supported).
(CT)
haunch-a deepened portion of a beam in the vicinity of a support. (CT)
head or header-a member spanning over an opening or between two closely spaced
shores; also the difference in elevation between two points in the body of a fluid, as a
measure of the pressure of the fluid.
honeycomb-voids left in concrete between coarse aggregates due to inadequate
consolidation. (CT)
horizontal bracing-horizontal load-carrying members attached to formwork compo
nents to increase lateral load resistance; when attached to shores, they may also serve as
lacing. (See also horizontal lacing.)
horizontal lacing-horizontal members attached to shores to reduce their laterally
unsupported length, but not designed to provide resistance to lateral forces.
horizontal shoring-see shoring, horizontal.
insulating concrete form (ICF)-stay-in-place form made of rigid insulating material such
as expanded polystyrene foam, fabricated into molded blocks or panels with plastic or
steel ties and having voids into which concrete is placed.
insulation, form-insulating material applied to outside of forms between studs and over
the top in sufficient thickness and air tightness to conserve heat of hydration to maintain
concrete at required temperatures in cold weather. (CT)
invert-lowest visible surface; the floor of a drain, sewer, tunnel, culvert, or channel.
jack-a mechanical device used for applying force to prestressing tendons, for adjusting
elevation of forms or form supports, and for raising objects small distances.
jack shore-te l escoping, or otherwise adjustable, single-post metal shore.
joint, construction-interface between concrete placements intentionally created to
facilitate construction. (CTJ
joint, contraction-formed, sawed, or tooled groove in a concrete structure to create
a weakened plane to regulate the location of cracking resulting from the dimensional
change of different parts of the structure. (See also joint, construction.) (CT)
APPEND/XC
joist-a horizontal structural member such as that which supports deck form sheathing;
usually supported by stringers or ledgers.
jumbo-traveling support for forms, commonly used in tunnel work.
kerf-a cut or notch in a wood beam or sheet of plywood that facilitates bending the
beam or plywood around a curve; also a cut or notch in a member such as a rustication
strip to prevent damage from swelling and permit easier removal.
key-see keyway.
keyway-a recess or groove in one lift or placement of concrete that is filled with
concrete of the next lift, giving shear strength to the joint.(CTJ
kicker-a wood block or board attached to a formwork member to make the member
more stable.
knee brace-a diagonal brace between horizontal and vertical members in a frame or
formwork shoring frame.
L-head-top of a shore with a braced horizontal member projecting on one side, forming
an inverted l-shaped assembly.
L-shore-shore with an l-head.
lacing-See horizontal lacing (preferred term).
lagging -heavy sheathing used in underground work to withstand earth pressure.(See
also sheathing.) (CT)
laminated strand lumber (LSL)-structural composite lumber made from thin strands
cut directly from logs and bonded together with adhesive with strands parallel to the axis
of the member.
laminated veneer lumber (LVL)-structural composite lumber manufactured from
veneers laminated with adhesive so that the grain of all veneers runs parallel to the axis of
the member.
ledger-horizontal formwork member attached to a beam, wall, or other vertical form
work side that supports horizontal formwork members or facing material.
lining-any sheet, plate, or layer of material attached directly to the inside face of form
work to improve or alter the surface texture and quality of the finished concrete.(See also
form lining and sheathing.) {CT)
lost formwork or lost deck-form material that cannot be removed; remains perma
nently in place and is thus, Nlost.N
mockup-a sample of a component of the building as specified in the contract docu
ments that is used to establish the expected surface finish.(ACI 347.3R-13)
mold-the cavity or surface against which fresh concrete is cast.
mud sill-a wood plank, timber assembly, or precast concrete pad bedded on earth as a
footing for a shore or post in formwork.
mud slab-a layer of concrete beneath a structural concrete floor or footing over soft, wet
soil; also called mud mat. (CT)
multi-tier shoring -single post shores used in two or more tiers to increase height of the
shoring system.
nailer-a strip of wood or other fitting attached to or set in concrete, or attached to metal
to facilitate making nailed connections. {CT)
neat line-a line defining the proposed or specified limits of an excavation or structure.
nosing-the projection of a stair tread over the riser.
nut washer-a large, round retention nut used on she bolts.
offset-an abrupt change in alignment or dimension, either horizontally or vertically; a
horizontal ledge occurring along a change in wall thickness of the wall above.(CT)
one-sided formwork-see single-sided formwork.
oriented strand board (OSB)-a panel product manufactured from waterproof heat
cured adhesives and rectangularly shaped wood strands that are arranged in cross
oriented layers.
overbreak-excavation beyond the neat line of a tunnel or other structure.
pan-a prefabricated form unit used in concrete joist floor construction. (CT)
panel-a section of form sheathing that can be erected and stripped as a unit. (CT)
parapet-the part of a wall that extends above the roof level; a low wall along the top of
a dam.(CT)
parallel strand lumber (PSL)-a structural composite wood product made by gluing
together, parallel to the member long axis, long strands of wood that have been cut from
veneer.
pencil rod-plain metal rod of about 1/4 in. (6 mm) diameter. (CT)
GLOSSARY
permanent form-see form, permanent.
pilaster-column built with a wall, usually projecting beyond the wall. (CT)
plate-a flat, horizontal member either at the top, bottom, or both of studs or posts;a
mud sill if on the ground. (See also mud sill.)
plumb-vertical or to make vertical. (CT)
post-vertical formwork member used as a support. (See also shore or jack.) (CT)
preshores-added shores placed snugly under selected panels of a deck forming system
before any primary (original) shores are removed;preshores and the panels they support
remain in place until the remainder of the complete bay has been stripped and back
shored, a small area at a time. (AC I 347.2R-05)
purlin-see joist (preferred term).
raker-a sloping brace or shore for lateral support of one-sided forms;a sloping brace for
a shore head.
ranger-see wale (preferred term).
reference area-a significantly large area of a completed concrete surface serving as a
basis of comparison for the acceptance of a surface category of work at a specified loca
tion of a given project. (ACI347.3R-13)
reglet-a groove in a wall to receive flashing.
release agent-material used to prevent bonding of concrete to a surface. (CT)
reshores-shores placed snugly under a stripped concrete slab or other structural
member after the original forms and shores have been removed from a full bay, requiring
the new slab or structural member to deflect and support its own weight and existing
construction loads to be applied before the installation of the reshores. (See also drop
head shore, backshores, preshores.) (ACI347R-14)
reveal (n.)-the vertical surface forming the side of an opening in a wall, as for a window
or door. (See also rustication.) (CT)
ribbon-a narrow strip of wood or other material used in formwork.
rib-one of a number of parallel structural members backing sheathing. (CT)
riser-the vertical part of a step in a flight of stairs.
runner-see joist (preferred term).
rustication-a groove in a concrete surface. (CT)
rustication strip-see strip, rustication.
sand box (or sand j ack)-a tight box filled with clean, dry sand, on which rests a tight
fitting timber plunger that supports the bottom of posts used in falsework or centering;
removal of a plug from a hole near the bottom of the box permits the sand to run out
when it is necessary to lower the falsework or centering.
scab-a short piece of wood fastened to two formwork members to secure a butt joint.
scaffold or scaffolding-temporary structure with an elevated platform for supporting
workers, tools, and materials. (ACI347R-14)
screed-
(1) to strike off a cementitious mixture lying beyond the desired plane or shape;
(2) a tool for striking off the cementitious mixture surface, sometimes referred to as a
strikeoff;or
(3) a ribbon or pad of a cementitious mixture that is preplaced to act as a guide for main
taining the desired level as more material is placed. (CT)
screed guide-firmly established grade strips or side forms for unformed concrete that
guide the strikeoff in producing the desired plane or shape. (CT)
screed rails-see screed guide.
sheathing-the material forming the contact face of forms;also called lagging or
sheeting. (CT)
sheeting-see sheathing (preferred term).
shore-vertical or inclined support member or braced frame designed to carry the weight
of the formwork, concrete, and construction loads. Also called prop, tom, post, or strut.
(See also L-head and T-head.) (ACI347R-14)
shore, pole-see shore, post.
shore, post-individual vertical member used to support loads;also known as pole shore.
(1) adjustable timber single-post shore-individual timber used with a fabricated clamp to
obtain adjustment and not normally manufactured as a complete unit;
(2) fabricated single-post shore-Type 1: single all-metal post with a fine-adjustment screw
or device in combination with pin-and-hole adjustment or clamp;Type I:I single or double
APPENDIXC
wooden post members adjustable by a metal damp or screw and usually manufactured as
a complete unit; and
(3) timber single-post shore-timber used as a structural member for shoring support.
(CT)
shore head-connector placed on and fastened to vertical shoring to receive and support
horizontal members of the formwork system.
shoring-props or posts of timber or other material in compression used for the tempo
rary support of excavations, formwork, or unsafe structures; the process of erecting shores.
(CT)
shoring frame-metal frame with two posts and welded horizontal bars often with knee
braces.
shoring, horizontal-metal or wood load-carrying strut, beam, or trussed section used to
carry a shoring load from one bearing point, column, frame, post, or wall to another; may
be adjustable. (CT)
shoring layout-a drawing prepared before erection showing arrangements of equip
ment for shoring. (CT)
shuttering-British term for formwork in general or, more particularly, form panels in
direct contact with concrete; see formwork.
side form spacer-a device that maintains the desired distance between a vertical form
and reinforcing bars.
sill-the lowest part of an opening in a wall such as a door sill or window sill; also a hori
zontal bearing member. (See also ledger or mud sill.)
single-sided formwork-a wall formwork system having only one forming side, requiring
provision for tying or other support.
single-waler forming-forming system using plywood sheathing with a tie-restraining
bracket device designed for use with single-member wales.
skew back-see also strip, chamfer.
slick line-pipe line used in placing concrete by pump.
sliding form-see slipform (preferred term).
slipform-a form that is pulled or raised as concrete is placed. (ACI347R-14)
snap tie-a concrete wall-form tie, the end of which is fabricated such that it can be
twisted or snapped off aher removing the forms.
soffit-the underside of a part or member of a structure, such as a beam, stairway, or arch.
(CTI
soldier-a vertical wale used to strengthen or align formwork or excavations. (See also
strong back.)
spandrel-that part of a wall between the head of a window and the sill of the window
above it. (CT)
spandrel beam-a beam in the perimeter of a building, spanning between columns and
usually supporting a floor or roof. (CT)
spreader-a piece of lumber approximately 1 by 2 in. (25 by 50 mm) cut to the thickness
of a wall or other formed element and inserted in the form to hold it temporarily at the
correct dimension against tension of form ties. (CT)
stay-in-place form-any form that remains in place after the concrete has developed its
design strength; may or may not become an integral part of the structure. (See also form,
permanent.)
stiffback-see strong back (preferred term).
strike-see striking.
striking-the releasing or lowering of centering or other temporary support.
stringer-horizontal structural member usually, in slab forming, supporting joists and
resting on shores or other vertical supports.
strip-to remove formwork or a mold; also a long thin piece of wood, metal, or other
material. (See also stripping.) (CT)
strip, cant-see strip, chamfer (preferred term).
strip, chamfer-either a triangular or curved insert placed in an inside form corner to
produce either a rounded or flat chamfer or to form a rustication. Also called cant strip,
fillet, dummy joint, and skew back. (CT)
strip, grade-usually a thin strip of wood tacked to the inside surface of forms at the
elevation to which the top of the concrete lift is to rise, either at a construction joint or the
top of the structure. (CT)
strip, kick-see kicker.
GLOSSARY
strip, rustication�a strip of wood or other material attached to a form surface to
produce a groove or rustication in the concrete. (CT)
strip, wrecking�small piece or panel fitted into a formwork assembly in such a way that
it can be easily removed ahead of main panels or forms, making it easier to strip those
major form components. (See also crush plate.)
stripping�the removal of formwork or a mold. (CT)
strongback�a frame or member attached to the back of a form to stiffen, reinforce, or
align the form during concrete placing operations or handling operations; a vertical wale.
structural composite lumber (SCL)-a generic term for a family of engineered wood
products in which veneer sheet, strands, or other small wood elements are bonded
together with exterior structural adhesives to form lumber-like materials.
stud�member of appropriate size and spacing to support sheathing of a vertical
concrete form.
surface air voids�small regular or irregular cavities, usually not exceeding 0.6 in. (1 S
mm) in diameter, resulting from entrapment of air bubbles in the surface of formed
concrete during placement and consolidation. (ACI347R-14)
surface void ratio�the ratio of the total surface void area to the total concrete surface
area after stripping with no subsequent surface treatment. (ACI347.3R-13)
sway brace�a diagonal brace used to resist wind or other lateral forces. (See also brace,
cross bracing, and X-brace.) (CT)
T-head�top of a shore with a horizontal member projecting on two sides forming a
T-shaped assembly.
T-shore-a shore with aT-head. (CT)
telltale�any device designed to indicate movement of formwork.
template�a thin plate or board frame used as a guide in positioning or spacing form
parts, reinforcement, or anchors; also a full-size mold, pattern, or frame shaped to serve as
a guide in forming or testing contour or shape. (CT)
tie, form�a mechanical connection in tension used to prevent concrete forms from
spreading due to the fluid pressure of fresh concrete. (CT)
tie hole-void in a concrete surface left when a form tie end is snapped off, broken back,
or otherwise removed.
tolerance-the permitted deviation from a specified dimension, location, or quantity. (CT)
tom-see shore (preferred term).
top form-see form, top.
tunnel forming system-forms that resemble a tunnel; modular formwork units of
inverted U or L-shape used for bearing wall structures having a large number of same-size
rooms and where walls and slab above can be cast as a unit with one open end for form
removal.
wale-a long formwork member (usually double) used to gather loads from several
studs (or similar members) to allow wider spacing of the restraining ties; when used with
prefabricated panel forms, this member is used to maintain alignment; also called waler or
ranger. (CT)
waler-see wale.
waterstop-a thin sheet of metal, rubber, plastic, or other material inserted across a joint,
or material adhered within a joint, to obstruct the seepage of water through the joint.
wedge-a piece of wood or metal tapering to a thin edge; used to adjust elevation or
tighten formwork. (CT)
wreck-see strip.
wrecking strip-see strip, wrecking.
X-brace-a crossing pair of diagonal members used to provide lateral stability. Normally
considered to be effective only in tension. (See also brace, cross bracing, and sway
brace.)
yoke-a tie or clamping device around column forms or over the top of wall or footing
forms to keep them from spreading because of the lateral pressure of fresh concrete; also
part of a structural assembly for slipforming that keeps the forms from spreading and
transfers form loads to the jacks. {CT)
APPENDIX D-CONVERSIONS
Length
millimctcr(mm) 25.4E+
milc(statutc) k.ilomctcr(km)
""
square inch 1
square ccntimctcr(cm )
�uan:yard 2 O.ft361
squaremetcr(m )
Volumc(cupuclty)
3 29.51
cubic centimctcr(cm )
gallon 3
cubicmetcr(m )t.
cubic yard 3
cubicm.,tt:r(m )t
Foret
Prcssureorsln!SS
(foi'CC'per area)
l pascal w�>
newtoRisquare meter (Nim )
pound-foree/squarefOOl pas.::ai{Pa)
Bendinwmomentortorque
Mass
oun.:e-ma,s(a•·oirdupoi.,) grarn{g) 28.)4
pound-mass{a•·oirdupois) kilogram(kg)
pound-ma�s/cubic yard 3
kilogramfcubicmeter(kgtm ) 0.5933
pound-ma,sfgalkm 3
kilogramfcubicmeter(kgtm )
Tempc!ratun!f
dcgFahn:nlleit{F) degCelsius(C) lc•(tF-32)/1.8
*This selected list givts pr�ctical ronvcn;ion factors of units found in concrett technol08Y· The reference
oourcc for infonnation on Sl units and more exact con•·c�ion facto� is �standard for Metric Practice'" ASTM E
380. Symbol.,ofmetric units aregiven in puenthe.<es.
tEindicates that thefactor givcn i, cxact
3 3
tOne liter(cubic decimeter) equalsO.O OI m or 1000cm .
§"Thescequations com·cTlone tcmperature rcading to anothcr and in.:ludc thc ncccssaryscalc cofTC(:tions.To
convert a difference in temper.uure fromFahrenheit toCelsiu.•degrees.divide by l.8 only.i.e..a changefrom70
m88F repn:senls a changenftRF orl8/1.8alOC.
APPENDIX E-ACI 347R-14 GUIDE
Objectives of safety, quality, and economy are given priority in lhese CHAPTER 2-NOTATION AND DEFINITIONS
guidelines for formwork. A section on contract documen/s explains 2.1-Notation
the kind and amount of specification guidance the engineer/ 2.2-Definitions
architect should provide for the contractor. The remainder of the
guide advises rhe formwork engineerlconrraclor on the besr ways
CHAPTER 3-GENERAL CONSIDERATIONS
ro meet rhe specificarion requiremenrs safely and economically.
3.1-Achicving economy in fonnwork
Separale chapters deal wilh design. conslnlclion. and materials
3.2-Contract documents
for formwork. Considerations specific to architectural concrete
are also owlined in a separate chapter. Other sections are devoted
to formwork for bridges, shells, mars concrete, and underground CHAPTER 4--DESIGN
work. The concluding chaprer on formwork for special merhods of 4.1----General
constmction includes slipforming. preplaced-aggregare concrete. 4.2-Loads
tremie concrere, precart concrete, and presrressed concrete. 4.3-Member capacities
4.4--Safety factors for accessories
Key..·ords: anchors; architecturnl concrete: coatings: construction:
4.5-Shores
constroction loads: contract documents;falsework; fonn ties; fonns; fonn
work: foundations: quality control;reshoring;shoring;slipfonn construc
4.6--Bracing and lacing
tion;spccifkations;tolerances. 4.7-Foundations for fonnwork
4.8-Settlemem
CONTENTS
CHAPTER 5-CONSTRUCTION
CHAPTER 1-INTRODUCTION AND SCOPE 5.1-safety precautions
!.\-Introduction 5.2-Construction practices and workmanship
1.2-Scope 5.3-Tolerances
5.4-- lrregularities in formed surfaces
5.5-Shoring and centering
ACI Committee Repons, Guides, and Commentaries are 5.6--Inspection and adjustment of fonnwork
intended for guidance in planning. designing. executing. and 5.7-Removal of fonns and supports
inspecting construction. This document is intended for the use 5.8-Shoring and reshoring of multistory structures
of individuals who are competent to evaluate the significance
and limitations of its content and recommendations and who
will accept responsibilityfor the application of the material it
contains. The American Concrete Institute disclaims anyand
all responsibility for the stated principles. The Institute shall
not be liable for anyloss or damage arising therefrom. ACt 347R-14 supo:rwdcs ACt 347..(14 and Wall adopted and published July
20144Docomen1Efl"tt1iverighuof rtproduc1ionanduseinanyform orbyanymeans.
Reference to this document shall not be made in contract
inctuding�making of copicsbyanypholo pi"O(ess.orbyeltt1ronic or mechanical
documents. If items found in this document are desired by
dcvicc,prin!ed.wrinen,or oral,orreoording for sound or visual,..,produclionorfor
the Architect/Engineer to be a pan of the contract documents,
use in any knowtedg� or rt"trit�al sytttm Qr o:kv'-'t.unl«!i po:m1ission in ,.,.,;,;'41 is
theyshall be restated in mandatorylanguage for incorporation obuoil"lt<lfrom1�copyrigh1propric1on.
bytheArchitecliEngineer.
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
1.1-lntroduction 2.2-Definitions
Many individuals, firms, and companies are usually The 2014 ACJ Concrete Terminology (http://www.
involved in the design of the facility to be built and in the concrete.org/Tools/ConcreteTerminology.aspx) provides a
design and construction of the formwork. The facility team comprehensive list of definitions. The definitions provided
typically involves structural engineers and architects who herein complement that source.
determine the requirements for the concrete structure to be backshores-shores left in place or shores placed snugly
built. For simplicity, the facility design team will usually under a concrete slab or structural member after the original
be referred to as the engineer/architect, although they may formwork and shores have been removed from a small area,
be referred to separately in some situations. The form without allowing the entire slab or member to deflect or
work team may include the general contractor, formwork support its self-weight and construction loads.
specialty subcontractors, formwork engineers, form manu brace---structural member used to provide lateral support
facturers, and form suppliers. The participating companies for another member, generally for the purpose of ensuring
and firms also have form designers and skilled workers stability or resisting lateral loads.
executing many detailed tasks. For simplicity, the fonnwork centering-falsework used in the construction of arches,
team will usually be referred to as the formwork engineer/ shells, space structures, or any continuous structure where
contractor, although they may be referred to separately in the entire falsework is lowered (struck or decentered) as a
some sttuattons. unit.
This guide is based on the premise that layout, design, climbing form-form that is raised vertically for
and construction of fonnwork should be the responsibility succeeding lifts of concrete in a given structure.
of the formwork engineer/contractor. This is believed to be
APPENDIXE
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
drop-head shore-shore with a head that can be lowered mized. The cost of formwork can be greater !han half the
to remove forming components without removing the shore tOial cost of the concrete struclure. This investment requires
or changing its support for the floor system. careful thought and planning by the engineer/architect when
engineer/architect-the engineer, architect, engineering designing and specifying the structure and by the formwork
firm, architectural firm, or other agency issuing project plans engineer/contractor when designing and constructing 1he
and specifications for the permanent structure, administering formwork. Formwork drawings, prepared by the fonnwork
the work under contract documents, or both. engineer/contractor, can identify potential problems and
falsework-temporary structure erected to support work should give project site employees a clear picture of what is
in the process of construction; composed of shoring or required and how to achieve it.
vertical posting and lateral bracing for formwork for beams The following guidelines show how the engineer/architect
and slabs. can plan the structure so that fonnwork economy may best
flying forms-large. prefabricated, mechanically handled be achieved:
sections of floor system formwork designed for multiple a) To simplify and permit maximum reuse of formwork,
reuse; frequently including supporting truss, beam, or the dimensions of footings, columns, and beams should
shoring assemblies completely unitized. be of standard material multiples, and the number of sizes
form-temporary structure or mold for the support of should be minimized.
concrete while it is setting and gaining sufficient strength to b) When interior columns are the same width as or smaller
be self-supporting. than the girders they support, the column form becomes a
formwork-total system of support for freshly placed simple rectangular or square box without boxouts, and the
concrete, including the mold or sheathing that contacts the slab form does not have to be cut out at each comer of the
concrete as well as supporting members, hardware, and column
necessary bracing. c) When all beams are made one depth (beams framing
form work engineer/contractor--engineer of the form into girders as well as beams framing into columns), the
work system or contractor in charge of designated aspects of supporting struciUres for the beam fonns can be carried on a
formwork design and formwork operations. level platform supported on shores.
ganged forms-large mechanically hoisted assemblies d) Considering available sizes of dressed lumber,
with special lifting hardware used for forming vertical plywood, and other ready-made formwork components and
surfaces; also called "gang forms". keeping beam and joist sizes constant will reduce labor cost
horizontal lacing-horizontal bracing members attached and improve material use.
to shores to reduce their unsupported length, thereby e) The design of the structure should be based on the use
increasing load capacity and stability. of one standard depth wherever possible when commercially
preshores-added shores placed snugly under selected available forming systems, such as one- or two-way joist
panels of a deck-forming system before any primary (orig systems, are used.
inal) shores are removed. f) The structural design should be prepared simultane
reshores-shores placed snugly under a stripped concrete ously with the architectural design so that dimensions can
slab or other structural member after the original forms and be better coordinated. Minor changes in plan dimensions to
shores have been removed from a full bay, requiring the better fit fonnwork layout can result in significant reductions
new slab or structural member to deflect and support its own in formwork costs.
weight and existing construction loads to be applied before g) The engineer/architect should consider architectural
installation of the reshores. features, depressions, and openings for mechanical or elec
scaffold-temporary structure with an elevated platform trical work when detailing the structural system, with the aim
for supporting workers, tools, and materials. of achieving economy. Variations in the structural system
shore-vertical or inclined support member or braced caused by such items should be shown on the structural
frame designed to carry the weight of the formwork, plans. Wherever possible, depressions in the tops of slabs
concrete, and construction loads. should be made without a corresponding break in elevations
slipform-a form that is pulled or raised as concrete is of the soffits of slabs, beams, or joists.
placed. h) Embedments for altachment to or penetration through
surface air voids-small regular or irregular cavities, the concrete structure should be designed to minimize
usually not exceeding 0.6 in. (15 mm) in diameter, resulting random penetration of the formed surface.
from entrapment of air bubbles in the surface of formed i) Avoid locating columns or walls, even for a few floors,
concrete during placement and consolidation. where they would interfere with the use of large formwork
shoring units in otherwise clear bays.
CHAPTER 3-GENERAL CONSIDERATIONS j) Post-tensioning sequences should be carried out in
stages and planned in a way that will minimize the need for
3.1-Achieving economy in formwork additional shoring that may be required due to redistribution
The engineer/architect can improve the overall economy of post-tensioning loads.
of the structure by planning so that fonnwork costs are mini-
ACI347R·J4
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
3.2-contract documents two-way joist systems, plans should be drawn to make use
The contract documents should set forth the tolerances of available shapes and sizes. Some variation from normal
required in the finished structure but should not attempt to tolerances should be permitted by the specification: a) for
specify the means and methods by which the formwork engi connections of form units to other framing; and b) to reflect
neer/contractor designs and builds the formwork to achieve normal installation practices and typical used condition of
the required tolerances. the form type anticipated.
The layout and design of the formwork should be a 3.2.3 Finish ofexposed concrete- Finish requirements for
joint effort of the formwork engineer and the formwork concrete surfaces should be described in measurable terms
contractor. The formwork construction in compliance with as precisely as practicable. Refer to 5.4, Chapter 7, and ACI
the formwork design is the responsibility of the formwork 347.3R.
contractor. When formwork design is not by the contractor, 3.2.4 Design, inspection, review, and approval of form
formwork design is the responsibility of the formwork work-Although the safety of formwork is the responsibility
engineer. This approach gives the necessary freedom to of the contractor, the engineer/architect or approving agency
use skill, knowledge, and innovation to safely construct an may, under certain circumstances, decide to review and
economical structure. By reviewing the formwork drawings, approve the form work, including drawings and calculations.
the engineer/architect can understand how the formwork If so, the engineer/architect should call for such review or
engineer/contractor has interpreted the contract documents. approval in the contract documents.
Some local jursidictions have legal requirements defining Approval might be required for unusually complicated
the specific responsibilities of the engineer/architect in structures, structures whose designs were based on a partic
formwork design, review, or approval. ular method of construction, structures in which the forms
3.2.1 Individual specifications-The specification for impart a desired architectural finish, certain post-tensioned
formwork will affect the overall economy and quality of the structures, folded plates, thin shells, or long-span roof
finished work; therefore, it should be tailored for each partic structures.
ular job, clearly indicate what is expected of the contractor, The following items should be clarified in the contract
and ensure economy and safety. documents:
A well-written formwork specification tends to equalize a) Who will design the formwork
bids for the work. Vague or overly restrictive requirements b) Who will determine post-tensioning sequence and
can make it difficult for bidders to understand exactly what support needed for redistribution of loads resulting from
is expected. Bidders can be overly cautious and overbid or stressing operations
misinterpret requirements and underbid. Using standard c) Who will design shoring and the reshoring system
specifications such as ACI 301 that have many input sources d) Who will inspect the specific feature of formwork and
in development can mitigate these possible problems. when will the inspection be performed
A well-written formwork specification is of value not only e) What reviews, approvals, or both, will be required for:
to the owner and the contractor, but also to the field repre i. Formwork drawings, calculations, or both
sentative of the engineer/architect, approving agency, and ii. Post-tensioning support
the subcontractors of other trades. Some requirements can iii. Reshoring design
be written to allow discretion of the contractor where quality iv. Fonnwork preplacement inspection
of finished concrete work would not be impaired by the use f) Who will give such reviews, approvals, or both.
of alternative materials and methods. 3.2.5 Contract documents-The contract documents
Consideration of the applicable general requirements should include all information about the structure neces
suggested herein are not intended to represent a complete sary for the formwork engineer to design the form work and
specification. Requirements should be added for actual prepare formwork drawings and for the formwork contractor
materials, finishes, and other items peculiar to and neces to build the formwork such as:
sary for the individual structure. The engineer/architect can a) Number, location, and details of all construction joints,
exclude, call special attention to, strengthen, or make more contraction joints, and expansion joints that will be required
lenient any general requirement to best fit the needs of the for the particular job or parts of it
particular project. Further detailed information is given in b) Sequence of concrete placement, if critical (examples
ACI SP-4. include pour strips and hanging floors)
3.2.2 Formwork materials and accessories-If the partic c) Tolerances for concrete construction
ular design or desired finish requires special attention, the d) The live load and superimposed dead load for which the
engineer/architect can specifY in the contract documents structure is designed and any live-load reduction used
the formwork materials and any other feature necessary to e) Intermediate supports under stay-in-place forms, such
auain the objectives. If the engineer/architect docs not call as metal deck used for forms and permanent forms of other
for specific materials or accessories, the formwork engineer/ materials supports, bracing, or both, required by the struc
contractor can choose any materials that meet the contract tural engineer's design for composite action; and any other
requirements. special supports
When structural design is based on the use of commer f) The location and order of erection and removal of shores
cially available form units in standard sizes, such as one- or for composite construction
APPENDIX£
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
g) Minimum concrete strength required before removal of communication of the toads, it should be clear whether they
shoring and any project specific reshoring requirements are service loads or factored loads.
h) Special provisions essential for fonnwork for special Throughout this guide, the tenns "design", "design load",
construction methods and for special structures such as and "design capacity" are used to refer to design of the fonn
shells and folded plates. The basic geometry of such struc work. Where reference is made to design load for the penna
tures, as well as their required camber, should be given in nent structure, structural design load, structural dead load, or
sufficient detail to permit the fonnwork contractor to build some similar tenn is used to refer to unfactored loads (dead
the forms and live loads) on the structure. Load effects on these tempo
i) Special requirements for post-tensioned concrete rary structures and their individual components should be
members. The effect of load transfer and associated move determined by accepted methods of structural analysis.
ments during tensioning of post-tensioned members can be 4.1.3 Basic objectives-Fonnwork should be designed so
critical, and the contractor should be advised of any special that concrete slabs, walls, and other members will have the
provisions that should be made in the fonnwork for this correct dimensions, shape, alignment, elevation, and posi
condition tion within established tolerances. Fonnwork should also be
j) Amount of required camber for slabs or other struc designed so that it will safely suppon all vertical and lateral
tural members to compensate for deflection of the structure. loads that might be applied until such loads can be supported
Measurements of camber attained should be made at the by the concrete structure. Vertical and lateral loads should
soffit level after initial set and before removal of fonnwork be carried to the ground by the fonnwork system or by the
supports in-place construction that has adequate strength for that
k) Where chamfers are required or prohibited throughout purpose. Responsibility for the design of the fonnwork rests
the project at all element comers, such as door openings, with the contractor or the fonnwork engineer hired by the
window openings, beams, columns wall ends, and slab edges contractor to design and be responsible for the fonnwork.
I) Requirements for insens, waterstops, built-in frames for 4,1.4 Design deficiencies-Some design deficiencies that
openings and holes through concrete; similar requirements can lead to unacceptable perfonnance or structural failure
where the work of other trades will be attached to, supported are:
by, or passed through fonnwork a) Lack of allowance in design for loadings such as
m) Size and location of fonned openings through a struc concrete pressures, wind, power buggies, placing equip
tural slab or wall should be shown on the structural drawings ment, and temporary material storage
n) Where architectural features, embedded items, or the b) Inadequate design of shoring, reshoring, or backshoring
work of other trades could change the location of structural c) Inadequate provisions to prevent rotation of beam fonns
members, such as joists in one- or two-way joist systems; where the slabs frame into them on only one side (Fig. 4.1.4)
such changes or conditions should be coordinated by the d) Insufficient anchorage against uplift due to banered
engineer/architect fonn faces or vertical component of bracing force on single
o) Locations of and details for architectural concrete; sided fonns
when architectural details are to be cast into structural e) Insufficient allowance for eccentric loading due to
concrete, they should be so indicated or referenced on the placement sequences
structural plans because they can play a key role in the struc f) Failure to investigate bearing stresses between individual
tural design of the fonn. fonnwork elements and bearing capacity of supponing soils
g) Failure to design proper lateral bracing or lacing of
CHAPTER 4-DESIGN shoring
h) Failure to investigate the slenderness ratio of compres
4.1-General sion members
4.1.1 Planning-All fonnwork should be well planned i) Inadequate provisions to tie comers of intersecting
before construction begins. The amount of planning required cantilevered fonns together
will depend on the size, complexity, and imponance (consid j) Failure to account for loads imposed on fonn hardware
ering reuses) of the fonn. Fonnwork should be designed for anchorages during closure of fonn panel gaps when aligning
strength and serviceability. System stability and member fonnwork
buckling should be investigated in all cases. k) Failure to account for elastic shortening during
4.1.2 Design me!ho<h-Fonnwork is made of many post-tensioning
different materials, and the commonly used design practices I) Failure to account for changing load patterns due to
for each material are to be followed (refer to Chapter 6). post-tensioning transfer
For example, fonns are designed by either allowable stress 4.1.5 Formwork drawings o11d calculations-Before
design (ASD) methods or load and resistance factor design constructing fonns, the fonnwork engineer/contractor may
(LRFD) methods. When the concrete structure becomes be required to submit detailed drawings, design calculations,
a pan of the fonnwork support system, as in many multi or both, of proposed fonnwork for review and approval by
story buildings, it is imponant for the fonnwork engineer/ the engineer/architect or approving agency. If such draw
contractor to recognize that the concrete structure has been ings are not approved by the engineer/architect or approving
designed by the strength design method. Accordingly, in agency, the fonnwork engineer/contractor should make such
AC/ 347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
INCOIIIAIECTI ...,.,...,,.wo.L
IIOTUIWH(Mkat•IU. .. I .. Otl co•uurcT1 .. ac:_ •n.. '""M ,_
ONIIOOf.A""IRACIIIGIIIOOTI'IIOWOOf.D IIOUTIIIGAI.TII(IO.IGHIJUIFU...I ..
Fig. 4.1.4-Prevemion of rotation is important where slab frames into beam form on only
one side.
changes as may be required before the stan of construction h) Screeds and grade strips
of the fonnwork. i) Location of external vibrator mountings
The review, approval, or both, of the formwork draw j) Crush plates or wrecking plates where stripping can
ings docs not relieve the contractor of the responsibility damage concrete
for adequately constructing and maintaining the forms so k) Removal of spreaders or temporary blocking
that they will function properly. Design values and loading I) Cleanout holes and inspection openings
conditions should be shown on forrnwork drawings. As m) Construction joints, contraction joints, and expansion
related to form use, these include forrnwork design values of joints in accordance with contract documents
construction live load, allowable venical or lateral concrete n) Sequence of concrete placement and minimum elapsed
pressure, maximum equipment load, required soil bearing time between adjacent placements
capacity, material specification, camber required, and other o) Chamfer strips or grade strips for exposed comers and
peninent information, if applicable. construction jomts
In addition to specifying types of materials, sizes, lengths, p) Reveals (rustications)
and connection details, fonnwork drawings should provide q) Camber
for applicable details, such as: r) Mudsills or other foundation provisions for fonnwork
a) Procedures, sequence, and criteria for removal of s) Special provisions, such as safety, fire, drainage, and
forms, shores, rcshores, and backshores and for retracting protection from ice and debris at water crossings
and resnugging drophead shores to allow slab to deflect and t) Special fonn face requirements
suppon its own weight prior to casting of next level u) Notes to fonnwork erector showing size and loca1ion of
b) Design allowance for construction loads on new slabs conduits and pipes projecting through formwork
when such allowance will affect the development of shoring v) Temporary openings or attachments for climbing crane
schemes, reshoring schemes, or both (refer to 4.5 and 5.8 for or other material handling equipment.
shoring and reshoring of multistory structures)
c) Anchors, form ties, shores, lateral bracing, and hori- 4.2-Loads
zontal lacing 4.2.1 Vertical loads-Venical loads consist of dead and
d) Means to adjust forms for alignment and grade live loads. The weight of forrnwork plus the weight of the
e) Waterstops, keyways, and insens reinforcemenl and freshly placed concrete is dead load. The
f) Working scaffolds and runways live load includes the weight of the workers, equipment,
g) Weepholes or vibrator holes, where required material storage, runways, and impact.
APPENDIX£
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
T+\7.8
l (4.2.2.1b(c))
ACI 347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
Table 4.2.2.1a(a)-Applicable lateral pressure equations for concrete other than sec ·Inch-pound version
Slump lnternal•·ibratlondrpth F:lrment Rateofplacement Pressure equation
7 to lSMI 4.2.2.la( c)
wan:
Gn:aterthaniSftllt 4.2.2.1a(a)
'Slump for dtlcrmon.ot1011 oflat�l prnsutl' shall be measum.l after tiM: oddtt1011 ofall admoxtum
1For the purpose ofthis docummt. oolumns are defined as •·mical t�Lll "·ilh no plan dimcnsioocxc«<ling6.5 fl.
:For the purpose ofthis document. walls are defined as •·mica! elements with at least one plan dimension exc«<ling6.5 II
None 1.0
l.ll.o rlll Noo< None
Included 1.2
None 1.2
Lessthan70pm:ent Lessthan40percent
Included
A"Y
None
Gn:aterthanorequal to70percent Greaterthanorequalto40percent
Included 1.5
'Retarders tnclu.de any admoxtllll'. such as a tl'tardcr. rcwdong \\-atcr reducer, tl'tardtng mod-range \\atcr-rtducong admoxtutl', or htgh-nonge \\ater-reducmg adm!Xll!ll', that delays
'1Cttingofconcr<1e
Table 4.2.2.1b-Applicable lateral pressure equations for concrete other than SCC - Sl version
Slump lntcrnal•·ibrationdepth Element Raleofplaeemenl Pressure equation
Lessthanorequalto 17Smm Lessthanorequal to1.2m Wall:greatcrthan4.2m tal1 Less than 2.1 mfh 4.2.2.1b( c)
'FortM purpose ofthis docum�nt. columns are dc:fined as ,·miul clements with no plan dimension cxc..., ding 2m
:Forthe JIIIIPOS" ofthis docum�nl. walls are defined as •·enical elements with at luot one plan dimension exceeding 1m
4.2.2.2 When working with self-consolidating concrete, on-site measurements. Often, laboratory tests are needed as
the lateral pressure for design should be the full liquid head a precursor to on-site monitoring tests. Several methods for
unless the effect on fonnwork pressure is understood by estimating lateral pressure of nonvibrated sec have been
measurement or prior studies and experience. The lateral proposed (Gardner et al. 2012; Khayat and Omran 2011;
pressures developed by sec are determined by consid Lange et al. 2008; DIN 18218:2010-01; "DIN S1andard on
ering the rate of concrete placement relative to the rate of Formwork Pressures Updated" 2010; Proske and Graubner
development of concrete stiffness/strength. Any method has 2008) and continue to be developed as additional data become
to include a measure of the stiffening characteristics of the available. Experience with these methods is presently some
sec and should be capable of being easily ch�ked using what limited. Thus, evaluation of estimated pressure on the
APPENDfXE
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
basis of more than one method is advisable until satisfactory pressure but not less than 15 lb/fV (0.72 kPa). Consideration
performance is confirmed for the range of parameters asso should be given to possible wind uplift on the formwork.
ciated with the project. Measuring pressures during place 4.2.3.2 For elevated floor formwork, the applied value of
ment and adjusting the rate of placement to control pres horizontal load due to wind, dumping of concrete, inclined
sures within the capacity of the forms can be a wise precau placement of concrete, and equipment acting in any direc
tion when using unproven SCC mixtures. Researchers and tion at each floor line should produce effects not less than the
contractors have used pressure cells inserted through the effect of 100 lb/linear ft (1.5 kN/m) of floor edge or 2 percent
form face and load cells on form ties with pressure based on of total dead load on the form distributed as a uniform load
tributary area as methods of measurement (Johnston 20 I 0). per linear foot (meter) of slab edge, whichever is greater.
sec placement pressures have the potential to reach full 4.2.3.3. For wall and column form bracing design, the
liquid head pressures. Generally, concrete lateral pressures applied value of horizontal load due to wind and eccen
will not reach full equivalent liquid head pressure but agita tric vertical loads should produce effects not less than the
tion of the already-placed concrete in the form will cause effect of 100 lb/linear ft (1.5 kN/m) of wall length or column
form pressure to increase. There are site and placement width. applied at the top.
conditions that will increase form pressure. Site conditions 4.2.3.4 Formwork in hurricane-prone regions should be
that can transmit vibrations to the freshly-placed concrete given special consideration in accordance with ASCEJSEI
can cause it to lose its internal structure and reliquefy. Heavy )7.
equipment operating close to the forms, or continued work 4.2.4 Special loads-The formwork should be designed
on the forms, will transmit vibration. Dropping concrete for any special conditions of construction likely to occur,
from the pump hose or placing bucket will also agitate the such as unsymmetrical placement of concrete, impact of
in-place concrete. Concrete pumped into the bottom of a machine-delivered concrete, uplift from concrete pressure,
form will always create pressures higher than full liquid uplift from wind, concentrated loads of reinforcement, form
head. handling loads, and storage of construction materials. Form
4.2.2.3 Alternatively, a method for either conventional designers should provide for special loading conditions, such
or self-consolidating concrete based on appropriate exper as walls constructed over spans of slabs or beams that exert
imental data can be used to determine the lateral pressure a different loading pattern before hardening of concrete than
used for form design (Gardner and Ho 1979; Gardner 1980, that for which the supporting structure is designed.
1985; Clear and Harrison 1985; British Cement Association Imposition of any construction loads on the partially
1992; Dunston et al. 1994; Barnes and Johnston 1999, completed structure should not be allowed, except as speci
2003) or a project-specific procedure can be implemented fied in formwork drawings or with the approval of the engi
to control field-measured pressures in instrumented forms neer/architect. Refer to 5.8 for special conditions pertaining
to the maximum pressure for which the form was designed to multistory work.
(Johnston 2010). 4.2.5 Posr-rensioning loach-Shores, reshores, and
4.2.2.4 If concrete is pumped from the base of the form, backshores need to be analyzed for both concrete place
the form should be designed for full hydrostalic head of men! loads and for all load transfer that takes place during
concrete wh (or pgh) plus a minimum allowance of 25 post-tensioning.
percent for pump surge pressure. Pressures can be as high as
the face pressure of the pump piston; thus, pressure should 4.3-Member capacities
be monitored and controlled so that the design pressure is Member capacities for use in the design of formwork, exclu
not exceeded. sive of accessories, are determined by the applicable codes
4.2.2.5 Caution is necessary and additional allowance for or specifications listed in Chapter 6. When fabricated form
pressure should be considered when using external vibration work, shoring, or scaffolding units are used, manufacturer's
or concrete made with shrinkage-compensating or expansive recommendations for working capacities should be followed
cements. Pressures in excess of the equivalent hydrostatic if supported by engineering calculations or test reports of a
head can occur. qualified and recognized testing agency. The effects of cumu
4.2.2.6 For slipform lateral pressures, refer to 9.2.2.4. lative load duration should be considered in accordance with
4.2.3 Horizontal loads- Braces and shores should be the applicable design specification for the materiaL
designed to resist all horizontal loads such as wind, cable
tensions, inclined supports, dumping of concrete, and 4.4-Safety factors for accessories
starting and stopping of equipment. Wind loads on enclo Table 4.4 shows recommended minimum factors of
sures or other wind breaks attached to the formwork should safety, based on committee and industry experience, for
be considered in addition to these loads. formwork accessories, such as fonn ties, form anchors, and
4.2.3.1 Formwork exposed to the elements should be form hangers. In selecting these accessories, the formwork
designed for wind pressures determined in accordance with designer should be certain that materials furnished for the
ASCEISEl 7 with adjustment as provided in ASCEISEI 37 job meet these minimum ultimate-strength safety require
for shorter recurrence interval. Alternately, formwork may ments compared to the unfactored load. When manufactur
be designed for the local building code-required lateral wind er's recommended factors of safety arc greater, the manu
facturers recommended working capacities should be used.
ACI347R·14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
Table 4.4-Minimum safety factors of formwork Field-constructed butt or lap splices of timber shoring
accessories arc not recommended unless they are made with fabricated
Safery hardware devices of demonstrated strength and stability. If
ACCl'S.SOry f�clor" Typl'OfcOnSiruction' plywood or lumber splices arc made for timber shoring, they
Formtie 2.0 Allapplicalions should be designed to prevent buckling and bending of the
2.0 Fonnwork anchors supporting form weight. shoring.
concretepressures andwindloadonly Before construction, an overall plan for scheduling of
Form anchor
shoring and reshoring or backshoring, and calculation of
3.0 Fonnwork anchors supporting form weight,
loads transferred to the structure, should be prepared by a
concrete pressures,windloads,construction
qualified and experienced formwork designer. The struc
personnellive loads,andimpact
ture's capacity to carry these loads should be reviewed or
Fo� 2.0 All applications
hangrn;
approved by the engineer/architect. The plan and responsi
bility for its execution remain with the contractor.
Anci!Qring 2.0 Precast-concretc panels"'henusedas
insertsused formwork
as form tics 4.6-Bracing and lacing
Sa fctyfactors�basc<l011!hculumatc st�nsthoftl>c a«:cssoryv.hcnncw The formwork system should be designed to transfer all
'Higher faclors ofN.f�ty q ired byOSHA 1926 for work platform ll:<:cS50rics.
�reu horizontal loads to the ground or to completed construction
in such a manner as to ensure safety at all times. Diagonal
4.5---Shores bracing should be provided in vertical and horizontal
Shores and reshores or backshores should be designed planes where required to resist lateral loads and to prevent
to carry all loads transmitted to them. A rational analysis instability of individual members. Horizontal lacing can
(ACI 347.2R and ACI SP-4) should be used to determine be considered in design to hold in place and increase the
the number of floors to be shored, reshored, or backshored; buckling strength of individual shores and reshores or back
and to determine the loads transmitted to the floors, shores, shores. Lacing should be provided in whatever directions are
and reshores or backshores as a result of the construction necessary to produce the correct slenderness ratio /lr for the
sequence. load supported, where I is the unsupported length and r is
The analysis should consider, but should not necessarily the least radius of gyration. The braced system should be
be limited to: anchored to ensure stability of the total system.
a) Structural design load of the slab or member including
live load, partition loads, and other loads for which the engi 4.7-Foundations for formwork
neer of the permanent structure designed the slab. Where Proper foundations on ground, such as mudsills, spread
the engineer included a reduced live load for the design of footings, or pile footings, should be provided. Formwork
certain members and allowances for construction loads, such footings and bracing anchors should be designed to resist the
values should be shown on the structural plans and be taken loads imposed without exceeding the allowable soil bearing
into consideration when performing this analysis. capacity, without incurring excessive settlements affecting
b) Dead load weight of the concrete and formwork the formwork structural integrity and stability, and without
c) Construction live loads, such as the placing crews and deviating from the specified concrete elevation. If soil under
equipment or stored materials mudsills is or may become incapable of supporting super
d) Specified design strength of concrete imposed loads without appreciable settlement, it should be
e) Cycle time between the placement of successive floors stabilized or other means of support should be provided.
f) Strength of concrete at the time it is required to support Mudsills should be protected from loss of soil bearing
shoring loads from above strength. Causes might include scour due to running water,
g) The distribution of loads between floors, shores, and nearby excavations, or the increase of moisture content
rcshores or backshores at the time of placing concrete, strip caused by the supporting soil becoming wet or saturated. No
ping formwork, and removal of reshoring or backshoring concrete should be placed on formwork supported on frozen
(Grundy and Kabaila 1963; Agarwal and Gardner 1974; ground.
Stivaros and Halvorsen 1990)
h) Span of slab or structural member between permanent 4.8-Settlement
supports Formwork should be designed and constructed so that
i) Type of formwork systems, that is, span of horizontal vertical adjustments can be made to compensate for antici
formwork components and individual shore loads pated take-up, elastic deformations, and settlements
j) Minimum age of concrete when creep deflection is a
concern CHAPTER 5-CONSTRUCTION
k) Loads applied due to post-tensioning transfer
Commercially available load cells can be placed under 5.1-Safety precautions
selected shores to monitor actual shore loads to guide the Formwork engineers and formwork contractors should
shoring and reshoring during construction (Noble 1975). follow all state, local, and federal codes, ordinances, and
regulations pertaining to forming and shoring. In addition to
APPENDIX£
GUJOETO FORMWORK FOR CONCRETE (ACJ 347R-14)
the very real moral and legal responsibility to maintain safe d) Failure to comply with manufacturer's recommendations
conditions for workers and the public, safe construction is, e) Failure to construct fonnwork in accordance with the
in the final analysis, more economical than any short-tenn fonn drawings
cost savings from cutting comers on safety provisions. f) Failure to obtain fonnwork engineer's approval for field
Attention to safety is particularly significant in fonnwork modifications
construction that supports the concrete during its plastic state g) Lack of proper prepour field inspection by competent
and until the concrete becomes structurally self-supporting. persons to ensure that fonn design has been properly inter
Following the design criteria contained in this guide is essen preted by fonn builders
tial for ensuring safe perfonnancc of the fonns. All structural h) Failure to inspect fonnwork during and after concrete
members and connections should be carefully planned so placement to detect abnonnal deflections or other signs of
that a sound detennination of loads may be accurately made imminent or potential failure that should be corrected
and stresses calculated. 5.1.1.1 Examples of deficiencies in vertical formwork
In addition to the adequacy of the fonnwork, special'struc Construction deficiencies sometimes found in vertical fonn-
tures, such as multistory buildings, require consideration of work include:
the behavior of newly completed structural elements that are a) Failure to control rate of placement of concrete without
used to support fonnwork and other construction loads. Note regard to design parameters
that the strength of newly completed structural clements will b) Inadequately tightened or secured fonn ties or hardware
be less than their final design strength. c) Fonn damage in excavations resulting from embank
Fonnwork failures can be anributcd to substandard mate ment failure
rials and equipment, human error, and inadequacy in design. d) Usc of external vibrators on fonns not designed for
Careful supervision and continuous inspection of fonnwork their use
during erection, concrete placement, and removal can help e) Deep vibrator penetration of earlier semi-hardened lifts
prevent accidents. f) Improper framing of blockouts
Construction procedures should be planned in advance g) Improperly located or constructed pouring pockets
to ensure the safety of personnel and the integrity of the h) Inadequately supponed bulkheads or construction joint
finished structure. Some of the safety provisions that should fonnwork
be considered include: i) Improperly anchored top forms on a sloping face
a) Erection of safety signs and barricades to keep unau j) Failure to assess and control concrete properties and
thorized personnel clear of areas in which erection, concrete admixture effects with respect to concrete lateral pressure
placing, or stripping is under way k) Failure to provide adequate support for lateral pressures
b) Providing experienced fonnwork personnel with direct on fonnwork
communication means to the placing crew, to closely watch I) Failure to recognize and resolve forces at locations in
during concrete placement to ensure early recognition of the fonnwork where lateral pressure is not resisted by fonn
possible fonn displacement or potential failures; a supply of ties, such as at T-intersections of walls and at outside comers
extra shores or other material and equipment that might be m) Installation of lateral bracing at steeper angles than
needed in an emergency should be readily available designed, resulting in an inability to maintain lateral stability,
c) Provision for adequate illumination of the fonnwork plumb, and alignment of the fonnwork
and work area n) Placing concrete in such a manner that unbalanced
d) Inclusion of lifting points in the design and detailing forces are applied to wall opening blockouts, causing deflec
of all fonns that will be hoisted by cranes or other lifting tion or displacement of the blackout fonn
equipment. This is especially important in Hying fonns or o) Failure to provide adequate bracing resulting in attempts
climbing fonns; in the case of wall fonnwork, consideration to plumb fonns against concrete weight, wind loads, or other
should be given to an independent work platfonn adequately horizontal forces
fastened to the previous lift p) Inadequately supported wall fonn or column fonn panels
e) Incorporation of scaffolds, working platfonns, and q) Inadequate fastening of the fonn to previous concrete
guardrails into fonnwork design and all fonnwork drawings placement or foundation
f) Incorporation of provisions for anchorage of fall protec 5.1.1.2 Examples of deficiencies in horizontalformwork
tion devices, such as personal fall arrest systems, safety net Construction deficiencies sometimes found in horizontal
systems, and personnel positioning device systems fonns for elevated structures include:
g) A program of field safety inspections of fonnwork a) Failure to properly regulate the sequence of placing
5.1.1 Formwork construction deficiencies-Some concrete to avoid unanticipated loadings on the fonnwork
common construction deficiencies that can lead to fonnwork b) Shoring not plumb, thus inducing lateral loading and
failures include: reducing vertical load capacity
a) An ineffective inspection process for removing damaged c) Locking devices on metal shoring not locked, inoper
or wom material(s), accessories, or other fanning equipment ative, or missing. Safety nails missing on adjustable two
having lower strength than required piece wood shores
b) Insufficient nailing, bolting, welding, or fastening d) Failure to account for vibration from adjacent moving
c) Insufficient or improper lateral bracing loads or load carriers
AC/ 347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACt 347R·14)
"OR
Fig. 5.1.1.2a-lnadequare bearing under mudsill. Fig. 5.1.1.2b-Uplifi of formwork. Conneclion of shores to
joisls and stringers should hold shores in place when uplift
e) Inadequately tightened or secured shores and rcshores or torston occurs.
including hardware or wedges
g) Fabricate ganged fonnwork, tables, and column fonns
f) Loosening or premature removal of reshores or back·
shores under floors below on a suitable platfonn, horses, or other means of support
g) Premature removal of supports, especially under canti· to assure correct and square geometry, straight fonnwork
edges, and the absence of built-n warp within tolerances.
levered sections
h) Inadequate bearing area or unsuitable soil under 5.2.2 Joints in concre1e
mudsills (Fig. 5.1.1.2a) 5.2.2.1 Contraction joints, expansion joints, control joints,
i) Mudsills placed on frozen ground subject to thawing construction joints, and isolation joints should be installed
or on saturated ground; mudsills placed prior to a large rain as specified in the contract documents (Fig. 5.2.2.1) or as
requested by the contractor and approved by the engineer/
event during which water accumulates and washes the soil
out from under the sill architect.
k) Failure to consider effects of load transfer that can through the bulkhead, and installing the supports such
occur during post-tensioning (refer to 5.8.6) that the sheathing material is supported along these cuts
and is supported frequently enough to limit its deflection.
I) Failure to perfonn, document, and follow up on
Construction joint fonnwork should be made in such sizes
preplacement fonnwork inspections
m) Kinked, bent, or otherwise damaged shoring equipment so that it is not trapped behind the reinforcing steel. By
n) Inadequate shoring and bracing of composite construction doing this, the fonnwork can be removed more easily and,
o) Inadequate bracing for horizontal loads due to wind or in some cases, reused.
other horizontal forces 5.2.2.3 When required by the contract documents, beveled
inserts at control or contraction joints should be left undis
turbed when fonns are stripped, and then removed only after
5.2-Construction practices and workmanship
the concrete has been sufficiently cured.
5.2.1 Fabrication and assembly details-The following
are examples of good construction practice:
5.2.2.4 Wider wood feature strips, reveals, or rustications
inserted for architectural treatment can be kerfed on their
a) Properly spliced studs, wales, strongbacks, shores, and
back sides so as to allow for expansion to take place in the
other members of two or more pieces.
b) Shores should be installed plumb within the allowable wooden piece as a result of moisture absorption.
should be used. to hold the shape of the concrete during placement, unless it
d) All fonn ties or clamps should be installed and properly can be demonstrated that the top fonns can be omitted.
APPENDIXE
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
c) Blockouts, inserts, sleeves, anchors, and other embedded Table 5.3.1-Permitted abrupt or gradual irregulari
items should be properly identified, positioned, and secured. ties in formed surfaces as measured within a 5 ft
d) Fonnwork should be checked for required camber when (1.5 m) length with a straightedge
specified in the contract documents or shown on the fonn Clanofsurf�ce
AC1347R-74
GUIDE TO FORMWORK FOR CONCRETE (ACt 347R-14)
one section of the specifications should not be construed as 5.5--Shoring and centering
permitting violation of the more stringent requirements for 5.5.1 Shoring-The design process and construction prac
any other part of the construction or in any other such speci tices should be in accordance with ACI 347.2R. Shoring
fication section. should be supported on satisfactory foundations, such as
The engineer/architect should be responsible for coor spread footings, mudsills, slabs-on-ground, piers, caissons,
dinating the tolerances for concrete work with the toler or piling, as discussed in 4.7.
ance requirements of other trades whose work adjoins the Shores resting on intermediate slabs or other construction
concrete construction. For example, the connection detail already in place need not be located directly above shores
for a building's fa�,:ade should accommodate the tolerance or reshores below, unless the slab thickness and the loca
range for the lateral alignment and elevation of the perimeter tion of its reinforcement are inadequate to take the reversal
concrete member. of moments and punching shear. The reversal of bending
moments in the slab over the shore or reshore below may
5.4-lrregularities in formed surfaces occur as shown in Fig. 5.5.la. If reshores do not align with
ACI 347.3R provides detailed guidance and methods for the shores above, then calculate for reversal of moments.
producing and evaluating concrete formed surfaces. This Generally, the moment induced by the slab dead loads will
section provides a summary of ways of evaluating surface not be reversed by the effect of having the upper shore offset
variations due to forming quality but is not intended for eval in location from the reshore below. Reshores should be
uation of surface defects, such as surface voids (bugholes prevented from falling by such means as spring clips at the
and blowholes), and honeycomb attributable to placing and top of reshores and positively attaching perimeter reshores
consolidation deficiencies. These are more fully explained back into the interior of the structure with appropriate lacing
by ACI 347.3R and ACI 309.2R. Allowable irregularities or bracing. The reshoring plan should be submitted to the
are designated either abrupt or gradual. Offsets and fins engineer/architect for review related to effects on permanent
resulting from displaced, mismatched, or misplaced forms, structures. Multi-tier shoring-single-post shoring in two or
sheathing, or liners, or from defects in forming materials are more tiers-is a dangerous practice and is not recommended
considered abrupt irregularities. Irregularities resulting from (refer to Fig. 5.5.lb).
warping and similar uniform variations from planeness or Where a slab load is supported on one side of the beam
true curvature are considered gradual irregularities. only (refer to Fig. 4.1.4), edge beam forms should be care
Gradual irregularities should be checked with a straight fully planned to prevent rotating of the beam side form due
edge for plane surfaces or a shaped template for curved to unequal loading.All members should be straight and true
or warped surfaces. In measuring irregularities of plane without twists or bends. Special attention should be given
surfaces, the straightedge can be placed anywhere on the to beam and slab construction or one- and two-way joist
surface in any direction. construction to prevent local overloading when a heavily
Four classes of formed surface are defined inACI 117-10, loaded shore rests on a thin slab.
4.8.3 (Table 5.3.1). The engineer/architect should indicate Vertical shores should be erected so that they cannot tilt
which class is required for the work being specified or indi and should have a firm bearing. Inclined shores should be
cate other irregularity limits where needed; or the concrete bmced securely against slipping, sliding, or buckling. The
surface tolerances as specified in ACI 301-10, 5.3.3.3, with bearing ends of shores should be square to the supported
form-facing materials meeting the requirements of ACI member. Wedges may be cut and installed to achieve
301-10, 2.2.1.1, should be followed. full bearing on sloped surfaces or with inclined support
Class A is suggested for surfaces prominently exposed members. Connections of shore heads to other framing
to public view where appearance is of special importance. should be adequate to prevent the shores from falling out
Class B is intended for coarse-textured, concrete-formed when reversed bending causes upward dellection of the
surfaces intended to receive plaster, stucco, or wainscoting. forms (refer to Fig. 5.1.1.2b).
Class C is a general standard for permanently exposed 5.5.2 Centering- When centering is used, lowering is
surfaces where other finishes arc not specified. Class 0 is a genemlly accomplished by the use of sand jacks, jacks, or
minimum-quality requirement for surfaces where roughness wedges beneath the supporting members. For the special
is not objectionable, usually applied where surfaces will be problems associated with the construction of centering for
permanently concealed. folded plates, thin shells, and long·span roof structures, refer
Construction methods such as using metal form pans to 8.4.
provide a finish unique to itself and should be given special
consideration by the engineer/architect. Special limits 5.6--lnspection and adjustment of formwork
on irregularities can be needed for surfaces continuously Helpful information about forms before, during, and after
exposed to flowing water, drainage, or exposure. lf pcrmincd concrete placement can be found in ACI SP-2, ACI SP-4,
irregularities are different from those given in Table 5.3.1, andACI 311.4R.
they should be specified by the engineer/architect. 5.6.1 Before concrete placement-Telltale devices should
be installed on shores or forms to detect formwork move
ments during concrete placement and wedges used for final
APPENDIX£
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
II 1'1 1.1 II II
Fig. 5.5. Ja-Reshore installation. Improper positioning of shore from floor to
fo
l or can create bending stresses for which the slab was not designed.
ACI347R·14
GUtDETO FORMWORK FOR CONCRETE (ACt 347R-14)
a,, . · ·
INCORRECT:
·� � �· 1m
FORMS AND SHORING
STRIPPED IN THIS MANNER WILL CNJSE
STRESSREVEASALINTHEMIDOLESTRIP.
designated in the contract documents. It should be clearly sent. The temperature of the concrete while curing, not the
stated if a minimum time after placement is a requirement to ambient air temperature, is an important factor in the strength
strip forms in addition to the normal minimum compressive gain of concrete. The curing time and concrete temperature
strength requirement. records can serve as a basis to assist the engineer/architect
Determination of the time of form removal should be with review or approval of form stripping.
based on the resulting effect on the concrete. When forms 5.7.2.3 Because the minimum stripping time is usually
are stripped, there should be no excessive deflection or a function of concrete strength, the preferred method of
distortion and no evidence of damage to the concrete due to determining stripping time is a comparison of the actual
either removal of support or to the stripping operation (Fig. strength gained to the strength required for stripping the
5.7.2.1 ). If forms are removed before the specified curing is element. Walls, columns, and beam sides can usually be
completed, measures should be taken to continue the curing stripped at fairly low concrete strengths. Soffits of slabs,
and provide adequate thermal pr01ection for the concrete. beams, and other elevated work need greater strength to
Supporting forms and shores should not be removed from be self-supporting and carry imposed construction loads.
beams, floors, and walls until these struc!Ural units are strong ACI 301 lists tests of job�cured cylinders, several tests of
enough to carry their own weight and any approved super� concrete in place, and evaluation by the maiUrity method as
imposed load. In no case should supporting forms and shores acceptable methods of determining field strength. When the
be removed from horizontal members before the concrete contract documents do not specify the minimum concrete
has achieved the stripping strength specified by the engineer/ strength required at the time of stripping, the engineer/archi
architect. Shores supporting post-tensioned construction tect should be consulted and methods discussed in ACI 301
should not be removed until sufficient tensioning force is should be used for determining appropriate form removal
applied to support the dead load, formwork, and anticipated criteria. The elapsed times shown in Table 5.7.2.3 may be
construction loads. used as guidance for determining stripping time for general
As a general rule, the vertical forms for columns, walls, planning purposes. The times shown represent a cumulative
beam sides, and piers can be removed before horizontal number of days, or hours, not necessarily consecutive, during
forms for beams and slabs. Formwork and shoring should which the temperature of the air surrounding the concrete is
be constructed so that each can be easily and safely removed above 50°F (1 0°C). If high-early-strength concrete is used,
without impact or shock, and permit the concrete to carry its these periods can be reduced as approved by the engineer/
share of the load gradually and uniformly. architect. Conversely, if ambient temperatures remain below
5.1.2.2 The removal of forms, supports, and protective 50°F (I 0°C), or if retarding agents are used, then these
enclosures, and the discontinuation of heating and curing periods should be increased at the discretion of the engi·
should follow the requirements of the contract documents. ncer/architect. Shorter stripping times listed for live load
When standard beam or cylinder tests are used to determine to dead load ratios greater than 1.0 are the result of more
stripping times, test specimens should be cured under condi� reserve strength being available for dead load in absence of
tions that are not more favorable than the most unfavorable live load at the time of stripping. It is important to note that
conditions for the concrete that the test specimens repre- the temperature of the concrete is the key to strength gain,
APPENDIX E
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
Table 5.7.2.3-Guidance for stripping time when contract documents do not specify stripping time or
stripping strength required
Structurallin•loadnotgreatcr StructuralliH·Ioadgreater lhan
StrutturAitlcmcntsupporll'd thAnstructural dead lo�d SlrU�IUrAI dt�d load
Panjoisl forms'
30in.(760mm)wide orless Jdays )days
Over 30in.(760mm)widc 4days 4days
Joist.bcam or girdcrsoffils
Under 10ft(Jm)clearspanbc\weenslructuralsupports 7days: 4days
l 0w20ft(3to 6m)clearspanbctweens\ruc\uralsuppons l4daysl 7days
Over20ft( 6m)clear spanbc!"·eens!ruc\uralsuppons 2l days: 14days
Two-wayslabsystemsl Removal limes arc comingcm on placcmem ofreshorcs where required. Reshorcs
shouldbcplaced as soon as practicable aftcr stripping opcrations arc compkh:bu!
no!later !han the endof the workingday in"·hichslrippingoccurs.Whcrc rcshores
arert"quiredlo implemenlearly slripping"·hilc minimizing:�.ag or creep(ralher !han
for dislribution of supcrimpo>edconstruction loadsas covered in5.8),capacily and
spacing of such reshoresshould bc dcsignedby che formwork engincerleonlractor
andrevicwcdby!he engincer/architcct.
"Whc.-c such forms also supf10<1 fonn1H>rk f<>r slab<>< beam soffits, the rcmo,·•l times oflllc latter should so,·em.
1Rcfcr lO Section �.8 for S!X'cial conditions aiTe<:lingthe numbcr offtoors to remam shoml or rcshom:l
nol the ambient air temperature. Ambient air temperature loads will be distributed among all members connected by
is only used in lhis case to show a minimum ambient air reshores.
temperature that will still allow concrele temperatures to be Multistory work presents special conditions, panicularly
adequate for proper cement hydration. Concrete lemperature in relalion to Ihe removal of forms and shores. Reuse of form
inside forms can vary depending on the type of forms used material and shores is an obvious economy. Furthermore,
and any methods that are employed to reduce heat loss from the speed of construction in this type of work permits other
unformed surfaces, such as the top of a wall or top of a slab. trades to follow concrete placement operations from floor to
ACI305R and ACI 306R provide funhcr discussion of how floor as closely as possible. The shoring that supports freshly
ambient air temperature affects concrete strength gain. placed and low-strenglh early-age concrete, however, is
supponed by lower floors that were not originally designed
5.8-Shoring and reshoring of multistory specifically for these loads. The loads imposed should not
structures exceed the safe capacity of each floor providing suppon. For
This section discusses methods of shoring and reshoring this reason, shoring or reshoring should be provided for a
of multistory structures and provides general guidance and sufficient number of floors to distribute the imposed construc
considera1ions. ACI 347.2R expands on these concepts and tion loads to several slab levels without causing excessive
should be consulted for further guidance on shoring and stresses, excessive slab deflections, or both (Grundy and
reshoringpractices. Kabaila 1963; Agarwal and Gardner 1974; Stivaros and
5.8.1 Discussion-Shores or falsework are vertical or Halvorsen 1990). Reshoring is used to distribute construc
inclined suppon members designed to carry the weight of tion loads to the lower floors.
formwork, concrete, and construction loads, and reshores are In a common method of analysis (ACI347.2R;ACI SP-4),
shores placed snugly under a stripped concrete slab or struc· while reshoring remains in place at grade level, each level of
tural member after the original forms and shores have been reshores carries the weight of only the new slab plus other
removed from at least full bays. This requires the new slab or construction live loads. The weight of intermediate slabs is
structural member to deflect and suppon its own weight and not included because each slab carries its own weight before
existing construction loads applied before the installation of reshores are put in place.
the reshores. It is assumed that the reshores carry no load at Once the tier of reshores in contact with grade has been
the time of installation. Aften.vard, additional construction removed, the assumption is made that the system of slabs
ACI347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
behaves elastically. The slabs interconnected by reshores will shores below, an analysis should be made 10 determine
deflect equally during addition or removal of loads. Loads whether or not detrimental stresses are produced in the
will be distributed among the slabs in proportion to their slab. This condition seldom occurs in reshoring because the
developed stiffness. The dellection of concrete slabs can be bending stresses normally caused by the offset reshores are
considered elastic, that is, neglecting shrinkage and creep. not large enough to overcome the stress resulting from the
Caution should be exercised when a compressible wood slab carrying its own dead load. Where slabs are designed
shoring system is used. Such systems tend to shift most of for light live loads or on long spans where the loads on the
the imposed construction loads to the upper floors, which shores are heavy, care should be exercised in placing the
have less strength. Addition or removal of loads may be due shores so that the loads on the shores do not cause excessive
to construction activity or to removing shores or reshores in punching shear or bending stress in the slab.
the system. Shore loads are determined by equilibrium of While reshoring is under way, no construction loads
forces at each floor level. should be permitted on the new construction unless it has
5.8.2 Advantages of res/wring-Stripping formwork is been determined by the formwork engineer/contractor that
more economical if all the material can be removed at the the new construction can safely suppon the construction
same time and moved from the area before placing reshores. loads.
Slabs arc allowed to support their own weight, reducing the When placing reshores, care should be taken not to preload
load in the reshores. Combination of shores and reshores the lower floor and not to remove the normal deflection of
usually requires fewer levels of interconnected slabs, thus the slab above. The reshore is simply a strut and should
freeing more areas for other trades. be tightened only to the extent necessary to achieve good
If prefabricated drop-head shores are used, the shores can bearing contact without transferring load between upper and
become the reshores if a large area of shoring is unloaded, lower floors.
permitting the structural members to deflect and support 5.8.5 Removal of reshoring-Shores should not be
their own weight. The drop-head shore has a head that can be removed until the supponed slab or member has attained
lowered to remove forming components without removing sufficient strength to support itself and all applied loads.
the shore or changing its support for the floor system. Later Shores should be removed or released before reshore
the shore may be retracted and resnugged to act as a reshore. removal. Premature reshore removal can be dangerous as it
It can also be used as a backshore or preshore. can result in overloading the slabs above. Removal opera
5.8.3 Other methods-Other methods of supporting new tions should be carried out in accordance with a planned
construction are less widely used and involve leaving the sequence so that the structure supported is not subject to
original shores in place or replacing them individuatty impact or nonsymmetric load patterns.
(backshoring and preshoring), which prevents the slab from 5.8.6 Post-tensioning effects on shoring and reshoring
deflecting and carrying its own weight. Preshores and the The design and placement of shores and reshores for post
panels they support remain in place until the remainder of tensioned construction requires more consideration than for
the complete bay has been stripped and backshorcd, a small normal reinforced concrete. The stressing of post-tensioning
area at a time. These methods are not recommended unless tendons can cause overloads to occur in shores, reshores, or
performed under careful supervision by the formwork engi· other temporary supports. The stressing sequence has the
neer/contractor and with review by the engineer/architect greatest effect. When a slab is post-tensioned, the force in
because excessively high slab and shore stresses can develop. the tendon generally produces a downward load at the beam.
5.8.4 Placing reshores-When used in this section, the If the beam is shored, the shoring should be designed to carry
word "shore" refers to either rcshores or the original shores. this added load. The magnitude of the load can approach the
Reshoring is one of the most critical operations in form dead load of half the slab span on both sides of the beam. If
work; consequently, the procedure should be planned in the floor slab is tensioned before the supporting beams and
advance by the formwork engineer/contractor and should be girders, a careful analysis of the load transfer to the beam
reviewed or approved by the engineer/architect. Operations or girder shores or reshores will be required. Additionally,
should be performed so that areas of new construction will special attention should be given to locations where a post
not be required to support combined dead and construction tensioned beam intersects a post-tensioned girder with no
loads in excess of their capacity, as determined by design column at the intersection. Post-tensioning forces at these
toad and developed concrete strength at the time of stripping points due to accumulated dead load transfer can be substan
and reshoring. tial and should be accounted for in the reshoring design.
Shores should not be located so as to alter the pattern of Similar load transfer situations occur in post-tensioned
stress determined in the structural analysis of the completed bridge construction.
structure or induce tensile stresses where reinforcing bars
are not provided. Size and number of shores and bracing, CHAPTER &-MATERIALS
if required, should provide a supporting system capable of
carrying anticipated loads. 6.1-General
Where practical, shores should be located in the same posi The selection of materials suitable for formwork should
tion on each floor so that there will be continuous support be based on the price, safety during construction, and the
from floor to floor. When shores above are not directly over quality required in the finished product. Approval of form-
APPENDIX£
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
ACJ 347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI 347R-14)
Table 6 2 1-Form materials with data sources for design and specification
Princip�l uS« Dala§ources
Panelframingand bracing
AISC325- II;A1SID1()()..{18
Heavyforms andfalsework
Shoring SH 304-00
lntcmaland under-slabvoidforms
CorrugatL-dcardboard Voidforms in beams and girdcrs{normally used "'ith Zil·ens(l%4)
intemalcgg-crate stiffeners)
Stay-in-placeforms
Concrete AC1318
Moldsforprecast units
Ready-made columnforms
Form ties
"Structuf111 composnc lumber producu are propnmry and untquc to a parttcular manufacturt:r. They cannot be mtert:hanged because 11\dusuy ""'de commoo grades ha•e 1>01 bc.>n
estobli$hed to scn·c as a basis for�ui•·aknce
'Shouldbc rt:adilyweldablc al\d protectedagainstsat.·antc actioo atthepointof cootactwithsteel.lfuscd as a facingmaterialin cootaC1withfresh concretc.it shouldbc oonrt:ac
'i'·ewcoocretc or concme cootaining calciumchloride.
:clw:cksurface rt:actioo""-ithwetroncrcte.
No:>�c; Manufacturers" recommendations. "hen supported by u:st data and fidd c•pericnce.are a primary source for many form materials. Jn addition. the handbooks, standards.
specification•.and otbcrdatasourccs citcdflcrcinarclistcdin more detailinACISf>-4al\d inthe rcfcrencescited inChaplcr8al\dCbaptcrlOofthis document
APPENDIX£
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
removed unless the contract documents pennit their remaining to architectural concrete. Additional information is available
in place. A minimum specification for fonn tics should require in ACI 301. ACI 303R, and ACI 347.3R.
that the bearing area of external holding devices be adequate This chapter identifies and emphasizes additional factors
to prevent excessive bearing stress in the fonn members. It is that can have a critical influence on fonnwork for cast-in
important to minimize mortar leakage at fonn ties. place architectural concrete. Tilt-up, precast archit<.-ctural
Fonn hangers should support all construction loads concrete, and concrete receiving coatings or plasters that
imposed on the formwork supported by the hangers. Fonn hide the surface color and texture arc not considered herein.
hangers should be symmetrically arranged on the supporting Concrete receiving coatings or plasters that hide the surface
member and loaded symmetrically, through proper color and texture is not considered architectural.
sequencing of the concrete placement, to minimize twisting 7.1.2 Factors affectingformwork-Architectural concrete
or rotation of the hanger or supporting members. Form is concrete that will be pcnnanently exposed to view and
hangers should closely fit the flange or bearing surface of therefore requires special care in the selection of the
the supporting member so that applied loads are transmitted concrete materials, fanning, placing, and finishing to obtain
properly as per the manufacturer's instructions. the desired architectural appearance. Architectural concrete
Where the concrete surface is exposed and appearance should be specifically designated as such in the contract
is important, the proper type of form tie or hanger will not documents. Particular care should be taken in the selec
leave exposed metal at the surface. Noncorrosive materials tion of materials, design, and construction of the fonnwork,
should be used when tie holes are left unpatched, exposing and placing and consolidation of the concrete to eliminate
the tie to possible corrosion. bulges, offsets, or other unsightly features in the finished
surface and to maintain the integrity of the surface texture
6.4-Form coatings and release agents or configuration. The character of the concrete surface to be
6.4.1 Coatings-Fonn coatings or scalers are usually produced should also be considered when the form materials
applied in liquid fonn to contact surfaces either during manu are selected. Special attention should be given to closure
facture or in the field to serve one or more of the following techniques, concealment of joints in formwork materials,
purposes: and to the scaling of fonns to minimize mortar leakage.
a) Alter the texture of the contact surface 7.1.3 Factors in addition to formwork-Many factors
b) Improve the durability of the contact surface other than fonnwork affect the architectural effects achieved
c) Facilitate release from concrete during stripping in concrete surfaces. They start at the design stage and
d) Seal the contact surface of the fonn from intrusion of carry through to the completed project. Factors affecting
moisture the surface appearance of the concrete can also include the
6.4.2 Release agenls-Fonn release agents are applied to mixture proportions or aggregate, the method of placing the
the fonn contact surfaces to prevent bond and thus facili concrete, the consolidation technique, and the curing proce
tate stripping. They may be applied pennanently to certain dure. Chemicals can have an effect on the final product,
fonn materials during manufacture, but arc nonnally applied whether used as additives in the mixture; applied directly
to the fonn before each use. When applying in the field, be to the concrete, such as curing compounds; or applied indi
careful to avoid coating adjacent construction joint surfaces rectly, such as fonn release agents. Even after the structure is
or reinforcing steel. completed, weather and air pollution will affect the appear
6.4.3 Manufacturers' recommendations-Manufacturers' ance of the concrete. These and other influencing factors
recommendations should be followed in the use of coat should be identified and their effects evaluated during the
ings, sealers, and release agents. Independent verification initial design stages. The single most important factor for
of product pcrfonnance is recommended before use. When the success of architectural concrete construction is quality
concrete surface color is critical, effects of the coating, workmanship.
sealing, and release agents should be evaluated. Where 7.1.4 Uniform construction procedures-Architectural
surface treatments such as paint, tile adhesive, sealers, or concrete should minimize color variations and differences
other coatings are to be applied to fanned concrete surfaces, in surface finish. The best way for the contractor to achieve
be sure that adhesion of such surface treatments will not this unifonnity is to maintain consistency in all construc
be impaired or prevented by use of the coating, sealers, or tion practices. Fanning materials should remain the same
release agent. Also, consider bonding requirements of subse throughout the project, and release agents should be applied
quent concrete placements. Follow the manufacturer recom unifonnly and consistently. Placement and consolidation of
mendations when applying fonn release agents. A common the concrete should be standardized so that unifonn density
problem is applying too much material, which can nega is achieved. Stripping and curing sequences should be
tively affect the surface of the concrete. consistenl throughout the work to minimize color variations.
ACI347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACt 347R-14)
The architect can use the latest information available in the zontal long-span member is sagging). The architect should
an of forming and concrete technology during the design be aware that horizontal members are checked for compli
process to keep plans in line with the budget for the struc ance with tolerances and camber before the removal of the
ture. Intricacies and irregularities, however, can raise the forms and shores. Detennining the correct amount of camber
budget to a point that outweighs the aesthetic contributions is not an exact science. If the calculated camber for a specific
of the architectural concrete. The architect can make form member does not result in its deflection to a straight line, the
reuse possible by standardizing building elements such as result wi11 be a convex or concave concrete surface.
columns, beams, and windows, and by making uninterrupted 7.2.5 Joims and details-Location, number, and details
form areas the same size wherever possible to facilitate of items such as openings, contraction joints, construc
the use of standard form gangs or modules. The increased tion joints, and expansion joints should be shown on the
size of these uninterrupted areas will contribute to forming design drawings or the architect should specify a review
economy and greater uniformity of appearance. A prebid of the proposed location of all of these details as shown on
conference with qualified contractors will bring out many the formwork drawings. (Some guidance on joint locations
practical considerations before the design is finalized. can be found in ACI 224R, 303R, and 332.1 R.) Because it
7.2.2 Comract doc11mems and advance approvals-The is impossible to disguise the presence of joints in the form
architect should prepare contract documents that fully face, it is important for their positions to be predetermined
instruct the bidder as to the location and desired appearance and, if possible, planned as part of the architectural effect.
of architectural surfaces, as well as other specific require The architect can plan joint locations between surface
ments listed in 7.2.3 to 7.2.7. Specifying a preconstruction areas on a scale and module suitable to the size of available
mockup prepared and finished by the contractor for approval materials and prevailing construction practices. If this is not
by the architect using proposed form materials; jointing tech aesthetically satisfactory, dummy joints can be introduced
niques; and form surface treatments such as wetting, oiling, to give a sma11er pattern. Actual joints between sheathing
or lacquering should be a requirement for all architectural materials can be masked by means of rustication strips
concrete. Once such a mockup has been completed to the attached to the fonn face. Rustication strips at horizontal
satisfaction of the architect and owner, it should remain at and vertical construction joints can also create crisp edges
the site for the duration of the work as a standard with which accented by shadow lines instead of the potential ragged
the rest of the work should comply. edge of a construction joint left exposed to full view. Special
Design reference samples, which are smaller specimens care should be taken during placement and vibration to mini
of concrete with the proposed surface appearance, may also mize surface voids (bugholes) and honeycombing that form
be created for approval by the architect that can help define when air is trapped beneath horizontal rustications.
what is required for the mockup. Small samples like these, Sometimes construction joints in beams can be concealed
kept at the job site for reference, arc not as good as a full above the support columns and joints in floors above their
scale mockup, but can be helpful in defining mockup require supporting beams instead of in the more customary regions
ments. The samples should be large enough to adequately of low shear in beams and slabs, usually the middle third of
represent the surface of the concrete desired. The samples the span.
are to be used as a basis for the mockup only. Several 7.2.6 Ties and inserts-Form ties and accompanying
should be made to represent the variations that can occur tie holes are an almost inescapable part of wa11 surfaces.
in the final finish. It would be helpful for all architectural Architects frequently integrate tie holes into the visual design
concrete to include a required mockup so that the contractors quality of the surface. If this is planned and any effects or
can demonstrate they are capable of producing the desired materials other than those provided in 7.3.4 are desired, they
results. The mockup should be approved in writing by the should be clearly specified as to both location and type.
architect and owner. Where tie holes are to be patched or filled, the architect
It can be helpful to specify viewing conditions under should specify the treatment desired and specify examples
which the concrete surfaces will be evaluated for compli of the patches as part of the mockup.
ance with the approved mockup. 7.2. 7 Cover over reinforcing steel-Adequate cover over
7.2.3 Tolerances-The architect should specify dimen reinforcement, as required by codes, is needed for protec
sional tolerances considered essential to the successful tion of steel and long-term durability of the concrete.
execution of the design, keeping in mind that tolerances in Reinforcement that is properly located is important in the
excess of those specified in ACl 117 need to be necessary, control of surface cracking. For positive control of required
achievable, and economically feasible. ACI 303R and 1 17 cover, the architect can specify appropriate side fonn spacers
may be consulted for further discussions concerning toler as defined in 6.3.4.
ances for architectural concrete. The architect should specify sufficient cover to allow
7.2.4 Camber-The contractor should camber form for any reduction that will result from the incorporation of
work to compensate for deflection of the fonnwork during grooves or indented details and from surface treatments such
concrete placement. The architect should, however, specify as aggregate exposure and tooling. The maximum thickness
any additional camber required to compensate for structural of any material to be removed should be added to basic
deflection or optical sag (the i11usion that a perfectly hori- required cover.
APPENDIX£
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
7.3-Materials and accessories start erecting or closing fonnwork until the reinforcing steel
7.3.1 Sheathing or form facing-Architectural concrete is in its correct location, in a relaxed state, so that it does
fonn sheathing should be of appropriate quality to main not rely on the fonnwork to push it into correct position.
tain the specified unifonnity of concrete surfaces through Contractors are encouraged to experiment with different
multiple uses and to control deflection within specified limits. types of spacers for differem exposed elements to detcnnine
Plywood, steel, glass fiber-reinforced plastic, aluminum, and which are best for the various applications on a project. The
other suitable materials can all be used as sheathing or facing same spacers that will be used on the finished work should
materials. Select the grade or class of material needed for be incorporated in the mockup.
pressure, framing, and deflection requirements. Be sure that 7.3.6 Reinforcing accessories and tie wire-Noncorrosive
the chosen material meets the specification requirements for types of tic wire and accessories should be used for archi
the concrete surface texture. Procedures for controlling the tectural concrete, especially when close to or in contact with
rusting of steel fonns should be carefully followed. the fonns. Suitable materials include stainless steel, epoxy
7.3.2 Stmctura/ framing-Form facing can be supported coated material, or plastic-coated material; use of these items
with lumber, steel, or aluminum members straight and rigid needs to be specified. Stainless steel is often the best choice
enough to meet the architectural specifications. as wire snippings often fall into the fonns and are difficult to
7.3.3 Form liners-A fonn liner is a material attached remove before placing concrete.
to the inside face of the fonn to alter or improve surface
texture or quality of the concrete. It is not required struc· 7.4-0esign
turally. Wood, rigid plastic, elastomcric materials, and glass 7.4.1 Special considerations-The general design proce
fiber-reinforced plastics are all suitable liner materials when dure will follow the principles outlined in Chapter 4. The
carefully detailed and fabricated. Plastics should be handled fonnwork engineer/contractor, however, will frequently
and assembled with care to avoid distortion caused by daily need to work with limitations imposed by the architectural
temperature cycles at the job site. design. Some of these considerations include tie spacing
7.3.4 Form ties-Fonn-tie assemblies for architectural and size, fonn facing preferences, location and special treat
concrete should pennit tightening of fonns and leave no ment of fonn joints, special tolerances, and use of admix
metal closer to the surface than 1-1/2 in. (38 mm) for steel tures. Because these factors can influence fonn design, they
ties and I in. (25 mm) for stainless steel ties. The ties should should be fully reviewed at the beginning of the fonn design
not be fitted with lugs, cones, washers, or other devices that process.
will leave depressions in the concrete Jess than the diameter 7.4.2 Lateral pressure of concrete-Architectural concrete
of the device, unless specified. Ties should be tight fitting or can be subjected to external vibration, revibration, set
tie holes in the fonn should be sealed to minimize leakage at retarding admixtures, high-range water-reducing admix
the holes. If textured surfaces are to be fanned, ties should tures, and slumps greater than those assumed for deter
be carefully evaluated with regard to fit, pattern, mortar mining the lateral pressure as noted in 4.2.2. Particular care
leakage, and aesthetics. should be exercised in these cases to design the forms for the
7.3.5 Side form spacers-Side fonn spacers, as defined increased lateral pressures that may result from these effects,
in 6.3.4, are particularly important in architectural concrete high rates of pour, or from other effects noted in 4.2.2.
to maintain adequate cover over reinforcing steel and to 7.4.3 Structural considerations-Because deflections in
prevent development of rust streaking on concrete surfaces. the contact surface of the fonnwork directly influence the
Plastic, plastic-protected, rubber-tipped, or other noncor appearance of finished surfaces viewed under varying light
roding spacers should be anached to the reinforcing bar so conditions, forms for architectural concrete should be calcu
that they do not become dislodged during concrete place lated and evaluated carefully to minimize deflections. In
ment and vibration. The number and location of the side most cases, deflections govern design rather than bending
fonn spacers should be adequate for job conditions. (flexural stress) or shear. Deflections of sheathing, studs,
A contributing factor to reinforcing spacers being visible and wales should be designed so that the finished surface
at exposed concrete surfaces is the amount of load that meets the architectural specifications. Limiting these deflec
exists between the reinforcing steel, the spacer, and the tions to //400, where l is the clear span between suppons, is
fonn facing. If the reinforcing steel is installed plumb, satisfactory for most architectural fonnwork (refer to ACJ
straight, and with the correct spacing where it protrudes 301 and ACI 303R). Fonns bow with reuse; therefore, more
from previous castings, there should not be an extraordinary bulging will occur in the fonned surface after several uses
amount of force required between these elements and the of the same fonn. This effect should be considered when
spacer should be there only to prevent the reinforcing bar designing fonns.
from being displaced during concrete placement operations. When tic size and spacing are limited by the architect,
If, on the other hand, the fonnwork and spacers are being the fonnwork engineer/contractor may have to reverse the
used to forcibly push the reinforcing bar into position, there usual procedure to arrive at a balanced fonn design. Given
is a chance that the legs of the spacers can leave imprints in the capacity of the available tie and the area it supports, the
the sheathing that will result in visible spacers. There is also fonnwork engineer/contractor can find the allowable pres
a chance that the fonnwork itself can be distorted by these sure, design supporting members, and establish a rate of
forces. With architectural fonnwork, it is advisable not to concrete placing.
ACI 347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
Where wood fonns arc used, stress-graded lumber (or two-way joist systems) in areas that are considered archi
equivalent) free of twists and warps should be used for tectural, the architect and engineer should coordinate their
structural members. Fonn material should be sized and posi requirements to be sure the architectural effect is consistent
tioned to limit deflections within the requirements of the with the fanning method and material specified.
project specification. Joints of sheathing materials should be Fonns that will be reused should be carefully inspected
backed with structural members to minimize offsets. and cleaned after each usc to ensure that they have not
7.4.4 Tie and reanchor design-Tie layout should be become damaged, distorted, disassembled, or otherwise
planned. If the holes arc to be exposed as part of the archi unable to perfonn as designed.
tectural concrete, tie placement should be symmetrical 7.5.:Z Sheathing and jointing-Contact surfaces of the
with respect to the member fanned. If tie holes are not to fonnwork should be carefully installed to produce neat and
be exposed, ties should be located at rustication marks, symmetrical joint patterns, unless otherwise specified. Joints
control joints, or other points where the visual effect will be should be either venical or horizontal and, where possible,
minimized. should be staggered to maintain structural continuity.
Externally braced fonns can be used instead of any of the Nailing should be done with care using hammers with
aforementioned methods to avoid objectionable blemishes smooth and well-dressed heads to prevent marring of the
in the finished surface. Externally braced fonns, however, fonn surfaces. When required, box nails should be used on
can be more difficult and more costly to build. the contact surface and should be placed in a neat pattern.
Consideration should be given to re-anchoring fonns in Screws are often used to fasten the sheathing. Back fastening
preceding or adjacent placements to achieve a tight fit and should be used if the imprints from nail or screw heads are
minimize grout leakage at these points. Tics should be objectionable.
located as close as possible to the construction joint to facili Wherever possible, sheathing or panel joints should be
tate re-anchoring the fonn to adjacent placements. positioned at rustication strips or other embedded features
7.4.5 Joints and details-In architectural concrete, joints that can conceal or minimize the joint.
should, where feasible, be located at the junction of the Construction joints should be fonncd with a grade strip
formwork panels. At contraction or construction joints, attached to the fonn to define a clean straight line on the
rustication strips should be provided and fastened to the face joint of the fanned surface. Fonnwork should be tightened
or back-fastened to the fonns. at a construction joint before the next placement to minimize
Comers should be carefully detailed to minimize grout seepage of water and mortar between the fonn and previ
leakage. Sharp comers should, wherever possible, be elimi ously placed concrete surfaces.
nated by the usc of chamfer strips except when prohibited by Architectural concrete fonns should be designed to mini
project specifications. mize water leakage and avoid discoloration. One method to
7.4.6 Tolerances-The fonnwork engineer/contractor minimize water loss from the concrete at the joints between
should check for dimensional tolerances specified by the sections of the formwork and at construction joints is to
architect that can have a bearing on the design of the fonns. attach a gasket of flexible material to the edge of each panel.
If no special tolerances are given, the fonnwork engineer/ The gasket is compressed when the fonnwork is assembled
contractor can usc ACI 117 tolerances for structural concrete. or placed against the existing concrete. Caulk, tape, joint
compound, or combinations of these can be used to seal
7.5-Construction joints. In all cases, unsupported joints between sheathing
7.5.1 Generai-Fonns should be carefully built to resist sheets should be backed by framing. Tight fonns require
the pressures to which they will be subjected and to limit more care during vibration to remove entrapped air that can
deflections to a practicable minimum within the tolerances cause surface voids (bugholes).
specified. Joints in structural members should be kept to a Textured surfaces on multi-lift construction should be
minimum and, where necessary, should be suitably spliced separated with rustication strips or broad reveals because
or otherwise constructed to maintain continuity. accumulation of construction tolerances, random textures,
Pour pockets for vibrating or placing concrete should be or both. prevents texture matching. Furthcnnore, the grout
planned to facilitate careful placement and consolidation of seal between the bottom of a textured liner and the top of
the concrete to minimize segregation, honeycomb, sanding, the previous placement is impractical without the rustication
or cold joints in the concrete. It should be noted that if pour strip.
pockets are required on the fonns for architectural concrete, 7.5.3 Cleaning. coating. and release agenls-Fonn coat
they will nonnally leave a mark on the finished concrete. ings or releasing agents should be applied before reinforcing
The location of pour pockets should be coordinated with the steel is placed and should be applied carefully to avoid
architect. contacting adjacent construction joints or reinforcement.
Attachment of inserts, rustication strips, and ornamental The form coating to be used should not stain the concrete or
reliefs should be planned so that fonns can be removed impair the adhesion of paints or other surface treatments and
without exerting pressure on these attachments or causing should be submitted to the architect for approval.
damage to the fonns. Fonn sealers should be tested to ensure that they will not
Where special fanning systems are specified by the engi adversely affect the texture when a fonn lining material is
neer of the project for structural purposes (such as one- and used.
APPENDJXE
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
Ties that are to be pulled from the wall should be coated 7.6.3 Uniformity-To maximize surface quality, unifor
with nonstaining bond breaker or encased in sleeves to facil mity in stripping time and curing practices are essential.
itate removal. Where the objective is to produce as consistent an appear
Fonns should be carefully cleaned and repaired between ance as possible, it is beneficial to protect the concrete by
uses to prevent deterioration of the quality of surface fanned. leaving the fonnwork in place somewhat longer than nonnal.
Film or splatter of hardened concrete should be completely Early exposure of concrete to the air affects the manner in
removed. which the surface dries. Ambient conditions and sunlight
7.5.4 Ornamental liners and detail-Ornamental concrete exposure can influence the eventual color of the concrete.
is usually fonned by elastomeric molds or wood, plastic, 7.6.4 Avoiding thermal shock-Cold-weather concrete
or plaster waste molds. Members making up wood molds placement requires that special attention be paid to the
should be kerfed on the back wherever such members can sudden temperature change of concrete. To avoid thennal
become wedged between projections in the ornament. Molds shock and consequent crazing of the concrete surface, the
should be constructed so that joints will not be opened by change in temperature of the concrete should be controlled
slight movement or swelling of the wood. Joints in the molds within the limits outlined in ACI 303R. This can be accom
should be made inconspicuous by sealing. plished by heating the work area, leaving the fonns in place
The molds should be carefully set in the forms and securely to contain the heat of hydration, or by insulating the concrete
held in position to reproduce the design shown on the plans. after the fonns have been removed (refer to ACl 306R).
Where wood fonns adjoin molds, the wood should be neatly Positive steps should be taken to inspect, record, and docu
fitted to the profile of the mold and all joints should be care ment the procedures used to cure the concrete. It should be
fully scaled. The molds and the adjacent wood fonns should noted that it is the temperature of the concrete that is impor
be detailed so that the wood fonns can be stripped without tant to proper curing, not the ambient air temperature.
disturbing the molds. The edge of the mold or pattern strip
should be tapered to a slight draft to pennit removing the CHAPTER 8-SPECIAL STRUCTURES
detail material without damaging the concrete. Special
provisions should be made for early fonn removal, retar 8.1-Discussion
dation, or both, when sandblasting, wire brushing, or other Fonnwork for all structures should be designed,
treatments are required. constructed, and maintained in accordance with recommen
Fonn liners should be attached securely with fasteners or dations in Chapters I to 6. This chapter deals with the addi
glue recommended by the manufacturer. The fonn behind tional requirements for formwork for several special classes
the liner should hold the fasteners. The surfaces should be of work. ACI 372R and 373R contain information on design
cleaned and dried thoroughly so that the glue will bond. Do and construction of circular prestressed-concrete structures.
not use glue at temperatures lower than those recommended
by the manufacturer. 8.2-Bridges and viaducts, including high piers
8.2.1 Discussion-The construction and removal of form
7.6--Form removal work should be planned in advance. Fonns and supports
7.6.1 Avoiding damage-When concrete surfaces are to be should be sufficiently rigid to ensure that the finished struc
left as cast, it is important not to damage or scar the concrete ture will fulfill its intended structural function and that
face during stripping. Forms should be supported so that exposed concrete finishes will present a pleasing appearance
they do not fall back or against the architectural surface. The to the public.
use of pry bars and other stripping tools should be strictly 8.2.2 Shoring and centering-Recommended practice in
supervised. In no case should pi)' bars be placed directly 5.5 and 5.7 for erection and removal should be followed.
against the concrete. Even the use of wood or plastic wedges In continuous structures, support should not be released in
does not ensure that damage will not occur. Once fonnwork any span until the first and second adjoining spans on each
is removed. the architectural surfaces should be protected side have reached the specified strength. For post-tensioned
from continuing construction operations as specified in the bridges, the shore design should consider the resulting
contract documents. redistribution of loads on the shores similar to the effects
7.6.2 Concrete strength-It is desirable for architcc discussed in 5.8.6.
IUral concrete to have a higher compressive strength than 8.2.3 Forms-Forms can be of any of a large number
normal for stripping. This can be accomplished by adjusting of materials but the most common are wood or metal.
the mixture proportions or leaving fonns in place longer. They should be built mortar-tight of sound material strong
If concrete is not strong enough to overcome the adhesion enough to prevent distortion during placing and curing of
between the fonn surface and the concrete, concrete can scale the concrete.
or spaII. Therefore, a good quality surface might require the
fonns to stay in place longer. The longer the fonns stay in 8.3-Structures designed for composite action
place, however, the darker the concrete will become. The 8.3.1 Recommendations-Structures or members that are
engineer/architect should specify what concrete strength is designed so that the concrete acts compositely with other
required before stripping can take place. materials or with other parts of the structure present special
fanning problems that should be anticipated in the design of
ACI347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
the structure. Requirements for shoring or other deflection Where camber is required, a distinction should be made
control of the fonnwork should be clearly presented by the between the part that is an allowance for settlement or deflec
engineer/architect in the specifications. Where successive tion of fonnwork or shoring and the portion of camber that
placements are to act compositely in the completed struc is provided for design loadings. The fanner should generally
ture, deflection control becomes critical. be the responsibility of the fonnwork engineer/contractor
Shoring, with or without cambering portions of the struc who designs the fonns and supports unless such camber is
ture during placement and curing of the concrete, should be stipula1ed by the engineer/architect. Measurement of camber
analyzed separately for the effects of dead load of newly provided for structural design loadings should be made after
placed concrete and for the effect of other construction loads hardening of the concrete but before removal of the supports
that can be imposed before the concrete attains its design (refer to 3.2.5). This is because the structural deflection
strength. occurring upon removal of the suppons is a function of the
8.3.2 Design-Fonnwork members and shores should be structural design and cannot be contro11ed by the contractor.
designed to limit deflections to a practical minimum consis 8.3.4 Removai-Fonns, supports, or both, should be
tent with the structural member being constructed. Where removed only after tests and specified curing operations
camber is specified for previously installed components of indicate, to the satisfaction of the engineer/architect, that
the structure, allowance should be made for the resultant the most recently placed concrete has attained the strength
preloading of the shores before application of the dead load required to develop composite action, and then only after
of concrete. approval of the engineer/architect. The sequence of such
In members constructed in several successive placements, removal should be approved by the engineer/architect.
such as box-girder structures, fonnwork components should
be sized, positioned, supported, or all three, to minimize 8.4-Folded plates, thin she11s, and long-span roof
progressive increases in deflection of the structure that would structures
excessively preload the reinforcing steel or other portions of 8.4.1 Discussion-For long-span and space structures
the composite member. requiring a complex, three-dimensional design analysis, and
In multistory work where shoring of composite members presenting three-dimensional problems in fonnwork design,
is required, consideration should be given to the number of erection, and removal, fonnwork planning should be done
stories of shores necessary, in conjunction with the speed of by fonnwork engineers having the necessary special quali
construction and concrete strengths, to minimize deflections fications and experience. These fonnwork engineers should
due to successive loadings. Distinction should be made in consult and cooperate with the engineer/architect to make
such analyses between shores posted to relatively unyielding sure that the resulting surfaces will confonn to the engineer/
supports, such as foundations, and shores posted to struc architect's design.
tures or members that are already elastically supported (refer 8.4.2 Design-The following are items that should be
to 5.8). included in the contract documents:
Composite construction can incorporate beams of rela a) The engineer/architect should specify limiting values
tively light cross sections that are fully adequate when and directions of the reactive forces when the falsework is
construction is complete. During construction, however, supported by the pennanent structure.
these beams may require lateral support from the fonnwork. b) When applicable, the engineer/architect should include
The engineer/architect should alert the contractor to this a decentering sequence plan with the bidding documents as
condition in general notes on the strucrural drawings or in a basis for the design of the fanning and support system 10
notes on applicable drawings where this condition exists. be used by the contractor.
The fonnwork engineer/contractor should be alert to this c) In detennining the lateral forces acting on the fonn
possibility and provide shoring or lateral support where work, the wind load should be calculated on the basis of a
needed. minimum of 15 lb/ft2 (0.72 kPa) of projected vertical area
8.3.3 Erection--Construction of pennancnt elements, as specified for wall fonns in 4.2.3. For structures such as
erection of fonnwork, or both, for composite construc domes, negative forces due to suction created by the wind
tion follows basic recommendations contained in Chapter on the leeward side of the structure should be considered.
5. Shoring of members that will act compositely with the d) The recommendations of 4.1.I and 4.3 should be
concrete to be placed should be done with great care to followed in fonnwork planning.
ensure sufficient bearing, rigidity, and tightness to prevent Fonnwork design loads should be shown on the fonnwork
settlement or deflections beyond allowable limits. Wedges, drawings. Complete stress analyses should be prepared by
shims, and jacks should be provided to penn it adjustment if structural engineers experienced in these types of structures,
required before or during concrete placement, as well as to and the maximum and minimum values of stress, including
pennit removal without jarring or impacting the completed reversal of stress, should be shown for each member for
construction. Provision should be made for readily checking the most severe loading conditions. Consideration should
the accuracy of position and grade during placement. Even be given 10 unsymmetrical or eccentric loadings that might
though adjustment of fonns may be possible during or after occur during concrete placement and during erection, decen
placing, it is not recommended and may only be attempted tering, or moving of travelers. The vertical or lateral deflec
prior to initial set of the concrete. tion of the moving fonns or travelers, as well as the stability
APPENDIXE
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
under various loads, should be investigated to confirm that to ACl 334.1 R, 5.2.3). Decentering should begin at points
the formwork will function satisfactorily and that the speci of maximum deflection and progress toward points of
fied tolerances will be met. minimum deflection, with the decentering of edge members
Panicular care should be taken in the design and detailing proceeding simultaneously with the adjoining shell.
of individual members and connections. Where truss
systems are used, connections should be designed to keep 8.5-Mass concrete structures
eccentricities as small as possible to minimize deflections 8.5.1 Discussion-Mass concrete occurs in heavy civil
or distonions. engineering construction, such as in gravity dams, arch
Because the weight of the formwork can be equal to or dams, gravity-retaining walls, lock walls, power-plant struc
greater than the design live load of the structure, form details tures, and large building foundations (ACI 207.1 R). Special
should be designed to avoid the formwork hanging up and provisions arc usually made to control the temperature rise
overloading the structure during decentering. in the mass by the use of cement or cementitious material
Due to the special shapes involved, tolerances should be combinations possessing low or moderate heat-generating
specified by the engineer/architect in the bidding documents. characteristics, by postcooling (cooling the fresh concrete)
8.4.3 Drawings-When required, the formwork engineer/ or by placing sequence. Heat rise in mass concrete is most
contractor should submit detailed drawings of the formwork often controlled by replacement of cement with pozzolans,
for approval of the engineer/architect. particularly fly ash.
These drawings should show the proposed concrete Fonnwork for mass concrete falls into two distinct catego
placing sequence and the resulting loads. To ensure that the ries: low lift and high lift. Low-lift formwork, for heights
structure can assume its deflected shape without damage, the of 5 to 10 ft (1.5 to 3 m), usually consists of multi-use steel
dccentcring or handling sequence of the formwork should cantilever form units that incorporate their own work plat
be shown on the drawings. The formwork design, drawings, forms and, on occasion, lifting devices. High-lift formwork
and procedures should comply with federal and local safety is comparable to the single-usc wood forms used extensively
laws, as well as the contract documents. for structural concrete.
Deflection of these structures can cause binding between 8.5.2 Lateral pressure of concrelt-'-The lateral pressure
the form and the concrete during decentering. Formwork formulas for concrete placed in walls can be used for mass
drawings and form details should be planned to prevent concrete (refer to 4.2.2). The formwork engineer needs to
binding and facilitate stripping of forms. Drawings should carefully review the concrete mixture proportion to deter
show such details as the type of insens and joints in mine the appropriate formula from 4.2.2. Concrete additives
sheathing, where spreading of the form can result in the form or cement substitutes can improve heat generation character
becoming keyed into the concrete. istics, but the same materials can increase concrete set time
8.4.4 Approval-The engineer/architect should review and increase lateral pressures.
the design and drawings for the formwork and the proce Consideration should be given to placing sequence in the
dures for construction to ensure the structural integrity of the determination of pressure. Frequently, concrete is layered in
permanent structure. The engineer/architect should approve such a way that the fresh concrete rate of placement locally
in writing the loads imposed by the formwork, the sequence is substantially greater than the average rate of placement.
of the concrete placing operations, and the timing and proce Local lateral pressures can be greater than would be esti
dures of dccentering and stripping. mated on the basis of the average rate of placement. In addi
8.4.5 Construction-In planning and erecting formwork, tion, the use of large concrete buckets with rapid discharge
provisions should be made for adequate means of adjustment of concrete can cause high impact loads near the forms.
during placing where necessary. Telltales should be installed 8.5.3 Design considerations-Mass concrete forming can
to check alignment and grade during placement. Where the require special form tie and anchor design. Forming sloping
forming system is based on a cenain placing sequence, that surfaces requires ties or anchors to resist pressures that are
sequence should be clearly defined by the formwork engi perpendicular to the face of the form. Therefore, only using
neer/contractor and adhered to in the field. horizontal ties will leave the vertical component of pressure
8.4.6 Removal of formwork-Formwork should be untied. Vertical (hold-down) anchors should be used. Forms
removed and decentered in accordance with the procedure tied or anchored to a rock face require particular care. Often.
and sequence specified on the form drawings or on the rock anchors are placed before the forms are erected. This
contract documents. Decentering methods used should be requires the form designer to accommodate tie and anchor
planned so as to prevent unanticipated concentrated reac misalignment. The fonnwork engineer/contractor should
tions on the permanent structure. Due to the large deflec check to assure that loads resulting from the tie spacings do
tions and the high dead load-to-live load ratio common to not exceed the working capacity of the rock anchors.
this type of structure, decentering and form removal should Bending and welding of high-tensile-strength steel tie
not be permitted until specified tests demonstrate that the rods should not be pennittcd without the approval of the tic
concrete strength and the modulus of elasticity specified in manufacturer. Any approved welding should be by a welder
contract documents have been reached. Although required certified by the American Welding Society (AWS) using
compressive strengths may already have been attained, approved written welding procedures.
moduli of elasticity can control time of decentering (refer
AC1347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R·14)
The capacity of anchors and form ties embedded in previ the pressure should be compatible with the pressures
ously placed concrete is dependent on the strength of the discussed under vertical loads in 8.6.2.1.
concrete, which is very low at early ages. The embedded 8.6.3 Drawings-In addition to the provisions of Chapters
strength should be sufficient to sustain design loadings from 3, 4, and 5, the following data should be included on the
the new placement and initial bolting stresses. drawings for specialized formwork and formwork for
tunnels:
8.6---Underground structures a) All pressure diagrams used in the design of the fonn,
8.6.1 Discussion-Underground structures differ from including diagrams for uplift, unbalanced lateral or vertical
corresponding surface installations in that the construc loads, pressurized concrete, or any other load applicable to
tion takes place inside an excavation instead of in the open, the particular installation
presenting unique problems in handling and supporting b) Recommended method of supplemental strutting or
formwork and in the associated placement of concrete. As bracing to be employed in areas where form pressures can
a result, four factors usually make the design of formwork exceed those listed due to abnormal conditions
for underground structures entirely different than for their c) Handling diagrams and procedures showing the
above-ground counterparts. First, concrete to fill otherwise proposed method of handling the form during erection or
inaccessible areas can be placed pneumatically or by posi installation for concrete placement plus the method of
tive displacement pump and pipeline. Second, rock is some bracing and anchorage during normal operation
times used as a form backing, permitting the use of rock d) Concrete placement method and, for tunnel arch forms,
anchors and tie rods instead of external bracing and shores. whether the design is based on the bulkhead system of
Third, the limits of the excavation demand special handling concrete placement or the continuously advancing slope
equipment that adds particular emphasis to the removal and method
reuse of forms. Fourth, rock surfaces can sometimes be used e) The capacity and working pressure of the pump and
for attaching hoisting devices. size, length, and maximum embedment of the discharge line
When placement is done by pneumatic or positive displace when placement by pumping is anticipated
ment pump and pipeline methods, the plastic concrete is 8.6.4 Construction-The two basic methods of placing
forced under pressure into a void, such as the crown of a concrete in a tunnel arch entail problems in the construction
tunnel lining. For more information on the pumping process, of the fonnwork that require special provisions to pennit
refer to ACl 304.2R. proper reuse. These two basic methods arc commonly known
8.6.2 Design loads as the bulkhead method and the continuously advancing
8.6.2.1 Vertical loads-Vertical and construction loads slope method.
assumed in the design of formwork for underground struc The former is used exclusively where poor ground condi
tures arc similar to those for surface structures, with the tions exist, requiring the lining to be placed concurrently
exception of unusual vertical loads occurring near the crown with tunnel driving operations. It is also used when some
of arch or tunnel forms and flotation or buoyancy effect factor, such as the size of the tunnel, the introduction of rein
beneath tunnel forms. forcing steel, or the location of construction joints precludes
In placing concrete in the crowns of tunnel forms, pres the advancing slope method. The advancing slope method
sures up to 3000 lbltV ( 144 kPa) have been induced in areas a continuous method of placement-is usually preferred for
of overbreak and near vertical bulkheads from concrete tunnels driven through competent rock, ranging between 10
placed pneumatically or by positive displacement pump and 25 fl (3 and 8 m) in diameter and at least I mi (I .6 km)
(ACl SP-4). Overbreak is the excess removal of rock in length.
or other excavated material above the forms beyond the The arch form for the bulkhead method is usually fabri
required tunnel lining thickness. Until more definite recom cated into a single unit between 50 and ISO fl (I 5 and 45
mendations can be made. the magnitude and distribution of m) long, which is stripped, moved ahead, and re·crected
pressure should be determined by the formwork engineer. using screw jacks or hydraulic rams. These are permanently
The assumed pressure should not be less than 1500 lblft2 (72 attached to the form and supporting traveling gantry. The
kPa) acting normally to the form plus the dead weight of the arch form for the continuously advancing slope method
concrete placed pneumatically or by pump (ACI SP-4). usually consists of eight or more sections that range between
8.6.2.2 Lateral loads-For shafts and exterior walls 15 and 30 ft (5 and 9 m) in length. These are successively
against rock, the values listed in 4.2.2 should apply. stripped or collapsed, telescoped through the other sections,
When the shaft form relies on the single shear value of and re-erected using a fonn traveler.
embedded anchors in the previous placement as a means Although the minimum stripping time for tunnel arch
of support, the minimum time lapse between successive forms is usually established on the basis of experience, it can
placements (or minimum concrete strength) and maximum be safely predetermined by tests. At the start of a tunnel arch
allowable loading in addition to the dead weight of the form concrete placement operation, the recommended minimum
should be specified. stripping time is 12 hours for exposed surfaces and 8 hours
For arch forms and portions of tunnel forms above the for construction joints. If the specifications provide for a
maximum horizontal dimension or spring line of the fonn, reduced minimum stripping time based on site experience,
such reductions should be in time increments of 30 minutes
APPENDIX£
GUIDE TO FORMWORK FOR CONCRETE (AC1347R-14)
or less and should be established by laboratory tests, visual fonn. Injection pipes spaced 5 to 6 ft (1.5 to 1.8 m) apart,
inspection, and surface scratching of sample areas exposed penetrating the face of the form, require that the fonn be
by opening the fonn access covers. Arch fonns should not be checked for structural integrity as well as a means of plug
stripped prematurely when unvented groundwater seepage ging or shutting off the openings when the injection pipes
could become trapped between the rock surface and the are removed. Some of these problems are reduced where
concrete lining. mortar can be injected vertically in open top fonns.
8.6.5 Materials-The choice of materials for underground Fonns, ties, and bracing should be designed for the sum of:
fonnwork is typically predicated on the shape, degree of a) The lateral pressure of the coarse aggregate as deter
reuse and mobility of the fonn, and the magnitude of pump mined from the equivalent fluid lateral pressure of the dry
or pneumatic pressures to which it is subjected. Usually, aggregate using the Rankine or Coulomb theories for gran
tunnel and shaft fonns are made of steel or a composite of ular materials, or a reliable bin action theory (refer to theo
wood and steel. Experience is important in the design and ries and references presented in ACI 313)
fabrication of a satisfaciOry tunnel fonn due to the nature of b) The lateral and uplift pressure of the injected monar,
the pressures developed by the concrete, placing techniques, as an equivalent fluid; the mortar nonnally weighs 130 lb/f"tl
and the high degree of mobility required. (21 kN/m3), but can weigh as much as 200 lb/ft3 (32 kN/m1)
When reuse is not a factor, plywood and tongue-and for high-density mortars
groove lumber are sometimes used for exposed surface The time required for the initial set of the fluidized mortar
finishes. High humidity in underground construction usually and the rate of rise should be ascertained. The maximum
alleviates nonnal shrinkage and warping of wood fonn height of fluid to be assumed in detennining the lateral pres
materials. sure of the mortar is the product of the rate of rise (fVh [m/h])
and the time of initial set in hours. The lateral pressure for
CHAPTER �SPECIAL METHODS OF the design of fonnwork at any point is the sum of the pres
CONSTRUCTION sures detennined from Steps (a) and (b) for the given height.
9.1.3 Constnlclion-ln addition to the information
9.1-Preplaced-aggregate concrete presented in Chapter 5, the fonns should be mortar-tight and
9.1.1 Discussion-Preplaced-aggrcgate concrete is made effectively vented because preplaced-aggregate concrete
by injecting (intruding) mortar into the voids of a preplaced entails forcing mortar into the voids around the coarse
mass of clean, graded aggregate. For nonnal construction, aggregate.
the preplaced aggregates are vibrated thoroughly into fonns 9.1.4 Materials for formwork-For unexposed surfaces,
and around reinforcing and then wetted and kept wet until mortar-tight forms of steel or plywood arc acceptable.
the injection of mortar into the voids is completed. In under Absorptive fonn linings are not recommended because
water construction, the mortar displaces the water and fills they permit the coarse aggregate to indent the lining and
the voids. In both types of construction, this process can fonn an irregular surface. Fonn linings, such as hardboard
create concrete with a high content of coarse aggregate. on common sheathing, arc not successful because they do
The injected mortar contains water, fine sand, portland not transmit the external fonn vibration nonnally used for
cement, pozzolan, and a chemical admixture designed to ensuring a void-free finished surface. Fonnwork should be
increase the penetration and pumpability of the mortar. The designed for the effects of external vibration.
structural coarse aggregate is similar to coarse aggregate for
conventional concrete. It is well washed and graded from 112 9.2-Siipforms
in. (13 mm) to the largest size practicable. After compaction 9.2.1 Discussion-Refer to ACI 313 for silo construc
in the fonns, it usually has a void content ranging from 35 to tion. Slipfonning is a quasi-continuous fanning process in
45 percent (ACI 304.1 R). which a special form assembly slips or moves in the appro
9.1.2 Design considerations-Due to the method of place priate direction, leaving the fanned concrete in place. The
ment, the lateral pressures on fonnwork are considerably process is, in some ways, similar to an extrusion process.
different from those developed for conventional concrete, Plastic concrete is placed in the forms, and the fonns can be
as described in 4.2.2. The fonnwork engineer/contractor thought of as moving dies to shape the concrete. The rate of
should be alerted to the unique problems that may occur in movement of the fonns is regulated so the fonns leave the
preplaced aggregate placements. In mass placements, heat concrete only after it is stiff enough to retain its shape while
of hydration and drying shrinkage are important consider supporting its own weight and the lateral forces caused by
ations. Differential pressures may occur in the fonn structure wind and equipment.
when mortar injection varies greatly from one fonn face to The vertical or horizontal movement of fonns can be a
another. For additional infonnation, refer toACI 207.1R and continuous process or a planned sequence of finite place
ACI SP-34. Because of the pressure created during aggregate ments. Slipfonns used on structures such as tunnels and
packing and mortar pumping, fonns that mortar is injected shafts should follow 8.6. Slipfonns used on mass concrete
through should be anchored and braced far more securely structures, such as dams, should follow 8.5.
than for ordinary concrete. Particular attention should be 9.2.2 Vertical slipforms
paid to uplift pressures created in battered fonns. Provisions 9.2.2. I Slipfonns can be used for vertical structures, such
should be made to prohibit even the slightest uplift of the as silos, storage bins, building cores, bearing wall build-
ACJ 347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
APPENDIXE
GUIDE TO FORMWORK FOR CONCRETE (ACJ 347R·14)
lish safe lifting rates. Forms should be leveled before they 9.3.2 Design considerations-If the stay-in-place form is
are filled and should be maintained level unless otherwise not covered in the contract specifications because it has no
required for out-of-tolerance corrections. Care should be function in the finished structure, the form manufacturer's
taken to prevent drifting of the forms from alignment or specifications should be used; the manufacturer's recom
designed dimensions and to prevent torsional movement. mended practice should be followed for size, span, fasten
Experience has shown that a plumb line, optical plummet, ings, and other special features pertinent to this type of form,
laser, or combination of these used in conjunction with a water such as being water-repellent and protected against chem
level system is effective in maintaining the form on line and ical attack from wet concrete (refer to Chapters 4 and 5).
grade and for positioning openings and embedded items. Particular care should be taken in the design of such forms
The alignment and plumbness of a structure should prefer by the formwork engineer/contractor to minimize distortion
ably be checked every 2 hours but at a minimum once during or deformation of the form or supporting members under the
every 4 hours that the slide is in operation. In work that is construction toads.
done in separate intermittent slipping operations, a check of The engineer/architect who specifies the use of permanent
alignment and plumbness should be made at the beginning rigid forms should consider in the struciUral analysis both
of each slipping operation. the construction dead and live loads on the form as well
More frequent readings should be taken on single tall as the structure's stability during construction, in addition
structures with relatively small plan sections, as the form to consideration of the form's performance in the finished
system in these structures tends to twist and go out of plumb structure.
more readily. When metal deck is used as a permanent fonn and the
Sufficient checks of plumbness should be provided to deck will become an integral part of the structure, the deck's
readily detect and evaluate movements of the form for all shape, depth, gauge, coating, physical dimensions, proper
slipformed structures so that appropriate adjustment can be ties, and intermediate temporary support should be as called
made in sufficient time by experienced personnel. for in contract documents. If structural continuity is assumed
Detailed records of both vertical and lateral form move in the design of the form, the engineer of the permanent
ments should be maintained throughout the slipform structure should specifY the required number of permanent
operation. supports over which the form material should be continuous.
9.2.3 Horizontal slipforms-Horizontal slipforming When composite metal deck requires shoring to minimize
lends itself to concrete structures such as tunnel linings, its deflection due to the concrete placement, the camber of
water conduits, drainage channels, precast elements, the members supporting the completed composite slab and
canal linings, highway median barriers, pavements, curbs, deck should be considered. If the supporting members are
shoulder barriers, and retaining walls. Horizontal stipforms cambered for the dead load of the concrete, and that toad is
generally move on a rail system, tractor treads, wheels, and prevented from being applied to the supporting members due
other similar means resting on a shaped berm. Working and to the presence of the shoring, there may be excess camber
storage decks and finisher's scaffolding are attached to and left in the supporting members. The engineer/architect who
carried by the moving formwork. designed the structure should consider this effect and adjust
The general provisions of 4.1.4 should be met and the the camber appropriately.
formwork engineer/contractor should submit drawings of 9.3.3 Installation
the slipform for review and approval by the engineer/archi 9.3.3.1 Shop drawings-The formwork engineer/
tect. These drawings should show the handling diagrams, the contractor should submit fully detailed shop drawings for all
placing procedure, and the provisions for ensuring attain permanent deck forms to the engineer/architect for review,
ment of the required concrete surfaces. approval, or both, as applicable to the project. Shop drawings
should show all form thicknesses, metal gauges, physical
9.3-Permanent forms dimensions and properties, accessories, finishes, methods of
9.3.1 Discussion-Permanent forms, or stay-in-place attachment to the various classes of the work, and temporary
forms, are forms left in place that may or may not become shoring requirements.
an integral part of the structural frame. These fonns can be 9.3.3.2 Fastenings-The permanent deck form should be
rigid-such as metal deck, precast concrete, wood, plastics, properly fastened to supporting members and to adjacent
and various types of fiberboard--or the flexible type-such sections of deck form and properly lapped, in accordance
as reinforced, water-repellent, corrugated paper, or wire with manufacturers' recommendations, to provide a tight
mesh with waterproof paper backing. joint that will prevent loss of mortar during the placement
When the permanent form is used as a deck form, it is of concrete. Where required, end closures for corrugated or
supported from the main structural frame with or without fluted forms should be provided, together with fill pieces
an intermediate system of temporary supports. lf temporary where a tight fit is required. To prevent buckling, allow for
supports are required under, or to provide structural stability expansion of metal deck forms after fastening and before
for, the structural frame members to support the weight of concrete placement.
the fresh concrete without causing excessive deflection or Flexible types of fonns (those that depend on supporting
member instability, such information should be specified by members for lateral stiffness) should be tightly joined for
the engineer/architect. proper installation. Adequate temporary bracing or anchors
ACI347R·14
GUIDE TO FORMWORK FOR CONCRETE (ACI 347R-14)
should be provided in the plane of the top chord of the dead load of the member remains on the formwork during
supporting members to prevent lateral buckling and rotation prestressing, displacement of the dead load toward end
of these supports and to maintain the required tension in the supports should be considered in design of the forms and
flexible fonn shoring, including sills or other foundation support.
Paper or metal fonns used to form voids in concrete 9.4.3 Construction accessories-Hold-down or push
construction should be properly placed and anchored to the down devices fOr deflected cables or strands should be
reinforcement and to side or deck forms with wire ties or provided in the casting bed or forms. All openings, offsets,
other approved methods to prevent displacement or flota brackets, and all other items required in the concrete work
tion during placing of concrete. Water should be prevented should be provided for in the formwork. Bearing plates,
from entering voids. Where water intrusion is possible, weep anchorage assemblies, prestressing steel, conduits, tube
holes should be provided to reduce entrapment of water. enclosures, and lifting devices shown or specified to be set
9.3.4 Deflections-The vertical and lateral deflections of in concrete should be accurately located with formwork
the permanent fonn between supports under the load of fresh templates and anchored to remain within the tolerances
concrete should be investigated by the engineer/architect. given on contract documents. Quality and strength of these
Temporary supports, such as shoring and stringers, should accessories should be as specified.
be specified, if necessary, to keep deflection within desired 9.4.4 Tolerances-Prescribed ranges of tolerances for
tolerances. job-site precast and plant-manufactured precast-prestressed
concrete members are given in ACI 117 and PC! MNL
9.4-Forms for prestressed concrete construction 135-00.
9.4.1 Discussion-The engineer/architect should indi 9.4.5 Curing-Where necessary to allow early reuse of
cate in the contract documents any special requirements for forms, provisions should be made to use accelerated curing
prestressed concrete construction. processes such as steam curing, vacuum processing, or other
It may be necessary to provide appropriate means of approved methods.
lowering or removing the formwork before full prestress is 9.4.6 Worker safety-Safety shields should be provided
applied to prevent damage. Pretensioning or post-tensioning at end anchorages of prestressing beds or where necessary
of strands, cables, or rods can be done with or without side for the protection of workers or equipment against possible
forms of the member in place, as discussed in 9.4.2. Bottom breakage of prestressing strands, cables, or other assemblies
forms and supporting shores or falsework should remain in during prestressing or casting operations.
place until the member is capable of supporting its dead load
and anticipated construction loads, as well as any fonnwork 9.5--Forms for site precasting
carried by the member. 9.5. I Discussion-Forms for site precasting are used for
The concrete placement sequence for certain structures precast concrete items that can be either load- or non-load·
should also be planned so that concrete is not subjected to bearing members for structural or architectural uses.
bending stress caused by deflection of the formwork. 9.5.2 Construction-Exterior braces only should be used
9.4.2 Design when exposed metal or filled-in pockets resulting from the
9.4.2.1 Where the side forms cannot be conveniently use of metal ties would present an objectionable appearance.
removed from the bottom or soffit form after concrete has To ensure uniformity of appearance in the cast members
set, such forms should be designed with slip joints or with or units, particularly in adjacent units where differences
added panel and connection strength for additional axial or in texture, color, or both, would be visible, care should be
bending loads that can be superimposed on them during the taken that the contact surfaces of forms or form liners are of
prestressing operation. unifonn quality and texture.
9.4.2.2 Side forms that remain in place during the transfer Form oil (nonstaining, if required) should be applied
of preS!Tessing force should be designed to allow for vertical uniformly and in accordance with manufacturers' recom
and horizontal movements of the cast member during the mendations for this particular class of work.
prestressing operation. The form should be designed to mini 9.5.3 Accessories-It is particularly important in this class
mize the restraint to elastic shortening in the prestressing of work that positive and rigid devices be used to ensure
operation. For example, small fanning components should proper location of reinforcement. All openings, cutouts,
be planned for removal to relieve load on side forms as offsets, inserts, lift rings, and connection devices required to
well as to eliminate their restraint during prestressing. In be set in concrete should be accurately located and securely
all cases, the restraint to shrinkage of concrete should be anchored in the formwork.
kept to a minimum, and the deflections of members due to The finished surfaces of members should be free of lift
prestressing force and the elastic deformation of forms or rings and other erection items where it will be exposed,
falsework should be considered in the design and removal interfere with the proper placing of precast members or other
of the forms. materials, or be subject to corrosion. Such items should
9.4.2.3 For reasons of safety, when using post-tensioned, be removed so that no remaining metal will be subject to
cast-in-place elevated slabs, the contractor should be careful corrosiOn.
to ensure that supporting shores do not fall out due to lifting The quality and strength of these accessories should be as
of the slab during tensioning. For large structures where the required by the contract documents, but the lifting devices or
APPEND/XE
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
other accessories not called for in the contract documents are Lifting hooks in a form unit can be designed to serve also as
the responsibility of the contractor. anchors or shear connectors.
9.5.4 Tolerances-Prescribed tolerances for precast 9.6.2.4 Code requirements-Precast concrete forms used
concrete construction arc listed in ACl 117. in composite design with cast-in-place concrete in buildings
9.5.5 Removal of forms-Precast members or units should should be designed in accordance with ACI 318.
be removed from forms only after the concrete has reached 9.6.3 During and after concrete placement
a specified strength, as determined by the field-cured test 9.6.3.1 Yibration-Thorough consolidation of site-cast
cylinders or beams and job history of concrete curing. concrete is required to prevent voids that would interrupt the
Where required to allow early reuse of forms, provi bond of the form to structure concrete, but sufficient care
sions can be made to use accelerated curing processes such should be used to prevent damage of concrete panels by
as steam curing or other approved methods. Methods of contact with vibrators.
lifting precast units from forms should be approved by the 9.6.3.2 Protection of architectural finish--Care should be
engineer/architect. taken to avoid spilling fresh concrete on exposed surfaces,
and any spilled or leaked concrete should be thoroughly
9.6--Use of precast concrete for forms removed before it has hardened. After concrete placement,
9.6.1 Discussion-Precast concrete panels or molds have protection of precast architectural concrete form facings
been used as forms for cast-in-place and precast concrete, may need to be considered.
either as permanent forms, integrated forms, or as remov
able, reusable forms. They have been used for both struc 9.7-Forms for concrete placed under water
tural and architectural concrete, designed as structurally 9.7.1 Discussion-There are two basic approaches to the
composite with the cast-in-place material or to provide a problem of placing concrete under water: the concrete can
desired quality of outer surface and, in some cases, to serve be mixed in the conventional manner and then placed by
both of these purposes. Concrete form units can be plain, special methods, or the preplaced aggregate method can be
reinforced, or prestressed, and either cast in the factory or used.
at the job site. The most common use of precast concrete In the first approach, placement can be made by either
form units has been for elevated slabs acting compositely pump, underwater bucket, or tremie. The tremie is a steel
with topping concrete, as in bridge and commercial or insti pipe suspended vertically in the water with a hopper attached
tutional construction. Precast units are also common as to the upper end above the water surface. The lower end of
ground-holding systems in tunneling and as stay-in-place the pipe, with an ejectable plug, extends to the bottom of
forms for rehabilitation of navigation lock walls. Match the area where concrete is to be placed. This pipe is charged
casting is a process where a previously cast element is used with concrete from the surface. Once the pipe is filled
as the bulkhead for the casting of a subsequent element to with concrete, it is kept full and its bottom should be kept
assure tight fit. Match casting is often used in the process of immersed in the fresh concrete.
casting units for segmental bridge construction In the second approach, the forms are filled with coarse
9.6.2 Design aggregate, which is then grouted so that the voids around the
9.6.2.1 Responsibility for design-Where the integrated aggregate are filled, as discussed in 9.1. The grout is intro
form is to act compositely with the structure concrete, the duced at the bottom and the water is displaced upward as the
form panel should be designed by the engineer/architect, grout rises.
who should also indicate what additional external support 9.7.2 Underwater bucker and rremie
is required for the permanent forms. For permanent forms 9.7.2.1 Design-Forms for underwater concrete place
intended to achieve a desired architectural effect, the ment are designed with the same considerations as
engineer/architect can specifY surface finish and desired other forms covered in 4.2, except that the density of the
minimum thickness of architec!Ural material. Design and submerged concrete can be reduced by the weight of the
layout of temporary forms and supporting systems should water displaced. Because of large local pressures that can
normally be the responsibility of the formwork engineer/ develop due to the head of concrete in the trcmic, the loca
contractor. tion of the tremie and possible resulting loads on the form
9.6.2.2 Connections--C onnection details should be should be evaluated by experienced personnel. Ignoring the
planned to overcome problems of mating precast members effects of submergence will result in a practical conservative
to each other and to the existing or cast-in-place structure. design that is sturdy enough to withstand the extra rigors of
9.6.2.3 Bonding concrete form to concrete srmcrure underwater conditions.
EfTective bond between precast form unit and the concrete In tidal zones, forms should be designed for the lowest
structure is essential and can be achieved by: I) special possible water level. Changes in construction schedules
treatment, such as grooving or roughening the form face can transform a planned submerged placement to one made
in contact with the structure concrete; 2) use of anchoring above water, thus losing the offsetting water pressure.
devices extending across the interface between form panel 9.7.2.2 Consrmcrion-Underwater forms should be built
and structure concrete; 3) a combination of Items I and on the surface in large units because final positioning and
2; and 4) use of paint-on or spray-on bonding chemicals. fitting when done under water by divers is slow and costly.
For this reason, foundations should be kept simple in shape,
AC1347R·14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
and forms should be free of complex bracing and connec ACI 309.2R-98-Identification and Control of Visible
tion details. Through-ties, which could interfere with the Effects of Consolidation on Fonned Concrete Surfaces
concrete placing, should be avoided. Forces imposed on (Reapproved 2005)
preassembled fonns during lifting should be considered in ACI 311.4R-05-Guide for Concrete Inspection
the fonn design. ACI 313-97-Standard Practice for Design and
Fonns should be carefully fitted and secured to adjacent Construction of Concrete Silos and Stacking Tubes for
materials or construction to avoid Joss of mortar under pres Storing Granular Materials
sure developed. If there is any water current flow past the ACI 318-11-Building Code Requirements for Structural
fonn. small openings in the fonn should be avoided, as they Concrete and Commentary
will pennit washing or scouring of the fresh concrete. ACI 332.1R-06-Guide to Residential Concrete
When it is intended to pennit concrete to overflow the Construction
fonn and screed it off to grade, it is essential that the fonn ACI 334.1R-92--Concrctc Shell Structures Practice and
is positioned to the proper grade and is detailed so that the Commentary (Reapproved 2002)
overflow will not interfere with the proposed method and ACI 372R-03-Design and Construction of Circular Wire
devices for stripping. and Strand Wrapped Prestressed Concrete Structures
Fonns should be well detailed, and such details should be ACI 373R-97-Design and Construction of Circular
scrupulously followed so that divers employed to remove the Prestressed Concrete Structures with Circumferential Tendons
fonn can visualize and plan their work before descending. ACI 347.2R-05-Guide for Shoring!Reshoring of
Multi-use fonns can have special devices for positioning Concrete Multistory Buildings
fonns from above water and special stripping devices, such as ACI 347.3R-13-Guide for Fonned Concrete Surfaces
hydraulic jacks, that pennit releasing the fonn from the surface. ACI SP-2(07)--Manual of Concrete Inspection
9.7.3 Prep/aced aggregate ACI SP-4-Fonnwork for Concrete, seventh edition
9.7.3.1 Design-The fonnwork should be designed with ACI SP-34-Concrete for Nuclear Reactors
the same considerations as mentioned previously in 9.1.2.
9.7.3.2 Constmction-lt is important to ensure that silt is American lnsli/Uie ofS!eel Cm/Sinlclion
excluded from the fonns because silt chokes the voids in the AISC 325-11-Steel Construction Manual
aggregate and interferes with the flow of grout. Silt, if left
adhering to the aggregate, can reduce the bond between the American Iron and Sleellnstitute
aggregate and the grout. AlSI DI00-08--Cold-Fonned Steel Design Manual
The inspection of the fonns before concrete placement
should verify that the perimeters of the fonns arc effectively American Na1ional Swndards Jnslitute
sealed against the leakage of grout or the intrusion of silt or ANSI A48.1-1986-Fonns for One-Way Concrete Joist
other fines Construction
ANSI A48.2-1986-Fonns for Two-Way Concrete Joist
CHAPTER 1D-REFERENCES Construction
Committee documents are listed first by document number ANSI A208.1-2009-Particleboard
and year of publication followed by authored documents
listed alphabetically. American Society of Civil Engineers
ASCE/SEI 7-10-Minimum Design Loads for Buildings
American Concrete Institute and Other Structures
ACI 117-10-Specification for Tolerances for Concrete ASCE/SEI 37-02-Design Loads on Structures during
Construction and Materials and Commentary Construction
ACI 207.IR-05-Guide to Mass Concrete (Reapproved
2012) American Wood Council
ACI 224R-0 !-Control ofCracking in Concrete Structures ANSIIAWC NDS-2012-National Design Specification
(Reapproved 2008) for Wood Construction
ACI 228.1R-03-ln-Place Methods to Estimate Concrete
Strength APA-The Engineered Wood Associalion
ACI 237R-07-Self-Consolidating Concrete APA 0510-2012-Panel Design Specification
ACI 301-10--Specificalions for Structural Concrete APA V345-2012-Design/Construction Guide: Concrete
ACI 303R-12-Guide to Cast-in-Place Architectural Fonning
Concrete Practice APA YSl0-1998-Piywood Design Specification
ACI 304.1R-92-Guide for Use of Preplaced-Aggregate
Concrete for Structural and Mass Concrete Applications ASTM lmemalional
ACI 304.2R-96-Placing Concrete by Pumping Methods ASTM A446-76(1981)-Standard Specification for Steel
(Reapproved 2008) Sheet, Zinc-Coated (Galvanized) by the Hot-Dip Process,
ACI 305R-10--Guide to Hot Weather Concreting Structural (Physical) Quality
ACI 306R-l 0--Guide to Cold Weather Concreting
APPENDIXE
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
ASTM CJ61J/Cl 61JM-09-Standard Test Method for Clear, C. A., and Harrison, T. A., 1985, "Concrete Pres
Slump Flow of Self-Consolidating Concrete sure on Fonnwork," C/RIA RepOI't No. 108, Construction
Industry Research and lnfonnation Association, London,
Canadian Standards Association UK, 32 pp.
CSA-086M-84-Engineering Design in Wood CRSI, 2009, Manual of Standard Practice, 28th edition,
Concrete Reinforcing St1..-ellnstitutc,Schaumburg, IL,144 pp.
Dewsches lnstitutfiir Normung "DIN Standard on Fonnwork Pressures Updated," 2010,
DIN 18218:2010-01-Frischbetondruck auf Lotrcchtc Concrete International, V. 32, No. 6,June, pp. 27-29.
Schalungen (Pressure of Fresh Concrete on Vertical Dunston, P. S.;Johnston, D. W.; and McCain, P. P., 1994,
Fonnwork) "Fonnwork Pressures in Tall Walls with Extended Set
Concrete," Concrete lntemationol, V. 16, No. II, Nov., pp.
Precast/Prestre.�sed Concrete lnstitllle 26-34.
MNL 135-00--Tolcrance Manual for Precast and Gardner, N. J., 1980, "Pressure of Concrete against Fomt·
Prestressed Concrete Construction work," AC/ Journal Proceedings, V. 77, No. 4,July-Aug.,
pp. 279-286.
Scaffolding. Shoring. and Forming Institute Gardner, N.J.,1981,"discussion on "Pressure of Concrete
SH 301-03-Horizontal Shoring Beam Safety Rules Against Fonnwork,"," ACI Journal Proceedings. V. 78, No.
SH 304-00--Rccommended Frame Shoring Erection 3, May-June, pp. 243-246.
Procedure Gardner, N. J., 1985, "Pressure of Concrete on Fonn
work-A Review," AC/ Journal Proceedings, V. 82, No. 5,
U.S. Department of Commerce. National Institute of July-Aug., pp. 744-753.
Standards and Technology Gardner, N. J., and Ho, P. T.-1., 1979, "Lateral Pressure
PSI-09-Construction and Industrial Plywood of Fresh Concrete," ACI Journal Proceedings, V. 76, No. 7.
PS20-10--Perfonnance Standard for Wood-Based July, pp. 809-820.
Structural-Use Panels Gardner. N.J.;Keller, L; Quattrociocchi,R.;and Charitou,
G., 2012. "Field Investigation of Fonnwork Pressures using
U.S. Departme/11 of Lobar. Occupational Safety and Self Consolidating Concrete:· Concrete lmemational. V. 34.
Health Administration No. I,Jan., pp. 41-47.
OSHA 1926-07-Safety and Health Regulations for Grundy,P.,and Kabaila,A., 1963,"Construction Loads on
Construction Slabs with Shored Fonnwork in Multistory Buildings," ACI
Journal Proceedings, V. 60, No. 12, Dec., pp. 1729-1738.
Authored references Hurd, M. K., 1993, "Nonmeta11ic Fonn Ties," Concrete
ACI Committee 622, 1957, "Form Construction Prac Constmction, V. 38, No. 10, pp. 695-699.
tices," ACI Journal Proceedings, V. 53, No. 12, June, pp. Hurd, M. K., 1994, "Plastic Fonn Liners," Concrete
1\05-1118. Construction, V. 39, No. II, Nov., pp. 847-853.
ACI Committee 622, 1958, "Pressures on Formwork," Hurd, M. K., 1996, ''Choosing and Using a Fonn Release
ACI Journal Proceedings, V. 55, No. 2,Aug., pp. 173-190. Agent," Concrete Construction, V. 41, No. 10, pp. 732-736.
Agarwal,R. K.,and Gardner, N.J.,1974,"Fonn and Shore Hurd, M. K., 1997a, ''Using Glass-Fiber-Reinforced
Requirements for Multistory Flat Slab Type Buildings," ACI Plastic Fonns," Concrete Construction, V. 42, No. 9, pp.
Journal Proceedings, V. 71, No. II. Nov., pp. 559-569. 689-692.
American Institute of Timber Construction, 2012, Timber Hurd, M. K., 1997b, "Expand Your Fonning Options,"
Construction Manual, sixth edition, John Wiley & Sons, Concrete Construction, V. 42, No. 9, Sept, pp. 725-728.
New York, 648 pp. Johnston, D. W., 2010, ''Field Measurement of Concrete
American Wood Council, 2012, Wood Frame Construc Lateral Pressure in Fonnwork," Proceedings of the ASCE-C/
tion Manual, Leesburg, VA. Construction Research Congress. pp. 1335-1344.
Barnes,J. M., and Johnston, D. W., 1999, "Modification Johnston, D. W.; Kahn, K. P.; and Phillips, J. B., 1989,
Factors for Improved Prediction of Fresh Concrete Lateral "Fonnwork Pressures in Tall and Thick Concrete Walls,"
Pressures on Fonnwork," Institute of Construction, Depart Journal of Constmction Engineering and Manage
ment of Civil Engineering, North Carolina State University, ment, V. 115, No. 3, Sept., pp. 444-461. doi: 10.1061/
Raleigh, NC, Oct., 90 pp. (ASCE)0733-9364(1989)115>3(444)
Barnes,J. M., and Johnston, D. W., 2003, "Fresh Concrete Khayat, K. H., and Omran,A. F.,2011, "Field Verification
Lateral Pressure on Fonnwork," Proceedings ofthe ASCE-CI of Fonnwork Pressure Prediction Models," Concrete /Iller
Constmction Research Congress, 8 pp. national, V. 33, No. 6,June, pp. 33-39.
British Cement Association, 1992, "Hi-Rib Permanent Lange, D. A.; Birch, B.; Henschen,J.; Liu, Y.-S.; Tejeda
Fonnwork Trials," Report and Appendix REL031.01.1 Dominquez, F.; and Struble, L. J., 2008, "Modeling Fonn
BCA, Slough, UK, Feb., 22 pp., and July, 9 pp. work Pressure of SCC," Proceedings of the Jrd North Amer
Bryer, D.; Fridley Jr., K.; and Pollock, K. C., 2006, Design ican Conference on De�·ign and Use of Self Consolidaring
of Wood Structures, sixth edition, McGraw-Hill, 1025 pp. Concrete (SCC2008), 6 pp.
ACI347R-14
GUIDE TO FORMWORK FOR CONCRETE (ACI347R-14)
Noble, J., 1975, "Stop Guessing at Reshore Loads Stivaros, P. C., and Halvorsen, G. T., 1990, "Shoring/
Measure Them," Concrete Construction, V. 20, No. 7, pp. Reshoring Operations for Multistory Buildings," AC! Struc
277-280. tura/Journal, V. 87, No. 5, Sept.-Oct., pp. 589-596.
Proske, T., and Graubner, C.-A., 2008, "Fonnwork Pres The Aluminum Association, 2010, Aluminum De�;ign
sure Using Self-Compacting Concrete," Technische Univer Manual, Arlington, VA.
sitat Dannstadt, lnstitut fur Massivbau, 25 pp. U.S. Department of Agriculture, 20\0, Wood Handbook:
Randall Jr., F. A., and Courtois, P. D., 1976, "Side Fonn Wood as an Engineering Material, General Technical Report
Spacers," ACI Journal Proceedings, V. 73, No. 2, Feb., pp. FPL-GTR-190, Forest Products Laboratory, Madison, WI,
116-120. 508 pp. www.fpl.fs.fed.us/documnts/fplgtr/fpl_gtrl90.pdf
Smulski, S., ed., 1997, Engineered Wood Products: A Zivcrts, G. J., 1964, "A Study of Cardboard Voids for
Guide for Specifiers, Designers. and Users, PFS Research Prestressed Concrete Box Slabs," PC! Journal, V. 9, No. 3,
Foundation, Madison, WI, 330 pp. pp. 66-93, and V. 9, No. 4, pp. 33-68.
Steel Joist Institute, 2010, "Standard Specifications and
Load and Weight Tables for Steel Joists and Joist Girders,"
43rd edition, Florence, SC, 77 pp.
APPENDIX£
APPENDIX F-ACI318-11 CODE AND COMMENTARY
CODE COMMENTARY
6.1- Design of formwork R6.1 -Design of form work
6.1.1 - Forms shaH result in a final structure that Only minimum performance requirements for formwork.
conforms to shapes, lines, and dimensions of the necessary to provide for public health and safety, are
1 members as required by the contract documents. prescribed in Chapter 6. Formwork for concrete, including
proper design, construction, and removal, demands sound
6.1.2 - Forms shall be substantial and sufficiently judgment and planning to achieve adequate forms that are
tight to prevent leakage of mortar. both economical and safe. Detailed information on form
work for concrete is given in: "Guide to Formwork for
6.1.3 - Forms shall be properly braced or tied Concrtte," reported by Committee 347.6·1 (This provides
together to maintain position and shape. recommendations for design, construction, and materials for
formwork, forms for special structures. and formwork for
6.1.4- Forms and their supports shall be designed special methods of construction. Directed primarily to
so as not to damage previously placed structure. contractors, the suggested criteria will aid in preparing
project specifications for the contractors.)
6.1.5 - Design of formwork shall include consider·
ation of the following factors: Fonnworkfor Co11crete.6·2 reported by ACI Committee 347.
(This is a how-to-do-it handbook for contractors, engineers,
(a) Rate and method of placing concrete; and architects following the guidelines established in ACI
347. Planning. building, and using formwork are discussed,
(b) Construction loads, including vertical, horizontal, including tables, diagrams. and formulas for form design
and impact loads; loads.)
6.2 - Removal of forms, shores, and R6.2 - Removal of forms, shores, and
reshoring reshoring
6.2.1 - Removal of forms In determining the time for removal of forms, consideration
should be given to the construction loads and to the possibilities
63
Forms shall be removed in such a manner as not to of deflections. · The construction loads are frequently at
impair safety and serviceability of the structure. least as great as the specified live loads. At early ages, a
Concrete exposed by form removal shall have sufficient structure may be adequate to support the applied loads but
strength not to be damaged by removal operation. may deflect sufficiently to cause permanent damage.
6.2.2- Removal of shores and reshoring Evaluation of concrete strength during construction may be
demonstrated by field-cured test cylinders or other procedures
The provisions of 6.2.2.1 through 6.2.2.3 shall apply to approved by the building official such as:
slabs and beams except where cast on the ground.
(a) Tests of cast-in-place cylinders in accordance with
6.2.2.1 - Before starting construction, the ASTM C873.6·4 (This method is limited to use in slabs
contractor shall develop a procedure and schedule for where the depth of concrete is from 5 to 12 in.):
removal of shores and installation of reshores and for
(b) Penetration resistance in accordance with ASTM
calculating the loads transferred to the structure during
the process.
C8036·5:
STRUCTURAL CONCRETE BUILDING CODE (ACI318-11) AND COMMENTARY
CODE COMMENTARY
(a) The structural analysis and concrete strength (c) Pullout strength in accordance with ASTM C9006.6:
data used in planning and implementing form
(d) Maturity index measurements and correlation in
removal and shoring shall be furnished by the
accordance with ASTM C\074.6·7
contractor to the building official when so requested;
(b) No construction loads shall be supported on, nor Procedures (b), (c), and (d) require sufficient data, using job
materials, to demonstrate correlation of measurements on
any shoring removed from, any part of the structure
the structure with compressive strength of molded cylinders
under construction except when that portion of the
or drilled cores.
structure in combination with remaining forming and
shoring system has sufficient strength to support
Where the structure is adequately supponed on shores. the
safely its weight and loads placed thereon;
side forms of beams, girders, columns. walls, and similar
(c) Sufficient strength shall be demonstrated by venical forms may generally be removed after 12 hours of
structural analysis considering proposed loads, cumulative curing time, provided the side forms suppon no
strength of forming and shoring system, and loads other than the lateral pressure of the plastic concrete.
concrete strength data. Concrete strength data shall Cumulative curing time represents the sum of time intervals.
be based on tests of field-cured cylinders or, when not necessarily consecutive, during which the tempera!Ure
approved by the building official, on other procedures of the air surrounding the concrete is above SOOF. The 12-hour
to evaluate concrete strength. cumulative curing time is based on regular cements and
ordinary conditions: the use of special cements or unusual
6.2.2.2 - No construction loads exceeding the conditions may require adjustment of the given limits. For
combination of superimposed dead load plus specified example. concrete made with Type II or V (ASTM Cl50) or
live load shall be supported on any unshored portion ASTM C595 cements, concrete containing retarding
of the structure under construction, unless analysis admixtures. and concrete to which ice was added during
indicates adequate strength to support such additional mixing (to lower the temperature of fresh concrete) may not
loads. have sufficient strength in 12 hours and should be investigated
before removal of formwork.
6.2.2.3 - Form supports for prestressed concrete
members shall not be removed until sufficient The removal of formwork for multistory construction
prestressing has been applied to enable prestressed should be a pan of a planned procedure considering the
members to carry their dead load and anticipated temporary suppon of the entire structure as well as that of
construction loads. each individual member. Such a procedure should be
worked out prior to construction and should be based on a
structural analysis taking into account the following items,
as a minimum:
APPENDIXF
STRUCTURAL CONCRETE BUILDING CODE (ACI318-11) AND COMMENTARY
CODE COMMENTARY
6.3.1 - Embedments of any material not harmful to R6.3.1 - Any embedmems (e.g, conduits, pipes, and
concrete and within limitations of 6.3 shall be sleeves) not harmful to concrete can be placed in the
permitted in concrete with approval of the licensed concrete, but the Work should be done in such a manner that
design professional, provided they are not considered the structure will not be endangered. Empirical rules are
to replace structurally the displaced concrete, except given in 6.3 for safe installations under common conditions;
as provided in 6.3.6. for other than common conditions, special designs should
be made. Many general building codes have adopted ANSI/
ASME piping codes 8 31.1 for power piping6·8 and 8 31.3
for chemical and petroleum piping.6·9 The licensed design
professional should be sure that the appropriate piping
codes are used in the design and testing of the system. The
contractor should not be permitted to install conduits, pipes.
I ducts, or sleeve.s that are not shown in the contract documents
or not approved by the licensed design professional.
6.3.2 - Any aluminum embedments in structural R6.3.2 - The Code prohibits the use of aluminum in
concrete shall be coated or covered to prevent structural concrete unless it is effectively coated or covered.
aluminum-concrete reaction or electrolytic action Aluminum reacts with concrete and. in the presence of
between aluminum and steel. chloride ions, may also react electrolytically with steel.
causing cracking and/or spalling of the concrete. Aluminum
electrical conduits present a special problem since stray electric
current accelerates the adverse reaction. Provision 3.6.4
prohibits calcium chloride or any admixture containing
chloride from being used in concrete with aluminum
embedments.
CODE COMMENTARY
6.3.5.3 - They shall not impair significantly the
strength of the construction.
6.3.7 -Pipes and fittings shall be designed to resist R6.3.7- The 1983 Code limited the maximum pressure in
effects of the material, pressure, and temperature to embedded pipe to 200 psi, which was considered too
which they will be subjected. restrictive. Nevenheless, the effects of such pressures and
the expansion of embedded pipe should be considered in the
design of the concrete member.
6.4.1 - Surface of concrete construction joints shall For the integrity of the structure, it is imponant that all
be cleaned and laitance removed. construction j oints be defined in construction documents
and constructed as required. Any deviations should be
.
approved by the licensed design professional.
APPENDIXF
STRUCTURAL CONCRETE BUILDING CODE (ACI318·11) AND COMMENTARY
CODE COMMENTARY
6.4.2 - Immediately before new concrete is placed, R6.4.2- The requirements of the 1977 Code for the use of
all construction joints shall be wetted and standing neat cement on vertical joints have been removed, since it is
water removed. rarely practical and can be detrimental where deep forms
and steel congestion prevent proper access. Often wet
blasting and other procedures are more appropriate.
Because the Code sets only minimum standards, the
licensed design professional may have to specify additional
procedures if conditions warrant. The degree to which
mortar batches are needed at the start of concrete placement
depend on concrete proportions, congestion of steel,
vibrator access. and other factors.
6.4.3 - Construction joints shall be so made and R6.4.3- Construction joints should be located where they
located as not to impair the strength of the structure. will cause the least weakness in the structure. When shear
Provision shall be made for transfer of shear and other due to gravity load is not significant, as is usually the case in
forces through construction joints. See 11.6.9. the middle of the span of flexural members, a simple
vertical joint may be adequate. Lateral force design may
require special design treatment of construction joints.
Shear keys, intermittent shear keys, diagonal dowels. or the
shear transfer method of 11.6 may be used whenever a force
transfer is required.
6.4.6 - Beams, girders, or slabs supported by R6.4.6- Delay in placing concrete in members supported
columns or walls shall not be cast or erected until by columns and walls is necessary to prevent cracking at the
concrete in the vertical support members is no longer interface of the slab and supporting member caused by
plastic. bleeding and settlement of plastic concrete in the supporting
member.
6.4.7- Beams, girders, haunches, drop panels, shear R6.4. 7 - Separate placement of slabs and beams,
caps, and capitals shall be placed monolithically as haunches, and similar elements is pennitted when shown on
part of a slab system, unless otherwise shown in I the contract documents and where provision has been made
1 contract documents. to transfer forces as required in 6.4.3.
As ACI begins its second century of advancing concrete knowledge, its original chartered purpose
remains "to provide a comradeship in finding the best ways to do concrete work of all kinds and in
spreading knowledge." In keeping with this purpose, ACJ supports the following activities:
Technical committees that produce consensus reports, guides, specifications, and codes.
· Periodicals: the ACI Structural Journal, Materials Journal, and Concrete International.
Benefits of membership include a subscription to Concrete International and to an ACI Journal. ACI
members receive discounts of up to 40% on all ACI products and services, including documents, seminars
and convention registration fees.
As a member of ACI, you join thousands of practitioners and professionals worldwide who share
a commitment to maimain the highest industry standards for concrete technology, construction,
and practices. In addition, ACI chapters provide opportunities for interaction of professionals and
practitioners at a local level.
Safety regulations related to formwork and shoring are found on Subpart Q of the Federal
OSHA Construction Industry Regulations {Title 29 CFR 1926). The Subpart Q standards
for Concrete and Masonry Construction are reproduced in this section for reference. The
safety regulations of individual states may substitute for the Federal requirements, but
the state standards (and the enforcement of those standards) must be at least as effective
in providing safe and healthful employment and places of employment as the standards
promulgated under Federal requirements which relate to the same issues.
(b) Reinforcing steel. All protruding reinforcing steel, onto and into which employees
could fall, shall be guarded to eliminate the hazard of impalement.
(2) Signs and barriers shall be erected to limit employee access to the post
tensioning area during tensioning operations.
(d) Riding concrete buckets. No employee shall be permitted to ride concrete buckets.
(1) No employee shall be permitted to work under concrete buckets white buckets
are being elevated or lowered into position.
(2) To the extent practical. elevated concrete buckets shall be routed so that no
employee, or the fewest number of employees, are exposed to the hazards
associated with falling concrete buckets.
(1) Bulk storage bins, containers, and silos shall be equipped with the following:
(2) No employee shall be permitted to enter storage facilities unless the ejection
system has been shut down, locked out, and tagged to indicate that the ejection
system is not to be operated.
(b) Concrete mixers. Concrete mixers with one cubic yard (-8 m(3)) or larger loading skips
shall be equipped with the following:
{c) Power concrete trowels. Powered and rotating type concrete troweling machines that
are manually guided shall be equipped with a control switch that will automatically
shut off the power whenever the hands of the operator are removed from the
equipment handles.
(d) Concrete buggies. Concrete buggy handles shall not extend beyond the wheels on
either side of the buggy.
APPENOIXG
(1) Concrete pumping systems using discharge pipes shall be provided with pipe
supports designed for 100 percent overload.
(2) Compressed air hoses used on concrete pumping system shall be provided
with positive fail-safe joint connectors to prevent separation of sections when
pressurized.
(1) Concrete buckets equipped with hydraulic or pneumatic gates shall have
positive safety latches or similar safety devices installed to prevent premature or
accidental dumping.
(2) Concrete buckets shall be designed to prevent concrete from hanging up on top
and the sides.
(g) Tremies. Sections of tremies and similar concrete conveyances shall be secured
with wire rope (or equivalent materials) in addition to the regular couplings or
connections.
(h) Bull floats. Bull float handles used where they might contact energized electrical
conductors, shall be constructed of nonconductive material or insulated with a
nonconductive sheath whose electrical and mechanical characteristics provide the
equivalent protection of a handle constructed of nonconductive material.
(1) Masonry saw shall be guarded with a semicircular enclosure over the blade.
(2) A method for retaining blade fragments shall be incorporated in the design of the
semicircular enclosure.
(2) Tags shall read Do Not Start or similar language to indicate that the equipment is
not to be operated.
(2) Drawings or plans, including all revisions, for the jack layout, formwork (including
shoring equipment), working decks, and scaffolds, shall be available at the
jobsite.
(3) Erected shoring equipment shan be inspected immediately prior to, during, and
immediately after concrete placement.
(4) Shoring equipment that is found to be damaged or weakened after erection, such
that its strength is reduced to less than that required by 1926.703(a){1), shall be
immediately reinforced.
(5) The sills for shoring shall be sound, rigid, and capable of carrying the maximum
intended load.
(6) All base plates, shore heads, extension devices, and adjustment screws shall be in
firm contact, and secured when necessary, with the foundation and the form.
(7) Eccentric loads on shore heads and similar members shall be prohibited unless
these members have been designed for such loading.
{8) Whenever single post shores are used one on top of another (tiered), the
employer shall comply with the following specific requirements in addition to the
general requirements for formwork:
(i) The design of the shoring shall be prepared by a qualified designer and the
erected shoring shall be inspected by an engineer qualified in structural
design.
(iv) The single post shores shall be a adequately braced in two mutually
perpendicular directions at the splice level. Each tier shall also be diagonally
braced in the same two directions.
(9) Adjustment of single post shores to raise formwork shall not be made after the
placement of concrete.
(10) Reshoring shall be erected, as the original forms and shores are removed,
whenever the concrete is required to support loads in excess of its capacity.
(1) The steel rods or pipes on which jacks climb or by which the forms are lifted shan
be-
(2) Forms shall be designed to prevent excessive distortion of the structure during
the jacking operation.
(3) All vertical slip forms shall be provided with scaffolds or work platforms where
employees are required to work or pass.
(4) Jacks and vertical supports shall be positioned in such a manner that the loads do
not exceed the rated capacity of the jacks.
{5) The jacks or other lifting devices shall be provided with mechanical dogs or other
automatic holding devices to support the slip forms whenever failure of the
power supply or lifting mechanism occurs.
(6) The form structure shall be maintained within all design tolerances specified for
plumbness during the jacking operation.
APPENDfXG
(7) The predetermined safe rate of lift shall not be exceeded.
(1) Reinforcing steel for walls, piers, columns, and similar vertical structures shall be
adequately supported to prevent overturning and to prevent collapse.
{2) Employers shall take measures to prevent unrolled wire mesh from recoiling. Such
measures may include, but are not limited to, securing each end of the roll or
turning over the roll.
(I) Forms and shores (except those used for slabs on grade and slip forms) shall
not be removed until the employer determines that the concrete has gained
sufficient strength to support its weight and superimposed loads. Such
determination shall be based on compliance with one of the following:
{i) The plans and specifications stipulate conditions for removal of forms and
shores, and such conditions have been followed, or
(ii) The concrete has been properly tested with an appropriate ASTM standard
test method designed to indicate the concrete compressive strength,and
the test results indicate that the concrete has gained sufficient strength to
support its weight and superimposed loads.
(2) Reshoring shall not be removed until the concrete being supported has attained
adequate strength to support its weight and all loads in place upon it.
APPENDfXG
or blocking devices, which will provide positive connection between the lifting rods
and attachments and will prevent components from disengaging during lifting
operations.
:c•thtslab�rdrop
panel thickness
Chapter 1
1.1. What three factors ultimately determine whether to use metal versus wood and manu
factured versus job-built formwork systems for a particular project?
Chapter 2
2.1. What are the latest editions of three ACI publications referenced as older editions by
OSHA 1926 Subpart Q?
2.2. Based on the suggested basis of measurement of form area for payment purposes,
calculate the payment area of the single wall shown in Fig. 13.8. Assume the wall is 12 in.
thick, there are no rustication joints, and the depression is 3-1/2 in. deep on the inside
face. The wall will be constructed with a low-slump concrete not requiring a top form.
Chapter3
3.1. Formwork economic considerations usually involve a comparison of what three
options?
3.2. During the erection of the formwork, what other three construction trades are most
active and require coordination?
3.3. Draw three separate images of Pier No. 3 from the planning example in Section 3.7.1,
showing each stage of formwork erection for the individual placements and showing
the specific form segments in place.
3.4. Explain four ways in which a formwork contractor can use BIM to make formwork proj-
ects to be more predictable, controllable, and profitable.
Chapfer4
4.1. Determine the density of Southern Pine at 19% moisture content.
4.2. S4S 4x6 dimension lumber will be used as a beam oriented for bending about the
strong axis. Use tabulated values to find the cross-section width, depth, area, moment of
inertia, and section modulus.
4.3. S4S 2xB dimension lumber will be used as a beam oriented for bending about the
weak axis. Use tabulated values to find the cross-section width, depth, area, moment of
inertia, and section modulus.
4.4. A 6x6 rough wood timber will be used as a shore oriented vertically in falsework. Use
Table 4.2 to find the cross-section dimensions, area, moment of inertia, and section
modulus.
4.5. A No. 2 Spruce-Pine-Fir (SPF) S4S 2x12 with moisture content greater than 19% is used
as a joist in bending about the strong axis under a load duration less than 7 days. You
are preparing to investigate the ASD bending strength. List the values of the following
parameters:
4.8. Two double-headed 16d common nails will be used to attach a Douglas Fir-Larch 545
2x4 to a Douglas Fir-Larch 545 4x4 in side grain under normal temperature conditions
for a load duration less than 2 months. Determine the total A5D withdrawal capacity of
the connection if assembled under dry conditions but subject to significant wetting and
drying in service.
4.9. Three 16d box nails will be used to attach a Southern Pine 2x4 S4S to a Spruce-Pine-Fir
S4S 4x4 in side grain under normal temperature conditions for a load duration less than
7 days. Determine the total LRFD withdrawal capacity of the connection if assembled
under dry conditions but subject to significant wetting and drying in service.
Chapter 5
5.1. A formwork member is subjected to the following unfactored axial loads: Formwork
load= 1 kip; variable material load=10 kip; construction personnel=5 kip; and wind
load= 3 kips {based on A5CEJ5EI7-10). Determine
a) The A5D controlling combination (kip); and
b) The LRFD controlling combination (kip).
5.2. A 10 in. thick concrete slab will be constructed with concrete having a density (unit
weight) of 1431b/ftl. The slab is reinforced with No. 7 bottom bars at 8 in. on centereach
way and No. 6 top bars at 8 in. on center each way.
a) Determine the average weight of the slab (lb/ft1) based on the actual mass of the
concrete and steel materials.
b) Determine the equivalent density (unit weight) (lb/ftl) of the combined concrete and
steel.
c) Determine the total steel as a percentage of the slab volume.
5.3. Using Table 5.2, determine the total vertical load (lb/ft1) of a two-way concrete joist
system using a 12 in. pan depth and a 24 x 24 in. plan void with a construction live load
of 50ib/ft2•
5.4. Determine the unit weight coefficient Cw for a lightweight concrete with a unit weight
of 120ib/ft3•
5.5. Verify the maximum pressure magnitudes found in Table 5.7 for the following condi
tions by direct calculation based on Table 5.4. Note that these values are prior to adjust
ment by C, and Cw
a)R=9ft/h, T=70°F,h=12 ft
b)R = 3 ftlh, T = SO"F, h = 10 ft
c)R=3 ft/h, T=50"F,h= 18 ft
5.6. Lines of shores with X-braces are used to support an elevated form. The shore height is
9ft and the spacing between the seven repeating lines of shores and braces is 5 ft. The
face area of the shores and braces perpendicular to the wind direction under consider
ation is 100 ft1 and the gross area bounded by a line of braced shores is 500 ft1. Deter
mine the cumulative shielding coefficient 11m by calculating the actual series. Compare
the value calculated from the actual series to the value calculated from the equivalent
equation.
APPENDIXH
5. 7. Given the following conditions for a wall form at ground level:
Form height= 16ft, length= 64ft;
location: Iowa; Exposure C, not at top of hill or in a special wind region;
Duration of exposure: less than two weeks.
Determine the wind load force F..,. to be applied at a height of 0.55h using the ASCE/SEI
7-10 method with ASCE/SEI3 7-1 4reductions for an ASD application and compare to
the ACI3 47R minimum lateral force applied at the top of the form to determine which
controls.
5.8. An elevated slab form is to support a 10 in. slab weighing 150 lbfftl. The formwork
weighs 8 lb/ft1• The slab is96ft long parallel to the wind direction being evaluated.
Compare the two ACJ 3 47R minimum levels of lateral load (lb/ft) that must be consid
ered other than load based upon wind pressure calculation.
5.9. Formwork for the floor slab in Problem 5.8 will have the following characteristics:
Edge form boards 10 in. high, 3/ 4in. plywood sheathing, 2x6joists, 4x6stringers
(girders).
Flat-faced shores and braces;
Framework of braced shores with A,= 42 ft1 for the face width of 64ft. A,/A = 0. 1 2,
9
�.=63. ;
Basic wind speed 115 mph based on ASCE/SEI7-10; Exposure B, not at top of hill or in
a special wind region;
Duration of exposure: less than 3 weeks;
Highest elevation of use: 100ft above ground;
Typical structure floor-to-floor height= 1 2 ft;
Chapter6
6.1. A floor slab will have a concrete weight of 130 lb/ft1• The forms and shores weigh
10 lb/ft1, and reshores weigh 41b/ft1• Construction personnel and equipment loading
will be SO lb/ft1• Convert each load to be expressed in terms of the floor slab dead load D
(rounded to three decimal places).
6. 2. A shoring and reshoring analysis has been conducted for the case of two levels of
forms/shores and one level of reshores. The result for a particular step is shown. The
formS/shores weigh 0.01 200. From the information provided, first determine the load
of the reshores. In the next construction step, the lowest level of forms/shores will be
removed. Draw the view of the cells for the next step and show the various resulting
loads in the cells for the slabs and the shores/reshores.
PROBLEMS
6.3. A shoring and reshoring analysis has been conducted for the case of one level of
forms/shores and two levels of reshores. The result for a particular step is shown. In
the next step, the forms/shores are erected at the top level and the next slab is placed.
The combined load of the forms/shores, slab, and construction personnel and equip·
ment load is 1.7000. Draw the view of the cells for this next step and show the various
resulting loads in the cells for the slabs and the shores/reshores.
Slop• loodc_lly_
.....
.. ..
6.4. A shoring and reshoring analysis has been conducted for the case of two levels of
forms/shores and two levels of reshores. The result for a particular step is shown. From
the information provided, first determine the load of the forms/shores and the load of
the reshores. In the next step, the lowest level of forms/shores will be removed. Draw
the view of the cells for this next step and show the various resulting loads in the cells
for the slabs and the shores/reshores.
6.5. Drawings for a structure indicate it was designed for a 120 lb/ft2 slab self weight,
20 Jb/ff partition load, 81b/ft2 mechanical and ceiling load, and 60 Jb/ft1 occupancy
live load with noLL reductions taken. The design load factors were 1.20L and 1.6LL
Determine:
a) The original factored design load stated in lb/ft2 and in terms of D.
b) The total factored load strength available at 10 days if the 40°F curve shown in Fig 6.6
is for the concrete mixture used on the project and the temperature of the curing
concrete, and it is assumed that structure strength is directly proportional to the
percent of 28·day strength attained.
c) The total factored load strength available at 10 days if the 40°F curve shown in Fig 6.6
is for the concrete mixture used on the project and the temperature of the curing
concrete, and it is assumed that structure strength is proportional to the square root
of the proportion of 28·day strength attained.
APPENOIXH
6.6.The temperature of the concrete for an elevated slab is measured every hour after it
was placed at 12 noon.The record of those measurements is shown in the table below.
The datum temperature for the concrete mixture has been previously evaluated by lab
tests to beT0= 23"F.
a) Determine the maturity (°F·hours) at the end of 24, 48, and 72 hours.
b) If the maturity-versus-strength curve for this particular concrete mixture is given
in Fig. 6.11, estimate the percent of specified 28-day strength gained at 24, 48, and
72 hours
Record a/concrete temperature, °F
Hour PM AM PM AM PM AM
12 70 95 80 67 65 69
I 81 93 81 62 70 67
2 95 91 83 59 76 65
3 115 89 85 57 81 62
' 125 86 " " 83 60
5 128 " " " 85 57
6 122 82 83 53 " 55
7 120 81 82 5I 82 55
8 '" 80 80 52 80 56
9 110 79 76 53 77 59
10 105 78 73 56 73 63
II 100 79 71 60 71 69
Chapter 7
Solve the following problems based on detailed calculations, not based on the span and
load tables of Chapter 9.
7.1. Southern Pine S4S 2x4 No. 2 wall form studs, bending about the strong axis, are
continuous over three or more spans of 27 in. Given: load duration less than 7 days, wet
use, temperature under 100°F, not incised, and repetitive use. Determine the maximum
ASD uniform load (lb/in.) that can be carried based on each of the following criteria
separately and identify the controlling maximum load.
a) Bending;
b) Shear, with eb = 1.5 in.; and
c) Deflection if limited to £/400.
7.2. Douglas Fir-larch S4S 4x6 No. 2 stringers bending about the strong axis are contin·
uous for two spans of 5 ft. Given a load duration of greater than 7 days but less than 2
months, dry use, temperature under 100°F, incised, and not repetitive use. Determine
the maximum uniform load (lb/in.) that can be carried based on each of the following
criteria separately.
a) Bending (factored load from LRFD for A.= 0.9);
b) Shear (factored load from LRFD for A= 0.9), with €11 = 3.5 in.;
c) Deflection (unfactored load) if limited to E/240.
7.3. Structural I. 5/8 in. B-B Plyform plywood is to support a load of 12Sib/ft1 over 3 or
more equal spans with face grain oriented parallel to the direction of plywood span.
Determine the maximum span e (in.) based on each of following criteria separately and
identify the controlling maximum span.
a) Bending;
b) Shear, with eb = 1.5 in.;
c) Deflection if limited to €/400.
7.4. Same as problem 7.3 but with plywood face grain perpendicular to the plywood span
direction.
PROBLEMS
7.5. The narrow edge of No. 2 S4S 2x6 Southern Pine joists will bear on the narrow edge
of 4x6 S4S No. 2 Douglas Fir (South) stringers at locations that are more than 6 in. from
the end of either member. Given: load duration less than 7 days, dry use, temperature
under lOOeF, and not incised. Determine the maximum load that can be resisted by each
member in bearing at the location of contact. What is the controlling maximum load
that can be transmitted in bearing?
Chapter 8
Solve the following problems based on detailed calculations, not based on the span and
load tables of Chapter 9.
8.1.A 6x6 rough-sawn wood shore is planned for use in bridge falsework. lf K� = 1.0, what
is the maximum laterally unbraced height allowed for the shore?
8.2. Determine theASD f.wo' for the following conditions: Construction-grade shore,
incised Douglas Fir-Larch, 545 4x4, moisture content greater than 19%, load duration
less than 7 days, and temperature environment between 100 and 12S0F.
8.3. Determine the LRFD £,.,'for the following conditions: Construction-grade shore,
incised Douglas Fir-Larch, S4S 4x4, moisture content greater than 19%, load duration
less than 7 days, and temperature environment between 100 and 12S°F.
8.4.A Douglas Fir (South) S4S 4x4 shore is axially loaded in compression. Given: K.= 1.0, C0
= 1.25, C"'= 1.0, C,= 1.0, and C;= 1.0. Determine theASD load capacity by calculation for
each of the following unbraced shore lengths:
a) 4 ft
b) 8 ft
c) 12 ft
d) 16 ft
B.S. Repeat problem 8.4 to determine the LRFD load capacity for each length, assuming A
=0.8.
8.6. Based onASD, what load will a 16 ft tall 545 4x6 No. 2 grade Southern Pine shore carry
in axial compression if it is braced laterally at midheight only in the weak direction?
Given: K�= 1.0, not incised, normal temperature conditions, dry use, and cumulative
load duration greater than 7 days but less than 2 months.
8.7. Based on LRFD, what factored load will a 16 ft tall S4S 4x6 No. 2 grade Southern Pine
shore carry in axial compression if it is braced laterally at midheight only in the weak
direction? Given: K. = 1.0, not incised, normal temperature conditions, dry use, cumula
tive load duration greater than 7 days but less than 2 months, and A= 0.9.
8.8. Two double-headed 16d common nails will be used to attach a Douglas Fir-larch 545
2x4 to a Douglas Fir-Larch S4S 4x4 in side grain under normal temperature conditions
for a load duration less than 2 months. Determine the totalASD lateral load capacity of
the connection if assembled under dry conditions but subject to significant wetting and
drying in service.
Chapter 9
Respond to the following problems using the design tables.
9.1. B-B Plyform Class t plywood continuous for three or more spans is loaded with a pres
sure of 800 lb/ft1 in a wall form. What is the indicated maximum span when deflection is
limited to t/240 but not more than 1/16 in. if
a) Thickness=SIB in., C0=1.0, and face grain is parallel to span direction?
b) Thickness= 5/8 in., CD= 1.25, and face grain is perpendicular to span direction?
c) Thickness= 1 in., CD= 1.25, and face grain is parallel to span direction?
APPENDIXH
9.2. Determine the spacings of wall form vertical studs, horizontal double wales, and ties
for a 12 ft tall wall form for a maximum pressure of BOO lb/ftl_ Assume 3/4 in. Plyform B-B
Class I plywood with face grain horizontal and No 2. grade 2x4 $4$ Spruce-Pine-Fir studs
and wales with moisture content less than 19%.load duration is less than 7 days and all
members are continuous over three or more spans. Round down to the nearest whole
inch for each spacing.
9.3. Determine the indicated maximum concentric axial load for the following conditions:
a) Douglas Fir-Larch construction-grade 4x4 rough with effective length of 11 ft.
b) Southern Pine construction-grade S4S 4x4 with effective length of 12 ft.
c) Hem-Fir No. 2 grade 545 3x4 with effective length of 10 ft.
d) Douglas Fir-larch No. 2 grade 545 4x4 with effective length of 15 ft.
9.4. Determine the indicated allowable bearing load for the following shore sizes and
allowable bearing design values if bearing contact area is the full end area of the shore.
a) 545 4x6 shore and Fd'= 625 psi
b) $4$ 4x4 shore and Fa'= 565 psi
c) 545 3x4 shore and F,J.'= 405 psi
Chapter 10
10.1. Referring to Fig. 10.2, what is:
a) The beam size on Line A3 betweenlines 1 and 2?
b) The beam size on line 7 betweenlines A and B?
c) Requested to be verified?Who is making the request?Who should respond?
d) The size of the beam corner chamfers?
e) The most typical elevated slab thickness?
10.2.1n Fig. 10.5, why does the drawing indicate that the adjustable shores are to be
turned in opposite directions?
10.3. Based on simple tributary area, calculate the maximum shoring frame leg load for the
shoring towers in Fig. 10.9 on line K betweenlines 1 and 2. Assume Cl'f= 50 lb/ftl, w,=
1SO lb/ft', and formwork weight of 10 lb/ftl of contact area.
Chapter 11
1 1.1. list five items of personal protective equipment that may be required for formwork
crews depending on the actual task.
11.2. Determine the allowable deviation in location for a 4 ft square footing according to
ACI117-10.
11.3. Name and describe a device that reduces or eliminates the need for reinforcing bar
penetrations through bulkheads.
11.4. When many forms of similar size must be built or assembled on the project site,
building a __ will reduce deviation from square and size and improve crew
productivity.
11.6. Name a device intended to keep wood reshores in place when the stab above the
reshore rebounds upward.
Chapter 12
12.1. What is a side form spacer? Describe three devices that are used to serve this
purpose.
12.2. Why is ·release agent- a better general term than ""form oil"?
12.3. Name the two basic types of form release agents and briefly describe, distinguishing
the two types.
PROBLEMS
12.4. Why is it necessary for aluminum forms to be specially seasoned or coated prior to
contact with fresh concrete?
12.6. Steel forms will be used to cast a 12 in. thick wall in cold weather with concrete
containing 300 lb/ydl ofType I cement.The wall will be wrapped with a 2 in. thick
blanket made with mineral fiber insulation. Assuming linear interpolation is appropriate,
what is the minimum acceptable surrounding ambient temperature for 3 days curing
without providing additional protection?
Chapter 13
13.l. ln accordance with the concrete surface classes defined by ACI117, what is the
class of each of the separate formed surfaces where the following irregularities were
measured?
a) Abrupt deviation of 3/8 in.
b) Abrupt deviation of 5/8 in.
c) Gradual deviation of 112 in. measured with a 5 ft straight edge.
d) Gradual deviation of 3/16 in. measured with a 5 ft straight edge.
13.2.1n accordance with ACI301, what are the criteria for Surface Finish 2.0?
13.3. As defined by ACI347.3R, what are the criteria for CSC4 when a non-absorbent form
facing is used? list codes for texture, void ratio, color, irregularities, joints, and form
facing.
13.4. Voids were measured in an as-cast wall surface.The approximately circular voids had
the following counts of diameter in inches: 3/32, 19; 1/8, 1 7; 5/32, 15; 3/16, 13; 7/32, 10;
1/4, 14; 9/32, 7; S/16, 6; 11/32, 2; 3/8, 1. Determine the Surface Void Ratio classification.
INDEX
INDEX
Formwork erection safety 11-4 lateral pressure of fresh concrete 5-4,18-19
Formwork for architectural concrete 14-1 layout and detail drawings 10-3
Formwork planning process 3-8 layout of casting area 18-24
Formwork requirements 18-24 lift method of construction 18-13
Foundations or starting lifts 16-9 line drawings 10-2
Foundations 15-2 live loads 5-4
Framing and facing materials 4-16 load combinations 5-2
Friction collars and support brackets 4-36 loads and pressures 5-1,14-3,17-8,18-3
loads on the formwork 16-4
G location of shop at project site 11-2
Ganged panel forms and climbing forms 11-12 long line segment casting 15-17
Glass fiber-reinforced polymer 4-18 long-radius curves 11-15
Glossary C-1 low walls 11-11
Glued laminated timber 4-9 lRFDanalysis 6-17,7-21,8-4
Ground anchors 8-14 lRFDcombinations 5-2
Guides and specifications for formwork design and lumber finish and sizes 4-3
construction 2-2 lumber 4-1
H M
Handling,erecting,stripping 16-7 Maintaining and coordinating tolerances 2-11
Hangers 4-36,7-37 Maintaining level and alignment 18-7
Hardware and fasteners 4-23 Making precast bridge segments 15-17
Heat curing considerations 15-19 Manufactured shoring devices 8-7
High walls 11-12 Mass concrete formwork 16-1
Highway and airport paving 11-8 Massive piers 15-6
Highwaypavers 18-11 Materials and accessories related to formed surface of exposed
History of lateral pressure values for form design 5-7 concrete 2-13
Horizontal construction joints 11-18 Materials and hardware 3-4
Horizontalloads 5-13 Materials 14-7
Horizontal slip forms 18-8 Materials 18-24
How formwork affects concrete quality 2-3 Materials,accessories,and proprietary products 4-1
How the Engineer/Architect can reduce form costs 2·14 Maturity of concrete 6·28
Hurricane-prone regions 5-14 Measurement and payment for formwork 2-14
Metal deck 4-42,11-34
Metal molds 14-20
1-Joists 4-11 Minimum horizontal loads 5-13
Improper stripping and shore removal 2-5 Monitoring early strength gain of concrete in the field 6-27
Improving soil bearing and bracing 2-4 Monolithic slab, beam,and girder 15-8
Incising factor,C; 4-8 Mudsills or shoring foundations 11-37
Incremental launching or pushout method 15-17 Multi-story buildings 6-1,12-16
Inflated forming methods 18-17
Influence of placing equipment 17-7 N
Inspection and form watching 12-8 Nail holding power 4-24
Insulation and insulating forms 4-22 Nail types used for formwork 4-24
Invert forms 17-2 Nail-down lap pans 11-31
Nails in plywood 4-26
Nails 4-23
Jacking system 18-6 Non-cantilevered formwork 16-7
Job-built forms 3-4,11-9 Notation for loads and pressures 5-1
Joint surfaces 15-19 Notation 7-2, B-1
Joints 11-17,14-23
Joints 18-26 0
Joists,studs,and beams: Tables 9.6 to 9.8 9-4 Objectives in formwork building 2-1
Occupational Safety and Health Administration {OSHA) A-3
K One-way joist system 11-30
Kinds of lumber 4-2 Ornamental detail 14-18
OSHA regulations for formwork and shoring G-1
Overhang,sidewalks,parapets,and median barriers 15-10
lack of attention to formwork details 2-10 Overlaid plywood 4-14
lateral pressure of concrete equations 5-8 Overlapping inspections 12-9
INDEX
p Reconstituted wood materials 4-16
Panel assembly and erection 11-26 Reducing slipformed wall thickness 18-7
Panel forms and forming systems 4-38 Referenced standards and reports A-1
Pans and domes for concrete joist construction 4-39 Regulations for safety 2-1,11-4
Paving work 11-7 Relationship of architect, engineer, and contractor 2-10
Penetration resistance 6-29 Removal of forms and shores 6-1,11-36,12-12
Permanent shores and back shores 11-39 Rented forms 3-6
Pier caps and tie struts 15-7 Repetitive member adjustment, C, 4-7
Piers 15-5 Reshoring 12-16
Pilasters 11-14,14-15 Reuse schemes 3-4
Piles 15-4 Ribbed and fluted surfaces 14-8
Placing and vibrating-effect on formwork 12-11 Rock or soil offering direct support 15-4
Placing concrete 18-16 Round and flared columns 11-21
Placing reinforcement and inserts 12-2 Round piers 15-6
Planning and supervision 16-11 Rubbed surface finishes 13-3
Planning for maximum reuse 3-3 Rubber liners 4-21
Planning for safety 2-3
Planning form sizes 3-10 5
Planning 3·1 Scaffolding, Shoring, and Forming Institute A-3
Plastermolds 14-19 Scheduling 3-11
Plastic and rubber molds 14-20 Segmental box-girder bridge construction 15-12
Platforms and access for workers 2-3 Seismic loads 5-20
Plywood construction and sizes available 4-12 Selection of formwork and facing 13-8
Plywood types and grades 4-12 Setting, stripping, and cycling costs 3-6
Plywood 4-11 Shafts 17-11
Polymeric form liners 4-20 Shear in plywood 7-12
Polymeric form materials 4-18 Shear in wood beams 7-10
Positioning bars; placement tolerances 12-4 Shear 7-10
Post-tensioned structures6-27 Sheathing and lining 14-13
Post-tensioning 18-27 Sheathing design 7-7, 9-4
Precast concrete 4-43,18-23 Sheathing 18-5
Precast panels as forms or liners 14-10 Shell form design considerations 18-15
Precast segmental construction 15-13 Shells, domes, and folded plates 18-14
Precast/Prestressed Concrete Institute A-3 Shielding from wind pressure 5-17
Precasting advantages 18-23 Shielding of formwork by surroundings and obstructions 5-17
Prefabricated forms 4-38 Shore layout and installation 11-35
Prefabricated panel systems 11-12 Shore loads 6-16
Preparation for concreting 12-5 Shore loads 6-26
Preparing a formwork specification 2-11 Shoring 11-35
Preparing effective drawings 10-1 Shoring and bracing members 8-1
Preplaced aggregate concrete 18-19 Shoring and floor loads in multi-story structures 6-1
Pressure from Aggregate 18-20 Shoring and reshoring loads in multi-story structures 6-3
Pressure from grout 18-20 Shoring and reshoring 2-4,6-1
Pressure of concrete 5-4,5-8 Shoring frames 4-44
Pressure on sloping surfaces 5-11 Shoring not plumb 2-8
Prestressed precast concrete 18-26 Shoring system design 6-21
Pretensioning 18-29 Shoring towers 11-38
Principal erection methods 15-14 Shoring 4-43
Problems H-1 Short line precasting 15-18
Progressive placing 15-16 Short-radius curves 11-16
Pullout tests 6-29 Shotcrete 18-21
Purchased or rented forms 3-6 Single-post shores 4-44
Size factor, CF 4-8
Q Slab form design 7-22
� �
Quality and c : �nlif1ess f the formwork 12-10 Slab forms 11-28
-_.. Slab loads 6-5
R .·· Slab separation 18-14
I . .
Rate of placemeQt _. ?;{I J"' 1 Slabs supported on steel beams or precast concrete beams 11-34
INDEX
Sliding Operations 18�6 Tolerances for completed work 18-4
Slipformconstruction 18-1 Tolerances for slab work 11-34
Slipformed precast hollow-core floor slab 18-12 Tolerances for walls 11-19
Smooth as-cast surfaces 14-6 Tolerances 11-28,16-11,17-10
Soffits 14�17 Total allowance for camber and adjustments 8-13
Solid wood compression members 8-2 Total pressure on forms 18-20
Spacers and spreaders 4�37 Trades 3-8
Span-by-span construction, stepping formwork 15-15 Traveling forms 18-17
Spandrel beams 11�27 Tremie concrete 18-21
Spandrels and parapets 14-16 Trial plans 3-9
Special purpose and cu�tom-made forms 4-43 Tubular steel shores 8-5
Special techniques in concrete construction 18-1 Tunnel and shaft formwork 17-1
Specifications for quality 2-2 Tunnel forming components 17-1
Specifications 13-5,14-2 Tunnel inverts 18-9
Splicing of Shores 8-5 Two-way joist or waffle slab 11-32
SquareCorners 11-14 Types of cantilever forms in common use 16-2
Stability adjustments 4-8 Types of column forms 7-31
Standards,sp�cifications,and guides related to formwork 2-1
Stay-in-place forms 2�12,4-42 u.
Steel Joist Institute A-3 U.S. Department ofCommerce, National Institute of Standards and
Steel shoring frames 8-6 Technology A-3
Steel strapping 4-37 Unstable soil under mudsills 2-8
Steel 4-16 Use of water on the forms 12-8
Sticking and staining problems 12-7 Usingthe forms 12-1
Stonework facing 15-6
Storage of materials and finished parts 11-3 v
Strength and stability 12-10 Vacuum liners 4-21
Strength properties 4-15 Vertical alignment 15-6
Strength requirements 6-27,18-17 Vertical construction joints 11-17
Stringer design 7-7, 9-4 Verticalloads 5-3
Stripping and decentering 2-12 Vertical slipform construction 18-1
Stripping bridge forms 15-11 Vibration and form access 17-9
Stripping techniques 12-14 Vibration and impact 2-6
Stripping time based on concrete strength 12-12 Vibration 5-6,15-19
Stripping time 12-12,17-10 Void and duct forms 4-40
Stripping 14-24,18-8,18-26 Voids, inserts, attachments 15-19
Structural composite lumber 4-10
Structures designed for composite action 6-26 w
Studs design 7-7, 9-4 Wales 7-7,9-4,18-4
Superstructures 15-8 Wall footings 11-5
Supervision and inspection 2-3 Wall form bracing loads 8-8
Support for reinforcing bars 12-3 Wall form design. 7-15
Support for shoring 8-8 Wall forms 5-10,11-9
Support for superstructure forms 15-10 Wall openings 11-17
Surface void ratio 13-4 Walls 14-12
Suspended forms for fireproofing and composite Weight of concrete 5-6
construction 11-27 Where to construct forms 3-5
Wind load on wall and column forms 5-18
Wind loads on elevated slab formwork 5-19
Temperature 5-7 Wind loads 5-14
Textured as-cast surfaces 14-8 Wind shielding of repetitive objects of formwork system 5-17
Textured surfaces 4-15 Wood grading and design values 4-4
The Aluminum Association A-2 Wood molds 14-18
Ties and braces 11-26 Wood screws 4-26
Ties for water-retaining structures 4-35 Wood shores 8-1,9-5,11-37
Ties 4-31,7-36,14-14 Wood trusses 4-11
Tilt-up construction 18-12
Toenailing and clinching 4-26 y
Tolerance requirements 15-20 Yokes 18-4
INDEX
American Concrete Institute 38800 Country Club Drive
Always advancing Farmington Hills, Ml 48331 USA
+1.248.848.3700
www.concrete.org
9
111111111111111111 1111 11
780870 319129