Professional Documents
Culture Documents
Reference #0017820197
No:
March 2018
This report has been prepared and reviewed by EQMS company, with all responsible
skill, care and diligence within the terms of the Contact with the client, incorporating
our General Terms and Conditions of Business and taking account of the resources
devoted to it by agreement with the client.
We disclaim any responsibility to the client and others in respect of any matters outside
the scope of the above.
This report is confidential to the client and we accept no responsibility of whatsoever
nature to third parties to whom this report, or any part thereof, is made known. Any
such party relies on the report at their own risk.
LIST OF TABLES
Table 1-1: Segregation of Installed Generation Capacity of Bangladesh...................................................3
Table 1-2: Power Generation Units (fuel type wise) of Bangladesh...........................................................3
Table 1-3: Maximum Power Demand form 2015 to 2041..............................................................................6
Table 1-4: Impact Assessment Process............................................................................................................9
Table 1-5: Nature of the Impact......................................................................................................................10
Table 1-6: Impact Extent from the project location......................................................................................10
Table 1-7: Duration of Impact.........................................................................................................................10
Table 1-8: Intensity of Impact.........................................................................................................................11
Table 1-9: Potential for irreplaceable loss of resources...............................................................................11
Table 1-10: Probability of Impact...................................................................................................................11
Table 1-11: Significance..................................................................................................................................12
Table 1-12: Significance of issues (based on Environmental Parameters)...............................................12
Table 1-13: Potential Social Impact Significance..........................................................................................13
Table 1-14: Potential Public Health Impact Significance............................................................................14
Table 1-15: EIA study team.............................................................................................................................18
Table 1-16: Layout of the EIA Report............................................................................................................18
Table 2-1: Policies relevant to Environment.................................................................................................22
Table 2-2: National Legal Instruments relevant to the Project...................................................................24
Table 2-3: Project Relevant International Treaties and Conventions........................................................34
Table 2-4: Project Categorization as per ADB Safeguards.........................................................................38
Table 2-5: IFC Performance Standards..........................................................................................................39
Table 3-1: Key Information of Proposed HFO based power plant at Chandpur...................................51
LIST OF FIGURES
Figure 1-1: Bangladesh Power Sector Overview (Source: PSMP-2016)......................................................4
Figure 1-2: Estimated Composite Daily Load Curve in the summer..........................................................5
Figure 1-3: Peak Demand Projection using GDP Elasticity Method (case comparison)..........................5
Figure 1-4: EIA study Process...........................................................................................................................8
Figure 1-5: 10 Km Study Area Map...............................................................................................................15
Figure 1-6: Location Map Of the proposed Project......................................................................................16
Figure 2-1: DoE Environmental Clearance Applicability and Procedure................................................33
Figure 3-1: Location Map of proposed power plant...................................................................................53
Figure 3-2: Proposed power plant layout.....................................................................................................55
Figure 3-3: Typical Wärtsilä 18V generating set arrangement...................................................................56
Figure 3-4: The combustion process in W18V50 Engine............................................................................57
Figure 3-5: Simplified process flow diagram of DECPCL power plant...................................................60
Figure 3-6: HFO Transportation Model.......................................................................................................62
Figure 3-7: Power evacuation route of DECPCL.........................................................................................63
Figure 3-8: Tentative project construction schedule of the proposed power plant at Gunrajdi,
Chandpur..........................................................................................................................................................68
Figure 3-9: Plant layout along with green belt.............................................................................................70
Figure 4-1: Baseline Map of the Proposed Power Plant.............................................................................73
Figure 4-2: Location of key feature around the proposed project site......................................................74
Figure 4-3: Key features in and around the project site..............................................................................79
CO : Carbon Mono-oxide
dB : Decibel
DO : Dissolve Oxygen
EC : Environmental Clearance
FD : Forest Department
HR : Human Resource
LC : Least Concern
CO : Carbon Mono-oxide
dB : Decibel
DO : Dissolve Oxygen
EC : Environmental Clearance
FD : Forest Department
HR : Human Resource
LC : Least Concern
Project Description
Desh Energy Chandpur Power Company Ltd. has purchased about 32 acre land at Gunrajdi Mouza,
Chandpur Sadar Upazila, Chandpur District. The land is fallen type and inundated most of time of
a year. Geographical location of the DECPCL project site is between 23°13'23.83"N to 23°13'35.95"N
latitude and 90°40'16.01"E to 90°40'28.72"E longitude. The project is located beside Dakatia River.
Chandpur-Faridganj Road is about 400 meter away from the project site. Proponent need to
construct about 60 meter approach road to touch nearest road which run to the main road. The
nearest road from the power plant is narrow and non-metaled. The road needs to be widened and
repaired to allow large vehicle to reach plant site via road network. The basic information of the
project is given below:
HFO fuel will be collected from global market. The proposed power plant has 15 day HFO storage
capacity. Fuel will be imported via oil vessel at Chittagong. The mother vessel has 35000 MT
capacity. Fuel is then transfer to lighterage having capacity 800 MT and carry to plant site jetty. Fuel
Reciprocating Generator
HFO 11/132 KV
Engine
transformer
and substation
Steam Generator
Boiler
200 MW
National Grid
Exhaust gas will be discharged via 50 meter stack. Air dispersion modeling has been performed
using AERMOD USEPA model to see SO2 and NOX concentration in the ambient air at ground level
due to emission from the proposed power plant. Predicted SO2 and NOX level in the receptor point
are within Bangladesh standard limit. To predict noise level in important receptors point around
the power plant during operation phase, Sound Plan 7.4 noise model has been used. From the
model output it is found that noise control mechanism in the power plant is adequate enough to
keep existing noise level within standard value set by DoE. Details of the air dispersion and
modeling results are presented in Chapter 5.
Implementation of EMP
It is recommended that a qualified plant employee should be designated as the focal point who will
have overall responsibility for plant’s environmental management and monitoring. The focal point
should be supported with required manpower and expertise (i.e., a committee with designated
members) to ensure proper environmental monitoring to take appropriate measures to mitigate any
adverse impact and to enhance beneficial impacts, resulting from the project activities. This person
through his team will make sure that the Contractor undertake and implement appropriate
measures as stipulated in the contract document, or as directed by him to ensure proper
environmental management of the project activities. The plant management will hire environmental
and social specialists as necessary to him in overseeing these activities. The activities will include
preparation of quarterly reports on Environmental Management activities in the plant.
The Plant Management should set up a procedure to address complaints and grievances (e.g.,
receiving formal complaints/ grievances, arrange hearing involving all stakeholders and keeping
records of such hearings, device and implement mitigation measures).The plant management
authority (DECPCL) should be responsible for overall environmental management during
operation phase of the project. An implementation schedule for environmental management and
monitoring during the construction phase will be prepared by the Contractor as part of construction
contract following recommended mitigation measures of potentially significant impacts.
Stakeholder Consultation
A range of stakeholder engagement and consultation methods have been used to identify concerns,
issues and suggestions for the Project. This included any suggested management and mitigation
measures. This involved Government consultation, face-to face interviews, small group meetings,
focus group discussions and a household level survey.
Outcomes from this consultation showed that the community was generally supportive of the
proposed Project and that the community believed that Project would bring some benefits to them
and the local area. Such perceived benefits included the potential for local employment relating to
the Project and the potential that infrastructure investment in the local area may occur as a result of
the Project.
Key concerns that government stakeholders and local people were found to have about the Project
included safety aspects of the Project, the potential for pollution to occur and that there might be
some damage caused to local roads or other infrastructure during construction. This EIA has
addressed each stakeholder concern with the development of specific mitigation and management
measures.
Conclusion
The present EIA report finds that though there are certain adverse environmental impacts
associated with the industrial unit under consideration, these are manageable.
The project is indispensable in view of the current energy shortage scenario in Bangladesh. The
project has positive impact on the socio-economy. It will facilitate jobs and business opportunity for
local people. The project will help in the industrialization, accelerating socioeconomic growth, and
improving quality of life. One of the most critical issues for the project is safety. This has been
adequately addressed through compliance with national building code (BNBC) in the construction
to ensure safety during natural disasters like earthquake and cyclone and a full-containment for the
HFO storage tank.
This EIA has fulfilled the requirements of the ECA’95, ECR’97 and other associated rules of
DoE;
The project is designed to meet up electricity demand of Bangladesh as per PSMP 2016
Potential negative impacts arising from the Project can be effectively managed and
mitigated;
Potential cumulative impacts from existing operations are not significant; and
The Project will also have potential positive (beneficial) impacts.
The proponent is committed to take necessary measures to mitigate adverse impact from the
proposed power plant during construction stage and also during operation phase as well.
EQMS would recommend to approve this EIA report as a guide book to manage environmental
impact due to the power plant’s construction and operation activities.
Electricity is the major source of power for most of the country's economic activities. Bangladesh's
total installed electricity generation capacity (including captive power) was 16046 MW as of
December 2017. In 2015 92% urban population and 67% rural population have the access to the
electricity for their source of light. Average 77.9% population has the access to the electricity in
Bangladesh. Problems in the Bangladesh's electric power sector include, high system losses, delays
in completion of new plants, low plant efficiency, erratic power supply, electricity theft, blackouts,
and shortages of funds for power plant maintenance. Overall, the country's generation plants have
been unable to meet system demand over the past decade. Noncommercial energy sources, such as
wood fuel, and crop residues, are estimated to account for over half of the country's energy
consumption.
Acceleration in industrial growth is expected due to the ongoing liberalization of the country's
economic policy. Most of the investment required for this increased capacity addition is expected to
be provided by private sector. Several new power projects have been identified to bridge the gap
between demand and availability. The problems of extensive load shedding; poor electrification
ratio can be reduced by setting up new power plants which add to the generation capacity which
also caters to the increasing load demand of the country.
Desh Energy Limited was formed in 2005. The company is a sister concern of Mohammadi Group, a
renowned conglomerate of the country. They have two power plants at present. One is a 100 MW
diesel fired plant at Siddhirgaj, Narayanganj having 96 numbers Caterpillar Generator sets of 1.2
MW capacity each. The other one is belonging to Desh Cambridge Kumargaon Power Company
Limited (DCDECPCL), a subsidiary of Desh Energy Limited. It is a gas fired 10 MW power plant at
Kumargaon, Sylhet. The company produces and supply power to Bangladesh Power Development
Board (BPDB). To meet up power demand and considering the proposal of Desh Energy Limited ,
BPDB has issued a LOI in favor of the company to set up 200 MW HFO based power generation
facility at Chandpur on Build-Own-Operate (BOO) basis under Private Sector Power Generation
Policy 1996 of Bangladesh. Power Division under the Ministry of Power, Energy and Mineral
Resources (MPEMR) selected the contractor to build the power plant under the 'Speedy Supply of
Power and Energy (Special Provision) Act 2010' bypassing the tendering process. The levelized
tariff is tk. 8.3772/ kWh.
At present environmental conservation is being given highest priority worldwide. Bangladesh is not
exceptional. It is mandatory to obtain environmental clearance from the Department of
Power Generation Units (fuel type wise) of Bangladesh as on December 2017 are presented below
focusing the Installed and Derated Capacity.
Table 1-2: Power Generation Units (fuel type wise) of Bangladesh
Installed Capacity of BPDB Power Plants as on December 2017
Fuel Type Capacity (Unit) Total (%)
Coal 250.00 MW 1.81%
F.Oil 0.00 MW 0%
Gas 8754.00 MW 63.22%
HFO 2794.00 MW 20.18%
HSD 1158.00 MW 8.36%
Hydro 230.00 MW 1.66%
Imported 660.00 MW 4.77%
Total 13846.00 MW 100 %
Derated Capacity of BPDB Power Plants as on October 2017
Fuel Type Capacity (Unit) Total (%)
Coal 170.00 MW 1.29%
F.Oil 0.00 MW 0%
Gas 8161.00 MW 62.07%
HFO 2792.00 MW 21.24%
HSD 1134.00 MW 8.63%
Hydro 230.00 MW 1.75%
Imported 660.00 MW 5.02%
Total 13147.00 MW 100%
Figure 1-3: Peak Demand Projection using GDP Elasticity Method (case comparison)
The results of peak demand projection in "High-growth Scenario", "Base Scenario" and "Low-
growth Scenario" are shown in Figure 1-3. While the average GDP growth rates from 2015 to 2041
are 6.4% in the "High-growth", 6.1% in the "Base" and 5.9% in the "Low-growth" scenarios, the peak
demand in each scenario in 7.0% p.a. in "High-growth", 6.7% p.a. in "Base" and 6.3% p.a. in "Low-
growth".
The increase in the power demand, including potential demand driven by the rapid economic
development in recent years, is expected to continue. The shortage of supply is considered to be the
main cause of the continuation of this imbalance between the supply and demand. The actual
outputs of the gas and coal thermal power generation were only at 40% and 60% of the outputs
described in PSMP 2010, respectively. In the case of the coal thermal power generation, a very
important base load power source in the energy mix, while the output in 2015 was forecast at 1,850
MW in PSMP 2010, even the construction of coal power plants has not been commenced five years
after the formulation of the plan. The lack of integrated planning and implementation for the
construction of large-scale port facilities, indispensable for the stable import of fuel, and the
construction of the power plants and the increased difficulty in fundraising for such a large-scale
infrastructure development are considered to be major factors in the failure to develop power
generating facilities as planned.
Therefore, it is considered necessary for the Energy Division and the Power Division to develop an
organizational structure and operating system more integrated than before. They must also make
concerted efforts to formulate a joint infrastructure development plan, to raise funds in the public-
private partnership and to develop infrastructure systematically in order to achieve a stable energy
supply, a source of future economic development.
Present a brief discussion on the EIA process and its role in the planning and
implementation of development projects;
Present a general description of the project and the process;
Present a description of the pre-project environment;
Delineate the significant environmental issues found and believed to be involved;
Assess the existing environmental conditions in the project area, including the identification
of environmentally sensitive issues;
Assess the proposed activities to identify their potential impacts, evaluate the impacts, and
determine their significance;
Suggest the plan for management of the environment, during the implementation and
operation of the plant.
Mitigation/
Predict Evaluate
Enhance Residual
Impacts
The key issues that will be identified during the scoping phase will be analyzed upon the baseline
information. Each issue consists of components that on their own or in combination with each other
give rise to potential impacts, either positive or negative, from the project onto the environment or
from the environment onto the project. In the ESIA study the significance of the potential impacts
will be considered before and after identified mitigation is implemented, for direct, indirect and
cumulative impacts, in the short and long term.
The following criteria will be used to evaluate Significance:
A) Nature: This is an assessment of the type of effect the activity is likely to have on the
surrounding affected environment. The description includes what is being affected and
its magnitude. The nature of the impact will be classified as positive or negative, and
direct or indirect.
Direct Potential/ possible Impacts will be generated directly from the project activities
and its associated facilities which is directly linked with the project. ( e.g. loss of
land due to project development or air emission from a power plant)
Indirect Potential/ possible Impacts will be generated from secondary sources which
are induced by the project activities. (e.g. loss of any species habitat due to the
project activities)
Induced Potential/ possible Impacts will be generated (which are not part of the Project)
due to effect /consequence/ outcome of the Project (e.g., influx of camp
followers resulting from the importation of a large Project workforce).
B) Extent and location: This indicates the spatial area that may be affected by the project
activities or its associated facilities.
Table 1-6: Impact Extent from the project location
Extent Description
Potential/ possible Impacts’ area only at or within the project site/ project boundary
Project Site
Potential/ possible Impacts’ area is not only limited to the site but also its immediate surrounding
Local
areas/ receptors.
Potential/ possible Impacts’ area extends to the immediate surrounding areas along with adjacent
Regional
areas
Impact considered of not only within national level but also neighboring country.
Trans
boundary Impact considered global level.
Medium term Potential/ possible Impact duration will continue after construction period but stop/
discontinue/cease within a tenure of 10 years
Long term Potential/ possible Impact duration will continue more than 10 years, or entire operational life of
project.
Permanent – Potential/ possible Impact will remain after operational life of project but appropriate mitigation
Mitigated measures reduce the impact
Permanent – no Potential/ possible Impact will remain after operational life of project.
mitigation
No mitigation measures will reduce impact after implementation.
D) Intensity/severity: This is the degree to which the project affects or changes the
environment; it includes a measure of the reversibility of impacts.
High Cultural and social functions and processes distorted/ disturbed/ impacted.
Potentially ceasing to Environmental function temporarily.
Negative impacts cannot be fully reversed.
Very high Natural, cultural and social functions and processes permanently cease, and valued,
important, sensitive or vulnerable systems or communities are substantially affected.
Negative impacts cannot be reversed.
E) Potential for irreplaceable loss of resources: This is the degree to which the project will
cause loss of resources that are irreplaceable.
Table 1-9: Potential for irreplaceable loss of resources
Potential for Description
irreplaceable loss of
resources
Irreplaceable/ unique resources can be replaced, with mitigation measure/ effort and will
Medium
be replaced after certain period of time.
F) Probability: This is the likelihood or the chances that the impact will occur
Table 1-10: Probability of Impact
Probability Description
Unlikely Under normal conditions, no Potential/ possible Impact expected.
Low The probability of the impact to occur is low due to its design or historic experience.
Positive
Insignificant
Low
Medium-low
Medium - high
High
Very High
In the case of a potential positive impact, no magnitude designation (aside from ‘positive’) is
assigned. It is considered sufficient for the purpose of the ESIA to indicate that the Project has the
potential to result in a potential positive impact, without characterizing the exact degree of positive
change that may occur.
H) Significance: The significance will be rated by combining the consequence of the impact
and the probability of occurrence (i.e. Magnitude x probability = significance).
Table 1-11: Significance
Probability of Impact
Item
Unlikely Low Medium High Definite
Insignificant Very Low Very Low Very Low Low Low
Magnitude of Impact
Medium
Very High Low High High Very High
Low
Potential social impacts are inherently variable because community response to a potential impact,
perceptions of existing and changing conditions, and the degrees of vulnerability are all heavily
dependent on local conditions and the human factor. The significance designations for potential
social impacts take into consideration social science expertise and previous experience in
Bangladesh regarding the relationships between individuals, communities, government agencies,
NGOs and special interest groups, and the oil and gas industry.
Table 1-13: Potential Social Impact Significance
Significance Definition
Positive Potential/ possible impacts that have a beneficial impact to affected
Impact stakeholders.
Very low Potential/ possible impacts that are practically indistinguishable from the social
baseline, with little to no potential impacts to or concerns from affected external
stakeholders.
To determine potential public health impacts, the assessment team considers the public which has
the potential to be exposed to various aspects and potential impacts of the project, whether it is a
permanent resident with continuous exposure or a periodic exposure to a fisherman transiting
through the project area. The significance determinations for potential public health impacts take
into consideration local and regional public health expertise and previous experience in Bangladesh
regarding the relationships between individuals, communities, health care providers, government
agencies, NGOs, and the oil and gas industry.
Table 1-14: Potential Public Health Impact Significance
Significance Definition
Positive Impact Potential that has a beneficial impact to affected stakeholder.
Very low No impact to the public
Potential/ possible illness or adverse effect with limited or no impacts on
Low
ability to function and medical treatment is limited or not necessary.
This chapter is designated to present details of potential impact characteristics of the proposed
power plant based on methodology developed by EQMS consulting Limited. Effective mitigation
measures are also recommended to attenuate the impact intensity. The following subsections will
describes details of impact assessment methodology, impact identification, impact types, sources,
significances and mitigation measures.
Source: EQMS
Delineate any specific baseline information required to be collected for the study area with
reference to the physical, biological and social components of the environment
Review analysis of alternatives available for site, resources, technology, building materials
etc.; and
Review project inbuilt mitigation measures available for potential adverse impacts.
Identification of the standard guidelines at regional and international level related to the
power plant setup.
Identifying and regulating all activities that pollute and destroy the environment;
Promoting active association, as far as possible, with all international initiatives related to
environment.
To conduct EIAs for all new public and private industrial developments;
To ban, or find environmentally sound alternatives for, the production of goods that cause
environmental pollution; and
To minimize waste and ensure sustainable use of resources by industry.
The policy also states that EIA's should conduct for any development activity and the DOE is
directed to review and approve all Environmental Impact Assessments.
All industries shall be subject to an EIA and the adoption of pollution prevention/ control
technologies shall be enforced;
Regulation with respect to vehicles emitting smoke harmful for the environment;
Regulation of development activities from environmental perspective;
Promulgation of standards for quality of air, water, noise, and soils for different areas and
for different purposes;
Promulgation of acceptable limits for discharging and emitting waste; and
The National Environmental Quality Standards (EQS) for ambient air, surface water,
groundwater, drinking water, industrial effluents, emissions, noise and vehicular exhaust;
Categorization of industries, development projects and other activities on the basis of actual
(for existing industries/development projects/activities) and anticipated (for proposed
industries/development projects/activities) pollution load;
Procedure for obtaining environmental clearance;
Requirements for undertaking IEE and EIA's as well as formulating EMP's according to
categories of industries/development projects/activities; and
Defining EIA procedures and issuing environmental clearance permits - the latter being
the legal requirement before the proposed Project can be implemented;
Providing advice or taking direct action to prevent degradation of the environment;
Pollution control, including the monitoring of effluent sources and ensuring mitigation
of environmental pollution;
Setting the Quality Standards for environmental parameters;
Convention Concerning the Protection of the World Cultural and natural 03.08.83 (accepted)
Heritage (Paris, 1972.)
03.11.83 (ratified)
Convention on International Trade in Endangered Species of Wild Fauna
18.02.82 (ratified)
and flora (Washington, 1973.) ("CITES convention")
United Nations Convention on the Law of the Sea (Montego Bay, 1982.) 10.12.82 (ratified)
Vienna Convention for the Protection of the Ozone Layer (Vienna, 1985.) 02.08.90(accessed)
31.10.90(entry into force)
Montreal Protocol on Substances that Deplete the Ozone Layer (Montreal 02.08.90
1987.)
31.10.90 (accessed) (entry into
force)
London Amendment to the Montreal Protocol on substances that Deplete
the Ozone Layer (London, 1990) 18.03.94(accessed)
16.06.94(entry into force)
Copenhagen Amendment to the Montreal protocol on Substances that 27.11.2000 (accepted)
Deplete the Ozone Layer, Copenhagen, 1992 26.2.2001 (entry into force)
Montreal Amendment of the Montreal Protocol on Substances that Deplete 27.7.2001 (Accepted)
the Ozone Layer, Montreal, 1997
26.10.2001 (Entry into force)
Basel Convention on the Control of Transboundary Movements of 01.04.93 (accessed)
Hazardous Wastes and Their Disposal (Basel, 1989.)
As the project has been categorized as Category ‘A’ with respect to environmental categorization,
the specific requirements of ADB are:
The provisions for the EMPs must also be fully reflected in the Project administration
memorandums; and
To ensure proper and timely implementation of the EMPs and adherence to the agreed
environmental covenants, ADB requires borrowers or executing agencies to submit semi-
annual reports on implementation of EMPs, and that this requirement will be reflected in
the loan agreements.
customary cultural, economic, social, or political institutions that are separate from those of
the dominant society and culture; and
an indigenous language, often different from the official language of the country or region.
The OP defines the process to be followed if the project affects the indigenous people.
There are no indigenous communities residing in the project area and therefore, no impacts on them
are expected under the project. Therefore, this OP is not triggered.
The Bank normally declines to finance projects that will significantly damage nonreplicable
cultural property, and will assist only those projects that are sited or designed so as to
prevent such damage.
The Bank will assist in the protection and enhancement of cultural properties
encountered in Bank-financed projects, rather than leaving that protection to chance.
In some cases, the project is best relocated in order that sites and structures can be
preserved, studied, and restored intact in situ. In other cases, structures can be
relocated, preserved, studied, and restored on alternate sites. Often, scientific study,
selective salvage, and museum preservation before destruction is all that is
necessary. Most such projects should include the training and strengthening of
institutions entrusted with safeguarding a nation’s cultural patrimony. Such activities
should be directly included in the scope of the project, rather than being postponed for some
possible future action, and the costs are to be internalized in computing overall project costs.
Deviations from this policy may be justified only where expected project benefits are
great, and the loss of or damage to cultural property is judged by competent
authorities to be unavoidable, minor, or otherwise acceptable. Specific details of the
justification should be discussed in project documents.
This policy pertains to any project in which the Bank is involved, irrespective of
whether the Bank is itself financing the part of the project that may affect cultural
property.
Displaced persons should be assisted in their efforts to improve their livelihoods and
standards of living or at least to restore them, in real terms, to pre-displacement levels or to
levels prevailing prior to the beginning of project implementation, whichever is higher.
The project will be developed on the purchased land. The land owner sold the land willingly and
they got the land value properly. Additional land requirement is not expected and hence this OP is
not triggered.
There are no particularly sensitive ecological, cultural and archeological sites in the area. The area
enjoys necessary infrastructure facilities, which include transport, electricity, telecommunication
etc. For all construction activities for the plant, the provisions of Bangladesh National Building
Code (BNBC) will be followed that include structural designs and seismicity tolerance. All the
relevant social and environmental risks and potential impacts will be taken due care of as part of
the assessment in compliance of the Performance Standards set by the World Bank besides
following the guidelines set forth by DoE. The basic data of the Desh Energy Chandpur Power
Company Limited are furnished in Table 3-1.
Table 3-1: Key Information of Proposed HFO based power plant at Chandpur
Company Name : Desh Energy Chandpur Power Company Limited
200 MW HFO Based Power Plant at Chandpur Sadar, Chandpur
Project Name : District, Bangladesh
Entrepreneur Name : Navidul Huq
Chandpur Sadar(on the southern bank of river Dakatia), Word No.-12,
Project Location : Gunrajdi, Chandpur, Bangladesh
GPS Location 23°13'30.22"N, 90°40'25.22"E
Level-15, Lotus Kamal Tower-1, 57 Joar Sahara C/A, Dhaka-1229,
Head Office :
Bangladesh
Nature of Business : Power Generation
Project Tenure : 15 years
Status of the Plant
Equipment : New Machine
Plant type : Reciprocating Engine based Power Project
Engine model : W18V50
Net Guaranteed Heat
Rate ( LHV) : 8300 KJ/KWh
Source of HFO : Imported
Desh Energy Chandpur Power Company Ltd. has purchased about 32 acre land at Gunrajdi Mouza,
Chandpur Sadar Upazila, Chandpur District. The land is fallen type and inundated most of time of
a year. Geographical location of the DECPCL project site is between 23°13'23.83"N to 23°13'35.95"N
latitude and 90°40'16.01"E to 90°40'28.72"E longitude. The location of the proposed power plant is
shown in Figure 3-1 . There is few scattered house hold within 150 meter radius from center of the
proposed power plant.
(1) Four main HFO storage tank, (2) one HSD storage tank, (3) Two HFO Buffer tanks, (4) one HFO
service tank (6) one fresh lube oil tank, (7) one used lube oil tank and (8) one service lube oil tank.
Switchyard:
Power evacuation corridor connecting to the nearest substations has been considered during the
preparation of the plant layout. The switchyard will contain two step-up transformers, breakers,
Administrative Building:
Location of the administrative building will be close to the main gate of the power plant.
Cogeneration unit
Cooling radiators and cooling tower
HFO treatment building
Fuel receiving facilities
Water treatment and waste water treatment building
Fire water pump house
Black start DG set room
Workshop
Warehouse
Security office building
The space requirement of these miscellaneous facilities, even though comparatively less when
compared with the area required for major facilities also needs consideration in deciding the
overall space requirement for the station.
Roads:
Approach road from the power plant to main road will be 6 meter wide and about 60 meter long.
All main roads in the power plant will be 6 meter wide.
Jetty:
There will be two temporary jetties on Dakatia River to carry construction materials and equipment
to the power plant during construction period. One permanent pontoon will be set up close to the
tank farm to transfer fuel from oil tanker to storage tank.
Other Facilities:
A training center will be set up in south west side of the project site close to the main gate. There are
two 4 storied dormitories, 4 residential quarters, a mosque, a school in the power plant area. There
will be a playground; a gymnasium and volleyball play ground in the premises. A Bungalow and a
helipad will be set up in the northern side of the project site.
Source: DECPCL
Length 18.781 M
Width 4.09 M
Height 6.02 M
Weight(dry) 368000 Kg
Weight (wet) 383000 Kg
The Wärtsilä 18V50 is a four stroke engine. The engine is designed for continuous operation on
Heavy fuel oil, and can be started and stopped on Heavy fuel oil if the fuel is heated to the
operating temperature. Light fuel oil is a back-up fuel.
Diesel process
The engine works according to the diesel process. In this process liquid fuel is injected into the
cylinder at high pressure by camshaft operated pumps. The fuel is ignited instantly due to the
high temperature resulting from the compression.
A2. Generator
The generator is of the synchronous, three-phase, brushless, salient pole type. The main data of
generator is given in Table 3-4.
1. Work safe and reliable. Boiler design is widely used vertical flue-type natural circulation
exhaust gas boiler, evaporative heating surface is designed according to the maximum flue
gas parameters, remaining enough allowance to ensure that the flue gas parameters to
ensure that the effects of the flue gas parameters fluctuations are accommodated
2. It adopts H-finned tube structure with expanded heating surface, small size and light
weight.
3. Strong mobility, this type of boiler is with small water capacity and fast start
4. Low operating costs. The exhaust gas boiler only has the feed water pump and no
combustion equipment, therefore the equipment work is reliable and the operation cost is
low.
5. Simple structure, easy manufacture, convenient installation.
6. Gas duct section shape is good. The boiler gas duct section length and width ratio is better
than the general exhaust gas boiler, flue gas fullness, boiler heat uniformity, thermal
deviation small, heating surface erosion complete, which are good for improving the boiler
heat transfer performance, work reliability and reducing the flue gas pressure drop.
7. Modular framework structure to make boiler installation easier and less cost on-site
installation.
8. Super-heater, evaporator, economizer and other major heat pipes of the exhaust gas boiler
are adopted H-finned tube as heat transfer enhancement components to enhance the heat
transfer effect.
9. Boiler wall with metal plate; seal joints of the manhole, wall tube (header) and guard plate
are full sealed design, to ensure that the exhaust gas boiler is not air leakage.
10. Select the appropriate flue gas flow rate, to solve fouling on heating surface of exhaust gas
boiler effectively.
Exhaust gas boiler system
The exhaust gas boiler is vertical and outdoor arrangement, and it is a modular structure, composed
of inlet smoke box, super-heater section, evaporator section, economizer section and an outlet
The steam turbine model is N3-1.27/300. This type turbine is the compound quick-assembling set,
single cylinder, LP impulse condensing turbine with the rated power of generator 3000KW. It has
the characteristics of strong packaged performance, small in volume, light in weight, and easy
transportation, which are based on the simple structure, high safety, convenient installation,
operation, disassembly and maintenance. Adapting to the compound quick-assembling, this turbine
satisfies the electricity use demand for forest cutting, mine exploring, military supplying and waste
heat utilization from the cement kiln, etc., especially suitable for the inland electric grid
construction. The turbo set can be operated as an isolated power station, or merged with grid
system. The turbine has the flexible rotor, with critical speed 3554r/min, and the rated speed is
5600r/m, decelerating to 3000r/m by the gear reducer, to driving the generator.
The turbine proper is arranged in a single floor, with the operating floor elevation at zero.
The total length of the turbo set is 4451mm, installed in the turbine house with the span of 10m.
Detail technical specification of the steam turbine is given in Annex-L
The other supporting machineries are HP Air Compressors, Charge Air Filters, Engine Hall
Ventilation Air Filters, Fuel Treatment Plant, Water Treatment Plant, Oily Water Treatment Plant,
Auxiliary Boiler, Auxiliary Diesel Generator etc.
Lighterage vessel having capacity of 800 MT HFO shall carry liquid fuel from Chittagong port to
Chandpur site storage tank.
After Commercial Operations Date the Company shall hand over the EIF except generator,
switchgear, unit transformer and its associated switchyard, metering and others equipment to
PGCB a no cost. Thereafter, the PGCB shall maintain and operate the EIF including replacement of
equipment (if required) throughout the Term at its own cost and responsibility. The power
evacuation route is shown in Figure 3-7.
There will be also a horizontal lube oil service tank and a cubic fire water tank (1800 M3) inside the
power plant. Detail design drawing of the power plant tanks are given in Annex O.
Time to time these accumulated water and sludge are to be drained out from the storage tank
using the drain valves provided for each fuel tank. Remaining suspended solid and water goes to
The centrifugal Heavy fuel oil separator units remove water and solids from the Heavy fuel
oil. The separator receives fuel from the buffer tank and sends clean fuel to the day tank. The
separators and auxiliary equipment are built on a steel frame, which forms a compact skid
unit. The Heavy fuel oil separator unit consists of the following equipment:
Water 12 m3/day Deep tube well Water 100 m3/hr Mostly River;
Ground water for potable
purpose only
Electricity 800 REB (Rural Electricity 6 MW/day From own source
KW/day Electric Board)/
National Grid line
HSD 5 HFO 2,78,208 Local/Imported
MT/Month
MT/year
3.4.3 Foundations
Foundations should be designed to British Standard Code of Practice BS 8004 or equivalent
Bangladesh National Building Code. The design of foundations for all structures and equipment are
to be such that differential and total settlements or other movements should not exceed acceptable
limits and ensure safe and maintenance-free operation of the plant.
Detail design parameters for the civil works would be provided by the relevant consultant. The
nature of the fill material and the construction techniques used should be such that the less heavily
loaded equipment and the buildings may be founded on rafts or spread footings.
3.4.4 Roads
The roads should be designed to be capable of carrying all the vehicles likely to be used during
construction and throughout the life of the plant including articulated vehicles and transporters
used for the removal and replacement of major items of the plant. Car parking and hard standing
areas should be of similar construction to the roads. The road pavements should be of reinforced
concrete and in conformity with relevant British or equivalent Bangladesh National Code of
Practice.
All waste drainage should be taken to a septic tank. A septic tank is a long retention time tank
where solids deposit out in an anaerobic bottom layer. A septic tank will be constructed for the
original power station. The Contractor shall satisfy himself that the capacity of the septic tank is
sufficient to cater for the additional load arising from the new power station. The septic tank should
3.4.7 Sub-station
Transformer compounds should be constructed with oil containment facilities. Compounds should
each be provided with suitable fencing and a lockable access gate. Fences to transformer
compounds and other electrical areas within the site boundary should be of 2.4 m minimum height.
The tank should be fitted with a suitable overflow system, air vents, access hatches, ladders, a sump
and a means of emptying the tank. DECPCL will evacuate power via LILO system to 132 kV
Chandpur-Chowmuhoni double circuit line.
Secondary Sources: This included data from literature reviews, maps and monitoring
reports;
Primary Sources: This included gathering information from field surveys, laboratory
analysis and public consultations in the project area.
The baseline condition of environmental quality in the locality of project site serves as the basis for
identification, prediction and evaluation of impacts. The baseline environmental quality is assessed
through field studies within the impact zone for various components of the environment, viz. air,
noise, water, land and socio-economic etc.
Data was collected from secondary sources for the macro-environmental setting like climate
(temperature, rainfall and humidity), physiography, geology etc. Firsthand information have been
collected to record the micro-environmental features within and adjacent to the project area.
Collection of primary information includes extrapolating environmental features on proposed
project design, location and measurement of socio-cultural features adjoining proposed project area.
Ambient air, noise and water quality samples were collected in terms of environment quality to
prepare a baseline database. Consultation was another source of information to explain local
environmental conditions, impacts and suggestions etc.
The following section describes the baseline environment into four broad categories:
Study area boundary of the proposed project was selected for the baseline studies;
The environmental and social field monitoring and survey was conducted during September
2017 to October 2017.
Social base line data collection through house-holds survey, FGD, Stakeholder meeting etc.
Ambient Air, surface and ground water, soil and sediment sample collection and
Laboratory analysis
Secondary data was collected from government reports, academic institutes, websites,
published literature, interactions with government department and stakeholders etc.
4.3 Area of Influence (AoI)
The Area of Influence (AoI) of the project comprises of the project site and the surrounding area,
where the influence of the project activities is anticipated. The areas likely to be affected by the
project and its associated activities include:
The project activities and facilities that are directly owned operated or managed by the
project proponent (including by contractors) and that are components of the project, such as
switchyard, control room and transmission line to power grid sub-stations;
Impacts from unplanned but predictable developments caused by the project that shall
occur later or at a related location such as increase in traffic on the approach road;
Impacts on biodiversity or on ecosystem services upon which affected communities’
livelihood are dependent;
Further to this, the AoI with respect to the environmental and social resources was considered
based on the following reach2 of impacts:
Air Quality
The areas immediately adjacent to the project footprint within which a zone of ecological
disturbance is created through increased dust, human presence and project related activities
(e.g., trampling, water intake/outfall, transportation). This kind of disturbance has been
estimated to occur within the project footprint and surrounding areas of about 500 m to 1
km from the activity areas.
Based on the above the AoI for environmental studies was limited to 5 km from the project site.
Socio-economic/Social
The AoI for social receptors was fixed to include 2 km radial zone which has been developed based
on the reconnaissance site visits and stakeholder consultations with the local community.
The base line map for the EIA study is shown in Figure 4-1.We have considered 5 km AOI for the
proposed power plant construction and operational activities.
Figure 4-2: Location of key feature around the proposed project site
23°13'39.76"N
2. Darjighat Madrasha and Mosque North-West 236 EHS
90°40'10.58"E
23°13'26.36"N
3. Institute of Marine Technology East 465 EHS
90°40'44.02"E
23°13'24.45"N
4. Baitun Noor Mosque, Gachtola East 392 EHS
90°40'40.87"E
23°13'13.51"N
6. Chandpur 132/33 kV substation South-West 442 EHS
90°40'4.46"E
23°13'20.45"N
7. Mosque at Char Gunrajdi South 120 EHS
90°40'23.46"E
23°13'37.94"N
8. Chandpur Water Treatment Plant North-East 602 EHS
90°40'45.50"E
Inside 23°13'25.82"N
10. Power Hook point South-East project EHS
90°40'28.72"E
boundery
Closest Residential area from the power plant Bridge over Dakatia River(Chandpur-Faridganj Road)
4.4.1.1 Temperature
The proposed project site is situated on flat land of South-eastern region of Bangladesh. During the
monsoon, the temperature varies between 26°C to 32°C. The temperature falls below 10°C in winter
which is spread over December and January and may well include November and February.
Monthly Maximum, Average and Minimum Temperature (°C) at Chandpur Station (1986-2016)
40
35
30
25
Temperature (°C)
20
15
10
5
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Maximum 24.54 28.25 31.98 32.30 33.41 32.50 31.70 31.98 32.08 31.78 29.66 26.20
Average 19.02 22.30 26.40 28.09 29.19 29.29 28.88 29.08 29.02 28.14 25.01 20.92
Minimum 13.50 16.35 20.82 23.88 24.98 26.08 26.06 26.19 25.96 24.50 20.37 15.64
85
Relative Humidity in %
80
75
70
65 JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Values 78.21 72.1 72.19 76.53 80.04 83.71 85.84 84.78 84.22 82 78.02 79.15
200
100
0
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Values 4.76129 21.5613 48.1613 100.135 251.148 325.619 411.452 324.645 285.2 175.045 43.9032 4.07419
4.4.2 Geology
The geology profile of Bangladesh is reflective of country’s location, as Bangladesh is riverine
country. The geological evolution of Bangladesh is related to the uplift of to the Himalayan
mountains and outbuilding of deltaic landmass by major River systems having their origin in the
uplifted Himalayas. This geology is mostly characterized by the rapid subsidence and filling of a
basin in which a huge thickness of deltaic sediments were deposited as a mega delta built out and
progressed towards the south. The floodplains of the Ganges, the Brahmaputra (Jamuna) and the
Meghna Rivers cover approximately 40% of Bangladesh.
The geology of Bangladesh can be divided into three distinct regions, each having distinguishing
characteristics of their own:
4.4.3 Topography
Most of Bangladesh is plain land except the hilly regions to the east and northest. The plain land
mainly consists of fluvio-deltaic sediments deposited by the Padma, the Bramaputra (currently
named as Jamuna) and the Meghna River systems. The elevation of the major part of the floodplain
ranges from 3 to 5 meters. As the floodplains approach the Himalayas from the northern part of the
Pabna District the elevation gradually increases.
A digital elevation model (DEM) or 3-D representation of the terrain surface of 10km study radius is
shown in Figure 4-12. The proposed power plant location, its 10-km buffer area as well as the other
linear features are shown in the Relief maps with the height range.
Contour of the study area are generated from the Advanced Space borne Thermal Emission and
Reflection Radiometer (ASTER) relief maps. Topo sheets were not available for the study area and
therefore all the relevant information is extracted from the Shuttle Radar Topography Mission
(SRTM) DEM only. All the processing was done in the ARC GIS 10.1 software.
4.4.4 Physiography
Physiography map of Bangladesh along with project site is shown in Figure 4-13. According to the
physiography of Bangladesh, the proposed project site falls under “Lower Meghna Floodplain”.
The project area of 10 km distance also falls in “Gangas Tidal Floodplain” and Old Meghna
Estuarine Floodplain.
Lower Meghna Floodplain:
Southward from Matlab, the Meghna Rivewr Floodplain comprises mixed alluvium from the
Ganges, young Brahmaputra (Dhaleswari, Sitalakya Channels) and Meghna Rivers. For a few
kilometers inland from the Meghna River, the materials are vary slightly calcareous because of the
admixture of calcareous Ganges alluvium. Further inland, the alluvium is not calcareous and may
have been deposited before the Ganges shifted into its present lower Meghna course in the 1840s.
The latter deposits are similar to old Meghna estuarine deposits, but the soils are younger and are
stratified at a shallow depth. This area is included in agro ecological Region 17.
Seasonal flooding formerly was mainly moderately deep over the whole area. In the south, flooding
depth fluctuated with the daily tides. Within the embanked Chandpur Irrigation Project area, most
Under natural conditions, this area was flooded at high tide, either throughout the year or during
the rainy season when rivers entering from the north brought in increased flows. Embankments,
especially in the southwest, have cut off this tidal flooding in places, but basin are flooded by
rainwater which accumulates in the monsoon season. The rivers are saline throughout the year in
the west. In the east, they carry fresh water to the coast during the rainy season, and only become
saline in their lower courses during the dry season. Most of the eastern half of the unit is non-saline
throughout the year, therefor. Tidal and seasonal flooding are mainly shallow, but basin centres in
the north are moderately deeply flooded in the monsoon season.
Old Meghna Estuarine Flood plain
This extensive subunit underlies agroecological Region 19. It occupies and almost level landscape of
smooth, broad ridges and basins which are underlain by deep silty deposits. In some basins, those
silts have been buried by a layer of clay which usually is less than 50 cm thick. This older floodplain
subunit differs from the younger subunits 12a and 12b in generally having deeply developed soils
with well oxidized subsoils, and in having non-calcareous sediments. Although non-calcareous, the
subsurface material generally is neutral to moderately alkaline in reaction. Slight topsoil salinity
occurs pathily in the dry season in some sites near the boundary with Saline Yound Meghna
Estuarine Floodplain.
Seasonal flooding is mainly by accumulated rainwater. It is moderattely deep or deep in the north
and west ( including the areas of the Middle and Lower Meghna River channels), but it is shallow in
the south-east. Only a few rivers such the Gumti, Dakatia and Little Feni cross the subunit ,
bordered by a narrow strip of their own, more variable, leass rectangualar network of
interconnecting man-made canals (khals) which serve both for drainage and for navigation.
However, silting up of the river channels and failure to maintain the khals has increased congestion
of drainage, and a lagre area in the south between Comilla, Hajiganj and Begumganj is now slow to
drain after heavy rainfall or flash floods from the adjoining hills, and remains wet for most or all of
the dry season. It seems probably that, unless artificial drainage is provided, this area will gradually
develop into an area like the Gopalganj-Khulna Bils and will eventually develop peat soils.
Dakatia River:
Dakatia River is one of the trans-boundary Rivers of Bangladesh. It enters the country from India's
Tripura state at Bagsara of Camilla district. It is a tributary of the Meghna. The main source of flow
In general, most of the soils within the country, particularly those found within alluvial floodplains,
share the following broad characteristics (Brammer, 1996 and Rashid, 1991):
Regarding soil formation, two distinct conditions occur in Bangladesh: alternating seasonal wet or
inundated and dry conditions, as prevalent on most of the floodplain areas and intermittently wet
or moist or dry conditions, as on the upland areas of hills and terraces. This is due to variation of
agro-climatic parameters in different seasons. The soil formation process differs significantly
between floodplain, hill and uplifted terrace. The project site falls under the floodplain ranges.
The SRDI has identified about 500 soil series in Bangladesh and FAO-UNDP has identified 21
different general soil types based on the diagnostic horizons and diagnostic properties of the soil
(FAO-UNDP, 1998). Bangladesh soil map with the project site is shown in Figure 4-15. The study
area can be classified as Calcareous Grey Floodplain soils which are described below.
They have grey matrix cambic B-horizon and lime in the profiles. They range from silt loam and
silty clay loam on riverbanks and floodplain ridges to silty clays in basins. Soils of this group mainly
occur on the Ganges tidal floodplain in the southwest, also minor areas on the river floodplain of
the Ganges and Lower Meghna. They are Calcaric Gleysols.
The project site is situated in Chandpur Sadar Upazila. The major soils are grey to olive, deep,
calcareous silt loam, and silty clay loams and stratified either throughout or at shallow depth.
Calcareous Alluvium and Noncalcareous Grey Floodplain soils are the dominant General Soil
Types. The soils in the south become saline in dry season. Top soils and sub-soils of the area are the
dominant General Soil Types which are slightly alkaline. General fertility is medium but low in
nitrogen and organic matter. Sulphur status is medium to high. It has predominantly deep silty
To study the land use/cover in the 10 km radius areas of the proposed DECPCL project site
and provide inputs for environmental planning of the proposed plant by analyzing the
existing land use/land cover scenario; and
To establish the existing base line scenario using a GIS database for incorporation of
thematic information on the different physical features including water bodies, settlements,
transport networks and administrative boundaries etc.
The evaluation of the existing environmental status of the study area was considered 0-10 km. This
revealed that the land use/land cover consists mainly of agricultural land, settlement with
homestead vegetation and water bodies. Table 4-2 describes the existing land use composition
around 10 km of the project study area.
Table 4-2: Existing Land Use Composition Around 10 km of the Project Study Area
Criteria 10 Km
Area (Acres) Percentage (%)
Agriculture 22025.08 27.31
Brick field 23.71 0.03
Industrial Area 18.14 0.02
Char land 4164.33 5.16
Urban Area 2205.01 2.73
Homestead Vegetation 31208.90 38.70
Water Body 20990.58 26.03
Total Area 80635.74 100
Source: Google earth image analysis
Figure 4-16 shows the Land use/Land cover map shows the land use pattern within 10 km of the
study area.
People become helpless. Fishermen are lost due to lack or absence or ignorance of weather forecast
and/or for not having lifesaving appliances. Number of cyclone shelters is also inadequate to
accommodate the affected people during cyclones. There is evidence that during 1770 till to date, at
least 25 major cyclones occurred in this belt damaging significant loss of life and properties. At least
70 major cyclones have hit the coastal belt of Bangladesh in the last 200 years. The Cox’s Bazar -
Chittagong coast is the most vulnerable and received 40 % of the cyclones during the last 35 years.
The cyclone affected area normally covers several hundred square kilometres. So, being adjacent to
There is major Cyclone has been reported in the project area in recent years or recent past. Cyclone
Strom Tracks area in Bangladesh have been shown in Figure 4-17.
Figure 4-17: Map showing cyclonic storm tracks of Bangladesh with project area
Table 4-3: List of Tornadoes had hit the project site and surroundings
Date Location
4.5.4 Floods
Figure 4-20 shows the flood affected areas of Bangladesh. Due to the geographical location of the
project area is not flood prone.
The landscape of Sadar has a combination of plain land, lower floodplains, rivers, canals and beels.
Due to huge sediment load from the upstream and river erosion, the river beds and canals of the
upazila are silted up gradually losing their navigation and drainage capacity. It is equally
responsible for losing the water holding capacity of the wetlands. So, during monsoon, when the
Meghna water exceeds the danger level due to excessive rain in the upstream, flood occurs in the
downstream shallow floodplains of the Chandpur District that includes Sadar Upazila. Flood is a
In the Chandpur- Faridganj road, (500 meter away from project area) total 7935 numbers of vehicles
were moving in 24 hours. During survey period no non-motorized vehicle on the road was
observed. Maximum traffic volume of 601 vehicles in an hour was recorded between 17:00-18:00
PM and minimum traffic volume of 94 vehicles in an hour was recorded between 3:00-4:00 AM.
Vehicular distribution on the road is shown in Figure 4-22.
Van/Pickup/Truck
12%
Motor Cycle Bus/Coach
21% 1%
CNG/Easy Bike
66%
Heavy, medium, light and small types of vehicles plying on the highway with a ratio of 1: 12: 66: 21.
Light nad small vehicles are dominating on the road.
404
323
289 296 298
225
192 156172
154 167 145167
124
94
7-8 AM
8-9 AM
6-7AM
1-2 AM
2-3 AM
3-4 AM
4-5 AM
5-6 AM
9-10 AM
10-11 AM
11-12 AM
00-01 AM
12-13 PM
13-14 PM
14-15 PM
15-16 PM
16-17 PM
17-18 PM
18-19 PM
19-20 PM
20-21 PM
21-22 PM
22-23 PM
23-00 PM
Source: Traffic Survey, conducted by EQMS Team, October 2017
The boat traffic survey was conducted continuously for 24 hours, one time during the study period.
The boat traffic survey was done for both way movement of vessels and categorized as fishing boat
(motorized), trawler (goods carrying), passenger service boat (large), fishing boat (Non- motorized).
Water vessels distribution on Dakatia River is given in Figure 4-24.
Trawler/Burge
73%
18 19 18
16 16 17 16 15 15
12 11 12 13
10 10 9 10
7 8 7
4 5
6-7AM
7-8 AM
8-9 AM
9-10 AM
10-11 AM
11-12 AM
12-13 PM
13-14 PM
14-15 PM
15-16 PM
16-17 PM
17-18 PM
18-19 PM
19-20 PM
20-21 PM
21-22 PM
22-23 PM
23-00 PM
00-01 AM
1-2 AM
2-3 AM
3-4 AM
4-5 AM
5-6 AM
Figure 4-25: Hourly vessels movement on Dakatia River, Chandpur
Methodology
The existing ambient air quality of the study area was monitored at four (4) locations during the
monitoring period (October 2017). The monitoring parameters included Particulate Matter (PM10
and PM2.5), Sulphur Dioxide (SO2), Oxides of Nitrogen (NOx), and Carbon Monoxide (CO). All the
parameters except CO were monitored on 24-hourly basis twice a week during the duration of the
study. CO was monitored as eight-hourly average.
The baseline status of the ambient air quality has been established through a scientifically designed
ambient air quality monitoring network. The ambient air quality monitoring locations were based
on the following aspects covered in field survey plan developed prior to the field work.
The particulate and gaseous samples collected during the monitoring have been analyzed as per the
procedures specified in Table 4-5.
5. CO Digital CO meter
Pictures taken during air quality monitoring are shown in Figure 4-27.
PM2.5
PM2.5 was monitored 24 hours two times. The maximum concentrations were 25.82, 19.42, 18.95
and 20.90 µg/m3 in the four locations respectively. All the results are within the 24-hourly National
Ambient Air Quality Standard (NAAQS) of Bangladesh.
PM10
Maximum PM10 levels in four monitoring locations were 58.65, 51.42, 48.12 and 42.85 respectively.
These values are within Bangladesh ambient air quality guideline value.
SO2
Average SO2 concentrations in the monitoring locations are 6.15, 7.08, 6.50 and 7.02 µg/m3
respectively .These concentrations are well below the national ambient SO 2 permissible limit for
Bangladesh.
NOx
Maximum NOx level found in the four locations are 18.91, 35.32, 18.45 and 16.17 µg/m3
respectively. DOE has set guideline value for ambient NOx level for annual averaging time. Annual
NOx standard is 100µg/m3 as per DOE. As per World Health Organization (WHO) the annual
permissible limit for NOx is 40µg/m3. The monitoring NOx levels are within these standard values.
CO
Monitoring level of CO in ambient air at four locations are less than 2 ppm which is well below the
national ambient air quality standard for CO.
The purpose of ambient noise level measurement was to determine sound intensity at the
monitoring locations. These locations are chosen in such a way that a representative data could be
recorded all over the project site. The sound level is recorded in form of A-weighted equivalent
continuous sound pressure level values (Leq) with the use of A-weighting filter in the noise
measuring instrument. Noise monitoring points are shown in Figure 4-26.
23°13'33.63"N
1.
NL1 Project Site
90°40'23.93"E Mixed
2.
In front of Dilo Tohsilder’s House Char
Gunrajdi Village. 23°13'30.32"N
NL2 Residential
90°40'31.41"E
23°13'26.41"N
3.
NL3 In front of Marine Academy
90°40'44.52"E Silent
4.
In front of Dulal Patwari’s house,
Gunrajdi 23°13'21.04"N
NL4 Residential
90°40'29.28"E
23°13'22.29"N
5.
NL5 In front of BPDB Power Plant
90°40'8.04"E Industrial
23°13'36.29"N
6.
NL6 In front of Gunrajdi Primary School
90°40'10.64"E Silent
23°13'40.73"N
7.
NL7 Beside Dorjibari Ghat Rail line
90°40'10.20"E Mixed
23°13'50.54"N
8.
NL8 In front of Chandpur Stadium
90°40'0.88"E Commercial
Pictures taken during noise monitoring in and around project site are shown in Figure 4-28
NL1 NL2
NL3 NL4
NL7 NL8
Figure 4-28: Pictures taken during noise monitoring in and around project site
Noise monitoring results are shown in Table 4-9 below.
Table 4-9: Noise Level Parameter in and around the Proposed Site
Location Average Noise level (dB(A)) Location Applicable World Bank
setting Standard * Standard**
(dB(A)) (dB(A))
The project area falls into industrial zone according to Bangladesh Environmental Quality Standard
ECR’97 categorization. Although NL3 and NL6 receptor point falls under silent zone criteria, noise
The samples were analyzed as per standard procedure/method given in Standard Method for
Examination of Water and Waste water Edition 20, published by APHA. Water quality parameters
are checked against Environment Conservation Rules (ECR), 1997-Schedule 3 (a) and ECR-
Shcedule-3 (b). Details of the analysis method and protocol are presented in Table 4-10.
The quality of surface water was compared with the standards for Inland Surface Water,
Environment Conservation Rules (ECR), 1997-Schedule 3 (a) whereas the groundwater was
compared with the Drinking Water Standard ECR-Schedule-3 (b), 1997. The standards have been
presented along with the monitoring results of surface and groundwater for comparison.
1 Surface Water
Collection at Upstream 23°13'38.67"N
SW1 10.12.2017 90°40'28.66"E
2 Surface Water River
Collection at 23°13'19.98"N
SW2 10.12.2017 90°40'18.62"E
Sampling locations of surface and ground water is shown in Figure 4-29 below.
Pictures taken during sampling and on field testing are shown in Figure 4-30.
Figure 4-30: Photographs taken during surface water sampling and on-site test
Analytical results from surface water sampling test are presented in Table 4-12 along with GoB
standards for surface water (ECR, 1997).
Table 4-12: Surface Water Quality of Dakatia River
Sl. No Parameters Unit Sampling Location
SW1 SW2
1 pH - 6.8 6.9
2 EC µmhos/ cm 120 110
Table 4-13 shows the standard values of some surface water quality parameters as per the ECR,
1997.
6 Water usable for irrigation 6.5 – 8.5 10 or less 5 or more 1000 or less
pH
pH level in the two surface water samples are found 6.8 and 6.9 which is within the standard value
as per ECR 1997.
Samples are collected from upstream and downstream of the Dakatia River. DO in SW1 and SW2
sampling points are 7.3 and 7.1 mg/l respectively. There is sufficient DO in the river for survival of
fish species.
The BOD concentrations of the surface water are less than 2mg/l. The values are within permissible
limit as per 1997 Bangladesh environmental conservation rules.
TSS found within the limiting value of Bangladesh surface water standard.
Pictures captured during ground water sampling and on field test are shown in Figure 4-31.
Figure 4-31: Photographs taken during ground water sampling and on-site test
Analytical results from groundwater sampling test are presented in Table 4-15 along with GoB
standards for drinking water (ECR, 1997).
Table 4-15: Ground water analysis result
Sl Parameters Unit Sampling code Bangladesh
No Standard*
GW1 GW2
1. pH - 6.58 6.52 6.5-8.5
2. Temperature °C 27.5 27.8 20-30 °C
3. Salinity ppt 0.06 0.03 -
4. Turbidity NTU 4.1 3.4 10
5. Chloride (Cl-) mg/l 163.68 145.37 150-600 mg/l
6. Iron (Fe) mg/l 3.42 5.35 0.3-1.0 mg/l
7. Chemical Organic Demand (COD) mg/l 2.6 2 4
8. Biological Oxygen Demand (BOD) mg/l < 0.2 < 0.2 0.2
9. Total Dissolved Solid(TDS) ppt 1.84 1.82 1
10. Total Suspended Solids (TSS) mg/l 18 15 -
11. EC µmhos/cm 367 240 -
12. DO mg/l 4.1 4.3 6
13. Total Coliform n/100 ml 0 0 0
14. Potassium mg/l 4 3.6 12
15. Phosphate mg/l 0.18 0.27 6.0
16. Nitrate mg/l 10 15.8 10
17. Nitrite mg/l 7 5 <1
18. Manganese(Mn) mg/l 0.19 0.21 0.1
19. Lead mg/l BDL BDL 0.05
20. Mercury mg/l BDL BDL 0.001
21. Cadmium mg/l 0.001 0.003 0.005
Source: DPHE and EQMS Laboratory Analysis and on field test data
*Environmental Conservation Rules 1997; SCHEDULE – 3; Standards for Water; (B) Standards for drinking water
pH
The pH of two samples is 6.58 and 6.52 which is within the Bangladesh standard range of 6.5 to 8.5.
The TDS concentrations of the samples are 1.84 and 1.82 ppt which is above the Bangladesh
Standard (ECR’97) 1 ppt.
The BOD concentrations of the surface water are less than 2mg/l. The values are within permissible
limit as per 1997 Bangladesh environmental conservation rules.
Both baseline soil and sediment qualities were observed to be well below the threshold limit
compared with the USEPA standard of heavy metal content in soil.
Enumeration of terrestrial and aquatic floral and faunal species within the study area.
Identification of floral and faunal species with conservational significance.
To develop the ecological mitigation and management plan.
The Primary data collection of different components of the study area conducted by using well
established and accepted ecological methods in the different habitats. Ecological surveys were
undertaken in September 2017 in the study area of Desh HFO power plant at Chandpur Sadar,
Chandpur. Quadrate sampling method has been used for the counting the vegetation structure in
and around the study area. A quadrat is a frame that is laid down to mark out a specific area of the
community to be sampled. Within the quadrat frame, the occurrence of plants is recorded using an
appropriate measure of abundance. The quadrat method can be used in virtually any vegetation
type to quantify the plant community. There were no any floral and faunal diversity inside the
project area that’s why the ecology team has been considered the 5km radius of the study area. A
total four quadrates study in all four directions from the project boundary has taken out of different
floral aspects. The ecology team has counted the different floral species in the study area. The
Quadrates study sites have been provided in the Table 4-20.
Table 4-20: Quadrates location
The field data collection was mainly included on biodiversity assessment of different life of floral
elements such as trees, shrubs, climbers, herbs and grasses.
Terrestrial Floral Analysis
In its adjoining area’s (study area) terrestrial flora were divided into three categories.
a. Agricultural or crop field vegetation
b. Homestead Plantation
a. Agricultural or crop field vegetation
Crop field vegetation is a major type vegetation of the study area. A big portion of crop fields is
inundated in rainy season. The most common agricultural crops cultivated in the study area are
Jute, Aus (Local), Aus (HYV), Broadcast Aman (Local), L.T. Aman, Aman (HYV), Local Boro, HYV
Boro, Hybrid Boro, Wheat, Maize, Cheena & Kaon, Lentil (Masur), Pea (Motor), Green Gram (Mug),
Black Gram (Mashkalai), Keshari, Sesame, Mustard, Groundnut, Soya bean, Chili, Onion, Garlic,
Turmeric, Ginger, Coriander, Sugarcane, Date-Palm, Cotton, Betelnut and so on. Local inhabitant
b. Homestead Plantation
A total of 34 homestead species of 21 Families were listed from the site. Majority of the family
belongs to the family of Arecaceae, Fabaceae and Myrtaceae. Moreover, among the resulted species
the Trees are 82%, Shrub 12%, Herb 3% and Grass 3%.
GrassHerbShrubTree
3% 3%
12%
82%
Common planted tree species are Aam (Mangifera indica), Supari (Areca catechu), Mehogani
(Swietenia mahagoni), Kola (Musa sp), Guava (Psidium guajava) etc. Raintree (Samanea saman), Narikel
(Cocos nucifera) and Supari (Areca catechu) occupied the top canopy. Homesteads are commonly
found near the plain land which favors healthy growth of the plant. Among the shrubs Lemon
(Citrus sp.) is the most common of all species. Homestead flora consists of both native and exotic
species (Acacia auriculiformis) and some of them are naturalized. Homestead plantation species are
listed in the Table 4-22.
A) Image view of block studied area B) Image view of grassland block studied area
7%
13%
13%
67%
Shannon's equitability (EH) can be calculated by dividing H by Hmax (here Hmax = lnS).
Equitability assumes a value between 0 and 1 with 1 being complete evenness.
On the diversity scale, biologically realistic H’ values range from 0 (only one species presents with
no uncertainty as to what species each individual will be) to about 4.5 (high uncertainty as species
are relatively evenly distributed). In theory, the H’ value can be much higher than 4.5, although
most real world estimates of H’ range from 1.5 to 3.5.
Birds
Amphibians and Reptiles
Mammals
Fisheries
4.8.4.1 Birds
The basic method has been chosen based on setting up a single line at each site called a “transect”.
The birds were identified either visually, by their calls or digitally recorded. This method involves
identifying all the birds; it has been seen or heard while standing at a series of points along a
transect (Straight line through the site). Bird’s counts were conducted at the early in the morning. It
is also time of maximum bird movement as birds through the bush to begin feeding. A systematic
search in the project impact area (over a fixed area and/ or for a fixed time) such as the method
specified here has been the added advantage of providing an index of the abundance of individuals
and species. Nesting also consider during the survey tenure in order identified the taxon. The
reliability of the abundance index can be reduced by either overestimates or underestimates of bird
numbers. To reduce overestimates, particularly when a member is observing, try to ensure that each
individual bird is recorded only once. Hence, ensure that a least one member of the team was
watching at all times. Focus Group Discussion (FGD) with local people (including villagers, school
teachers, Mosque Imam, help us to get information of the local species available in the study area.
3.5
3
2.5
2
1.5
1
0.5
0
The highest number of birds dominated in the site belonging to the family Sturnidae. However, the
birds belong to the family alcedenidae, columbidae, ardidae, corvidae and accipitaridae consist two
species among all. Homestead forest, grassland and bush, and some aquatic habitat of this site have
supported the wild birds for feeding and roosting.
All of the bird species at this were found to be Least Concern (LC) both locally and globally
according to IUCN Red List 2015. A detail about the bird’s species checklist has shown in Table 4-24
and the picture of the birds has been provided in Figure 4-39.
Table 4-24: Birds species counted in the study area
Sl. Common Local Name Scientific Family IUCN IUCN
No Name Name Global Local
Status Status
1. Black-rumped Sonali kaththokra Dinopium Picidae LC LC
Flameback benghalense
2. Common King Chhoto Alcedo atthis Alcedinidae LC LC
fisher Maachranga
3. White-throated Dhola gola Halcyon Alcedinidae LC LC
kingfisher Machranga smyrnensis
4. Rose-ringed Shobuj Tia Psittacula Psittacidae LC LC
Parakeet krameri
5. Blue Rock Gola Paira Columba livia Columbidae LC LC
pigeon
6. Spotted dove Tila Ghughu Streptopelia Columbidae LC LC
chinensis
7. Indian pond Kani Bok Ardeola grayii Ardidae LC LC
heron
8. Cattle egret Go Boga Bubulcus ibis Ardidae LC LC
9. Long-tailed Lenja Latora Lanius schach Lanidae LC LC
Shrike
10. House Crow Patikak Corvus Corvidae LC LC
4.8.4.4 Fisheries
Fish survey has been conducted based on discussion with the Fishermen and FGD at fish market,
discussion with local people and secondary information for fish species in the study area. It has
been considered different water body within the area. Total 28 fish species under eight families
have been found. Among all, fishes from the family Cyprinidae consist highest eight species. Fis
species found in the study area is presented in Table 4-27.
Table 4-27: List of fish species found in the study area
SL Local Name Common Name Scientific Name Family IUCN
Status*
1 Koi Climbing perch Anabus testudines Anabantidae LC
2 Choto Tengra Tengara Catfsh Mystus tengara Bagridae LC
3 Tengra Striped Dwarf Catfsh Mystus vittaus Bagridae LC
4 Aier Long-whiskered catfish Sperata aor Bagridae VU
5 Magur Walking Catfsh Clarias batrachus Clariidae LC
6 Mrigal Mrigal Carp Cirrhinus cirrhosus Cyprinidae NT
7 Jat Punti Spotfn Swamp Barb Puntius sophore Cyprinidae LC
8 Mola Mola Carplet Amblypharyngodon mola Cyprinidae LC
9 Bata Bata Labeo Labeo bata Cyprinidae LC
10 Rui Ruhu Labeo rohita Cyprinidae LC
According to the IUCN red list status 2015, it has been found that majority of the fish species at the
study area are least Concern (about 65%). Moreover, fishes are found to be Near Threatened,
Vulnerable, and endangered are almost same. But there is good news is that, there found no
critically endangered fish at the survey area.
Near
Least Threatened 12%
Concern 65%
a) Fishing equipment used at the study area b) Fishermen at the study area
4.9.3.1 Religion
As per the population and housing census 2011, the population of the study area dominated by the
Muslim community 92.43% in terms of faith. The second group goes to Hindu who is only 7.31%
and other groups (Christian and Buddhist) are very negligible in percentage. The following Figure
4-44 indicates the various religious profile of the study area.
100
Population %
80
60
40
0
Muslim Hindu ChristianBuddhist Others
Source: Population and Housing Census, 2011, Bangladesh Bureau of Statistics (BBS)
Source: Population and Housing Census, 2011, Bangladesh Bureau of Statistics (BBS)
Housing Structure(%)
1%
8%
13%
Pucka
Semi-pucka
Kutcha Jhupri
78%
Source: Population and Housing Census, 2011, Bangladesh Bureau of Statistics (BBS)
7%
91%
Source: Population and Housing Census, 2011, Bangladesh Bureau of Statistics (BBS)
13%
8%
79%
Source: Population and Housing Census, 2011, Bangladesh Bureau of Statistics (BBS)
4.9.6.2 Electricity
Electricity is an important indicator for measuring the quality of life in the Study area. In the study
area, 71.85% of the households have grid electricity connection. Table 4-32 shows the detail
electricity connection situation by union. However, households mostly use the electricity for
lighting and fanning purposes and some people for irrigation purpose.
4.9.6.3 Sanitation
In the study area, about 23.2% and 52.3% of households use water sealed and non-water-sealed
sanitary latrine facility respectively which represents the 75.5% households of the study area. About
22.2% households use non sanitary facilities. Only 2.4% households defecate in open places with no
access to hygienic latrine facility. Sanitation facility in the study is presented in Figure 4-49.
60
Households %
40
52.3
20
23.2 22.2
2.4
0
Sanitary (water-sealed) Non-sanitary
Sanitation Type
Source: Population and Housing Census, 2011, Bangladesh Bureau of Statistics (BBS)
Figure 4-49: Sanitation Facility in the study area
Pre-Construction
Construction
Operation
Impacts are identified and predicted based on the analysis of the information collected from the
following:
Project information;
Baseline information.
The identification of likely impacts during construction and operation phases has been carried out
based on likely activities having their impact on environmental and socio-economic parameters.
The details of the activities and their impacts have been worked out in the following sections. The
next section discusses in detail the impact assessment methodology adopted as part of EIA process
for the proposed Power Plant Project.
The interaction matrix enables a methodical identification of the potential interactions each Project
activity may have on the range of resources/ receptors within the Area of Influence i.e. the study
area for the Project. An activity-impact interaction matrix for pre-construction, construction and
operation phase is presented in Table 5-1.
Population Displacement
Economy and Livelihood
Vulnerable Group
Sediment Quality
Potential Impacts/
Drainage Pattern
Aquatic Ecology
Climate Change
GHG Emission
Vibration level
Social Conflict
Risks Activity
Employment
River Traffic
Road Traffic
Noise Level
Soil quality
Air Quality
Landscape
Structure
Land use
Impact
Safety
safety
Pre-Construction & Construction Phase
Land Purchase/
Acquisition
Site Clearing
Filling of land
Building of structures
including temporary
structures
Heavy equipment
operations
Storage, handling and
disposal of waste
Generation of sewage
and discharge
Construction of
transmission line
Construction of
Temporary Jetty
Influx of construction
workers
Concreting work
Transportation of
manpower, equipment &
materials by road
Population Displacement
Economy and Livelihood
Vulnerable Group
Potential Impacts/
Sediment Quality
Drainage Pattern
Aquatic Ecology
Climate Change
GHG Emission
Vibration level
Social Conflict
Risks Activity
Employment
River Traffic
Road Traffic
Noise Level
Soil quality
Air Quality
Landscape
Structure
Land use
Impact
Safety
safety
Storage and handling of
chemicals (unplanned
release)
Operation Phase
Air Emission from
stacks of the power
plant
Noise generation due
to operation of plant
and auxiliaries
Water demand for
plant operation
Wastewater
discharge/disposal
Hazardous material
and waste storage
Construction of
pontoon
Storages of
flammables
HFO transportation
Job facilities
Sources of impact:
Soil will be compacted during the establishment of laydown areas, internal roads and
installation of equipment to ensure stability
Movement of heavy vehicles and heavy construction machinery will also cause soil
compaction
Impact Significance:
Soil compaction and possible damage to the soil structure due to heavy vehicular movement will
only be limited to the vicinity project site. Based on the impact assessment matrix given below the
impact was assessed as low.
Impact Impact on soil due to compaction
Impact Nature Direct Indirect Induced
Impact Scale within project site and near site boundary area
Sources of Impacts:
Soil contamination during the construction phase may result from leakage and spillage of
oil, lubricants, fuel from heavy equipment or leakage from chemical/fuel storage.
Transportation of construction material, equipment and personnel;
Storage of construction materials including hazardous material;
Hazardous materials and waste disposing;
Civil work activities;
Erection of construction yards;
Impact Significance:
The waste both solid and small quantity of hazardous waste generated from the proposed project
will be handled as per the GOB ECR 1997 guideline. Liquid effluents arising from construction
activities will be treated to the standards specified in Schedule 9 and 10 of ECR, 1997 of the GOB and
the applicable International guidelines prior to discharge. Therefore, the likelihood of unplanned
events leading to soil contamination is possible but low. Based on the matrix the impact has been
considered as low.
Probability of
Unlikely Low Medium High Definite
Impact
Medium- Very
Very low Low Medium-high High
Impact Significance Low High
Mitigation Measures:
A site specific Emergency Response Plan will be prepared by the Contractor for soil clean-up
and decontamination;
Design processes to prevent/minimize quantities of wastes generated and hazards
associated with the waste generated;
Minimize the production of waste materials by 3R (Reduce, Recycle and Reuse) approach;
Leaching from the sediments should be contained to seep into the subsoil or should be
discharged into settling lagoons before final disposal;
Training labourers for waste disposal in designated areas and use of sanitation facilities;
The storage areas of oil, fuel and chemicals will be surrounded by bunds or other
containment device to prevent spilled chemicals from percolating into the ground or
reaching the receiving waters;
Proper storage of the construction materials and wastes to minimize the potential damage or
contamination of the materials; and
Fuel tanks and chemical storage areas will be sited on concrete platform and provided with
locks to prevent unauthorized entry.
With implementation of mitigation measures the impact will be very low.
Earthworks in the Project area may increase the erosion, especially during rainfall events,
which may increase the suspended sediment concentrations and pollute water sources.
Similar impacts are possible from construction of the floating jetty at Dakatia River for
receiving construction materials and equipment;
Wastewater generated from washing of equipment and machinery on site.
Surface water runoff from construction site
Generation and disposal of domestic waste water from construction camp
Pilling activities
Use of poisonous chemicals.
Discharge of hydro-testing water.
Impact Significance:
The wastewater may contain suspended solids and trace amount of HFO. The contractor will be
responsible for ensuring that any wastewater discharged meets the standards stipulated in Schedule
10 of ECR, 1997 and the applicable World Bank/IFC General EHS Guidelines prior to discharge of such
wastewater. Sanitary facilities including toilets will be provided for the use of the construction
workforce both on-site and at the workers’ accommodation. Such sewage streams are likely to be
high in organic matter, suspended solids, coliform and other Pollutants. Septic tanks will be
provided to treat sanitary wastewater. Potential impacts are expected to be short-term and localized
in nature. A potential impact on surface water is low.
The spillage and seepage of chemical, oil and lubricants from storage area, waste handling
area and generation of domestic waste/wastewater from construction labour camp area may
adversely affect ground water quality in the area.
Liquid effluents will be generated from washing of construction equipment and vehicles
Impact Significance:
The existing groundwater quality analysis around project does not reveal any existing
contamination or pollution. Groundwater contamination during the construction phase may occur
from unplanned events such as leaks and spills of oil, lubricants, fuel from heavy equipment,
improper handling of sewage or chemical/fuel storage. Mitigation measures such as storage of
chemicals at concretedlay down areas will be implemented to minimize contamination in the event
of a spill. Septic tanks will be provided to treat sanitary wastewater. As stated above, all wastewater
discharges will meet the standards stipulated in Schedule 9 and 10 of ECR, 1997 and the applicable
World Bank/IFC General EHS Guidelines prior to discharge. While there is a potential for long-term
direct impacts to groundwater quality from construction, with the implementation of mitigation
Mitigation Measure:
The following measures can be taken to minimize impact on ground water during construction
phase
Dust generated from stockpiles of materials, waste, loose earth, handling and moving
excavated material and transporting wastes on vehicles.
Potential for
irreplaceable loss of Low Medium High
resources
Insignific
Magnitude Low Medium-low Medium - high High Very High
ant
Implementation of a regular watering and sprinkling dust suppression regime, during the
dry season;
Concrete batching plant will be located within the Protected site to keep it away from
sensitive receptors;
Restricting heights from which materials are dropped as far as practicable, to minimize the
fugitive dust arising from unloading/loading;
Stockpiles will be maintained at site only, which is a fenced area. No stockpiles will
maintained outside, and maximum Possible distance between the stockpiles and receptors
will be maintained;
Use effective dust suppression techniques, such as on-site watering and street cleaning;
Water the material stockpiles, access roads and bare soils on an as required basis to
minimize the potential for environmental nuisance due to dust;
Effective water sprays should be used to control potential dust emission sources;
Cover haul vehicles carrying dusty materials moving outside the construction site;
All diesel-powered equipment will be regularly maintained and idling time reduced to
minimize emissions;
Establish adequate locations for storage, mixing and loading of construction materials, in a
way that dust dispersion is prevented because of such operations;
Dusty activities should be re-scheduled where possible if high-wind conditions are
encountered;
Crushing of rocky and aggregate materials shall be wet-crushed, or performed with particle
emission control systems.
The movement of construction vehicles will be minimized and a 20 km/hr speed limit will
be enforced around the construction site,
Low sulphur diesel (S<O.5%) will be used in diesel powered equipment in collaboration
with best management practices;
The impact of air will have low intensity with locally extent for a short term duration which will
result in an overall low impact without mitigation. However, with proper implementation of
suggested mitigation the impact will be reduced to very low.
The potential sources of noise during the construction phase of the Project include equipment,
machinery and transportation used for the construction activities. The heavy equipment used for
The nearest settlement is located adjacent to the south-western and south-eastern boundary. The
household is located within the 100 m of the project area and also closest to access road as a result
they will be affected due to construction work and movement of vehicle.
Construction traffic is expected to be generated throughout the entire construction period; however
the volume and type of traffic generated will depend on construction activities being conducted
which will vary during the construction period. There is potential for disturbance to habitations in
proximity of construction site. Movement of traffic during night hours can also disturb the local
community. So the impact on ambient noise due to the project activities during the construction
phase has been assessed as Medium-Low.
Mitigation measures
Noise level shall be minimized as follows:
Normal working hours of the contractor will be between 06:00 and 21:00 hours. If work
needs to be undertaken outside these hours, it should be limited to activities that do not
exceed the noise criteria at nearby noise sensitive receptors;
Machinery and construction plant that may be in intermittent use (e.g. trucks) shall be shut
down or throttled down during non-work periods;
Equipment known to emit noise strongly in one direction should be orientated so that the
noise is directed away from nearby NSRs as far as practicable;
Noisy plant (such as breakers and rollers) shall be located as far away from receptors as
practicable.
The contractor should consider the noise emission characteristics of equipment when
selecting equipment for the project and select the least noisy machine available to perform
the specific work (this is a requirement of OSHA 2007);
Mobile noise sources such as cranes, earth moving equipment shall be routed in such a way
that there is minimum disturbance to receptors;
Developer shall instruct their Safety Officers to arrange for inherently quiet construction
equipment and machines to maintain the noise level to minimum;
Restrict the night time vehicle movement through the access road;
Adopt the vehicle speed (20 km/hr) limit in the access road
Temporary noise barriers shall be provided surrounding the high noise generating
construction equipment;
The personnel involved in high noise generating activities shall be provided with personal
protective devices to minimize their exposure to high noise levels;
Construction vehicles and machinery will be well maintained and not kept idling when not
in use;
The impact of noise level will have medium intensity with locally extent for a short term duration
which will result in an overall medium- low impact without mitigation. However, with proper
implementation of suggested mitigation the impact will be reduced to low.
Clearance of vegetation at the temporary jetty location for unloading the heavy equipment
and clearance of vegetation in the transportation routes to the project site.
Impact Significance
Project site was previously agricultural land. There were no trees on the site. . There is no significant
plant species found in the project site according to the IUCN red list status 2015. Small species like
frog, rat, odonate, butterfly etc, are observed in and around the project site. These species are
moving from project site to other places during construction phases. Noise and dust during
construction activities can be harmful for the local terrestrial ecology. Significance of Impact
calculated as very low.
Impact Impact on Terrestrial Ecosystem
Impact Nature Direct Indirect Induced
Impact Scale Within the project site
Frequency Limited to construction Phase
Extent and location Project Site Local Regional National Trans boundary
Medium- Medium -
Magnitude Insignificant Low High Very High
low high
Medium- Medium-
Very low Low High Very High
Impact Significance Low high
The noise generating activities should be schedule during day time only.
Tree species which are present edge of the project boundary should keep remain alive;
Plantation of local species for stabilization of the filled in material and plantation in
surrounding areas;
B. Impact on Aquatic Ecosystem
Sources of Impact
Medium- Medium-
Very low Low High Very High
Impact Significance Low high
Significance of impact is considered as Very Low
Mitigation measures
The following mitigation measures should be taken to minimize impact on aquatic ecosystem.
Avoidance of any leakage of fuels and other contaminants from barges/trawlers to Dakatia
River;
Trawlers/barges with valid requisite licenses and emergency handling capacity or tie-ups
shall only be engaged; and
Standard codes and practices to be followed during unloading of fuels and construction
material.
Proper maintenance for avoidance of any leakage of fuels and other contaminants from
barges/trawlers to the Dakatia River;
Impact on aquatic habitat due to construction of temporary Jetty
The requirement for a jetty is primarily for receiving the heavy equipment (engine, Transformer,
construction materials etc.), which could not be able to transport by road. Jetty construction needs
limited scale dragging which may impact on aquatic Habitat. The impact significance on aquatic
habitat due to construction of jetty is calculated as low.
Probability of
Unlikely Low Medium High Definite
Impact
Very
Impact Very low Low Medium-Low Medium-high High
High
Significance
Significance of impact is considered as low
Mitigation Measures
Construction workers will be given conservation and awareness training to promote
sustainable resource use.
Vegetation clearing will be kept to the minimum extent practicable for the temporary jetty
construction
There is very low impact on the road traffic during construction period of the power plant. The
Chandpur-Faridganj main road is about 500 meter away from the project site and there is no
suitable link road between the project site and the main road. The proponent has no other option
except use River Dakatia to carry construction materials and equipment in the project site. There is
no impact on existing road traffic in the study area during construction period.
Mitigation Measures
The following steps should be taken to minimize impact due to increasing river traffic.
Proper signalling light on the vessel at night time to avoid collision
Barge and vessels should be anchored close to the bank so that they will not impede normal
boat movement
Vessel movement should not hamper fish cultivation activities in Dakatia River.
A 24 hours river traffic management plan
During the construction phase of the project the main sources of impacts on community health and
safety are:
Construction sites are a health and safety nightmare – almost every conceivable hazard exists
within this constantly changing working environment. Unsatisfactory architectural and/or
organizational options or poor planning of the works at the project preparation stage have played a
role in more than half of the occupational accidents occurring on construction sites in the
Community. Community has risks to transmission of sexually transmission diseases due to
interaction with workers and the local community. Activities in construction activities pose low
impact on community health and safety.
Medium- Medium -
Magnitude Insignificant Low High Very High
low high
Mitigation Measures
Medium -
Magnitude Insignificant Low Medium-low High Very High
high
Mitigation Measures
The following mitigation measures should be taken to minimize impact on occupational health and
safety.
The Contractor will prepare and implement a Health and Safety Plan prior to commencing
work. This plan will include method statements for working methods, construction
sequence and safety arrangements;
Measures will be implemented to reduce the likelihood and consequence of the following
hazards:
o falling from height;
o falling into water;
o entanglement with machinery;
A. Impact on Employment
An extensive number of un-skilled and semi-skilled contractual labour will work during the
construction phase in the project. Also a large number of female workers will get opportunity to
Local enterprises, particularly those involved in the production and sale of construction materials,
material suppliers are potential benefactors of the civil works involved in the project. Local market,
business man and shop owners will also be benefited from the construction activity as a
considerable number of man power will engage this project. The significance of the benefit to local
enterprises is shown in the following table.
Medium-
Very low Low Medium-high High Very High
Impact Significance Low
Significance of impact is considered as low
Mitigation Measures
The following mitigation measures are proposed to avoid impact due to labor influx:
Proper disposal of wastes generated from the camp and construction activity to maintain
general hygiene in the area;
It is planned that hazardous wastes generated from the proposed Project will be collected and
stored in designated roofed-areas and/or barrels with concrete flooring and secondary containment
and disposed of/ sold through contractors or treated prior to discharge.
Mitigation Measures
In addition to the proper collection, storage and disposal options the following steps will be taken
further to manage hazardous wastes:
Wastes will be stored in a manner that will prevent contact between incompatible wastes i.e.
post compatibility checks,
Proper labeling of hazardous wastes;
Special care will be taken in the storage areas to prevent any spillage of hazardous wastes
and restrict access (except for trained staff) to such areas;
Periodic audits will be carried out for such areas and containers; also on the segregation and
collection systems and the findings will be documented and appropriate action taken
against irregularities;
A spill response plan and emergency plan will be prepared to address accidental spillages or
release of hazardous wastes; and
A proper manifest record will be maintained of waste travelling/ removed from the site.
With proper waste management the impact will be very low.
The discharge of effluent and sewage from the operational plant that may have an impact on
the quality of surface water;
Spillage from HFO containing cargos
Spillage of Chemicals
The abstraction of ground water for plant operation and drinking purposes for the
employees of the power plant.
A. Impact due to Groundwater Abstraction
The power plant will utilize River water for the power plant operation. Only drinking water will be
abstracted from ground. This requirement of groundwater is insignificant to have any kind of
impact on the groundwater table. The overall significance is therefore assessed as very low.
Impact Impact due to ground water abstraction
Impact Nature Direct Indirect Induced
Impact Scale Within the project site
Frequency limited to start-up phase
Extent and location Project Site Local Regional National Trans boundary
Medium Permanent – no
Impact Duration Short Term Long-term Permanent – Mitigated
Term mitigation
Impact Intensity/
Insignificant Low Medium High Very High
severity
Potential for
irreplaceable loss of Low Medium High
resources
Probability of
Unlikely Low Medium High Definite
Impact
Impact Significance
No effluent will be discharged from the power plant. Spillage of oil and lubricant during plant
operation has very small impact on surface and ground water in and around the power plant. The
significance of impact is calculated as very low.
Extent and location Project Site Local Regional National Trans boundary
Medium Permanent – Permanent – no
Impact Duration Short Term Long-term
Term Mitigated mitigation
Impact Intensity/ severity Insignificant Low Medium High Very High
Potential for irreplaceable
Low Medium High
loss of resources
Medium-
Magnitude Insignificant Low Medium - high High Very High
low
Mitigation Measures
Some mitigation measure needs to be implemented to keep the impact at minimum level
Leak proof oil transfer mechanism from oil tanker to oil storage tank
Sanitary effluent should deposit in septic tank
Liquid wastes such as waste oil, etc. will be collected and stored for recycling in cemented
areas; and
All drainage/tanks, etc. will be positioned on concrete hard standing to prevent any seepage
into ground.
Storm water drainage and waste water of similar nature from different
units will be treated in accordance to GOB Environment Conservation Rule
(1997) Schedule 10 (Standards for Waste from Industrial Units or Project Waste)
and the applicable World Bank Group environmental requirements and
World Bank/IFC guidelines
During operation stage main source of air pollution is engine exhaust gas. The rate of
emission is 110, 089 kg/hr (dry basis) per stack.
Emission from oil carrier fuel vessels
Types of air pollutants
Meteorological Data: The input meteorological data for the AERMOD was generated using the
MM5 model, which was downscaled to fine grid data suitable for modelling. The data used in the
study was site specific and was collected over a one year period (2016). In all there were 8760 hours
of meteorological data used in the model. This quantity of data allows an adequate assessment of
hourly, 8-hourly, daily and annual average pollutant concentrations around the Project site.
Terrain Data: Terrain data for the AERMAP model were taken from the 90 m SRTM database, while
land cover data was sourced from satellite imagery of the Project site and its surroundings.
Receptors locations are shown in Table 5-2.
Table 5-2: Receptor Location with Respect to the Project
Sl. Location Station Geographic Elevation Distance Direction from
Code Location* (m) from center plant center
(m)
1. Inside project side AQ1 24°46'3.98"N 5 130 N
89°20'49.58"E
2. In Front of BPDB AQ2 24°46'12.89"N 11 710 W
150 MW Combined 89°20'51.11"E
Cycle Power Plant
3. Besides Chandpur- AQ3 24°46'9.96"N 8 1000 NE
Faridganj Road 89°20'41.09"E
From the model prediction it is observed that ground level NOx at some receptors point will be
increased in comparison to existing 24 hr average level. However, the NOx level at the receptor
point will be within permissible limit set by DoE. 24 hour Max and annual average SO2
concentration at ground level receptors are presented in Table 5-4.
Table 5-4: Predicted SO2 concentration in the receptor point
Predicted SO2 level Bangladesh Standard 1 (µg/m3)
Baseline SO2 level
Receptor ( 24 hr average) Averaging period Averaging period
(µg/m3) 24 hour Annual 24 hour Annual
AQ1 6.15 203.83 16.66
AQ2 7.08 212.58 30.14
365 80
AQ3 6.50 222.17 30.59
AQ4 7.02 281.47 26.17
1 The Bangladesh National Ambient Air Quality Standards have been taken from the Environmental Conservation Rules, 1997 which was
amended on 19July 2005 vide S.R.O. No. 220-Law/2005.
Present SO2 status at the receptors will be drastically increased due to the operation of the power
plant. However, the predicted SO2 level value is below Bangladesh Air Quality standard for SO 2
which is set as 80 for a µg/m3 for annual average and 365 µg/m3 for daily average. AERMOD
model has been run for 1 hour, 24 hour and annual average time for the power plant NOx and SO 2
emission. The generated contour maps from the model output are given in Annex-K.
Predicted maximum NOx and SO2 concentration in various distances from the power plant due to
operation of the power plant is given in Table 5-5.
Table 5-5: Maximum NOx and SO2 concentration in various distances from the power plant
Feature Name of the Averaging Distance from the Power plant stack ( meter)
component time 200 400 600 800 1000
Ground level NOx (µg/m3) Annual 20 36 61 53 48
concentration
SO2 24 hour 200 256 341 360 327
(µg/m3)
(µg/m3) Annual 17 39 58 40 32
Source: AERMOD model dispersion modeling analysis
Mitigation Measures
The following mitigation measures should be taken to control air quality around the project site
Fuel should have low sulfur content
Ensure excess oxygen to ensure complete combustion in the engine
Green belt development around the project site
Air quality monitoring
Maintain equipment and engine regularly
Sufficient stack height to disperse air pollutant above the local area
Based on the HFO requirement for the proposed project, it is anticipated that the annual GHG
emission from the plant will be 8, 72,744 (tCO2e/year). It is evident from
Table 5-6 that the estimated GHG emissions from the power plant while using HFO as primary fuel
will exceed the threshold of both ADB SPS (100,000 tons CO 2e per year) and IFC PS3 (25,000 tons
CO2e per year) that define them as significant GHG emission sources. Therefore, the Project is
required to report annual GHG emissions. Considering this fact, the GHG emission impact will be
medium low.
3 Source: Intergovernmental Panel on Climate Change (IPCC) (1995), Second Assessment Report
4 http://www.ifc.org/wps/wcm/connect/Topics_Ext_Content/IFC_External_Corporate_Site/CB_Home/Measuring+Reporting/
Mitigation Measures
The following mitigation measures will minimise GHG emissions to ALARP levels:
Continuous monitoring and recording of CO2 emission from the stacks through CEMS.
Ensure that all equipment and machinery is maintained in accordance with manufacturer’s
specifications; and
Improved efficiency of auxiliary drives.
Major sources of noise during operation of the proposed power plant are:
Ministry of Environment, Bangladesh has set standard for noise level for different area of use. Noise
standard as per Bangladesh Noise Control Act 2006 is presented in Table 5-7.
1 Silent zone 50 40
2 Residential Area 55 45
3 Mixed zone 60 50
4 Commercial Area 70 60
5 Industrial Area 75 70
1Daytime is defined as the period 6.00am-9.00 pm and night-time is defined as the period 9.00pm-6.00am.
International Finance Corporation (IFC) has also set EHS guidelines for ambient noise level. EHS
noise guidelines of IFC are given Table 5-8 below.
Industrial; commercial 70 70
Prediction of Impacts
Methodology:
The environmental noise prediction model Sound PLAN 7.4 was used for modeling noise emissions
from the power plant operation. The major noise sources are Engines, Charge air Intake, Exhaust
gas outlet, CO generator turbine, cooling radiator fan. Noise generated from these sources is given
in Table 5-9 below.
Table 5-9: Noise generated from major sources at DECPCL power plant
Source Noise Level dB(A) Noise Attenuation using Net noise intensity
insulation and silencers dB(A)
Engine 110 30 80
Charge air Intake 120 40 80
Exhaust gas outlet 123 25 90
CO generator turbine 95 35 60
Day time Night time
Radiator fans 70 65
Noise escape from the engine hall is 80 dB(A), from co-generator turbine noise release 60 dB(A).
Noise generated in charge air intake is 80 dB(A) and exhaust gas out let is 90 dB(A). We have
assumed radiator fan speed is decreased by 20% during night time and noise generation from fan
Extent and location Project Site Local Regional National Trans boundary
Medium Permanent – Permanent – no
Impact Duration Short Term Long-term
Term Mitigated mitigation
Impact Intensity/ severity Insignificant Low Medium High Very High
Potential for irreplaceable
Low Medium High
loss of resources
Mitigation Measures:
Noise level in the proposed power plant can be controlled to a tolerable limit by implementing
following mitigation measures:
Install noise attenuation provisions such as air intake silencers and acoustic insulation
around noisy equipment
Comply with the noise emission criteria as per the Schedule 4 of ECR 1997; Noise Pollution
(Control) Rules, 2006
Monitor ambient noise levels in and around the Project site as per the
Environment Monitoring Program formulated for the project which will comply with
National Regulatory requirements.
Selection of equipment with lower sound power levels (< 85 dB);
Buildings will be designed with improved acoustic performance and sound insulation will
be provided;
Installation of acoustic barriers without gaps and with a continuous
minimum surface density in order to minimize the transmission of sound through the
barriers.
Installation of vibration isolation for mechanical equipment
Green belt development
Avoid the unnecessary use of alarms, horns and sirens
With proper mitigation measures impact will be very low
Source of Impact
Mitigation Measures
The mitigation measures are as follows
Source of Impact
The impact extent is local as the as the impacts are likely to happen near the project footprint. The
impact duration in long term, impact scale will be medium as the impact will be reversible and
likely to have minor change over baseline in due course of time. Impact magnitude thus assessed is
low. Based on the table below the impact on aquatic habitat is assed as low.
Impact Impact on aquatic ecosystem due to operation of the powe plant
Impact Nature Direct Indirect Induced
Impact Scale In and around project site
Frequency Limited to operation Phase
Extent and location Project Site Local Regional National Trans boundary
Medium Permanent – Permanent – no
Impact Duration Short Term Long-term
Term Mitigated mitigation
During the operation phase of the project the main sources of impacts on community health and
safety are:
Mitigation Measures
Monitoring emission from the power plant
Green belt development
Regular inspection of the oil tanker and storage tank
Proper maintenance of the power plant equipment
Implementing proper mitigation measures the impact will be very low
Medium- Medium-
Very low Low High Very High
Impact Significance Low high
Significance of impact is considered as low
The following steps should be taken to minimize impact due to increasing river traffic.
Proper signalling light on the vessel at night time to avoid collision
Barge and vessels should be anchored close to the bank so that they will not impede normal
boat movement
Vessel movement should not hamper fish cultivation activities in Dakatia River.
A 24 hours river traffic management plan
A. Impact on Employment
The power plant will create job facilities for the local people. It will be a positive impact on the
society.
Impact Impact on Employment
Impact Significance
With reference to the proposed power plant base line environmental data transmission line will
impose negligible impact on physical and social during construction and operation phase.
Impact Impact on Environment due to construction and operation of High Voltage Transmission Line
Impact Nature Direct Indirect Induced
Impact Scale Within plant boundery
Frequency Entire life of the power plant including construction phase
Extent and location Project Site Local Regional National Trans boundary
Medium Long- Permanent – no
Impact Duration Short Term Permanent – Mitigated
Term term mitigation
Impact Intensity/ severity Insignificant Low Medium High Very High
Potential for irreplaceable
Low Medium High
loss of resources
Insignifica
Magnitude Low Medium-low Medium - high High Very High
nt
Probability of Impact Unlikely Low Medium High Definite
Impact Significance Very low Low Medium-Low Medium-high High Very High
Mitigation Measures
Following mitigation measures should be taken to minimize impact on environment due to
construction and operation of the power transmission line to evacuate electricity to national grid
line.
The contractor will judiciously limit vegetation clearing in the line corridor to avoid
excessive and unnecessary loss of trees outside the line corridor.
The contractor will take due care to avoid excessive sediment migration into surface
watercourses.
No waste will be dumped in watercourses.
Project vehicles will have a restricted speed limit of 40 kph through settlements and trading
centers to minimize road dust.
Line construction workers will be provided appropriate safety gear for protection against
excessive noise and dust emissions.
All waste generated at a given construction location will be collected in appropriate
containers and disposed as per standard procedure
Transmission lines must meet the requirements of the international standard
Plant boudery with apprach road Low land in and around the approach road
Figure 5-3: Approach road and surrounding features
About 100 meter approach road will be constructed to connect the power plant main entrance with
nearby local road which is connected with main road. The source of impact due to construction of
the approach road will be:
Extent and location Project Site Local Regional National Trans boundary
Permanent – Permanent – no
Impact Duration Short Term Medium Term Long-term
Mitigated mitigation
Impact Intensity/
Insignificant Low Medium High Very High
severity
Potential for
irreplaceable loss of Low Medium High
resources
Probability of
Unlikely Low Medium High Definite
Impact
Very low Low Medium-Low Medium-high High Very High
Impact Significance
Significance of impact is considered as very low
Mitigation Measures
The following steps should be taken to minimize impact on environment due to the approach road.
It is concluded that the ‘No build’ alternative is unacceptable and the potential socio-economic
benefits of implementation of such project far outweigh the adverse impacts which are minor and
temporary can be controlled and minimized to an acceptable level.
To avoid or minimize the impacts resulting from the activities of the project, CPRL authority is
expected to adopt appropriate technological design, improvements or adjustments, policy including
good site operational practices and applicable EMP, etc. The overall strategy shall follow the
following sequence:
integration of the ESMP with Project planning, design, construction and operation;
The construction phase of the Project is anticipated to last approximately 270 days. However, the
design life of the Project is 15 years and DECPCL will be responsible for ensuring that the
mitigation measures in the ESMP are implemented throughout the life span of the Project. A
summary of mitigation measures identified for the construction and operation phases of the project
is presented in Table 7-1 and Table 7-2.
1.3 Soil Quality Storage, handling Soil contamination Design processes to prevent/minimize Appointed EPC On site Project Half yearly report EPC Contractor
and disposal of quantities of wastes generated and hazards Contractor Management by 3rd party Cost
construction associated with the waste generated; team and Organization to
waste designated HSE DECPCL
Implement a construction materials team of DECPCL
inventory management system to minimize
over-supply of which lead the construction
materials, may the end of the disposal of
the surplus at construction period;
2.1 Water Wastewater Wastewater Vehicle servicing areas and wash bays Appointed EPC On site Project Quarterly report by EPC Contractor
Resources Discharge from contamination located within roofed and cemented Contractor Management 3rd party Cost
washing of areas. team and Organization to
equipment and designated HSE DECPCL
machinery The drainage in these covered areas team of DECPCL
Sanitary connected to oil/water separator and
facilities channelized properly to the land/inland
waters;
2.2 Surface Water Leaks and spills Surface water
Quality of oil, contamination
Oil leakage or spillage contained and
lubricants, fuel cleaned up immediately. Waste oil to be
Improper collected and stored for recycling or
handling of disposal;
sewage or
chemical
Oil and grease separator shall be used
for wastewater generated from cleaning
activities;
3.1 Air Quality Site preparation Dust generation Implementation of a regular and rigorous Appointed EPC On site Project Quarterly report by EPC Contractor
and Contractor Management 3rd party Cost
watering and sprinkling regime for dust
levelling; suppression during the dry season; team and Organization to
Excavation of designated HSE DECPCL
soil to create Maintain the maximum possible distance team of DECPCL
building and between stockpiles and receptors;
equipment
foundations; Cover and/or water spray all stockpiles of
Pile driving for dusty materials such as excavated spoils,
the equipment loose construction material piles to avoid
foundation; fugitive dust;
Concrete works
During construction, the access road will
Transportation be regularly maintained to keep it clean,
related free from mud and slurry.
activities
Material transport will be totally enclosed
with impervious sheeting and wheel
washing will be carried out at site.
3.2 Air Quality Operation of Exhaust Emissions A speed limit of 20 km/hr will be enforced Appointed EPC On site Project Quarterly report by EPC Contractor
heavy on the construction site/access road; Contractor Management 3rd party Cost
machinery and team and Organization to
transport Regularly maintain all diesel-powered designated HSE
4.1 Noise Heavy Increase in ambient Normal working hours of the contractor Appointed EPC On site Project Monthly report by EPC Contractor
machinery noise levels Contractor Management 3rd party Cost
will be between 06:00 and 21:00 hours from
operations for Saturday to Thursday. If work needs to be team and Organization to
construction undertaken outside these hours, it should designated HSE DECPCL
works be limited to activities that do not lead to team of DECPCL
Transportation exceedance of the noise criteria at nearby
related residential area;
activities
Pilling activities Only well-maintained equipment should
be operated on-site;
6.1 Occupational General Health and safety The Contractor will prepare and Appointed EPC On site Project Monthly report by EPC Contractor
Health and construction of construction implement a Health and Safety Plan Contractor Management 3rd party Cost
Safety activities workforce prior to commencing work. This plan team and Organization to
will include method statements for designated HSE DECPCL
working team of DECPCL
methods, plant utilization, construction
sequence and safety arrangements;
6.2 Occupational Changes Health of Provision of clean drinking water in Appointed EPC On site Project Monthly report by EPC Contractor
Health and to/existing construction accordance with Schedule 3 (b) of ECR, Contractor Management 3rd party Cost
Safety environmental workforce 1997; team and Organization to
designated HSE DECPCL
team
6.3 Occupational Labor and Working The EPC contractor will comply with the Appointed EPC On site Project Monthly report by EPC Contractor
Health and working conditions IFC Performance Standard 2 for labor and Contractor Management 3rd party Cost
Safety conditions working conditions; team and Organization to
Terms of designated HSE DECPCL
employment No child and/or forced labor will be team of DECPCL
Child/ forced employed by the EPC contractor and its
labor sub-contractors; and
7.1 Terrestrial Site preparation Clearance of Construction schedule to be managed Project On site Project Visual Inspection Project
Ecosystem and related shrubs, herbs and management HSE by HSE developer cost
such that the foundation work is not done
activities weeds and appointed Management Management of and EPC
during monsoon season;
EPC Contractor Team of DECPCL Contractor Cost
Strict instruction shall be given to the DECPCL
construction workers not to cut trees from
the nearby areas for their kitchen fuel and
timber use;
8.1 Aquatic Leakages and Impact on habitat Conservation training shall be given and a Project On site Project Visual Inspection Project
Ecosystem Discharges of aquatic and ban on hunting, capture of species by any Management HSE by HSE Developer Cost
of chemicals reverence fauna contractor/subcontractor/construction along with hired Management Management of and EPC
Construction of due to accidental worker working on water pipeline, specialists and Team of DECPCL Contractor Cost
temporary jetty spillage including logistics contractor not Appointed EPC DECPCL
Leakages and complying being immediately removed Contractor
Discharges from the project;
from River
Transportation Proper maintenance for avoidance of any
leakage of fuels and other contaminants
from barges/trawlers to Dakatia River;
Standard codes and practices to be
followed during unloading of fuels and
1.2 Community General Health Impacts Barriers will be provided to prevent Appointed EPC On site Project Visual Inspection EPC Contractor
Health and construction due to Changes Contractor along Management by HSE Cost
ingress of persons into the construction site
Safety activities in environmental with Project Team and Management of
and also to protect public exposure to
Influx of conditions hazards associated with construction Management Designated HSE DECPCL
construction activities; team on site of
workers Increased DECPCL
prevalence of Screening, surveillance and treatment of
disease workers, through the provision of medical
facilities and, where required,
immunization programmes;
2.1 Water Water Extraction Operation team Designated Record maintained Plant O&M
Lowering of If the local community do not get water
Resources Groundwater Team and Cost
during the dry period DECPCL need to be
level comprising of Quarterlyreports to
install a deep tube well for the local people to
serve the water for community peoples; representation top management
from EHS and
Ground
Monitoring the underground water level in Operations of Also, quarterly
subsidence DECPCL monitoring from the
the surrounding wells;
3rd party
Dig wells of appropriate deepness organization
as necessary
2.2 Water Storage and Plant EHS Team Designated Record maintained Plant O&M
Impact on soil Oily water runoff collected in the Plant Storm
Resources handling of fuel, oil and ground and operations Team and monthly Cost
water drains especially from the Power House
and chemicals water comprising of internal reports to
area, Transformer area, oil handling & storage
Contaminated representation top management
area and oil filled motors and pump bases will
storm water from EHS and
be collected in different sump and taken to a
Operations of Also, quarterly
runoff common oily waste water sump;
DECPCL monitoring from the
carrying
contaminants The oily wastewater and storm runoff 3rd party
collected from specific areas mentioned organization
to nearby low
lying areas above will be treated using an oil water
and Dakatia separator;
River and
2.3 Water Discharge of plant Plant EHS Designated Record maintained Plant O&M
Resources wastewater
Impact on The wastewater will be treated prior to discharge to
Team and Team and monthly Cost
Dakatia river meet GOB ECR 1997 Schedule 10 (Standards for operations comprising of internal reports to
water quality Waste from Industrial Units or Project Waste) and representation top management
IFC EHS Guidelines; In order to monitor ETP from EHS and
performance, continuous evaluation and monitoring Operations of
of discharge parameters will be done at the outlet
DECPCL
points of ETP; and
Quality of treated effluent discharged into Dakatia
River will be monitored periodically as per the
Project Environment Monitoring Program and
accordingly appropriate corrective actions will be
implemented, if any non-compliance is observed.
3.1 Noise Plant operations Plant EHS Designated Record maintained Plant O&M
Increased noise Selection of equipment with lower sound power
Team and Team and monthly Cost
level levels (< 85 dB);
operations comprising of internal reports to
Installation of mufflers on engine exhausts and representation top management
compressor components; from EHS and Also, Monthly
Operations of monitoring from the
Installation of acoustic enclosures for equipment DECPCL 3rd party
(e.g. turbine, compressor) casing radiating noise; organization
The proponent will take the following measures to control river erosion around the power plant
or toxic
chemicals and
Half Yearly
Monitoring
report
Water Contamination Turbidity, pH, DO, Dakatia River Standard analytical Quarterly 3rd Party EPC Contractor
of surface Total dissolved (upstream and methods Environmental Cost (300,000
water solids, oil & grease, downstream) Consultant BDT/annum)
total coliform,
heavy metals
Ground water Hardness, Ground water Standard analytical Quaterly 3rd Party EPC Contractor
quality Chloride, Fluride, source in the project methods Environmental Cost (600,000
Iron ,Manganese, area Consultant BDT/annum)
Magnesium,
Arsenic, Chlorine,
Fecal Coliform,
Total Coliform,
Heavy Metal
Occupational Accidents or Near-misses, Project activity As defined in As defined in EHS Team of EPC Contractor
Health and incidents due incidents, areas and construction phase H&S plan EPC Cost
safety to construction occupational construction camp health & safety Contractor (1xHSE Manager,
activities diseases, area plan to be prepared 1xDeputy HSE
workers health dangerous by EPC contractor Manager &
occurrences 1xHSE Executive)
Community Community Accident, incidents Access Road Incidents, accidents Based on EHS and / or EPC Contractor
Health and disturbance and complaints connecting site and community occurrence Community Cost
Safety and potential complaints Liaison Officer (1xHSE Manager,
safety hazard of EPC 1xDeputy HSE
due to road
Aquatic Impact on Habitats and Near temporary Identification and Prior to start Project EPC Contractor
ecology habitat of disturbance to jetty and river Enumeration by the work and company with Cost (300,000
aquatic and aquatic fauna transportation route ecologist continuous help of experts BDT)
riverine fauna
due to spillage
Impact on Habitat and Near temporary Deck monitoring Continuous Project EPC Contractor
mammals due disturbance aquatic jetty and river company Cost
to trawlers fauna transportation route
and barges
Environmental Training need 1 – day training for At project site As per national and Before Contractor EPC Contractor
and Social those people of IFC/ WB standard contractor start through 3rd Cost
Issue Contractor who guideline party (300,000 BDT)
involved in engagement
environmental and
social issues
Operation Phase
General Inspection of General Project activity Visual inspection Daily EHS Team of Included in
mitigation compliance with areas of all active work DECPCL operation and
compliance mitigation areas maintenance
measures (O&M) cost
presented in the
ESMP and
operational manual
Air pollution Stack Emission NOx, SO2, CO, Main stack CEM Continuous DECPCL Installation
Concentration PM2.5 included in EPC
Cost
Monitoring and
Maintenance in
O&M Cost
Emission NOx, SO2, CO and Main stack Standard Methods Annual 3rd party O&M Cost
Concentration PM2.5 Environmental (150,000
Consultant BDT/annum)
Ambient Air PM10, PM2.5, NOx, 4 Locations where Standard Methods Quarterly 3rd party O&M Cost
Quality SO2, CO the samples were Environmental (500,000
collected during Consultant BDT/annum)
baseline monitoring
Noise Noise Sound pressure 1 m from the noise Noise monitor Monthly EHS Team of O&M Cost
generation level generation DECPCL or 3rd
Surface water Temperature, Upstream and Standard Methods Quarterly 3rd party O&M Cost
quality Conductivity, pH, downstream of Environmental (100,000
DO, TDS Dakatia River Consultant BDT/annum)
Aquatic Impact on Fish count, Upstream and Abundance of Once post one Plant O&M Cost
ecology fishes and phytoplankton’s, downstream of aquatic flora and year of management (200,000
riverine flora zooplankton’s Dakatia River fauna commissioning BDT/annum)
and fauna number of the plant by
experts
Community Community Accidents, Access Road Accidents, Based on Visual O&M Cost
Health and disturbance incidents and incidents and occurrence Inspection
safety and potential complains complains report by EHS
safety hazard Team of
due to road DECPCL or
traffic community
liaison officer
Public Complains from Neighboring As per grievance Continuous Visual O&M Cost
Concern community communities redress mechanism Inspection
report by EHS
Team of
DECPCL or
community
liaison officer
CSR Activities Community Activities/ Vulnerable group No of beneficiaries Periodic and Admin/ HR CSR Budget
Development programs and no around the project and outcome of the need based Manager
of beneficiaries activities area activities
While the contractor or a particular party is responsible for physical implementation of the
mitigating measures, the whole implementation process requires supervision, checking,
documentation and verification so that problems are identified and properly addressed before they
get out of hand.
Management
Environmental Manager
Safety Manager
7.8 Budget
The EPC Contractor and the DECPCL will allocate separate budget for environmental and social
management plan implementation, training, environmental monitoring, analysis and reporting,
verification monitoring and capacity building. It should be noted that cost for many in-built
mitigation measures, such as, acoustic enclosures for noise control, water and wastewater
treatment, CEM etc, are already included in the EPC contract cost estimate and/or operating cost
estimates. In addition to that separate budget will be allocated for CSR activities, which will be
conducted by the Project Developer for community development. The budget estimate for the 3rd
party monitoring and verification has been included in Table 7-3.
In this EIA report, detailed assessment has been carried out to identify and mitigate the potential
hazard associated with construction and operation of the power plant.
8.2 RA Study Objective
The overall objective of this RA with respect to the proposed project involves identification and
evaluation of major risks, prioritizing risks identified based on their hazard consequences and using
the outcome to guide and strengthen both onsite and offsite ERP. Hence in order to ensure effective
management of any emergency situations that may arise from failure of various fuel storages. The
following specific objectives need to be achieved.
Identify potential risk scenarios that may arise from storage of volatile fuels in the plant
Review existing information and historical databases to arrive at possible likelihood of such
risk scenarios.
Predict the consequences of such potential risks scenarios and if consequences are observed
to be high, establish the same through application of quantitative simulation
Recommend feasible preventive and risk mitigation measures as well as provide inputs for
strengthening of the project Emergency Response Plan(ERP)
Vehicles movement Noise generation Running engine, hydraulic horns, sirens etc. Injuries
Accident Mechanical failure Health problems
Emission from vehicles Old engine or engine parts/lack of maintenance ( e.g. respiratory,
Spread of dust and hearing and/or cardiac
minute particles due to problems)
vehicle movement Fatalities
Disabilities
Chemical storage Accidental release of Lack of safety protocols Health injuries (burns,
area chemicals Carelessness( e.g. smoking near chemical storage area) anxiety, depression
Handling of Acute/chronic toxicity Not proper bounding of chemical storage area etc.)
The effect of fire on people and property outside will chiefly manifest itself in the form of thermal
radiation. A criterion was selected for deciding the maximum level of thermal radiation to which
the outside population can be subjected. Thermal radiation levels from fire scenarios of each tank
are worked out at various distances and their effects are evaluated against the set criteria.
The main hazards associated with the storage and handling of fuels are pool fires resulting from the
ignition of released material as well as explosions. Hazardous chemicals also can be realized
following tank overfilling and leaks/failures in the storage tank and ancillary equipment such as
transfer pumps, metering equipment, etc. Fuel oil is a combustible liquid, which will burn if the
temperature of the liquid exceeds the flash point and the vapor generated at the liquid surface is
ignited. The resultant incident is a pool fire that radiates heat to the surroundingarea resulting in po
tential equipment damage and or injury/fatality. Fuel oil is also a contaminant to the biophysical
environment and its release can damage sensitive environmental areas surrounding the storage area
in the event a leak occurs and escapes to the environment. Fuel will also float on water and be
carried a significant distance from a leak point by a water course.
The flammable liquid in a pool will burn with large turbulent diffusion flame. This releases
heat based on the heat of combustion and the burning rate of the liquid. A part of heat is
radiated while the rest is convected away by rising hot air and combustion products. The
radiations can heat nearby storage or process units to above their ignition temperatures and
thus result in spread of fire.
The radiation can also cause severe burns or fatalities to workers or firefighters located within a
certain distance. Hence, it will be important to know beforehand the damage potential of flammable
liquid pool likely to be crated due to leakage or catastrophic failure of storage or process vessel.
This will help decide the location of other storage/process vessels, decide the protective clothing
the workers/firefighters need, the duration of time for which they can be in the zone, the fire
Accidental release of fuel from Diesel and HFO tank can create a pool fire in presence of an ignition
source. Following an accidental release, fuel will form a confined pool within the dyke area. If the
vapor above the pool ignites, the liquid will burn as a pool fire. The pool fire will result in thermal
radiation. It could also damage the storage tanks located within the common dyke area. The pool
fire simulation scenarios for the major tanks of the power plant are given in the following sub-
section.
Pool Fire
SOURCE STRENGTH:
Leak from hole in vertical cylindrical tank
Flammable chemical is burning as it escapes from tank
Tank Diameter: 7.75 meters Tank Length: 5.8 meters
Tank Volume: 321 cubic meters
Tank contains liquid Internal Temperature: 70° C
Chemical Mass in Tank: 191 tons Tank is 78% full
Circular Opening Diameter: 10 centimeters
Opening is 5 meters from tank bottom
Max Flame Length: 15 meters Burn Duration: 55 minutes
Max Burn Rate: 341 kilograms/min
Total Amount Burned: 10,396 kilograms
Note: The chemical escaped as a liquid and formed a burning puddle.
The puddle spread to a diameter of 9.3 meters.
THREAT ZONE:
Threat Modeled: Thermal radiation from pool fire
Red : 28 meters --- (10.0 kW/(sq m) = potentially lethal within 60 sec)
Orange: 35 meters --- (5.0 kW/(sq m) = 2nd degree burns within 60 sec)
Yellow: 49 meters --- (2.0 kW/(sq m) = pain within 60 sec)
The pool fire thermal radiation threat zone of the HFO Buffer tank is shown in Figure 8-4.
Pool Fire:
ATMOSPHERIC DATA: (MANUAL INPUT OF DATA)
Wind: 7.6 meters/second from SW at 10 meters
Ground Roughness: open country Cloud Cover: 7 tenths
Air Temperature: 30° C Stability Class: D
No Inversion Height Relative Humidity: 75%
SOURCE STRENGTH:
Leak from hole in vertical cylindrical tank
Flammable chemical is burning as it escapes from tank
Tank Diameter: 9 meters Tank Length: 8.7 meters
Tank Volume: 617 cubic meters
Tank contains liquid Internal Temperature: 90° C
Chemical Mass in Tank: 373 tons Tank is 81% full
Circular Opening Diameter: 10 centimeters
Opening is 5 meters from tank bottom
Max Flame Length: 16 meters
Burn Duration: ALOHA limited the duration to 1 hour
Max Burn Rate: 337 kilograms/min
Total Amount Burned: 20,056 kilograms
Note: The chemical escaped as a liquid and formed a burning puddle.
The puddle spread to a diameter of 8.8 meters.
THREAT ZONE:
Threat Modeled: Thermal radiation from pool fire
Red : 28 meters --- (10.0 kW/(sq m) = potentially lethal within 60 sec)
Orange: 35 meters --- (5.0 kW/(sq m) = 2nd degree burns within 60 sec)
Yellow: 49 meters --- (2.0 kW/(sq m) = pain within 60 sec)
The pool fire thermal radiation threat zone of the HFO Service tank is shown in Figure 8-5.
Plant failure;
Human error;
Vehicle crash;
Sabotage;
Earthquake;
Lightning; and
Fire.
Rescuing people;
Treating the injured;
Safeguarding others;
Minimizing damage to property and environment;
Controlling the incident, removing the hazard, preventing escalation;
Maintaining the welfare of personnel involved in controlling the occurrence;
Identifying casualties;
Informing and assisting relatives;
Informing the news media;
Informing/collaborating with the authorities and emergency services;
Preserving records.
- Assembly points;
- Truck parking area; and
- Surrounding location.
- Assess the magnitude of the situation and decide whether the evacuation of staff
from the plant is needed;
- Exercise and direct operational control over areas other than those affected;
- Maintain a continuous review of possible development and assess in consultation
with work incident controller and other key personnel;
- Liaison with Police, Fire Service, Medical Services, Factory Inspectorate and other
Government Agencies;
- Direct and control rehabilitation of affected area after emergency; and
- Ensure that evidence is preserved for enquiries to be conducted by statutory
authorities.
The Works Main Controller will declare the emergency and he will instruct gate office to
operate the emergency siren after assessing the gravity of the situation.
b. Work Incident Controller
He is the next responsible officer after the works main controller. Generally the plant
manager is designated as work incident controller. In case of emergency he will rush to the
place of occurrence and take overall charge and report to the works main controller by
personnel communication system like cell phones or walky-talky and inform about the
magnitude of emergency. His duties are to:
- Assess the situation and considering the magnitude of emergency he will take
decision and inform Communication Officer to communicate the news of emergency
to different agencies;
- Give direction to stop all operations within the affected area;
- Take the charge of Main Controller till the Main Controller arrives;
- Order for shutdown and evacuation of workers and staffs from affected area;
- Inform all Key Personnel and all outside agency for help;
Fire protection and firefighting facilities (a pool/tank capacity is about 6000 m3 will
be preserved at the project site for emergency use during fire accident);
Emergency lighting and standby power;
Emergency equipment and rescue equipment:
- Breathing apparatus with compressed air cylinder.
- Torches.
- Ladders
Safety Equipment:
- Respirators.
- Gum boots.
- Safety helmets.
- Asbestos Rubber hand gloves.
- Goggles and face shield.
- Toxic gas measuring instruments.
- Explosive meter.
- Oxygen measuring instruments.
- Wind direction indicator.
Walky-Talky;
Telephone (internal and external);
Cell Phone;
Intercom;
Runners (verbal or written messages).
8.10.5 Evacuation
All non-essential staff should be evacuated from the emergency site. As soon as the
emergency siren rings the workers have to shut down the plant and move to the assembly
point. The plant shut down procedure in case of emergency should be prepared and kept
ready and responsible persons should be nominated for the purpose.
Mutual aid must be a written document signed by the Chief Executive of the
industries concerned;
Specify key personnel who are authorized to give requisition of materials from other
industries;
Specify the available quantity of material/equipment that can be spared;
Mode of requisition during emergency;
Mode of payment/replacement of material given during an emergency;
May be updated from time to time based on experience gained.
Mock drills on emergency planning should be conducted once in 6 months and sequence of events
should be recorded for improvement of the exercise.Exercises on Onsite Emergency
Planning should be monitored by Factory Inspectorate and the high officials of the organization and
the plan is reviewed every year.
8.11.2 Responsibility
ERP Coordinators: Any person of Emergency Response Team can act as a responsible person
during working day. They are responsible to handle any types of emergency situation individually
and follow up the all preventive procedure followed by respective team. They communicate to all
local administrative personal or offices during emergency occur.
Shift Executive: Shift Executive isacting as a site controller’s role during night shift operation and
will be continuing the role till any above mention person comes to the factory. Security supervisor is
to assess all types of emergency work with the shift executive.
Security supervisor: Security supervisors acting as a site controller role during Holiday or weekly
off day and he will be continuing the role till any above mention persons comes to the factory.
First Aid Team: The member of the first aid team is totally responsible to handle any type of
personal injury / accident and communicate the same to crisis management team and follow up
their guidance and procedure as illustrated bellow.
Evacuate the people from flooded area and send them to a safe area.
Switch of the power supply from effected area.
Remove all types of obstructions from the drainage system.
Coordinate with the Emergency Response Team and take action as per their guideline.
In cases of any accident in human life please call first aid team and get medical attention as
soon as possible.
Call local fire brigade through communication system in case of worst or out of control
situation.
In case of over flood polythine and sand bag to protect adverse effect.
For emergencies and potential danger or after hours call to Control room 333.
In a situation where a building needs to be evacuated, please proceed to the building specific
evacuation area.
Turn off equipment, machines and computers.
Assist disabled persons as needed.
Do not use elevators.
Stay at the designated evacuation area until the fire department or designated representative
has given the “all clear” to re-enter the building.
8.14 Emergency Plan should contain
DECPCL power plant authority will prepare immediately an emergency plan before the starting of
commercial production. In this emergency plan following matters will be consider:
The proposed Grievance Redress Mechanism (GRM) will be developed for the Project in order to
settle as many disputes as possible through consultations, negotiation and mutual settlement. Such
a mechanism is important as it is expected that most cases, if not all, would be resolved amicably;
and the process, as a whole, will promote dispute settlement through mediation to reduce litigation.
However, the options of legal recourse will not be restricted in any way by the project proponent.
The fundamental objective of GRM is to resolve any social (including labor, contractor, community
amongst others) and environmental related grievances locally in consultation with the aggrieved
party to facilitate smooth implementation of project related work activities. The other important
objective is to democratize the development process at the local level and to establish accountability
towards the stakeholders.
The GRC will be driven internally by DECPCL and shall have the following representation to
ensure fair and timely solution to the grievances:
Review, consider and resolve grievances related to social and environmental aspects
received by the Lance Field Office having the GRC; Entertain grievances of indirectly
affected persons and/or persons affected during project implementation;
Resolve grievances within a period of two weeks at the GRC level and communication of the
resolution to the aggrieved party;
The GRC shall not engage in any review of the legal standing of an “awardee” nor shall deal
with any matters pending in the court of law;
Arrive at decisions through consensus, failing which resolution will be based on majority
vote. Any decision made by the GRC must be within the purview of Environmental
Management Plan, Corporate EHS and Social Policies or any such documents of relevance of
that matter;
In case the grievance relates to environmental monitoring results or engineering matters, the
GRC will validate the information available to it, as provided by Lance Project management
team/ environmental monitoring team. However, GRC will not be in a position to question
the validity of the data provided to it. The GRC team shall meet at least twice a month for
review of grievances registered and the resolution vetted out to the concerned parties. The
frequency of meeting may increase or decrease depending on the number grievances
received.
If needed, may undertake field visits to verify and review the issues, dispute or other
relevant matters.
10.5 Disclosure of the Grievance Redress Mechanism
Some of the important points regarding disclosure of the grievance e redress mechanism are:
Grievances primarily related to any serious event such as accidents involving g the community,
labor related major disputes such as non-payment of wages or work related injuries or fatalities,
major intrusion of project on any community resource, and other issues for which the aggrieved
party in his or her free will wants to register a grievance or complaint.
On receipt of complaint the GRC shall give an acknowledgement to the complainant with
date, time and venue of hearing of his/her grievance.
The GRC shall prepare a brief note on the grievance for discussion on scheduled date. On
the given date, the GRC shall hear the complainant and give its decision. A written copy of
decision shall be provided to the complainant. If the complainant is satisfied with the
decision, an acknowledgement of same shall be obtained from him on the decision copy and
the case shall be closed.
If the complainant is not satisfied with the outcome of GRC’s decision, he or she can opt for
any grievance redress forum available at the administrative level or undertake the course of
law available to him/her. However, every effort shall be made to resolve the case amicably
10.9 Budgeting
The DECPCL administration shall ensure adequate budgeting and resource allocation for
implementing the grievance redress mechanism.
Mapping and identification of key stakeholders such as primary (direct project influence)
and secondary (indirect project influence) stakeholders;
Undertaking expert consultations, interviews and focus group discussions (FGD) with the
respective stakeholders;
Undertaking structured on field consultations, interviews and FGD with the respective
stakeholders;
Assessing the influence and impact of the project on these stakeholder groups;
Primary Stakeholders: include people, groups, institutions that either have a direct influence
on the project or are directly impacted (positively or adversely) by the project and its
activities; and
Secondary stakeholders: are those that have a bearing on the project and its activities by the
virtue of their being closely linked or associated with the primary stakeholders and due to
the influence they have on the primary stakeholder groups.
Apart from categorization, the stakeholders have also been classified in accordance with the
level of influence they have over the project as well as their priority to the project proponent
in terms of importance.
The influence and priority have both been primarily rates as:
- High Influence/Priority (Manage Closely): People who have high power and interest are
grouped in this category. They always must be managed closely. This implies a high degree
of influence of the stakeholder on the project in terms of participation and decision making
or high priority for project proponent to engage that stakeholder.
- Medium Influence/Priority (Keep Satisfied/ keep informed): People who have high power
but low interest as well as who have high interest but low power should be kept satisfied or
informed. This implies a moderate level of influence and participation of the stakeholder in
the project as well as a priority level for project proponent to engage the stakeholder who
are neither highly critical nor are insignificant in terms of influence.
- Low Influence/Priority (Monitor with minimum effort): This implies a low degree of
influence or interest of the stakeholder on the project in terms of participation and decision
making or low priority for project proponent to engage that stakeholder.
Other Regulatory & Primary High - Agencies required for obtaining permits and licenses
Permitting for establishment and operation of the project;
-
Authorities - Primary involvement during pre-construction and
operation phases.
Political Administration
Thana Political Secondary Elected representative of Medium - Key linkage between the community and the project
Administration people at Thana level for a proponent;
fixed tenure. - Low interest with high influence.
Ward leaders & Primary Elected representative at Medium - Issuance of no objection certificate as the
local representatives ward level for a fixed tenure. representative of the local level representative;
- Plays important role in providing public opinion and
sentiment on the project;
- Empowered to provide consent and authorization for
establishment of project on behalf of the community.
Other Institutional Stakeholders Groups
Printed and Secondary - Medium - Public watchdog on the project related activities;
Electronic Media - No major influence on the project.
Md. Hassan has been working at Gunrajdi Government Primary School as Assistant Teacher. The
school was established in 1938 and reestablished in 1999. There are approx. 500 students currently
enrolled in the government primary school. The school is located at just opposite of the project
adjacent river. His suggestion was to establishment of air pollution and noise generation unit as far
as possible from the school. Project authority should have in mind that a lot of students come to the
school by crossing the river. The school authority has no objection but the project authority must be
responsible for providing associated facilities for school going students.
B. Views of Mr. Abdul Matin, Upazila Engineer, Local Government Engineering Department
(LGED), Chandpur Sadar Upazila, Chandpur.
Mr. Matin told that the demand of electricity is increasing day by day. So i think HFO based power
plant helps to improve the performance of the power sector in Bangladesh. LGED is responsible for
the construction and maintenance of rural road network in Bangladesh. So if there anything to do
LGED should take the step.
C. Views of Mr. Showkat Kabir Choudhury. Senior Upazila Fisheries Officer, Chandpur Sadar
Upazila, Chandpur.
Mr. Kabir stated that Impact due to the power plant activities to the surface water bodies is
considerable. But should aware of the fact that not to pollute adjacent any cannel as much as
possible. Some box culture fishing is located in project surrounding area.
D. Views of Mr Md Abdur Sattar, Sub Assistant Engineer, Dept. of Public Health Engineering,
Chandpur Sadar Upazila, Chandpur.
Mr. Sattar stated that in the proposed power plant a large amount of water will be used from the
ground water source or surface water source. Due to the rapid lowering of static water level and the
Consultation with Mr. Md. Hassan, Assistant Consultation with Mr. Kazi Sumon,
Teacher, Gunrajdi Government Primary School Senior Chemist, DoE, Chandpur.
Consultation with Mr. Siddiqur Rahman Dhali, Consultation with Mr. Md Abu Ryhan, Executive
Panel Mayor, Chandpur Municipality, Chandpur. Engineer, Bangladesh Water Development Board
(BWDB), Chanfpur O&M Division, Chandpur.
General perception about the Most of the participants are in favor of the Acceptance of the project
proposed project and the project and have been made aware of the
awareness about the proposed proposed project through the various
project surveys that have taken place
Support of local people for the Almost everybody said that they will The consultants informed
proposed project? support the project and advised the that during the study, the
consultants to take precautions in the design and layout of all
environmental mitigation to avoid the infrastructures have been
various impacts anticipated during the considered the anticipated
pre-construction, construction and adverse impacts
operation stages of the project and to
ensure protection of the natural water
bodies of the areas
Does the proposed project People of the project area site were aware Impact of the project upon
create any problem with of this problem specially the water ambient air, noise quality,
ambient air, noise quality and pollution. They think they will suffer for water quality is assessed in
water quality? oil contamination in water during heavy the ESIA study
rainfall for HFO based power plant.
Any critical issue or concern Respondents requested that Noise mitigation, water
by the local people regarding environmental hotspots (like school, pollution and gas emission
the project? Or Any criteria temples, mosques etc.) should be avoided are considered in the EMP
you would like to see as much as possible. Moreover, noise
considered during project mitigation, water pollution and gas
design, construction and emission must be considered
operation stage?
Is the proposed project going All the participants raised their voice for Some concerns over safety,
to provide better traffic reconstructing the existing road for better supporting design measures
system? traffic system such as increased number of
sign board, road mark, bump
etc.
Protected areas (national The proposed project construction area
parks protected forest, has no any protected or ecological critical
-
historical or archaeological area.
sites), if any
Employment Status: Employment is expected in the project Job chance and employment
Percentage of area will be enhanced and
employment/unemployment/ promoted once the pre-
underemployment construction and
construction has been started
If this project is improved, The respondents welcome the project. Residents understand that
there may be large groups of Many observed that the measures are construction impacts can be
workers living temporarily in temporary and besides there will be more expected and do not have an
the area and construction chances for local communities to be issue with these, provided
operations that generate noise employed during construction, providing safety measures are taken
and other pollutants. Are skilled, semi-skilled and unskilled labor.
there any other issues?
Proposed 200 MW HFO fired power plant project of Desh Enegry Chandpur Power
Company Limited located at Gunrajdi, Chandpur Sadar, Chandpur will produce electricity
to supply national grid line.
The project proponent has obtained the clearance for the proposed power plant from the
local authority and DoE
This EIA report has been prepared for DECPCL in accordance with but not limited to the
environmental guideline published by the DoE. The report is one of the requirements of DoE
to issue environmental clearance of the proposed power plant.
Multiple data collection technique has been used in conducting the EIA study which
included document review, observation, and interview with key informants, focus group
discussions and interaction with the DOE personnel. The EIA is prepared through
identifying the potential impacts, assessing them and recommending possible mitigating
and enhancing measure for adverse and positive impacts respectively.
No major adverse environmental impact is to be associated during operation phase of the
proposed plant. However, appropriate mitigating measures would be undertaken that
would reduce the low to medium impacts to an acceptable level as prescribed in the
Environmental Quality Standards of Bangladesh. All these mitigating measures have been
discussed in details in Chapter 5 of this report. The management aspect of environmental
and social parameters associated with these impacts has also been discussed in Chapter 7 of
the EIA report.
The proposed power generation facility is given highest priority by the present Government
of Bangladesh to provide affordable and reliable electricity for all citizens by 2021.
Power energy is an indicator of development of any country. This project will contribute to
development of entire Bangladesh.
This project is also provide employment for many persons and thus help reduce
unemployment problem of Bangladesh
Overall, the project has few negative impacts on the environment. However, its positive
impacts on socio economy can replenish that impact.
12.2 Recommendation
Based on the available information and environmental survey conducted in the project area, it is
found that the proposed industry will not adversely affect the environment of the project area and
its surroundings as long as certain mitigation measures are taken. Mitigation measures have been
formulated and will be adopted during implementation and operation to ensure that the residual
environmental impact of the project is within acceptable levels. The negative environmental impacts
The Environmental impact assessment (EIA) has not identified any comprehensive, broad diverse
or irreversible adverse environmental impacts caused by the project.
It is therefore, concluded that (i) the project will have few low to moderate adverse environmental
impacts , (ii) these adverse impacts will be small, (iii) they can be easily mitigated (iv) the project
has a net positive socio-economic impact.