LARP Implementation Process

Land acquisition of Government entity Land acquisition / purchase of Private entity

Proponent needs to submit request


letter to DC office for Land acquisition Proponent needs to submit request letter
to DC office for Land purchase

DC office will forward this letter to Ministry of Land


(MoL) for review and upon acceptance, MoL will give DC office will forward this letter to MoL
permission to DC office to do further proceedings for review and upon acceptance, MoL
will give permission to DC office to do
further proceedings
DC office will issue a preliminary notice of land
acquisition and will conduct a joint verification with
Affected households and relevant organization to identify DC office will conduct a field survey
the present status of the land, structures, trees etc. and if acceptable then they will
provide permission to the private
entity to purchase required land
After the survey, DC office publish the Notice of final
decision to acquire the property and notifying the
interested parties to submit their claims for
compensation which is called the cut-off date Private entity will Engage a
contractor/consultant/ NGO for purchasing
the land following to LARP study
After hearing the claims (if any), DC office prepares final
budget for Land acquisition and sends the estimate of
compensation to the requiring agency to deposit the
estimated Land acquisition budget to government
treasury

After depositing the budget amount by Govt. entity,


the DC office starts the land acquisition process by
dispatching the budget amount

N.B.: Govt. entity conducts LARP study by their engaged


consultant team for international lender safeguard
requirement (if any) as well as for supporting document
of DoE application

N.B.: The cut-off date is the date of publication of notice


that land is subject to acquisition, and that any
alteration or improvement there on will not be
considered for compensation.