Professional Documents
Culture Documents
Nilesh (210430106543)
Nilesh (210430106543)
AN INTERNSHIP REPORT
Submitted by
KANAJARIYA NILESH
210430106543
BACHELOR OF ENGINEERING
In
Civil Engineering
April, 2024
CERTIFICATE
• This is certify that the internship report submitted along with the
2023-24.
DECLARATION
We hereby declare that the Internship report submitted along with the
Internship entitled Construction Of Affordable Housing
Development (EWS-II) submitted in partial fulfilment for the degree
of Bachelor of Engineering in Civil Engineering to Gujarat
Technological University, Ahmedabad, is a bonafide record of
original project work carried out by me at Kruti Consultancy&
Aaditya Construction under the supervision of Bhaveshbhai and
that no part of this report has been directly copied from any student’s
reports or taken from any other source, without providing due
reference.
ACKNOWLEDGEMENT
My first thank goes to Prof. H.K.SARVAIYA Sir, the guide of the Internship
for giving me necessary suggestions and advice along with their valuable
coordination in completing this internship.
I wish to express my sincere gratitude to External Guide Er. Mehul S Patel for
continuously guiding me at the company and answering all my doubts with
patience. I would also like to thank all the staff member of company for their
valuable support in the completion of the project.
Thank
Kanajariya Nilesh D
• As part of curriculum, and for the partial fulfilment of the requirement for completion
of B.E degree from SHANTILALSHAH ENGINEERING COLLEGE,
BHAVNAGAR, I’m NILESH KANAJARIYA underwent a training as site engineer
at the Aditya Construction Ltd. For 12 weeks during 15th Jaunary to 15th April. The
report consists of brief study and description of the on-field construction work.
• This study presents the compendia of the observations made during the 12 weeks of
our internship study.
• In the opening content I have given details of the company background. In the second
content I have explained my overall internship familiarity in the last successive
weeks. In this part the main content that I have recorded and it contains overall work I
have been executing.
TABLE OF CONTENTS
College Certificate
Company Certificate
Declaration
Acknowledgement…………………………………………..……………………………..I
Abstract………………………………………………………………………….………...II
List of Figure……………………………………………………………………………..III
List of Table……………………………………………………………………………...VI
Chapter: 1 Introduction………………………………………………………………….1
2.1 Structure…………………………………………………………………………...8
3.1 Cement…………………………………………………………………………...12
3.2 Aggregate………………………………………………………………………...13
3.3 Reinforcement……………………………………………………………………14
3.4 Water……………………………………………………………………………..14
3.5 RCC………………………………………………………………………………15
Chapter: 4 Excavation………………………………………………………………….16
Chapter: 6 Footing……………………………………………………………………...21
Chapter: 7 Column……………………………………………………………………..27
10.2 Transportation……………………………………………………………………42
Property detail: Total Area-38122 SQ.M and Unit Size-661.8 SQ.M (Drawing room,
Bed room, Study room, Kitchen, Bath)
20 Residential Buildings, 2 Commercial Building, 2 Anganwadi, 2 Sewage Treatment
Plant And 2 Underground Water Tanks are located inside the site.
Building storied: G+7 Storied Residential Building
Fig
: 1.6
2.1 STRUCTURE
A building that has been built or made from a number of parts. Or to arrange something in
organized way is known as structure.
Type of Structure
Construction of the structure is done in at least two steps. Which are following.
1. Sub structure
2. Super structure
Foundation is a part of the sub structure. Sub structure is constructed according to soil
quality at that site. If soil have good bearing capacity than we use shallow foundation in
construction. If the bearing capacity of the soil is not good or suitable than we use deep
foundation at that site. Sub structure is a load bearing structure and it is designed for load
bearing.
Foundation:
A foundation is the element of any structure which connects it to the ground, and transfers
loads from the structure to the ground. Foundations are generally considered either
shallow or deep.
The low artificially built part of a structure which transmits the load of the structure to the
Ground is called foundation. Foundation is a load bearing structure which bears all loads
coming on the building or any structure.
1. Shallow Foundation
2. Deep Foundation
Shallow foundations are also called spread footings or open footings. The ‘open’ refers to
the fact that the foundations are made by first excavating all the earth till bottom of the
footing, and then constructing the footing. During the early stages of work, the entire
footing is visible to the eye, and is therefore called an open foundation. Some types of
shallow foundation such as:
1. Wall footing/strip footing
2. Spread Footings.
3. Isolated footings.
4. Stepped footings.
5. Combined footings
6. Sloped footings.
7. Mat or raft foundation.
8. Strapped footings.
A deep foundation is a type of foundation which transfers building loads to the earth
farther down from the surface than a shallow foundation does, to a subsurface layer or a
range of depths.
PILE FOUNDATION:
A pile is basically a long cylinder of a strong material such as concrete that is pushed into
the ground so that structures can be supported on top of it.
1. When there is a layer of weak soil at the surface. This layer cannot support the weight
of the building, so the loads of the building have to bypass this layer and be
transferred to the layer of stronger soil or rock that is below the weak layer.
2. When a building has very heavy, concentrated loads, such as in a high rise structure
There are two types of pile foundations, each of which works in its own way.
Super structure is a part of structure that is above the plinth level generally, columns and
walls are constructed in super structure. Following are the important parts of super
structure:
1. Floor
2. Roof
3. Lintel
4. Doors& Windows
2.2.1 Floor:
Floor is that part of a building on which furniture, household, commercial, industrial or
any other type of items is stored. Floor is used for walking around Floor separates the
different levels of a building. Building is also named with reference to floor. Like Ground
floor, first floor, or a floor that is below ground level like basement floor. In our site there
are three types of flooring take places.
2.2.2 Roof:
Roof is made to cover room from upper face. Different types of roofs are used in building
depending on the location and weather. Sloping roofs are generally considered better in
mountain areas. While, in plan areas flat roofs are preferred.
2.3.3 Lintel:
Lintel is constructed above doors, windows etc. To support load of wall on openings.
Lintel beam is generally made as reinforced cement concrete member. While, in
residential houses sometime lintel is made by using concrete and bricks. Breadth of lintel
is generally equals to the breadth of wall. In case of metric unit, it is normally equals to
10cm 15cm 20cm etc. While, in case of FPS system it is consider as 6”, 9”, 12” etc.
Thickness of lintel should not be less than 10cm (4.5”) and maximum thickness of lintel
Should not be more than its breadth
A door is a moving structure used to block off, and allow access to, an entrance to or
within an enclosed space, such as a building or vehicle. Doors normally consist of a panel
that swings on hinges on the edge, but there are also doors that slide or spin inside of a
space. A window is an opening in a wall, door, roof or vehicle that allows the passage of
light and, if not closed or sealed, air and sound.
3.1 CEMENT:
Cement was first discovered by an English brick layer named Joseph Aspdin in 1824. He
called it Portland cement for the reason that the cement he discovered resembled the
limestone found in Portland. The approximate composition of Portland cement is given
below,
The function of cement is to combine with water and to form cement paste.
Quality of cement is based on grade of cement. The grades of cement are as
33 Grades
43 Grades
53 Grades
33 Grade OPC is used for general construction works like plastering and finishing out
works in normal environmental conditions. However, its use is virtually phased today.
43 Grade OPC is the most commonly used grade for home construction. It has its
applications in plastering finishing works, precast items, foundations, brick work, and
compound wall and so on. It has more strength development than the 33-grade
cement.
3.2 AGGREGATE:
Aggregates are small pieces of broken stones in irregular size and shapes. Neat cement is
very rarely used in construction works since it is liable to shrink too much and become
cracks on setting. Moreover, it will be costly to use neat cement in construction work
Therefore cement is mixed with some inert strong & durable hard materials. They also
reduce the cost of concrete because they are comparative much cheaper as cement.
TYPES OF AGGREGATES
Fine Aggregate
Coarse Aggregate
The aggregate, which pass through 4.75 mm, IS sieve and entirely retain on 75 micron IS
sieve is known as fine aggregate.
The function of using fine aggregate in a concrete mix is to fill up the voids existing in the
coarse aggregate and to obtain a dense and strong concrete with less quantity of cement and
increase the workability of the concrete mix.
The aggregate, which pass through 75 mm 15 sieve and entirely retain on 4.75 mm IS
sieve is known as coarse aggregates.
The coarse aggregates are used in mixing of concrete. It is mixed cement, sand with
water. These aggregates increase the strength of bonding in aggregates. Coarse aggregates
are used in construction of plan cement concrete (PCC), foundation, beams and columns
etc.
3.3 REINFORCEMENT
The material that develops a good bond with concrete in order to increase its strength is
called reinforcement. Steel bars are highly strong in tension, shear, bending moment,
torsion and compression.
8mm 59.15
10mm 57.97
12mm 57.12
16mm 57.12
Function of Reinforcement:
3.4 WATER:
3.5 R.C.C:
Though plain cement concrete has high compressive strength and its tensile strength is
relatively low. Normally, the tensile strength of a concrete is about 10% to 15% of its
compressive strength. Hence if a beam is made up of plain cement concrete, it has a very
low load carrying capacity since its low tensile strength limits its overall strength. It is There
reinforced by placing steel bars in the tensile zone of the concrete beam so that the
compressive bending stress is carried by concrete and tensile bending stress is carried by
steel reinforcing bars. Generally, in simply supported and Cantilever beans the tension zone
occurs at bottom and top of beam respectively.
CHAPTER 4: EXCAVATION
4.1 EXCAVATION DETAILS
Plain cement concrete is a cement mixture commonly used for paving and flooring
and also known as PCC. It is one of the most important element in a building
structure. PCC is laid on the soil surface and acts as shield for the reinforced concrete
against direct contact with soil and water.
Then the surface was ready for the P.C.C. work.
After hardening the surface, column footing marking was started as per drawing.
The foundation plan is a plan view drawing, in section, showing the location and size
of footing, distance between two columns.
Here the footing shape is isolated footing was used as per drawing.
All the reinforcement was cut and fixed as per design.
After that all column footings were placed on their marked area.
50MM cover used for footing at bottom.
17.15CUM
Fig 7.1 Column starter in Aanganwadi Fig 7.2 Column starter in residential
building
Formwork of beam:
Wooden ply sheets and supports used for the beam formwork.
In beam formwork ply sheets cut in beam size and made bottom of beam.
Then the bottom formwork of the beam is set up in their position.
Beam bottom supported and fixed on columns.
After that all side formwork was set up.
Formwork of slab:
Steel plates were used in slab formwork and wooden supports were used.
Steel plates were fixed with beam formwork.
Fig 8.2 Shuttering of Beam Bottom and Slab Bottom in Residential Building
Below are some of the concrete test which is perform on concrete at site.
Equipment’s used:
1. The concrete shall be filled into the moulds in layers approximately 5 cm deep. It
would be distributed evenly and compacted either by vibration or by hand tamping.
After the top layer has been compacted, the surface of concrete shall be finished level
with the top of the mould using a trowel and covered with a glass plate to prevent
evaporation.
2. The specimen shall be stored at site for 24+1/2H under damp matting or sack. After
that, the samples shall be stored in clean water at 27+2°C; until the time of test. The
ends of all cylindrical specimens that are not plane within 0.05 mm shall be capped.
3. Just prior to testing, the cylindrical specimen shall be capped with Sulphur mixture
comprising 3 parts Sulphur to I part of inert filler such as fire clay.
4. Specimen shall be tested immediately on removal from water and while they are still
in wet condition wet condition.
5. The bearing surface of the testing specimen shall be wiped clean and any loose
material removed from the surface. In the case of cubes, the specimen shall be placed
in the machine in such a manner that the load cube as cast, that is, not to the top and
bottom,
6. Align the axis of the specimen with the steel plates, do not use any packing.
7. The load shall be applied slowly without shock and increased continuously at a rate
of approximately 140 kg/sq.cm/min until the resistance of the specimen to the
increased load breaks down and no greater load can be sustained. The maximum load
applied to the specimen shall then be recorded and unusual features noted at the time
of failure brought out in the report.
8. Compressive strength (kg/cm2) =W/A
Grade : M25
10.2 TRANSPORTATION:
The process of carrying the concrete mix from the place of it's mixing a final position of
deposition is termed as transportation of concrete. There are many methods of
transportation as mentioned below
Transport of concrete by pans
Transport of concrete by barrows
Transport of concrete by tipping lorries
When the concrete has been placed, it shows a very loose structure. Hence, it must be
compacted to remove the air bubbles and voids so as to make it dense and solid concrete
to obtain a high strength. There are two method of compaction. Manual compaction
Generally, in large projects mechanical compactors are used. There are various
mechanical compactors which uses according to requirement as needle vibrator and soil
compaction machine needed to compact the column and soil respectively.
For Various lengths cutting Metal cutting machines are machine tools used to fabricate
parts by the removal of material, typically metal. At the site all the reinforcement bars are
available at length of 12 meter. So, it is not possible to use a single 12-meter length bars
so we would use the metal cutting machine to cut the bars as per requirement.
The bricks are obtained by moulding clay in rectangular block of uniform size and then
drying and burning these blocks. Brick masonry easy to construct compare stone
masonry. It is less time consuming and there is no need of skilled labour to construct it.
The bricks do not require dressing and the arty of laying bricks is so simple.
CLASS A
CLASS B
CLASS C
The bricks are prepared in various sizes. On the basis of size. BIS bricks are categories in
two parts.
MODULAR BRICKS:
BIS recommends a standard size of brick which is 190mm X 90mm X 90mm. With
mortar thickness, size of such a brick becomes 200mm X 200mm X 100mm.
TRADITIONAL BRICKS:
The brick of which size varies and not standardized known as traditional brick.
WEIGHT OF BRICK:
It is found that the weight of I cubic meter brick earth about 1800 kg. Hence the average
weight of a brick will be about 3 to 3.5 kg
STRETCHER
If brick laid along its length then front view of brick is known as stretcher.
HEADER:
If brick laid along its width, then front view of brick is known as header.
FROG:
It is top of brick. It provides strong bonding between two courses of masonry by filling
the mortar. It also consists the name of company
QUEEN CLOSER:
BAT:
This is piece of brick, considered in relation to the length of brick as half bat, three
quarter bat, etc.
The aim of the internship is to address more practical knowledge for student. So, I
found a practical knowledge at the site as much possible. The knowledge we have
learn in the class is helpful to get those practical or real work in the site and totally
different from the actual knowledge gained from the class. Thus I found some
The internship is a bridge between the theoretical knowledge and the practical or the reality
work at the field of construction or civil engineering work. I go to companies that already
working either as a consultant or a contractor. The responsibilities of the hosting company are
to teach student and shape them as a real site worker. My hosting company is a contractor
team and they help me in acquiring different knowledge in different positions.
This program played an important role to break the conventional thought that field works can
be only implemented by students who hold a degree or people who have an experience in
building construction. We were able to acquire a high level of confidence to deal with
problem that arises in a building construction.
Overall, the internship program laid sound foundation for us to start our career. We are proud
to be able to contribute toward nation building during the country’s extremely critical period
of the history. It will be definitely sensible to scale this practice up and to replicate in other
disciplines as well.