JADWAL PELAKSANAAN PEKERJAAN PEMAGARAN

Aug-22 Sep-22 Oct-22


No. Uraian Pekerjaan Bobot %
M11 M12 M13 M14 M15 M16 M17 M18 M19
1 Material Pagar 59,89% 14,97% 14,97% 14,97% 14,97%
2 Galian Pagar 2,01% 1,003% 1,003%
3 Pengurugan pagar kembali 0,80% 0,40% 0,40%
4 Pemagaran 37,31% 4,66% 4,66% 4,66% 4,66% 4,66% 4,66% 4,66% 4,66%
Total 100,00%
RENCANA PROGRESS KUMULATIF 15,97% 36,61% 56,65% 76,68% 81,35% 86,01% 90,67% 95,34% 100,00%
REALISASI PROGRESS HARIAN
REALISASI PROGRESS KUMULATIF
DEVIASI