PUBLIC WORKS DEPARTMENT (R & B) KASHMIR

Detailed Project Report


For
Construction of District Prosecution Headquarter Ganderbal

PROJECT COST = Rs 302.66 Lacs

PWD (R&B) Ganderbal Division


APPLICATION FOR ACCORD OF ADMINISTRATIVE APPROVAL
CONSTRUCTION OF DISTRICT PROSECUTION HEADQUARTER GANDERBAL

AUTHORITY:- Deputy Director Prosecution Ganderbal

HISTORY AND NECESSITY:-

Govt. of J&K envisages to provide doorstep delivery of services to its citizens. In order to
achieve this goal, the Government aims to provide better facilities to employs so as to increase their
efficency and delivery. Keeping up with the same , the Government aims to construct District Prosecution
Headquarters. As such the DPR for construction has been prepared as per the space requirements
conveyed by the Deputy Director Prosecution, Ganderbal, and comprises of RCC Framed two storey
structure with provison for Land Development and other ammenities.

The AAA has been framed on CPWD Plinth area Schedule of 2023

PROPOSAL:-

PROPOSED ACCOMMODATION:-

Ground Floor:
General Branch : 20'-9" x 12'-0"
Sr Prosecuting Officer Room (2 No) :
12'-0" x 12 '-0"
Account Section : 14'-0" x 12'-0"
Recipt Dispatch : 12'-0" x 10'-0"
Store Room : 20'-0" x 12'-0"
Meeting Hall : 19'-2" x 20'-0"
Wash Room 3 No
First Floor:
Deputy Director Office : 11'-0" x 18'-0"
Retiring Room : 12'-0" x 12 '-0"
PA Section : 12'-0" x 12 '-0"
Legal/Crime Section : 14'-0" x 12'-0"
Establishment Section : 12'-0" x 10'-0"
Record Room : 20'-0" x 12'-0"
Reader Room : 10'-0" x 12'-0"
Meeting Hall : 19'-2" x 20'-0"
Wash Room 3 No
COST AND TIME OF COMPLETION:-

The Cost of the project shall be: 306.22 Lacs

The work shall be completed in two working season subject to availibity of funds and Encumberance free
Land.

Assistant Executive Engineer, Executive Engineer,


(R&B) Sub-Division, Ganderbal , (R&B) Ganderbal Division

Superintending Engineer,
(R&B) Circle Ganderbal
GENERAL ABSTRACT OF COST FOR:
CONSTRUCTION OF DISTRICT PROSECUTION HEADQUARTER GANDERBAL

Amount (In
S.No. Item Description Unit Qty Rate Lacs)
A Construction Cost:
1 Counstruction of RCC Framed Sqm 508.11 54331.69 276.06
Structure

2 Land Development by Way of Filling sqm 1011.15 2100.00 21.23


(For Two Kanals upto 1.8 m Dept)

TOTAL (A) 297.30

Add Cost of Work Charges & 8.92


Contengies 3%

GRAND TOTAL 306.22

Say 306.22 Lacs

Assistant Executive Engineer Executive Engineer


(R&B) Sub-Division, Ganderbal (R&B) Ganderbal Division
ESTIMATE OF COST
FOR
CONSTRUCTION OF DISTRICT PROSECUTION HEADQUARTER GANDERBAL

Estimate Framed on:


Type of Building RCC Framed Structutre
No Of Floors 2 Plinth Area Schedule 2023
Ground Floor Area 254.05 Sqm
First Floor Area 254.05 Sqm
Built up Area 508.11 Sqm

Unit Qty Rate Amount

Floor Height 3.60 mtr sqm 508.1052416 30820 15659803.55

Total A 15659804
Every 0.3 mt. Deeper foundations over normal
depth of 1.20 mtr. (on G.F. Area only for 0.90 sqm 254.05 421 106956.1534
mtr deeper than normal)

Pile Foundation upto a Depth of 15. 0 mtr


sqm 254.05 19460 4943864.001
(ground floor only)

Automatic Fire Alarm system sqm 254.05 600 152431.5725

Total (A)
Total B 5203252
ADDITIONAL ITEMS
Steel Truss (provided @ 45.0 Kgs/Sqm of the plinth
a Kgs 13718.84152 138.00 1893200
area*1.2 )
Roofing using Color Coated GI Sheets (0.63mm
b thick) of approved brand over steel trusses (@30% Sqm 330.2684071 1350.00 445862
extra over plinth area)

c Provison for Septic Tank/Soakage Pit /Water Tank NO 3.0 150000.00 450000

Services
Internal water supply & sanitary installation 4 % of (A) 626392
External Electric Service Connection 3.75 % of (A) 587243
Reade
Internal Electric Installation 12.5 % of (A) 1957475
Power Wiring and Plugs 4% of (A) 626392
Provison For Third Party Quality Assuarance 1% of (A) 156598
Total C 6743163
Total A +B+ C 27606218

Assistant Executive Engineer Executive Engineer


(R&B) Sub-Division, Ganderbal (R&B) Ganderbal Division