You are on page 1of 3

Client: Project : Contractor:

Contract : _
No.
Doc. Type : Method Statement (MTS)
Title : RA For Construct and Operate Detours
Doc. No. :
PMC Supervision Consultant:

Project Name WADI SAFAR Related Documentation/ Legislation

Routine non-Routine Emergency Task/Activity: Construct and Operate Detours RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Original Risk Original Risk with Residual Risk with
Without Controls Present Control Additional Control
Haza
Affe Additional Control Measures
SN Risk Control Measure Already in Use rd
Rate Iden
cted
Risk
Needed Rate
Pers
S L tifie S L
on
(1-5) (1-5) d (1-5) (1-5)

Mobilization of 1-Ensure that all personnel are inducted by the RTCC HSE
Equipment & Serious Injury or Department.
1 Concreate Barrier Operation Team even fatal injury 5 3 15 2-All persons are skilled and trained for the job & they are 5 2 10
Workers During could occur fully aware of Job hazards.
construction stage Ensure that all personnel take part in the toolbox meeting
and Discussion.
2 Working under Workers Failure to consider 4 3 12 Monitor temperature and humidity throughout the day 4 2 8 Supervision of the activity by the 4 1 4
direct sunlight weather / climate Use heat Index and stop work if required as per competent person.
Site Staff
Workers exposed to index Do not allow works in sunlight for extended time (15 Weather monitoring should be performed
heat Weakness min max) at all the working hours-Continuously
Unconscious
Heat stress,
Heat stroke,

IF THE RESIDUAL RISK RATING IS 16 OR ABOVE, then additional controls need to be developed for the activity
Legend: S àSeverity and LàLikelihood: Hierarchy of Controls: Elimination, Substitution, Engineering, Administrative, PPE
LIKELYHOOD
Very Unlikely Unlikely Likely Very Likely Almost Certain
SEVERITY 1 2 3 4 5
Catastrophic 5 5 10 15 20 25
Critical 4 4 8 12 16 20 Prepared By: Approved By:
Serious 3 3 6 9 12 15
Medium 2 2 4 6 8 10 Engr. Engr.
Minimal 1 1 2 3 4 5 Logistic DEPARTMENT HSE MANAGER

REV-00 Page 1 of 3
Client: Project : Contractor:
Contract : _
No.
Doc. Type : Method Statement (MTS)
Title : RA For Construct and Operate Detours
Doc. No. :
PMC: Supervision Consultant:

Routine non-Routine Emergency Task/Activity: Construct and Operate Detours RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Original Risk Original Risk with Residual Risk with
Without Controls Present Control Additional Control
Haza
Affe Additional Control Measures
SN Risk Control Measure Already in Use rd
Rate Iden
cted
Risk
Needed Rate
Pers
S L tifie S L
on
(1-5) (1-5) d (1-5) (1-5)
De-hydration,
Fatality
Illness due to
temperature
extremes e.g.
Irrational and / or
violent behaviour

 TTMP shall be Implemented on the job location


 Ensure that all slinging parts are checked and in a safe
condition to avoid collapse of concrete barrier
Operation team and may crush injuries,  Lifting permit and plan shall be prepared by the
3 Lifting Operation working/passing or worse, if the 5 3 15 competent person. 5 5 5
near by collapse  Proper supervision shall assigned on the operation.
 Ensure that the concrete barrier are stable
 Awareness training to the workers to be aware what are
the hazards regarding of concrete blocks

 Speed humps shell be installed.


Pedestrian and  Speed limit sing board will be installed
Over speeding others Road Users Strick by vehicle
4 5 3 15  Proper safety induction and training shall be given to all 5 1 5
driving /fatal or injury
drivers and operators
 Applying sufficient violation ticket system at site

5 Zero gap between concreate barrier shall be applied. Mechanical joint will be provided
between concrete barrier if needed.

Page 2 of 3
Client: Project : Contractor:
Contract : _
No.
Doc. Type : Method Statement (MTS)
Title : RA For Construct and Operate Detours
Doc. No. :
PMC: Supervision Consultant:

Routine non-Routine Emergency Task/Activity: Construct and Operate Detours RA No: REVISION 0
RISK ASSESSMENT RISK CONTROLS
Original Risk Original Risk with Residual Risk with
Without Controls Present Control Additional Control
Haza
Affe Additional Control Measures
SN Risk Control Measure Already in Use rd
Rate Iden
cted
Risk
Needed Rate
Pers
S L tifie S L
on
(1-5) (1-5) d (1-5) (1-5)
All needed safety and traffic sign board will be
installed
Cars fallen on cliff All Road
area Users Car crash /fatal
/injury 5 4 20 5 2 10 5 1 5

Car crash /fatale


6 Blind spots at road All drivers 5 3 15  All needed safety sign boards will be installed 5 1 5
/injury
 Reflected mirrors will be installed at all road curves

Page 3 of 3

You might also like