You are on page 1of 2

MEASUREMENT BOOK

NAME OF DIVISION EXECUTIVE ENGINEER PW(R&B) DIVISION CHADOORA


NAME OF SUB-DIVISION PW(R&B) SUBDIVISION CHADOORA
WORK ID (JKPWDOMS) RD/U/1689338424018

Improvement/ Upgradation of inner links of Wanbal Kralpora road by way of P/L of WBM GII, 75mm thick wet mix
NAME OF WORK
macadam, 50mm thick bituminous macadam, 25mm thick semidense with 6mm thick seal coaT

M/s Valley road construction company,Lasjan,Sgr


Name of contractor
M.P Faroz Ahmad Mir S/O Jalal ud din Mir R/O Uri chersoo, Pulwama.
ALLOTMENT NO. 5601-04 DATED: 8/12/2023
S.No. OF BILL CC-1ST DOS 6/18/2023 DOC WIP
S.No. Description Of Item Quantity unit Rate Amount
Providing/ Laying, Spreading and Compacting 75mm thick wet mix with graded stone aggregate size ( 53 mm - 0.075 mm) as per
1 the specifications and as per specifications of engineer in charge

RD L W W(Avg) SA(Avg)
0 - 5.75 - -
2 2 4.2 4.98 9.95
17 15 3.45 3.83 57.38
Lane no.1
32 15 3.35 3.40 51.00
47 15 3.55 3.45 51.75
50.9 3.9 4.45 4.00 15.60
0 - 4.25 - -
3.4 3.4 3.15 3.70 12.58
18.4 15 3.35 3.25 48.75
33.4 15 3.25 3.30 49.50
Lane no.2 48.4 15 2.35 2.80 42.00
63.4 15 3.35 2.85 42.75
78.4 15 3.25 3.30 49.50
93.4 15 3.25 3.25 48.75
108.4 15 3.25 2.80 42.00
0 - 4.55 - -
1.5 1.5 3.25 3.90 5.85
16.5 15 3.35 3.30 49.50
31.5 15 3.55 3.45 51.75
Lane no.3 46.5 15 3.55 3.55 53.25
61.5 15 3.75 3.65 54.75
76.5 15 3.55 3.65 54.75
91.5 15 3.45 3.50 52.50
105.7 14.2 3.55 3.55 50.41
0 - 5 - -
2 2 3.75 4.38 8.75
17 15 3.65 3.70 55.50
32 15 3.55 3.60 54.00
Lane no.4
47 15 4.25 3.90 58.50
62 15 3.45 3.85 57.75
77 15 3.65 3.55 53.25
89.3 12.3 3.45 3.55 43.67
TOTAL SA (SQM) 1225.68 sqm A
@{(0.60+0.075+0.090)/3} mm thick (avg) 91.93 cum 1555.160 142959.64
Providing and applying tack coat on W.B.M. @ 0.75 Kg/sqm using hot straight run bitumen of grade VG-10, including heating the
bitumen, spraying the bitumen with mechanically operated spray unit fitted on bitumen boiler, cleaning and preparing the existing
2 road surface as per specifications.

RD L W W(Avg) SA(Avg)
0 - 5.75 - -
2 2 4.2 4.98 9.95
17 15 3.45 3.83 57.38
Lane no.1
32 15 3.35 3.40 51.00
47 15 3.55 3.45 51.75
50.9 3.9 4.45 4.00 15.60
0 - 4.25 - -
3.4 3.4 3.15 3.70 12.58
18.4 15 3.35 3.25 48.75
33.4 15 3.25 3.30 49.50
Lane no.2 48.4 15 2.35 2.80 42.00
63.4 15 3.35 2.85 42.75
78.4 15 3.25 3.30 49.50
93.4 15 3.25 3.25 48.75
108.4 15 3.25 2.80 42.00
0 - 4.55 - -
1.5 1.5 3.25 3.90 5.85
16.5 15 3.35 3.30 49.50
31.5 15 3.55 3.45 51.75
Lane no.3 46.5 15 3.55 3.55 53.25
61.5 15 3.75 3.65 54.75
76.5 15 3.55 3.65 54.75
91.5 15 3.45 3.50 52.50
105.7 14.2 3.55 3.55 50.41
0 - 5 - -
2 2 3.75 4.38 8.75
17 15 3.65 3.70 55.50
32 15 3.55 3.60 54.00
Lane no.4
47 15 4.25 3.90 58.50
62 15 3.45 3.85 57.75
77 15 3.65 3.55 53.25
89.3 12.3 3.45 3.55 43.67
0 - 5.1
Stretches on main road
12.6 12.6 5.3 5.20 65.52
L W
Patches on main road
1.4 3.4 4.76
TOTAL SA (SQM) 1295.96 sqm 61.30 79442.348
Providing and applying 50 mm thick Bituminous Macadam base course with stone agg. Of quantity size and grading as specified in
CPWD specifications and straight run bitumen of 80/100 @ 3% by weight of total mix incld. hot mixing of stone agg. and bitumen
in hot mix plant, transporting and laying mixed material with paver finisher to the required level and grade, rolling with road roller
of 8-10 tonne capacity to achieve the required compaction and density incld. Cost and carriage of all materials involved upto site of
3 work complete, tools, plants, equipments and all allied machinery, labour taxes, fee, testing charges for maintaining quality control
during and after execution of work complete in all respects incld. Cost and carriage of bitumen.

Qty vide item no. 2 1295.96 sqm


@{(0.025+0.050+0.075)/3} mm THICK (avg) 64.80 cum 7084.150 459038.75
Providing and laying 25 mm thick Semidense bituminous concrete using material agg. Satisfying the gradation set out in
specification with 4% binder content ( by weight of total mix) bitumen of grade VG 10 with the laid of hot mix plant and paver
finisher incl. rolling with 8-10 tonne capacity road roller to achieve the required compaction and density (with bitumen 80/100) incl.
cost and carriage of all materials involved upto site of work complete, tools, equipments and all allied machinery, labour, taxes, fee,
4 testing charges for maintaining quality control during and after execution of work complete in all respects incl. cost and carriage of
bitumen including all carriages.

Qty vide item no. 2 1295.96 sqm 241.70 313233.532


Providing and laying seal coat of premixed fine aggregate (passing 2.36 mm and retained on 180 micron sieve) with bitumen using
128 kg of bitumen of grade VG-10 bitumen per cum of fine aggregate and 0.60 cum of fine aggregate per 100 sqm of road surface
5 including rolling and finishing with road all complete.

Qty vide item no. 2 1295.96 sqm 83.610 108355.22


TOTAL 1103029.48546
DEDUCT 30.53 %BELOW 336754.90
NET AMOUNT 766274.58
ADD 18 % GST 137929.43
NET PAYABLE AMOUNT 904204.01