MẪU PHIẾU THAO TÁC

CHALEUN SEKONG
ENERGY- NK3 HPP
OPERATION SHEET
OPERATION WORKSHOP

Operation ticket name: Isolate line 171 for repair................................................................................


Vote writer: .......................................................... Position:...................................................................
Vote reviewer: ...................................................... Position:..............................................................
Vote Supervisor: ..................................................Position:..............................................................
.....................................................................................................................................................................
Vote operator: …...................................................... Position:...............................................................
.....................................................................................................................................................................
Purpose of operation: Isolate line 171 for repair........................................................
Intend time:
Begin: .................... h .......... Day..................Month ............... Year....................................................
End: ……........... h ........... Day ..................Month ............... Year ...................................................
The unit recommends the operation: Repair workshop.............................................................................
Necessary conditions for implementation: (if any)
1. ...............................................................................................................................................................
2.................................................................................................................................................................
3.................................................................................................................................................................
Note: (if any)
1..................................................................................................................................................................
2..................................................................................................................................................................
3..................................................................................................................................................................
3..................................................................................................................................................................

Delivery and acceptance of electrical lines and equipment before operation: (if any)
Vote: / /

Page number: /

Time Workshop Full name Content

Sequence of operation items:


Location Sequence of operations Time Person

Item Get
Step Content Made Begin End Command
order

I Factory 1 Ask for A0 and stop


generating units H1, H2, H3
2 Check MC901, MC902,
MC903 and QE1, QE2, QE3
open well
3 Convert self-use to region
grid or diesel generator
4 Open MC941, check open
well
5 Open MC942, check open
well
6 Open MC971, check open
well
7 Open MC972, check open
well
8 Open MC931, check open
well
9 Open MC932, check open
well
10 Open MC131, check open
well
11 Open MC132, check open
well
12 Open MC171, Isolate control
and power sources
II Switchyard 13 Open MC173, Isolation of
control and resource sources
Vote: / /

Page number: /

III Factory 14 Open DCL 171-7, Control


and resource isolation
IV Switchyard 15 Open DCL 173-7, Control
and resource isolation
V Factory 16 Check line 171 has no power

17 Close DTĐ 171-76 check


close well

VI Switchyard 18 Close DTĐ 173-76 check


close well

19 Open AB TU173

VII Factory 20 Open AB TU171

21 Implement safety measures,


post signs, barricades and
allow the work team to work

Delivery and acceptance of electrical lines and equipment after operation: (if any)
Time Workshop Full name Content

Day.........Month........Year....... Day.........Month........Year.......

Vote writer Vote reviewer

(Sign and write full name) (Sign and write full name)

Abnormal events during operations:………………………………….................................................


……………………………………………………………………………………………………………
Person performing the operation
Day.........Month........Year.......

Supervisor The operator


Vote: / /

Page number: /

(Sign and write full name) (Sign and write full name)

Diagram: (attached if necessary)