Professional Documents
Culture Documents
From the Financial Year 2024, the Project Definition is provided at the Cost Center level (Section Office instead
of Circle Level) for Distribution related estimates and Non Scheme Estimates. Each Cost Center will have a
separate Project Definition, and the users are instructed to create the estimates under their respective Cost
Center Project Definition only. These changes are being done to avoid following errors:
1. Movement not allowed even after the work order getting approved
2. Work order approver is unable to approve the work order.
3. Investment Updation failed issue.
4. User unable to create WBS estimate while another user is approving work order
5. More load on single project definition.
Example: DW-24A-22063108
DW – Distribution Work (For now, this project definition is being rolled out only for Distribution
Circles)
T-Code ZPSES
Note: Do not type or edit any other characters. Please use only the search option to get the data
into the all field. Please follow the instructions scrupulously.
Step 1:
1. In project def. Give your respective Cost Center project definition. Ex. DW-24A-22063108
2. Click enter
3. Click search button (F4) in the field WBS element
Step 2:
Step 3:
Step 4:
1. In WBS estimate number type 2nd level WBS element (WBS Cost Center) and then type “-001” as
estimate number for creating first estimate. For further estimates, change the last digits as 002, 003
004 and so on.
2. Give Estimate description and click enter it will lead to estimate creation screen.
Create estimate by adding material and labour in the activity as done previously.
Note:
While creating the next further estimates, follow the same procedures as explained above from step 1 to Step
3. For the Step 4, Click search button in field WBS Estimate Number (as shown below)
1. Select the last estimate number and change the estimate number to next series number as shown
below
All the remaining steps from Recording estimate approval till WO Closure are the same as
followed till now. Please make note of the changes in the Project Definition and WBS element to
be filled wherever applicable.
Input Fields (To be taken for Example purpose only and to be adopted as applicable):
After giving data Click Execute button and it will lead to ZPSESR working Screen:
Work order Approval and Final Closure T-Code ZPSESWO:
Input Fields:
After giving data Click Execute button to go to Work Order approve screen.