Tank No. : No.1 Double Hull Side Tank (P) Tank Protection 1) C, A
Areas under consideration Remarks 4)
Double Hull Side Tank
Upper Middle Lower
Fore Transverse Bulkhead F G G
Aft Transverse Bulkhead F G G
Side Shell F F F
Longitudinal Bulkhead G G G
Deck G
Bottom G
JSKS-SHQE FORM-JP-06-47V(1/3)/1/2011.05. 18
REKAMAN INSPEKSI TANKI BALAS
BALLAST TANK INSPECTION RECORD
Photos;
JSKS-SHQE FORM-JP-06-47V(2/3)/1/2011.05. 18
REKAMAN INSPEKSI TANKI BALAS
BALLAST TANK INSPECTION RECORD
Tank No. : No.1 Double Hull Side Tank (P) Tank Protection 1) C, A
Areas under consideration Remarks 4)
Double Hull Side Tank
Upper Middle Lower
Fore Transverse Bulkhead
Aft Transverse Bulkhead
Side Shell
Longitudinal Bulkhead
Deck
Bottom
JSKS-SHQE FORM-JP-06-47V(3/3)/1/2011.05. 18
REKAMAN INSPEKSI TANKI BALAS
BALLAST TANK INSPECTION RECORD
JSKS-SHQE FORM-JP-06-47V(4/3)/1/2011.05. 18