Professional Documents
Culture Documents
PREPARED FOR:
TECHNICAL REPORT
INDEX
2.0 REFERENCES............................................................................................................................... 3
3.0 CONSIDERATIONS....................................................................................................................... 4
3.1 Jack-Ups........................................................................................................................................ 4
5.1 Interferences with ACTIVO Central and PPL Pacific Class 400................................................12
5.2 Interferences with ACTIVO Satellite and PPL Pacific Class 400..............................................14
6.1 Interferences with ACTIVO Central and KEPPEL FELS Super A..............................................16
6.2 Interferences with ACTIVO Satellite and KEPPEL FELS Super A............................................18
7.1 Interferences with ACTIVO Central and KEPPEL FELS Super B..............................................20
7.2 Interferences with ACTIVO Satellite and KEPPEL FELS Super B............................................22
10.0 CONCLUSIONS............................................................................................................................. 27
11.0 RECOMMENDATIONS.................................................................................................................. 27
Rev.
TECHNICAL REPORT PAGE: 3 OF 31
Date: FEB
2.0 REFERENCES.
The considerations taken to generate this document are based in the standards, regulations and
recommended practices listed in the table below and should be taken in the latest edition unless otherwise
indicated.
RenewableUK by London Offshore Guidelines for the Selection and Operation of Jack-ups in the
[1]
Consultants. Marine Renewable Energy Industry.
3.0 CONSIDERATIONS
For these assessment we are consider different classes of Jack Ups, one specific model of crane and a
minimum value in the Air Gap to discard possible clashes or interferences between both structures.
3.1 Jack-Ups
COSL CJ-46
Rev.
TECHNICAL REPORT PAGE: 5 OF 31
Date: FEB
Its necessary take special attention in a possible overhang outside of the beam clearance, of certain units
during handing
We are considering a value of 98 ft to use in the air gap dimension (Figure 3 -3).
The hull elevation used in the arrangement shall comply with the requirements specified in:
A hull elevation resulting in at least 1,5 m clearance between the assessment return period extreme wave
crest elevation and the underside of the hull shall be provided (Table 1 REF. 2).
The minimum clearance between the jack-up hull and an adjacent structure or another floating vessel during
positioning should not be less than 3.0 meters at any point during the positioning operation (Table 1 REF. 1)
DRILL FLOOR
ENVELOP
DRILL FLOOR
ENVELOP
In the centered position at first look we don’t have possible interference between the cantilever or drill floor
and some elements over the main deck of Structure as shown in the Figure 4 -6
In the port position of the drill floor over the wells area we noticed a possible interference with the crane and
drill floor as shown in the Figure 4 -7, for this reason we check the elevations in this arrangement to
corroborate the possibility to have a clash between these elements.
For the elevation arrangement we consider minimum 98 ft for the Air Gap. With this consideration we confirm
the null possibility to have a clash between the drill floor and the crane as shown in the Figure 4 -8 with
31.89ft (9.72m) of clearance between crane and the bottom of the drill floor.
In the stbd position of the drill floor over the wells area we don’t noticed a possible clash with some element
over the main deck.
Rev.
TECHNICAL REPORT PAGE: 9 OF 31
Date: FEB
CO
CLEARANCE 9.72m
CO
DRILL FLOOR
ENVELOP
DRILL FLOOR
ENVELOP
5.1 Interferences with ACTIVO Central and PPL Pacific Class 400
In the centered position at first look we don’t have possible clashes between the cantilever or drill floor and
some elements over the main deck of Structure as shown in the Figure 5 -13
In the port position of the drill floor over the wells area we noticed a possible clash with the crane and drill floor
as shown in the Figure 5 -14, for this reason we check the elevations in this arrangement to corroborate the
possibility to have a clash between these elements.
For the elevation arrangement we consider minimum 98 ft for the Air Gap. With this consideration we confirm
the null possibility to have a clash between the drill floor and the crane as shown in the Figure 5 -15 with
7.55ft (2.30m) of clearance between crane and the bottom of the drill floor.
In the stbd position of the drill floor over the wells area we don’t noticed a possible clash with some element
over the main deck.
Rev.
TECHNICAL REPORT PAGE: 13 OF 31
Date: FEB
CLEARANCE 2.30m CO
CO
5.2 Interferences with ACTIVO Satellite and PPL Pacific Class 400
In the case of the works with ACTIVO Satellite we don’t noticed a clash or interference between the drill floor
and some element over the main deck as shown in the Figure 5 -16 and Figure 5 -17.
DRILL FLOOR
ENVELOP
DRILL FLOOR
ENVELOP
In the port position of the drill floor over the wells area we noticed a possible clash with the crane and drill floor
as shown in the Figure 6 -21, for this reason we check the elevations in this arrangement to corroborate the
possibility to have a clash between these elements.
For the elevation arrangement we consider minimum 98ft for the Air Gap. With this consideration we confirm
the null possibility to have a clash between the drill floor and the crane as shown in the Figure 6 -22 with
10.93ft (3.33m) of clearance between crane and the bottom of the drill floor.
In the stbd position of the drill floor over the wells area we don’t noticed a possible clash with some element
over the main deck.
Rev.
TECHNICAL REPORT PAGE: 17 OF 31
Date: FEB
CLEARANCE 3.33m CO
In the case of the works with ACTIVO Satellite we don’t noticed a clash or interference between the drill floor
and some element over the main deck as shown in the Figure 6 -23Error: Reference source not found and
Figure 6 -24.Error: Reference source not found
DRILL FLOOR
ENVELOP
DRILL FLOOR
ENVELOP
In the centered position at first look we don’t have possible clashes between the cantilever or drill floor and some
elements over the main deck of Structure as shown in the Figure 7 -27.
In the port position of the drill floor over the wells area we noticed a possible clash with the crane and drill floor as
shown in the Figure 7 -28Error: Reference source not found, for this reason we check the elevations in this
arrangement to corroborate the possibility to have a clash between these elements.
For the elevation arrangement we consider minimum 98 ft for the Air Gap. With this consideration we confirm the null
possibility to have a clash between the drill floor and the crane as shown in the Figure 7 -29 with 4.66ft (1.42m) of
clearance between crane and the bottom of the drill floor.Error: Reference source not found
In the stbd position of the drill floor over the wells area we don’t noticed a possible clash with some element over the
main deck.
Rev.
TECHNICAL REPORT PAGE: 21 OF 31
Date: FEB
CO
CLEARANCE 1.42m
In the case of the works with ACTIVO Satellite we don’t noticed a clash or interference between the drill floor
and some element over the main deck as shown in the Figure 7 -30Error: Reference source not foundError:
Reference source not found and Figure 7 -31.Error: Reference source not foundError: Reference source not
found
DRILL FLOOR
ENVELOP
DRILL FLOOR
ENVELOP
COSL CJ-46
In the port position of the drill floor over the wells area we noticed a possible clash with the crane and drill floor
as shown in the Figure 8 -35, for this reason we check the elevations in this arrangement to corroborate the
possibility to have a clash between these elements.
For the elevation arrangement we consider minimum 98 ft for the Air Gap. With this consideration we confirm
the null possibility to have a clash between the drill floor and the crane as shown in the Error: Reference
source not found with 7.58ft (2.31m) of clearance between crane and the bottom of the drill floor.
In the stbd position of the drill floor over the wells area we don’t noticed a possible clash with some element
over the main deck.
Rev.
TECHNICAL REPORT PAGE: 26 OF 31
Date: FEB
COSL CJ-46
COSL CJ-46
CO
CLEARANCE 2.31m
COSL CJ-46
COSL CJ-46
10.0 CONCLUSIONS
With the consideration of the use 98 ft in the Air Gap for each RIG we obtain good results in the separation
between the Deck elements and Rig elements with possibilities of clash or interference.
If we compare the assessments of both Jackets (ACTIVO Central/Satellite) we can clearly see that
interference problems are between ACTIVO Central and the Jack-ups
Below is shown a table with the result of the assessment of clearance between the elements of the Jack-Ups
and the elements of ACTIVO Central.
Clearance
MODELO DE JACK-UP
Horizontal Vertical
F&G JU 2000e 13 ft 4.1 m 32 ft 9.7 m
PACIFIC CLASS 400 13 ft 4.1 m 7.6 ft 2.3 m
KEPPEL FELS SUPER A 13 ft 3.8 m 11 ft 3.3 m
KEPPEL FELS SUPER B 10 ft 3.1 m 4.7 ft 1.4 m
COSL CJ-46 26 ft 7.9 m 7.6 ft 2.3 m
Table 2 – Clearances between ACTIVO Central and Jack-Ups
In the Table 2 we can see the comparative of clearances with ACTIVO Central and Jack-Ups, with base in this
comparative we can see that the most unfavorable Jack-up is the Keppel Fels Super B class (Option 4) with
the most shorter clearance in both directions.
The Figure 10 -39 shows the horizontal clearance and Figure 10 -40 shows the vertical clearance between
ACTIVO Central and the Keppel Fels Super B class Jack-up
Rev.
TECHNICAL REPORT PAGE: 30 OF 31
Date: FEB
3.1m
1.4m
11.0 RECOMMENDATIONS
For the options 2, 4 and 5 the free height it does not provide a reasonable tolerance for possible adjustments
in the height of the pedestal crane, for this reason our suggestions are.
Take this three Jack-ups (options 2, 4 and 5) in the last use options unless increase the Air Gap 6ft
(1.8m).
Don’t reduce the value in the Air Gap to warranties cero interferences between the structures.
In the case of having to reduce the value of the AIR GAP take off the crane during the drilling works to
prevent equipment damage.
Is necessary the approbation of the operating area about the use of the considerations in the Air Gap.