GOVERNMENT OF JHARKHAND

झारखण्ड सरकार

Water Resources Department


जल ससं ाधन विभाग
Name of work – Cost estimate of Tenughat Dam under Dam
Rehabilitation and Improvement Project (DRIP).
Financial Year = 2024-25
ESTIMATED COST- Rupees

Chief Engineer zone = Hazaribagh


Circle = Tenughat Dam Circle
Division = Tenughat Dam Division, Tenughat.
Cost estimate for Tenughat Dam under Dam Rehabilitation and
Improvemnet Project (DRIP).

Cost Estimates of Rehabilitation Proposal


Sl.No. Work Description Amount in Rupees Remarks

Refer
A Structural Rehabilitation Works/Estimation Part Annexure-i
Estimate for rooting out and removal of vegetation of
1 Tenughat Dam Upstream slope as well as Downstream ₹ 1,48,13,011.0
slope as per DSRP 2021 Recommendation,
Estimate for Rearranging disturebd Rip Rap and
2 depressed patches as per DSRP Recommendation Page ₹ 1,99,67,885.0
30 U/S Slope(b)(ii)
Estimate for Closing down the gap in U/S Parapet wall
and providing continous parapet wall and Removal of Estimate has
3
different components as per DSRP 2021
₹ 14,66,650.0 been
Recommendation Page 30 (b)U/S Slope(iii) and (iv) prepared and
sent to
Estimate for Cleaning and Repair of longitudinal
department
4 ,transverse and toe drains as per DSRP 2021 ₹ 3,34,59,115.0 vide letter
Recommnedation of Page 30 ( C ) D/S Slope(iv) and (v).
number CE
Estimate for Removal of coffer dam in U/S of Tenu WRD
Bokaro Link Canal approach Channel and cleaning of HAZARIBAG
5
approach channel of TBLC as per Recommnedation of
₹ 39,19,483.0
103/DATED
DSRP 2021 from Page 26. 12/02/2024
Estimate for Filling the good quality compact earth
,Benching and Turfing in D/S slope of Tenughat Dam as
6
per DSRP Recommnedation from Page 30 ( C )D/S Slope
₹ 1,34,25,956.0
(ii) & (iii).

Estimate for Whitewashing of Parapet wall and painting


7
of Railing as per DSRP 2021Report Page Page 52 1.3.7
₹ 47,72,421.0

Total Amount in Rupees for estimation prepared as


per Jharkahnd SOR July 2022
₹ 9,18,24,521.0

Mechanical Repair and maintenance Part of Refer


B
Tenughat Dam Annexure ii
Maintenance of radial gates and their hoists mechanism
1
(Size of gate 50’ x 39’)
₹ 1,50,00,000.0

Maintenance of Under Sluice gates, emergency gate,


2 service gate and their hoists mechanism (Size of gate 8’ x ₹ 1,00,00,000.0
6’) as per IS code

1
Sl.No. Work Description Amount in Rupees Remarks
Maintenance of 70 M.T. Gantry Crane and of Lifting
3 beam. Following issues need to be considered and ₹ 30,00,000.0
attended during maintenance:
Stop log/Bulkhead Gates , Following issues need to be
4
considered and attended during maintenance
₹ 60,00,000.0

Repair, maintenance and overhauling of 125 KVA DG


5 sets complete job as per specification and direction of ₹ 6,00,000.0
E/I.

Repair, maintenance and overhauling of 75 HP VT pump


6
set complete job as per specification and direction of E/I.
₹ 8,00,000.0

Repair, maintenance and overhauling of manually


7 operated outlet gate and its mechanism parts of Tenu- ₹ 6,00,000.0
Bokaro Link canal.
Repair and maintenance of corrugated Galvanized Iron
sheets at Spillway of Tenughat Dam over radial gate
8
operation machines/ motors, all complete as per client
₹ 30,00,000.0
scope and specification
Repair and maintenance of Inspection (iron) bridge with
9 stairs in downstream side of spillway, all complete as per ₹ 40,00,000.0
client scope and specification

Maintenance of flap gates all complete as per client scope


10 and specification all complete as per client scope and ₹ 80,00,000.0
specification

Painting of all gates (radial gates, under sluice gates,


emergency gate, service gate etc.), civil structure,
mechanical equipment’s, hoist plaƞorm of radial gate,
11
footway bridge at Trunnion level etc. As per IS code
₹ 8,20,00,000.0
14177:199. This painƟng work will be done two times in
the period of three years i.e. at 1st year and 3rd year.

Maintenance and operation of radial gates, under sluices


gates, gantry crane, stoplogs, DG set, 75 HP VT pump,
12
flap gates, etc. as per the maintenance schedule of the
₹ 45,00,000.0
client (3 Year)
Supply and Installation of 125 KVA DG set as per
13
specification and direction of E/I
₹ 12,50,000.0

14 Repair and maintenance of Tenughat Dam control room ₹ 70,000.0

15 Gardening of Tenughat Dam control room lawn 3years ₹ 1,50,000.0


16 Clearing of vegetation of spillway portion 3 years ₹ 60,000.0

2
Sl.No. Work Description Amount in Rupees Remarks
17 Painting of Spillway portion of Tenughat Dam ₹ 19,70,000.0
Total amount without taxes in Rupees = ₹ 14,10,00,000.0
Net amount after 1% Rate negotiation in Rupees= ₹ 13,95,90,000.0
Add (18% GST in Rupees) = ₹ 16,47,16,200.0
Add 1% LC and 1/2% cnc in Rupees = ₹ 24,70,743.00
Grand Total in Rupees = ₹ 16,71,86,943.00

Structural Measures for Ensuring Hydrological Refer


C
Safety Annexure iii
a Spillway
(i)The U/S face in the non-¬overflow portion be checked
minutely and cracks/holes, if any observed, mapping be
1 done for such cracks by remote operated vehicle (ROV)
to assess the extents of damages. Cement/polymer
grouting be taken up in the U/S face.

(ii)All the reports, findings and video recording after


2 ROV mapping should be submitted to Office of the
Executive Engineer Tenughat Dam Division Tenughat.

(iii)However, if the mapping indicates presence of


more cracks / cavities, required remedial measures with EOI has been
advance technology is recommended to prevent such prepared and
sent to
seepages. The application of CCGM/CCGC
3 department
(Cementitious Geo-synthetic Concrete Mattress/Carpet)
vide letter
as per Standards of EN 13253 & 13254 as used in
number CE
Reservoir & Dams be adopted in the u/s face of the
WRD
spillway. HAZARIBAG
(iv)The cavities occurred in the piers be filled up with 1016/DATED
4
CC M-30 to make the surface smooth. 08/12/2023

(v)The damaged concrete surface of glacis below all


Tenughat Dam gates or wherever necessary be made
5 good with rich cement mortar and report about this
should be submitted to Office of the Executive Engineer
Tenughat Dam Division Tenughat.

(vi)The damage below the bottom of the deck slab be


6
made good with rich mortar.
(vii)The vegetation noticed over the retaining wall be
7 uprooted and removed and the cracks be made good using
rich cement mortar.

3
Sl.No. Work Description Amount in Rupees Remarks
b Gallery: Inspection and Drainage gallery.
Necessary remedial measures with application of
synthetic Cementous Concrete Mattress/Geo‐synthetic
Cementous Concrete Carpet (GCCM/GCCC) as per
1
Standards of EN 13253 & 13254 used in Dams, as
appropriate, be adapted in the u/s face of the dam.

Necessary chemical and physical analysis of the


2 deposited /Injected Mud be tested in the soil testing
laboratory for reference on remedial measure.
Chemical composition of mud and presence of organic
and inorganic substance test report which clearly
comprises the cause of deposition of mud and preventive
3
measures against this in future should be submitted to
Office of the Executive Engineer Tenughat Dam Division
Tenughat.
The calcinations occurred over the steps and floors
need to be removed. The U/S and D/S wall surface need EOI has been
4 prepared and
to be cleaned properly such that the walls will be free
from calcinations. sent to
department
Prepare the
vide letter
detailed report the report should comprise cause of
number CE
calcination and suggest the remedial measures to avoid
5 WRD
future calcination.
HAZARIBAG
1016/DATED
08/12/2023
The vertical drainage in inspection gallery and
6
foundation drainage holes are reamed and cleaned.
Chainage, Reduced levels and other necessary
information such as component specifications are to be
7 painted over the wall in each block with block numbers at
appropriate locations in English language with
illuminating paint colour.
Finding the cause of Seepage in Galleries and on d/s
8 face of the dam and provide feasible solution of this.

Removal of mud deposits, Presence of calcium and other


9 deposits from the drains inside the inspection gallery.

In inspection gallery there are leaching from the seepage


water and deposition of lime near the seepage of exit
10
spots, Finding the cause of this and provide feasible
solution of this.

4
Sl.No. Work Description Amount in Rupees Remarks

c Masonry/Concrete dams & Spillways

Cracking in concrete (potential causes are alkali –


aggregate reaction, thermal stresses because of heat of
hydration or temperature variations, foundation
problems). Prepare the detailed report on this and
1
submitted to Office of the Executive Engineer Tenughat
Dam Division Tenughat.

Repair to upstream face of masonry dams in case the


pointing is damaged, leading to increased seepage. To EOI has been
2 ensure that the dam is behaving as designed based on prepared and
instrumentation programs. sent to
department
Periodic maintenance should be performed of all concrete vide letter
surfaces to repair deteriorated areas. Repair deteriorated number CE
concrete at the earliest; it is most easily repaired in its WRD
HAZARIBAG
initial stages. Deterioration can accelerate and, if left
3 1016/DATED
unattended, can result in serious problems or dam failure.
08/12/2023
For this prepare the report which comprises types and
causes of concrete deterioration and use of most suitable
type of concrete.
Repair the Damages on spillway glacis, spillway piers,
training/divide walls, energy dissipaters, downstream
areas (probable causes are cavitation, abrasion,
4 unsymmetrical flows, unfavourable downstream
conditions). Prepare the detailed report on this and
submitted to Office of the Executive Engineer Tenughat
Dam Division Tenughat.

d Drains and Seepage


(i)Remove debris in and around the Tenughat Dam to
prevent clogging.
(ii)Remove debris and repair the small drainage
channels leading to the Tenughat Dam so that water is
properly directed and contained within the channels.
(iii)Clean algae and dirt from the Tenughat Dam staff
gauges to allow easy reading.
e Embankment Protection
(i)Provision of fences to provide site security and to Refer annexure
exclude livestock from the embankments. Repair ₹ 1,73,99,830.00 iv Estimate
damaged embankment surfaces. attached

5
Sl.No. Work Description Amount in Rupees Remarks

C Water Quality Aspects


(i) Chemical and physical analysis of reservoir water all
water tests should be done confirming IS Code IS 3025-11 (1983):
Methods of sampling and Test of water and waste water) and IS
Refer annexure V
10500:2012 ) and detailed test result report should be submitted to
Office of the Executive Engineer Tenughat Dam Division
₹ 21,45,780.00 Govt of Punjab
Rates attached.
Tenughat.Periodic chemical analysis of Tenughat Dam Reservoir
water from different location.(3 samples at 3 different locations per
week for one year =4585.00 rs. x 3 samples x 3 locations x 52 weeks)

D Non-structural Measures
Survey of Tenughat dam u/s land for acquisition and
1 E.O.I
rehabilitation problem

E Basic Facilities Improvement


2,58,93,456.00
funded by Rs.
Electrification of Tenughat dam top road ,dam gallery and R/M Government of
1 ₹ 0.00 Jharkhand and
of dam gallery
work is in
Progress

10% of
Maintenance of Electrical items and electrification of 25893456.00
2 ₹ 77,68,036.80 each year for 3
Tenughat Dam top road and Dam Gallery.
years

F Instrumentation, SCADA, Surveillance system, etc.


Work is in
Recommendation regarding Instrumentation, SCADA,
1 0.00 progress undr
Surveillance system, etc. NHP

G CCTV camera For Dam safety and monitoring

CCTV Camera installation on Tenughat Dam and nearby Refer


₹ 4,89,225.00
Control room under Tenughat Dam Division Tenughat. Annexure vi

G Others (investigation, Design Studies, Consultancy)


1 Consultancy charges of Emergency action plan EOI format
submitted in
2 Consultancy charges of Dam Break Analysis department vide
3 Consultancy charges of Geotechnical Investigation letter number CE
WRD HAZARIBAG
4 Consultancy charges of Geophysical Investigation 1016/DATED
5 Consultancy charges of Stability analysis and other studies 08/12/2023

Total Amount excluding EOI of dam safety in rupees= ₹ 28,68,14,335.80

J.E A.E Executive Engineer


Tenughat Dam Division,Tenughat

6
Annexure -I
झारखण्ड सरकार

Water Resources Department


जल संसाधन विभाग

Chief Engineer zone = Hazaribagh


Circle = Tenughat Dam Circle
Division = Tenughat Dam Division, Tenughat.
General Abstract of Cost for Estimates for DSRP 2021
Recommnedations under Tenughat Dam Division Tenughat
Cost of Estimate in
Sl.No. Name of Work
Rupees
Estimate for rooting out and removal of vegetation of
Tenughat Dam Upstream slope as well as Downstream slope
1
as per DSRP 2021 Recommendation on Page 30 (b)(i)U/S ₹ 1,48,13,011.00
Slope and Page 31 ( C ) D/S Slope (i).

Estimate for Rearranging disturebd Rip Rap and depressed


2 patches as per DSRP Recommendation Page 30 U/S ₹ 1,99,67,885.00
Slope(b)(ii)

Estimate for Closing down the gap in U/S Parapet wall


and providing continous parapet wall and Removal of
3
different components as per DSRP 2021
₹ 14,66,650.00
Recommendation Page 30 (b)U/S Slope(iii) and (iv)

Estimate for Cleaning and Repair of longitudinal ,transverse


4 and toe drains as per DSRP 2021 Recommnedation of Page 30 ₹ 3,34,59,115.00
( C ) D/S Slope(iv) and (v).

Estimate for Removal of coffer dam in U/S of Tenu Bokaro


Link Canal approach Channel and cleaning of approach
5
channel of TBLC as per Recommnedation of DSRP 2021 from ₹ 39,19,483.00
Page 26.

Estimate for Filling the good quality compact earth ,Benching


6 and Turfing in D/S slope of Tenughat Dam as per DSRP ₹ 1,34,25,956.00
Recommnedation from Page 30 ( C )D/S Slope (ii) & (iii).

Estimate for Whitewashing of Parapet wall and painting


7
of Railing as per DSRP 2021Report Page Page 52 1.3.7
₹ 47,72,421.00

Total in Rupees = ₹ 9,18,24,521.00

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

General Abstract of Cost 1


Unit -1

Rooting out and Removal of


vegetation of Tenughat Dam
Upstream slope as well as
Downstream slope as per
DSRP 2021 Recommendation
on Page 30 (b)(i) U/S Slope
and Page 31 (C) D/S Slope (i).
Abstract of cost of rooting out and removal of vegetation of Tenughat Dam Upstream slope as
well as Downstream slope as per DSRP 2021 Recommendation on Page 30 (b)(i)U/S Slope and
Page 31 ( C ) D/S Slope (i).

Sl.No. Item unit Qunatity Rate Amount

Clearing and grubbing road land


including uprooting rank
1
vegetation,grass,bushe,shrubs,saplin
Part A
gs and trees girth upto 300 mm by Hectare 117.124 88499.50 10365398.81
page 195
2.3(i)A manual means upto lead of 1000 m
in area of light jungle .(jh sor July
2022)

Clearing and grubbing road land


including uprooting rank
2
vegetation,grass,bushe,shrubs,saplin
Part A
gs and trees girth upto 300 mm by Hectare 17.937 108259.80 1941854.92
page 195
2.3(i)B manual means upto lead of 1000 m
in area of thorny jungle .(jh sor July
2022)

Total (A) ₹ 1,23,07,253.73


B =Add 18% GST of
2215305.67
(A)
C= Sub total = 14522559.40
1% Contigecy of C = 145225.59
1% Labor cess of C = 145225.59
Grand Total ₹ 1,48,13,010.59

₹ 1,48,13,011.00

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

AOC for Jungle clearance 1


Detailed estimate for rooting out and removal of vegetation of Tenughat Dam Upstream
slope as well as Downstream slope as per DSRP 2021 Recommendation on Page 30
(b)(i)U/S Slope and Page 31 ( C ) D/S Slope (i).

Distance from Horizontal Jungle on Avg slope


Chain Area in
Sl.No. Centre of View distance in Slope Length between Remark
Number square meter
Tower Meter In meter two chains

0 0.00 16.00 0.00


Centre of View Tower is
1 213.00 0.00 30.00 19.00 17.50 525.00 chain 213.00

Just 4 meter ahead of


2 212.00 30.00 30.00 30.00 24.50 735.00 flag post

3 211.00 60.00 30.00 35.60 32.80 984.00 Actual dam start

4 210.00 90.00 30.00 40.50 38.05 1141.50 upto RCD road


5 209.00 120.00 30.00 47.60 44.05 1321.50 upto RCD road

(36.00 + 18.00 (dam


6 208.00 150.00 30.00 54.00 50.80 1524.00 slope + toe drain )

7 207.00 180.00 30.00 60.00 57.00 1710.00


8 206.00 210.00 30.00 65.00 62.50 1875.00
9 205.00 240.00 30.00 70.00 67.50 2025.00
10 204.00 270.00 30.00 76.50 73.25 2197.50 Including Toe Drain

11 203.00 300.00 30.00 76.50 76.50 2295.00 Including Toe Drain

12 202.00 330.00 30.00 78.00 77.25 2317.50 Including Toe Drain

13 201.00 360.00 30.00 79.50 78.75 2362.50 Including Toe Drain

14 200.00 390.00 30.00 81.00 80.25 2407.50 Including Toe Drain

15 199.00 420.00 30.00 82.50 81.75 2452.50 Including Toe Drain

16 198.00 450.00 30.00 79.00 80.75 2422.50 Including Toe Drain

68.00 M before security


17 197.00 480.00 30.00 73.00 76.00 2280.00 gate towards OP

18 196.00 510.00 30.00 67.00 70.00 2100.00


Secuirty gate OP side
(541.00 m from CVP)
19 195.00 540.00 30.00 66.00 66.50 1995.00 distance btw both
security gates = 360.00M

Stairs
20 194.00 570.00 30.00 62.00 64.00 1920.00 downstream(548.00 M
from view point centre)

21 193.00 600.00 15.00 61.00 61.50 922.50


Exact spillway (45 m
22 193.50 615.00 15.00 61.00 61.00 915.00 from SG gate 1 towards
saram)

23 192.00 630.00 30.00 0.00 30.50 915.00 No slope concrete dam

24 191.00 660.00 30.00 0.00 0.00 0.00 No slope concrete dam

25 190.00 690.00 30.00 0.00 0.00 0.00 No slope concrete dam

Unit 1 -Detailed estimate for Jungle Clearance 1


26 189.00 720.00 30.00 0.00 0.00 0.00 No slope concrete dam

27 188.00 750.00 30.00 0.00 0.00 0.00 No slope concrete dam

28 187.00 780.00 30.00 0.00 0.00 0.00 No slope concrete dam

29 186.00 810.00 30.00 0.00 0.00 0.00 No slope concrete dam

30 185.00 840.00 30.00 0.00 0.00 0.00 No slope concrete dam

31 184.00 870.00 30.00 0.00 0.00 0.00 No slope concrete dam

32 183.00 900.00 30.00 82.00 41.00 1230.00 Security Gate Saram side

33 182.00 930.00 30.00 86.00 84.00 2520.00


34 181.00 960.00 30.00 90.00 88.00 2640.00
Peterbar Gumia road
35 180.00 990.00 30.00 98.00 94.00 2820.00 curve
36 179.00 1020.00 30.00 103.00 100.50 3015.00
37 178.00 1050.00 30.00 109.60 106.30 3189.00
38 177.00 1080.00 30.00 116.20 112.90 3387.00
39 176.00 1110.00 30.00 122.80 119.50 3585.00
40 175.00 1140.00 30.00 129.40 126.10 3783.00
41 174.00 1170.00 30.00 136.00 132.70 3981.00
42 173.00 1200.00 30.00 142.60 139.30 4179.00
43 172.00 1230.00 30.00 149.20 145.90 4377.00
44 171.00 1260.00 30.00 155.80 152.50 4575.00
45 170.00 1290.00 30.00 162.40 159.10 4773.00
46 169.00 1320.00 30.00 169.00 165.70 4971.00
47 168.00 1350.00 30.00 175.60 172.30 5169.00
48 167.00 1380.00 30.00 182.20 178.90 5367.00
49 166.00 1410.00 30.00 188.80 185.50 5565.00
50 165.00 1440.00 30.00 202.00 195.40 5862.00 Longest slope start

51 164.00 1470.00 30.00 198.00 200.00 6000.00


52 163.00 1500.00 30.00 192.00 195.00 5850.00
53 162.00 1530.00 30.00 195.00 193.50 5805.00
54 161.00 1560.00 30.00 196.00 195.50 5865.00
55 160.00 1590.00 30.00 195.00 195.50 5865.00
56 159.00 1620.00 30.00 191.00 193.00 5790.00 Longest slope end
In Google map Tenughat
57 158.00 1650.00 30.00 189.00 190.00 5700.00 Dam
58 157.00 1680.00 30.00 187.00 188.00 5640.00
59 156.00 1710.00 30.00 185.00 186.00 5580.00
60 155.00 1740.00 30.00 183.00 184.00 5520.00
61 154.00 1770.00 30.00 179.90 181.45 5443.50 Water in Toe drain

62 153.00 1800.00 30.00 176.80 178.35 5350.50 Big tree in upstream

63 152.00 1830.00 30.00 173.70 175.25 5257.50


64 151.00 1860.00 30.00 170.60 172.15 5164.50

Unit 1 -Detailed estimate for Jungle Clearance 2


65 150.00 1890.00 30.00 167.50 169.05 5071.50
66 149.00 1920.00 30.00 164.40 165.95 4978.50
67 148.00 1950.00 30.00 161.30 162.85 4885.50
68 147.00 1980.00 30.00 158.20 159.75 4792.50
69 146.00 2010.00 30.00 155.10 156.65 4699.50
70 145.00 2040.00 30.00 152.00 153.55 4606.50
71 144.00 2070.00 30.00 148.90 150.45 4513.50
72 143.00 2100.00 30.00 145.80 147.35 4420.50
73 142.00 2130.00 30.00 142.70 144.25 4327.50
74 141.00 2160.00 30.00 139.60 141.15 4234.50
75 140.00 2190.00 30.00 136.50 138.05 4141.50
76 139.00 2220.00 30.00 133.40 134.95 4048.50
77 138.00 2250.00 30.00 130.30 131.85 3955.50
78 137.00 2280.00 30.00 127.20 128.75 3862.50
79 136.00 2310.00 30.00 124.10 125.65 3769.50
80 135.00 2340.00 30.00 121.00 122.55 3676.50
81 134.00 2370.00 30.00 117.90 119.45 3583.50
82 133.00 2400.00 30.00 89.40 103.65 3109.50 Bharat Mata stairs

83 132.00 2430.00 30.00 82.20 85.80 2574.00


84 131.00 2460.00 30.00 81.20 81.70 2451.00
85 130.00 2490.00 30.00 80.00 80.60 2418.00
86 129.00 2520.00 30.00 85.00 82.50 2475.00
87 128.00 2550.00 30.00 85.00 85.00 2550.00
88 127.00 2580.00 30.00 85.00 85.00 2550.00
89 126.00 2610.00 30.00 85.00 85.00 2550.00
90 125.00 2640.00 30.00 85.00 85.00 2550.00
91 124.00 2670.00 30.00 85.00 85.00 2550.00
92 123.00 2700.00 30.00 88.90 86.95 2608.50
93 122.00 2730.00 30.00 95.00 91.95 2758.50
94 121.00 2760.00 30.00 95.50 95.25 2857.50
95 120.00 2790.00 30.00 95.80 95.65 2869.50
96 119.00 2820.00 30.00 95.00 95.40 2862.00
Transformer ka rasta
97 118.00 2850.00 30.00 96.20 95.60 2868.00 (Tiraha)

98 117.00 2880.00 30.00 93.00 94.60 2838.00


99 116.00 2910.00 30.00 89.50 91.25 2737.50
100 115.00 2940.00 30.00 86.00 87.75 2632.50
101 114.00 2970.00 30.00 82.50 84.25 2527.50
102 113.00 3000.00 30.00 79.00 80.75 2422.50
103 112.00 3030.00 30.00 75.50 77.25 2317.50

Unit 1 -Detailed estimate for Jungle Clearance 3


104 111.00 3060.00 30.00 72.00 73.75 2212.50
105 110.00 3090.00 30.00 68.50 70.25 2107.50
106 109.00 3120.00 30.00 57.50 63.00 1890.00
107 108.00 3150.00 30.00 51.50 54.50 1635.00
108 107.00 3180.00 30.00 45.50 48.50 1455.00
109 106.00 3210.00 30.00 39.50 42.50 1275.00
110 105.00 3240.00 30.00 33.50 36.50 1095.00
111 104.00 3270.00 30.00 27.50 30.50 915.00
112 103.00 3300.00 30.00 21.50 24.50 735.00
113 102.00 3330.00 30.00 15.50 18.50 555.00
114 101.00 3360.00 30.00 9.50 12.50 375.00
115 100.00 3390.00 30.00 9.00 9.25 277.50 Central Golamber

116 99.00 3420.00 30.00 42.00 25.50 765.00


117 98.00 3450.00 30.00 42.00 42.00 1260.00
118 97.00 3480.00 30.00 42.00 42.00 1260.00
119 96.00 3510.00 30.00 42.00 42.00 1260.00
120 95.00 3540.00 30.00 42.00 42.00 1260.00
121 94.00 3570.00 30.00 42.00 42.00 1260.00
122 93.00 3600.00 30.00 42.00 42.00 1260.00
123 92.00 3630.00 30.00 42.00 42.00 1260.00
124 91.00 3660.00 30.00 42.00 42.00 1260.00
125 90.00 3690.00 30.00 42.00 42.00 1260.00
126 89.00 3720.00 30.00 42.00 42.00 1260.00
127 88.00 3750.00 30.00 42.00 42.00 1260.00
128 87.00 3780.00 30.00 42.00 42.00 1260.00
129 86.00 3810.00 30.00 42.00 42.00 1260.00
130 85.00 3840.00 30.00 42.00 42.00 1260.00
131 84.00 3870.00 30.00 42.00 42.00 1260.00
132 83.00 3900.00 30.00 42.00 42.00 1260.00
133 82.00 3930.00 30.00 42.00 42.00 1260.00
134 81.00 3960.00 30.00 40.30 41.15 1234.50
135 80.00 3990.00 30.00 38.60 39.45 1183.50
136 79.00 4020.00 30.00 36.90 37.75 1132.50
137 78.00 4050.00 30.00 35.20 36.05 1081.50
138 77.00 4080.00 30.00 33.50 34.35 1030.50
139 76.00 4110.00 30.00 31.80 32.65 979.50
140 75.00 4140.00 30.00 30.10 30.95 928.50
141 74.00 4170.00 30.00 28.40 29.25 877.50
142 73.00 4200.00 30.00 26.70 27.55 826.50
143 72.00 4230.00 30.00 25.00 25.85 775.50

Unit 1 -Detailed estimate for Jungle Clearance 4


144 71.00 4260.00 30.00 23.30 24.15 724.50
145 70.00 4290.00 30.00 21.60 22.45 673.50
146 69.00 4320.00 30.00 19.90 20.75 622.50
147 68.00 4350.00 30.00 18.20 19.05 571.50
148 67.00 4380.00 30.00 16.50 17.35 520.50
149 66.00 4410.00 30.00 20.00 18.25 547.50
150 65.00 4440.00 30.00 20.50 20.25 607.50
151 64.00 4470.00 30.00 21.00 20.75 622.50
152 63.00 4500.00 30.00 21.50 21.25 637.50
153 62.00 4530.00 30.00 22.00 21.75 652.50
154 61.00 4560.00 18.00 22.50 22.25 400.50
155 61.60 4578.00 12.00 20.60 21.55 258.60 Neeche utarne ka rasta

156 60.00 4590.00 30.00 18.70 19.65 589.50


157 59.00 4620.00 30.00 16.80 17.75 532.50
158 58.00 4650.00 30.00 14.90 15.85 475.50
159 57.00 4680.00 18.00 13.00 13.95 251.10
160 57.60 4698.00 12.00 13.60 13.30 159.60 TBLC ground first gate

161 56.00 4710.00 30.00 15.60 14.60 438.00


162 55.00 4740.00 30.00 17.60 16.60 498.00
163 54.00 4770.00 30.00 19.60 18.60 558.00

164 53.00 4800.00 30.00 21.00 630.00 TBLC ground second gate
22.40
165 52.00 4830.00 30.00 21.20 21.80 654.00
166 51.00 4860.00 30.00 20.00 20.60 618.00
167 50.00 4890.00 30.00 18.80 19.40 582.00
168 49.00 4920.00 30.00 17.60 18.20 546.00
169 48.00 4950.00 30.00 16.40 17.00 510.00
170 47.00 4980.00 30.00 15.20 15.80 474.00
171 46.00 5010.00 30.00 14.00 14.60 438.00
172 45.00 5040.00 30.00 12.80 13.40 402.00
173 44.00 5070.00 30.00 11.60 12.20 366.00
174 43.00 5100.00 30.00 10.40 11.00 330.00

175 42.00 5130.00 30.00 10.70 321.00 Santoshi Mandir road


11.00
176 41.00 5160.00 30.00 10.60 10.80 324.00
177 40.00 5190.00 30.00 10.20 10.40 312.00
178 39.00 5220.00 30.00 9.80 10.00 300.00
179 38.00 5250.00 30.00 9.40 9.60 288.00
180 37.00 5280.00 30.00 9.00 9.20 276.00
181 36.00 5310.00 30.00 8.60 8.80 264.00

Unit 1 -Detailed estimate for Jungle Clearance 5


182 35.00 5340.00 30.00 8.20 8.40 252.00

183 34.00 5370.00 30.00 8.35 250.50 School ke peeche


8.50
184 33.00 5400.00 30.00 8.90 8.70 261.00
185 32.00 5430.00 30.00 9.30 9.10 273.00
186 31.00 5460.00 30.00 9.70 9.50 285.00
187 30.00 5490.00 30.00 10.10 9.90 297.00
188 29.00 5520.00 30.00 10.50 10.30 309.00
189 28.00 5550.00 30.00 10.90 10.70 321.00
190 27.00 5580.00 30.00 11.30 11.10 333.00
191 26.00 5610.00 30.00 11.70 11.50 345.00
192 25.00 5640.00 30.00 12.10 11.90 357.00
193 24.00 5670.00 30.00 12.50 12.30 369.00
194 23.00 5700.00 30.00 12.90 12.70 381.00

195 22.00 5730.00 30.00 14.60 13.75 412.50 Lugu shiv mandir

196 21.00 5760.00 30.00 14.00 14.30 429.00


197 20.00 5790.00 30.00 14.00 14.00 420.00
198 19.00 5820.00 30.00 14.00 14.00 420.00
199 18.00 5850.00 30.00 14.00 14.00 420.00
200 17.00 5880.00 30.00 14.00 14.00 420.00
201 16.00 5910.00 30.00 14.00 14.00 420.00
202 15.00 5940.00 30.00 14.00 14.00 420.00
203 14.00 5970.00 30.00 14.00 14.00 420.00
204 13.00 6000.00 30.00 14.00 14.00 420.00
205 12.00 6030.00 30.00 14.00 14.00 420.00
206 11.00 6060.00 30.00 14.00 14.00 420.00
207 10.00 6090.00 30.00 14.00 14.00 420.00
208 9.00 6120.00 30.00 14.00 14.00 420.00
209 8.00 6150.00 30.00 14.00 14.00 420.00
210 7.00 6180.00 30.00 14.00 14.00 420.00
211 6.00 6210.00 30.00 14.00 14.00 420.00
212 5.00 6240.00 30.00 14.00 14.00 420.00
213 4.00 6270.00 30.00 14.00 14.00 420.00
214 3.00 6300.00 30.00 14.00 14.00 420.00
215 2.00 6330.00 30.00 14.00 14.00 420.00
216 1.00 6360.00 14.00 14.00 0.00
402400.80 M2

Unit 1 -Detailed estimate for Jungle Clearance 6


2
(A) Total Area of downstream slope in M 402400.80 M2
Area of Jungle is 95% of total slope
(a) 0.95
Area =
Area where vegetation is clearly visible
(B) 382280.76 M2
=(0.95 x 402400.80 M2 )=

(b) Density of Jungle in concerned Area =90%= 0.90

Area where vegetation needs to be


(C) 344052.68 M2
removed =(0.90 x 382280.76 M2 )=

Density of Light Jungle =90% 0.90


Density of Light Jungle =90% of
(D) 309647.42 M2
344052.68 M2
Density of Thorny Jungle =10% 0.10
Density of Thorny Jungle =10% of
(E) 34405.27 M2
344052.68 M2

1 Light Jungle clearance of D/S Slope of Tenughat Dam in Hectare= 30.96 Hectare
Thorny Jungle clearance of D/S Slope of Tenughat Dam in
2
Hectare= 3.44 Hectare

Tenughat Dam Upstream slope Jungle clearance calculation

Jungle on
Distance from Horizontal Avg slope Area in
Chain Slope
Sl.No. Centre of distance in between square Remark
Number Length In
View Tower Meter two chains meter
meter
0 0.00 16.00 0.00
Centre of View Tower is
1 213.00 0.00 30.00 16.00 16.00 480.00 chain 213.00
Just 4 meter ahead of
2 212.00 30.00 30.00 16.60 16.30 489.00 flag post
3 211.00 60.00 30.00 30.00 23.30 699.00 Actual dam start
4 210.00 90.00 30.00 35.00 32.50 975.00 upto RCD road
5 209.00 120.00 30.00 38.00 36.50 1095.00 upto RCD road
(36.00 + 18.00 (dam
6 208.00 150.00 30.00 42.80 40.40 1212.00 slope + toe drain )
7 207.00 180.00 30.00 44.00 43.40 1302.00
8 206.00 210.00 30.00 44.20 44.10 1323.00
9 205.00 240.00 30.00 44.40 44.30 1329.00
10 204.00 270.00 30.00 44.60 44.50 1335.00 Including Toe Drain
11 203.00 300.00 30.00 44.80 44.70 1341.00 Including Toe Drain
12 202.00 330.00 30.00 45.00 44.90 1347.00 Including Toe Drain
13 201.00 360.00 30.00 45.20 45.10 1353.00 Including Toe Drain
14 200.00 390.00 30.00 45.00 45.10 1353.00 Including Toe Drain

Unit 1 -Detailed estimate for Jungle Clearance 7


15 199.00 420.00 30.00 32.00 38.50 1155.00 Including Toe Drain
16 198.00 450.00 30.00 32.00 32.00 960.00 Including Toe Drain
68.00 M before security
17 197.00 480.00 30.00 32.00 32.00 960.00 gate towards OP
18 196.00 510.00 30.00 45.00 38.50 1155.00
Secuirty gate OP side
(541.00 m from CVP)
19 195.00 540.00 45.00 45.00 1350.00 distance btw both
30.00 security gates = 360.00M
Stairs
20 194.00 570.00 0.00 22.50 675.00 downstream(548.00 M
30.00 from view point centre)
21 193.00 600.00 15.00 0.00 0.00 0.00
Exact spillway (45 m
22 193.50 615.00 0.00 0.00 0.00 from SG gate 1 towards
15.00 saram)
23 192.00 630.00 30.00 0.00 0.00 0.00 No slope concrete dam
24 191.00 660.00 30.00 0.00 0.00 0.00 No slope concrete dam
25 190.00 690.00 30.00 0.00 0.00 0.00 No slope concrete dam
26 189.00 720.00 30.00 0.00 0.00 0.00 No slope concrete dam
27 188.00 750.00 30.00 0.00 0.00 0.00 No slope concrete dam
28 187.00 780.00 30.00 0.00 0.00 0.00 No slope concrete dam
29 186.00 810.00 30.00 0.00 0.00 0.00 No slope concrete dam
30 185.00 840.00 30.00 0.00 0.00 0.00 No slope concrete dam
31 184.00 870.00 30.00 0.00 0.00 0.00 No slope concrete dam

32 183.00 900.00 30.00 45.30 22.65 679.50 Security Gate Saram side

33 182.00 930.00 30.00 45.00 45.15 1354.50


34 181.00 960.00 30.00 45.00 45.00 1350.00
Peterbar Gumia road
35 180.00 990.00 30.00 45.00 45.00 1350.00 curve
36 179.00 1020.00 30.00 45.00 45.00 1350.00
37 178.00 1050.00 30.00 45.00 45.00 1350.00
38 177.00 1080.00 30.00 48.50 46.75 1402.50
39 176.00 1110.00 30.00 45.00 46.75 1402.50
40 175.00 1140.00 30.00 45.00 45.00 1350.00
41 174.00 1170.00 30.00 45.00 45.00 1350.00
42 173.00 1200.00 30.00 46.00 45.50 1365.00
43 172.00 1230.00 30.00 45.00 45.50 1365.00
44 171.00 1260.00 30.00 45.00 45.00 1350.00
45 170.00 1290.00 30.00 47.50 46.25 1387.50
46 169.00 1320.00 30.00 45.00 46.25 1387.50
47 168.00 1350.00 30.00 45.00 45.00 1350.00
48 167.00 1380.00 30.00 45.00 45.00 1350.00
49 166.00 1410.00 30.00 45.00 45.00 1350.00
50 165.00 1440.00 30.00 45.00 45.00 1350.00 Longest slope start
51 164.00 1470.00 30.00 45.00 45.00 1350.00
52 163.00 1500.00 30.00 45.00 45.00 1350.00
53 162.00 1530.00 30.00 45.00 45.00 1350.00
54 161.00 1560.00 30.00 45.00 45.00 1350.00
55 160.00 1590.00 30.00 45.00 45.00 1350.00
56 159.00 1620.00 30.00 45.00 45.00 1350.00 Longest slope end
In Google map Tenughat
57 158.00 1650.00 30.00 43.00 44.00 1320.00 Dam
58 157.00 1680.00 30.00 43.00 43.00 1290.00

Unit 1 -Detailed estimate for Jungle Clearance 8


59 156.00 1710.00 30.00 43.00 43.00 1290.00
60 155.00 1740.00 30.00 43.00 43.00 1290.00
61 154.00 1770.00 30.00 43.00 43.00 1290.00 Water in Toe drain
62 153.00 1800.00 30.00 43.00 43.00 1290.00 Big tree in upstream
63 152.00 1830.00 30.00 43.00 43.00 1290.00
64 151.00 1860.00 30.00 43.00 43.00 1290.00
65 150.00 1890.00 30.00 43.00 43.00 1290.00
66 149.00 1920.00 30.00 43.00 43.00 1290.00
67 148.00 1950.00 30.00 43.00 43.00 1290.00
68 147.00 1980.00 30.00 43.00 43.00 1290.00
69 146.00 2010.00 30.00 43.00 43.00 1290.00
70 145.00 2040.00 30.00 43.00 43.00 1290.00
71 144.00 2070.00 30.00 43.00 43.00 1290.00
72 143.00 2100.00 30.00 46.00 44.50 1335.00
73 142.00 2130.00 30.00 46.00 46.00 1380.00
74 141.00 2160.00 30.00 46.00 46.00 1380.00
75 140.00 2190.00 30.00 46.00 46.00 1380.00
76 139.00 2220.00 30.00 46.00 46.00 1380.00
77 138.00 2250.00 30.00 46.00 46.00 1380.00
78 137.00 2280.00 30.00 46.00 46.00 1380.00
79 136.00 2310.00 30.00 46.00 46.00 1380.00
80 135.00 2340.00 30.00 46.00 46.00 1380.00
81 134.00 2370.00 30.00 46.00 46.00 1380.00
82 133.00 2400.00 30.00 46.00 46.00 1380.00 Bharat Mata stairs
83 132.00 2430.00 30.00 47.50 46.75 1402.50
84 131.00 2460.00 30.00 47.50 47.50 1425.00
85 130.00 2490.00 30.00 47.50 47.50 1425.00
86 129.00 2520.00 30.00 47.50 47.50 1425.00
87 128.00 2550.00 30.00 47.50 47.50 1425.00
88 127.00 2580.00 30.00 47.50 47.50 1425.00
89 126.00 2610.00 30.00 47.50 47.50 1425.00
90 125.00 2640.00 30.00 47.50 47.50 1425.00
91 124.00 2670.00 30.00 47.50 47.50 1425.00
92 123.00 2700.00 30.00 47.50 47.50 1425.00
93 122.00 2730.00 30.00 47.50 47.50 1425.00
94 121.00 2760.00 30.00 47.50 47.50 1425.00
95 120.00 2790.00 30.00 47.50 47.50 1425.00
96 119.00 2820.00 30.00 47.50 47.50 1425.00
Transformer ka rasta
97 118.00 2850.00 30.00 47.50 47.50 1425.00 (Tiraha)
98 117.00 2880.00 30.00 47.50 47.50 1425.00
99 116.00 2910.00 30.00 47.50 47.50 1425.00
100 115.00 2940.00 30.00 47.50 47.50 1425.00
101 114.00 2970.00 30.00 47.50 47.50 1425.00
102 113.00 3000.00 30.00 47.50 47.50 1425.00
103 112.00 3030.00 30.00 47.50 47.50 1425.00
104 111.00 3060.00 30.00 47.50 47.50 1425.00
105 110.00 3090.00 30.00 47.50 47.50 1425.00
106 109.00 3120.00 30.00 47.50 47.50 1425.00
107 108.00 3150.00 30.00 47.50 47.50 1425.00
108 107.00 3180.00 30.00 47.50 47.50 1425.00

Unit 1 -Detailed estimate for Jungle Clearance 9


109 106.00 3210.00 30.00 47.50 47.50 1425.00
110 105.00 3240.00 30.00 47.50 47.50 1425.00
111 104.00 3270.00 30.00 47.50 47.50 1425.00
112 103.00 3300.00 30.00 47.50 47.50 1425.00
113 102.00 3330.00 30.00 47.50 47.50 1425.00
114 101.00 3360.00 30.00 47.50 47.50 1425.00
115 100.00 3390.00 30.00 47.50 47.50 1425.00 Central Golamber
116 99.00 3420.00 30.00 37.00 42.25 1267.50
117 98.00 3450.00 30.00 37.00 37.00 1110.00
118 97.00 3480.00 30.00 37.00 37.00 1110.00
119 96.00 3510.00 30.00 37.00 37.00 1110.00
120 95.00 3540.00 30.00 37.00 37.00 1110.00
121 94.00 3570.00 30.00 37.00 37.00 1110.00
122 93.00 3600.00 30.00 37.00 37.00 1110.00
123 92.00 3630.00 30.00 37.00 37.00 1110.00
124 91.00 3660.00 30.00 37.00 37.00 1110.00
125 90.00 3690.00 30.00 37.00 37.00 1110.00
126 89.00 3720.00 30.00 37.00 37.00 1110.00
127 88.00 3750.00 30.00 37.00 37.00 1110.00
128 87.00 3780.00 30.00 37.00 37.00 1110.00
129 86.00 3810.00 30.00 37.00 37.00 1110.00
130 85.00 3840.00 30.00 37.00 37.00 1110.00
131 84.00 3870.00 30.00 37.00 37.00 1110.00
132 83.00 3900.00 30.00 37.00 37.00 1110.00
133 82.00 3930.00 30.00 37.00 37.00 1110.00
134 81.00 3960.00 30.00 36.20 36.60 1098.00
135 80.00 3990.00 30.00 35.40 35.80 1074.00
136 79.00 4020.00 30.00 34.60 35.00 1050.00
137 78.00 4050.00 30.00 33.80 34.20 1026.00
138 77.00 4080.00 30.00 33.00 33.40 1002.00
139 76.00 4110.00 30.00 32.20 32.60 978.00
140 75.00 4140.00 30.00 31.40 31.80 954.00
141 74.00 4170.00 30.00 30.60 31.00 930.00
142 73.00 4200.00 30.00 29.80 30.20 906.00
143 72.00 4230.00 30.00 29.00 29.40 882.00
144 71.00 4260.00 30.00 28.20 28.60 858.00
145 70.00 4290.00 30.00 27.40 27.80 834.00
146 69.00 4320.00 30.00 26.60 27.00 810.00
147 68.00 4350.00 30.00 25.80 26.20 786.00
148 67.00 4380.00 30.00 25.00 25.40 762.00
149 66.00 4410.00 30.00 27.00 26.00 780.00
150 65.00 4440.00 30.00 26.00 26.50 795.00
151 64.00 4470.00 30.00 25.00 25.50 765.00
152 63.00 4500.00 30.00 24.00 24.50 735.00
153 62.00 4530.00 30.00 23.00 23.50 705.00
154 61.00 4560.00 18.00 22.00 22.50 405.00
155 61.60 4578.00 12.00 20.00 21.00 252.00 Neeche utarne ka rasta
156 60.00 4590.00 30.00 19.80 19.90 597.00
157 59.00 4620.00 30.00 19.60 19.70 591.00
158 58.00 4650.00 30.00 19.40 19.50 585.00

Unit 1 -Detailed estimate for Jungle Clearance 10


159 57.00 4680.00 18.00 19.20 19.30 347.40

160 57.60 4698.00 12.00 19.00 19.10 229.20 TBLC ground first gate

161 56.00 4710.00 30.00 18.00 18.50 555.00

162 55.00 4740.00 30.00 18.00 18.00 540.00

163 54.00 4770.00 30.00 18.00 18.00 540.00

164 53.00 4800.00 30.00 18.30 18.15 544.50 TBLC ground second gate

165 52.00 4830.00 30.00 17.50 17.90 537.00

166 51.00 4860.00 30.00 16.50 17.00 510.00

167 50.00 4890.00 30.00 15.63 16.07 482.00

168 49.00 4920.00 30.00 14.73 15.18 455.50

169 48.00 4950.00 30.00 13.83 14.28 428.50

170 47.00 4980.00 30.00 12.93 13.38 401.50

171 46.00 5010.00 30.00 12.03 12.48 374.50

172 45.00 5040.00 30.00 11.13 11.58 347.50

173 44.00 5070.00 30.00 10.23 10.68 320.50

174 43.00 5100.00 30.00 9.33 9.78 293.50

175 42.00 5130.00 30.00 9.00 9.17 275.00 Santoshi Mandir road

176 41.00 5160.00 30.00 9.50 9.25 277.50

177 40.00 5190.00 30.00 10.00 9.75 292.50

178 39.00 5220.00 30.00 10.50 10.25 307.50

179 38.00 5250.00 30.00 11.00 10.75 322.50

180 37.00 5280.00 30.00 11.50 11.25 337.50

181 36.00 5310.00 30.00 12.00 11.75 352.50

182 35.00 5340.00 30.00 12.50 12.25 367.50

183 34.00 5370.00 30.00 13.50 13.00 390.00 School ke peeche

184 33.00 5400.00 30.00 13.80 13.65 409.50

185 32.00 5430.00 30.00 14.10 13.95 418.50

186 31.00 5460.00 30.00 14.40 14.25 427.50

187 30.00 5490.00 30.00 14.70 14.55 436.50

188 29.00 5520.00 30.00 15.00 14.85 445.50

189 28.00 5550.00 30.00 15.30 15.15 454.50

190 27.00 5580.00 30.00 15.60 15.45 463.50

191 26.00 5610.00 30.00 15.90 15.75 472.50

192 25.00 5640.00 30.00 16.20 16.05 481.50

193 24.00 5670.00 30.00 16.50 16.35 490.50


194 23.00 5700.00 30.00 16.80 16.65 499.50
195 22.00 5730.00 30.00 19.60 18.20 546.00 Lugu shiv mandir

Unit 1 -Detailed estimate for Jungle Clearance 11


196 21.00 5760.00 30.00 17.00 18.30 549.00

197 20.00 5790.00 30.00 16.00 16.50 495.00

198 19.00 5820.00 30.00 16.00 16.00 480.00

199 18.00 5850.00 30.00 16.00 16.00 480.00

200 17.00 5880.00 30.00 16.00 16.00 480.00

201 16.00 5910.00 30.00 16.00 16.00 480.00

202 15.00 5940.00 30.00 16.00 16.00 480.00

203 14.00 5970.00 30.00 16.00 16.00 480.00

204 13.00 6000.00 30.00 16.00 16.00 480.00

205 12.00 6030.00 30.00 16.00 16.00 480.00

206 11.00 6060.00 30.00 16.00 16.00 480.00

207 10.00 6090.00 30.00 16.00 16.00 480.00

208 9.00 6120.00 30.00 16.00 16.00 480.00

209 8.00 6150.00 30.00 16.00 16.00 480.00

210 7.00 6180.00 30.00 16.00 16.00 480.00

211 6.00 6210.00 30.00 16.00 16.00 480.00

212 5.00 6240.00 30.00 16.00 16.00 480.00

213 4.00 6270.00 30.00 16.00 16.00 480.00

214 3.00 6300.00 30.00 16.00 16.00 480.00

215 2.00 6330.00 30.00 16.00 16.00 480.00

216 1.00 6360.00 16.00 16.00 0.00


202055.60 M2
(A) Total of
Area Area of upstream
Jungle is 97% ofslope in M2
total slope 202055.60 M2
(a) Area where vegetation
Area = is clearly visible 0.97
2
(B) =(0.97 x 202055.60 M )= 195993.932 M2
(b) Density of Jungle in concerned Area =96%= 0.96
Area where vegetation needs to be
(C) 188154.17 M2
removed =(0.96 x 19599.932 M2 )=
Density of Light Jungle =80% 0.80
Density of Light Jungle =80% of
(D) 150523.34 M2
188154.17 M2
Density
DensityofofThorny
ThornyJungle
Jungle=20%
=20%of 0.20
2
(E) 188154.17 M 37630.83 M2

1 Light Jungle clearance of U/S Slope of Tenughat Dam in Hectare= 15.05 Hectare
Thorny Jungle clearance of U/S Slope of Tenughat Dam in
2
Hectare= 3.76 Hectare

Unit 1 -Detailed estimate for Jungle Clearance 12


Jungle clearance at Top Road of Dam 1.00 meter single side and
Special
2.00 meter both sides (1.00m and 1.00 m )=
Length of Top Road =(213.00 -13.00 -11.00 chain
5670.00 M
(spillway) = 189.00 chains x 30.00 m =
Width in meter = 2.00 M
Area in square meter = 11340.00 M2
Light jungle area in Top Road with 90% Density = 10206.00
Light jungle area in Top Road with 90% Density in
1.021 Hectare
Hectare =
Light Jungle clearance of U/S Slope and Downstream slope combined in
A
Hectare=(15.05 Hectare + 30.96 Hectare + 1.021)= in Hectare 47.04
Thorny Jungle clearance of U/S Slope and Downstream slope combined in
B
Hectare=(3.76 Hectare + 3.44 Hectare)= in Hectare 7.20

(a) Light Jungle cuuting in first time = 47.04 Hectare


Light Jungle clearance in First year after one
(b)
complete cutting = 66% of first cutting
31.04 Hectare

Light Jungle clearance in First year after one


(c)
complete cutting =50% of first cutting
23.52 Hectare

Light Jungle clearance in First year after one


(d)
complete cutting = 33% of first cutting
15.52 Hectare

Total Light Juncle cutting in first year with Three


(A)
Years of Maintenance = 117.12 Hectare

(a) Thorny Jungle cuuting in first time = 7.20 Hectare

Thorny t Jungle clearance in First year after one


(b)
complete cutting = 66% of first cutting
4.75 Hectare

Thorny Jungle clearance in First year after one


(c)
complete cutting =50% of first cutting
3.60 Hectare

Thorny Jungle clearance in First year after one


(d)
complete cutting = 33% of first cutting
2.38 Hectare

Total Thorny Juncle cutting in first year with Three


(A)
Years of Maintenance = 17.94 Hectare

J.E A.E Executive Engineer


Tenughat Dam Division
Tenughat

Unit 1 -Detailed estimate for Jungle Clearance 13


Unit -2
Rearranging disturbed
Rip Rap and depressed
patches of Tenughat
Dam as per DSRP
Recommendation Page
30 U/S Slope(b)(ii).
Abstract of cost of Rearranging disturebd Rip Rap and depressed patches as per DSRP
2021 Recommendation Page 30 U/S Slope(b)(ii)

Sl.No. Item Unit Qunatity Rate Amount

Supplying and laying sand filter on slope


of the dam as per design drawing
including the cost of material royalty and
1 all taxes etc. but excluding the cost of M3 1545.00 1415.17 2186437.65
carriage all complete as per specification
and direction of E/I.(Common Part A
/JH SOR 2022/Page 209/5.6.5)

Supplying and laying stone metal filter


(size 20mm to 63mm) in slope of the
dam as per design drawing including the
cost of material royalty and all taxes etc.
2 M3 1545.00 2103.59 3250046.55
but excluding the cost of carriage all
complete as per specification and
direction of E/I.(Common Part A /JH
SOR 2022/Page 209/5.6.7)

Labor charge for taking out disturbed


boulder from boulder pitching or rip rap
or rock toe etc. and cleaning the surface
3
3 and stacking the same within the lead of M 5874.47 398.00 2338038.26
100m as per specification and direction
of E/I.(WRD/JH SOR 2022/Page
153/7.7.41)

Labor charge for pitching on apron slope


of bank with stone boulders duly packed
(uncrated) complete job (materials
4 within 150mm and all lifts as per M3 6461.91 968.17 6256232.05
specification and direction of
E/I.(WRD/JH SOR 2022/Page
151/7.7.18)

Unit 2 - AOC Rip Rap


1
Supplying and laying (properly as per
design and drawing) rip- rap with good
quality of boulders duly packed
including the cost of materials, royalty
5 M3 579.38 1756.40 1017614.25
all taxes etc. but excluding the cost of
carriage all complete as per specification
and direction of E/I(Part A /Page
209/5.6.8)

Supply of Boulders (10%CP + 4.5%


6 M3 587.45 151.734 89135.65
OHC)(common Part A/JH SOR /Page 29)

7 Carriage of Sand T.Km 1545.00 199.060 307547.70

8 Carriage of Boulder (293.72+1545.00) T.Km 2132.45 536.980 1145081.28

Total (A) ₹ 1,65,90,133.40


B =Add 18% GST of (A) 2986224.01
C= Sub total = (A
19576357.41
+ B) =
1% Contigecy of C = 195763.57
1% Labor cess of C = 195763.57
Grand Total ₹ 1,99,67,884.56

₹ 1,99,67,884.56

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 2 - AOC Rip Rap


2
Detailed estimate of earranging disturebd Rip Rap and depressed patches as per DSRP 2021
Recommendation Page 30 U/S Slope(b)(ii)

Slope length U/S slope Stone


Distance
Horizontal Slope Avg slope which is in for stone
Chain from Centre Area in square Pitching
Sl.No. distance in Length In between continous pitching
Number of View meter Area(Total
Meter meter two chains contact with (Above
Tower
water water) U/S area)

1 2 3 4 5 6 7 8 9 10.0 11

0 0.00 16.00 3.00 0.00


1 213.00 0.00 30.00 16.00 16.00 2.50 75.00 13.50 480.0
2 212.00 30.00 30.00 16.60 16.30 2.50 75.00 13.80 489.0
3 211.00 60.00 30.00 30.00 23.30 2.50 75.00 20.80 699.0
4 210.00 90.00 30.00 35.00 32.50 2.50 75.00 30.00 975.0
5 209.00 120.00 30.00 38.00 36.50 2.50 75.00 34.00 1095.0
6 208.00 150.00 30.00 42.80 40.40 2.50 75.00 37.90 1212.0
7 207.00 180.00 30.00 44.00 43.40 2.50 75.00 40.90 1302.0
8 206.00 210.00 30.00 44.20 44.10 2.50 75.00 41.60 1323.0
9 205.00 240.00 30.00 44.40 44.30 2.50 75.00 41.80 1329.0
10 204.00 270.00 30.00 44.60 44.50 2.50 75.00 42.00 1335.0
11 203.00 300.00 30.00 44.80 44.70 2.50 75.00 42.20 1341.0
12 202.00 330.00 30.00 45.00 44.90 2.50 75.00 42.40 1347.0
13 201.00 360.00 30.00 45.20 45.10 2.50 75.00 42.60 1353.0
14 200.00 390.00 30.00 45.00 45.10 2.50 75.00 42.60 1353.0
15 199.00 420.00 30.00 32.00 38.50 2.50 75.00 36.00 1155.0
16 198.00 450.00 30.00 32.00 32.00 2.50 75.00 29.50 960.0
17 197.00 480.00 30.00 32.00 32.00 2.50 75.00 29.50 960.0
18 196.00 510.00 30.00 45.00 38.50 2.50 75.00 36.00 1155.0
19 195.00 540.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
20 194.00 570.00 30.00 0.00 22.50 0.00 0.00 22.50 675.0
21 193.00 600.00 15.00 0.00 0.00 0.00 0.00 0.00 0.0
22 193.50 615.00 15.00 0.00 0.00 0.00 0.00 0.00 0.0
23 192.00 630.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
24 191.00 660.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
25 190.00 690.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
26 189.00 720.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
27 188.00 750.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
28 187.00 780.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
29 186.00 810.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
30 185.00 840.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
31 184.00 870.00 30.00 0.00 0.00 0.00 0.00 0.00 0.0
32 183.00 900.00 30.00 45.30 22.65 2.50 75.00 20.15 679.5
33 182.00 930.00 30.00 45.00 45.15 2.50 75.00 42.65 1354.5
34 181.00 960.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
35 180.00 990.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
36 179.00 1020.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
37 178.00 1050.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
38 177.00 1080.00 30.00 48.50 46.75 2.50 75.00 44.25 1402.5
39 176.00 1110.00 30.00 45.00 46.75 2.50 75.00 44.25 1402.5
40 175.00 1140.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0

Unit 2 - Detailed estimate for Rip Rap 1


41 174.00 1170.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
42 173.00 1200.00 30.00 46.00 45.50 2.50 75.00 43.00 1365.0
43 172.00 1230.00 30.00 45.00 45.50 2.50 75.00 43.00 1365.0
44 171.00 1260.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
45 170.00 1290.00 30.00 47.50 46.25 2.50 75.00 43.75 1387.5
46 169.00 1320.00 30.00 45.00 46.25 2.50 75.00 43.75 1387.5
47 168.00 1350.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
48 167.00 1380.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
49 166.00 1410.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
50 165.00 1440.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
51 164.00 1470.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
52 163.00 1500.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
53 162.00 1530.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
54 161.00 1560.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
55 160.00 1590.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
56 159.00 1620.00 30.00 45.00 45.00 2.50 75.00 42.50 1350.0
57 158.00 1650.00 30.00 43.00 44.00 2.50 75.00 41.50 1320.0
58 157.00 1680.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0
59 156.00 1710.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0
60 155.00 1740.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0
61 154.00 1770.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0
62 153.00 1800.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0
63 152.00 1830.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0

64 151.00 1860.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0


65 150.00 1890.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0

66 149.00 1920.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0

67 148.00 1950.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0

68 147.00 1980.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0

69 146.00 2010.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0

70 145.00 2040.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0

71 144.00 2070.00 30.00 43.00 43.00 2.50 75.00 40.50 1290.0


72 143.00 2100.00 30.00 46.00 44.50 2.50 75.00 42.00 1335.0

73 142.00 2130.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

74 141.00 2160.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

75 140.00 2190.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

76 139.00 2220.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

77 138.00 2250.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

78 137.00 2280.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

79 136.00 2310.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

80 135.00 2340.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0


81 134.00 2370.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

82 133.00 2400.00 30.00 46.00 46.00 2.50 75.00 43.50 1380.0

83 132.00 2430.00 30.00 47.50 46.75 2.50 75.00 44.25 1402.5

84 131.00 2460.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

Unit 2 - Detailed estimate for Rip Rap 2


85 130.00 2490.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

86 129.00 2520.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

87 128.00 2550.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0


88 127.00 2580.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

89 126.00 2610.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

90 125.00 2640.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

91 124.00 2670.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

92 123.00 2700.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

93 122.00 2730.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

94 121.00 2760.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

95 120.00 2790.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0

96 119.00 2820.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0


97 118.00 2850.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
98 117.00 2880.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
99 116.00 2910.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
100 115.00 2940.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
101 114.00 2970.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
102 113.00 3000.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
103 112.00 3030.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
104 111.00 3060.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
105 110.00 3090.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
106 109.00 3120.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
107 108.00 3150.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
108 107.00 3180.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
109 106.00 3210.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
110 105.00 3240.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
111 104.00 3270.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
112 103.00 3300.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
113 102.00 3330.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
114 101.00 3360.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
115 100.00 3390.00 30.00 47.50 47.50 2.50 75.00 45.00 1425.0
0.00 7725.00 0.00 0.0
116 99.00 3420.00 30.00 37.00 42.25 12.33 1267.50 42.25 1267.5
117 98.00 3450.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
118 97.00 3480.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
119 96.00 3510.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
120 95.00 3540.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
121 94.00 3570.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
122 93.00 3600.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
123 92.00 3630.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0

Unit 2 - Detailed estimate for Rip Rap 3


124 91.00 3660.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
125 90.00 3690.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
126 89.00 3720.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
127 88.00 3750.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
128 87.00 3780.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
129 86.00 3810.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
130 85.00 3840.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
131 84.00 3870.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
132 83.00 3900.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
133 82.00 3930.00 30.00 37.00 37.00 12.33 1110.00 37.00 1110.0
134 81.00 3960.00 30.00 36.20 36.60 12.07 1098.00 36.60 1098.0
135 80.00 3990.00 30.00 35.40 35.80 11.80 1074.00 35.80 1074.0
136 79.00 4020.00 30.00 34.60 35.00 11.53 1050.00 35.00 1050.0
137 78.00 4050.00 30.00 33.80 34.20 11.27 1026.00 34.20 1026.0
138 77.00 4080.00 30.00 33.00 33.40 11.00 1002.00 33.40 1002.0
139 76.00 4110.00 30.00 32.20 32.60 10.73 978.00 32.60 978.0
140 75.00 4140.00 30.00 31.40 31.80 10.47 954.00 31.80 954.0
141 74.00 4170.00 30.00 30.60 31.00 10.20 930.00 31.00 930.0
142 73.00 4200.00 30.00 29.80 30.20 9.93 906.00 30.20 906.0
143 72.00 4230.00 30.00 29.00 29.40 9.67 882.00 29.40 882.0
144 71.00 4260.00 30.00 28.20 28.60 9.40 858.00 28.60 858.0
145 70.00 4290.00 30.00 27.40 27.80 9.13 834.00 27.80 834.0
146 69.00 4320.00 30.00 26.60 27.00 8.87 810.00 27.00 810.0
147 68.00 4350.00 30.00 25.80 26.20 8.60 786.00 26.20 786.0
148 67.00 4380.00 30.00 25.00 25.40 8.33 762.00 25.40 762.0
149 66.00 4410.00 30.00 27.00 26.00 9.00 780.00 26.00 780.0
150 65.00 4440.00 30.00 26.00 26.50 8.67 795.00 26.50 795.0
151 64.00 4470.00 30.00 25.00 25.50 8.33 765.00 25.50 765.0
152 63.00 4500.00 30.00 24.00 24.50 8.00 735.00 24.50 735.0
153 62.00 4530.00 30.00 23.00 23.50 7.67 705.00 23.50 705.0
154 61.00 4560.00 18.00 22.00 22.50 7.33 405.00 22.50 405.0
155 61.60 4578.00 12.00 20.00 21.00 6.67 252.00 21.00 252.0
156 60.00 4590.00 30.00 19.80 19.90 6.60 597.00 19.90 597.0
157 59.00 4620.00 30.00 19.60 19.70 6.53 591.00 19.70 591.0
158 58.00 4650.00 30.00 19.40 19.50 6.47 585.00 19.50 585.0
159 57.00 4680.00 18.00 19.20 19.30 6.40 347.40 19.30 347.4
160 57.60 4698.00 12.00 19.00 19.10 6.33 229.20 19.10 229.2
161 56.00 4710.00 30.00 18.00 18.50 6.00 555.00 18.50 555.0
162 55.00 4740.00 30.00 18.00 18.00 6.00 540.00 18.00 540.0
163 54.00 4770.00 30.00 18.00 18.00 6.00 540.00 18.00 540.0
164 53.00 4800.00 30.00 18.30 18.15 6.10 544.50 18.15 544.5
165 52.00 4830.00 30.00 17.50 17.90 5.83 537.00 17.90 537.0
166 51.00 4860.00 30.00 16.50 17.00 5.50 510.00 17.00 510.0
167 50.00 4890.00 30.00 15.63 16.07 5.21 482.00 16.07 482.0
168 49.00 4920.00 30.00 14.73 15.18 4.91 455.50 15.18 455.5
169 48.00 4950.00 30.00 13.83 14.28 4.61 428.50 14.28 428.5
170 47.00 4980.00 30.00 12.93 13.38 4.31 401.50 13.38 401.5
171 46.00 5010.00 30.00 12.03 12.48 4.01 374.50 12.48 374.5
172 45.00 5040.00 30.00 11.13 11.58 3.71 347.50 11.58 347.5
173 44.00 5070.00 30.00 10.23 10.68 3.41 320.50 10.68 320.5
174 43.00 5100.00 30.00 9.33 9.78 3.11 293.50 9.78 293.5

Unit 2 - Detailed estimate for Rip Rap 4


175 42.00 5130.00 30.00 9.00 9.17 3.00 275.00 9.17 275.0
176 41.00 5160.00 30.00 9.50 9.25 3.17 277.50 9.25 277.5
177 40.00 5190.00 30.00 10.00 9.75 3.33 292.50 9.75 292.5
178 39.00 5220.00 30.00 10.50 10.25 3.50 307.50 10.25 307.5
179 38.00 5250.00 30.00 11.00 10.75 3.67 322.50 10.75 322.5
180 37.00 5280.00 30.00 11.50 11.25 3.83 337.50 11.25 337.5
181 36.00 5310.00 30.00 12.00 11.75 4.00 352.50 11.75 352.5
182 35.00 5340.00 30.00 12.50 12.25 4.17 367.50 12.25 367.5
183 34.00 5370.00 30.00 13.50 13.00 4.50 390.00 13.00 390.0
184 33.00 5400.00 30.00 13.80 13.65 4.60 409.50 13.65 409.5
185 32.00 5430.00 30.00 14.10 13.95 4.70 418.50 13.95 418.5
186 31.00 5460.00 30.00 14.40 14.25 4.80 427.50 14.25 427.5
187 30.00 5490.00 30.00 14.70 14.55 4.90 436.50 14.55 436.5
188 29.00 5520.00 30.00 15.00 14.85 5.00 445.50 14.85 445.5
189 28.00 5550.00 30.00 15.30 15.15 5.10 454.50 15.15 454.5
190 27.00 5580.00 30.00 15.60 15.45 5.20 463.50 15.45 463.5
191 26.00 5610.00 30.00 15.90 15.75 5.30 472.50 15.75 472.5
192 25.00 5640.00 30.00 16.20 16.05 5.40 481.50 16.05 481.5
193 24.00 5670.00 30.00 16.50 16.35 5.50 490.50 16.35 490.5
194 23.00 5700.00 30.00 16.80 16.65 5.60 499.50 16.65 499.5
195 22.00 5730.00 30.00 19.60 18.20 6.53 546.00 18.20 546.0
196 21.00 5760.00 30.00 17.00 18.30 5.67 549.00 18.30 549.0
197 20.00 5790.00 30.00 16.00 16.50 5.33 495.00 16.50 495.0
198 19.00 5820.00 30.00 16.00 16.00 5.33 480.00 16.00 480.0
199 18.00 5850.00 30.00 16.00 16.00 5.33 480.00 16.00 480.0
200 17.00 5880.00 30.00 16.00 16.00 5.33 480.00 16.00 480.0
201 16.00 5910.00 30.00 16.00 16.00 5.33 480.00 16.00 480.0
202 15.00 5940.00 30.00 16.00 16.00 5.33 480.00 16.00 480.0

Area from ch. 100.00 to ch. 1.00 59116.10 M2 195815.60 M2

Supplying and laying sand filter on slope of the dam as per design drawing including the cost of material
Item 1 royalty and all taxes etc. but excluding the cost of carriage all complete as per specification and direction of
E/I.(Common Part A /JH SOR 2022/Page 209/5.6.5)
Total surface area of upstream slope where Sand
7725.00 M2
filter is required
Thickness of Sand filter (200mm)= 0.200 M
Volume of sand filter = 1545.00 M3

Supplying and laying stone metal filter (size 20mm to 63mm) in slope of the dam as per design drawing
Item
including the cost of material royalty and all taxes etc. but excluding the cost of carriage all complete as per
2
specification and direction of E/I.(Common Part A /JH SOR 2022/Page 209/5.6.7)
Total surface area of upstream slope where Gravel
7725.00 M2
filter is required
Thickness of Sand filter (200mm)= 0.200 M
Volume of sand filter = 1545.00 M3

Unit 2 - Detailed estimate for Rip Rap 5


Labor charge for taking out disturbed boulder from boulder pitching or rip rap or rock toe etc. and cleaning
3 the surface and stacking the same within the lead of 100m as per specification and direction of E/I.(WRD/JH
SOR 2022/Page 153/7.7.41)
2
Total Area considered for Pitching in M2 195815.60 M
Atleast 10% area needs Pitching because of disturbed boulder 0.10
2
Net Pitching area = 19581.56 M
Depth of pitching stone =300mm = 0.300 M
Volume of stones = 5874.468 M3

Labor charge for pitching on apron slope of bank with stone boulders duly packed (uncrated) complete job
4 (materials within 150mm and all lifts as per specification and direction of E/I.(WRD/JH SOR 2022/Page
151/7.7.18)
Total Area considered for Pitching in M2 195815.60 M2
Atleast 10% area needs Pitching because of disturbed = 0.10
Net Pitching area = 19581.56 M2
Depth of pitching stone =300mm = 0.300 M
Volume of stones = 5874.47 M3 H248
10% extra Supply boulders required so Volume of stones for
pitching=
587.45 M3
Total volume of stones in cubic meter= 6461.91 M3

Supplying and laying (properly as per design and drawing) rip- rap with good quality of boulders duly packed
5 including the cost of materials, royalty all taxes etc. but excluding the cost of carriage all complete as per
specification and direction of E/I(Part A /Page 209/5.6.8)

Total Area considered for Rip rap from ch. 213.00 to ch.100.00 in
7725.00 M2
M2
Atleast 25% area needs Pitching because of disturbed = 0.25
Net Pitching area = 1931.25 M2
Depth of pitching stone =300mm = 0.300 M
Volume of stones for arranging rip rap = 579.375 M3

6 Supply of Boulders (10%CP + 4.5% OHC)(common Part A/JH SOR /Page 29)

Extra 10% boulders for Pitching =10% X 5874.47 587.45 M3

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 2 - Detailed estimate for Rip Rap 6


Unit -3
Closing down the gap in U/S
Parapet wall and providing
continuous parapet wall and
Removal of different
components as per DSRP 2021
Recommendation Page 30
(b)U/S Slope(iii) and (iv).
Abstract of cost of Closing down the gap in U/S Parapet wall and providing
continous parapet wall and Removal of different components as per DSRP 2021
Recommendation Page 30 (b)U/S Slope(iii) and (iv)

Sl.No. Item unit Qunatity Rate Amount

Providing randam rubble stone masonry in CM (1:4) in


superstructure including cost of screening of materials
3
1 scaffolding raking out joints to 20 mm depth, curing taxes and M 34.50 2987.47 103067.72
royalty all complete as per building specification and direction
of E/I.(BCD JH SOR /PAGE 102/5.2.34)

Removal of telephone/electric poles and lines including


excavation and dismantling of foundation concrete and lines
under the supervision of concerned department disposal with
2 Each 18.00 185.10 3331.80
all lifts and upto lead of 1000 meters and stacking the
serviceable material and unserviceable material
separately.(Common SOR Part A/Page 199/2.14/202)

Dismantling of existing structures like culverts, bridges,


retaining walls and other structure of comprising of masonry,
cement concrete, wood of work, steel work, including T&P and
scaffolding Wherever necessary, sorting the dismantled
3 M3 12.88 286.30 3687.54
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000
metres.Dismantling Brick/tile work by manual means in
cement mortar (Common SOR Part A/Page 196/2.04/202/i/C)
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure of comprising of masonry,
cement concrete, wood of work, steel work, including T&P and
scaffolding Wherever necessary, sorting the dismantled 3
4 M 5.10 1263.70 6444.87
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres.RCC
M-20 by manual means (Common SOR Part A/Page
196/2.04/202/ii/B)

Providing and laying cement concrete in retaining walls,


return walls, walls (any thickness) including attached
pilasters, columns, piers, abutments, pillars, posts, struts,
buttresses, string or lacing courses, parapets, coping, bed
3
5 blocks, anchor blocks, plain window sills, fillets, sunken M 3.39 5989.72 20305.15
floor etc., up to floor five level, excluding the cost of
centering, shuttering and finishing: 1:1½:3 (1 cement : 1½
coarse sand (zone-III) : 3 graded stone aggregate 20 mm
nominal size).(BCD 2022/5.3.2.1)

Unit 3 - closing the gap of Parapet wall removal of components 1


Providing cement deep rulled pointing (1:3) with clean
coars sand F.M 1.5 including cost of screening of
6 materials curing taxes ,scaffolding and royalty all M2 5607.90 187.94 1053948.73
complete as per building specification and direction of
E/I.(commn SOR 2022/Page 200/5.7.7)

7 Carriage of Cement(Lead =13.00km)= T.km 6.47 524.00 3388.62

8 Carriage of Sand (Lead = 7.00km)= T.km 13.80 199.06 2747.03


9 Carriage of Chips(Lead = 31.00km)= T.km 4.56 536.98 2446.57
10 Carriage of Boulder (Lead =31.00km) T.km 34.50 556.08 19184.76
Total (A) ₹ 12,18,552.78
B =Add 18% GST of
219339.50
(A)
C= Sub total = 1437892.28
1% Contigecy of C = 14378.92
1% Labor cess of C = 14378.92
Grand Total ₹ 14,66,650.12

₹ 14,66,650.00

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 3 - closing the gap of Parapet wall removal of components 2


DETAILED ESTIMATE of Closing down the gap in U/S Parapet wall and providing continous
parapet wall and Removal of different components as per DSRP 2021 Recommendation Page 30
(b)U/S Slope(iii) and (iv)
Providing randam rubble stone masonry in CM (1:4) in superstructure including cost of
screening of materials scaffolding raking out joints to 20 mm depth, curing taxes and
1
royalty all complete as per building specification and direction of E/I.(BCD JH SOR /PAGE
102/5.2.34).
Location Length Height width Volume
At chain 100.00 upstream side 8.00 2.50 0.600 12.00
TBLC Ground 9.00 2.50 0.600 13.50
At chain 14.00 U/S 6.00 2.50 0.600 9.00
Total volume of RRM = 34.50 M3
Removal of telephone/electric poles and lines including excavation and dismantling of
foundation concrete and lines under the supervision of concerned department disposal with all
2 lifts and upto lead of 1000 meters and stacking the serviceable material and unserviceable
material separately.(Common SOR Part A/Page 199/2.14/202)
Numbers pf electric poles in Dam reservoir area = 18.00 Nos.
Dismantling of existing structures like culverts, bridges, retaining walls and other structure of comprising
of masonry, cement concrete, wood of work, steel work, including T&P and scaffolding Wherever
3 necessary, sorting the dismantled material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres.Dismantling Brick/tile work by manual means in
cement mortar (Common SOR Part A/Page 196/2.04/202/i/C)
No. of Volume in
Sl.No. Location Height Thickness Length
walls M3
Old pump house in
1 4.00 3.5 0.230 4.00 12.88
Reservoir
Dismantling of existing structures like culverts, bridges, retaining walls and other structure of comprising
of masonry, cement concrete, wood of work, steel work, including T&P and scaffolding Wherever
4 necessary, sorting the dismantled material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres.RCC M-20 by manual means in cement mortar
(Common SOR Part A/Page 196/2.04/202/ii/B)
No. of Volume in
Sl.No. Location Width Thickness Length
roof M3
Old pump house in
1 1.00 5.00 0.150 4.00 3.000
Reservoir
Room at chain
1.00 3.50 0.150 4.00 2.100
100.00
3
Total RCC Removal in cubic meter = 5.100 M

Providing and laying cement concrete in retaining walls, return walls, walls (any
thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts,
5/BCD
buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain
5.3.2.1/
window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of
2022
centering, shuttering and finishing: 1:1½:3 (1 cement : 1½ coarse sand (zone-III) : 3
PAGE 35 graded stone aggregate 20 mm
nominal size).
Location Length Thickness width Volume
At chain 100.00 upstream side 11.50 0.100 0.600 0.69
TBLC Ground 29.00 0.100 0.600 1.74

Unit 3 - Detailed estimate 1


At chain 14.00 U/S 16.00 0.100 0.600 0.96
3
Total volume of PCC for coping = 3.39 M

Providing cement deep rulled pointing (1:3) with clean coars sand F.M 1.5 including cost
6 of screening of materials curing taxes ,scaffolding and royalty all complete as per
building specification and direction of E/I.(commn SOR 2022/Page 200/5.7.7)

Location Length Height Sides Area(Length x height)

At chain 213.00 to 196.00


510.00 1.000 2.00 1020.00 M2
upstream side
At chain 213.00 to 196.00
510.00 0.600 2.00 612.00 M2
DOWNSTREAM side
At chain 196.00 to 1.00
5700.00 0.200 2.00 2280.00 M2
DOWNSTREAM side
At chain 196.00 to 1.00 U/S side 5700.00 0.750 2.00 8550.00 M2
Total area of both sides of
12462.00 M2
parapet wall
45% area needs Pointing= 0.450 x12462.00 m2 5607.90 M2

Material statement
Cement in Stone in
S.No. Item Unit QTY Sand in M3
M3 M3
3
RRM(1:4) M 34.50 3.45 13.80 34.50
Cement in
Unit QTY Sand in M3 Chips in M3
M3
3
PCC (1:1.5:3) M 3.39 0.95 1.42 2.85
total 4.40 15.22
Cement in MT =(X1.47)= 6.47 MT
Sand in MT =(X1.6)= 24.36 MT
Stone in MT =(X1.6)= 55.20 MT
Chips in MT =(X1.6)= 4.56 MT

JE AE Executive Engineer
Tenughat Dam Diviison

Unit 3 - Detailed estimate 2


Unit -4
Cleaning and Repair of
longitudinal, transverse and
toe drains as per DSRP 2021
Recommendation of Page 30 (
C ) D/S Slope(iv) and (v).
Abstract of cost of Cleaning and Repair of longitudinal ,transverse and toe drains as per DSRP 2021
Recommnedation of Page 30 ( C ) D/S Slope(iv) and (v).

S.No. Item Unit Quantity Rate in Rs. Amount in Rs.

Earth work in bed clearance or desilting of canals


carrying F.S.discharge between 8.5 cumecs (300
cusecs) and 0.14 cumecs (5 cusecs) and renovation of
pynes etc disposal of excavated earth etc. and in
1 M3 6886.50 120.61 830580.38
ordinary soil including rough dressing with initial
lead of 10M and lift of 1.5M as per specification and
direction of E/I. (JH SOR 2022/WRD/ Page
134/7.1.20)

Extra for wet earth all complete as per specification


2 and direction of E/I. (JH SOR 2022/WRD/ Page M3 6886.50 13.27 91383.81
134/7.1.22)

Scrapping of stone from dismantled stone masonary


3 in cemnet mortar and lime mortar (JH SOR M3 5255.58 553.30 2907912.77
2022/common Part A/ Page 197/2.04/(vii)/A)

Scrapping Plaster in lime and cement mortar from


4 Brick/Stone Masonary (JH SOR 2022/common Part M2 17518.60 16.50 289056.94
A/ Page 197/2.04/(viii)

Providing random rubble stone masonary (1:4) in


foundation and plinth with hammer dressed stone of
less than 0.03 M3 in volume and clean coarse sand of
F.M. 2 to 2.5 including cost of screening materials
5 M3 5255.58 2739.68 14398609.17
raking out joints to 20mm depth , curing , taxes and
royalty all complete as per builiding specification and
direction of E/I.(JH SOR 2022/Part A /Page
204/5.2.28)

Providing tuck pointing in cement on stone masonary


(1:3) with clean coarse sand of F.M 1.50 including
screening curing with all leads and lifts of water
6 M2 13920.00 254.73 3545841.60
scaffolding taxes and royalty all complete as per
building specification and direction of E/I. (JH SOR
2022/Part A /Page 204/5.7.10).

Unit 4 - AOC for Drains 1


Providing 25 mm thick water proof cement plaster
(1:3) clean coarse sand of F.M 1.50 with 5% cico or
any other water proofing compound including
7 screening curing with all leads and lifts of water M2 8818.60 275.94 2433405.07
scaffolding taxes and royalty all complete as per
building specification and direction of E/I. (JH SOR
2022/Part A /Page 204/5.7.16).

Providing 1.5mm cement punning including


screening curing with all leads and lifts of water all
8 M2 27599.29 54.43 1502229.54
complete as per building specification and direction
of E/I. (JH SOR 2022/Part A /Page 204/5.7.11).

9 Carriage of Cement T.Km 2262.84 524.00 1185729.53

10 Carriage of Sand T.Km 2356.96 199.06 469177.17

11 Carriage of Boulder T.Km 525.56 536.98 282214.17

Total in Rupees 27936140.15


18% GST in Rupees 5028505.226
Sub Total in Rupees 32964645.37
1% Labor Cess in Rupees 329646.4537
0.5% contigency = 164823.227

Grand Total in Rupees = 33459115.05

₹ 3,34,59,115.00

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 4 - AOC for Drains 2


Detailed estimate of Cleaning and Repair of longitudinal ,transverse and toe drains as per
DSRP 2021 Recommnedation of Page 30 ( C ) D/S Slope(iv) and (v).
Item no. 1 :- Earth work in bed clearance or desilting of canals carrying F.S.discharge
between 8.5 cumecs (300 cusecs) and 0.14 cumecs (5 cusecs) and renovation of pyines etc
disposal of excavated earth etc. and in ordinary soil including rough dressing with initial
lead of 10M and lift of 1.5M as per specification and direction of E/I.

(i) Toe Drain

Length of Toe Drain in meter =(Ch. 213.00


From To Chains
to 196.00 and ch. 184.00 to ch. 3.00)
213.00 196.00 17.00
184.00 3.00 181.00
Total 198.00
Length in Meter = 5940.00 Meter
Average depth of silt in Toe drain in meter = 0.600 M
0.5 x sum of parallel sides x
Area of Cross section at depth of 600mm =
perpendicular distance
Lower side /Base of Trapezoidal shape 610.00mm= 0.610 M
Upper side of Trapezoidal shape = 0.610 + 2x.600x1.5 = 2.410 M
Sum of Parallel sides = 3.020 M
Vertical distance in m = 0.600 M
Area of Cross section at depth of 600mm = 0.906 M2
Volume of silt in cubic meter =(0.906M2x 5940.00m) 5381.64 M3

(II) Slope Drain

Unit 4 - Detailed estimate for Drains 1


(A) Chain 213.00 to 196.00

Nearest
sum of
chain of Length in Avg silt in Base side of Top side of Area of silted
Volume in
Sl.No. Trapezoidal Trapezoidal Parallel Trapezoidal
slope M M shape shape shape M3
sides
drain
1 213.00 11.20 0.150 0.300 0.525 0.825 0.0619 0.69
2 210.00 21.00 0.150 0.300 0.525 0.825 0.0619 1.30
3 209.00 29.00 0.150 0.300 0.525 0.825 0.0619 1.79
4 208.00 31.00 0.150 0.300 0.525 0.825 0.0619 1.92
5 207.00 39.00 0.150 0.300 0.525 0.825 0.0619 2.41
6 206.00 45.60 0.180 0.300 0.57 0.870 0.0783 3.57
7 205.00 48.60 0.180 0.300 0.57 0.870 0.0783 3.81
8 204.00 51.60 0.180 0.300 0.57 0.870 0.0783 4.04
9 203.00 56.40 0.180 0.300 0.57 0.870 0.0783 4.42
10 202.00 57.80 0.180 0.300 0.57 0.870 0.0783 4.53
11 201.00 59.20 0.150 0.300 0.525 0.825 0.0619 3.66
12 200.00 65.00 0.150 0.300 0.525 0.825 0.0619 4.02
13 194.00 64.60 0.150 0.300 0.525 0.825 0.0619 4.00
Total Volume of silt in M3 40.16
(B) Chain 184.00 to Ch. 134.00
Nearest
sum of
chain of Length in Avg silt in Base side of Top side of Area of silted
Volume in
Sl.No. Trapezoidal Trapezoidal Parallel Trapezoidal
slope M M shape shape shape M3
sides
drain
1 184.00 59.80 0.175 0.300 0.5625 0.863 0.0755 4.51
2 183.00 78.40 0.175 0.300 0.5625 0.863 0.0755 5.92
3 182.00 89.30 0.175 0.300 0.5625 0.863 0.0755 6.74
4 181.00 95.60 0.175 0.300 0.5625 0.863 0.0755 7.21
5 180.00 97.00 0.180 0.300 0.57 0.870 0.0783 7.60
6 179.00 112.00 0.180 0.300 0.57 0.870 0.0783 8.77
7 178.00 116.00 0.180 0.300 0.57 0.870 0.0783 9.08
8 177.00 120.00 0.180 0.300 0.57 0.870 0.0783 9.40
9 176.00 124.00 0.180 0.300 0.57 0.870 0.0783 9.71
10 175.00 128.00 0.180 0.300 0.57 0.870 0.0783 10.02
11 174.00 132.00 0.180 0.300 0.57 0.870 0.0783 10.34
12 173.00 136.00 0.180 0.300 0.57 0.870 0.0783 10.65
13 172.00 140.00 0.180 0.300 0.57 0.870 0.0783 10.96
14 171.00 144.00 0.180 0.300 0.57 0.870 0.0783 11.28
15 170.00 148.00 0.180 0.300 0.57 0.870 0.0783 11.59
16 169.00 152.00 0.180 0.300 0.57 0.870 0.0783 11.90
17 168.00 156.00 0.180 0.300 0.57 0.870 0.0783 12.21
18 167.00 160.00 0.180 0.300 0.57 0.870 0.0783 12.53
19 166.00 164.00 0.180 0.300 0.57 0.870 0.0783 12.84
20 165.00 172.00 0.180 0.300 0.57 0.870 0.0783 13.47

Unit 4 - Detailed estimate for Drains 2


21 164.00 169.60 0.150 0.300 0.53 0.825 0.0619 10.49
22 163.00 167.22 0.150 0.300 0.53 0.825 0.0619 10.35
23 162.00 164.83 0.150 0.300 0.53 0.825 0.0619 10.20
24 161.00 162.44 0.150 0.300 0.53 0.825 0.0619 10.05
25 160.00 160.05 0.150 0.300 0.53 0.825 0.0619 9.90
26 159.00 157.66 0.150 0.300 0.53 0.825 0.0619 9.76
27 158.00 155.27 0.150 0.300 0.53 0.825 0.0619 9.61
28 157.00 152.88 0.150 0.300 0.53 0.825 0.0619 9.46
29 156.00 150.49 0.150 0.300 0.53 0.825 0.0619 9.31
30 155.00 148.10 0.150 0.300 0.53 0.825 0.0619 9.16
31 154.00 145.71 0.150 0.300 0.53 0.825 0.0619 9.02
32 153.00 143.32 0.150 0.300 0.53 0.825 0.0619 8.87
33 152.00 140.93 0.150 0.300 0.53 0.825 0.0619 8.72
34 151.00 138.54 0.150 0.300 0.53 0.825 0.0619 8.57
35 150.00 136.15 0.150 0.300 0.53 0.825 0.0619 8.42
36 149.00 133.76 0.150 0.300 0.53 0.825 0.0619 8.28
37 148.00 131.37 0.150 0.300 0.53 0.825 0.0619 8.13
38 147.00 128.98 0.150 0.300 0.53 0.825 0.0619 7.98
39 146.00 126.59 0.150 0.300 0.53 0.825 0.0619 7.83
40 145.00 124.20 0.150 0.300 0.53 0.825 0.0619 7.68
41 144.00 121.81 0.150 0.300 0.53 0.825 0.0619 7.54
42 143.00 119.42 0.150 0.300 0.53 0.825 0.0619 7.39
43 142.00 117.03 0.150 0.300 0.53 0.825 0.0619 7.24
44 141.00 114.64 0.150 0.300 0.53 0.825 0.0619 7.09
45 140.00 112.25 0.150 0.300 0.53 0.825 0.0619 6.95
46 139.00 109.86 0.150 0.300 0.53 0.825 0.0619 6.80
47 138.00 107.47 0.150 0.300 0.53 0.825 0.0619 6.65
48 137.00 105.08 0.150 0.300 0.53 0.825 0.0619 6.50
49 136.00 102.69 0.150 0.300 0.53 0.825 0.0619 6.35
50 135.00 100.30 0.150 0.300 0.53 0.825 0.0619 6.21
51 134.00 96.00 0.150 0.300 0.53 0.825 0.0619 5.94
Total Volume of silt in M3 453.17

(C) Chain 134.00 to Ch. 100.00


Nearest
sum of
chain of Length in Avg silt in Base side of Top side of Area of silted
Volume in
Sl.No. Trapezoidal Trapezoidal Parallel Trapezoidal
slope M M shape shape shape M3
sides
drain
1 133.00 92.00 0.175 0.300 0.5625 0.863 0.0755 6.94
2 132.00 90.00 0.175 0.300 0.5625 0.863 0.0755 6.79
3 131.00 88.00 0.175 0.300 0.5625 0.863 0.0755 6.64
4 130.00 86.00 0.175 0.300 0.5625 0.863 0.0755 6.49
5 129.00 84.00 0.180 0.300 0.57 0.870 0.0783 6.58
6 128.00 82.00 0.180 0.300 0.57 0.870 0.0783 6.42
7 127.00 80.00 0.180 0.300 0.57 0.870 0.0783 6.26
8 126.00 78.00 0.180 0.300 0.57 0.870 0.0783 6.11

Unit 4 - Detailed estimate for Drains 3


9 125.00 76.00 0.180 0.300 0.57 0.870 0.0783 5.95
10 124.00 74.00 0.180 0.300 0.57 0.870 0.0783 5.79
11 123.00 72.00 0.180 0.300 0.57 0.870 0.0783 5.64
12 122.00 70.00 0.180 0.300 0.57 0.870 0.0783 5.48
13 121.00 68.00 0.180 0.300 0.57 0.870 0.0783 5.32
14 120.00 66.00 0.180 0.300 0.57 0.870 0.0783 5.17
15 119.00 64.00 0.180 0.300 0.57 0.870 0.0783 5.01
16 118.00 70.00 0.180 0.300 0.57 0.870 0.0783 5.48
17 117.00 66.50 0.180 0.300 0.57 0.870 0.0783 5.21
18 116.00 63.00 0.180 0.300 0.57 0.870 0.0783 4.93
19 115.00 59.50 0.180 0.300 0.57 0.870 0.0783 4.66
20 114.00 56.00 0.180 0.300 0.57 0.870 0.0783 4.38
21 113.00 52.50 0.150 0.300 0.53 0.825 0.0619 3.25
22 112.00 49.00 0.150 0.300 0.53 0.825 0.0619 3.03
23 111.00 45.50 0.150 0.300 0.53 0.825 0.0619 2.82
24 110.00 42.00 0.150 0.300 0.53 0.825 0.0619 2.60
25 109.00 38.50 0.150 0.300 0.53 0.825 0.0619 2.38
26 108.00 35.00 0.150 0.300 0.53 0.825 0.0619 2.17
27 107.00 31.50 0.150 0.300 0.53 0.825 0.0619 1.95
28 106.00 28.00 0.150 0.300 0.53 0.825 0.0619 1.73
29 105.00 24.50 0.150 0.300 0.53 0.825 0.0619 1.52
30 104.00 21.00 0.150 0.300 0.53 0.825 0.0619 1.30
31 103.00 17.50 0.150 0.300 0.53 0.825 0.0619 1.08
32 102.00 14.00 0.150 0.300 0.53 0.825 0.0619 0.87
33 101.00 10.50 0.150 0.300 0.53 0.825 0.0619 0.65
34 100.00 13.50 0.150 0.300 0.53 0.825 0.0619 0.84
Total Volume of silt in M3 141.44
( D ) Chain 100.00 to chain 42.00
sum of
Number Length in Avg silt in Base side of Top side of Area of silted
Volume in
Sl.No. Trapezoidal Trapezoidal Parallel Trapezoidal
of drains M M shape shape shape M3
sides
1 12.00 26.00 0.175 0.300 0.5625 0.863 0.0755 23.55
2 10.00 22.00 0.180 0.300 0.57 0.870 0.0783 17.23
3 6.00 20.50 0.150 0.300 0.525 0.825 0.0619 7.61
Total Volume of silt in M3= 48.38
( E ) Chain 42.00 to chain 13.00
sum of
Number Length in Avg silt in Base side of Top side of Area of silted
Volume in
Sl.No. Trapezoidal Trapezoidal Parallel Trapezoidal
of drains M M shape shape shape M3
sides
1 6.00 12.00 0.175 0.300 0.5625 0.863 0.0755 5.43
2 5.00 10.00 0.180 0.300 0.57 0.870 0.0783 3.92
3 3.00 7.50 0.150 0.300 0.525 0.825 0.0619 1.39
Total Volume of silt in M3= 10.74
Total Volume of Silt in M3 in All slope drains = 693.89 M3

Unit 4 - Detailed estimate for Drains 4


Berm Drains
No. of sum of
Length in Avg silt in Base side of Top side of
Sl.No. Description Berms Trapezoidal Trapezoidal Parallel
Meter M shape shape
drains sides
1 Ch. 213.00 to 194.00 1.00 570.00 0.175 0.300 0.650 0.950
2 Ch. 184.00 to 172.00 3.00 360.00 0.180 0.300 0.660 0.960
3 Ch. 172.00 to 140.00 4.00 960.00 0.150 0.300 0.600 0.900
4 Ch. 140.00 to 116.00 3.00 720.00 0.150 0.300 0.600 0.900
5 Ch. 116.00 to 100.00 2.00 480.00 0.150 0.300 0.600 0.900
6 Ch. 100.00 to 1.00 1.00 2970.00 0.150 0.300 0.600 0.900

sum of Area of
Top side of
silted Volume in
Sl.No. Description Trapezoidal Parallel
shape
Trapezoidal M3
sides shape
1 Ch. 213.00 to 194.00 0.950 0.0831 47.38
2 Ch. 184.00 to 172.00 0.960 0.0864 93.31
3 Ch. 172.00 to 140.00 0.900 0.0675 259.20
4 Ch. 140.00 to 116.00 0.900 0.0675 145.80
5 Ch. 116.00 to 100.00 0.900 0.0675 64.80
6 Ch. 100.00 to 1.00 0.900 0.0675 200.48
3
Total Volume of silt in M 810.97

Earth work in bed clearance or desilting of canals carrying F.S.discharge between 8.5
cumecs (300 cusecs) and 0.14 cumecs (5 cusecs) and renovation of pynes etc disposal of
Item
excavated earth etc. and in ordinary soil including rough dressing with initial lead of 10M
number 1
and lift of 1.5M as per specification and direction of E/I. (JH SOR 2022/WRD/ Page
134/7.1.20)
S.No. Description of Silt Volume Remark
3
1 Volume of Silt in Toe Drain 5381.64 M
2 Volume of Silt in Slope Drain 693.89 M3
3 Volume of Silt in Berm Drain 810.97 M3
Total Volume of Silt in Dam = 6886.50 M3

Extra for earth work in marshy, slushy and daldal soil(Vide classification of soil item-F)
Item 2
all complete as per specification and direction of E/I.
3
Same as item no. 1 = 6886.50 M

DETAILS OF DRAINS
Length of Toe Drain in meter =(Ch. 213.00 From To Chains
213.00 196.00 17.00
184.00 3.00 181.00
Total 198.00
Length in Meter = 5940.00 Meter

Unit 4 - Detailed estimate for Drains 5


Vertical Depth in centre of Toe drain =3.5 feet = 1.100 M
0.5 x sum of parallel sides x
Area of Cross section at depth of 1100 mm =
perpendicular distance
Lower side /Base of Trapezoidal shape 600.00mm= 0.600 M
Upper side of Trapezoidal shape = 0.600 + 2x.600x1.1 = 3.900 M
Sum of Parallel sides = 4.500 M
Vertical distance in m = 1.100 M
Area of Cross section at depth of 1100mm = 2.475 M2
Single stone Masonary (300mm depth stone)= 0.300 M
Total Surface Area of stone Masonary in M2 14701.50 M2
Total Volume of Stone Masonary in M3 4410.45 M3

Total Perimeter of Toe drain =19 feet = 5.80 meter


Deoth of stone =300mm = 0.3 meter
Length = 200.00 chain = 200x30m= 6000 meter
Total surface area in M
2
34800.00 M2
Total stone masonary Volume in Toe drain in M3 10440.00 M3

SLOPE DRAINS
(A) Chain 213.00 to 196.00

Nearest
Length of Perimeter Depth of
chain of stone Suraface Volume in
Sl.No. slope of drain Masonary 2
slope Area in M M3
drain in M in M 300mm
drain
1 213.00 11.20 2.000 0.300 22.400 6.72
2 210.00 21.00 2.000 0.300 42.000 12.60
3 209.00 29.00 2.000 0.300 58.000 17.40
4 208.00 31.00 2.000 0.300 62.000 18.60
5 207.00 39.00 2.000 0.300 78.000 23.40
6 206.00 45.60 2.000 0.300 91.200 27.36
7 205.00 48.60 2.000 0.300 97.200 29.16
8 204.00 51.60 2.000 0.300 103.200 30.96
9 203.00 56.40 2.000 0.300 112.800 33.84
10 202.00 57.80 2.000 0.300 115.600 34.68
11 201.00 59.20 2.000 0.300 118.400 35.52
12 200.00 65.00 2.000 0.300 130.000 39.00
13 194.00 64.60 2.000 0.300 129.200 38.76
580.00
M2
2
Total Surface Area of stone Masonary in M 1160.00
Total Volume of Stone Masonary in
348.00
M3
(B) Chain 184.00 to Ch. 134.00

Unit 4 - Detailed estimate for Drains 6


Nearest
Perimeter Depth of
chain of Length in stone Suraface Volume in
Sl.No. of drain Masonary 2
slope M Area in M M3
in M 300mm
drain
1 184.00 59.80 2.000 0.300 119.60 35.88
2 183.00 78.40 2.000 0.300 156.80 47.04
3 182.00 89.30 2.000 0.300 178.60 53.58
4 181.00 95.60 2.000 0.300 191.20 57.36
5 180.00 97.00 2.000 0.300 194.00 58.20
6 179.00 112.00 2.000 0.300 224.00 67.20
7 178.00 116.00 2.000 0.300 232.00 69.60
8 177.00 120.00 2.000 0.300 240.00 72.00
9 176.00 124.00 2.000 0.300 248.00 74.40
10 175.00 128.00 2.000 0.300 256.00 76.80
11 174.00 132.00 2.000 0.300 264.00 79.20
12 173.00 136.00 2.000 0.300 272.00 81.60
13 172.00 140.00 2.000 0.300 280.00 84.00
14 171.00 144.00 2.000 0.300 288.00 86.40
15 170.00 148.00 2.000 0.300 296.00 88.80
16 169.00 152.00 2.000 0.300 304.00 91.20
17 168.00 156.00 2.000 0.300 312.00 93.60
18 167.00 160.00 2.000 0.300 320.00 96.00
19 166.00 164.00 2.000 0.300 328.00 98.40
20 165.00 172.00 2.000 0.300 344.00 103.20
21 164.00 169.60 2.000 0.300 339.20 101.76
22 163.00 167.22 2.000 0.300 334.44 100.33
23 162.00 164.83 2.000 0.300 329.65 98.90
24 161.00 162.44 2.000 0.300 324.87 97.46
25 160.00 160.05 2.000 0.300 320.09 96.03
26 159.00 157.66 2.000 0.300 315.31 94.59
27 158.00 155.27 2.000 0.300 310.53 93.16
28 157.00 152.88 2.000 0.300 305.75 91.73
29 156.00 150.49 2.000 0.300 300.97 90.29
30 155.00 148.10 2.000 0.300 296.19 88.86
31 154.00 145.71 2.000 0.300 291.41 87.42
32 153.00 143.32 2.000 0.300 286.63 85.99
33 152.00 140.93 2.000 0.300 281.85 84.56
34 151.00 138.54 2.000 0.300 277.07 83.12
35 150.00 136.15 2.000 0.300 272.29 81.69
36 149.00 133.76 2.000 0.300 267.51 80.25
37 148.00 131.37 2.000 0.300 262.73 78.82
38 147.00 128.98 2.000 0.300 257.95 77.39
39 146.00 126.59 2.000 0.300 253.17 75.95
40 145.00 124.20 2.000 0.300 248.39 74.52
41 144.00 121.81 2.000 0.300 243.61 73.08
42 143.00 119.42 2.000 0.300 238.83 71.65

Unit 4 - Detailed estimate for Drains 7


43 142.00 117.03 2.000 0.300 234.05 70.22
44 141.00 114.64 2.000 0.300 229.27 68.78
45 140.00 112.25 2.000 0.300 224.49 67.35
46 139.00 109.86 2.000 0.300 219.71 65.91
47 138.00 107.47 2.000 0.300 214.93 64.48
48 137.00 105.08 2.000 0.300 210.15 63.05
49 136.00 102.69 2.000 0.300 205.37 61.61
50 135.00 100.30 2.000 0.300 200.59 60.18
51 134.00 96.00 2.000 0.300 192.00 57.60
Total Surface Area of stone Masonary in M2 13337.3 M2
3
Total Volume of Stone Masonary in M 4001.19

(C) Chain 134.00 to Ch. 100.00


Nearest
Perimeter Depth of
chain of Length in stone Suraface Volume in
Sl.No. of drain Masonary 2
slope M Area in M M3
in M 300mm
drain
1 133.00 92.00 2.000 0.300 184.00 55.20
2 132.00 90.00 2.000 0.300 180.00 54.00
3 131.00 88.00 2.000 0.300 176.00 52.80
4 130.00 86.00 2.000 0.300 172.00 51.60
5 129.00 84.00 2.000 0.300 168.00 50.40
6 128.00 82.00 2.000 0.300 164.00 49.20
7 127.00 80.00 2.000 0.300 160.00 48.00
8 126.00 78.00 2.000 0.300 156.00 46.80
9 125.00 76.00 2.000 0.300 152.00 45.60
10 124.00 74.00 2.000 0.300 148.00 44.40
11 123.00 72.00 2.000 0.300 144.00 43.20
12 122.00 70.00 2.000 0.300 140.00 42.00
13 121.00 68.00 2.000 0.300 136.00 40.80
14 120.00 66.00 2.000 0.300 132.00 39.60
15 119.00 64.00 2.000 0.300 128.00 38.40
16 118.00 70.00 2.000 0.300 140.00 42.00
17 117.00 66.50 2.000 0.300 133.00 39.90
18 116.00 63.00 2.000 0.300 126.00 37.80
19 115.00 59.50 2.000 0.300 119.00 35.70
20 114.00 56.00 2.000 0.300 112.00 33.60
21 113.00 52.50 2.000 0.300 105.00 31.50
22 112.00 49.00 2.000 0.300 98.00 29.40
23 111.00 45.50 2.000 0.300 91.00 27.30
24 110.00 42.00 2.000 0.300 84.00 25.20
25 109.00 38.50 2.000 0.300 77.00 23.10
26 108.00 35.00 2.000 0.300 70.00 21.00
27 107.00 31.50 2.000 0.300 63.00 18.90
28 106.00 28.00 2.000 0.300 56.00 16.80
29 105.00 24.50 2.000 0.300 49.00 14.70

Unit 4 - Detailed estimate for Drains 8


30 104.00 21.00 2.000 0.300 42.00 12.60
31 103.00 17.50 2.000 0.300 35.00 10.50
32 102.00 14.00 2.000 0.300 28.00 8.40
33 101.00 10.50 2.000 0.300 21.00 6.30
34 100.00 13.50 2.000 0.300 27.00 8.10
Surface Area 3816.00
Total Volume of Stone Masonary in M3 1144.80
Total Surface area of Stone Masonary in M2 = 3816.00

( D ) Chain 100.00 to chain 42.00


Perimeter Depth of
Number Length in stone Suraface Volume in
Sl.No. of drain Masonary
of drains M Area in M2 M3
in M 300mm
1 12.00 26.00 2.000 0.300 52.00 15.60
2 10.00 22.00 2.000 0.300 44.00 13.20
3 6.00 20.50 2.000 0.300 41.00 12.30
137.00
Total Volume of Stone Masonary in M3= 41.10
2
Total Surface area of Stone Masonary in M2 = 137.000 M

( E ) Chain 42.00 to chain 13.00


Perimeter Depth of
Number Length in stone Suraface Volume in
Sl.No. of drain Masonary
of drains M Area in M2 M3
in M 300mm
1 6.00 12.00 2.000 0.300 24.00 7.20
2 5.00 10.00 2.000 0.300 20.00 6.00
3 3.00 7.50 2.000 0.300 15.00 4.50
Total Volume of Stone Masonary in M3= 17.70
Total Surface area of Stone Masonary in M2 = 59.00
3
Total Volume of stone in M3 in All slope drains = 5552.79 M
Total Surface area of stone in M2 in All slope drains = 18509.29 M2
Berm Drains

No. of Depth of Volume in


Length in Perimeter in Surface Area
Sl.No. Description Berms stone stone
Meter meter in M2
drains Masonary Masonary in M3

1 Ch. 213.00 to 194.00 1.00 570.00 0.300 2.000 1140.00 342.000


2 Ch. 184.00 to 172.00 3.00 360.00 0.300 2.000 720.00 216.000
3 Ch. 172.00 to 140.00 4.00 960.00 0.300 2.000 1920.00 576.000
4 Ch. 140.00 to 116.00 3.00 720.00 0.300 2.000 1440.00 432.000
5 Ch. 116.00 to 100.00 2.00 480.00 0.300 2.000 960.00 288.000
6 Ch. 100.00 to 1.00 1.00 2970.00 0.300 2.000 5940.00 1782.000
Total Volume of Stone Masonary in Berm drains in M3 3636.00
Total surface area of Stone Masonary in Berm drains in M2 12120.00

Unit 4 - Detailed estimate for Drains 9


Surface
S.No. Description of Stone Volume Unit Unit
Area
3
1 Toe Drain 10440.00 M 34800.00 M2
3
2 Slope Drain 5552.79 M 18509.29 M2
3 2
3 Berm Drain 3636.00 M 12120.00 M
Total Volume of Stones in Drains= 19628.79 M3 65429.29 M2
Damaged Net
S.No. Description of Stone Volume Unit
% Volume
3
1 Toe Drain 10440.00 M 0.25 2610.00
3
2 Slope Drain 5552.79 M 0.28 1554.78
3
3 Berm Drain 3636.00 M 0.30 1090.80
Total Volume of Stone Masonary in
19628.79 M3 0.28 5255.58 M3
Drains=

Damaged Net Surface


S.No. Description of Stone Total Area Unit
% Area
2
1 Toe Drain 34800.00 M 0.25 8700.00
2
2 Slope Drain 18509.29 M 0.28 5182.60
2
3 Berm Drain 12120.00 M 0.30 3636.00
Total Surface Area of Stone Masonary in
65429.29 M2 0.28 17518.60 M2
Drains =

Scrapping of stone from dismantled stone masonary in cemnet mortar and lime mortar
Item 3
(JH SOR 2022/common Part A/ Page 197/2.04/(vii)/A)
Scrapping stone = 5255.58 M3

Scrapping Plaster in lime and cement mortar from Brick/Stone Masonary (JH SOR
Item 4
2022/common Part A/ Page 197/2.04/(viii)
Scrapping Plaster = 17518.60 M2

Providing random rubble stone masonary (1:4) in foundation and plinth with hammer dressed stone
of less than 0.03 M3 in volume and clean coarse sand of F.M. 2 to 2.5 including cost of screening
Item 5
materials raking out joints to 20mm depth , curing , taxes and royalty all complete as per builiding
specification and direction of E/I.(JH SOR 2022/Part A /Page 204/5.2.28)

RRM in Dam = 5255.58 M3

Providing tuck pointing in cement on stone masonary (1:3) with clean coarse sand of F.M
1.50 including screening curing with all leads and lifts of water scaffolding taxes and royalty
Item 6
all complete as per building specification and direction of E/I. (JH SOR 2022/Part A /Page
204/5.7.10).
For Damaged Part 100%= 34800.00 Toe Drain Area
40% of this needs tuck pointing = 0.40
Net Area for Tuck pointing = 13920.00 M2

Providing 25 mm thick water proof cement plaster (1:3) clean coarse sand of F.M 1.50 with
5% cico or any other water proofing compound including screening curing with all leads
item 7
and lifts of water scaffolding taxes and royalty all complete as per building specification and
Unit 4 - Detailed
direction of E/I. (JH SOR 2022/Part A /Pageestimate for Drains
204/5.7.16). 10
Providing 25 mm thick water proof cement plaster (1:3) clean coarse sand of F.M 1.50 with
5% cico or any other water proofing compound including screening curing with all leads
item 7
and lifts of water scaffolding taxes and royalty all complete as per building specification and
direction of E/I. (JH SOR 2022/Part A /Page 204/5.7.16).
S.No. Description Net Area
2
1 Slope Drain 5182.60 m
2
2 Berm Drain 3636.00 m
Total Area for Cement Plaster = 8818.60 M2
Providing 1.5mm cement punning including screening curing with all leads and lifts of
Item 9 water all complete as per building specification and direction of E/I. (JH SOR 2022/Part A
/Page 204/5.7.11).
S.No. Description Area
2
1 Slope Drain (100%) Punning = 18509.29 m
2
2 Berm Drain (75% Punning) 9090.00 m
2
Total Punning in slope as well as berm drain= 27599.29 m

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 4 - Detailed estimate for Drains 11


Material Consumption Statement

Cement in
S.No. Item Unit Qty Sand Boulder
M3
RR Stone Masonary
1 (1:4)(0.125 Cement M3 5255.58 656.95 1970.843 5255.58
and 0.375 sand )
Cement Plaster (1:3)
2 M2 8818.60 793.67 246.92 0
25mm thick
1.50 mm neat
3 M2 27599.29 41.399 0.00 0
Cement Punning
4 Tuck Pointing (1:3) M2 13920.00 47.33 139.20 0

Total 1539.35 2356.96 5255.58

Cement in M3 1539.35 M3
Cement in MT = 2262.84 MT
Cement in Number of Bags = 45257 bags
Only 10% Boulder Required = 525.56 M3

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 4 - Material Statement for drains 1


Unit -5

Removal of coffer dam in U/S


of Tenu Bokaro Link Canal
approach Channel and
cleaning of approach channel
of TBLC as per
Recommendation of DSRP
2021 from Page 26.
Estimate for Removal of coffer dam in U/S of Tenu Bokaro Link Canal approach Channel and cleaning of
approach channel of TBLC as per Recommnedation of DSRP 2021 from Page 26.

SL.No. Item Unit Quantity Rate Amount in Rs.

Earth work in bed clearance or de silting of


canals carrying F.S. discharge of 28 cumecs
(1000 cusecs) and 8.5 cumecs (300 cusecs)
including rough dressing with initial lead of
1 M3 18748.725 120.61 2261283.72
10 M and Lift of 1.5 M as per specification
and direction of E/I (Specification revised
vide T.E.C letter No. 63 dt. 07.10.1994)(JH
SOR 2022 WRD/Page 134/7.1.19)

Extra for wet earth all complete as per


specification and direction of E/I.(JH SOR
2 M3 18748.725 13.27 248795.58
2022 WRD/Page 135/7.1.22)

Extra for earth work in each additional lead


of 25 M beyond the Initial as per
specification and direction of E/I.
For Ordinary or hard soil (vide classification
3 M3 18748.725 26.54 497591.16
of soil item A and B) Lead 2.00 nos.
(13.27x2 = 26.54 rs.(JH SOR 2022
WRD/Page 136/7.1.33.1)

Extra for earthwork for each subsequent lift


of 1M over the initial lift of 1.50M.For
Ordinary or hard soil (vide classification of 3
4 M 18748.725 13.27 248795.58
soil item A and B(JH SOR 2022 WRD/Page
136/7.1.34.1)

Total in Rs. 3256466.05


18% GST in Rs. 586163.89
Sub-Total in Rs. 3842629.93
1% Labor Cess = 38426.30
1% CNC = 38426.30
Grand total in Rs.= 3919482.53
Say in Rupees = ₹ 39,19,483.00

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 5 -AOC TBLC coffer dam Removal 1


Calculation of soil in Cubic meter for de siltation from chain 18.00 to chain
24.00 in Tenu - Bokaro Link Canal under Tenughat Dam Division

Sr. Chain Length in C/S Area in Mean C/S Quantity


No. (M) (M2) Area in (M2) in
(M3)

1. 18.00 0.00 105.00 0.00 0.00

2. 19.00 30.00 125.00 115.00 3450.00

3. 20.00 30.00 104.00 114.50 3435.00

4. 21.00 30.00 79.00 91.50 2745.00

5. 22.00 30.00 72.00 75.50 2265.00

6. 23.00 30.00 62.00 67.00 2010.00

7. 24.00 30.00 41.00 51.50 1545.00

Total 15450.00

Total soil for de silting is 15450.00 M3

Junior Engineer Assistant Engineer Executive Engineer


Tenughat dam division
Tenughat
Calculation of Volume of silt to be removed from Approach Channel

SL.N Base in Top sum of Soil top Length


Chain Depth Area RL of base Avg Area Volume
o. M width sides layer RL in M

17.86 TO 18.00
A COFFER DAM 32.00 5.819 49.46 81.46 236.98 249.83 255.65 236.98 13.92 3298.725

B Approach Channel
1 18.00 0.5 38.25 2.50 45.75 84.00 105 249.98 252.48
2 19.00 0.5 38.25 2.93 47.04 85.29 125 249.83 252.76 115.00 30.00 3450
3 20.00 0.5 38.25 2.48 45.69 83.94 104 249.68 252.16 114.50 30.00 3435
4 21.00 0.5 38.25 1.93 44.04 82.29 79 249.53 251.46 91.50 30.00 2745
5 22.00 0.5 38.25 1.75 43.50 81.75 72 249.38 251.13 75.50 30.00 2265
6 23.00 0.5 38.25 1.52 42.81 81.06 62 249.23 250.75 67.0 30.00 2010
7 0.5 38.25 1.02 41.31 79.56 41 249.08 250.10 51.50 30.00 1545
Total Volume in cubic meter =(Coffer dam + Approach channel Silt)= 18748.725 M3

JE AE Executive Engineer
Tenughat Dam Division
TBLC Intake point Reduced Level
SL.NO. Distance Back sight Inter sight foresight H.I R.L Remark
1 Station A 2.96 255.70 252.74
2 1.8 253.90
3 Station B 0.400 3.10 253.00 252.60
4 Station C 1.49 1.25 253.24 251.75
5 Chain 18 0.760 252.480
6 0.800 252.440
7 0.850 252.390
8 0.900 252.340
9 0.910 252.330
10 Chain 19 0.480 252.760
11 0.800 252.440
12 1.000 252.240
13 1.200 252.040
14 1.300 251.940
15 Chain 20 1.080 252.160
16 1.200 252.040
17 1.350 251.890
18 1.250 251.990
19 Chain 21 1.780 251.460
20 1.860 251.380
21 1.960 251.280
22 2.000 251.240
23 Chain 22 2.110 251.130
24 2.200 251.040
25 Chain 23 2.490 250.750
26 2.560 250.680
27 2.750 250.490
28 Chain 24 3.140 250.100

JE AE Executive Engineer
Tenughat Dam Division
Tenughat
chanel
Chain 18-00 0F TBLC Approagh

Boe wicth 38 25 m

A rea of so s l05 60

Ri252- 42

RL249.98

LChain: l9o0
Base Widy 2 38-2S M

s.A2. |25 Dm
-R.L252-76

RL= 249.83
Chon 20:00
Bae 38-25

Cs Are 2 l04-o0 m

RL=252-J6

RL-249.68

Chain 21:(0

Slle
de243

R:l2 2I-6.

24953
Chain 22co
Bae olesn 33 25 m
Y3 So

Rl 2S1·13

RL2993 &

Tob wnlh42-&1 M.
Bajei wstts.3 25 M

ofea |.52m

RLe. 2So.7s

Re 249. 23
IChun= 24-00

Bae oh342sm

COffer DARM
Base 32-0M

KLa 2Ss6S.

bam

R-L 249-.83
ea, . 236: 92 m
Unit -6

Filling the good quality


compact earth, Benching and
Turfing in D/S slope of
Tenughat Dam as per DSRP
Recommendations from Page
30 ( C )D/S Slope (ii) & (iii).
Abstract of cost of Filling the good quality compact earth ,Benching and Turfing in D/S
slope of Tenughat Dam as per DSRP Recommnedation from Page 30 ( C )D/S Slope (ii) &
(iii).
Sl.No. Item unit Qunatity Rate Amount

Fine dressing of the earthen embankmnet and


turfing with 75mm grass sods,obtained within
a lead of 150M including the cost of watering Per100
1 2 3219.21 1502.86 4838016.53
the grass surface till it requires greenness as M
per specification and direction of E/I. (WRD
JH SOR 2022/Page 121/6.1.24.1)

Extra for each lead of 150.00 m over initial


lead of 150.00 m as per specifictaion and
Per100
2 direction of E/I.(WRD JH SOR 2022/Page 3219.21 1127.14 3628496.30
M2
121/6.1.24.2)(2 lead of 150.00 m each
=563.37x2 =1127.14 Rs.)

E/W in dam fill in semi pervious or


impervious zone excavation by Hydraulic
excavator and carriage by tipper truck making
dam in proper design section including earth
to be laid in layers of not more than 225mm
3 thick and breaking clods to maximum 63mm M3 18108.04 148.46 2688319.02
cube with all lifts including construction and
maintenance of haul road etc. all complete as
per specification and direction of E/I.Lead
beyond 2Km but upto Km (WRD JH SOR
2022/Page 102/5.1.22.4)

Total (A) ₹ 1,11,54,831.86


B =Add 18% GST of
2007869.73
(A)
C= Sub total = 13162701.59
1% Contigecy of C = 131627.02
1% Labor cess of C = 131627.02
Grand Total ₹ 1,34,25,955.62

₹ 1,34,25,956.00

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 6-AOC of D/S slope Turfing 1


Detailed estimate of Filling the good quality compact earth ,Benching and Turfing in
D/S slope of Tenughat Dam as per DSRP Recommnedation from Page 30 ( C )D/S
Slope (ii) & (iii).
Distance from Horizontal Jungle on Avg slope
Chain Area in
Sl.No. Centre of View distance in Slope Length between Remark
Number square meter
Tower Meter In meter two chains

0 0.00 16.00 0.00


Centre of View
1 213.00 0.00 30.00 19.00 17.50 525.00 Tower is chain 213.00

Just 4 meter ahead


2 212.00 30.00 30.00 30.00 24.50 735.00 of flag post

3 211.00 60.00 30.00 35.60 32.80 984.00 Actual dam start

4 210.00 90.00 30.00 40.50 38.05 1141.50 upto RCD road


5 209.00 120.00 30.00 47.60 44.05 1321.50 upto RCD road

(36.00 + 18.00 (dam


6 208.00 150.00 30.00 54.00 50.80 1524.00 slope + toe drain )

7 207.00 180.00 30.00 60.00 57.00 1710.00


8 206.00 210.00 30.00 65.00 62.50 1875.00
9 205.00 240.00 30.00 70.00 67.50 2025.00
10 204.00 270.00 30.00 76.50 73.25 2197.50 Including Toe Drain

11 203.00 300.00 30.00 76.50 76.50 2295.00 Including Toe Drain

12 202.00 330.00 30.00 78.00 77.25 2317.50 Including Toe Drain

13 201.00 360.00 30.00 79.50 78.75 2362.50 Including Toe Drain

14 200.00 390.00 30.00 81.00 80.25 2407.50 Including Toe Drain

15 199.00 420.00 30.00 82.50 81.75 2452.50 Including Toe Drain

16 198.00 450.00 30.00 79.00 80.75 2422.50 Including Toe Drain


68.00 M before
17 197.00 480.00 30.00 73.00 76.00 2280.00 security gate
towards OP
18 196.00 510.00 30.00 67.00 70.00 2100.00
Secuirty gate OP side
(541.00 m from CVP)
19 195.00 540.00 30.00 66.00 66.50 1995.00 distance btw both
security gates =
360.00M

Stairs
downstream(548.00
20 194.00 570.00 30.00 62.00 64.00 1920.00 M from view point
centre)

21 193.00 600.00 15.00 61.00 61.50 922.50


Exact spillway (45 m
22 193.50 615.00 15.00 61.00 61.00 915.00 from SG gate 1
towards saram)
No slope concrete
23 192.00 630.00 30.00 0.00 30.50 915.00 dam
No slope concrete
24 191.00 660.00 30.00 0.00 0.00 0.00 dam

Unit 6 - Detailed estimate for turfing 1


No slope concrete
25 190.00 690.00 30.00 0.00 0.00 0.00 dam
No slope concrete
26 189.00 720.00 30.00 0.00 0.00 0.00 dam
No slope concrete
27 188.00 750.00 30.00 0.00 0.00 0.00 dam
No slope concrete
28 187.00 780.00 30.00 0.00 0.00 0.00 dam
No slope concrete
29 186.00 810.00 30.00 0.00 0.00 0.00 dam
No slope concrete
30 185.00 840.00 30.00 0.00 0.00 0.00 dam
No slope concrete
31 184.00 870.00 30.00 0.00 0.00 0.00 dam
Security Gate Saram
32 183.00 900.00 30.00 82.00 41.00 1230.00 side
33 182.00 930.00 30.00 86.00 84.00 2520.00
34 181.00 960.00 30.00 90.00 88.00 2640.00
Peterbar Gumia
35 180.00 990.00 30.00 98.00 94.00 2820.00 road curve
36 179.00 1020.00 30.00 103.00 100.50 3015.00
37 178.00 1050.00 30.00 109.60 106.30 3189.00
38 177.00 1080.00 30.00 116.20 112.90 3387.00
39 176.00 1110.00 30.00 122.80 119.50 3585.00
40 175.00 1140.00 30.00 129.40 126.10 3783.00
41 174.00 1170.00 30.00 136.00 132.70 3981.00
42 173.00 1200.00 30.00 142.60 139.30 4179.00
43 172.00 1230.00 30.00 149.20 145.90 4377.00
44 171.00 1260.00 30.00 155.80 152.50 4575.00
45 170.00 1290.00 30.00 162.40 159.10 4773.00
46 169.00 1320.00 30.00 169.00 165.70 4971.00
47 168.00 1350.00 30.00 175.60 172.30 5169.00
48 167.00 1380.00 30.00 182.20 178.90 5367.00
49 166.00 1410.00 30.00 188.80 185.50 5565.00
50 165.00 1440.00 30.00 202.00 195.40 5862.00 Longest slope start

51 164.00 1470.00 30.00 198.00 200.00 6000.00


52 163.00 1500.00 30.00 192.00 195.00 5850.00
53 162.00 1530.00 30.00 195.00 193.50 5805.00
54 161.00 1560.00 30.00 196.00 195.50 5865.00
55 160.00 1590.00 30.00 195.00 195.50 5865.00
56 159.00 1620.00 30.00 191.00 193.00 5790.00 Longest slope end
In Google map
57 158.00 1650.00 30.00 189.00 190.00 5700.00 Tenughat Dam
58 157.00 1680.00 30.00 187.00 188.00 5640.00
59 156.00 1710.00 30.00 185.00 186.00 5580.00
60 155.00 1740.00 30.00 183.00 184.00 5520.00
61 154.00 1770.00 30.00 179.90 181.45 5443.50 Water in Toe drain
62 153.00 1800.00 30.00 176.80 178.35 5350.50 Big tree in upstream

63 152.00 1830.00 30.00 173.70 175.25 5257.50


64 151.00 1860.00 30.00 170.60 172.15 5164.50

Unit 6 - Detailed estimate for turfing 2


65 150.00 1890.00 30.00 167.50 169.05 5071.50
66 149.00 1920.00 30.00 164.40 165.95 4978.50
67 148.00 1950.00 30.00 161.30 162.85 4885.50
68 147.00 1980.00 30.00 158.20 159.75 4792.50
69 146.00 2010.00 30.00 155.10 156.65 4699.50
70 145.00 2040.00 30.00 152.00 153.55 4606.50
71 144.00 2070.00 30.00 148.90 150.45 4513.50
72 143.00 2100.00 30.00 145.80 147.35 4420.50
73 142.00 2130.00 30.00 142.70 144.25 4327.50
74 141.00 2160.00 30.00 139.60 141.15 4234.50
75 140.00 2190.00 30.00 136.50 138.05 4141.50
76 139.00 2220.00 30.00 133.40 134.95 4048.50
77 138.00 2250.00 30.00 130.30 131.85 3955.50
78 137.00 2280.00 30.00 127.20 128.75 3862.50
79 136.00 2310.00 30.00 124.10 125.65 3769.50
80 135.00 2340.00 30.00 121.00 122.55 3676.50
81 134.00 2370.00 30.00 117.90 119.45 3583.50
82 133.00 2400.00 30.00 89.40 103.65 3109.50 Bharat Mata stairs

83 132.00 2430.00 30.00 82.20 85.80 2574.00


84 131.00 2460.00 30.00 81.20 81.70 2451.00
85 130.00 2490.00 30.00 80.00 80.60 2418.00
86 129.00 2520.00 30.00 85.00 82.50 2475.00
87 128.00 2550.00 30.00 85.00 85.00 2550.00
88 127.00 2580.00 30.00 85.00 85.00 2550.00
89 126.00 2610.00 30.00 85.00 85.00 2550.00
90 125.00 2640.00 30.00 85.00 85.00 2550.00
91 124.00 2670.00 30.00 85.00 85.00 2550.00
92 123.00 2700.00 30.00 88.90 86.95 2608.50
93 122.00 2730.00 30.00 95.00 91.95 2758.50
94 121.00 2760.00 30.00 95.50 95.25 2857.50
95 120.00 2790.00 30.00 95.80 95.65 2869.50
96 119.00 2820.00 30.00 95.00 95.40 2862.00
Transformer ka rasta
97 118.00 2850.00 30.00 96.20 95.60 2868.00 (Tiraha)

98 117.00 2880.00 30.00 93.00 94.60 2838.00


99 116.00 2910.00 30.00 89.50 91.25 2737.50
100 115.00 2940.00 30.00 86.00 87.75 2632.50
101 114.00 2970.00 30.00 82.50 84.25 2527.50
102 113.00 3000.00 30.00 79.00 80.75 2422.50
103 112.00 3030.00 30.00 75.50 77.25 2317.50

Unit 6 - Detailed estimate for turfing 3


104 111.00 3060.00 30.00 72.00 73.75 2212.50
105 110.00 3090.00 30.00 68.50 70.25 2107.50
106 109.00 3120.00 30.00 57.50 63.00 1890.00
107 108.00 3150.00 30.00 51.50 54.50 1635.00
108 107.00 3180.00 30.00 45.50 48.50 1455.00
109 106.00 3210.00 30.00 39.50 42.50 1275.00
110 105.00 3240.00 30.00 33.50 36.50 1095.00
111 104.00 3270.00 30.00 27.50 30.50 915.00
112 103.00 3300.00 30.00 21.50 24.50 735.00
113 102.00 3330.00 30.00 15.50 18.50 555.00
114 101.00 3360.00 30.00 9.50 12.50 375.00
115 100.00 3390.00 30.00 9.00 9.25 277.50 Central Golamber

116 99.00 3420.00 30.00 42.00 25.50 765.00


117 98.00 3450.00 30.00 42.00 42.00 1260.00
118 97.00 3480.00 30.00 42.00 42.00 1260.00
119 96.00 3510.00 30.00 42.00 42.00 1260.00
120 95.00 3540.00 30.00 42.00 42.00 1260.00
121 94.00 3570.00 30.00 42.00 42.00 1260.00
122 93.00 3600.00 30.00 42.00 42.00 1260.00
123 92.00 3630.00 30.00 42.00 42.00 1260.00
124 91.00 3660.00 30.00 42.00 42.00 1260.00
125 90.00 3690.00 30.00 42.00 42.00 1260.00
126 89.00 3720.00 30.00 42.00 42.00 1260.00
127 88.00 3750.00 30.00 42.00 42.00 1260.00
128 87.00 3780.00 30.00 42.00 42.00 1260.00
129 86.00 3810.00 30.00 42.00 42.00 1260.00
130 85.00 3840.00 30.00 42.00 42.00 1260.00
131 84.00 3870.00 30.00 42.00 42.00 1260.00
132 83.00 3900.00 30.00 42.00 42.00 1260.00
133 82.00 3930.00 30.00 42.00 42.00 1260.00
134 81.00 3960.00 30.00 40.30 41.15 1234.50
135 80.00 3990.00 30.00 38.60 39.45 1183.50
136 79.00 4020.00 30.00 36.90 37.75 1132.50
137 78.00 4050.00 30.00 35.20 36.05 1081.50
138 77.00 4080.00 30.00 33.50 34.35 1030.50
139 76.00 4110.00 30.00 31.80 32.65 979.50
140 75.00 4140.00 30.00 30.10 30.95 928.50
141 74.00 4170.00 30.00 28.40 29.25 877.50
142 73.00 4200.00 30.00 26.70 27.55 826.50
143 72.00 4230.00 30.00 25.00 25.85 775.50

Unit 6 - Detailed estimate for turfing 4


144 71.00 4260.00 30.00 23.30 24.15 724.50
145 70.00 4290.00 30.00 21.60 22.45 673.50
146 69.00 4320.00 30.00 19.90 20.75 622.50
147 68.00 4350.00 30.00 18.20 19.05 571.50
148 67.00 4380.00 30.00 16.50 17.35 520.50
149 66.00 4410.00 30.00 20.00 18.25 547.50
150 65.00 4440.00 30.00 20.50 20.25 607.50
151 64.00 4470.00 30.00 21.00 20.75 622.50
152 63.00 4500.00 30.00 21.50 21.25 637.50
153 62.00 4530.00 30.00 22.00 21.75 652.50
154 61.00 4560.00 18.00 22.50 22.25 400.50
Neeche utarne ka
155 61.60 4578.00 12.00 20.60 21.55 258.60 rasta

156 60.00 4590.00 30.00 18.70 19.65 589.50


157 59.00 4620.00 30.00 16.80 17.75 532.50
158 58.00 4650.00 30.00 14.90 15.85 475.50
159 57.00 4680.00 18.00 13.00 13.95 251.10
160 57.60 4698.00 12.00 13.60 13.30 159.60 TBLC ground first gate

161 56.00 4710.00 30.00 15.60 14.60 438.00


162 55.00 4740.00 30.00 17.60 16.60 498.00
163 54.00 4770.00 30.00 19.60 18.60 558.00
TBLC ground second
164 53.00 4800.00 30.00 21.00 630.00
22.40 gate

165 52.00 4830.00 30.00 21.20 21.80 654.00


166 51.00 4860.00 30.00 20.00 20.60 618.00
167 50.00 4890.00 30.00 18.80 19.40 582.00
168 49.00 4920.00 30.00 17.60 18.20 546.00
169 48.00 4950.00 30.00 16.40 17.00 510.00
170 47.00 4980.00 30.00 15.20 15.80 474.00
171 46.00 5010.00 30.00 14.00 14.60 438.00
172 45.00 5040.00 30.00 12.80 13.40 402.00
173 44.00 5070.00 30.00 11.60 12.20 366.00
174 43.00 5100.00 30.00 10.40 11.00 330.00
Santoshi Mandir
175 42.00 5130.00 30.00 11.00 10.70 321.00 road

176 41.00 5160.00 30.00 10.60 10.80 324.00


177 40.00 5190.00 30.00 10.20 10.40 312.00
178 39.00 5220.00 30.00 9.80 10.00 300.00
179 38.00 5250.00 30.00 9.40 9.60 288.00
180 37.00 5280.00 30.00 9.00 9.20 276.00
181 36.00 5310.00 30.00 8.60 8.80 264.00

Unit 6 - Detailed estimate for turfing 5


182 35.00 5340.00 30.00 8.20 8.40 252.00
183 34.00 5370.00 30.00 8.50 8.35 250.50 School ke peeche
184 33.00 5400.00 30.00 8.90 8.70 261.00
185 32.00 5430.00 30.00 9.30 9.10 273.00
186 31.00 5460.00 30.00 9.70 9.50 285.00
187 30.00 5490.00 30.00 10.10 9.90 297.00
188 29.00 5520.00 30.00 10.50 10.30 309.00
189 28.00 5550.00 30.00 10.90 10.70 321.00
190 27.00 5580.00 30.00 11.30 11.10 333.00
191 26.00 5610.00 30.00 11.70 11.50 345.00
192 25.00 5640.00 30.00 12.10 11.90 357.00
193 24.00 5670.00 30.00 12.50 12.30 369.00
194 23.00 5700.00 30.00 12.90 12.70 381.00
195 22.00 5730.00 30.00 14.60 13.75 412.50 Lugu shiv mandir
196 21.00 5760.00 30.00 14.00 14.30 429.00
197 20.00 5790.00 30.00 14.00 14.00 420.00
198 19.00 5820.00 30.00 14.00 14.00 420.00
199 18.00 5850.00 30.00 14.00 14.00 420.00
200 17.00 5880.00 30.00 14.00 14.00 420.00
201 16.00 5910.00 30.00 14.00 14.00 420.00
202 15.00 5940.00 30.00 14.00 14.00 420.00
203 14.00 5970.00 30.00 14.00 14.00 420.00
204 13.00 6000.00 30.00 14.00 14.00 420.00
205 12.00 6030.00 30.00 14.00 14.00 420.00
206 11.00 6060.00 30.00 14.00 14.00 420.00
207 10.00 6090.00 30.00 14.00 14.00 420.00
208 9.00 6120.00 30.00 14.00 14.00 420.00
209 8.00 6150.00 30.00 14.00 14.00 420.00
210 7.00 6180.00 30.00 14.00 14.00 420.00
211 6.00 6210.00 30.00 14.00 14.00 420.00
212 5.00 6240.00 30.00 14.00 14.00 420.00
213 4.00 6270.00 30.00 14.00 14.00 420.00
214 3.00 6300.00 30.00 14.00 14.00 420.00
215 2.00 6330.00 30.00 14.00 14.00 420.00
216 1.00 6360.00 14.00 14.00 0.00
402400.80 M2
2
(A) Total Area of downstream Slope in M 402400.80 M2
80% of total D/S slope Area is required for Turfing= 0.8

Total area for turfing in M2 321920.64 M2

Total Area for turfing in Per 100 M2 3219.21 Per % M2

Fine dressing of the earthen embankmnet and turfing with 75mm grass sods,obtained within a
1 lead of 150M including the cost of watering the grass surface till it requires greenness as per
specification and direction of E/I. (WRD JH SOR 2022/Page 121/6.1.24.1)

As per above calculation (321920.64/100)= 3219.21 Per % M2

Unit 6 - Detailed estimate for turfing 6


Extra for each lead of 150.00 m over initial lead of 150.00 m as per specifictaion and direction of
2
E/I.(WRD JH SOR 2022/Page 121/6.1.24.2)(2 lead of 150.00 m each =563.37x2 =1127.14 Rs.)
same as item number 1 = 3219.21 Per % M2

E/W in dam fill in semi pervious or impervious zone excavation by Hydraulic excavator and
carriage by tipper truck making dam in proper design section including earth to be laid in
3 layers of not more than 225mm thick and breaking clods to maximum 63mm cube with all lifts
including construction and maintenance of haul road etc. all complete as per specification and
direction of E/I.Lead beyond 2Km but upto Km (WRD JH SOR 2022/Page 102/5.1.22.4)

Total Area for turfing in M2 = 321920.64 M2


Assume 25% of Area needs earthfill = 0.25
Area needs earhfill = 80480.16 M2
225mm layer of earth at least at concerned area = 0.225 M
Volume of E/W for dam slope in M3 =(0.225m x
2 18108.04 M3
65390.13M )=

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 6 - Detailed estimate for turfing 7


Unit -7
Whitewashing of Parapet wall
and painting of Railing as per
DSRP 2021Report Page 52
1.3.7
Abstract of cost of Whitewashing of Parapet wall and painting of Railing as per
DSRP 2021Report Page 52 1.3.7
S.No. Item Unit Qty Rate in rs. Amount in Rs.

Providing two coats of Snowcem of approved shade


and make over old surface including washing
cleaning and preparing the walls, scaffolding , curing 2
1 M 18817.74 90.55 1703946.36
and taxes all complete as per building specification
and direction of E/I.(JH SOR 2022/BCD/Page
132/5.8.23)
Providing one coat of Snowcem of approved shade
and make over old surface including washing
cleaning and preparing the walls, scaffolding , curing
2 M2 37635.48 42.89 1614185.74
and taxes all complete as per building specification
and direction of E/I.(JH SOR 2022/BCD/Page
132/5.8.22)

Providing one coat of Aluminium paint over steel


surface including cleaning the surface throughly,
2
3 scaffolding and taxes all complete as per building M 3017.52 90.86 274171.87
specification and direction of E/I..(JH
SOR/2022/BCD/Page 132/5.8.46)
Providing one coat of Plastic emulsion paint of
approved shade and make over old surface including
washing,cleaning and preparing the walls scaffolding 2
4 M 1029.60 152.41 156921.34
,washing of floor and taxes all complete as per
building specification and direction of
E/I.(BCD/5.8.19/P 132/2022/JH SOR)
Direction and Place identification sign with size more
than 0.90sqm size board (Providing and erceting
direction and place identification retro reflectorised
sign as per IRC 67 made of high intensity grade
5 Each 15.00 14393.10 215896.50
sheeting vide clause 801.30,fixed over sheeting with
minimum thickness of 4.00mm with area exceeding
0.90 sqm fixed over black support frame .
(RCD/2022/PAGE 376/8.06)
Total in Rupees = 3965121.80
18% GST in Rupees = 713721.92
Sub Total in Rupees= 4678843.72
1.0 % Contigency = 46788.44
1.0 % Labor Cess = 46788.44
Grand Total in Rupees = 4772420.60
Say in Rs.= ₹ 47,72,421.00

J.E A.E Executive Engineer


Tenughat Dam Division
Tenughat

Unit 7- AOC of Whitewashing and Painting of Railing 1


Detailed estimate of Whitewashing of Parapet wall and painting of Railing as per DSRP
2021Report Page Page 52 1

Providing two coats of snowcem of approved shade and make over old surface including
Item 1 washing cleaning and preparing the walls, scaffolding , curing and taxes all complete as per
building specification and direction of E/I.(JH SOR 2022/BCD/Page 132/5.8.23)

Surface Surface
Total Surface
Area for Area for
Avg Height Avg Height area including
From Distance snowcem snowcem
Sl.No. To Chain of wall in M of wall in M U/S and D/S Remark
Chain in M over U/S over D/S
U/S D/S both sides
wall both wall both
(7 + 8 )
sides sides

1 2 3 4 5 6 7 8 9 10

1 213.00 196.00 510.00 1.067 0.450 1088.34 459.00 1547.34

2 184.00 114.00 2100.00 1.370 0.600 5754.00 2520.00 8274.00

3 114.00 100.00 420.00 1.00 0.360 840.00 302.40 1142.40

4 100.00 56.00 1320.00 0.950 0.400 2508.00 1056.00 3564.00

5 56.00 1.00 1650.00 0.900 0.400 2970.00 1320.00 4290.00


13160.34 5657.40 18817.74 M2

Providing one coat of snowcem of approved shade and make over old surface including washing
Item 2 cleaning and preparing the walls, scaffolding , curing and taxes all complete as per building
specification and direction of E/I.(JH SOR 2022/BCD/Page 132/5.8.22)

Sl.No. Description of Old Parapet wall Area Unit


2
1 First year of maintenance one coat area = 0.00 M No need
2
2 Second year of maintenance one coat area = 18817.74 M From item 1
2
3 Third year of maintenance one coat area = 18817.74 M From item 1
Total Area of Parapet wall for one coat of
37635.48 M2
Snowcem

Providing one coat of aluminium paint over steel surface including cleaning the surface
Item 3 throughly, scaffolding and taxes all complete as per building specification and direction of
E/I..(JH SOR/2022/BCD/Page 132/5.8.46)
Surface Surface
Total Surface
Area for Area for
Height of Height of area including
From Distance snowcem snowcem
Sl.No. To Chain Railing in M Railing in U/S and D/S Remark
Chain in M over U/S over D/S
U/S M D/S both sides
Railing both Railing both
(7 + 8 )
sides sides

1 2 3 4 5 6 7 8 9 10

1 196.00 185.00 330.00 1.524 1.524 1005.84 1005.84 2011.68

Dam Spilllway Railing consits steel post and Net so Take


1005.84 M2
50% area as voids =

Sl.No. Description Area


Unit 7- Detailes estimate for whitewashing Painting 1
2 No need in
1 First year of maintenance one coat area = 0.00 M
first year
2 Second year of maintenance one coat area = 1005.84 M2
3 Third year of maintenance one coat area = 1005.84 M2
Total Area (Base year + second + third year)= 3017.52 M2

Providing one coat of plastic emulsion paint of approved shade and make over old surface
Item 3 including washing,cleaning and preparing the walls scaffolding ,washing of floo and taxes all
complete as per building specification and direction of E/I.(BCD/5.8.19/P 132

Surface Surface
Total Surface
Area for Area for
Perimeter Perimeter area
snowcem snowcem
From Distance Railing of Railing including U/S
Sl.No. To Chain over U/S over D/S Remark
Chain in M Base in M Base in M and D/S both
Railing Railing
U/S D/S sides (7
Base both Base both
+8)
sides sides

1 2 3 4 5 6 7 8 9 10

1 196.00 185.00 330.00 0.380 0.400 250.80 264.00 514.80 M2


Sl.No. Description Area
1 First year of maintenance one coat area = 0.00 M2 No need
2
2 Second year of maintenance one coat area = 514.80 M
3 Third year of maintenance one coat area = 514.80 M2
Total Area (Base year +first + second + third
1029.60 M2 (A)
year)=

Direction and Place identification sign with size more than 0.90sqm size board (Providing and erceting
direction and place identification retro reflectorised sign as per IRC 67 made of high intensity grade
Item 4
sheeting vide clause 801.30,fixed over sheeting with minimum thickness of 4.00mm with area exceeding
0.90 sqm fixed over black support frame . (RCD/2022/PAGE 376/8.06)

Sl.No. Description /Location of Sign Board No.


1 Both sides of Tenughat Dam 2.00 nos.
2 Spillway and Dam Control Room 2.00 nos.
3 Near View Tower Both sides 2.00 nos.
Near Tenu Bokaro Link Canal intake Point and
4 2.00 nos.
Ground
Near Turning for spillway from gomia Peterbar
5 1.00 nos.
Road
At Miscallaneous places near Tenughat Dam and
6 6.00 nos.
Divisional office for directions =
15.00 Nos.

JE AE Executive Engineer
Tenughat Dam Division
Tenughat

Unit 7- Detailes estimate for whitewashing Painting 2


Annexure -II
झारखण्ड सरकार

Water Resources Department


जल संसाधन विभाग

Chief Engineer zone = Hazaribagh


Circle = Tenughat Dam Circle
Division = Tenughat Dam Division, Tenughat.
Annexure -III
झारखण्ड सरकार

Water Resources Department


जल संसाधन विभाग

Chief Engineer zone = Hazaribagh


Circle = Tenughat Dam Circle
Division = Tenughat Dam Division, Tenughat.
1

Water Resources Department


Government of Jharkhand

EOI forexecution of DSRP


Recommendations on Tenughat
Dam Spillway,Inspection Gallery
& Drainage gallery
2

Contents

Section – I

Notice Inviting Expression of Interest (EOI).

Section – II

1. Introduction.
2. Salient Features of Tenughat Dam.
3. Details of Assets associated with Tenughat Dam system.
4. Eligibility criteria.
5. Instruction to bidder.
6. Scope of work.

Section – III

ANNEXURE – I: - List of Key Personal to be deployed on Contract Work


ANNEXURE – II: - BID SECURITY (BANK GUARANTEE).
ANNEXURE – III: - PERFORMANCE BANK GUARANTEE.
ANNEXURE – IV: - Template for Financial Cover.
ANNEXURE – V: - Undertaking letter for Expression of Interest.
ANNEXURE – VI: - Details of representative from Bidder.
ANNEXURE – VII: - Technical credentials of the Bidder.
ANNEXURE – VIII: - Description of Approach and Methodology responding to the
EOI scope.
ANNEXURE – IX: - BOQ details with estimated cost.
ANNEXURE – X: - F2 Agreement Format.
ANNEXURE – XI: - SBD Agreement Format.
ANNEXURE – XII: -WRD Jharkhand Ranchi letter No. -1/P.M.C./fofo/k
/470/2011/907 Dated 04/10/2023
ANNEXURE – XIII: - List of Equipments to be deployed on Contract Work
3

Section-I
4

OFFICE OF EXECUTIVE ENGINEER


TENUGHAT DAM DIVISION, TENUGHAT

Expression Of Interest Notice

E-Tender Reference No. –WRD/TDD Tenughat/ E.O.I. / Dates: - /2023

1 Name of Work Execution of DSRP recommendations on Tenughat


Dam Spillway, Inspection Gallery & Drainage gallery

2 Cost of Tender Fee (Online Mode) Rs. 10,000.00

3 Earnest Money Rs.5,00,000=00 (Five Lakh)

4 Period of Work 2 Years

5 Date of Publication of Tender on website at 11:00 AM

6 Period for downloading bid document up to 05:00 PM


from website
7 Date and Time of submission of E.M.D (Through designated SBI Payment gateway integrated with
e-Procurement portal of Government of Jharkhand
(http://jharkhandtenders.gov.in ) (11.00 AM) to up to
05:00 PM

8 Date of Pre- bid meeting at 12:00 PM

9 Date & Time of Opening of Technical at 03:00 PM


bid
10 Name & Address of the Office inviting Executive Engineer, Tenughat Dam Division, Tenughat.
tender
11 Contact no. of e- Procurement Officer 06546-267462 / 8789848809

NOTE: - Only e-Tender will be accepted.

Further details can be seen on website http://jharkhandtenders.gov.in

Executive Engineer
Tenughat Dam Division, Tenughat
5

GOVERNMENT OF JHARKHAND
WATER RESOURCES DEPARTMENT

OFFICE OF THE EXECUTIVE ENGINEER


TENUGHAT DAM DIVISION, TENUGHAT
NOTICE, INVITING
EXPRESSION OF INTEREST (E.O.I.)

E.O.I. Reference no.:WRD/TDD Tenughat/ E.O.I. Dated - /2023

The Undersigned on behalf of the Governor of Jharkhand invites Expression of Interest (E.O.I)
for the work mentioned in table below through e-Procurement in two envelope system (one containing
technical bid & other financial bid) from eligible Firms/Agencies/Manufactures/registered in
appropriate class in Water Resources Department, Government of Jharkhand herein after called WRD
G.O.J. However, those who have not yet registered in appropriate class in WRD, G.O.J can also
participate but they must have to get registered in appropriate category of WRD within two months
from the date of award of work. The E.O.I shall be submitted online on the website
http://jharkhandtenders.gov.in. The Bidder(s) must have necessary arrangement for access to the portal
with their own Digital Signature.
Table 1
1 SI. Name of Work Bid Security Cost of Period of
No. (Earnest Tender completion
money) (Rs.) paper (Rs.)
1. 2 3 4 5
Execution of DSRP Rs.5,00,000=00
recommendations on Tenughat ( Five Lakhs
Dam Spillway, Inspection Rupees Only) Rs. 2 Years
Gallery & Drainage gallery 10,000=00

2. Period of online availability of E.O.Iand Submission of bid are as under

SI. e- Place of Availability of tender on-line for Date & time


No. Procureme Opening bidding of opening of
6

nt Officer Bid downloading Bid submission technical bid


period period

a b c d e f

1 Executive e- procurement
Engineer, cell
up to 5.00 PM at 11.00 AM
Tenughat
Chief Engineer to
Dam at 03.00 PM
up to 5.00 PM
Division, Office
Tenughat.
Water
Resource
Department
Hazaribag
7

Section-II
8

1.0 Introduction: -
1. Tenughat Dam is situated on Damodar River in Bokaro District at a distance of
55 Km from Bokaro Steel City, Jharkhand. Purpose of this dam is to supply water
to Bokaro Steel Plant and other industries.

2. Tenughat Dam has ten radial gates having size of 50‟ (W) x 39‟ (H). Radial gates
are operated to release of excess water from dam into river. There are no stop
logs to close radial gates of spillway for its repair and maintenance. In order to do
repair and maintenance work of radial gate of spillway, reservoir level must be at
crest level or below i.e. 843‟. Conservation level of Tenughat Dam is 852‟.

3. Tenughat Dam has eight Under Sluice Gates (USG) having size of 6‟ (W) x 8‟
(H). Main function of USG is to remove siltation as well as excess water from
dam into river. Dam has two more USG i.e. Emergency gate and Service gate to
supply water to Steel Authority of India Ltd, Bokaro through Tenu Bokaro Canal.
Bulk head /stop log gate is being used to do repair and maintenance work for
these USGs. Bulk head/Stop log gate is being operated by 70 MT Gantry Crane.
9

2.0 Salient Feature of Tenughat Dam


SALIENT FEATURES OF TENUGHAT DAM BOKARO, JHARKHAND
No. Particulars Remarks
1 2 3
1. Location Across River Damodar near Tenu Village in
Bokaro District about eight miles south west of
Bokaro Thermal Power Station
(i) River Damodar
(ii) District Bokaro
(iii) Co-ordinate
a) Latitude 23°43‟12.39” N
b) Longitude 85°50‟22.65” E
2. Hydrology
a) Total catchment area 1730 Sq. Miles
b) Average monsoon rainfall 52 inches
c) Maximum probable flood 6,47,000 Cusecs
d) Maximum observed flood 2,50,000 Cusecs
2,80,000 Cusecs (In 1976)
e) 75 percent dependable annual -----
rainfall
f) Total yield
3. Reservoir
a) Full reservoir level R.L. 882.00 Ft.
i. Gross storage of F.R.L 0.822 m.ac. Ft.
ii. Conservation Level R.L. 852.00 Ft.
b) Maximum water level R.L. 887.00 Ft.
c) Outlets sill level
i. On the left side of Spillway/outlet R.L. 774.00 Ft.
sill level
ii. On the right side of R.L. 776.00 Ft.
Spillway/outlet sill level
d) Gross storage R.L. 852.00 Ft.= 44526 Ha-m
e) Live storage 28321 Ha-m (Gross Storage-Dead storage)
f) Dead storage R.L. 817.00 Ft.= 16205 Ha-m
g) Annual Utilization from the dam
4. Dam
a) Type Earthen
b) Length of Dam including 21,300.00 Ft.
Spillway
c) Top of Dam R.L R.L. 896.00 Ft.
d) Top width 6.71 Meter
e) Maximum height of Dam above 166.00 Ft.
deepest bed level
5. Spillway
a) Type Concrete
b) Location From chain 191.70 to 203.00 of the dam
c) Length of Spillway 1130.00 Ft. (From chain 191.70 to 203.00)
d) Crest of R.L. R.L. 843.00 Ft.
10

e) Free Board ---


f) Maximum flood discharge ---
6. Gate
a) Type of gate Spillway- Radial
Under Sluice – Vertical
b) No. of gate 10.00 Nos.Radial& 8.00 Nos. Under sluices
c) Size of gate Under sluices of spillway (6‟0‟‟x 8‟0‟‟)
7. Head Regulator
a) Number..... ....& Size.........
b) Type of Outlet Spillway
c) Sill R.L. R.L. 774.00 Ft.
i) Left Outlet R.L. 774.00 Ft.
ii) Right Outlet R.L. 776.00 Ft.
d) Capacity ---
i) Discharge of Left Outlet 350.00 Cusec
ii) Discharge of Right Outlet 300.00 Cusec
8. Canal Length
i) Left Main Canal 2.89 Km (95.00 Chain) [ Tenu Bokaro Link Canal]
ii) Right Main Canal 34.50 Km. (1145.00) [ Tenu Bokaro Canal]
9. Irrigation from Reservoir
i) C.C.A. in Ha 2370.00 Acre
ii) C.CA. Net in Ha
iii) Annual Irrigation
a) Kharif in Ha
b) Rabi in Ha
c) Hot weather in Ha

3.0 * Details of Assets associated with Tenughat Dam system.

i. Types of Gates :- Radial :-


 No. of Gates:- 10.00
 Size:- 50‟0‟‟ x 39‟0‟‟
 No. of U/S Gates:-8.00
 Size :- 6‟0‟‟x 8‟0‟‟
ii. Hoisting arrangements & its components:-
 Type of Hoisting arrangements :- Motor operated Radial gates hoist
iii. Gantry cranes:-
 Capacity: -70 M.T.
iv. Stop log gates: - 3.00 Nos.
 ……………..
v. Pump Sets if any: -Vertical Turbine (75 H.P.)
 No. of pump sets :- 2.00
11

 Capacity : - 75 H.P.
vi. DG Sets: - Existing 01 and proposed 01
 No. of existing Set :- 01 (Additional (STAND BY) 125KVA DG set is proposed to
be installed as per specification and direction of E/I.
 Capacity :- 125 KVA
vii. H/R gates
 No. of H/R gates :- NA
 Size…………..
viii. Outlet well and concerned associated gates.
 On the Right Side of Spillway & Size 6‟0‟‟x 8‟0‟‟
 On the Left Side Of Dam (TBLC)
ix. Control Room / watch tower
 1 Nos. of watch tower on the right embankment of the Dam Top Road
 1 Nos. of Control Room
x. Spillway Channel
 Type :- Ogee Spillway
 No. of spillway gates: - 10Nos. of Radial gate & 8 Nos. Under sluice gates
 ………..

4.0 Eligibility Criteria


(A) TECHNICAL BID:-
1. Technical bid shall contain the following documents :- (In PDF Format)
i. The Firm/Company/Consultant/Agency/Manufacturer shall have Registration Certificate,
Power of Attorney, PAN card, GST registration.
ii. The scanned copy of their work experience in similar nature of works credentials in
Tenughat Dam project and shall have successfully completed, at least one similar nature &
size and assignment has completed in last five years. Certificate issued shall not be below
the rank of Executive Engineer.
iii. List of personnel and list of Equipment in formats as Annexures- I &XIII respectively.
iv. Work schedule for completing work.
v. The scanned copy of financial turnover, Profit & loss account statement of Company/firm
for last 5 (five) previous consecutive years duly audited by Chartered Accountant and work.
vi. Tender fee of Rs. 10,000.00/- Through designated SBI Payment gateway integrated with e-
Procurement portal of Government of Jharkhand (http://jharkhandtenders.gov.in )
12

confirming letter number of water Resources department Ranchi पत्रांक -

1/P.M.C/विविध/470/2011 907 dated 04/10/2023 (Annexure XII) .

vii. Bid security Through designated SBI Payment gateway integrated with e-
Procurement portal of Government of Jharkhand (http://jharkhandtenders.gov.in )

confirming letter number of water Resources department Ranchi पत्रांक -

1/P.M.C/विविध/470/2011 907 dated 04/10/2023 (Annexure XII.

viii. Performance Bank Guarantee shall be submitted in prescribed form annexed as Annexure-
III.
ix. Details of Representative from Bidder, Technical credentials of Bidder and Description of
Approach and Methodology, Responding to EOI scope shall be submitted in prescribed form
annexed as Annexure-VI, VII & VIII respectively.

(B) Financial Bid:-


Financial bid shall contain the followings :- (In PDF Format)
i. Rate must be quoted against each of the work in format at Annexure- IV (Template for
Financial Bid). Bid amount shall be exclusive of all applicable taxes.
ii. BOQ Details with estimated cost shall be quoted in prescribed form annexed as
Annexure-IX

(C) TERMS &CONDITIONS: -

1. The bidder has to make all necessary arrangements of all required tools & Plants on their own
cost for the completion of the work.
2. Rate quoted must be clearly mentioned in figures and words exclusive of all applicable taxes
etc. required for completing the work.
3. The department reserves the right to cancel/modify this “Expression of Interest” without
assigning any reason at any stage. No any correspondence with the bidder shall be entertained
on this issue.
4. Tender fee and Earnest Money must be deposited to e-Procurement Officer from 10.11.2023 to
29.11.2023 up to 5.00 PM only through designated SBI Payment gateway integrated with e-
Procurement portal of Government of Jharkhand http://jharkhandtenders.gov.in
13

5. The financial bid of only those Bidders shall be opened, who qualify in the Technical Bid.
Lowest bidder will be invited for rate negotiation before competent authority. After acceptance
of Financial Bid, agreement will be executed on In case of F2 agreement Successful bidder
will have to furnish performance security deposit @ 5% at the time of agreement and rest
@ 5% shall be deducted from running Account Bill (Annexure X). In case of SBD
agreement Successful bidder will have to furnish performance security deposit @ 2% at
the time of agreement and rest @ 8% shall be deducted from Running Account Bill
(Annexure XI).
6. (i) Payment schedule should be submitted by the successful bidder which will be finally
decided and approved with mutual consent of competent authority and the successful
bidder.
(ii) All terms and condition laid down in this EOI along with Annexure-X (F2 Agreement
format) /Annexure-XI (SBD Agreement format) shall be the part of the Agreement.

(iii) The price quoted by the bidder shall be valid for 180 days from the Last date of Bid
Submission. Further details, if required, may be obtained from Executive Engineer
Tenughat Dam Division, Tenughat during office hours.

(iv) Expression of Interest (EOI) shall be submitted online on the website


http://jharkhandtenders.gov.in If the date of opening of EOI is declared a holiday, the
EOI will be opened on next working day at same time.

(D) Technical Qualification Criteria: -

1. Tender fee of Rs. 10000.00/- in shape as described in Para- vi of Technical Bid, through
designated SBI Payment gateway integrated with e-Procurement portal of Government of
Jharkhand (http://jharkhandtenders.gov.in )
2. Bid security of requisite amount as mentioned in table 1 of notice for EOI.(Through
designated SBI Payment gateway integrated with e-Procurement portal of Government of
Jharkhand (http://jharkhandtenders.gov.in )
3. PAN card
4. GST registration
5. Valid registration certificate
6. Income Tax Return
7. GST return
14

8. Audited balance sheet for last five previous consecutive years duly audited by Charter
accountant
9. Work experience certificate and credential in projects issued by not-below the rank of
Executive Engineer
10. Undertaking of EOI in format as Annexure-V.
11. Bidders shall have experience of having executed at least one similar nature and size of work
successfully completed during previous five years immediately preceding the financial year in
which bids are invited.
12. The bidders must have minimum annual turnover of Rs. 200.00 lakh in at least any one
financial year during the last five years in all classes of civil engineering work. (Attach
certificate of Chartered Accountant).
13. Work Schedule/Programme to complete the work.
14. List of personnel in format as per Annexure-I
5.0 Instruction to Bidders (ITB):-
Detailed instructions & documents to be furnished for online bidding
1. Guidelines for online submission of bids can be downloaded from the website
http://jharkhandtenders.gov.in
2. Interested bidders can download the bid from the website http://jharkhandtenders.gov.in
3. The firm/company/consultancy is advised to visit the proposed work site first (at their own
cost) and get acquainted with the site condition, nature of job before submission of their Bid.
No claim will be entertained afterwards.
4. Bidders in order to participate in the bidding process have to get their own „Digital Signature
Certificate (DSC)‟ as per Information Technology Act-2000 to participate in online bidding.
This certificate will be required for digitally signing the bid. Bidders can get the above-
mentioned digital signature certificate from any approved vendors. Bidders, who already
possess valid Digital Certificates, need not procure new Digital Certificate.
5. Bidders or the authorized person by the bidder have to submit their bids online in electronic
format with digital Signature. Bids without digital signature will not be accepted. No proposal
will be accepted in physical form.
6. Bids will be opened online as per time schedule mentioned in the NIT.
7. Bidders should be ready with the scanned copies of cost of documents & EMD as specified in
the tender document. Before submission of online bids, bidders must ensure that scanned
copies of all necessary documents have been attached with bid.
15

8 Bidders must pay EMD only through designated SBI Payment gateway integrated with e-
Procurement portal of Government of Jharkhand (http://jharkhandtenders.gov.in) confirming

letter number of water Resources department Ranchi पत्रांक -1/P.M.C/विविध/470/2011 907

dated 04/10/2023 (Annexure XII.)


.
9 Uploaded documents of the successful bidder will be verified with the original before signing
the agreement. The successful bidder has to provide the originals to the concerned authority.
10 The department will not be responsible for any delay in online submission due to any reason
what so ever.
11 All required information for bid must be filled and submitted online. Each document shall be
digitally signed by the bidders.
12 The contractor will be solely responsible for the compliance of the provisions of contract labour
(Abolition & Regulations) Act and other statutory rules and regulations in force from time to
time during the subsistence of this agreement. It shall keep the Department absolved and
indemnified from the liability in this respect of any nature whatsoever.

13 In case of any kind of dispute, following actions shall be followed for redressal of the dispute.
(i) Amicable Solution: -
(a) Save where expressly stated to the contrary in this Agreement, any dispute, difference
or controversy of whatever nature between the parties, whatsoever arising under, out of
or in relation to this Agreement (the “Dispute”) shall in the first instance be attempted
to be resolved amicably in accordance with the Procedure set forth in Clause 13 (i) (b)
of ITB.
(b) Either Party may require such Dispute to be referred to the Water Resources
Department and the contractor for the time being, for amicable settlement. Upon such
reference, both parties shall meet at the earliest mutual convenience and in any event
within 15 days of such reference to discuss and attempt to amicably resolve the Dispute.
If the Dispute is not amicably settled within 15 days of such meeting between the two,
either Party may refer the Dispute to arbitration in accordance with the provisions of
Clause 13 (ii)
(ii) Arbitration: -
(a) Procedure: -Subject to the provisions of Clause (13) (i) of ITB, any Dispute which is not
resolved amicably shall be settled by arbitration under the Arbitration and Conciliation
Act, 1996
16

(b) Place of arbitration: -The place of arbitration shall ordinarily be in Ranchi by mutual
agreement of the parties, the arbitration hearings, if required, may be held elsewhere.
(c) Enforcement of award: -The decision or award resulting from arbitration shall be final
and binding upon the both parties and shall be enforceable in accordance with the
provision of the Arbitration Act subject to the rights of the aggrieved parties to secure
relief from any higher forum.
(iii) Governing Law &Jurisdiction: -
This Agreement shall be governed by the laws of India. The Courts at Ranchi Shall
have jurisdiction over all matters arising out of or relating to this Agreement.
14 The contractor shall be responsible to comply with the following: -
i) Not to permit or carry on any unlawful activities or create indiscipline in the Tenughat
Dam premises.
ii) Not to employ any child labour.
iii) To be solely responsible for employment, dismissal, termination and re-employment of its
staff and personnel and shall keep the owner informed with all development in this regard.
iv) To pay all dues to its employees and keep the concerned department officials absolved and
identified from any liability in this respect.
v) To be responsible for behavior of its staff and personnel, their turnout and ensure good
conduct discipline, co-operation, etc. by them towards officers / staff of the Department
and its representatives.
vi) To ensure compliance of Sexual Harassment of Women at Workplace (Prevention,
Prohibition and Redressed Act, 2013) amongst its own staff/against owner‟s staff.
vii) Take appropriate corrective and disciplinary action against its employees against whom the
Department‟s notifies.
viii) On expiry of this agreement the contractor shall be liable and responsible to make all
statutory payment to its staff and personnel and make all other statutory obligation and
liability and obtain suitable discharge from Department so that no liability or obligation
dissolves on the Department.
ix) The agency will be responsible for compliance of all laws, acts and rules made there under,
statutory orders issued from time to time in relation to the environment and man-power
deployed by them for performance of the job under reference and the Department will have
a right to be indemnified in respect of any consequences resulting from any breach or
violation by the contractor of such rules, statutory obligations etc.

List of acts and omissions in accordance with Contractor's labour regulations :-


17

15 The contractor shall be responsible for the costs and risk for litigation, if any, which the
Department may have to face due to the acts of commission or commission of the agency of
any nature whatsoever subject to state government.
16 The contractor shall not be entitled to any compensation for any loss suffered by him on
account of delays in commencing or execution the work, whatever the cause of delays may be.
17 The successful bidder is bound to carry out any items of work necessary for the completion of
the job. Whatever additional work entrusted by the Department should also be undertaken by
the contractor.
18 The successful bidder must co-operate with the other contractors appointed by the Department
if any so that the work shall proceed smoothly with the least possible delay and to the
satisfaction of the Employer.

 Other details can be obtained from Executive Engineer concerned during working hours.

6.0 Scope of work


Execution of DSRP recommendations on Tenughat Dam Spillway, Inspection Gallery & Drainage
gallery

S. No Item of Work/Description Unit Qty.

1 Spillway
(i) Tenughat dam Spillway has a central spillway provided
with 10 no of radial gates of size 15.24 mx 11.89 m. There is no
emergency gate arrangement. The spillway is constructed with core
of RR stone masonry with concrete cover. In the non-overflow
section in the D/S wall over entrance to gallery, 2 nos. Of holes
are observed at about RL 250 m. These holes have history of
oozing out water like jet in the year 2017 & 2019. There is
probability that there is thorough passage from upstream to
downstream across the body of spillway. One hole and crack in the
upstream face have been notice over the body of wall. In the
bottom of deck slab, at places concrete has been found eroded and
reinforcement got visible. Cracks have been noticed in the
retaining wall in the D/S of spillway. Honey comb have also been
noticed at some places and some vegetation has grown over those
cracked portions. Cavities haves been observed in the Upstream
18

face of piers in spillway.


a) The U/S face in the non-overflow portion is to be checked
minutely and cracks/holes, if any observed, mapping is to be done
for such cracks by remote operated vehicle (ROV) to assess the
extents of damages. Cement/polymer grouting is to be taken up in
the U/S face. Submission of report on investigation and, mapping
of cracks holes and extent of damages a suggestion on any other
advanced remedial measures other than Cement/ polymers.

b) However, if the mapping indicates presence of more cracks


/ cavities, required remedial measures with advance technology is
recommended to prevent such seepages. The application of
CCGM/CCGC (Cementitious Geo-synthetic Concrete
Mattress/Carpet) as per Standards of EN 13253 & 13254 as used in
Reservoir & Dams be adopted in the u/s face of the spillway.

c) The cavities occurred in the piers are to be thoroughly


investigated and mapped and are to be filled up with CC M-30/
most advanced technology to make the surface smooth.

d) Investigation and preparation of the report on damaged


concrete surface of glacis on the downstream of the spillway gates
and their repair and restoration with suitable type of concrete.

e) The damage below the bottom of the deck slab be made


good with rich mortar.

f) The vegetation noticed over the retaining wall be uprooted


and removed and the cracks are made good using rich cement
mortar.

g) Preparation and submission of report on concrete cracking


in spillway (potential causes are alkali – aggregate reaction,
thermal stresses because of heat of hydration or temperature
variations, foundation problems) and suggestion and execution of
suitable remedial measures.

h) Preparation and submission of report on the damages on


spillway glacis, spillway piers, training/divide walls, energy
dissipaters, downstream areas (probable causes are cavitation,
abrasion, unsymmetrical flow unfavorable downstream
conditions).and there repair.

i) Removal of Vegetation growth in spillway, spill channel,


approach channel etc.

j) Repair to upstream face of masonry concrete spillway in


case the pointing is damaged, leading to increased seepage.

k) Preparation and submission of the report on deterioration of


19

concrete, types, causes and repair of deteriorated concrete with


suitable type of concrete in the spillway. .

l) Cleaning and removal of for proper operation of debris of


spillways, sluiceways, inlet and outlet structures, stilling basin/
energy dissipation arrangements, trash racks, debris control devices
etc. .

m) Cleaning algae and dirt from the staff gauges to allow easy
reading.
2 Gallery: - Inspection as well as drainage gallery
a) Necessary remedial measures with advanced technology
/treatments recommended to prevent such seepages. The
application of Geo-synthetic Cementitious Concrete Mattress/Geo-
synthetic Cementitious Concrete Carpet (GCCM/GCCC) as per
Standards of EN 13253 & 13254 used in the Dams and Reservoir
asappropriate be adapted in the u/s face of the dam. This
Technology can also be adopted for other such locations in the
reservoir to prevent seepage ensuring its stabilization.

b) Necessary chemical and physical analysis of the deposited


/injected mud be tested in the soil testing laboratory for reference
on remedial measure. Submission of lab test report of chemical and
physical analysis and suitable remedial measures taken.

c) The calcinations occurred over the steps and floors need to


be removed. The U/S and D/S wall surface need to be cleaned
properly such that the walls will be free from calcinations.

d) The vertical and foundation drainage holes be reamed and


cleaned.

e) Investigation, mapping and remedial measures for


prevention of Seepage in Galleries.

f) Chemical and physical analysis of reservoir water. All


water tests should be done confirming IS Code IS 3025-11 (1983):
Methods of sampling and Test of water and waste water) and IS
10500:2012). Submission of test reports and the analysis of effect
of the water on the spillway body.

3 DAM INVESTIGATIONS

a) Investigation, preparation and submission of report on Non-


destructive Geo-physical Scanning/investigation for the
health status of the dam by suitable advanced methods and
its mapping and execution of remedial measures.
ANNEXURE IV
झारखण्ड सरकार

Water Resources Department


जल ससं ाधन विभाग

Chief Engineer zone = Hazaribagh


Circle = Tenughat Dam Circle
Division = Tenughat Dam Division, Tenughat.
Abstract of cost of The work of Installation of Fencing Panel and Barbed wire fencing at
downstream slope of Tenughat Dam for preventing encroachment in dam Area Under Tenughat
Dam Division Tenughat
Rate in Amount in
Sl.No. Item Unit Quantity
Rupees Rupees

Earthwork in excavation in foundation trenches in


ordinary soil vide classification of soil item A and
disposal of excavated earth as obtained to a distance
upto 50M including all lifts levelling ramming the 3
1 M 1251.31 151.82 189973.79
foundation trenches removing roots of trees shrubs
all complete as per approved designed building
specification and direction of E/I.(5.1.1/WRD/Page
99)

Providing and laying in position cement concrete of


specified grade excluding the cost of centering and
2 M3 1251.31 3751.64 4694462.30
shuttering All work upto Plinth Level.1:4:8 M 7.5
Lean concrete (5.3.1.6/BCD 2022/Page 106)

Supply at site -R.C.C. Standards post/ struts/rails/


pales of mix 1:1.5:3 (1 cement : 1.5 coarsesand : 3
graded stone aggregate 12.5 mm nominal size) with
wooden plugs or 6mm bar nibs wherever required as
3 M3 161.36 28603.00 4615353.98
per direction of Engineer-incharge (cost of earth
works in excavation, concrete works in foundation to
be paid separately).(DSR 2021 Volume 2/
16.15.1/page 301)

Centering and shuttering including strutting


propping etc. and removal of formwork for 2
4 M 6673.05 194.50 1297908.23
foundation footing bases of columns (5.3.17.1/BCD
2022/Page 108)

Supply of Barbed wire of 4 Point ,2 Ply 12


5 SWG,150mm Apart (common Part A /Page56/M- Kg 16236.40 70.81 1149699.34
215)(10% CP and 4.95% OHC)

Labor for fitting and fixing barbed wire fencing in six


rows horizontal upto a height of 1.85M and two
diagonals including fixing of post in cement concrete
at 3.0 M contres including staples (but excluding the
6 Meter 7597.00 73.31 556936.07
cost of cement concrete angle iron post its cutting
and making holes,nuts and bolts )all complete as per
building specifications and direction of E/I.(5.5.22
BCD 2022/Page 121)

Abstract of cost of barbed wire fencing Page 1


Supplying,fitting and fixing stainging bolt with nut
size 25cm x 10 mm dia to tighten the barbed wire
7 Each 4064.00 8.41 34178.24
corner post complete as per building specification
and direction of E/I.(5.5.25 BCD 2022/Page 121)
Painting two coats on new concrete surfaces
(Painting two coats after filling the surface with
2
8 synthetic enamel paint in all shades on new M 5253.49 70.30 369320.40
palstered concrete surfaces.(8.08/RCD 2022/Page
377)
Printing New letter and figures of any shades with
per cm
synthetic enamel paint black or any other approved
9 height 156250.0 1.10 171875.00
colour to given an even shade) RCD2022/8.03/PAGE
per letter
374
Boundary Pillar (RCC M15 grade boundary pillars of
standard design as per IRC :25,fixed in position
10 Each 300.0 545.80 163740.00
including finishing and lettering but exclude
painting)RCD 2022/page 378/8.16
Steel post ISMB 100(M-423/page 87/Part A 2022 JH
11 Tonne 1.82 71786.27 130830.48
SOR / (4.95% OHC and 10% CP)
Mild steel 1.50 mm Thick sheet(4.95% OHC and 10%
12 M2 90.00 678.20 61038.00
CP) M382/page 85/RCD 2022
Welding by electric plant(4.95% OHC and 10% CP) M-
13 cm 22500.00 2.30 51750.00
1160/page 66/common part A)
14 Carriage of Cement MT 413.87 539.80 223407.34

15 Carriage of Sand M3 563.09 212.65 119740.92

16 Carriage of Chips M3 1126.18 547.45 616526.39

17 Carriage of steel MT 18.06 539.80 9748.19


(A) Total in Rupees 14456488.67
18% of (A)= (B) 18% GST in Rupees 2602167.96

C= (A) +(B) Sub total in Rupees 17058656.63


1% Of C 1% Labor cess 170586.57
1% Of C 1% Contigency 170586.57
Grand total in Rupees= 17399829.76
Say in Rupees=1,73,99,830=00

J.E A.E Executive Engineer


Tenughat Dam Division
Tenughat

Abstract of cost of barbed wire fencing Page 2


Detailed estimate of The work of Installation of Fencing Panel and Barbed wire fencing at
downstream slope of Tenughat Dam for preventing encroachment in dam Area Under Tenughat
Dam Division Tenughat
Total length in meter= 7597.00
Sl.No. Description Length in M
Dam downstream behind
1 1077.00
godowns
2 Tenughat OP to spillway 1077.00
3 Spillway to chain 109.00 2707.00
4 Chain 109.00 to 0 point= 2736.00
Total length for consideration = 7597.00

Spacing in meter between two Line posts as per IS 4996:1985= 3.00


Spacing in meter between two Strainer posts as per IS 4996:1985= 30.00
Total Number of posts in total length = 2532.33 2533.00
Total Number of Strainer posts in length = 253.23 254.00 At every 10th space
There are two additional diagonal post with Each strainer Post = 508.00
Total strainer posts (254.00+254.0 x 2 nos. )= 762.00 Nos.
Total Number of Line posts in total length( 2533.00-
2279.100 2280.00 Nos.
254.00) =
As per IS 4996:1984 Page 16 Table 2 serial number(vi) Goose Neck posts
Base dimension of post in mm (150mm x 150mm )= 150.00 150.00
Top dimension of post in mm (75 mm x 75 mm )= 75.00 75.00
Height of One Post in meter (0.672m + 2.50m +0.60m)= 3.772
Area of Base in Square mm = 22500.00
Area of Top in Square mm = 5625.00
Average of Top and Bottom Area= 14062.50
Average of Top and Bottom Area in square
meter= 0.0141
Voulume of One Post in Cubic
meter(3.772 meter x 0.0141 meter
0.0530
square) =
Total Volume of Line posts in cubic meter(2280.00 nos. x 0.0530)= 120.94
Total Volume of Strainer posts in cubic meter(762.00 nos. x 0.0530)= 40.42
Total Volume of R.C.C M20 in cubic meter = 161.36
Total Number of Pits for line posts and brace posts = 3042.00 Nos.
Total line posts PITS with 750MM X 750MMX depth 750mm = 2280.00 Nos. A
Total Brace posts pits with 750MM X 750MMX depth 675mm = 762.00 Nos. B
Number of warning sign boards = 45.00

Detailed estimate of Barbed wire fencing Page 1


Earthwork in excavation in foundation trenches in ordinary soil vide classification of soil item A and
disposal of excavated earth as obtained to a distance upto 50M including all lifts levelling ramming
1
the foundation trenches removing roots of trees shrubs all complete as per approved designed
building specification and direction of E/I.(5.1.1/WRD/Page 99).
Total Numbers of Pits= 3042.00
Width Depth Length
Exacavation for Line posts =
0.750 0.750 0.750
Exacavation for brace posts = 0.750 0.675 0.750
Volume of one line pit Excavating soil in Cubic meter= 0.422
Volume of one Brace pit Excavating soil in Cubic meter= 0.380
Total volume for line post pits = 961.875 (A)
Total volume for Corner/Brace post pits = 289.322 (B)
Excavation for sign boards (100mm x 100mm x 250mm depth)= 0.100 0.250 0.100
Number of sign boards 45.000
Total excavation for 45.00 sign boards 0.113 C
Total Volume for Excavation of of soil in Cubic meter(A + B +C)= 1251.31 M3

Providing and laying in position cement concrete of specified grade excluding the cost of centering
2
and shuttering All work upto Plinth Level.1:2:4 M15 (5.3.1.2/BCD 2022/Page 106)

Width Depth Length


PCC M-15 for Line posts =
0.750 0.750 0.750
PCC M15 for brace posts = 0.750 0.675 0.750
Volume of one line pit PCC M-10 in Cubic meter= 0.422
Volume of one Brace pit PCC M10 in Cubic meter= 0.380
Total volume for line post pits = 961.88 (A)
Total volume for Corner/Brace post pits = 289.32 (B)
Excavation for sign boards (100mm x 100mm x 250mm depth)= 0.100 0.250 0.100
Number of sign boards 45.000
Total excavation for 45.00 sign boards 0.113 C
Total Volume for Excavation of of soil in Cubic meter(A + B +C)= 1251.31 M3

R.C.C. Standards post/ struts/rails/ pales of mix 1:1.5:3 (1 cement : 1.5 coarsesand : 3 graded stone
aggregate 12.5 mm nominal size) with wooden plugs or 6mm bar nibs wherever required as per
3
direction of Engineer-incharge (cost of earth works in excavation, concrete works in foundation to be
paid separately).(DSR 2021 Volume 2 16.15.1/page 301)
Total Numbers of Posts height = 3042.00 (3.772 meter long)
R.C.C M20(1 CEMENT :1.5 COURSE SAND ZONE III : 3 GRADED Average Area Height
AGGREGATES 20MM NOMINAL SIZE)= 0.0141 3.772
Volume of M20 in one post in Cubic meter= 0.0530
Total volume of M20 in 3042.00 nos. of posts in cubic meter= 161.36 M3

Detailed estimate of Barbed wire fencing Page 2


Centering and shuttering including strutting propping etc. and removal of formwork for foundation
4
footing bases of columns (5.3.17.1/BCD 2022/Page 108)
Total Numbers of Pits = 3042.00
Width Depth Length
Area dimesnion for LINE POST shuttering=
0.750 0.750 0.000
Area for corner post shuttering = 0.750 0.675 0.000
Nos. of line posts = 2280.00 (A)
Nos. of Corner posts = 762.00 (B)
Width x Depth x 4 sides = Sides Width Depth
Line posts = 4.00 0.750 0.750
Brace posts = 4.00 0.750 0.675
Total area for shuttreing for 2280.00 line posts = 5130.00
Total area for shuttreing for 762.00 corner posts = 1543.05
Total Area for shuttering for 3190.00 nos. of foundation posts = 6673.05 M2

6 Barbed wire of 4 Point ,2 Ply 12 SWG,150mm Apart Calculation


Total Number of Horizontal wires = 16.00
Total Horizontal length in meters = 121552.00
Diagonal length of Barbed Wire between two Line posts in meter = 3.20
Number of Diagonal length Barbed wires between two posts = 2.00
Total Length of Barbed wires between two line posts = 6.400
Total Number of spaces between posts (3042.0-1.0)= 3041.00
Total Number of diagonal barbed wire length in meter = 19462.40
Grand Total of Barbed wire length in meter = 141014.40
01% Additional wire cosidering sagging, corner post and wastage= 1410.144
Total Barbed wire length in meter including additional length = 142424.54
Per unit weight of Specified Barbed wire as per IS 278:2009(gm/meter)= 114.00
Total weight of Barbed wire in gram to be used for Fencing = 16236398.02
Total weight of Barbed wire in Kilogram to be used for Fencing = 16236.40

Labor for fitting and fixing barbed wire fencing in six rows horizontal upto a height of 1.85M and two
diagonals including fixing of post in cement concrete at 3.0 M contres including staples (but excluding
7
the cost of cement concrete angle iron post its cutting and making holes,nuts and bolts )all complete
as per building specifications and direction of E/I.(5.5.22 BCD 2022/Page 121)
As per calculation = 7597.00
Accessories
Nuts and bolts for corner posts after every 10 Line posts .6 nos. for every strainer post
Numbers of nuts ,bolts and screw for each strainer post= 16.00
Numbers of strainer posts= 254.00
8 Total Number of Nuts and bolts = 4064.00

Painting two coats on new concrete surfaces (Painting two coats after filling the surface with
9
synthetic enamel paint in all shades on new palstered concrete surfaces.(8.08/RCD 2022/Page 377)
Base dimension of post in mm (150mm x 150mm )= 150.00 150.00

Detailed estimate of Barbed wire fencing Page 3


Top dimension of post in mm (75 mm x 75 mm )= 75.00 75.00
Height of One Post in meter = 3.77
Average of 75mm and 150mm = 0.1125
Area of one side in Square mm(3770 x
0.42
112.50) =
No. of sides in one post= 4.00
Total number of posts = 3042.00
Area of 45.00 numbers of boards = 90.00
Total Area in sqm of all Posts for Painting = 5253.49

Printing New letter and figures of any shades with synthetic enamel paint black or any other
10
approved colour to given an even shade) RCD2022/8.03/PAGE 374

यह संपत्ति जल संसाधन त्तिभाग झारखण्ड सरकार की है।इस पर अतिक्रमण करना गैर


कानन
ू ी है ।आदे शानस
ु ार काययपालक अभभयंिा िेनघ
ु ाट बााँध प्रमंडल िेनघ
ु ाट

For writing above lines at different places.Number of letters = 125.00


Height of each word in cm = 25.00
Number of places = 50.00
Per cm height per letter in single quantity (125 x 25 x 50)= 156250.00

Boundary Pillar (RCC M15 grade boundary pillars of standard design as per IRC :25,fixed in position
11
including finishing and lettering but exclude painting)RCD 2022/page 378/8.16
S.No
.
Item Nos.

1 Boundary pillars for 213.00 chains 213.00

2 Additional pillars for different places 87.00


Total Boundary pillars 300.00

12 Steel post ISMB 100(M-423/page 87/Part A 2022 JH SOR / (4.95% OHC and 10% CP)
Pipe in Total
ISMB 100 2.50 Meter long x 2.00 nos. (ISMB 100 = Beam No. of
One Length in
height 100.00mm/flange =55mm/web thickness =4.0mm) Boards
board meter
Vertical ( unit weight =(8.1 kg/m) 45.00 5.00 225.00

Total weight in Kg = 1822.50 Kg

Total eight in MT= 1.8225 MT

13 Mild steel 1.50 mm Thick sheet(4.95% OHC and 10% CP) M382/page 85/RCD 2

Warning board Width Height Area Nos. Total Area

Detailed estimate of Barbed wire fencing Page 4


2.00 1.00 2.00 45.00 90.00
14 Welding by electric plant(4.95% OHC and 10% CP) M-1160/page 66/common part A)
Length of Total
Warning board Width Height welding in one Nos. length in
board in cm cm
2.00 1.00 500.00 45.00 22500.00

J.E A.E Executive Engineer


Tenughat Dam Division
Tenughat

Material Statement
Cement in
Sand in chips in Steel in
Sl. Item Quantity cubic
cubic meter cubic meter MT
meter

1 P.C.C M15(1:2:4) 1251.31 281.545 563.089 1126.178 0.000

2 R.C.C M20(1:1.5:3) 0.000 0 0.000 0.000 0.000

3 Barbed wire in kg 16236.40 0.000 0.000 0.000 16.24

4 ISMB 100 1.82 0.000 0.000 0.000 1.82

5 Local Sand 0.00 0.000 0.000 0.000 0.00

Total 281.54 563.09 1126.18 18.06


Cement in MT= 413.87
Number of Cement Bags = 12172.664 6867.00

Detailed estimate of Barbed wire fencing Page 5


J.E A.E Executive Engineer
Tenughat Dam Division
Tenughat

Detailed estimate of Barbed wire fencing Page 6


J.E A.E Executive Engineer
Tenughat Dam Division
Tenughat

Detailed estimate of Barbed wire fencing Page 7


J.E A.E Executive Engineer
Tenughat Dam Division
Tenughat

Detailed estimate of Barbed wire fencing Page 8


Cost of carriage of different materials as per Jharkahnd SOR 2022
Common Part A
Item Description Cement
Rate per
A Cement Unit
unit
Quantity Amount in Rs.

Loading and unloading by


1 manual means (common part A MT 409.60 4.41 1806.34
/2022/page 212/1.03)
Cost of Haulage charge at Rate per quantity x km
2 surface road (common part A Unit Distance Amount in Rs.
unit (tonne x km)
/2022/page 213/1.04)

Gomia (Lead = 14.00 km) t.km 9.30 14.00 61.74 574.18

Total Amount of (loading + unloading + 14.00km


2380.52
Hauling on surface road) =
539.800

Sl.
No.
Item Description Steel
Rate per
A Steel Unit Quantity Amount in Rs.
unit
Loading and unloading by
1 manual means (common part A MT 409.60 0.417 170.80
/2022/page 212/1.03)
Cost of Haulage charge at
Rate per quantity x km
2 surface road (common part A Unit Distance Amount in Rs.
unit (tonne x km)
/2022/page 213/1.04)
Gomia (Lead = 14.00 km) t.km 9.30 14.00 5.84 54.29
Total Amount of (loading + unloading + 14.00km
225.10
Hauling on surface road) =
539.800

Conversion of chips and sand from cubic meter to Metric tonne

S.No. Item M3 Tonne Remark


10mm aggr. =1680kg/cum,
1 Chips (1 M3 = 1.50 tonne) 1126.18 1689.27 20mm agg. = 1550kg/cum ,
40mm agg =1450kg/cum

2 Sand 0.00 0.00 Average 1500 kg/cubic meter

Cost of carriage Page 1


Sl. No. Item Description Chips ( 1 cum = 1.50 tonne)
A Chips Unit Rate per unit Quantity Amount in Rs.

Loading and unloading stone


1 boulder/sand/chips (common M3 115.00 7.26 834.90
part A /2022/page 211/1.01 A)
Cost of Haulage charge at surface
Rate per quantity x km
2 road (common part A /2022/page Unit Distance Amount in Rs.
213/1.04) unit (tonne x km)

Narki (Lead = 31.00 km) t.km 9.30 31.00 337.59 3139.59


Total Amount of (loading + unloading + 31.00km Hauling on
surface road) =
3974.49
Per cubic meter rate including loading + unloading + hauling charge per cubic meter per kilometer = 547.450
Sl. No. Item Description Sand ( 1 cum = 1.50 tonne)
Rate per
A Sand Unit
unit
Quantity Amount in Rs.

Loading and unloading stone


1 boulder/sand/chips (common M3 115.00 6.49 746.35
part A /2022/page 211/1.01 A)
Cost of Haulage charge at
Rate per quantity x km
2 surface road (common part A Unit Distance Amount in Rs.
unit (tonne x km)
/2022/page 213/1.04)
Champi Lead (7.00 km) t.km 9.30 7.00 68.15 633.75
Total Amount of (loading + unloading + 7.00km Hauling on
surface road) = 1380.10
Per cubic meter rate including loading + unloading + hauling charge per cubic meter per kilometer
= 212.650

Sl. No. Item Description Boulder ( 1 cum = 1.50 tonne)


Rate per
A Boulder Unit
unit
Quantity Amount in Rs.
Loading and unloading of boulders by
1 manual means (common part A M3 279.30 1.00 279.30
/2022/page 212/1.02 )

quantity x km
2 Cost of Haulage charge at surface road Unit Rate per unit Distance
(tonne x km)
Amount in Rs.
(common part A /2022/page 213/1.04)
Narki (Lead = 31.00 km) t.km 9.30 31.00 46.50 432.45
Total Amount of (loading + unloading + 31.00km Hauling on
surface road) = 711.75

Per cubic meter rate including loading + unloading + hauling charge per cubic meter per kilometer = 711.750

J.E A.E Executive Engineer


Tenughat Dam Division
Tenughat

Cost of carriage Page 2


ANNEXURE V
झारखण्ड सरकार

Water Resources Department


जल ससं ाधन विभाग

Chief Engineer zone = Hazaribagh


Circle = Tenughat Dam Circle
Division = Tenughat Dam Division, Tenughat.
ANNEXURE VI
झारखण्ड सरकार

Water Resources Department


जल ससं ाधन विभाग

Chief Engineer zone = Hazaribagh


Circle = Tenughat Dam Circle
Division = Tenughat Dam Division, Tenughat.
CCTV Camera installation on Tenughat Dam and nearby Control room under
Tenughat Dam Division Tenughat.

Rate
Sl.No. Item Unit Qty including Amount
Taxes
HANUTECH Indoor-Outdoor Biggest 36x
Zoom Dome Pantilt PTZ Camera 3MP Auto
1 No. 6.00 ₹ 24,500.00 ₹ 1,47,000.00
Motion Tracking Surveillance Camera,2
Way Communication,IP66 Waterproof

Analog CCTV Camera HD 1080P 4-in-1


(TVI/AHD/CVI/CVBS) Security Dome
Camera, 2.8mm-12mm Manual
2 No. 20.00 ₹ 10,835.00 ₹ 2,16,700.00
Focus/Zoom Varifocal Lens, Weatherproof
Metal Housing 36 IR-LEDs Day & Night
Monitoring (White)
Seagate Expansion 10TB Desktop External
HDD - USB 3.0 for Windows and Mac with
3 No. 2.00 ₹ 25,999.00 ₹ 51,998.00
3 yr Data Recovery Services, Portable Hard
Drive (STKP10000400)
HIKVISION 8 Channel eDVR [ Built-in SSD
Storage ] Compatible with Upto 2MP CCTV
4 No. 3.00 ₹ 4,945.00 ₹ 14,835.00
Cameras DS-E08HGHI-B with USEWELL
HDMI, White

Roll over image to zoom in


Dell S2721HNM 27" (68.96 cm) FHD
Monitor 1920 X 1080 Pixels @75Hz, IPS
5 No. 3.00 ₹ 12,899.00 ₹ 38,697.00
Panel, 5-Year Warranty, 99% sRGB, Low
Blue Light Technology, 3-Sided bezelless,
HDMI x2, Tilt Adjustment, AMD FreeSync

CP PLUS 3+1 Coaxial Pure Copper CCTV


6 METER 1500.00 ₹ 13.33 ₹ 19,995.00
Camera Cable (90 Meter) White
Grand Total including all taxes= ₹ 4,89,225.00

JE AE Executive Engineer
Tenughat Dam Division
Tenughat
4/29/24, 4:34 PM Buy Analog CCTV Camera HD 1080P 4-in-1 (TVI/AHD/CVI/CVBS) Security Dome Camera, 2.8mm-12mm Manual Focus/Zoo…

Skip to main content


.in
Delivering to Patna 800001
Electronics Search Amazon.in
Hello, sign in Returns 0
Update location EN Account & Lists & Orders

All Amazon miniTV Sell Best Sellers Mobiles Today's Deals Prime Customer Service Electronics New Releases Home & Kitchen Fashion

Mobiles & Accessories Laptops & Accessories TV & Home Entertainment Audio Cameras Computer Peripherals Smart Technology Musical Inst

3MP High resolution | PTZ | 2024 new launch 2,771 -25% ₹4,480 00 ₹5,999.00
Sponsored
‹ Back to results

Analog CCTV Camera


HD 1080P 4-in-1

10,83500
FREE delivery 14 - 17 May.
(TVI/AHD/CVI/CVBS) Order within 12 hrs 26 mins.
Details
Security Dome
Delivering to Patna 800001 -
Camera, 2.8mm- Update location

12mm Manual
Ships from Cart2Globe
Focus/Zoom Sold by Cart2Globe

Varifocal Lens, Quantity: 1


Weatherproof Metal
Add to Cart
Housing 36 IR-LEDs
Day & Night Buy Now

Monitoring (White) Secure transaction


Brand: CUMCITIN
4.4 237 ratings Add to Wish List
| Search this page


10,835 Other sellers on Amazon
Inclusive of all taxes
EMI starts at ₹525. No Cost EMI New (2) from ₹10,83500 &
available EMI options FREE Delivery

Save Extra with 3 offers

No Cost EMI: Avail No Cost EMI


on select cards for orders above

Click to open expanded view Bank Offer (31): 10% Instant


Discount up to INR 750 on

See 1 more
VigilMate 3MP Dual Lens Wireless
WiFi Smart Indoor CCTV Camera |…
-67% ₹1,999 00 ₹5,999.00
Free 10 days Secure
Sponsored
Delivery Replacement
transaction

Recommended Night Vision


Uses For
Product
Brand CUMCITIN
Model Name Analog CCTV
Camera
Connectivity Wireless
Technology
See more
Special Feature night vision

Report an issue with this


product

https://www.amazon.in/Security-2-8mm-12mm-Varifocal-Weatherproof-Monitoring/dp/B07HN4ZKNC/ref=sr_1_fkmr1_2?crid=985HF5KNOY2N&di… 1/6
4/29/24, 4:34 PM Buy Analog CCTV Camera HD 1080P 4-in-1 (TVI/AHD/CVI/CVBS) Security Dome Camera, 2.8mm-12mm Manual Focus/Zoo…

PRAMA 2 MP Eco Lite Dome Camera PT-


HTD700E-IP || White || 1Pc

5 | ₹806.00

Shop now ›

Sponsored

Frequently bought together

Total price: ₹13,793.00

+ Add both to Cart

This item: Analog CCTV Camera [Real 18AWG 43x2pcs Wires] 10


HD 1080P 4-in-1 Pairs DC Power Pigtail Cable, 12V
(TVI/AHD/CVI/CVBS) Security… 5A Male & Female Connectors f…
₹ 10,83500 ₹ 2,95800

Product details
Is Discontinued By Manufacturer ‫‏‬: ‎No
Product Dimensions ‫‏‬: ‎11.8 x 11.8 x 9 cm; 998 g
Date First Available ‫‏‬: ‎2 December 2018
Manufacturer ‫‏‬: ‎no
ASIN ‫‏‬: ‎B07HN4ZKNC
Item model number ‫‏‬: ‎AM3128W
Manufacturer ‫‏‬: ‎no
Item Weight ‫‏‬: ‎998 g
Item Dimensions LxWxH ‫‏‬: ‎11.8 x 11.8 x 9 Centimeters
Net Quantity ‫‏‬: ‎1.0 count
Customer Reviews: 4.4 237 ratings

Related products with free delivery on eligible orders


Sponsored

CP PLUS 1MP Full HD IR CP PLUS 2MP Smart Wi- Trueview 4G Sim 4Mp CP PLUS 2 MP + IP Bullet Generic Rocktech1080P COUNTRYC
Bullet Camera | 1/4.5'' fi CCTV Camera | 360° & Solar Powered CCTV Camera + Night Vision Trail Cctv Camera For Sim Based
1MP PS CMOS Image Full HD Home Security | Security Camera with Outdoor IR Camera 30 Home Outdoor With CCTV Secu
Sensor| Max 30fps@... Full Color Nig... Solar Panel | Surveilla... Mtr. with 3.6mm... 0.8S Trigger Time, 90... Way Audio
46 7,519 218 194 5

83600 4K+ bought in past month 200+ bought in past month ₹
2,04000 ₹
3,49900 ₹
3,4990
#1 Best Seller Limited time deal
Limited time deal ₹ 8,19900 Save 5% with coupon

₹ 949 00 List: ₹21,300.00 (62% off)

List: ₹2,300.00 (59% off)

Brand in this category on Amazon

Smart Full HD CCTV Camera


Shop CP Plus

https://www.amazon.in/Security-2-8mm-12mm-Varifocal-Weatherproof-Monitoring/dp/B07HN4ZKNC/ref=sr_1_fkmr1_2?crid=985HF5KNOY2N&di… 2/6
4/29/24, 4:34 PM Buy Analog CCTV Camera HD 1080P 4-in-1 (TVI/AHD/CVI/CVBS) Security Dome Camera, 2.8mm-12mm Manual Focus/Zoo…


1,499 Limited time Deal Limited time Deal

₹ 1,889 ₹ 1,399
₹4,900 (61% off) ₹3,700 (62% off)

Sponsored

Product description

Tips:

1. This camera has 4 modes for video output: 1080p AHD, 1080p CVI, 1080p TVI and CVBS 960H analog (D1.700TVL, 800TVL)

2. Default MODE is TVI 1080P mode, please change to corresponding VIDEO MODE by DIP switch cable

3. The camera OSD Menu is controlled via DVR (through UTC function)

4. This surveillance camera needs a 12V/1A power adapter & BNC cable (Not Included) to connect with DVR system.

Technical Parameters :

- 1/2.7" color CMOS sensor - Resolution: 1920x1080

- 100' IR Range

- TV System: NTSC

- Video Output: HD-TVI(1080P),(AHD/TVI/CVI/CVBS)

- Day & Night: Support (ICR)

- Frame Rate: 25fps (50HZ), 30fps (60Hz)

- Min illumination: 0.1lux(LED ON) 0.01lux(0-3 lux LED)

- S/N Ratio: >52dB (AGC off)

- Electronic Shutter: Auto 1/50s (1/60s)-1/100.000s

- White Balance: Auto

- Gain Control: Auto

- Weatherproof for indoor/outdoor

- Power Supply: DC12V 1A

Package included :

1 x Dome camera

1 x Bag of mounting screws

1 x installation template

1 x Manual

Looking for specific info?

https://www.amazon.in/Security-2-8mm-12mm-Varifocal-Weatherproof-Monitoring/dp/B07HN4ZKNC/ref=sr_1_fkmr1_2?crid=985HF5KNOY2N&di… 3/6
4/29/24, 6:51 PM Buy HIKVISION 8 Channel eDVR [ Built-in SSD Storage ] Compatible with Upto 2MP CCTV Cameras DS-E08HGHI-B with U…

Skip to main content


.in
Delivering to Patna 800001
Electronics dvr 8 channel
Hello, sign in Returns 0
Update location EN Account & Lists & Orders

All Amazon miniTV Sell Best Sellers Mobiles Today's Deals Prime Customer Service Electronics New Releases Home & Kitchen Fashion

Mobiles & Accessories Laptops & Accessories TV & Home Entertainment Audio Cameras Computer Peripherals Smart Technology Musical Inst

PHILIPS 5000 Series Wi-Fi Camera with AI and Offline Recording | 360° CCTV ₹6,999 00
Camera for Home | 2K(3MP) Resolution | Privacy Shutter | Pan Tilt Zoom | 2-W…
22% off Ends in 05:03 ₹8,995.00

Sponsored
‹ Back to results

HIKVISION 8 Channel eDVR [


Built-in SSD Storage ]

4,94500
FREE delivery Sunday, 5 May.
Compatible with Upto 2MP Order within 18 hrs 23 mins.
Details
CCTV Cameras DS-E08HGHI-B
Delivering to Patna 800001 -
with USEWELL HDMI, White Update location
Brand: HIKVISION
4.8 6 ratings In stock
Amazon's Choice Ships from Amazon
Sold by Om Technocraft

Ends in 04:23:53
Quantity: 1

-55% 4,945 ₹
Add to Cart
M.R.P.: ₹10,900

Inclusive of all taxes Buy Now


EMI starts at ₹240. No Cost EMI available EMI
options Secure transaction
Add gift options
Offers
Add to Wish List
Roll over image to zoom in No Cost EMI Bank Offer
Upto ₹222.65 EMI Upto ₹2,000.00
interest savings on discount on select Other sellers on Amazon
Amazon Pay ICICI Credit Cards, select
1 offer 31 offers
New (2) from ₹4,94500
Fulfilled FREE Delivery.

Free Delivery Pay on Delivery 10 days Top Bra


Replacement

Connectivity HDMI
Technology
Compatible Camera
Devices
Brand HIKVISION SKY HUB Wireless Home and Office
Ultra HD 720P IP CCTV Security…
Number of 8
Channels -62% ₹1,149 00 ₹2,999.00

Media SD Card Sponsored


Format
Digital
Video

About this item


Hikvision 8 Channel eDVR Powered by eSSD
technology, BUILT-IN STORAGE
Compatible with upto 2 MP cameras || Inputs Up
to 1080p Lite@15 fps encoding capability
Scene-adaptive bitrate control video
compression
Low power consumption
HDTVI/AHD/CVI/CVBS/IP video

Report an issue with this product

https://www.amazon.in/HIKVISION-Channel-Storage-Compatible-DS-E08HGHI-B/dp/B0BY5FCDP5/ref=sr_1_5?crid=1W16XRDUWAIBY&dib=ey… 1/5
4/29/24, 6:51 PM Buy HIKVISION 8 Channel eDVR [ Built-in SSD Storage ] Compatible with Upto 2MP CCTV Cameras DS-E08HGHI-B with U…

Philips GoSure 3001 Car… Shop now >


33% off Limited time deal
₹5,999.00 ₹8,999.00

Sponsored

Buy it with

Total price: ₹7,133.00

+ + Add all 3 to Cart

These items are dispatched from and sold


by different sellers.
This item: HIKVISION 8 Channel CP PLUS 3+1 Coaxial Pure Copper Hikvision DS-2CE5AD0T-ITP/ECO Show details

eDVR [ Built-in SSD Storage ] CCTV Camera Cable (90 Meter) 2MP (1080P) Indoor Night Vision
Compatible with Upto 2MP CCT… White Dome Camera 1Pcs
₹ 4,94500 ₹ 1,19900 ₹ 98900

Related products with free delivery on eligible orders


Sponsored

JK Vision 4MP IP Camera CP PLUS 2MP Smart Wi- HIKVISION 8 Channel HIKVISION 8 Channel IMPACT BY HONEYWELL FEDUS 23A
Set, Bullet (8pcs), DHI- fi CCTV Camera | 360° & DVR with 5MP 8 Bullet DVR with 2MP 5 Bullet 2 MP CCTV KIT with 8 Copper 3+
NVR1108HS-S3/H 8 Full HD Home Security | Cameras with Audio Cameras (Day/Night Channel DVR I 2 Dome Camera Co
Channel NVR Dahua ... Full Color Nig... Recording (Day/Night V... Vision) + 1TB HDD + Ca... Cameras + 4 Bullet Ca... For High-S
7 7,519 370 363 30

27,41692 4K+ bought in past month ₹
21,99900 ₹
11,99900 Limited time deal Limited tim
#1 Best Seller
₹ 15,29900 ₹ 69200
Limited time deal
List: ₹45,470.00 (66% off) List: ₹999.00
₹ 94900
List: ₹2,300.00 (59% off)

What is in the box?


Main Unit DVR, Adaptor, Mouse, USEWELL HDMI

Brand in this category on Amazon

Smart Wi-Fi CCTV Cameras


Save up to 61% on CP Plus

Limited time Deal Limited time Deal Limited time Deal


1,299 ₹
1,889 ₹
1,889
₹2,600 (50% off) ₹4,900 (61% off) ₹4,100 (54% off)

Sponsored

https://www.amazon.in/HIKVISION-Channel-Storage-Compatible-DS-E08HGHI-B/dp/B0BY5FCDP5/ref=sr_1_5?crid=1W16XRDUWAIBY&dib=ey… 2/5
4/29/24, 6:51 PM Buy HIKVISION 8 Channel eDVR [ Built-in SSD Storage ] Compatible with Upto 2MP CCTV Cameras DS-E08HGHI-B with U…

Product information

Technical Details Additional Information

Manufacturer ‎Prama Hikvision India Pvt Ltd Manufacturer Prama Hikvision India Pvt Ltd

Country of Origin ‎India Item Weight 1 kg 200 g

Item model number ‎DS-E08HGHI-B Item Dimensions LxWxH 15 x 11 x 4 Centimeters

Product Dimensions ‎15 x 11 x 4 cm; 1.2 kg Net Quantity 1.00 count

ASIN ‎B0BY5FCDP5 Included Components Main Unit DVR, Adaptor, Mouse,


USEWELL HDMI

Best Sellers Rank #77,393 in Electronics (See Top


100 in Electronics)
#165 in Bullet Cameras

Feedback

Would you like to tell us about a lower price?

HIKVISION
Highly rated by customers for
79% positive ratings from 10K+ customers

10K+ recent orders from this brand value for money looks good good picture quality

9+ years on Amazon

Looking for specific info?

Product description

HIKVISION eDVR with Built-in STORAGE

Motion Detection 2.0


Human/Vehicle Analysis
Deep learning-based motion detection 2.0 is enabled by default for all analog channels, it can classify humans and vehicles, and extremely reduce false alarms caused by
objects like leaves and lights;

Quick search by object or event type is supported;

Video Compression: H.265 Pro/H.265


Encoding Resolution: 1080p Lite/720p/720p Lite/WD1/4CIF/CIF/QVGA

Comes with USEWELL HDMI

Sponsored

Qubo Philips Automotive PHILIPS


Shop the Store on Amazon › Shop the Store on Amazon › Shop the Store on Amazon ›

https://www.amazon.in/HIKVISION-Channel-Storage-Compatible-DS-E08HGHI-B/dp/B0BY5FCDP5/ref=sr_1_5?crid=1W16XRDUWAIBY&dib=ey… 3/5
4/29/24, 6:51 PM Buy HIKVISION 8 Channel eDVR [ Built-in SSD Storage ] Compatible with Upto 2MP CCTV Cameras DS-E08HGHI-B with U…

Qubo Smart 360 3MP 1296p WiFi CCTV Philips GoSure 3001 Car Dash Camera | PHILIPS
Security Camera for Home from Hero… 2MP FHD 1080p | ADAS | G-Sensor | 132… and Offl
691 30
₹1,890.00 M.R.P: ₹3,990.00 ₹5,999.00 M.R.P: ₹8,999.00 ₹6,999

Products related to this item


Sponsored

HIKVISION 8 Chennal HIKVISION 4 Channel HIKVISION 2MP IP DAHUA Cooper Series 16 HIKVISION OSS Ezviz 2 HIKVISION
DVR DS-7608NI-Q1 eDVR 1080p Lite 1U Camera Outdoor 2 Channel Penta-Brid MP C3WN Outdoor DVR with 2
Compatible with JK H.265 [SSD Included] Bullet, 1 Dome, 4 1080P Compact 1U Smart 1080p Full HD, Cameras (D
Vision BNC DVR with 14 Days… Channel NVR, 4 Port… Digital Video Recorder (... Wi-Fi Wireless Camera… Vision) + 1

7,72024 ₹
5,04500 4 5 37
₹ 17,99694 ₹ 6,95000 ₹ 3,63563 ₹ 11,999

Sponsored

Compare with similar items


This Item Recommendations

HIKVISION 8 Channel eDVR [ HIKVISION Upgraded Wired HIKVISION 16 Channel 8MP 4K CP Plus SRPL-CP-UVR-0801E1-
Built-in SSD Storage ] HQHI-K1 Series 1920 x 1080 NVR [DS-7616NXI-K1] for IP V4 /CP-UVR-0801E1-CS 8CH
Compatible with Upto 2MP… Resolution 8 Channel Turbo H… Network CCTV Cameras Black Cosmic HD DVR (Without Hard…

Add to Cart Add to Cart Add to Cart Add to Cart

Price -55% ₹4,94500 -47% ₹6,33700 -38% ₹9,49000 -52% ₹3,68000


M.R.P: ₹10,900.00 M.R.P: ₹11,900.00 M.R.P: ₹15,300.00 M.R.P: ₹7,600.00

Delivery Get it by Sunday, May 5 Get it by Saturday, May 4 Get it by Thursday, May 2 Get it by Friday, May 3

Customer Ratings 4.8 6 4.1 27 5.0 7 4.2 9

Sold By Om Technocraft Techno-Krat Appario Retail Private Ltd megahoard

https://www.amazon.in/HIKVISION-Channel-Storage-Compatible-DS-E08HGHI-B/dp/B0BY5FCDP5/ref=sr_1_5?crid=1W16XRDUWAIBY&dib=ey… 4/5
4/29/24, 6:55 PM CP PLUS 3+1 Coaxial Pure Copper CCTV Camera Cable (90 Meter) White : Amazon.in: Electronics

Skip to main content


.in
Delivering to Patna 800001
Electronics cctv camera cable 100 meter
Hello, sign in Returns 0
Update location EN Account & Lists & Orders

All Amazon miniTV Sell Best Sellers Mobiles Today's Deals Prime Customer Service Electronics New Releases Home & Kitchen Fashion

Mobiles & Accessories Laptops & Accessories TV & Home Entertainment Audio Cameras Computer Peripherals Smart Technology Musical Inst

CP PLUS 3+1 Coaxial Pure Copper CCTV Camera Cable for Video, Power and Audio Communication (70
Meter) White - CP-ECC-70RS
-54% ₹1,149 00 ₹2,500.00
Sponsored
‹ Back to results

CP PLUS 3+1 Coaxial Pure Copper


CCTV Camera Cable (90 Meter) White

1,19900
FREE delivery Thursday, 2 May.
Visit the CP PLUS Store
Details
3.9 665 ratings | Search this page
#1 Best Seller in Coaxial Cables Or fastest delivery Wednesday,
1 May. Order within 23 mins.
2 VIDEOS 200+ bought in past month
Details

Ends in 04:59:20 Delivering to Patna 800001 -


Update location

-46% ₹1,199
In stock
M.R.P.: ₹2,200
Ships from Amazon
Inclusive of all taxes
Sold by Appario Retail Private
EMI starts at ₹109 per month. EMI options
Ltd

Quantity: 1
Offers

Bank Offer Partner Offers Add to Cart

Upto ₹850.00 Get GST invoice and


Buy Now
discount on select… save up to 28% on…

Secure transaction
22 offers 1 offer
Add gift options
Roll over image to zoom in
Add to Wish List

Free Delivery Pay on Delivery 10 days Service Warranty Top Bran


Centre Policy
Replacement Other sellers on Amazon

Size: 90 Meter New (7) from ₹1,19900


Fulfilled FREE Delivery.
90 Meter 90 Meter (Pack of 2)
₹1,199.00 ₹2,398.00
(₹1,199.00 / count)

Brand CP PLUS
Connector Type Coaxial
Cable Type Coaxial
Compatible Security Camera
Devices
Special Feature Long Lasting, Durable, Insulated CP PLUS 3+1 Coaxial Pure Copper
CCTV Camera Cable for Video, Pow…
52
About this item
-61% ₹2,499 00 ₹6,400.00
CP PLUS Cable is 90 meter in length ideal for Surveillance Use,
Easy application & Budget Friendly. Sponsored

CP PLUS Cable is made up of Solid bare Copper , . Diameter:


0.81mm, Overall Diameter: 9.50mm Approx, Shield: Bonded
Aluminium Tap, 2nd Shield: Aluminium Alloy Braid
Insulation: PVC, Type A, Jacket(Overall): PVC Type 1.8mm
Ideal Co-axial cable for home and Office security cameras
CP PLUS Cable is Tough and tensile, Excellent coating, Well
insulated, Long lasting

Report an issue with this product

https://www.amazon.in/CP-PLUS-Coaxial-Copper-Camera/dp/B08GFWK3DZ/ref=sr_1_2_sspa?crid=3GUCEP8W82PU9&dib=eyJ2IjoiMSJ9.Jno… 1/7
4/29/24, 6:55 PM CP PLUS 3+1 Coaxial Pure Copper CCTV Camera Cable (90 Meter) White : Amazon.in: Electronics

Product information

Technical Details Additional Information

Brand ‎CP PLUS ASIN B08GFWK3DZ

Connector Type ‎Coaxial Customer Reviews 3.9 665 ratings


3.9 out of 5 stars
Cable Type ‎Coaxial
Best Sellers Rank #4,104 in Electronics (See Top 100
Compatible Devices ‎Security Camera in Electronics)
#1 in Coaxial Cables (Electronics)
Special Feature ‎Long Lasting, Durable, Insulated
Date First Available 2 November 2018
Compatible Phone Models ‎all models phone
Manufacturer CP PLUS, ADITYA Infotech Ltd,
Recommended Uses For Product ‎CCTV CABLING.
A12 sector 4 noida
Colour ‎White
Packer 8800952952
Connector Gender ‎Male-to-Female
Importer 8800952952
Data Transfer Rate ‎6 Gigabits Per Second
Item Dimensions LxWxH 10 x 25 x 25 Centimeters
Shape ‎Round
Net Quantity 1.00 count
Net Quantity ‎1.00 count
Generic Name Accessories
Item Weight ‎3000 Grams

Model Name ‎CP PLUS CABLE Feedback

Number of Items ‎1 Would you like to tell us about a lower price?

Manufacturer ‎CP PLUS

Country of Origin ‎India

Model number ‎CP-ECC-180R

Item Weight ‎3 kg

Product Dimensions ‎10 x 25 x 25 cm; 3 kg

Item model number ‎CP-ECC-180R

Item Height ‎25 Centimeters

Item Width ‎25 Centimeters

Included Components ‎cable

Are batteries included? ‎No

What is in the box?


cable

Product Description

CP PLUS 3+1 Coaxial Pure Copper CCTV Camera Cable (90 Meter) White
CP PLUS Cable is a 90 meter in length cabling that is ideal for surveillance use and easy to apply. It's budget friendly and made up of solid bare copper, which gives
it high durability. The cable has a diameter of 0.81mm, with an overall diameter of 9.50mm approx. The cable has bonded aluminum taps on both ends, and 2nd
shield: Aluminium alloy braid. The insulation is PVC Type A, which means it's flexible and can withstand high temperatures without melting or breaking down.

If you're looking for a CCTV cable that will work with your surveillance system, then CP PLUS Cable is the way to go. This cable is made up of solid bare copper and
comes in a 90-meter length. It's ideal for surveillance use, has an easy application process, and is budget friendly. It has a diameter of 0.81mm, an overall diameter
of 9.5mm, and a shielded outer jacket.

https://www.amazon.in/CP-PLUS-Coaxial-Copper-Camera/dp/B08GFWK3DZ/ref=sr_1_2_sspa?crid=3GUCEP8W82PU9&dib=eyJ2IjoiMSJ9.Jno… 3/7
4/29/24, 6:50 PM Dell S2721HNM 27" (68.96 cm) FHD Monitor 1920 X 1080 Pixels @75Hz, IPS Panel, 5-Year Warranty, 99% sRGB, Low Blue…

Skip to main content


.in
Delivering to Patna 800001
Electronics LED MONITOR FOR CCTV 55 INCH
Hello, sign in Returns 0
Update location EN Account & Lists & Orders

All Amazon miniTV Sell Best Sellers Mobiles Today's Deals Prime Customer Service Electronics New Releases Home & Kitchen Fashion

Mobiles & Accessories Laptops & Accessories TV & Home Entertainment Audio Cameras Computer Peripherals Smart Technology Musical Inst

MSI G244F E2 24 Inch FHD Gaming Monitor - 1920 x 1080 Rapid IPS Panel, 180 Hz / 1ms, 118%
sRGB Colour Gamut/Adaptive-Sync - DP 1.2a, HDMI2.0b
-48% ₹11,475 00 ₹22,200.00
Sponsored
‹ Back to results

Dell S2721HNM 27"


(68.96 cm) FHD

12,89900
Fulfilled
Monitor 1920 X 1080 FREE scheduled delivery as soon
as Wednesday, 1 May,
3 VIDEOS
Pixels @75Hz, IPS 7 AM - 10 PM. Order within 55
Panel, 5-Year mins. Details

Warranty, 99% sRGB, Delivering to Patna 800001 -


Update location
Low Blue Light
In stock
Technology, 3-Sided
Ships from Amazon
bezelless, HDMI x2, Sold by Appario Retail Private

Tilt Adjustment, AMD Ltd

FreeSync Add a Protection Plan:


1 Year Extended Warranty
Visit the Dell Store
for ₹1,077.00
4.3 1,210 ratings
1 Year Extended Warranty
| Search this page
Plan for ₹1,099.00
Amazon's Choice
2 Years Extended Warranty
200+ bought in past month
Plan for ₹1,999.00

Quantity: 1
-62% ₹12,899
M.R.P.: ₹33,989 Add to Cart

Fulfilled
Buy Now
Inclusive of all taxes
EMI starts at ₹625. No Cost EMI Secure transaction
available EMI options
Add gift options

Offers Add to Wish List


Roll over image to zoom in
No Cost EMI Bank Offe
Upto ₹580.84 EMI Upto ₹1,2
Other sellers on Amazon
interest savings on discount o
Amazon Pay ICICI… Credit Card
1 offer 22 offers New (2) from ₹12,89900
Fulfilled FREE Scheduled
Delivery

7 days Service Free Delivery 1 Yea


Centre Warran
Replacement

Style Name: 27" S Series

27" S Series 27" P Series


₹12,899.00 ₹15,299.00
Samsung 24-Inch(59.8cm) FHD,…
27" SE Series 510
₹10,590.00
₹ 7,69900
Add to cart
Brand Dell
Sponsored
Screen Size 27 Inches
Resolution FHD 1080p
ऊसर्गAspect 16:9
Ratioप्रत्नू
Screen Flat
Surface
Description

https://www.amazon.in/Dell-S2721HNM-Monitor-Minimalistic-Design-Brightness/dp/B09XR7CGY1/ref=sr_1_2_sspa?crid=1JR7B8B0AIQS6&dib=… 1/9
4/29/24, 6:47 PM Seagate Expansion 10TB Desktop External HDD - USB 3.0 for Windows and Mac with 3 yr Data Recovery Services, Portable…

Skip to main content


.in
Delivering to Patna 800001
Electronics 10 tb storage ssd
Hello, sign in Returns 0
Update location EN Account & Lists & Orders

All Amazon miniTV Sell Best Sellers Mobiles Today's Deals Prime Customer Service Electronics New Releases Home & Kitchen Fashion

Mobiles & Accessories Laptops & Accessories TV & Home Entertainment Audio Cameras Computer Peripherals Smart Technology Musical Inst

EVM Elite 1TB EnSave Pro - Smallest Portable SSD - USB 3.2 Gen 2x2
USB-C with 2000Mb/s Speed - Ultra-Compact External Solid State Driv…
790 -63% ₹7,499 00 ₹19,999.00
Sponsored
‹ Back to results

Seagate Expansion
10TB Desktop

25,99900 (₹8,666.33 /
Unit)
External HDD - USB FREE delivery Wednesday, 1
May. Order within 10 mins.
VIDEO
3.0 for Windows and Details
Mac with 3 yr Data Delivering to Patna 800001 -

Recovery Services, Update location

Portable Hard Drive In stock


(STKP10000400) Ships from Amazon
Sold by Appario Retail Private
Visit the Seagate Store
Ltd
4.4 61,347 ratings
Packaging Ships in product
| Search this page
packaging

-26% 25,999 ₹
Add a Protection Plan:
(₹8,666.33 / Unit) 1 Year Extended Warranty
M.R.P.: ₹34,999 for ₹2,057.00
1 Year Extended Warranty
Inclusive of all taxes
Plan for ₹2,999.00
EMI starts at ₹1,260. No Cost EMI
2 Years Extended Warranty
available EMI options
Plan for ₹4,999.00

Offers Quantity: 1

No Cost EMI Bank Offe Add to Cart

Upto ₹1,170.68 EMI Upto ₹2,0


interest savings on discount o Buy Now
Amazon Pay ICICI… Credit Card
Secure transaction
1 offer 22 offers
Add gift options

Roll over image to zoom in Add to Wish List

7 days Service Free Delivery 3 Yea


Centre Warran
Replacement

Color: Black
Seagate: Data
Capacity: 10 TB
Safe, Fast Rescue
1 TB 2 TB 4 TB 5 TB
Seagate One Touch 2TB External
6 TB 8 TB 10 TB HDD with Password Protection, US…
18,766
12 TB 16 TB 18 TB -20% ₹7,199 00 ₹8,999.00

Sponsored
Style Name: Expansion External
HDD

Expansion External HDD

Portable External HDD

Digital 10 TB
Storage
Capacity
Hard Disk USB 2.0/3.0