United Energy Pakistan Limited Page 1 of 7

Operation Summary Report


Common Well Name: Haider Deep-2 AFE No
Event Type: RE-ENTER- ONSHORE (RON) Start Date: 12/5/2016 End Date: 12/19/2016 3-9934 (1,842,180.00 USD)

Project: Mirpurkhas (MK) Site: Haider Deep


Rig Name/No.: HL - 21 Spud Date/Time: 9/26/2016 6:00:00AM Rig Release:
Rig Contractor: HILONG UWI: Haider Deep-2
Active datum: RKB @110.0ft (above Mean Sea Level)
Date From - To Hrs Task Code NPT NPT Depth Phase Description of Operations
(hr) (ft)
12/5/2016 21:00 - 00:00 3.00 STKOH P PROD2 Recorded survey. Downlinked PowerDrive.
Pattern Bit
(MDSIZ613, S#JM3706).

Drilled 6" production hole from 12,568 ft to 12,588


ft.

Drilling Parameters:
WOB: 12-14 KLBS, GPM: 169, RPM: 99, MW: 12
PPG
DRILLING HRS: 1.9 HRS, ROP: 10.5 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 3 HRS,
ROP: 6.6 FT/HR

FORMATION: TALHAR SHALE (100%


CLAYSTONE)
FORMATION TOP: 12,540 ft MD

Last Survey:
12,528 ft, Inc: 2.97 deg, Azm: 252.4 deg,
12,393.41 ft TVD

KOP: 12,500 ft
12/6/2016 00:00 - 00:00 24.00 STKOH P PROD2 Drilled ahead 6" hole with directional BHA from
12,588 ft to 12,718 ft.

Drilling Parameters:
WOB: 12-14 KLBS, GPM: 174, RPM: 110, MW:
13 PPG
DRILLING HRS: 19.5 HRS, ROP: 6.7 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 24 HRS,
ROP: 5.4 FT/HR

FORMATION: TALHAR SHALE (90%


CLAYSTONE, 10% SILTSTONE)
FORMATION TOP: 12,540 ft MD

Last Survey:
12,635 ft, Inc: 6.71 deg, Azm: 264.18 deg,
12,500.1 ft TVD

Printed 3/27/2017 9:05:28AM


United Energy Pakistan Limited Page 2 of 7

Operation Summary Report


Common Well Name: Haider Deep-2 AFE No
Event Type: RE-ENTER- ONSHORE (RON) Start Date: 12/5/2016 End Date: 12/19/2016 3-9934 (1,842,180.00 USD)

Project: Mirpurkhas (MK) Site: Haider Deep


Rig Name/No.: HL - 21 Spud Date/Time: 9/26/2016 6:00:00AM Rig Release:
Rig Contractor: HILONG UWI: Haider Deep-2
Active datum: RKB @110.0ft (above Mean Sea Level)
Date From - To Hrs Task Code NPT NPT Depth Phase Description of Operations
(hr) (ft)
12/7/2016 00:00 - 00:00 24.00 STKOH P PROD2 Drilled 6" production hole directinally from 12,718
ft to 12,910 ft.

Drilling Parameters:
WOB: 12-16 KLBS, GPM: 172, RPM: 110, MW:
13 PPG
DRILLING HRS: 22.2 HRS, ROP: 8.2 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 24 HRS,
ROP: 7.6 FT/HR, TORQUE: 5-10 FT.KLBS

FORMATION: TALHAR SHALE (90%


CLAYSTONE, 10% SILTSTONE)
FORMATION TOP: 12,540 ft MD

Lithology at 12,880 ft:


Clay 60%, Sand 30%, Silt 10%

Last Survey:
12,848 ft, Inc: 9.6 deg, Azm: 267.73 deg,
12,710.4 ft TVD

Max formation gas 65 units at 12,840 ft.


12/8/2016 00:00 - 05:00 5.00 STKOH P PROD2 Drilled 6" production hole directionally from
12,901 ft to 12,983 ft.

Drilling Parameters:
WOB: 10-14 KLBS, GPM: 167, RPM: 101, MW:
13 PPG
DRILLING HRS: 4.5 HRS, ROP: 18.2 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 5 HRS,
ROP: 16.4 FT/HR, TORQUE: 6-10 FT.KLBS

FORMATION: LBS RESERVOIR SAND U-I


FORMATION TOP: 12,906 ft MD

Max Formation Gases at 12,978 ft: 43 U


05:00 - 07:00 2.00 STKOH P PROD2 Pumped and swept hole with 25 bbl Hi-Vis pill.
Circulated hole clean.
07:00 - 08:00 1.00 STKOH P PROD2 Flow checked - static. POOH for Wiper trip to
shoe (pumped out from 12,890 ft to 12,792 ft.)
08:00 - 08:30 0.50 STKOH P PROD2 Circulated to cool down directional tools.
08:30 - 09:30 1.00 STKOH P PROD2 RIH to bottom at 12,983 ft. Washed down last
stand.

Printed 3/27/2017 9:05:28AM


United Energy Pakistan Limited Page 3 of 7

Operation Summary Report


Common Well Name: Haider Deep-2 AFE No
Event Type: RE-ENTER- ONSHORE (RON) Start Date: 12/5/2016 End Date: 12/19/2016 3-9934 (1,842,180.00 USD)

Project: Mirpurkhas (MK) Site: Haider Deep


Rig Name/No.: HL - 21 Spud Date/Time: 9/26/2016 6:00:00AM Rig Release:
Rig Contractor: HILONG UWI: Haider Deep-2
Active datum: RKB @110.0ft (above Mean Sea Level)
Date From - To Hrs Task Code NPT NPT Depth Phase Description of Operations
(hr) (ft)
09:30 - 00:00 14.50 STKOH P PROD2 Drilled 6" production hole directionally from
12,983 ft to 13,145 ft.

Drilling Parameters:
WOB: 12-16 KLBS, GPM: 172, RPM: 98, MW: 13
PPG
DRILLING HRS: 13.2 HRS, ROP: 12.3 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 14.5 HRS,
ROP: 11.2 FT/HR, TORQUE: 6-10 FT.KLBS

FORMATION: LBS SHALE U-I, SAND U-II,


SHALE U-II, SAND U-III, SHALE-I
FORMATION TOP: 12,949 ft MD, 12,992 ft MD,
13,034 ft MD, 13,080 ft MD, 13,137 ft MD

Lithology at 13,120 ft:


Clay 10%, Sand 90%

Last Survey:
13,030 ft, Inc: 9.3 deg, Azm: 267.96 deg,
12,889.89 ft TVD

Max formation gas 43 Units at 12978 ft.

NOTE:
Observed breakouts 2% from 13090 ft to 13150 ft.
Traces from 13150 ft onwards.
12/9/2016 00:00 - 22:30 22.50 STKOH P PROD2 Drilled 6" hole with directional BHA from 13,173 ft
to 13,268 ft.
22:30 - 00:00 1.50 STKOH P PROD2 Pumped 20 bbl Hi-Vis and circulating hole clean.

12/10/2016 00:00 - 00:30 0.50 STKOH P PROD2 Circulated hole clean.


00:30 - 02:30 2.00 STKOH P PROD2 POOH for wiper trip from 13,268 ft to 12,350 ft.
Observed tight spot at 13,035 ft and cleared
same. Circulated in shoe to cool MWD tools.
02:30 - 04:00 1.50 STKOH P PROD2 RIH to bottom at 13,268 ft. Observed tight spot at
13,018 ft (washed and reamed from 13,018 ft to
13,072 ft).
04:00 - 21:30 17.50 STKOH P PROD2 Drilled 6" hole with directional BHA from 13,268 ft
to 13,334 ft. Observed low ROP 2-3 ft/hr and
decided to POOH.
21:30 - 23:30 2.00 STKOH P PROD2 Pumped 20 bbl Hi-Vis and circulated hole clean.
23:30 - 00:00 0.50 STKOH P PROD2 POOH with 6" directional BHA from 13,334 ft to
12,893 ft.
12/11/2016 00:00 - 01:30 1.50 STKOH P PROD2 POOH from 12,893 ft to 12,350 ft. Flow checked
at 12,350 ft - static. Circulated to cool MWD tools.
01:30 - 11:30 10.00 STKOH P PROD2 POOH from 12,350 ft to surface. Found all three
Pads of PD worn out. Laid down MWD tools, PD
and Bit. Flow checked at 9,000, 6,000, 3,000 ft
and at BHA - static. During POOH, circulated to
cool MWD tools at 11,500 ft and 10,500 ft.
Changed liners of mud pump 1 and 2 to 5".
11:30 - 00:00 12.50 STKOH P PROD2 P/U and M/U new Smith 713 PDC 6" Bit with 4x11
jets, new PowerDrive, MWD tool and Jar. Surface
tested PowerDrive at 210 GPM and 650 psi.
Shallow tested MWD tool at 150 GPM and 500
psi. RIH 6" PDC Bit / directional BHA to 12,320 ft.
Circulated at various intervals to cool MWD tools.

Printed 3/27/2017 9:05:28AM


United Energy Pakistan Limited Page 4 of 7

Operation Summary Report


Common Well Name: Haider Deep-2 AFE No
Event Type: RE-ENTER- ONSHORE (RON) Start Date: 12/5/2016 End Date: 12/19/2016 3-9934 (1,842,180.00 USD)

Project: Mirpurkhas (MK) Site: Haider Deep


Rig Name/No.: HL - 21 Spud Date/Time: 9/26/2016 6:00:00AM Rig Release:
Rig Contractor: HILONG UWI: Haider Deep-2
Active datum: RKB @110.0ft (above Mean Sea Level)
Date From - To Hrs Task Code NPT NPT Depth Phase Description of Operations
(hr) (ft)
12/12/2016 00:00 - 04:00 4.00 STKOH P PROD2 RIH with 6" directional BHA to 13,334 ft with
circulation to keep MWD tool cool. Observed tight
spot at 13,035 ft and 13,210, cleared the same.
04:00 - 00:00 20.00 STKOH P PROD2 Drilled 6" production hole directionally from
13,334 ft to 13,457 ft.

Drilling Parameters:
WOB: 11-13 KLBS, GPM: 202, RPM: 90, MW: 13
PPG
DRILLING HRS: 18.3 HRS, ROP: 6.7 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 20 HRS,
ROP: 6.1 FT/HR, TORQUE: 6-9 FT.KLBS

FORMATION: LBS SHALE-I, SAND-II


FORMATION TOP: 13,137 ft MD, 13,420 ft MD

Lithology at 13,430 ft:


Clay 50%, Sand 40%, Silt 10%

Last Survey:
13,419 ft, Inc: 10.22 deg, Azm: 274.91 deg,
13,273.69 ft TVD

Max formation gas 19 Units at 13,432 ft.

NOTE:
Observed breakouts in traces from 13450 ft
onwards.

Increased MW from 13.0 ppg to 13.2 ppg.


12/13/2016 00:00 - 13:00 13.00 STKOH P PROD2 Drilled 6" production hole directionally BHA from
13,457 ft to 13,552 ft.

Drilling Parameters:
WOB: 11-13 KLBS, GPM: 200, RPM: 90, MW:
13.2 PPG
DRILLING HRS: 12.3 HRS, ROP: 7.7 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 13 HRS,
ROP: 7.3 FT/HR, TORQUE: 6-9 FT.KLBS

FORMATION: LBS RESERVOIR SAND-II


FORMATION TOP: 13,420 ft MD

Last Survey:
13,511 ft, Inc: 10.36 deg, Azm: 275.24 deg,
13,364.21 ft TVD
13:00 - 15:00 2.00 STKOH P PROD2 Circulated swept hole with 20 bbl Hi-Vis pill and
cleaned hole. Observed traces to 5% breakouts at
bottoms up of Hi-Vis Pill.
15:00 - 17:30 2.50 STKOH P PROD2 POOH for wiper trip to 12,988 ft. Cleared tight
spots at 13115, 13036 and 13009 ft. RIH to
bottom at 13,552 ft. During RIH circulated to cool
down MWD tools.

Printed 3/27/2017 9:05:28AM


United Energy Pakistan Limited Page 5 of 7

Operation Summary Report


Common Well Name: Haider Deep-2 AFE No
Event Type: RE-ENTER- ONSHORE (RON) Start Date: 12/5/2016 End Date: 12/19/2016 3-9934 (1,842,180.00 USD)

Project: Mirpurkhas (MK) Site: Haider Deep


Rig Name/No.: HL - 21 Spud Date/Time: 9/26/2016 6:00:00AM Rig Release:
Rig Contractor: HILONG UWI: Haider Deep-2
Active datum: RKB @110.0ft (above Mean Sea Level)
Date From - To Hrs Task Code NPT NPT Depth Phase Description of Operations
(hr) (ft)
17:30 - 23:00 5.50 STKOH P PROD2 Drilled 6" production hole directionally from
13,552 ft to 13,567 ft. Decided to POOH due to
low ROP of 1-2 ft/hr.

Drilling Parameters:
WOB: 9-11 KLBS, GPM: 198, RPM: 87, MW: 13.2
PPG
DRILLING HRS: 5.5 HRS, ROP: 2.7 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 5.5 HRS,
ROP: 2.7 FT/HR, TORQUE: 7-8 FT.KLBS

FORMATION: LBS RESERVOIR SAND-II


FORMATION TOP: 13,420 ft MD

Last Sample at 13,566 ft: Sand 80%, Clay 20%


23:00 - 00:00 1.00 STKOH P PROD2 Circulated swept hole with 20 bbl Hi-Vis pill and
cleaned hole at 13,567 ft.
12/14/2016 00:00 - 01:00 1.00 STKOH P PROD2 Circulated and cleaned hole at 13,567 ft.
01:00 - 13:00 12.00 STKOH P PROD2 POOH with 6" bit from 13,567 ft to surface. Laid
down MWD tools, PD and Bit. Flow checked at
12350, 9000, 7000, 4000 ft and at BHA - static.
Circulated at intervals to cool down MWD tool.
13:00 - 00:00 11.00 STKOH P PROD2 P/U & M/U new 6" PDC Bit (Smith 513,
S#JM3152) with 4x12, 1x14 jets, new PowerDrive
and MWD tool.

Surface tested PowerDrive at 202 GPM and 874


psi. Shallow tested MWD tool at 181 GPM and
912 psi - OK.

RIH 6" bit / directional BHA to 12,922 ft.

Circulated at various intervals to cool MWD tools.


12/15/2016 00:00 - 03:30 3.50 STKOH P PROD2 RIH 6" Bit / directional BHA to 13,424 ft. Observed
tight spot. Hard reamed from 13,424 ft to bottom
at 13,567 ft with high torque 7-10 klb.ft. Rotary
stalled while reaming at 13,426 ft and 13,494 ft.
Observed excessive cuttings and breakouts on
shakers during reaming (10% to 15%).

Printed 3/27/2017 9:05:28AM


United Energy Pakistan Limited Page 6 of 7

Operation Summary Report


Common Well Name: Haider Deep-2 AFE No
Event Type: RE-ENTER- ONSHORE (RON) Start Date: 12/5/2016 End Date: 12/19/2016 3-9934 (1,842,180.00 USD)

Project: Mirpurkhas (MK) Site: Haider Deep


Rig Name/No.: HL - 21 Spud Date/Time: 9/26/2016 6:00:00AM Rig Release:
Rig Contractor: HILONG UWI: Haider Deep-2
Active datum: RKB @110.0ft (above Mean Sea Level)
Date From - To Hrs Task Code NPT NPT Depth Phase Description of Operations
(hr) (ft)
03:30 - 00:00 20.50 STKOH P PROD2 Drilled 6" production hole from 13,567 ft to 13,721
ft. (Observed excessive cuttings and breakouts
during circulation. Swept hole with 15 bbl Hi- Vis
while drilling at 13,567 ft at the bottom up of
Hi-Vis Pill hole was clean). Increased Mud Wt
from 13.2 ppg to 13.5 ppg in stages.

Drilling Parameters:
WOB: 9-13 KLBS, GPM: 191, RPM: 94, MW: 13.5
PPG
DRILLING HRS: 19.9 HRS, ROP: 7.7 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 20.5 HRS,
ROP: 7.5 FT/HR, TORQUE: 7-9 FT.KLBS

FORMATION: LBS RESERVOIR SAND-II


FORMATION TOP: 13,420 ft MD

Last Survey:
13,606 ft, Inc: 10.07 deg, Azm: 271.71 deg,
13,457.7 ft TVD

Max formation gas 78 Units at 13662 ft.


30 Units to 70 Units gas from 13662 ft to 13670 ft.

Last sample: 13,710 ft: Clay 80%, Sand 20%


12/16/2016 00:00 - 23:30 23.50 STKOH P PROD2 Drilled 6" production hole directionally from
13,721 ft to 13,838 ft.
23:30 - 00:00 0.50 STKOH P PROD2 Circulated and swept hole with 20 bbl Hi-Vis pill
and cleaned hole at 13,838 ft.
12/17/2016 00:00 - 01:30 1.50 STKOH P PROD2 Circulated and cleaned hole at 13,838 ft.
01:30 - 03:00 1.50 STKOH P PROD2 POOH with 6" directional BHA for wiper trip to
13,270 ft. Observed tight spots at 13,627 ft and
13,510 ft - cleared same.
03:00 - 04:30 1.50 STKOH P PROD2 RIH to bottom at 13,838 ft.
04:30 - 14:30 10.00 STKOH P PROD2 Drilled 6" production hole directionally from
13,838 ft to 13,877 ft. Observed TDS wash pipe
started leaking badly. Decided to Pull Out In
casing shoe.
14:30 - 16:00 1.50 STKOH P PROD2 POOH In 7" casing (12,320 ft) for wiper trip.
Installed circulating head and started circulation to
cool down MWD Tools.
16:00 - 16:30 0.50 STKOH N PROD2 Replaced wash pipe of TDS. P/T same at 4,000
PSI - Ok.
16:30 - 18:30 2.00 STKOH P PROD2 RIH to bottom at 13,877 ft. Observed tight spot at
13,634 ft. Cleared same.
18:30 - 00:00 5.50 STKOH P PROD2 Drilled 6" hole with directional BHA from 13,877 ft
to 13,890 ft.

Printed 3/27/2017 9:05:28AM


United Energy Pakistan Limited Page 7 of 7

Operation Summary Report


Common Well Name: Haider Deep-2 AFE No
Event Type: RE-ENTER- ONSHORE (RON) Start Date: 12/5/2016 End Date: 12/19/2016 3-9934 (1,842,180.00 USD)

Project: Mirpurkhas (MK) Site: Haider Deep


Rig Name/No.: HL - 21 Spud Date/Time: 9/26/2016 6:00:00AM Rig Release:
Rig Contractor: HILONG UWI: Haider Deep-2
Active datum: RKB @110.0ft (above Mean Sea Level)
Date From - To Hrs Task Code NPT NPT Depth Phase Description of Operations
(hr) (ft)
12/18/2016 00:00 - 05:00 5.00 STKOH P PROD2 Drilled 6" production hole directionally from
13,890 ft to 13,901 ft (Well TD).

Drilling Parameters:
WOB: 10-11 KLBS, GPM: 192, RPM: 87, MW:
13.5 PPG
DRILLING HRS: 2.5 HRS, ROP: 4.4 FT/HR
DRILLING HRS (INCLUDING CONNECTION
TIME): 5 HRS,
ROP: 2 FT/HR, TORQUE: 7-8 FT.KLBS

FORMATION: LBS RESERVOIR SAND-II


FORMATION TOP: 13,420 ft MD

Last Survey:
13,860 ft, Inc: 9.96 deg, Azm: 267.61 deg,
13,707.76 ft TVD

Last sample: 13,901 ft: Clay 80%, Sand 10% Silt


10%
05:00 - 07:00 2.00 STKOH P PROD2 Circulated and swept hole with 20 bbls Hi-Vis pill.
Cleaned hole at 13,901 ft.
07:00 - 07:30 0.50 STKOH P PROD2 Performed short trip up to 13,740 ft.
07:30 - 09:00 1.50 STKOH P PROD2 Circulated bottoms up at 13,900 ft.
09:00 - 20:00 11.00 STKOH P PROD2 POOH 6" Bit from 13,901 ft to surface.

L/D Jar, MWD tools, PowerDrive & Bit. Flow


checked at 12,350, 9,000, 7,000, 4,000 ft & at
BHA - well static.

Circulated at intervals to cool down MWD tool.


20:00 - 22:00 2.00 BOPSUR P PROD2 Changed upper pipe rams from 3.5" to 7".

L/D Mouse hole. Retrieved wear bushing.


22:00 - 00:00 2.00 BOPSUR P PROD2 P/U Plug type tester assembly and Pressure
tested BOP stack:
Annular to 300 - 3000 psi.

Lower Pipe rams, Blind ram, Manual valves, HCR


valves & Choke Manifold to 300 - 4500 psi - in
progress.
12/19/2016 00:00 - 01:30 1.50 BOPSUR P PROD2 P/T BOPs - OK. L/D testing assembly.
01:30 - 03:00 1.50 EVALUATIO P PROD2 Installed Shooting nipple and wireline BOP and
N pressure tested same to 500 psi - OK. Rig up
Schlumberger Wireline sheaves.
03:00 - 16:30 13.50 EVALUATIO P PROD2 P/U and M/U E-logging tools on wireline for run #
N 1 (SP-BHC-HRLA-MSFL-PPC-GR). RIH and
recorded logs. POOH and laid down logging tools
& shooting Nipple. Rig down Schlumberger wire
line.

Printed 3/27/2017 9:05:28AM