Operations Summary for 02nd of July 2022 From 00:00 - 24:00 hours with 00:00 - 06:00 hours Update

Rig Name Total days Planned Days Planned TD (mAHD) Current formation Last Shoe
on well
Next locations
Operations Summary EPDTR Days at GOAL (Construction status)
Current well Days since Actual / Planned 24hr depth ZERO
Target formations Next Shoe
Type spud Cost & progress

30"
EDC 52 6.1 32.6 Moghra
14 m - Cont. rotary drilling 171/2" hole from 430 m to 912 m.
• Last ROP: 71 m/hr, Avg run ROP: 36 m/hr.
26 2144 Karam-L
589,192 / 912 m. 13 3/8" Next Opertation:
Al Magd-M 1.5
2,748,831 482 m. 1123 m. - Continue drilling 17½" hole to section TD, Circ. hole clean, POOH to surface and run 13 3/8'' CSG.

13 3/8"
EDC 72 16.0 33.2 4032 Khoman - P/U & M/U 12.25" RSS BHA and RIH same to btm.
1253 m.
- Cont. drill 12¼" hole with Motor BHA to 3015 m.
ASSIL 10 • Last ROP: 15 m/hr and Avg Run ROP: 21.8 m/hr. NEAG JG C5-A
19 1827
Deviated 940,766 / A/R "G" 3015 m 9 5/8"
11.6 Next Opertation:
Development Oil 3,057,083 U. Bahariya 219 m. 3285 m.
Producer - Change BHA.RIH w/12.25" RSS bHA. drill 12.25'' hole rotary steerable mode to section TD.

7"
NDC-7 52.7 31.0 2787 Kharita
2765 m - Cont. POOH W/ 4 1/2" TCP gun to surface.
- P/U & M/U Al-Khorayef ESP assy. Ongoing.
NEAG 3-1 ST 2 207 Fadl-IX
Deviated 1,652,109 2765 m Next Opertation:
28.2 L.Bahariya
Development Oil / 1,813,938 m. - RIH with Al-Khorayef ESP assy. on 3 1/2" completion.
Producer

13 3/8"
ECDC-810 151.0 32.5 3932 A/R "B"
1163 m. - Cont. drill 12¼" hole with Motor BHA in rotary mode from 3035 m to 3222 m.
• Last ROP: 15 m/hr and Avg Run ROP: 21.8 m/hr.
BED 16-15 16 181 BED 16-X
Deviated 1,310,399 / 3222 m 9 5/8" Next Opertation:
16.4 A/R "G" - Cont. Drill 12.25" Hole to section TD. POOH.
Development water 2,295,581 187 m. 3317 m.
Producer