Professional Documents
Culture Documents
Assignment 2 PM
Assignment 2 PM
Submitted by:
Mechanical Engineering
Syndicate: B
Date:4/06/2022
1. Project Scope:
PROJECT OBJECTIVE
To construct a small scale H Type Darius Vertical Axis Wind Turbine using the
blades of Alouette Helicopter for micro power generator within 9 months at not to
exceed 40 thousands rupees.
DELIVERABLES
Design of Vertical Axis Wind Turbine on Q blade software
3 D model on CREO Parametric.
To achieve power of 15 W on Matlab
3 bladed wind turbine having rotor of radius of 0.5 m.
Pulleys and belts system for electricity generation
MILESTONES
Planning and market visit___20 November 2021
Literature Review ____1 December 2021
MATLAB Code and Q blade Stimulation____15 January 2022
CAD Modelling____20 February 2022
Fabrication and Assembly ____ 30 April 2022
Testing ____ 30 May 2022
TECHNICAL REQUIREMENTS
Motor capacity of 15 W for electric power generation.
203 mm aluminum pulley and 50 mm steel pulley to transfer torque.
Cube base of length 457.2 mm angle Iron as a base.
Steel guy wires to be attached to prevent vibration and topper over in the shaft.
Thrust bearing 25 mm ID and 52 mm OD to transfer the weight of rotating
shaft onto the stationary shaft.
Nuts and bolts of 12.7 mm for joining blades on rotor.
Mild steel stationary shaft of 1524 length and 76.2 diameter for supporting the
weigth of rotor.
Galvanized iron rotating steel 2133 length and 19.04 diameter for transfering
torque from rotor to motor.
NACA 0021 of 140 mm chord length of tail rotor of Aloutte Helicopter.
LIMITS AND EXCLUSIONS
Limiting speed of bearing is 13 thousand rpm with the basis dynamic load
rating of 13.2 KN and fatigue load limit of 3.45 KN.
Design for the wind speed of 4.5 m/s and above.
Simulations and calculations do not account for wake expansion and yaw.
BEMT does not account for tip losses, though correction factors are included
but they do not achieve exact results.
Calculations are based on steady flow and they do not account for turbulence.
This project is based on assumption that flow is inviscid and incompressible.
Activity diagram
An activity diagram depicts the sequence of activities and their
relationship with one and other which gives an overall pictue of projects total duration
and the mean critical path of project.
Critical Path:
ACDEFGHIJKLMPRSTUVXYZabcd
Having a duration of 205 days
3. GANTT chart: