Professional Documents
Culture Documents
4-2 EDS 1unit.
4-2 EDS 1unit.
Marketed by:
UNIT
GENERAL CONCEPTS
1 SIA GROUP
PART-A
SHORT QUESTIONS WITH SOLUTIONS
Q1. Explain the various factors affecting the distribution system planning.
Ans: Model Paper-IV, Q1(a)
1. The most important factor affecting the distribution system planning is the load forecasting of electric power utility
2. Substation site selection and expansion
3. Physical size and land availability
4. Number of feeder circuits and selection of feeder conductor size
5. Design of overhead and underground transmission lines
6. The rates that are charged to the customer
7. Power loss and economic factors
8. Rating limitations
9. Availability of spare transformers, mobile substations etc
10. The overall cost of the distribution system, i.e., capital cost, installation cost, maintenance and operating cost etc.
Q2. Write short notes on (i) economic factor and (ii) demographic factor.
Ans:
(i) Economic Factor
There are several economic factors which has an impact on distribution system planning. The first factor is inflation. Due
to energy shortages, cost of energy conversion, environmental concerns and over expense of government, the inflation is rising
up which is a major factor.
The second important factor is increase in expenses to gain capital. As the inflation rises up, the supply of money will be
less which in turn will increase the competition for buying the capital for the expansion of distribution systems.
The third factor is the difficulty in raising customer rates. As the rates are increasing “Inertia” also rises up which usually
arrived from inflation.
(ii) Demographic Factor
Increase in population will effect the distribution system planning in the future. The important consideration in this is
that the migration of population from the rural areas to the urban areas. The number of large families from rural move towards
the metropolitan areas and there are no forces to stop them. The main consideration of distribution planners is that, as the rural
population migrate to urban areas, the population must also leave the small towns which are dependent on rural areas. Thus, the
migration of population from rural areas to urban areas result in the energy shortage.
Q3. Write short notes on Load Duration Curve.
Ans: Model Paper-I, Q1(a)
Load Duration Curve
A curve which is plotted by taking per unit peak load on y-axis and per unit time on x-axis is known as load duration curve.
In this curve, the maximum peak points of the daily demand variation. Curve are selected and then joined together.
In this curve, the magnitudes of the loads are in decreasing order. Therefore, the maximum load is represented to the left
and the decreasing loads are represented to the right of the curve.
Depending upon the time period of operation of loads, load-duration curves can be daily, weekly, monthly or annual.
SIA GROUP
1.2 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
Load-duration curve is shown in figure.
Dg
CF = n
∑D
i =1
i
Q5. Define coincidence factor and write its significance on distribution system.
Ans: Nov.-16, Set-4, Q1(a)
Coincidence Factor
For answer refer Unit-I, Q4, Topic: Coincidence Factor
Significance of Coincidence Factor
Generally, the individual maximum demands of loads occur at different time intervals. Hence, the sum of individual
maximum demands is higher than the maximum demand on the power system. Therefore, the coincidence factor is always less
than 1.
The coincidence factor plays a significant role on a distribution system. It affects the cost of generation in a power system,
i.e., lesser the coincidence factor, lesser will be the cost of generation. On the other hand, for high value of coincidence factor the
cost of generation will be high. But it is always economical to have less cost of generation. Hence, lesser values of coincidence
factor are preferred.
Q6. Write the significance of load factor?
Ans: Nov.-16, Set-1, Q1(a)
The load factor plays a key role in determining the overall cost per unit generated. To supply the maximum energy
requirements of consumers, it is necessary to install a power plant whose installed capacity should meet its maximum demand.
If the average load of consumers is equal to the maximum demand of the generating station, then the load factor will be equal
to its maximum value of 1 i.e., 100% and the consumer will make use of the total installed capacity all the time, due to which
the cost of energy per unit generated will be minimum. This can be explained better with the help of an example. Suppose a
∑D
i =1
i
∑C D i i
=i =1n
∑D
i =1
i
SIA GROUP
1.4 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
Q9. Explain the following factors,
(i) Contribution factor
(ii) Load diversity
(iii) Loss factor.
Ans:
(i) Contribution Factor
For answer refer Unit-I, Q7(ii).
(ii) Load Diversity
Load diversity is defined as the difference between the sum of individual maximum demands of two or more loads and
the overall peak load. Load diversity is denoted by L.D.
n
L.D = ∑D
i =1
i
– Dg
Where,
Di = Individual maximum demand of ith consumer
n = Total number of loads
Dg = Peak load.
(iii) Loss Factor
For answer refer Unit-I, Q4(ii).
Q10. What is meant by the term load? How loads can be classified?
Ans:
The term load means an entity, when operated, draws power from a system.
Loads are classified into the following,
(i) Domestic loads
(ii) Commercial loads
(iii) Industrial loads
(iv) Agricultural loads or irrigation loads
(v) Municipal or common loads
(vi) Traction loads.
Q11. The average load factor of a substation is 0.65. Determine the average loss factor at
(i) Urban area
(ii) Rural area.
Ans: Nov.-16, Set-2, Q1(a)
Given that,
Average load factor of a substation, FLD = 0.65
To determine,
(i) Average loss factor at urban area.
(ii) Average loss factor at rural area.
(i) Average loss factor at urban area is given by,
2
FLS = 0.3 FLD + 0.7 F LD
= 0.3(0.65) + 0.7 (0.65)2
= 0.491
(ii) Average loss factor at rural area is given by,
2
FLS = 0.16 FLD + 0.84 F LD
= 0.16(0.65) + 0.84 (0.65)2
= 0.459
Hot Reserve
The reserve generating capacity which is in operation but not in service is called hot reserve.
Spinning Power
The generating capacity which is connected to the bus bars and prepared for getting the load is called spinning reserve (or)
spinning power.
Q13. Discuss the characteristics of Industrial.
Ans:
Loads used in industries are called industrial loads. The industries uses the loads depending on the type of the industry,
i.e., for a cottage industry the load required is less about 5 kW.
For small scale industries the load requirement is of about 5 to 25 kW. For medium it is about 25-100 kW and for large
scale and heavy industries the load requirement is 100 to 500 kW and greater than 500 kW. The demand factor and load factor
for large scale industries are 70 to 80% and 60 to 65% respectively. Similarly, the demand factor and load factor for heavy scale
industries is given by 85 to 90% and 70 to 80% respectively. These loads are independent of weather i.e., the load required is
same irrespective of the climatic conditions. The load curve for an industrial load is shown in figure.
SIA GROUP
1.6 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
We have, (i) The Average Annual Power Loss
The demand factor is given by, We know that,
Maximum demand
Demand factor = FLS =
Total connected load
85 Average power loss = FLS × Power loss at peak load
=
120 = 0.15 × 80 kW
= 0.708
= 12 kW
Load factor is given by,
(ii) Total Annual Energy Loss
Energy consumed in T hours
Load factor, L.F = Total annual energy loss = Average power loss × 8760 hrs
Maximum demand × T
4300 = 12 kW × 8760 hrs
=
85 × 7 × 24 = 105120 kWh
= 0.301 = 105.12 MWh.
Q15. The annual input to a sub-transmission system Q17. A generating station supplies four feeders with
is 87600 MWh. On the peak load day of the year, the maximum demands of 16 MW; 10 MW; 12
the peak is 25 MW and the energy input on that MW and 7 MW. The overall maximum demand
day is 300 MWh. Find the load factor for the year on the station is 20 MW and the annual load
and for the peak load day. factor is 45%. Find the diversity factor and the
Ans: number of units generated annually.
Given that,
Annual input = 87600 MWh
Load supplied = 16 MW, 10 MW, 12 MW and 7 MW
Maximum demand = 25 MW
Maximum demand on station = 20 MW
Energy input on peak day = 300 MWh
Annual load factor = 45%
Load factor = To determine,
Diversity factor = ?
87600
∴ Load for the year = = 0.4 Number of units generated annually = ?
25 × 8760
300 Diversity Factor
Load factor for the peak load day =
25 × 24 Sum of maximum demands
Diversity factor =
= 0.5 Station maximum demand
Q16. Assume that the annual peak load of a primary 16 + 10 + 12 + 7
feeder is 2000 kW, at which the power is =
20
80 kW per three-phase. Assuming an annual
loss factor of 0.15. Determine, = 2.25
(i) The average annual power loss Number of Units Generated Annually
The load factor is given as,
(ii) The total annual energy loss due to the
copper losses of the feeder. Number of units generated annually
Annual load factor =
Maximum demand × 24 × 365
Ans: Nov.-16, Set-3, Q2(b)
SIA GROUP
1.8 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
We have,
Average demand
Load factor =
Maximum demand
Where,
Units supplied/annum
Average demand =
8760
60 ×106
=
8760
= 6849.32
Then,
Average demand
Load factor =
Maximum demand
6849.32
=
22 × 103
= 0.31
Maximum demand
Demand factor =
Connected load
22
=
45
=
0.49
PART-B
ESSAY QUESTIONS WITH SOLUTIONS
Q22. Explain how the load growth in a distribution system can be obtained?
Ans:
With the increase in population, there will be a growth in residential and commercial areas. Due to this growth, new loads
are added in the distribution system to obtain load growth, these loads must be properly optimized.
The load growth of the geographical area plays an important role in the expansion of the distribution system. Hence, load
forecasting of the increased loads is customary for the planning in a distribution system.
The data that is pertaining to the growth in load can be represented by a logarithmic function as specified by the exponential
trend.
z
yl = cd ... (1)
The above equation is sometimes referred to as load growth equation, as it is used to explain the changes occurring in load
for a given time.
If the rate of load growth is known, then the load at the end of ith year is given by,
pi = po (1 + g)i
Where, ... (2)
pi = Load at the end of i year
th
po = Initial load
g = Annual growth rate
i = Total number of years.
Hence, in this way load growth is obtained.
If in the equations (1) and (2), the values are set such that,
yl = pi, po = c, 1 + g = d and i = z, then, we get,
yl = cd z i.e., equation (2) is similar to that of equation (1).
Q23. List out and explain the various functions in distribution automation.
Ans:
The various control functions used in distribution automation are classified into three types. They are,
1. Load management functions
2. Real-time operational management functions
3. Remote meter reading functions.
1. Load Management Functions
These functions are used to control the loads at the consumer terminals. The loads are controlled by the remote control
present at the centre of the distribution automation.
Load management functions are further classified as follows,
(a) Discretionary load switching
(b) Peak-load pricing
(c) Load shedding
(d) Cold load pick up.
(a) Discretionary Load Switching
This function is also known as customer load management function. It controls the loads of the individual consumers from
a remote central location. The loads that can be controlled by this function are water heaters, air conditioners, space heaters,
thermal storage heaters etc. In this control function, the load is controlled not only by the meters but also by the dispatching
centres.
SIA GROUP
1.10 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
The two main purposes of this control function are, (c) Transformer Load Management (TLM)
(i) To reduce the peak load of the entire system and This function manages the transformer loading data and
(ii) To reduce the load on a particular distribution core temperature of the transformer by monitoring and
substation or feeder when it is overloaded. reporting it continuously. Hence, the main purpose of
this function is to avoid overload burnouts or abnormal
(b) Peak-load Pricing
operation of transformer by reinforcement, replacement
This function is similar to that of discretionary load or reconfiguration.
switching control function, except that the loads in this
function are controlled only by the meters. The main (d) Feeder Load Management (FLM)
purpose of peak-load pricing is to obtain the time of day The functions of Feeder Load Management (FCM) are
metering. Therefore, it employs automatic switching of similar to that of Transformer Load Management (TLM).
meter registers for implementing peak-load pricing But in this, the loads on the feeders are measured and
programs. monitored instead of the loads of transformers. This
(c) Load Shedding function allows the equalization of loads over several
feeders.
This function helps in rapid dropping of large blocks of
load, under certain conditions, according to a priority that (e) Capacitor Control
is established.
Using this function, the distribution capacitors in the
(d) Cold Load Pick Up distribution networks are controlled by remote control
The load that is dropped by the load shedding must be switching of the capacitors.
picked up by this function. Hence, this function can be
termed as a corollary of load shedding. (f) Dispersed Storage and Generation
2. Real-time Operational Management Functions This function exercises control over the storage and
generation equipment located at the strategic places
These functions are used to control the equipment
throughout the distribution system. These equipments
installed by the remote control of switches and breakers.
may be used for peak shaving. The main purpose of this
Real-time operational management functions are further function is to coordinate the sites where these equipments
classified as follows, are located, by the remote control.
(a) Load reconfiguration (g) Fault Detection, Location and Isolation
(b) Voltage regulation
This function permits the dispatcher to send the repair
(c) Transformer load management crews faster to the place where the fault is located. By
(d) Feeder load management doing so, the service interruption time of the consumers
can be reduced. The faults are detected by the sensors
(e) Capacitor control
present throughout the distribution network. Hence,
(f) Dispersed storage and generation when the faults are detected, the information regarding
(g) Fault detection, location and isolation the abnormal conditions is reported. This information is
used to locate the faults and to isolate the faulty portion
(h) Load studies
from the distribution network with the help of protective
(i) Condition and state monitoring. devices and by circuit reconfiguration.
(a) Load Reconfiguration (h) Load Studies
This function allows the daily, monthly and seasonal
load reconfiguration of feeders or feeder segments by This function involves the load data to be gathered and
the remote control of switches and circuit breakers. recorded automatically on-line. This data is used for
The main purpose of this function is to serve the larger special off-line analysis. This gathered data may be
loads effectively without any feeder reinforcement or located at the collection point, at the substation or it can
new construction. It considers the advantage of load be transmitted to a dispatch center. The main purpose of
diversity among feeders, for achieving its purpose. this function is to provide accurate and timely data for the
planning, designing of power systems to the distribution
(b) Voltage Regulation engineers.
This function involves the remote control of selected (i) Condition and State Monitoring
voltage regulators along with the network capacitor
switching within the distribution network. When the This function permits the gathering of real-time data
voltage regulators and network capacitor switching are and reporting it. The main purpose of this function is to
controlled, it results in effective coordination of voltage known the status of the power system at every minute
control from a central facility. of time.
SIA GROUP
1.12 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
Q25. Draw a block diagram in flow chart form for a distribution system required is directed by the characteristics of
typical distribution system planning process and demand type, load factor and other customer load. As soon as
explain the techniques for distribution planning. the customer loads are found, the secondary lines are defined,
which are then connected to the distribution transformers. The
Ans: Nov.-10, Set-4, Q1
loads of these transformers are now combined to determine the
In the electrical distribution system, planners uses a
demands on the primary distribution system. The substations
variety of computer programs such as load flow programs,
which are step down from subtransmission lines voltages are
radial or loop load flow programs, short circuit and fault current
assigned to primary distribution system. From the distribution
calculation programs, voltage drop calculation programs and
system loads, the size and location of the substation as well as
total system impedance calculation programs including other
the route and capacity of assigned subtransmission lines can
tools such as, load forecasting, voltage regulation, regulator
be found out. In the distribution planning process each step is
setting, capacitor planning, reliability and optimal siting and
provided with input for the steps that follows.
sizing algorithm. The concept of using output of each program
as the input for another program is not used. Computers makes In practice, this procedure is impossible to follow. On
calculations very quickly and thus engineers start reviewing the receiving the relevant load projection data, system calculations
calculations rather than making them. The above mentioned are made to check whether the present system is capable of
tools and programs are truly operated by the judgement of the handling the new increased load or not. These steps constitute
distribution planner and overall company operating policy. the second stage which requires the use of tools such as
distribution load flow program, a voltage profile and a regulation
The block diagram of distribution system planning program.
process is as shown in following figure,
In order to successfully implement the above procedure,
the acceptability criteria, company policies, obligations to the
consumers and additional constraints includes,
1. Supplying the maximum peak voltage drop to the last
customer on the secondary
2. Continuity of service
3. The maximum value of allowed peak load
4. Service reliability
5. Power losses.
From the block diagram, if the analysis shows that the
present system is not upto the mark to meet the future demand,
then the present system is needed to be replaced by the new,
relatively minor, system additions or a new substation may be
installed to meet the future loads. If the present system is to be
expanded with minor additions, then the additional network
configuration is designed and checked for satisfactory operation.
At this instant, the cost of each configuration is calculated. If the
configuration is expensive or satisfactory operation is not possible,
then the previous original network computation is re-evaluated
with some changes in it. If not the decision is to build a new
substation, then new site has to be selected. If furthermore, the
cost of new site is high then this process is again re-evaluated.
Thus, in this way all the operations are carried out by computer
aided programs until a satisfactory operation is achieved
providing a solution to existing future problems at a reasonable
cost.
1.2 LOAD MODELLING AND
CHARACTERISTICS
SIA GROUP
1.14 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
At Phase B Now the load currents are given by,
S V VRN
ILB = B ILR = RN = (δR – θR) = | ILR | ∠αR
VBN ZR ZR
VYN VYN
| S | ∠θ B
= B ILY =
ZY
=
Z Y (δY – θY) = | ILY | ∠αY
| VBN | ∠δ B
VYB VYB
| SB | ILB = = (δB – θB) = | ILB | ∠αB
= ∠θB – δB ZB ZB
| VBN |
The phase voltages in constant impedance model will
= ILB ∠αB change during each iteration but the impedances will remain
constant.
2. Constant Current Model
Characteristics of Load Models
In constant current model the magnitude of currents are
kept constant and the voltage angle (δ) is changed, which results Characteristics of a load model gives response to all loads
in a change of current angle to keep the power factor constant. as a function of voltage. It is the combination of constant power,
If the load is star connected, then the line currents are given by, constant current and constant impedance. The characteristics of
a load model are shown in figure (1).
ILR = | ILR | ∠δR – θR
ILY = | ILY | ∠δY – θY
ILB = | ILB | ∠δB – θB
| VRN |2
= ∠θR
| SR |
= ZR ∠θR
At Phase Y
| VYN |2
ZY =
SY*
| VYN |2
Figure (2): MVA Vs Node Voltage
=
| SY | ∠θY
Q27. Discuss about the three factors which affect the
= ZY ∠θY distribution system planning in the near future.
At Phase B Ans: Nov.-10, Set-3, Q1(b)
The three factors which affects the distribution system
| VBN |2 planning in the near future are,
ZB =
S B* (i) Economic factor
(ii) Demographic factor
| VBN |2
= ∠θB (iii) Technological factor.
| SB |
(i) Economic Factor
= ZB ∠θB For answer refer Unit-I, Q2, Topic: Economic Factor
SIA GROUP
1.16 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
If the diversity factor is high, then the cost of generation in a power system is less.
Here, the individual maximum demands of loads, occurs at different time intervals. Hence, the sum of the individual
maximum demands is higher than maximum demand of the overall system. Hence, diversity factor is always greater than one.
Therefore, the effect of diversity factor on the cost of generation in a power system is that, higher the diversity factor,
lesser will be the cost of generation on the other hand, for low value of diversity factor the cost of generation will be high. But it
is always economical to have less cost of generation. Hence, higher values of diversity factor are preferred.
Q30. A distribution substation experiences an annual peak load of 3,500 kW. The total annual energy supplied
to the primary feeder circuits is 107 kWh. Find,
(i) The annual average power
(ii) The annual load factor.
Ans: Oct./Nov.-17, Set-3, Q2(b)
Given that,
Annual peak load = 3,500 kW
10 7 kWh
= = 1141.55 kW
365 × 24 hours
(ii) Annual Load Factor
Total annual energy
Annual load factor, FLD =
Annual peak load × 8760 hours
10 7 kWh
FLD = = 0.326
3500 kW× 8760 hours
Q31. A 120 MW substation delivers 120 MW for 3 hours 60 MW for 8 hours and shutdown for rest of each day.
It is also shutdown for the maintenance for 15 days each year. Calculate its annual load and annual loss
factor.
Ans: Nov.-16, Set-4, Q2(b)
Given that,
120 MW substation delivers load,
Load (MW) Time (Hours)
120 3
60 8
Maximum demand = 120 MW
Substation shutdown for maintenance = 15 days each year
To determine,
Annual load factor = ?
Annual loss factor = ?
Power delivered for 3 hr = 120 MW × 3 hr
= 360 MWh
Power delivered for 10 hr = 60 MW × 8 hr
= 480 MWh
294000
= 120× (350×24)
Given that,
Time 6 a.m 9 a.m - 12 noon- 1 p.m- 6 p.m- 8 p.m- 11 p.m
9 a.m 12 noon 1 p.m 6 p.m 8 p.m 11 p.m 6 a.m
Residential, kW 400 300 300 300 400 300 200
Commercial, kW 100 500 550 600 900 400 100
(a) The contribution factor for each of load cases,
Cresidential = ?
Ccommercial = ?
(b) Diversified maximum demand of load group, Dg = ?
(c) The coincidence factor of the load group for the load data, Fc = ?
SIA GROUP
1.18 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
(a) The contribution factor for each of load cases,
Demand at the time of system peak
Ci =
Non coincident maximum demand
For residential load,
Here, system peak occurs between 6 p.m to 8 p.m
400 kW
∴ Cresidential = = 1.0
400 kW
For commercial load,
900 kW
Ccommercial = = 1.0
900 kW
(b) The diversified maximum demand of load group is given by,
n
Σ Di
i =1
Dg =
FD
Where,
Di = Maximum demand of load
FD = Diversity factor.
Diversity factor (FD) is given as,
n
Σ Di
i =1
FD = n [ n = Number of loads]
Σ Ci × Di
i =1
2
Σ Di 400 + 900
i =1
∴ FD = =
2 (1 × 400) + (1 × 900)
Σ Ci × Di
i =1
1300
FD = = 1.0
1300
∴ Diversified maximum demand of the load group is,
2
Σ Di 400 + 900
i =1
Dg =
=
FD 1.0
= 1300 kW
(c) The coincidence factor of the load,
Dg
FC = n
Σ Di
i =1
1300 × 103
=
400 × 103 + 900 × 103
=1
Alternate Method
1 1
FC = =
FD 1
=1
FD =
= 4.333 × 103
∴ Maximum demand on transformer 1,
(Dmax)1 = 4.333 kW
Maximum demand on transformer 2,
P2 × D2 (12 × 103 ) × 0.6
(Dmax)2 = =
FD 2 3.5
= 2.057 kW
SIA GROUP
1.20 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
Maximum demand on transformer 3,
P3 × D3
(Dmax)3 =
FD 3
(15 × 103 ) × 0.7
=
1.5
= 7 × 103 Watts
= 7 kW
The expression for the diversity factor is also given as,
Diversity factor, FD =
13.39 × 103
=
1.3
= 10.3 × 103 Watts
= 10.3 kW
∴ Maximum load on the feeder is 10.3 kW
Q34. Prove that approximate formula for loss factor (FLS) = 0.3 FLD + 0.7 FLD2, where FLD = load factor.
Oct./Nov.-17, Set-4, Q2(a)
OR
Explain the relationship between the load factor and loss factor.
Nov./Dec.-14, Set-2, Q1(a)
OR
Derive the relation between load factor and loss factor with a simplified approach.
Dec.-13, Set-2, Q1(a)
OR
Define and derive the relationship between load and loss factors.
(Nov.-11, Set-1, Q1(b) | Nov.-11, Set-2, Q1(a) | Model Paper-II, Q2(a))
OR
Obtain the relation between the load factor and loss factor.
An exact relation between the load factor and loss factor cannot be obtained. However, an approximate relation between
the load factor and loss factor is developed by Buller and Woodrow.
Consider a primary feeder connected to a variable load as shown in figure (a). An ideal load curve is plotted between the
load and time as shown in figure (b).
SIA GROUP
1.22 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
FLD =
PLD, avg
FLD = ... (1)
PLD, 2
The loss factor, FLS is defined as the ratio of average power loss to the peak power loss during certain period of time.
Average power loss
FLS =
Peak load power loss
PLS , avg
FLS = ... (2)
PLS , 2
As the copper losses are present in the given loads, they can be expressed as,
2
PLS, 1 = K × PLD , 1 ... (3)
2
PLS, 2 =K × PLD, 2 ... (4)
From the load curve in figure (b), PLD, avg can be calculated as,
PLD , 2 × t1 + PLD ,1 × (t 2 − t1 )
PLD, avg = ... (5)
t2
Substituting equation (5) in equation (1), we get,
PLD, 2 × t1 + PLD,1 × (t 2 − t1 ) / t 2
FLD =
PLD , 2
PLD , 2 × t1 + PLD ,1 × (t 2 − t1 )
=
PLD , 2 × t 2
PLD, 2 × t1 PLD ,1 × (t 2 − t1 )
= +
PLD, 2 × t 2 PLD , 2
t1 PLD,1 t 2 − t1
= + × ... (6)
t2 PLD, 2 t1
PLS , 2 × t1 + PLS ,1 × (t 2 − t1 )
PLS, avg = ... (7)
t2
Substituting equation (7) in equation (2), we get,
PLS , 2 × t1 + PLS ,1 × (t 2 − t1 ) / t 2
FLS =
PLS , 2
PLS , 2 × t1 + PLS ,1 × (t 2 − t1 )
= ... (8)
PLS , 2 × t 2
Substituting equation (3) in equations (4) and (8), we get,
2 2
( K × PLD , 2 ) × t1 + ( K × PLD ,1 ) × (t 2 − t1 )
FLS = 2
( K × PLD ,2 ) × t2
2 2
( K × PLD , 2 ) × t1 ( K × PLD ,1 ) × (t 2 − t1 )
= 2 + 2
( K × PLD ,2 ) × t2 ( K × PLD ,2 ) × t2
2
t1 PLD,1 t −t
= + × 2 1 ... (9)
t1
t2 PLD, 2
t1 t 2 − t1 t
FLD = + 0 = 1 and
t2 2 t t 2
t1 t 2 − t1 t
FLS = + 0 = 1
t2 t1 t 2
Therefore, when off-peak load is zero,
t1
FLD = FLS =
t2
Hence, load factor and loss factor are equal to t1 , when PLD, 1 is zero.
t2
Case II: If the Peak Load Exists for a Very Short Duration
As the peak load exists for a short duration of time, the time period t1 at which peak load occurs tends to approach zero
i.e., t1 ~ 0.
So, substituting t1 = 0 in equations (6) and (9), we get,
PLD,1 (t 2 − 0) PLD,1
FLD = 0 + = and
PLD, 2 (t 2 ) PLD, 2
2 2
PLD,1 t 2 − 0 PLD,1
FLS = 0 +
=
P
LD, 2 t 2 PLD, 2
t2 PLD,1 t2 − t2 t2
FLD = + × =
t2 PLD, 2 t2 t2
FLD = 1
2
t2 PLD,1 t2 − t2
FLS = + × t
t2 P
LD, 2 2
t
=2
t2
FLS =1
So, when the load connected is steady i.e., as t1 → t2, the loss factor value approaches the load factor value.
SIA GROUP
1.24 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
Hence, from the three different cases considered, it can be concluded that an exact relation between loss factor and load
factor cannot be obtained but an approximate relation can be obtained.
2
In practice, it is observed that the square of the load factor ( FLD ) is less than that of loss factor FLS and also the loss factor
2
value (FLS) is less than that of load factor value (FLD). Hence, FLS lies between FLD and FLD.
2
FLD < FLS < FLD
Note
The loss factor cannot be determined directly from the load factor the reason is that the loss factor is determined from
losses as a function of time which inturn are proportional to the time function of the square load.
However, Buller and Woodrow developed and approximate formula to relate the loss factor to the load factor as,
FLS = 0.3FLD + 0.7 FLD
2 ... (10)
= 0.3(0.32) + 0.7(0.32)2
= 0.16768
0.16768
Annual loss factor = 0.16768
(ii) Total Annual Copper Loss Energy and its Value at ` 1.5 per kWH
We know that,
Given that,
Annual peak load = 1300 kW
Peak load loss = 120 kW
Total annual energy supplied to the sending end of the feeder = 5.8 × 106 kWh
To determine,
(i) Annual loss factor
(ii) Total annual energy loss and the annual cost if the unit charge is ` 5.0
SIA GROUP
1.26 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
(i) Annual Loss Factor
We know that,
Annual loss factor,
Where,
FLD = Load factor
Total annual energy
Annual load factor, FLD =
Annual peak load × 8760 hrs
5.8 × 10 6 kWh
=
1300 kW × 8760 hrs/year
= 0.50
2
∴ Annual loss factor, FLS = 0.3FLD + 0.7 FLD
Given that,
Total annual energy = 87.6 × 106 kWh
Annual peak load = 25,000 kW
Energy input on peak day = 3 × 105 kWh
To find,
Annual load factor = ?
Daily load factor = ?
87 .6 × 10 6
= = 0.4
25000 × 8760
3 × 10 5
=
25000 × 24
= 0.5
∴ Daily load factor = 0.5
OR
Why loads are classified in distribution systems and how they are classified? Explain their different
characteristics.
Ans: Model Paper-IV, Q2(a)
The loads on the distribution system are of various types. The density of certain loads is different from the other. All the
loads are not in use through out the day. Hence, the load density, thus the demand varies with time. So, for proper planning of
distribution system the classification of loads is necessary.
In distribution system the loads are classified according to the types of consumers like irrigation, manufacturing, produc-
tion etc. Depending upon the type of usage the loads are classified or divided into five types. They are,
1. Domestic loads
2. Industrial loads
3. Agricultural loads
4. Commercial loads
5. Municipal loads.
The characteristics of load is studied in terms of demand factor, load factor, diversity factor, utilization factor and power factor.
1. Domestic Loads
Loads used for household purposes are called domestic loads. It involves domestic appliances such as lights, fans,
refrigerators, mixers, washing machines, radio’s, ovens, television etc. For these loads the demand factor will be in the range of
70 to 100 percent, the diversity factor is 1.2 to 1.3 and the load factor is in the range of 10 to 15 percent. A typical load-curve for
domestic loads is shown in figure (1).
SIA GROUP
1.28 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
Characteristics of Domestic Loads
(i) From figure (1) it is clear that, during the morning hours the load requirement is very less. Hence, the load utilized
is very less.
(ii) During evening hours the load requirement is very high and is maximum during the time period of 6 PM to 10 PM.
Hence, the load utilized is very high.
2. Industrial Loads
For answer refer Unit-I, Q13.
3. Agricultural Loads
Loads used for irrigation purpose are called agricultural loads. In fields, the water is supplied with the help of electric
motors. For these type of loads the diversity factor is 1 to 1.5 load factor is 20 to 15% and the demand factor is 90 to 100%.
4. Commercial Loads
Loads used for commercial purpose like lighting for shops, advertisements and fans and electric appliances used in shopping
malls, restaurants etc., are called commercial loads. For these loads the load factor is 25 to 30%, diversity factor is 1.2 to 1.2 and
the demand factor 90 to 100%. The load curve of commercial loads is shown in figure (2).
Depending upon the usage, the loads are classified into five types. They are,
1. Domestic loads
2. Industrial loads
3. Agricultural loads
4. Commercial loads
5. Municipal loads
Figure
Characteristics of Municipal Loads
(i) From above figure, it can be seen that the load requirement is maximum during the period of 0 to 7 hours. Hence, the load
utilized is maximum and constant.
(ii) During the time period 7 to 18 hours, there is no load required. Hence, the load is not utilized.
(iii) Again after the time period i.e., 18th hour the load requirement is high and constant. Hence maximum load utilized.
Q40. A power supply is having the following loads:
SIA GROUP
1.30 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
Ans: Oct./Nov.-17, Set-1, Q2(b) Industrial Customers
Given that, Sum of maximum demands = Maximum demand × Diversity
factor
Type of Load Max Diversity Demand = 10000 × 1.25
Demand of Group Factor
= 12500 kW
(kW)
∴ Connected industrial load
Domestic 1500 1.2 0.80
Commercial 2000 1.1 0.80 =
Industrial 10000 1.25 1.0
12500
Overall diversity factor = 1.35 =
1.0
To find,
= 12500 kW
(i) Maximum demand on supply system
Q41. A power supply system is having the following
(ii) Connected load of each type.
loads,
(i) Maximum Demand on Supply System
The sum of maximum demands of all three types of
loads,
= 1500 + 200 + 10000
= 11700
∴ Maximum demand on supply system
Sum of maximum demands
=
Overall system diversity factor
11700 If the overall system diversity factor is 1.5,
= = 8666.67 kW
1.35 determine the following,
(ii) Connected Load of Each Type Domestic Customers (i) Maximum demand on supply system
Sum of maximum demands = Maximum demand ×
(ii) Connected load of each type.
Diversity factor
= 1500 × 1.2 Ans: Nov.-11, Set-4, Q1(b)
= 2250 kW
Commercial Customer
Sum of maximum demands = Maximum demand ×
Diversity factor
Overall diversity factor = 1.5
= 200 × 1.1
To find,
= 220 kW
(i) Maximum demand on supply system
∴ Connected commercial load (ii) Connected load of each type.
Sum of maximum demands (i) Maximum Demand on Supply System
=
Demand factor The sum of maximum demands of all three types of
220 loads,
=
0.8 = 15000 + 25000 + 50000
= 275 kW = 90000
18750
= = 26785.71 kW
0.7
Commercial Customer
Sum of maximum demands = Maximum demand × Diversity factor
= 25000 × 1.2
= 30000 kW
Sum of maximum demands
∴ Connected commercial load =
Demand factor
30000
= = 33333.33 kW
0.9
Industrial Customers
Sum of maximum demands = Maximum demand × Diversity factor
= 50000 × 1.3
= 65000 kW
∴ Connected industrial load
Sum of maximum demand
=
Demand factor
65000
= = 66326.53 kW
0.98
Q42. The power supply has the following loads.
SIA GROUP
1.32 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
To find,
Maximum demand = ?
Connected load of each type = ?
Maximum Demand
The sum of maximum demands of all three types of loads,
= 1500 + 2000 + 10000
= 13500 kW
13500
= = 10000 kW
1.35
Connected Load of Each Type
Domestic Customers
Sum of maximum demands,
= Maximum demand × Diversity factor
= 1500 × 1.2
= 1800 kW
∴ Connected domestic load,
Sum of maximum demands
=
Demand factor
1800
= = 2250 kW
0.8
Commercial Customers
Sum of maximum demands,
= Maximum demand × Diversity factor
= 2000 × 1.1
= 2200 kW
∴ Connected commercial load,
Sum of maximum demands
=
Demand factor
2200
=
0.8
= 2750 kW
Industrial Customers
Sum of maximum demands,
= Maximum demand × Diversity factor
= 10000 × 1.25
= 12500 kW
∴ Connected industrial load,
Sum of maximum demands
=
Demand factor
12500
=
0.9
= 13888.888 kW
SIA GROUP
1.34 ELECTRICAL DISTRIBUTION SYSTEMS [JNTU-KAKINADA]
For Consumer 1
(i) Maximum demand = 800 W
Energy consumed during the day
(ii) Load factor = Maximum demand × Hours in a day ×100
= 45.83%
For Consumer 2
(i) Maximum demand = 1000 W
Energy consumed during the day
(ii) Load factor = Maximum demand × Hours in a day ×100
= 16.67%
For Consumer 3
(i) Maximum Demand = 1200 W
0 + (200×6) + (1200×2) + 0 + (200×2)
(ii) Load factor = 1200 ×24 ×100
= 13.89%
Sum of all maximum demands
(iii) Diversity factor = Maximum demand of whole plant