Professional Documents
Culture Documents
Detailed Work Plan For Xero Implementation
Detailed Work Plan For Xero Implementation
TARGET
MATERIALS/REPORTS ACCOMPLISHMENT
TIME FRAME ACTIVITY NEEDED PERSON CONCERN DATE
March 2023
Delivery of the Xero License
Xero License, Strong Accounting
Week 4 March 31, 2023
Assign xero access per Lacota Internet Connection Consultant
employees concern
April 2023
Setting up the the following
- Lacota Company Profile Accounting
2023 Bank Passbooks,
Week 1 - Chart of Accounts Consultant and April 08, 2023
List of Chart of Accounts
- Bank Details for Cash Bookkeeper
Monitoring
Database Build-up
List of Customers and Accounting
Week 2 April 15, 2023
-Setting up List of Customer and Suppliers in Excel Consultant
Supplier of the Company
Accounting
Week 3 Setting up the inventories on hand Inventory Reports Consultant and April 22, 2023
of Lacota as of December 2023 Inventory Officer
PREPARED BY:
EDISON G. BARING